UK Norway Share Fair 2006- BP NorwayApril 20th 2006, Aberdeen
Terje Ohrstrand - Supply Chain Management, BP Norge ASKjell M. Madsen – SCM Lead, Skarv Project
Topics
• BP Norway – Assets & Licenses
• How to become a supplier to BP Norway
• What we look for in a supplier
• Estimated spend 2006
• Possible Contract Opportunities 2006
• Valhall Re-Development Project
• Skarv Development Project
• Entry points to BP Norway
Key facts
• BP Norge Exploration and production− 564 employees
− Average daily production: 82 200 barrels of oil equivalents BP net
− Turnover: NOK 16.2 billion
− Result: NOK 8.1 billionFigures as pr. January 2006
• BP Fuels & Lubricants− 57 employees
− Turnover NOK 244 million
Activities on the Norwegian shelf
• Participant in 16 licences
• Operator for 12 of those
• Operates
− Ula & Tambar
− Valhall & Hod
• Projects
− Valhall Re-Development
− Skarv-Idun Development
• Partner in the Draugen field
PL 006B
VØRINGBASSENGET
VØRINGBASSENGET
MØREBASSENGET
BPs interesser
Andre lisensområder
Baser
Valhall
Ekofisk
Sleipner
Frigg
Oseberg
Heimdal
Troll
Visund
Snorre
Statfjord
Gulfaks
Ormen Lange
Njord
Heidrun
Norne
Ula
Draugen
Skarv
Sandnessjøen
Kristiansund
Trondheim
Stavanger
Bergen
Florø
OSLO
PL 093PL 158
PL 218
PL 033
PL 187
PL 065PL 019A
2°
4°
6° 8°
66°
62°
64°
58°
PL 262PL 261
10°
PL 025
PL 033B
PL 212b
PL 300
PL 212
PL 176
Core areas
Valhall and Hod
• Valhall production started 1982• Production to 2050 +• Remaining reserves 750 millioner boe• Estimated 2006 production 105 000 boe/d• 200 beds
• Hod production started 1990• Estimated 2006 production 8 500 boe/d • Unmanned wellhead platform remotely controlled from Valhall
Ula and Tambar
• Ula production started in 1986• Production to 2028+• Remaining reserves 92.7 mill boe• Estimated 2006 production 22 000 boe/d• 169 beds
• Tambar production started 2000• Estimated 2005 production 20 500 boe/d • Remaining reserves 24.2 mill boe• Unmanned wellhead platform remotely controlled from Ula
How to become a supplier to BP Norway
• Identify and connect with customer (BP end user)
• Registered in Achilles as approved supplier with updated info
• HSE - Self assesment (NORSOK S-006)
• Products/Services
• Track Record of Documented Capabilities
• Meet minimum HSEQ Req.
• HSEQ System and Processes
• HSE Performance
HSE matters for allocation of work!
We will not find you if your capabilities are not registered!
What we look for in a supplier
• Leadership in HSE .
• Track Record of Documented Capabilities
• The right Products / Services
• Execution Ability
• Desired Attributes
• Better use of technology
• Improved Ops Efficiency
• Value Creation
• Innovative, Creative, Proactive
• Willing to Share Ideas
BP’s SCM Strategy: STARSSector strategies – Clear strategies
for each sector maximising value whilst ensuring security of supply, enabled by a deep understanding of both BP’s demand and the characteristics of the market
Transparency – Clarity on all major cost and performance elements within the supply chain and their comparability with industry benchmarks
Aggregation – Aggregating spend to the highest level feasible and to the extent that this increases value
Relationships – Distinctive relationships based on performance, market reality, and technology development – access intellectual capital
Supply Chain Management – BP’s role in the supply chain understood and optimised
Investments in Norway
Capex
-
200
400
600
800
1 000
1 200
1 400
2006 2007 2008 2009 2010 2011
Cap
ex (
US
$ G
ross
) Skarv
Ula
Valhall
Estimated 2006 Spend (mill USD gross)
3
71
75
107
152
254
Seismic
Logistics
Business Office Support
Facilities Engineering & Construction
Production Operations
Drilling & Wells
Drilling & Wells• Drilling Fluids (NCS+UKCS)
