![Page 1: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/1.jpg)
Tim Smart
27th June 2016
Tunnel Presentation
P1509 (1) HOL/10014/0002
![Page 2: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/2.jpg)
2
Tunnel Briefing Agenda1. Operational aspects of tunnels
(1) Safety arrangements
(2) Noise and vibration
(3) Vent shafts and smoke control
(4) Energy use in tunnels
2. Construction
(1) Tunnelling techniques
(2) Shaft construction
(3) Settlement
(4) Construction aspects
3. Costs implications
(1) Costs of tunnelling
P1509 (2) HOL/10014/0003
![Page 3: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/3.jpg)
Tunnel Locations
3P1509 (3) HOL/10014/0004
![Page 4: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/4.jpg)
Tunnels Phase One
4
Twin Bored Tunnel
• 7.4km
• London ClayEuston
• 14km
• London Clay/Lambeth/Chalk
Northholt
• 15.8km
• ChalkChilterns
• 1.5km
• Penarth Group/Mercia Mudstone
Long Itchington
Wood
• 2.8km
• Penarth Group/Mercia Mudstone
Bromford
Cut & Cover
•1.4km
•ChalkWendover
•2.1km
•Glacial Till/Oolite/Whitby Mudstone
Greatworth
•2.5km
• Low Jurassic Marlstone/Mudstone
Chipping Warden
•0.4km
•Penarth Group/Mercia Mudstone
Long Itchington
Wood
•0.5km
• Lower Carboniferous Mudstone
Burton Green
P1509 (4) HOL/10014/0005
![Page 5: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/5.jpg)
1. Operational Aspects of Tunnelling
(1) Safety Arrangements
(2) Noise and Vibration
(3) Vent Shafts and Smoke Control
(4) Energy use in Tunnels
5P1509 (5) HOL/10014/0006
![Page 6: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/6.jpg)
1.(1) Minimum Safety Requirements (TSI)
Place of relative safety
If to the surface every 1 km To adjacent independent tunnel tube every 500m
Fire Fighting Points - Applies to all tunnels over 1 km and rolling stock dependent
Tunnel Length 1 to 5 km at portals with minimum standing area 550 sq m
Tunnels over 5km at every 5km depending on rolling stock characteristics
Fire Fighting Point defined as
Location inside or outside tunnel where fire fighting equipment can be used and passengers can evacuate
Water Supply capacity is a minimum of 800 l/min for 2 hrs.
6P1509 (6) HOL/10014/0007
![Page 7: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/7.jpg)
1.(1) Tunnel Cross Passage
7P1509 (7) HOL/10014/0008
![Page 8: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/8.jpg)
1.(1) Emergency Train Evacuation
8P1509 (8) HOL/10014/0009
![Page 9: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/9.jpg)
1.(1) Evacuation Walkway & Tunnel Cross Passage Opening HS1
9P1509 (9) HOL/10014/0010
![Page 10: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/10.jpg)
1.(1) Intervention Gap
10P1509 (10) HOL/10014/0011
![Page 11: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/11.jpg)
1. (2) Noise and Vibration
11P1509 (11) HOL/10014/0012
![Page 12: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/12.jpg)
1. (2) Vibration mitigation via “booted sleeper” track
12P1509 (12) HOL/10014/0013
![Page 13: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/13.jpg)
1. (2) Vent Shafts and Operational Noise
HS2 vent shafts are designed, constructed operated and maintained along with their associated stationary equipment so that noise in the worst affected residential receptors conforms to British Standard guidance and achieves the aims of the Noise Policy Statement for England.
Mechanical equipment within the vent shaft is only operated under the following circumstances;
During and emergency
During maintenance when required to maintain an acceptable air quality environment.
During tunnel congestion when required to maintain an acceptable air quality environment.
13P1509 (13) HOL/10014/0014
![Page 14: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/14.jpg)
1.(3) Vent Shafts and Smoke Control
Primary Purpose
Smoke extract and control. Pressure relief Access for emergency services. Passenger comfort to keep air quality and temperature
within acceptable limits.
Secondary Uses
Tunnel boring machine maintenance intervention. Access for railway maintenance.
14P1509 (14) HOL/10014/0015
![Page 15: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/15.jpg)
1.(3) Vent Shafts along Bored Tunnels
15P1509 (15) HOL/10014/0016
![Page 16: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/16.jpg)
1. (4) Energy use in Tunnels
Traction power
• Energy required for the traction power of the trains increases in tunnels.
• In the open air 80% of the energy used by the train goes into overcoming air resistance. This increases to 90% in a tunnel.
