U Pumped Hydro Energy Storage (UPHES): A pre … BUsiness Dialogue...1 Underground Pumped Hydro...
Transcript of U Pumped Hydro Energy Storage (UPHES): A pre … BUsiness Dialogue...1 Underground Pumped Hydro...
1
Underground Pumped Hydro Energy Storage (UPHES):
A pre-feasibility study from South Africa
Sustainable Use of Abandoned Mines in the SADC Region
Indaba Hotel, Johannesburg (South Africa), 28-30 Nov 2017
F Winde, E Erasmus, F Kaise r
2
Contents
(0) Summary
(1) Background and core idea
(2) Technical feasibility
(3) Economic viability
(4) Research needs/ uncertainties
(5) Conclusions
Surface mine area
Access shaft
Pressure pipe
Upper storage reservoir
Ventilation
Mine void =
lower storage reservoir
Turbine chamber
reservoir
Karstified dolomite
Tailings dams
Wind/solar power
not to scale
Engine/ generator
Pump/ turbine
Shutting device
3
Summary
UPHES in deep level GMs are:
(1) … technically feasible due to favourable conditions in SA
very deep shafts
stable hard rock
water-rich dolomites
large voids
existing infrastructure
accessibility
4
(2) … economically viable and affordable
…on national economy level (government)
- no flooding no perpetual pump-and-treat of AMD
- no last-man-standing problems (extend life of marginal mines)
- no ghost-town scenario sustainable economic development
- protection of large groundwater resources (karst)
- aids decarbonisation of current energy base
…on investor level (business case)
- different revenue streams
- possible added revenue in future
- currently low interest rates
5
(1)
Background
Background Technical feasibility Economic viability Research needs Conclusions
6
Karst
JHB
100 km
WEST RAND
FREE STATE
EVANDER
EAST RANDKOSH AREA
CENTRAL
RAND
FAR WEST RAND
operational
closed/ flooded
dolomitic compartments =
several x Vaal dam
Background Technical feasibility Economic viability Research needs Conclusions
7
Water- water deficit Gauteng latest drought 2016- AMD threat in FWR- karst aquifers of strategic importance to Gauteng- water for E (SA): 821 Ml/d(2017)
AMD- high costs for pump-and-treat: R 10 bn/ 130 Ml/d short-med term+ R 12bn long-term (RO) + R 9 bn Rand Water eventually: ~ 360 Ml/d indefinite costs
Energy - 2008-2016: peak load gap
now overcapacity (Medupi/ Kusile…)
- steep tariff increases- limited black start capacity - decarbonisation: increase
RE (grid stability)
UPHES
Mining - deepest mines worldwide high pumping cost threaten viability- last-man standing problem- post-closure requirements- mines now liable for legacy costs** Mine Water Management Policy July 2017
- mine void as asset: fully equipped shaft: R 10bn ($1bn) 270 mio. m³ total permanent void volume
Situation in South Africa
Background Technical feasibility Economic viability Research needs Conclusions
8
Pump / Turbine
Grid
E-output (turbine) (expensive, day)
E-input (pump)(cheap/ night)
E-input
(pump)
E-output
(turbine)= 0.80
consume 20% more energy than is produced
upper reservoir
lower reservoir
mature, tried and
tested technology
The concept
Background Technical feasibility Economic viability Research needs Conclusions
9
UPHESV: 1 Mm³
h: 2500 m
P: 1240 MW (5h/d)
Eff. 77%
…3800 m
Burj Khalifa
(839m, $1.5bn )
+ 1
/2
Drakensberg(3480 m)
+ 3
00
m
2016 (R 28bn)
V: 26 Mm³
P: 1340 MW (for 16h/d)
Eff: 78%
Ingula
460 mP/T
P/TFully equipped
shaft (2016):
R 14bn ($1bn)
