![Page 1: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/1.jpg)
Footer Text Date
TXDOT PROJECTS UPDATE IN FORT BEND COUNTY OCTOBER 2016
Grady Mapes, P.E. Fort Bend/Waller Area Office Houston District
![Page 2: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/2.jpg)
Footer Text Date
US 59 / IH-69 Freeway Upgrade and Reconstruction
![Page 3: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/3.jpg)
Footer Text Date
Schedule Chart
3
Projects 2013 2014 2015 2016 2017 2018 2019
0027-12-097 § Cost $156,029,235
§ Time: 1045 Days (34.8% Complete)
§ FM 2759 to FM 762
0027-12-105 § Cost $135,868,539
§ Time: 1079 Days (36% Complete)
§ FM 762 to Spur 10
0089-09-058 § Cost $100,144,090
§ Time: 919 Days (28% Complete)
§ Spur 10 to Darst Road
0089-09-067 § Cost $37,743,799
§ Time: 1208 Days (2% Complete)
§ Darst Road to Co. Line
![Page 4: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/4.jpg)
Footer Text Date
US 59 / IH-69
4
Existing Typical Section
Proposed Typical Section
![Page 5: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/5.jpg)
Footer Text Date
US 90A Widening & MISC.
![Page 6: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/6.jpg)
Footer Text Date
FM 359 @ US 90A Railroad Bridge over UPRR with Elevated T-intersection
![Page 7: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/7.jpg)
Footer Text Date
Schedule Chart
7
Projects 2013 2014 2015 2016 2017 2018 2019
0027-06-056 § Cost $4,585,130
§ Time: 120 Days (18% Complete)
§ Spur 529 to Millie St
0027-08-173 § Cost $9,975,760
§ Time: 190 Days (33% Complete)
§ FM 762 to Spur 10
0027-07-032 § Estimate $21,999,053
§ Time: 541 Days (Est.)
§ Lane Dr to FM 3155
0027-06-046 § Estimate $19,805,799
§ Time: 270 Days (Est.)
§ At UPRR West Rosenberg
![Page 8: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/8.jpg)
Footer Text Date
Schedule Chart
8
Projects 2013 2014 2015 2016 2017 2018 2019
0543-02-055 § Cost $27,124,548
§ Time: 482 Days (14% Complete)
§ At US 90A and UPRR
![Page 9: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/9.jpg)
Footer Text Date
US 90A
9
One-Way Pair Project ( 0027-06-056)
![Page 10: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/10.jpg)
Footer Text Date
US 90A
10
US 90A Widening between SH 6 and SH 99
Existing
Proposed
![Page 11: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/11.jpg)
Footer Text Date
SPUR 10 Widening
![Page 12: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/12.jpg)
Footer Text Date
Schedule Chart
12
Projects 2013 2014 2015 2016 2017 2018 2019
0187-05-048 § Cost $11,736,891.34
§ Time: 219 Days (1% Complete)
§ US 59 to SH 36
![Page 13: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/13.jpg)
Footer Text Date
SPUR 10
13
Spur 10 Widening between US 59 and SH 36
Existing
Proposed
![Page 14: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/14.jpg)
Footer Text Date
FM 2218 Widening
![Page 15: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/15.jpg)
Footer Text Date
Schedule Chart
15
Projects 2013 2014 2015 2016 2017 2018 2019
2093-01-010 § Estimates $36,560,700
§ Time: 360 Days
§ US 59 to SH 36
![Page 16: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/16.jpg)
Footer Text Date
FM 2759 CRABB RIVER RD Widening
![Page 17: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/17.jpg)
Footer Text Date
Schedule Chart
17
Projects 2013 2014 2015 2016 2017 2018 2019
0543-03-067 § Estimates $18,768,484
§ Time: 180 Days
§ Sansbury Rd to LCISD H.S.
![Page 18: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/18.jpg)
Footer Text Date
FM 2759 (Crabb River Road)
18
Existing
Proposed
![Page 19: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/19.jpg)
Footer Text Date
SH 36 Widening
![Page 20: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/20.jpg)
Footer Text Date
SH 36
20
• Currently at ROW acquisition stage • Two CSJs covering from North of FM 2218 to Fort Bend/Brazoria County Line
• 0188-02-029 from North of FM 2218 to Needville-Fairchilds
• Letting Date: TBD • 0188-02-036 from Needville-Fairchilds to the County Line
• Tentative Project letting date 11/2018
![Page 21: TXDOT PROJECTS UPDATE IN FORT BEND COUNTY ......Footer Text Date Schedule Chart 3 Projects 2013 2014 2015 2016 2017 2018 2019 0027-12-097 Cost $156,029,235 Time: 1045 Days (34.8% Complete)](https://reader036.fdocuments.net/reader036/viewer/2022071516/613871c70ad5d206764942af/html5/thumbnails/21.jpg)
Footer Text Date 21