Increased power for Mechanical and Electrical plant and equipment
• Increase in energy costs for the railway due to the plant necessary for safety arrangements (e.g fans, lifts, fire mains, emergency lighting plus tunnel integrity plant (e.g pumps, cooling arrangements)
16P1509 (16) HOL/10014/0017
![Page 17: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/17.jpg)
2. Construction
(1) Tunnelling techniques
(2) Shaft construction
(3) Settlement
(4) Construction aspects
17P1509 (17) HOL/10014/0018
![Page 18: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/18.jpg)
2.(1) Construction
18P1509 (18) HOL/10014/0019
![Page 19: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/19.jpg)
2.(1) Bored Tunnels
Earth Pressure Balance Tunnel Boring Machine (EPBM)
19P1509 (19) HOL/10014/0020
![Page 20: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/20.jpg)
2.(1) Bored Tunnels
20
HS1 EPBM in factory showing back up arrangements
P1509 (20) HOL/10014/0021
![Page 21: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/21.jpg)
2.(1) Bored Tunnels
Slurry or “Hydroshield” Tunnel Boring Machine
21P1509 (21) HOL/10014/0022
![Page 22: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/22.jpg)
2.(1) Segment Yard & Drive Site Locations
22P1509 (22) HOL/10014/0023
![Page 23: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/23.jpg)
2.(1) Precast Tunnel Lining Manufacture
23P1509 (23) HOL/10014/0024
![Page 24: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/24.jpg)
2.(1) Construction Plan - West Hyde
24P1509 (24) HOL/10014/0025
![Page 25: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/25.jpg)
2.(1) Construction Plan – South Heath
25P1509 (25) HOL/10014/0026
![Page 26: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/26.jpg)
2.(1) Types of Tunnel: Mined tunnel
26P1509 (26) HOL/10014/0027
![Page 27: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/27.jpg)
2.(1) Cut and Cover Construction Methodology 1
27P1509 (27) HOL/10014/0028
![Page 28: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/28.jpg)
2. (1) HS1 Cut and Cover Tunnel
28P1509 (28) HOL/10014/0029
![Page 29: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/29.jpg)
2. (1) Cut and Cover Construction Methodology 2
29P1509 (29) HOL/10014/0030
![Page 30: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/30.jpg)
2. (1) D-wall Construction
30P1509 (30) HOL/10014/0031
![Page 31: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/31.jpg)
2.(2) Shaft Construction
31P1509 (31) HOL/10014/0032
![Page 32: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/32.jpg)
2.(3) Settlement
32
INDICATIVEP1509 (32) HOL/10014/0033
![Page 33: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/33.jpg)
2.(3) Settlement & Rate of Tunnelling
The rate of tunnelling will be important in minimising settlement. This is achieved by operating tunnel boring machines appropriately such as using Earth Pressure Balance machines in “closed” mode.
In order to keep settlement to acceptable limits HS2 has specified maximum of 1% volume loss for bored tunnels.
Continuous 24 hour tunnelling also minimises settlement as it doesn’t allow time for the for the ground to fully relax.
Other methods of controlling settlement include grouting techniques, particularly compensation grouting.
33P1509 (33) HOL/10014/0034
![Page 34: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/34.jpg)
2.(3) Settlement and Protective Measures
The primary form of settlement mitigation will be by good tunnelling practice, including continuous working. Where required additional measures (e.g. grouting and structural solutions) will be carried out based on a three stage assessment as set out in Information Paper C3 Ground Settlement.
Phase 1 Assessment: A preliminary assessment based on “green field” conditions will be undertaken. Where the predicted settlement is less than 10 mm or less than 1/500 slope, no further assessment required.
Phase 2 Assessment: In the case of predicted settlement of more than 10mm or 1/500 slope an individual building assessment will be carried out. If the potential damage classification is category 2 (slight) or below no further assessment is required.
Phase 3 Assessment: Where predicted settlement indicates potential damage classification of 3 (moderate) or higher a detailed evaluation will be carried out with the aim to reduce the effects to acceptable levels. Where this is not possible further protective measures will be implemented.
Settlement Deed. Properties within 30 metres of tunnels may apply for a Deed as set out in information paper C3 to ensure that protective measures are implemented in accordance with the assessment criteria.
34P1509 (34) HOL/10014/0035
![Page 35: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/35.jpg)
2.(4) Construction Aspects – Noise Tunnel Drive Sites
Tunnel drive sites generate similar noise levels to other large construction sites.
Tunnelling activities and the associated local site material handling will be operated 24 hours a day.
Noise mitigation is provided by the standard means such as hoarding, muffling, baffles and noise suppression on plant and equipment .
Tunnel sites will be subject to the same HS2 procedures set out under the Code of Construction practice and will be subject to Local Authority Approval under Section 61 of CoPA.
35P1509 (35) HOL/10014/0036
![Page 36: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/36.jpg)
2.(4) Construction Aspects – Noise Tunnel Boring
Sound and vibration from the tunnel boring machine will be perceptible inside properties for a few days either side of the TBM as it passes beneath them.
The effects of ground‐borne sound and vibration from the TBM on building occupants will be short‐term and hence they are not considered to be significant.
36P1509 (36) HOL/10014/0037
![Page 37: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/37.jpg)
3. Costs of Tunnelling
Fixed Costs TBM typically £15 to £25m Back up material handling similar costs order Power supply
Linear Costs Labour Lining materials Excavated material disposal Ground monitoring Ground treatment Tunnel logistics
Incremental Cost increases
Surface arrangements for drive sites, reception sites, portal arrangements Increase in number of shafts Increase in number of cross passages; Shaft and tunnel M&E systems.
37P1509 (37) HOL/10014/0038
![Page 38: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/38.jpg)
Cost vs. Length
38P1509 (38) HOL/10014/0039
![Page 39: Tunnel Presentation - Welcome to GOV.UK · PDF fileTunnel Presentation P1509 (1) HOL/10014/0002. 2 ... HS1 EPBM in factory showing back up arrangements ... Incremental Cost increases](https://reader031.fdocuments.net/reader031/viewer/2022030401/5a7724507f8b9a0d558db9f0/html5/thumbnails/39.jpg)