South African conditions
Background Technical feasibility Economic viability Research needs Conclusions
10
UPHES consortium
Research Mining Energy
multilateral MoU signed
RDT
Background Technical feasibility Economic viability Research needs Conclusions
11
Existing studies/ projects
RAG + UDE (2012-2018): Ruhrgebiet (operating hard coal mines)
Eskom (1997-2006): Central Rand Au-mines
Patton Engineering (2013): KOSH: AGA Au-mines
Genex (2014-2019): Kidston Au-mine
Pyhäsalmi (2014-2020): Cu/Zn-mine
EFZN (2009-2011) : Harz, Erzgebirge (closed old ore mines)
Germany
Finland
Australia
South Africa
Background Technical feasibility Economic viability Research needs Conclusions
12
(2)
Technical feasibility
Background + core idea Technical feasibility Economic viability Risks Conclusions Background Technical feasibility Economic viability Research needs Conclusions
13
Selecting a suitable mine
Blyvoor # 4/6
Driefontein #7
Ezulweni shaft (Cooke #4)
24 100
70
Tautona South Deep
Cooke #3
Deelkraal
Blyvoor
Venterspost
REGMt
DRD
Luipaardsvlei/Cham d‘Or
- significant water ingress (resource protection, pumping infrastructure …)
- last-man-standing setting
- still accessible but no production
- sufficient depth
Background Technical feasibility Economic viability Research needs Conclusions
14
Driefontein GM 7# (Far West Rand): UPHES layout
3000 m
sub-vertical shaft
tertiary shaft
Karst aquifer (1000 Mm³)
machine cavern
(turbine, pump)
ingress
pump
P
lower reservoir (1 Mm³)T
upper reservoir (1000 Ml)
discharge +
access shaft
emergency
shaft
Pemergency sump
Shaft - diameter: 10 m
Pressure pipe – diameter (1 Mm³/5h at <7m/s): 3.6 m
Shaft elevator – max width: ~5 m: <largest part of machinery
bottom ingress: ~10 Ml/d
=1% circulated volume
~100 Ml/d ingress(90% captured)
Background Technical feasibility Economic viability Research needs Conclusions
15
0.5
-2 k
m
Shaft
Drive (10 km)
10 km x (5x3) 15m² = 0.15 Mm³
Shaft cross-cut (4 km)
1000 m x 15m² x 4/reef= 0.06 Mm³
100 m 100 m
Au-reef
Reef cross cuts (50 km)
total volume per level: 500 m
x (3 x 3) 9 m² x 100/level =
0.45 Mm³
5-2
000 m
Storage volume per level:
100 x reef cross cuts: 0.45 Mm³ (68%)
1 x main drive: 0.15 Mm³ (23%)
4 x shaft cross cuts: 0.06 Mm³ (9%)
Total: 0.66 Mm³ per level
lease
bo
un
da
y
lease
bo
un
da
y
Driefontein GM 7# (Far West Rand): estimating storage volume
Background Technical feasibility Economic viability Research needs Conclusions
16
P = (V * * g * h * T ) : t
Epot
water Volume= storage space
[Mm³]
height diff.
= shaft depth [m]
time of
operation
[h/d]
Power = energy
outpout [MW]
Energy storage
capacity [MWh]
T/P
V [m³]
da
y
nig
ht
- density of water (1t/m³)
g – gravitational pull (9.81 m/s²)
T – efficiency of turbine (91%)
Th
S M L XL Ingula
h [m] 1000 2000 3000 4000 470
V [106 m3] 1 1 1 2 26.3
Epot [MWh] 2725 5450 8175 21900 21440
t [h] 4 8 16 4 8 16 4 8 16 4 8 16 16
P [MW] 620 310 155 1240 620 310 1860 930 465 4960 2480 1240 1344
Driefontein: possible UPHES dimensions
Background Technical feasibility Economic viability Research needs Conclusions
17
Parameter Pilot UPHES(R ? bn*)
77% efficiency
h [m] 2500
V [Mm3] 1 (1000 Ml)
Epot [MWh] 6 800
t [h] 5 8 16
P [MW] 1230 770 335
Proposed dimensions of pilot plant
Complementary add-ons
+ Geothermal energy(T: 10 K, 100 Ml/d): 1 160 MWh/d
direct use of heated water (e.g.
