Trends and Developments in IT Procurement IT.CAN Information Technology Law Spring Forum May 4, 2015...
-
Upload
maude-emmeline-murphy -
Category
Documents
-
view
213 -
download
0
Transcript of Trends and Developments in IT Procurement IT.CAN Information Technology Law Spring Forum May 4, 2015...
Trends and Developments in IT Procurement
IT.CAN Information Technology Law Spring ForumMay 4, 2015
Paul EmanuelliGeneral Counsel and Managing Director
Procurement Law [email protected]
416-700-8528
www.procurementoffice.ca
Copyright Notice
The following excerpts from Government Procurement (copyright LexisNexis Butterworths 2005, 2008 and 2012), The Laws of Precision Drafting (copyright Northern Standard Publishing 2009), Accelerating the Tendering Cycle (copyright Northern Standard Publishing 2012), The Procurement Office Blog (copyright 2011-2015) and the National Tendering Law Update (copyright Paul Emanuelli 2006-2015) are reproduced with permission. The further reproduction of these materials without the express written permission of the author is prohibited.
© Paul Emanuelli, 2015
For further information please contact:[email protected].
About the AuthorPaul Emanuelli is the General Counsel and Managing Director of the Procurement Law Office. He has been ranked by Who’s Who Legal as one of the ten leading public procurement lawyers in the world and his firm was selected by Global Law Experts and Corporate INTL as Canada’s top public procurement law firm. Paul’s portfolio focuses on major procurement projects, developing innovative procurement formats, negotiating commercial transactions and advising institutions on the strategic legal aspects of their purchasing operations. Paul also has an extensive track record of public speaking, publishing and training. He is the author of Government Procurement, The Laws of Precision Drafting, Accelerating the Tendering Cycle and the National Tendering Law Update. Paul hosts the Procurement Law Update webinar series and has trained and presented to thousands of procurement professionals from hundreds of institutions across Canada and internationally.
Deploying Defensible NRFPsIndustry Overview and Implementation Guardrails
This presentation will provide a survey of the jurisdictions and sectors that are adopting flexible negotiated RFP formats. It will also offer practical guiding principles for the implementation of NRFPs, with an emphasis on proper project design planning and on establishing the following “guardrails” for ensuring the transparency and defensibility of evaluation and award processes: (1) a clear scoping of the contract opportunity; (2) transparent evaluation criteria; (3) transparent evaluation and award process paths.
4
With an increasing number of Canadian purchasing institutions adopting international best practices and implementing flexible, low-risk negotiated RFP models for everything from construction to information technology contracts, how long will it be before competitive bidding evolves to render the high-risk and inflexible “Contract A” operating system completely extinct?
The Rise of Negotiated RFPs
This article by Paul Emanuelli was previously published in the Summer 2013 inaugural edition of Negotiated RFP Newsletter.
5
6
The Rise of Negotiated RFPs
It has been over thirty years since the Supreme Court of Canada’s R. v. Ron Engineering decision imposed fixed-bid “Contract A” legalities onto the Canadian tendering process and almost fifteen years since the Supreme Court’s M.J.B. v. Defence Construction decision counter-balanced Ron Engineering by confirming that purchasing institutions remain free to use traditional contract law to negotiate flexible low-risk competitive bidding. After years of competing operating systems, we have reached the tipping point: M.J.B.’s open contracting logic has prevailed over the rigidity of Ron Engineering. Contract A is in an irreversible decline. Negotiated RFPs are the emerging standard.
The Rise of Negotiated RFPs
7
Contract A: Always a Bad Fit
Why was Contract A ever used in the first place? Just as Ron Engineering’s fixed-bid Contract A precedent was taking effect within the construction sector, senior governments across Canada were establishing trade treaties that required open, competitive bidding for most significant government purchases. Governments needed to quickly establish an operating system to facilitate these new requirements, so they repurposed the construction industry’s fix-bid tendering format and imposed its idiosyncratic rules on everyone else.
The Rise of Negotiated RFPs
8
Preconditions for Fixed-Bid Tendering
Lost in that equation was the fact that there were a number of pre-existing industry conditions that led to fixed-bid tendering in the construction industry, including an army of independent architects and engineers ready to prepare detailed specifications for the owners, an established industry group that created standard-form contract boilerplate to incorporate into tendering documents, and a prime-subcontractor supply chain that was ready to bid on pre-fabricated tender calls with bid bonds provided by the bonding industry.
The Rise of Negotiated RFPs
9
Systemic Defects
This combination of critical pre-conditions does not exist in other industries, yet under Contract A all sectors were called on to bid on government contracts under the same operating system used for construction tendering. Outside of the construction sector, this led to significant problems in designing and awarding contracts suited to the specific industry and project. By the 1990s, the systemic defects were largely apparent to anyone following the case law or in tune with conditions at the front lines of the procurement cycle.
The Rise of Negotiated RFPs
10
The Supreme Court Reboots Bidding
By confirming a clear passage out of Ron Engineering’s Contract A minefield, the Supreme Court’s M.J.B. decision served as the catalyst for rebooting the procurement cycle. Giving purchasing institutions the right to choose another operating system for competitive bidding that allowed them to cut through piles of red tape, avoid countless legal entanglements and negotiate refinements to align their tendering formats with a broader range of industries was a better fit than imposing a one-size-fits-all solution onto every tendering process.
The Rise of Negotiated RFPs
11
A Superior Operating System
More and more purchasing organizations soon began realizing that client satisfaction, supplier engagement and overall compliance with open tendering obligations could be increased by adopting a more flexible approach to tendering. The bottom line was that traditional contract law was proving to be a superior operating system, working better in more situations than the mass-produced Contract A steamroller.
The Rise of Negotiated RFPs
12
Construction Moves Beyond Contract A
In this tale of two operating systems, the post-M.J.B. years have seen a steady erosion of the once seemingly unassailable Contract A operating system. In fact, even within the construction sector, we see an accelerating migration towards flexible formats. This is particularly true domestically and internationally in the use of negotiated RFPs for complex and high-risk P3 projects. The endorsement of these formats in the United Nations Commercial Contracting Committee’s Model Procurement Law and Model Legislative Provisions on Privately Financed Infrastructure Projects further underscores the mainstream and widespread adoption of flexible formats within the construction industry.
The Rise of Negotiated RFPs
13
The Tipping Point of Innovation
Outside of the construction sector, change has occurred at an even faster pace. The spark of innovation has been lit on multiple fronts. From the Atlantic to the Pacific, the Arctic to the Equator, the standardized process-driven approach to tendering has lost ground to a more principled, nuanced and substantive approach. The tipping point has arrived within Canada and across many other Commonwealth jurisdictions.
The Rise of Negotiated RFPs
14
The Negotiated RFP Works BetterRectification Processes
The negotiated RFP has set the new standard by simply working better at meeting the overall needs of the tendering cycle. For example: • When bids contain technical irregularities, it’s no longer
necessary to disqualify bidders. Transparent rectification processes can now be used to maximize competition by allowing all proponents to cure irregularities in their bids, thus ensuring full competition while avoiding tender compliance lawsuits.
The Rise of Negotiated RFPs
15
• When bids come in over budget, it’s no longer necessary to cancel and retender and expose the institution to project delays and potential bid shopping lawsuits. While Negotiated RFPs permit the safe termination of a bidding process, they also help organizations avoid re-tendering by enabling transparent post-bid price adjustments so contract awards can be made on time and on budget.
The Negotiated RFP Works BetterAvoiding Budget Roadblocks and Bid Shopping Battles
The Rise of Negotiated RFPs
16
• When a selected proponent wants to discuss contract terms, it’s no longer necessary to impose pro forma boilerplate agreements with “take it or leave it” ultimatums. Where required, flexible formats permit the post-bid dialogue necessary to tailor contract terms to better reflect the interests of both parties.
