Trident Case Study - Hawkins Group
Transcript of Trident Case Study - Hawkins Group
Hawkins Roofing Ltd were awarded the contract with Trident Business
Consultancy to overcome major issues with the roof covering over
Weston Favell Shopping Centre. Over the years many attempts to stop the
roof leaking by other contractors resulted in a multi-layered roof make up
consisting of felt, liquid applied and EPDM roof membrane, all proving
inadequate.
The work undertaken by Hawkins Roofing included:
• Stripping out the existing gutter system and installing 254 linear
meters of new Factra gutter system in 3 locations.
• Removing the redundant plant upstands, stripping out of damaged
insulation and replacing the entire roof make-up complete with new
insulation and Firestone EPDM roof membrane.
• Removing 2 redundant large heater units and overlaying new roof
covering including all flashing requirements around existing air
conditioning units and new gutter system.
• Producing and installing 175 meters of 7 goosewing grey leathergrain
capping flashings and cladding panels to the parapet wall.
Telephone: 01295 252363
Email: [email protected]
Website: www.hawkins-group.co.uk
Client: Trident Business Consultancy
Duration: 3 Months
Location: Northampton
Contract Value: £264,000
Roofing Refurbishment Works