green houses, central heating)
Sibanye Gold Ltd. total need: ~500 MW/d
planned solar system (R 3bn) : 200 MW/d
Wind power
turbines on tailings dams/ Gatsrand)
storing wind energy
*Eskom (2000): 18%...40% cheaper than on surface
Patton Engineering (2013): R 4.5 bn (300 MWh)
overestimate (excavations): R 2-4 bn (6.8 GWh)
at 1 cycle /d: required pumping volume
1000 Ml/d, currently installed ~ 400 Ml/d
Background Technical feasibility Economic viability Research needs Conclusions
18
Ezulweni mine
Blyvoor # 4/6
Driefontein #7
Ezulweni shaft
(Cooke #4)
24 100
70
Tautona South Deep
Cooke #3
Deelkraal
Blyvoor
Venterspost
REGMt
DRD
Luipaardsvlei/Cham d‘Or
Background + core idea Technical feasibility Economic viability Risks Conclusions
19
Ezulweni U-mine
- closure application pending
- 66…88 Ml/d ingress (2016)
- pumping costs: ~R 15m/ month
+ staff and shaft maintenance
- large installed pumping capacity
- relatively low depth (1500 m)
- underground drop: 600 m
- storage volume per level currently determined
underground dams indicate suitability of tunnels
as storage reservoirs
7m
6m
…and pump chamber (50A level)current water pipes…
… pumps
Shaft barrel
Background Technical feasibility Economic viability Research needs Conclusions
20
Ezulweni U-mine
60
0m
underground dam at pump chamber
1500m
Option 2:
upper reservoir
on surface
Background Technical feasibility Economic viability Research needs Conclusions
21
(3)
Economic viability
Background Technical feasibility Economic viability Research needs Conclusions
22
Business case: Selling peak-load electricity
Eskom Megaflex Tariff (2015)[cent ZAR per kWh]
Peak(5h/d)selling
Standard(11h/d)selling
Av.(16h/d)selling
Off-peak(8h/d)buying
Winter: June-Aug (3 months) 223.63 67.74 116.45 36.79
Ratio selling : buying priceprofit margin
6.0 +460%
1.8 +38%
3.2+243%
Summer: Sep-May (9 months) 72.96 50.2 57.31 31.86
Ratio selling : buying priceprofit margin
2.3 +77%
1.5 +15%
1.8+38%
Average year (240 weekdays/a) 110.62 54.58 72.09 33.09
Ratio selling : buying priceprofit margin
3.3+257%
1.7+27%
2.2+68%
- Efficiency of 80% can currently be achieved (reduced by pumping ingress to 77%)
23% more energy is used than generated
can only operate profitable if E-selling price (peak) is 1/0.77 = 1.3 x larger than
E-buying price (off-peak)
Av. electricity selling-buying profit margin per year at 5-hour-operating mode: 257%
Background Technical feasibility Economic viability Research needs Conclusions
23
Business case: selling peak electricity and water
Peak-electricity sales Dfnt 7#(2500 m, 6800 MWh/d)
Ezulweni(1500 m; 4125 MWh/d)
Power selling (turbine)buying (pump)
5h x 1237 MWh8h x 1070 MWh
5h x 761 MWh8h x 469 MWh
Price [R/MWh] sellingbuying
1106330.9
1106330.9
[Mio R/d] sellingbuying
net-income
6.842.834.01
4.211.242.97
Electricity-income(240 weekdays/a)
R 962m/a R 713m/a
Water sales 100 Ml/d 70 Ml/d
Income/d at R5/kl R 500,000 R 350,000
Water income(365.25 days/a)
R 183m/a R 128m/a
Total revenue electricity/ water
R 1145m/a81% /19%
R 841m/a85 % / 15%
both sites may continue to be a gold mine after all…
Background Technical feasibility Economic viability Research needs Conclusions
24
Economic viability
Direct revenue Added (monetary) benefits
selling peak electricty
selling clean water
geothermal heat energy use (?)
selling grid services (future?)