The Negotiated RFP Works BetterFine-Tuning Contract Terms
The Rise of Negotiated RFPs
17
• When suppliers propose a creative solution that can save time and money, it’s no longer necessary to leave value on the table and reject new approaches. Negotiated RFPs allow you to obtain improved performance standards and improved pricing through structured, transparent and defensible negotiation processes.
The Negotiated RFP Works BetterEnabling Creative Solutions
The Rise of Negotiated RFPs
18
The Process Serves the Purpose
With Contract A tendering, the need to avoid getting sued often trumps the need to put a contract in place and have the requirements delivered on time. Rather than paving over the strategic objectives of a transaction with procedural orthodoxies, the use of flexible formats has re-established the paramount importance of achieving the desired outcome. With flexible Negotiated RFP formats, process no longer needs to be an end in itself. Timely results matter. The final contract is once again paramount.
The Rise of Negotiated RFPs
Moving Forward with InnovationAfter years of innovation and success, the debate over whether institutions should use flexible tendering formats is over. The verdict is in. The industry is voting with its feet in its race to adopt flexible tendering formats.
19
Moving Forward with Innovation
BC adopts JSP BAFO NRPs in early 2000s.
Manitoba runs RFP to design and implement NRFPs in 2014.
Increasing NRFP adoption in Manitoba agency and broader public sector since 2012.
Widespread NRFP adoption in Alberta municipal sector since 2011.
NRFP test pilot by Ontario government in 2006, formal recognition in subsequent updates of MBC and BPS Directives.
Widespread NRFP adoption in Ontario agency sector and broader public sector since 2009.
2014 New Brunswick regulations enable formal NRFP deployment.
21
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
In its May 2007 determination in Re Zenix Engineering Ltd., the Canadian International Trade Tribunal found the government liable for unilaterally terminating contract negotiations and bypassing the top ranked proponent. While this determination implicitly recognized the use of negotiated RFPs in the treaty-regulated federal procurement context, it also illustrated the importance of offering top ranked proponents a final opportunity to meet the government’s bottom line position before terminating talks and proceeding to the next proponent.
Negotiated RFPs and Negotiation Rules 21
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
The Tribunal considered the obligations regarding negotiations that were created between the government and top ranked proponent in the particular process:
According to paragraph 3.3 of RFAP, the negotiations were to include “… an agreement on a maximum amount for services authorized by DCC … .” The Tribunal is of the view that DCC never clearly communicated to Zenix what constituted the maximum budgeted amount authorized by DND. The Tribunal is of the view that, if the negotiation were to lead to an agreement on a maximum amount for services authorized, it was reasonable to expect that either DCC or DND would have had to identify, during the course of the negotiations, the monetary limit of DND’s budget authority.
Negotiated RFPs and Negotiation Rules 22
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
It also seems logical in that context that, because there were no items of discord between parties other than price, the appropriate time for communicating the nature of any budget limitations would have been when the negotiations had reached an impasse on price. In the case at hand, DND never asked Zenix to meet a price, nor were any budget limitations ever communicated to Zenix.
The meaning of the term “negotiation” is not defined in the RFAP. The Tribunal considered the dictionary definition of the verb “to negotiate” found in the Canadian Oxford Dictionary [footnote omitted] in which it is defined as “… to confer with others in order to reach a compromise or agreement … .”
Negotiated RFPs and Negotiation Rules 23
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
The Tribunal is of the view that negotiations involve a dynamic whereby parties exchange offers and counteroffers until a point where they reach either an agreement in respect of the object of the negotiations or a point where they conclude that have not reached an agreement. The concept of negotiation implies a communication between parties as to the items that are essential to reaching a compromise or an agreement. Negotiations are conducted within the limits that the parties set between themselves.
In the case at hand, those limits, to the extent that they existed, were found in paragraph 3.3 of the RFAP. The only limit imposed on the negotiations in paragraph 3.3 was in respect of the moment where it could be determined that the negotiations had failed.
Negotiated RFPs and Negotiation Rules 24
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
According to the terms of that paragraph, it would only have been at that moment that DCC would have been authorized to enter into negotiations with the next ranked proponent.
There is nothing in the language of paragraph 3.3 of the RFAP that could directly or indirectly be construed as indicating that the negotiations would be conducted in a manner that is different from what can generally be understood to take place in the context of a commercial negotiation. Nothing in that paragraph indicated that, contrary to what would normally be expected in the context of a negotiation, DCC could unilaterally determine when the negotiations had reach the point of failure.
Negotiated RFPs and Negotiation Rules 25
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
The Tribunal found that the government’s failure to make a clear final offer on price before terminating negotiations and proceeding to the second ranked bidder was a breach of the RFP rules:
… DCC unilaterally terminated negotiations with Zenix and began negotiations with the next ranked proponent. [footnote omitted] Contrary to what would have been reasonable to expect under the terms of paragraph 3.3 of the RFAP, DCC unreasonably decided that its negotiations with Zenix had reached an impasse on the issue of price, such that it meant that the negotiations had failed. DCC reached that conclusion before ever communicating to Zenix what constituted the maximum budgeted amount authorized by DND — the very object of the negotiations.
Negotiated RFPs and Negotiation Rules 26
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
… The Tribunal believes that it is only after communicating this information to Zenix and having sought a final response from Zenix in this regard that DCC could have reached the conclusion that the negotiations had failed. Given what it found to be a serious breach of the procurement rules, the Tribunal awarded the improperly bypassed top ranked proponent its lost profits.
In its March 2008 decision in Zenix Engineering Ltd. v. Defence Construction (1951) Ltd., the Federal Court of Appeal upheld a Canadian International Trade Tribunal’s finding of liability against the government for prematurely terminating contract negotiations with a top ranked proponent.
Negotiated RFPs and Negotiation Rules 27
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
However, while this Court of Appeal agreed with the Tribunal’s ultimate conclusion, it disagreed with the Tribunal’s finding that the government was required to disclose its budget during negotiations. As the Court of Appeal concluded, neither the specific tender call rules nor the applicable trade treaties required the government to disclose its budget during its negotiations with the top ranked proponent:
Negotiated RFPs and Negotiation Rules 28
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
In my view, a proper contextual interpretation of paragraph 3.3 of the RFAP is that in order for the applicant to award the contract, there must be an agreement between the negotiating parties on the maximum amount to be paid for services. It is quite sensible and typical of commercial negotiations that there be an agreement between the parties on the maximum amount to be paid before awarding a contract. Article 506(6) of the AIT requires that evaluation of the tenders follow the criteria outlined in the tender documents. I find that neither the RFAP itself, nor Article 506(6) of the AIT requires that the applicant disclose DND’s budget limits to Zenix. Such a reading would prevent the applicant from being able to use its competitive advantage to obtain the optimum value for DND, which is an object of the competitive tendering process.
Negotiated RFPs and Negotiation Rules 29
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
I would not, however, preclude such a situation from ever occurring. If a clause of the tender documents clearly required the applicant to disclose its budget limit, then under the AIT or NAFTA Articles discussed, the applicant would be required to abide by it. However, such a requirement would require clear language in the RFAP, as it is counter to the very nature of a competitive bidding and negotiated procurement process. In my view paragraph 3.3 of RFAP is clear in not requiring the applicant to disclose its budget limit while negotiating, and the CITT had no basis or justification for making such a finding.
Negotiated RFPs and Negotiation Rules 30
Public Sector NRFP Negotiations Subject to Due Process Zenix Engineering Ltd. v. Defence Construction (1951) Ltd.
Canadian International Trade Tribunal & Federal Court of Appeal
The Court of Appeal therefore recognized the government’s right to withhold its budget limits when conducting contract award negotiations, thereby preserving an element of bargaining leverage for the government during this crucial phase of the procurement process.