• Directional/MWD Service (NCS+UKCS)
• Slick Line Services (NCS+UKCS)
Logistics• Platform Support Vessels (NCS)
(Stand-By Boats)
Valhall Re-Development Project
Skarv Development Project
Operations• RE Maintenance (NCS+UKCS)
• Compressors
• Pumps
• Vendor Based Maintenance Services (NCS)
• Valves, Cranes & Lifting Eqm’t
• Instrumentation FA’s (NCS)
• Industrial gas FA (NCS)
• Electrical Consumables FA’s (NCS)
Other Projects• Tambar Multi-Phase Pump
• Ula Gas Upgrade
• Valhall Flank De-Bottelnecking
•Valhall Re-Development Sub-Sea Installation
•Valhall DP Derrick De-Commissioning
Possible Contract Opportunities 2006
Valhall Re-Development – New Production & Hotel Facility
• New Facility Design Life - 40 years
• Hotel - 150 single bed cabins
• Oil production capacity - 150 mbopd
• Gas handling capacity - 5 million Sm3/day
• Total liquid capacity - 250 mbpd (oil & water)
• Weight topside + hotel ~13 000 tne Weight jacket ~ 5 000 tne
• Power from Shore - 292 km HVDC cable
• Oil Export - Future offshore loading/EOR
Valhall Redevelopment – Preliminary Schedule
ITTs will be issued either directly from BP or via Mustang in HoustonSee Procurement plan at www.bp.no
Key events
Engineering
Procurement
Transport & Install
Skids / Packages
Deck fab / Integration
Jacket & P iles
Power from shore m odule
Living Q uarters m odule
G as com pression m odule
Brownfield m ods
Subsea installation
Hook-up / Com m issioning
Flotel
NewPlatformStart-up
Define
Award
2006 2007 2008 2009
OperateFabricationComplete
ProjectSanction
Engineer / Design Follow-on / Support
ITT Engineer / Procure Inst
ITT and Awards Fabricate and Deliver
ITT
Award
Fabricate / Integrate and Pre-Commission
ITT
Award
Fabricate
ITT
Award
Fabricate / Outfit
ITT
Award
Engineer / Procure / Fabricate
ITT Fabricate
ITT Fabricate
ITT Engineer / Execute
S/D
S/D
ITT
Award
Engineer HUC
Award
Award
Award
Previous plan
Skarv - Project overview
Export Pipeline :80 km, 26”, Water depth 300 - 400 m
ÅTS – Tie InGassco commence FEED April 06
Skarv FPSO
• FPSO with subsea tie-backs.
• FPSO Design Capacity : 85mbd & 670MMSCFD
• Largest Harsh Water Gas Processing FPSO
• Oil Export via shuttle tanker.
• Design for 95% OperatingEfficiency
• Timing:
− FEED thru 4Q 2006,
− PDO 1Q 2007
− Operate 3Q 2010
Skarv Subsea layout
• Largest undeveloped hydrocarbon resource offshore Norway
- Skarv A, B, C, Tilje- Idun- Snadd (Future)
• Water Depth: 350 - 400m
Subsea Production System• Development wells 13 wells• Subsea Templates 5 (Skarv Idun Tilje)• Flowlines Rigid, Flex, Bdles• Risers #11 flexibles• Seabed Challenging
WasteWaterWasteWater
1 x 4 slot template1 x 6 slot template
Tilje
4 slot template
Idun
Skarv BC
Snadd S
Gas Export
Skarv A
Flowlines2 x 12” Prod2 x 10” Prod1 x 10” Gas Inj
1 x 4 slot template1 x 6 slot template
4 slot template
10” ProdFlowline
26” ExportPipeline
Risers2 x 10” Prod2 x 8” Prod
Risers2 x 10” Prod1 x 10” Gas Inj1 x 8” Water 10” Prod
Riser
FPSO2 x 12” ExportRisers
10” ProdRiser
Flowlines2 x 12” Prod1 x 10” Gas Inj1 x 10” Water
ProductionGasWaste WaterUmbilical
Risers:11 + 1 Snadd + 2 umbilical+ spare riser slots
12” ProdFlowline
Gas Export• 80km, 26” OD spur pipeline to ÅTS• Capacity Upgrade at Kårstø (Gassled)
Skarv FPSO Contract Structure
Skarv FPSO Contract Overall Schedule
Skarv SURF Contract Overall Schedule
BP Norway PSCMEntry Points
Supply Chain ManagerHans Ole Lørup
Operations & LogisticsArnfinn Bærheim
Bjørn LandsvikBjoern.Landsvik
@no.bp.com
Crawford [email protected]
Wells
Ian Kerr [email protected]
Reidar Hå[email protected]
Agreements/ Purchasing
Jarl [email protected]
Performance Management
Terje [email protected]
VRD PSCMSimon [email protected]
Valhall and Ula PUs
Development Projects PU
Skarv PSCMKjell Magne [email protected]