UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 1 UCSB 4-Hybrid Thermal Test System Status 13 October 2003 Sam Burke Lance Simms UCSB HEP Group

description

UCSB 4-Hybrid Thermal Test System Status. 13 October 2003 Sam Burke Lance Simms UCSB HEP Group. Progress. Pulser sync problem resolved No LVDS Trigger pulse from ARC VME Controller board Discovered ARC VME Controller board assembly error Complete 4 Hybrid-PA Test time of 42 min. - PowerPoint PPT Presentation

Transcript of UCSB 4-Hybrid Thermal Test System Status

Page 1: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 1

UCSB 4-Hybrid Thermal Test System Status

13 October 2003

Sam Burke

Lance Simms

UCSB HEP Group

Page 2: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 2

Progress

• Pulser sync problem resolved No LVDS Trigger pulse from ARC VME Controller

board Discovered ARC VME Controller board assembly error

• Complete 4 Hybrid-PA Test time of 42 min

Page 3: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 3

Progress

• Complete testing of newly bonded Hybrid/PA’s Hybrid 30216711500708

• Introduced intentional open wire-bonds in one Hybrid/PA which were detected during testing.

Page 4: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 4

Pulser Troubleshooting

• Pulser had been triggering on noise. Needs to be synchronized with ARC Clock . Twisted cable from ARC

Controller card used Eliminated noise in UCSB

LVDS/CMOS Converter

• No LVDS signals from ARC Controller Card

Page 5: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 5

ARC Controller Problem

• LVDS Driver and LVDS Receiver U32 and U33 were switched during board assembly. Problem was never discovered.

• External Buss connector and associated IC’s on lower left of photo.

U32

Page 6: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 6

ARC Controller Problem

• ARC Controller Boards with functioning External Buss Ser 29 Ser 31

• U32 and U33 Switched on these boards causing inoperative External Buss function. Ser 56 Ser 57 Ser 59

Page 7: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 7

Cold Box in Clean Room

Page 8: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 8

Page 9: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 9

3 Open H/PA wire bonds

Page 10: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 10

Installing Hybrid/PA’s

Page 11: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 11

UCSB Cold Box

Page 12: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 12

Recent Test Sequence

Page 13: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 13

4Hybrid Temp Test Report

Page 14: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 14

New ARC Ground Straps

Page 15: UCSB 4-Hybrid Thermal Test System Status

UCSB CMS Weekly Status Meeting CMS 4-Hybrid Test System Sam Burke EE Slide 15

Future Plans

• Install copper grounding bars at each hybrid test position to reduce noise levels this method has been tested and verified

• Reduce mass of aluminum hybrid test position base plate Reduce thermal mass of chamber to reduce test time