Negotiated RFPs and Negotiation Rules 31
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
In the fall of 2014, the Canadian International Trade Tribunal issued a trilogy of interrelated determinations in CGI Information Systems and Management Consultants Inc. v. Canada Post Corporation. The complaint involved an RFP issued by Canada Post for the award of master services agreements for the provision of data centre services. CGI was an unsuccessful proponent. It launched a series of legal challenges, taking issue with the debriefing process, with the failure of Canada Post to maintain its evaluation records, and with Canada Post’s use of information collected during site visits in its evaluation process.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 32
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
In September 2014, the Tribunal released the first of the three interrelated determinations. It found that Canada Post had failed to comply with its debriefing duties under the North American Free Trade Agreement (NAFTA) by failing to adequately disclose evaluation criteria. The Tribunal provided an overview of the relevant debriefing duties under NAFTA and reiterated the obligation to maintain the individual notes of the evaluators when using consensus scoring since the individual scoring sheets should be provided to proponents during debriefings in order to satisfy NAFTA debriefing duties.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 33
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
In coming to this conclusion, the Tribunal rejected Canada Post’s assertion that disclosing more detailed information about its evaluation process would result in the disclosure of confidential and proprietary Canada Post information and would compromise the quality of future proposals. The Tribunal found that Canada Post failed to provide reasonable arguments to support these assertions:
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 34
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
Thus, information regarding the individual evaluators’ assessments of CGI’s proposal shows part of the reasons for or approach to establishing the final scores and outcome of this solicitation; as such, it is pertinent information for the purposes of Article 1015(6)(b) of NAFTA that can help provide transparency to an unsuccessful bidder seeking to understand how its tender was evaluated. Canada Post’s failure to provide this information is rendered more egregious by the fact that the Tribunal has found, in previous decisions, that, where consensus scoring is used, the debriefing must still include the communication of the considerations of each individual evaluator who contributed to the establishment of the consensus evaluation.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 35
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
The Tribunal also found that the failure to provide a proper debriefing was a serious deficiency in the integrity of the procurement process:
The deficiency found is serious due to its broader impact on the integrity and efficiency of the competitive procurement system. Disregarding debriefing obligations risks significantly affecting the trust of bidders and the public in the integrity of the procurement system, as well as the efficiency of the system. As stated, the debriefing obligations contemplated by NAFTA are one means of ensuring the transparency of the procurement system, which underpins the objectives of the procurement regime under the CITT Act and the trade agreements.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 36
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
In particular, debriefings serve to demonstrate that the procurement has been conducted with integrity, they provide bidders with the necessary information to assert, if need be, their NAFTA rights, and they can facilitate an early resolution of disputes between the parties. All of these are essential for the system to function efficiently. In light of these findings, the Tribunal directed Canada Post to align its debriefing policies and practices with its NAFTA obligations and ordered Canada Post to provide the required debriefing information to CGI.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 37
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
In October 2014, the Tribunal released the second of its three interrelated determinations, which focused on the duty to maintain evaluation records during consensus scoring. It noted that Canada Post had acknowledged that the destruction of the individual evaluator records during consensus scoring was a breach of its trade treaty duties and that it had initiated a review of its consensus scoring policies. As with the failures relating to the debriefing process, the Tribunal found that the failure to maintain evaluation records was a serious deficiency in the procurement process:
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 38
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
The Tribunal agrees with CGI that the destruction of documents relevant to the evaluation in a procurement process is serious due to its impact on the integrity and efficiency of the competitive procurement system. The destruction of relevant documents causes bidders and the public to view the whole procurement process with suspicion; however, confidence in that system is imperative, as it increases participation in the procurement system and increases the chances of the government getting quality goods and services at minimum expense. This inquiry is a case in point that the loss of part of the evaluation record creates additional difficulties, both procedural and substantive, in the Tribunal’s inquiry into a complaint.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 39
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
Although it was not the case here for reasons explained earlier, the loss of relevant documents and information can potentially prevent the procuring entity from reasonably justifying its decisions and the Tribunal from determining what has transpired in the procurement process; as such, the loss of pertinent documents and information can result in a procurement process being found unreasonable, even if it had otherwise been carried out in compliance with all applicable standards. Needless to say, this creates unnecessary inefficiencies, additional delays and extra costs of all kinds to the government, the bidders and, ultimately, the taxpayers.
The Tribunal therefore ordered Canada Post to change its record keeping practices to comply with its trade treaty duties.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 40
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
In October 2014, the Tribunal also released the third of its three interrelated determinations. It found that Canada Post had improperly used information obtained during site visits of proponent facilities to increase the score of one of the proponents, and that the RFP terms did not permit this type of adjustment. The Tribunal ordered Canada Post to conduct a re-evaluation with a new evaluation team once it had updated its record keeping and debriefing practices in order to comply with the two prior determinations:
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 41
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
The deficiencies identified in this process bring into question the accuracy of all bidders’ evaluations, including the bidder that was not initially granted a site visit and those bidders that did not take part in this inquiry process. The process used to change the final scores was not consistent with the consensus scoring process used for evaluating and ranking the other bidders. The final ranking of the bidders was affected by changes to the scoring of technical proposals made as a result of the site visits. Once they are brought to the Tribunal’s attention, it cannot ignore these serious issues in connection with this procurement on the sole basis that CGI has not conclusively demonstrated that its score and ranking was directly affected.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 42
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
While considering all the circumstances relevant to this procurement, including the factors set out in subsection 30.15(3) of the CITT Act, the Tribunal comes to the conclusion that, on the facts of this matter, it must recommend a remedy that will ensure fairness to all bidders that took part in this process. For those reasons, the Tribunal finds that the appropriate remedy is to recommend that Canada Post re-evaluate the technical proposals of all six original bidders with a new team of evaluators and that Canada Post’s debriefing and document retention practices and procedures be amended.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 43
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
In the event that the re-evaluation process resulted in a different ranking from the original process, the Tribunal ordered that Canada Post either cancel the original contract awards or award additional master service agreements to the top-ranking proponents in the new evaluation. As this case illustrates, the failure to properly assess information collected during site visits can have a significant detrimental impact on the defensibility of an evaluation process.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 44
Data Centre Tender Triggers Multiple Bid ComplaintsCGI Information Systems and Management Consultants Inc. v. Canada Post Corporation
Canadian International Trade Tribunal
The inability to defend the outcome of a procurement process from legal challenge is compounded where institutions fail to maintain proper evaluation records or conduct proper debriefings. This trilogy of determinations therefore serves as a useful reminder to public institutions of the need to ensure that their procurement practices and procedures align with their trade treaty obligations.
Debriefing Duty – Consensus Scoring Record Keeping – Site Visits During Evaluation Process 45
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
In its October 2014 decision in TPG Technology Consulting Ltd. v. Canada, the Federal Court dismissed a plaintiff bidder’s $250 million lost profit claim against the government of Canada. The October trial decision was the third part in a complex trilogy of legal proceedings that included a September 2011 Federal Court summary dismissal of the bidder’s claim, followed by a July 2013 Federal Court of Appeal reversal that directed the matter to trial.
Fair Evaluations – Consensus Scoring – Tender Compliance 46
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
The claim dealt with a federal government procurement process valued at approximately $428 million for the acquisition of information technology engineering and technical support services. TPG, an unsuccessful bidder, launched an action seeking damages against the federal government. TPG originally claimed that PPI Consulting Ltd., the external consulting firm retained by the government to assist in the evaluation process, was biased against it and lowered its score during consensus scoring sessions.
Fair Evaluations – Consensus Scoring – Tender Compliance 47
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
As the September 2011 summary dismissal decision detailed, TPG claimed that the consensus scoring had been arbitrarily applied by PPI, who they claimed had a pre-existing bias against them as a “body shop”:
TPG claims that PPI, the third party facilitator “had a manifest bias against awarding the contract to TPG and disparaged TPG as a ‘body shop’” (see Powell affidavit para 15). The evaluation consisted of a consensus score model whereby the five evaluators would meet to discuss their individual scores and then arrive at a consensus score. TPG alleges that these consensus scores were arbitrarily applied to unjustifiably reduce TPG’s scores.