- power storage capacity (RE)
- black start capacity
- frequency stabilisation
- regulating/ balancing power
Mines
Eskom
Government
Communities
- no last men standing problem
- protects against future tariff hikes
- post-closure community development
- no indefinite future liabilities
- image gain (share price)
- costs deductable from rehab funds?
- adds black start capacity
- cheaper than conventional PHES
- aids decarbonisation: storing RE
- free grid services
- cuts transmission losses
- export of know how
- no AMD costs to taxpayer
- no costly ghost towns
- protects scares water resources
- allows for post-mining development
- high social acceptance
Background Technical feasibility Economic viability Research needs Conclusions
25
(4)
Research needs,
uncertainties
Background Technical feasibility Economic viability Research needs Conclusions
26
Research needs, risks, uncertainties
Geological aspects
- seismic effects of frequent mass shifting
- natural and mining-related seismicity
- boundary pillar integrity/ stability
- stability of void structures (life span of tunnels etc.)
- water tightness of tunnels
Water-related aspects
- karst feed flow fluctuations (floods, droughts, sinkholes…)
- silting of reservoirs (precipitates)
- pressure and temperature induced calcite precipitation (scaling)
- contamination of bottom ingress
- acidification
Engineering aspects
- pressure pipe construction (raise boring vs. shaft pipe)
- suitable machinery for very high water pressure
- remote controlled machinery/ ventilation needs
- access shaft large enough for heavy machinery
- corrosion issues (humidity, acidification)
- drainage time from long tunnels (gradient flow)
Background Technical feasibility Economic viability Research needs Conclusions
27
Economic aspects
- future energy market in SA
share of renewable energy (CSIR,2017: 75%...79% by 2050?)
- exchange rate fluctuations (investment grading)
- run-away inflation
- development of interest rates…
Legal, administrative aspects
- liability issues (mining legacy)
- sterilisation of mineral resources
- regulatory uncertainty: status of UPHES and applicable fees (Germany)
Socio-political aspects
- nationalisation debate
- rapid economic transformation
- tensions between industry and government
- organised labour attitude
- others (corruption, state capture…)
General
-‘known unknowns’ vs. ‘unknown unknowns’
- conduct a pre-mortem
- SWOT analyses
Background Technical feasibility Economic viability Research needs Conclusions
28
(6)
Conclusions
Background Technical feasibility Economic viability Research needs Conclusions
29
(1) Favourable conditions in SA Geology: chemically inert and stable hard rock
Infrastructure: large volume, depth, pumps, grid access...
E-market: good price-spread, carbon tax savings,
Policy: decarbonisation, post-closure development, water resource
protection
High social acceptability: jobs, reuse of mining landscapes, water resource
protection ...
(2) Major potential benefits no perpetual pump-and-treat
improves energy and water security (locally and nationally)
no water pollution
aids decarbonisation of economy
no ghost towns and social disintegration
adds tax revenue
no losers
exportable knowledge
Background Technical feasibility Economic viability Research needs Conclusions
30
(3) Recommendations
secure governmental support (tax breaks....)
expand feasibility study
consult regulators (NERSA, DWS, DMR...)
develop market for grid services (E-storage...)
engage stakeholders: communities, unions, farmers...
explore complementing measures (aqua- and horticulture ...)
preserve knowledge, data and expertise
identify best ownership model
select and approach investor/s
Background Technical feasibility Economic viability Research needs Conclusions
31
Thank you!