Fair Evaluations – Consensus Scoring – Tender Compliance 48
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
TPG alleged that the government had selected the consensus scoring method because its high subjectivity allowed personal biases to infiltrate the evaluation. In support of its allegations, the plaintiff pointed to disparaging public remarks attributed to the president of PPI as evidence that bias had tainted the evaluation process:
Fair Evaluations – Consensus Scoring – Tender Compliance 49
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
The appropriateness and effectiveness of consensus method itself, specifically chosen by PWGSC in an effort to produce the fairest result by ensuring that evaluators are using a consistent understanding of the requirements, is questioned by TPG. During the hearing, counsel for TPG advanced the argument that PWGSC intentionally selected the consensus model, the most subjective model in their view, as a way to allow personal bias and preferences to infiltrate the process. The bias was one against “body shops” - TPG maintaining that Mr. Tibbo might have had a prejudice against small companies and “body shops” as Mr. Howard Grant, president of PPI was quoted in an industry publication in 2009, as speaking disparagingly of “body shops.”
Fair Evaluations – Consensus Scoring – Tender Compliance 50
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
With respect to the consensus scoring sessions, the court noted that PPI presided over group discussions to address instances where the five evaluators had arrived at different scores. While the court noted that some errors occurred during PPI’s tabulation of the consensus scores, it also cited affidavit evidence submitted by the individuals who were involved in the process who swore that, contrary to the plaintiff’s allegations, they had not been influenced by anyone to alter TPG’s scores or manipulate the outcome of the evaluation.
Fair Evaluations – Consensus Scoring – Tender Compliance 51
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
In its September 2011 summary judgment decision, the Federal Court rejected TPG’s allegations of impropriety in the evaluation process, finding that the plaintiff had failed to prove its theory of a tainted and biased evaluation. However, the Federal Court of Appeal disagreed with the Federal Court’s conclusions, finding that it had misapplied the rule for summary judgment and that there remained issues regarding liability that warranted a full trial.
Fair Evaluations – Consensus Scoring – Tender Compliance 52
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
In determining that there remained outstanding issues that warranted a trial, the Federal Court of Appeal also clarified the Supreme Court of Canada’s rule from Double N Earthmovers v. Edmonton (City) and held that post-award conduct could be relied on as evidence of whether a winning tender was compliant or non-compliant. This point was material to whether there were issues that required a trial since the winning bidder had allegedly planned to use TPG’s former employees in the performance of the awarded contract.
Fair Evaluations – Consensus Scoring – Tender Compliance 53
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
As the Federal Court of Appeal observed, the availability of those employees was far from certain and therefore brought the compliance of the winning tender into question. The matter then proceeded to a full trial, albeit by that point, TPG had abandoned its allegations against the government regarding conflict of interest, negligence, bad faith, misconduct, bias, fraud, unconscionability, inducing breach of contract and economic interference. TPG also abandoned its allegations that the RFP had been drafted to favour a competing bidder and abandoned claims for punitive damages.
Fair Evaluations – Consensus Scoring – Tender Compliance 54
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
At trial, TPG’s lost profit claim rested on the assertions that the government evaluation team had made significant errors in their evaluation that had cost it the contract award. The Federal Court’s lengthy decision considered the issue of court jurisdiction and also considered the fairness of the evaluation process, the compliance of the winning bidder and the issue of damages.
Fair Evaluations – Consensus Scoring – Tender Compliance 55
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
The Federal Court ultimately dismissed the claim by declining to take jurisdiction after concluding that the complaint should have been brought before the Canadian International Trade Tribunal. While the Federal Court acknowledged that the Tribunal does not have exclusive jurisdiction over federal government procurement but shares concurrent jurisdiction with the Federal Court, the Federal Court found that the remaining issues in TPG’s claim fell squarely within the Tribunal’s expertise. It therefore declined to exercise its jurisdiction over the matter.
Fair Evaluations – Consensus Scoring – Tender Compliance 56
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
However, while it dismissed the case on jurisdictional grounds, the Federal Court also considered TPG’s substantive claims and found that the government evaluation committee’s consensus scoring process was flawed. The Federal Court noted that an averaging of the evaluation committee’s individual scores showed a significant divergence in TPG’s scores before and after consensus scoring.
Fair Evaluations – Consensus Scoring – Tender Compliance 57
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
In one particular evaluation category, TPG’s average initial score was 80.6 out of 100 but its final consensus score was 49 out of 100. In another category, TPG’s average initial score was 32.8 out of 50 but its final consensus score was 22 out of 50. As the decision noted, confusion arose within the evaluation team about the method of scoring performance metrics. That confusion resulted in the evaluation committee abandoning its individual scores and re-scoring TPG’s proposal collectively. Given the government’s explanation, the Federal Court found no fairness issues arising out of this departure from the individual scores.
Fair Evaluations – Consensus Scoring – Tender Compliance 58
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
However, the Federal Court did find that the evaluation committee was inconsistent in its scoring process since it failed to re-evaluate the winning bidder’s scores by consensus as it had done for TPG’s proposal. Notwithstanding this finding, the Federal Court ultimately rejected TPG’s claim since it found that the evaluation errors in the two noted categories had had no impact on the ultimate ranking, particularly since TPG failed to provide any evidence regarding unfairness in any of the other seven evaluation categories.
Fair Evaluations – Consensus Scoring – Tender Compliance 59
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
The Federal Court also rejected TPG’s assertions that the winning bidder was non-compliant and that it should have been awarded the contract as the highest scoring compliant proponent. The Federal Court therefore found that TPG was not entitled to any lost profits.
Fair Evaluations – Consensus Scoring – Tender Compliance 60
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
While the government was ultimately able to defend itself against the $250 million lost profit claim, it was only able to do so after protracted legal proceedings. Irrespective of the final outcome of this controversial case, purchasing institutions should take note that controversial public comments made by their officials and by their external consultants can be used against them in legal proceedings in an attempt to impugn the integrity of an evaluation process through allegations of bias.
Fair Evaluations – Consensus Scoring – Tender Compliance 61
Federal Court Rejects $250 Million Lost Profit ClaimTPG Technology Consulting Ltd. v. Canada
Federal Court
Furthermore, when employing consensus scoring, purchasing institutions should ensure that such processes are implemented with a high degree of diligence since: (i) scoring changes arising out of consensus scoring can be subject to a legal challenge; and (ii) tabulation errors or procedural irregularities arising out of such sessions, however innocuous or inadvertent, can be used against the institution to launch protracted legal proceedings and create significant potential legal exposure.
Fair Evaluations – Consensus Scoring – Tender Compliance 62
Negotiated RFPs Remain Subject to Legal Challenge
By Paul Emanuelli, Procurement Law Office
The past ten years has seen a rapid expansion in the use of flexible negotiated RFPs (“NRFPs”) in the Canadian public sector as a means of increasing flexibility in the bidding process while reducing the financial risk of lost profit lawsuits. However, as the February 2014 decision in Rapiscan Systems Inc. v. Canada (Attorney General) shows, when using flexible formats public institutions must still follow due process rules or face legal challenges that can result in unfair contract award decisions being struck down by the courts.
This article by Paul Emanuelli was previously published in the June 2014 edition of Purchasing b2b magazine.
63
Negotiated RFPs and Judicial ReviewA Case Study in Undue Process
If properly drafted, NRFPs operate under traditional contract law rules instead of the high-risk and inflexible fixed-bid “Contract A” tendering model. This enables greater flexibility in evaluating creative solutions and in fine-tuning contract terms to reflect unique solution-based performance terms. It also helps protect against the financial exposures of lost profit claims from losing bidders. However, this does not mean that a public institution can now part ways with due process.
64Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial ReviewNo Contract A Not An Out From Legal Challenge
As the recent Federal Court of Canada decision in Rapiscan Systems Inc. v. Canada (Attorney General) illustrates, running an unreasonable or unfair competition with hidden preferences and providing misleading information to those responsible for making the ultimate contract award decision can get you sued even if you are not in Contract A.
65Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial ReviewCourt Strikes Down the Contract Award
In the case, the Canadian Air Transport Security Authority (“CATSA”) issued a non-Contract A solicitation for airport security screening equipment. After submitting an unsuccessful proposal, Rapiscan Systems launched a legal challenge alleging that CATSA had conducted an improper process. The court agreed, granting Rapiscan’s application and declaring that the award to its competitor was invalid, unlawful and unfair. By way of remedy, the court directed CATSA to redo its future procurement process for the required equipment.
66Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial ReviewFatal Flaws in the Contract Award Process
In its lengthy decision the court found: (a) that the evaluation “was not a fair or competitive process” since there was “the concealment of minimum requirements and performance standards” which unfairly favoured the applicant’s competitor and constituted bad faith on the part of CATSA; (b) that CATSA’s management failed to advise its board “that it had derogated drastically from the Contracting Procedures during the procurement process”; and (c) that “management did not provide the Board with accurate information upon which to base its decision” and that this conduct undermined “the integrity of the government’s tendering processes”.
67Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial ReviewUnfair, Unreasonable and in Bad Faith
Based on these findings, the court determined that the board’s decision “was unfair, unreasonable, made without proper consideration of relevant factors and in bad faith.” As the Rapiscan case illustrates, public sector procurement remains subject to legal challenge even when the tendering process does not create Contract A. While lost profit damages were not available as a remedy for the unfair process, the unfairly treated bidder still had legal recourse through the administrative law remedy of judicial review.
68Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial ReviewLong Line of JR Cases Establish Four-Part Test
This remedy gives the courts broad powers, including the ability to strike down government decisions when those decisions constitute an unreasonable exercise of statutory powers. The Rapiscan case is just one example in a long line of recent judicial review judgments that have established the following four-part legal test for reviewing government procurement decisions:
69Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial Review1. Does the Decision Involve a Public Body?
Does the procurement process involve a public institution? The judicial review remedy only applies to public institutions and does not apply to private sector purchasers.
70Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial Review2. Are there Alternative Remedies?
Are there alternative remedies available? If the process is subject to legal challenge based on Contract A lost-profit claims or trade treaty-based challenges at the Canadian International Trade Tribunal, then the courts may not entertain a judicial review application.
71Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial Review3. Was the Award Made Under Statutory Power and Did the Contract Include Public Interest Elements?
Did the decision involve the exercise of statutory power in a manner that attracts public interest concerns? While the courts will not generally review policy or budgetary decisions, they may review specific procurement decisions made under statutory powers (which captures most public procurement decisions) if the specific procurement decision is significant enough to attract public interest concerns. While the “public interest test” may be met by the size or public nature of the contract, it can also be informed by the gravity of the alleged misconduct.
72Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial Review4. Was the Decision Unreasonable?
Was the challenged decision unreasonable? If the court finds that the decision was unfair, absurd, made in bad faith, or made arbitrarily or in a procedurally unsound manner then it may order a reconsideration or strike down the decision.
73Negotiated RFPs and Judicial Review
Negotiated RFPs and Judicial ReviewDue Process a Core Duty
As recent judicial review decisions illustrate, public institutions cannot escape judicial scrutiny simply by contracting out of Contract A. In government procurement, the duty to follow due process is an inherent condition of exercising statutory powers. Using NRFPs and other flexible formats may offer some significant advantages, but breaking the rules with impunity is not one of them.
74Negotiated RFPs and Judicial Review
Court Orders Disclosure of Winning Bid to Losing BidderInzola Group Ltd. v. Brampton (City)
Ontario Superior Court of Justice
In its February 2014 judgment in Inzola Group Ltd. v. Brampton (City), the Ontario Superior Court of Justice dismissed a motion brought by a winning bidder seeking to limit the disclosure of business information it submitted during a bidding process. The case involved an RFP for the construction of public buildings, including new municipal offices and a public library, as part of a downtown renewal project in Brampton, Ontario. The contract was awarded to Dominus Capital Corporation.
Disclosure Duty – Disclosure of Winning Bid to Losing Bidder in Pre-Trial Discoveries 75
Court Orders Disclosure of Winning Bid to Losing BidderInzola Group Ltd. v. Brampton (City)
Ontario Superior Court of Justice
Inzola Group, an unsuccessful competing bidder, brought an action against Brampton claiming $27.5 million in damages and an additional $1 million in punitive damages. The material submitted by Dominus during that bidding process was sought by Inzola as part of its lawsuit. Dominus brought the motion for a protective order that would limit the public distribution of the information in question.
Disclosure Duty – Disclosure of Winning Bid to Losing Bidder in Pre-Trial Discoveries 76
Court Orders Disclosure of Winning Bid to Losing BidderInzola Group Ltd. v. Brampton (City)
Ontario Superior Court of Justice
As part of its claim, Inzola challenged Brampton’s requirement that prospective bidders sign a confidentiality agreement during the bidding process, alleging that its bid was ultimately disqualified since it refused to accept the process restrictions imposed by the non-disclosure agreement. In its defence, Brampton denied Inzola’s allegations and maintained that the confidentiality protocol was required to prevent lobbying of elected officials during the bidding process.
Disclosure Duty – Disclosure of Winning Bid to Losing Bidder in Pre-Trial Discoveries 77
Court Orders Disclosure of Winning Bid to Losing BidderInzola Group Ltd. v. Brampton (City)
Ontario Superior Court of Justice
Given the factual issues that had to be addressed in the proceedings, Brampton was ordered to provide Inzola certain documents that had been collected from Dominus during the bidding process. Dominus challenged the disclosure, maintaining that it was assured that the information it provided during the bidding process would be kept confidential. Dominus also asserted that the public disclosure of the information would cause it serious financial harm since its competitive position in the market would be prejudiced by allowing competitors access to its financial information.
Disclosure Duty – Disclosure of Winning Bid to Losing Bidder in Pre-Trial Discoveries 78
Court Orders Disclosure of Winning Bid to Losing BidderInzola Group Ltd. v. Brampton (City)
Ontario Superior Court of Justice
It argued that because it was a privately held company, this information was not otherwise publicly known. While Dominus agreed to allow Inzola to have access to the information, it sought a protective order to restrict access to that information by others or use by Inzola for any purposes other than the legal proceedings. The court ultimately rejected the request for a protective order, finding that Dominus had not established that the information in question was particularly sensitive.
Disclosure Duty – Disclosure of Winning Bid to Losing Bidder in Pre-Trial Discoveries 79
Court Orders Disclosure of Winning Bid to Losing BidderInzola Group Ltd. v. Brampton (City)
Ontario Superior Court of Justice
In support of its conclusion, the court noted that the information did not appear to be treated as confidential in the industry and that Dominus and Inzola did not appear to be true competitors. The court concluded that Dominus was unable to show how the disclosure of the information would result in a serious risk to Dominus and that, on balance, the public interest in the transparency of legal proceedings prevailed over any such potential risk.
Disclosure Duty – Disclosure of Winning Bid to Losing Bidder in Pre-Trial Discoveries 80
Court Orders Disclosure of Winning Bid to Losing BidderInzola Group Ltd. v. Brampton (City)
Ontario Superior Court of Justice
The court therefore dismissed the motion, thereby compelling the disclosure of the requested information to Inzola. To balance that disclosure, the court also ordered that Brampton disclose to Dominus the equivalent documents that Inzola had submitted during that contested bidding process.
Disclosure Duty – Disclosure of Winning Bid to Losing Bidder in Pre-Trial Discoveries 81
Court Orders Disclosure of Winning Bid to Losing BidderInzola Group Ltd. v. Brampton (City)
Ontario Superior Court of Justice
As this case illustrates, the confidentiality protocols that are established during a competitive bidding process will not necessarily shield information from the disclosure duties that arise in post-bid legal disputes. While pre-award confidentiality is often required to protect the integrity of the bidding process, public interest considerations tend to favour transparency in the post-award phase of that process, particularly when legal challenges are launched against the contract award decision.
Disclosure Duty – Disclosure of Winning Bid to Losing Bidder in Pre-Trial Discoveries 82
Court Orders Disclosure of Contract Award InformationHKSC Developments L.P. v. Infrastructure OntarioOntario Superior Court of Justice – Divisional Court
In its November 2014 judgement in HKSC Developments L.P. v. Infrastructure Ontario, the Ontario Superior Court of Justice ordered the disclosure of information contained in a contract awarded by Infrastructure Ontario to HKSC Developments L.P. notwithstanding HKSC’s objections to that disclosure. The dispute arose over a public access request for information contained in a contract between Infrastructure Ontario and HKSC for the development, design, construction and partial financing of highway service centres on Highways 400 and 401 in Ontario that was awarded pursuant to a competitive bidding process.
Disclosure Duty – Public Access Request – Disclosure of Information in Awarded Contract 83
Court Orders Disclosure of Contract Award InformationHKSC Developments L.P. v. Infrastructure OntarioOntario Superior Court of Justice – Divisional Court
When the parties could not agree on the amount of information that could be disclosed, the matter ultimately escalated to the Ontario Information and Privacy Commissioner pursuant to Ontario’s Freedom of Information and Protection of Privacy Act. This resulted in an adjudicator’s order to disclose most of the requested information. HKSC took issue with that order, arguing that the information was protected under the confidential business information exemption in the Act.
Disclosure Duty – Public Access Request – Disclosure of Information in Awarded Contract 84
Court Orders Disclosure of Contract Award InformationHKSC Developments L.P. v. Infrastructure OntarioOntario Superior Court of Justice – Divisional Court
However, the adjudicator ruled that information in question did not fall under the relevant statutory exemption since the information had not been “supplied in confidence” to the government but had been produced in the course of extensive negotiations between HSKC and the government institution. The court upheld the adjudicator’s disclosure order on that basis. As this case illustrates, a party that opposes the disclosure of information requested under public access laws has the onus of establishing why that information should be protected.
Disclosure Duty – Public Access Request – Disclosure of Information in Awarded Contract 85
Court Orders Disclosure of Contract Award InformationHKSC Developments L.P. v. Infrastructure OntarioOntario Superior Court of Justice – Divisional Court
In this instance, the contractor failed to meet that test since the information created in the course of post-bid negotiations between the contractor and the government agency did not fall within the meaning of “information supplied in confidence”. Rather, that information was considered to be jointly created by the parties during negotiations, and public interest considerations favoured the disclosure of that information to better ensure the transparency of the government contracting process.
Disclosure Duty – Public Access Request – Disclosure of Information in Awarded Contract 86
Initial Mapping Statement
Material Disclosures
Eligibility Requirements
Ranking & Selection Criteria
Legal Agreement
Horizontal IntegrationAligning Requirements, Ranking Criteria and Pricing Form
Initial Mapping Statement
Detailing Requirements
Pricing Form
Detailing Requirements
Vertical IntegrationAligning Legal Agreement,
Requirements and Pricing Form
1
2
3
4
56
7
Paul Emanuelli’s
Seven Stages of Precision Drafting
87
Initial Mapping Statement
Material Disclosures
Eligibility Requirements
Ranking & Selection Criteria
Legal Agreement
Horizontal IntegrationAligning Requirements, Ranking Criteria and Pricing Form
Initial Mapping Statement
Detailing Requirements
Pricing Form
Detailing Requirements
Vertical IntegrationAligning Legal Agreement,
Requirements and Pricing Form
1
2
3
4
56
7
Warning:Do Not Proceed Before Completing Project Design
88
Initial Mapping Statement
Material Disclosures
Eligibility Requirements
Ranking & Selection Criteria
Legal Agreement
Horizontal IntegrationAligning Requirements, Ranking Criteria and Pricing Form
Initial Mapping Statement
Detailing Requirements
Pricing Form
Detailing Requirements
Vertical IntegrationAligning Legal Agreement,
Requirements and Pricing Form
1
2
3
4
56
7
What Are We Buying?
What is the Evaluation
Plan?
What is the Pricing
Format?
How Do We
Assemble the Final Contract? What is the
Tendering Format?
RFX
RFXRFX
RFX
Design OverviewABC Sequencing: (A) Design (B) Drafting (C) Assembly
89
What is the
Tendering Format?
How Do We
Assemble the Final Contract?
What Are We
Buying?
What is the
Pricing Format?
What is the
Evaluation Plan?
Tender Planning
Hub
90
A. Design
B. Drafting
C. Assembly
91
1.Project
Planning
Business Plan
Requirements and
Specifications
Pricing Structure
Evaluation Plan
Format Selection
Business Units
4.Competition
3.Document Assembly
Procurement
RFX Document
Requirements and
Specifications
Pricing Structure
Evaluation Plan
Issuing of Competitive
Bid Document
Posting of Q&As and Addenda
Procurement
Bid Receipt
Bid Evaluations
Business Units
5.Contract
Formalization
Contract Legal Terms
Procurement
Supplier Selection
Letter
Contract Finalization
6.Post-Award
7.Contract
Management
Business Units
Debriefing
Procurement
Notice of Award
Bid Protest Process
Business Units
Performance Tracking and
Payment
Issue Management
Bidder Barring Process
Conditional Expenditure
Approval
Budget Approval
Expenditure Approval
Legal and Business
Units
Legal and Procurement
Legal and Procurement
2.Procurement
Streaming
Business Units
InvitationalCompetition
Open Competition
Pre-QualificationFrameworkCorporate
Agreements
© Paul Emanuelli, 2011
Business Unit
Direct Award
Stream Selection
Internal Governance Roadmap
92
Tendering TemplatesProcurement Playbook Menu
93
Tendering TemplatesProcurement Playbook Menu
Invitation to Tender No-Negotiation RFP Consecutive Negotiation/Rank-and-Run RFP Concurrent Negotiation/BAFO RFP Invitational Request for Quotation Open Request for Quotation Request for Information Request for Supplier Qualifications – Prequalification Version Request for Supplier Qualifications – Master Framework Version
94
Procurement Playbook
Direct Award
ITT
Concurrent Negotiation
RFP
RFP
Consecutive Negotiation
RFP
RFQ
Competitive Zone
Contract Formation
Zone
Prequalification Zone
PQ
PQ
PQ
PQ
PQ
PQ
RFI
Market Research ZoneIEI
RFI Market Research Zone
IEI
RFI
1. What are we Buying? Requirements and Material Disclosures
2. What is the Pricing Structure? Stipulated Sum or Time and Materials
3. What is the Evaluation Plan? Low Bid or High Score
4. What are the Contract Terms? Predefined or established through Dialogue
5. What is the Appropriate Tendering Template? The Procurement Playbook
SWAT Team Transactional DeploymentFocuses on the Five Core Questions
96
Tender Planning
Hub
How Do We
Assemble the Final Contract?
What Are We
Buying?
What is the
Pricing Format?
What is the
Evaluation Plan?
97
How Do We Assemble the Contract?Picking Between Prefabrication and Post-Bid Assembly
Project teams can’t afford to go into cruise control and ignore the contract assembly process. This segment will explore the turning points for proper contract design and help you pick between pre-fabrication or post-bid dialogue as the preferred method for aligning your project specifications and pricing grid with appropriately tailored legal terms and conditions.
98
The proper final assembly of a procurement document requires the vertical integration of the statement of requirements and the pricing structure with the terms and conditions of the legal agreement. Purchasing institutions should ensure that they properly integrate all of the document components together with a legal agreement that incorporates the business requirements and payment terms of the contract.
The Legal Agreement
Legal Agreement
Initial Mapping Statement
Detailing Requirements
Pricing Form
7
Vertical IntegrationAligning Legal Agreement,
Requirements and Pricing Form
99
Initial Mapping Statement
Material Disclosures
Eligibility Requirements
Ranking & Selection Criteria
Legal Agreement
Horizontal IntegrationAligning Requirements, Ranking Criteria and Pricing Form
Initial Mapping Statement
Detailing Requirements
Pricing Form
Detailing Requirements
Vertical IntegrationAligning Legal Agreement,
Requirements and Pricing Form
2
3
4
56
7
7. The Legal Agreement aims at vertical integration by tying together the requirements and pricing structure with the legal terms and conditions that govern contract performance.
1
100
The Legal Agreement Vertical Integration
The failure to properly align all of the critical contract components can undermine the certainty of terms and can cause significant business and legal exposures.
101
Laying the Foundation of Contract DesignBy Paul Emanuelli, Procurement Law Office
To properly leverage their purchasing power and effectively manage their supply chain, purchasing organizations need to proactively integrate contract design concepts into their procurement cycles.
This article by Paul Emanuelli was published in the October 2013 edition of Purchasing b2b magazine and is extracted from the Accelerating the Tendering Cycle handbook.102
Contract DesignThe Four Cornerstones
This article will introduce the four cornerstones of contract design: (i) contract anatomy; (ii) contract architecture; (iii) contract assembly; and (iv) contract award; and will explain how they serve as the foundation for effective contract management.
103
Contract DesignContract Anatomy
Purchasing professionals need to understand the contents of their contracts at an organic level. They need to dissect the terms and conditions and understand how the various components should work as part of a living agreement between the contracting parties. The basic organs of any properly designed procurement contract include performance terms and payment provisions.
104
Contract DesignContract Anatomy
The performance terms should clearly define the requirements, performance standards, warranties and delivery schedules. The payment provisions should establish payment structures and schedules and clearly connect those components to the performance terms. This basic DNA of contractual anatomy serves as the foundation onto which more specialized terms can then be added to adapt the procurement contract to the specific industry and particular transaction.
105
Contract DesignContract Anatomy
These specialized terms can include, among other things, change control provisions, confidentiality clauses, insurance and indemnity terms, limitation of liability clauses, dispute resolution and termination protocols, and document retention and audit provisions. Understanding basic and advanced contract anatomy helps to avoid complicating contracts with the dead weight of unnecessary provisions.
106
Contract DesignContract Architecture
The components of a contract can be housed in different structures. Some contract architectures are designed for speed, others for long-term endurance. The most evolved architectures synthesize speed and endurance with multi-module formats that allow purchasers to lock down standard terms while permitting the rapid incorporation of more complex components as required. Organizations need to direct their purchasing into appropriate format streams.
107
Contract DesignContract Architecture
Proper contract design takes pressure off of the system by allowing purchasers to direct standard “one-time delivery” transactions into rapid use purchaser order formats while also identifying situations that call for more complex legal agreement formats. It also enables the implementation of user-friendly multi-module formats that can help to quickly navigate the middle ground between these two extremes.
108
Contract DesignContract Assembly
Contract assembly is the third critical cornerstone of contract design. It takes skill, judgement and experience to properly assess the specific situation and incorporate the necessary elements of contract anatomy into the appropriate contractual architecture.
109
Contract DesignContract Assembly
Some situations are more self-evident than others. While a one-time delivery of a standard commodity can often be handled through simplified purchase order terms, a fifteen-year outsourcing deal will typically require a formal legal agreement with a complex set of tailored schedules.
110
Contract DesignContract Assembly
These conceptual extremes may be easy to identify, but it’s the unclear middle ground that often leaves purchasers bogged down in a contractual no man’s land. It’s in this legal grey zone that proper contract design can bring the greatest gains to the purchasing institution through the implementation of a contract assembly process that enables the rapid creation of modularized contracts tailored to the nuances of the specific industry and adapted to the requirements of the specific good or service.
111
Contract DesignContract Award
There’s no use having a perfectly assembled contract that no one will sign. Since it takes two to contract, purchasing organizations should incorporate commercially reasonable terms into their contract design process. Building a sustainable contractual relationship, particularly with strategically significant suppliers, often requires the precision of a scalpel, rather than the blunt force of a “standard form” hammer.
112
Contract DesignContract Award
While an adversarial “winner-take-all” approach may be suited for certain courtroom situations, getting mired in a “battle of the forms” with your suppliers and their lawyers will only lead to purchasing gridlock. To avoid unnecessary legal entanglements, the right starting point is to establish a proper contract design process that allows purchasing professionals to quickly adapt to the circumstances, identify real deal-breakers, and distinguish fundamental terms from the nuisance clauses that tend to unnecessarily bog down the contracting process.
113
Contract DesignImplementing Contract Design
Given the current economic conditions, purchasing professionals are under increasing pressure to find efficiencies and create competitive advantages for their organizations.
Those purchasing institutions that properly adapt to today’s purchasing challenges by integrating contract design concepts into their procurement cycle will be better positioned to survive and flourish in our increasingly competitive marketplace.
114
Integrating a Legal Agreement(Vertical Integration)
Typical Commercial Terms
Business and Technical
Requirements
Industry Specific Terms
Project Specific Adaptations
Pricing Form115
Integrating a Legal Agreement
Typical Commercial Terms
Business and Technical
Requirements
Industry Specific Terms
Project Specific
Adaptations
Pricing Structure 116
Integrating a Legal Agreement
Typical Commercial Terms
Business and Technical
Requirements
Industry Specific Terms
Project Specific
AdaptationsWarning: Legal OverloadReject Fixed-Form Contract!Deploy Negotiated Format
Pricing Structure 117
Initial Mapping Statement
Material Disclosures
Eligibility Requirements
Ranking & Selection Criteria
Legal Agreement
Horizontal IntegrationAligning Requirements, Ranking Criteria and Pricing Form
Initial Mapping Statement
Detailing Requirements
Pricing Form
Detailing Requirements
Vertical IntegrationAligning Legal Agreement,
Requirements and Pricing Form
1
2
3
4
56
7
Fixed-Bid Contract A Tendering
7. Contract Assembly occurs prior to going to market. Evaluated bid price is incorporated into final awarded contract.
118
Initial Mapping Statement
Material Disclosures
Eligibility Requirements
Ranking & Selection Criteria
Legal Agreement
Horizontal IntegrationAligning Requirements, Ranking Criteria and Pricing Form
Initial Mapping Statement
Detailing Requirements
Pricing Form
Detailing Requirements
Vertical IntegrationAligning Legal Agreement,
Requirements and Pricing Form
1
2
3
4
56
7
Negotiated RFP Formats
7. Contract Design occurs prior to going to market. Final contract assembly occurs after selecting the top-ranked proponent and incorporating the bid price and other performance related content from the evaluated proposal. 119
Legal Agreement WorksheetProvision Simple
Commodity One Time Delivery
Consulting Services
Construction Technology Major Project
Interpretive Provisions
Nature of Relationship
Performance Provisions
Payment Provisions
Confidentiality
Intellectual Property
Indemnity and Insurance
Termination
Paul Emanuelli © 2014
120
Non-Contract A Negotiated RFP
RFP
Evaluation Establishes Proponent Rankings
Initial ProponentRanking
Negotiation(Time Limited)
Proponent 1• Based on prescribed
evaluation criteria established to identify best supplier at best price.
• Evaluation can include assessment of proponent comments on Standard Agreement or Term Sheet or assessment of proponent’s proposed agreement terms.
RFP Issued
End Requirements
Standard Agreement or Term Sheet
(Optional)
Process Rules
Evaluation Criteria
Proponent 2
Proponent 4
Proponent 3
ContractPerformance
O
Proponent 5
P
ContractAward
Consecutive Negotiation RFPsRank-and-Run Process
121
Non-Contract A Negotiated RFP
RFP
Initial ProponentRanking
RFP Issued ContractPerformance
Concurrent Negotiation RFPsBest-and-Final-Offer Process
Concurrent Negotiations
(Time Limited)
Proponent 1
Proponent 2
Proponent 3
Proponent 4
Proponent 5
Proponent 6
End Requirements
Process Rules
Evaluation Criteria
Standard Agreement
Terms or Term Sheet
(Optional)
Proponent 1
Proponent 2
Proponent 3
Best and Final Offers
Final Ranking With Consecutive
Negotiations(Time Limited)
Proponent 2
Proponent 3
Proponent 1
BAFO Stage
Short-Listed Finalists
ContractAward
122
Negotiation Principles and NRFPsClosing the Deal Using NRFPs
Once your organization has finished its NRFP evaluation process and identified the top-ranked proponent, it can then enter into the final selection and award phase of the process. To close the deal your organization should develop a closing strategy that addresses the three pillars of NRFP closing:
1. Team: organizing the negotiating team
2. Terms: confirming the negotiation forum and issues
3. Tactics: assigning, prioritizing and sequencing issues
123
Negotiation Principles and NRFPsClosing the Deal Using NRFPs
Your organization should identify the individuals, drawn from the NRFP project team and from other relevant parts of the organization, that need to be part of the NRFP negotiation support team. These individuals, including the ultimate decision-makers, should play a “behind the curtain” role in supporting the individuals that are selected to serve as representatives on the negotiating team.
124
Evaluation Committee
Project Team Steering Committee
2. Evaluation of Non-Price
Rated Factors
3. Evaluation of Financial
Information
1. Evaluation of Mandatory
Requirements
Board/Council Approval Level
4. Ranking of Proponents
Obtaining Negotiating
Mandate
5. Negotiation of Contract with
Top Ranked Proponent
Obtaining Ratification of Negotiation
NegotiatingTeam
6. Formalization of Contract(Contract Signing)
6. Formalization of Contract(Contract Signing)
Is it better to get a full mandate to award
heading into negotiations or to get the deal ratified after
negotiations?
125
Negotiation Principles and NRFPsClosing the Deal Using NRFPs
Once your team is properly prepared with its negotiating mandate and strategy, the lead negotiating team representative should define the terms of engagement by issuing a selection letter to the top-ranked proponent. That selection letter should:
Reiterate the protocols of the NRFP, including the timeframe for negotiations, and confirm that any award is subject to the satisfactory conclusion and ratification of a negotiated agreement.
126
Negotiation Principles and NRFPsClosing the Deal Using NRFPs
Confirm the scheduling and logistics for direct communications during the negotiating process to protect against “flanking plays” or “end-runs” around the negotiating team by the proponent
Request a complete list of discussion points from the proponent prior to the initiation of direct discussions to enable the internal identification, assignment, prioritization and sequencing of negotiation issues.
127
Evaluation Committee
Project Team Steering Committee
2. Evaluation of Non-Price
Rated Factors
3. Evaluation of Financial
Information
1. Evaluation of Mandatory
Requirements
Board/Council Approval Level
4. Ranking of Proponents
Obtaining Negotiating
Mandate
5. Negotiation of Contract with
Top Ranked Proponent
Obtaining Ratification of Negotiation
NegotiatingTeam
6. Formalization of Contract(Contract Signing)
6. Formalization of Contract(Contract Signing)
Is there a single correct way to structure our
negotiations for NRFPs?
128
Evaluation Committee
Project Team Steering Committee
2. Evaluation of Non-Price
Rated Factors
3. Evaluation of Financial
Information
1. Evaluation of Mandatory
Requirements
Board/Council Approval Level
4. Ranking of Proponents
Obtaining Negotiating
Mandate
5. Negotiation of Contract with
Top Ranked Proponent
Obtaining Ratification of Negotiation
NegotiatingTeam
6. Formalization of Contract(Contract Signing)
6. Formalization of Contract(Contract Signing)
Complex Deployment
Boardroom
129
Evaluation Committee
Project Team Steering Committee
2. Evaluation of Non-Price
Rated Factors
3. Evaluation of Financial
Information
1. Evaluation of Mandatory
Requirements
Board/Council Approval Level
4. Ranking of Proponents
Obtaining Negotiating
Mandate
5. Negotiation of Contract with
Top Ranked Proponent
Obtaining Ratification of Negotiation
NegotiatingTeam
6. Formalization of Contract(Contract Signing)
6. Formalization of Contract(Contract Signing)
Simple Deployment
Office
130
Evaluation Committee
Project Team Steering Committee
2. Evaluation of Non-Price
Rated Factors
3. Evaluation of Financial
Information
1. Evaluation of Mandatory
Requirements
Board/Council Approval Level
4. Ranking of Proponents
Obtaining Negotiating
Mandate
5. Negotiation of Contract with
Top Ranked Proponent
Obtaining Ratification of Negotiation
NegotiatingTeam
6. Formalization of Contract(Contract Signing)
6. Formalization of Contract(Contract Signing)
Accelerated Deployment
Phone or Email
131
Negotiation Principles and NRFPsClosing the Deal Using NRFPs
Prior to the commencement of direct negotiations your project team should assemble to finalize your tactical planning for outstanding issues. This includes reviewing the proponent’s list of discussion points, as well as any outstanding internal issues that you want addressed in the negotiations prior to deal closing. Internal and proponent-specific issues should be consolidated and assigned to the appropriate individuals on your project team. Those final issues should also be prioritized and sequenced to serve as the meeting agenda for direct discussions.
132
Negotiation Principles and NRFPsClosing the Deal Using NRFPs
Your negotiating team should have a clear mandate of what it can and cannot agree to during direct negotiations. It should leverage the time constraints and its ability to proceed to the next-ranked proponent to counter any unreasonable proponent demands, to limit concessions and to obtain improved results during the final negotiation process. To the greatest extent possible, your team should “occupy the field” with the final version of all legal, business and technical terms during these discussions. This will limit any slippage during final contract signing.
133
List of Issues
Meeting AgendaComplex Deployment
Boardroom
134
List of Issues
Meeting AgendaSimple Deployment
Office
135
List of Issues
Meeting AgendaAccelerated Deployment
Phone or Email
136
A. Design
B. Drafting
C. Assembly
137
What is the
Tendering Format?
How Do We
Assemble the Final Contract?
What Are We
Buying?
What is the
Pricing Format?
What is the
Evaluation Plan?
Tender Planning
Hub
138
ConclusionKey Points for Future Reference
Over the past ten years, an increasing number of public institutions across Canada have successfully adopted flexible negotiated RFP formats.
When properly designed and used, these formats offer significant benefits in accelerating tendering cycles, increasing the flexibility of award options and managing legal risk.
139
ConclusionKey Points for Future Reference
However, public institutions remain subject to strict transparency obligations when conducting a competitive bidding process, even when they use a flexible negotiated RFP format.
Public institutions should therefore establish the following “guardrails” for ensuring the transparency and defensibility of their negotiated RFP evaluation and award processes: (1) a clear scoping of the contract opportunity; (2) transparent evaluation criteria; (3) transparent evaluation and award process paths.
140
www.procurementoffice.ca
For more information please contact:
Paul EmanuelliGeneral Counsel
Procurement Law [email protected]
416-700-8528
Marilyn BrownSenior Counsel
Procurement Law [email protected]
416-700-8531
Rosslyn YoungSenior Counsel
Procurement Law [email protected]
416-700-8529
Jennifer MarstonLegal Counsel
Procurement Law [email protected]
416-700-8537