Trenching for Underground Cables

download Trenching for Underground Cables

of 25

Transcript of Trenching for Underground Cables

  • 8/2/2019 Trenching for Underground Cables

    1/25

    5

    E T S A U t i l i t i e s D e l i v e r i n g e n e r g y t o S o u t h A u s t r a l i a n s

    ETSA Utilities, ABN 13 332 330 749,

    a partnership of:CKI Utilities Development Limited,

    ABN 65 090 718 880.

    HEI Utilities Development Limited,

    ABN 82 090 718 951.

    CKI Utilities Holdings Limited,

    ABN 54 091 142 380.

    HEI Utilities Holdings Limited,

    ABN 50 091 142 362.

    CKI/HEI Utilities Distribution Limited,

    ABN 19 091 143 038.

    each incorporated in The Bahamas

    Copyright2004

    TRENCHING AND CONDUIT STANDARD

    FOR

    UNDERGROUND CABLE NETWORKS

    Technical Standard TS-085

  • 8/2/2019 Trenching for Underground Cables

    2/25

    Trenching & Conduit Technical Standard TS - 085

    1.0 DEFINITIONS

    The term "ETSA Utilities" means :-

    ETSA Utilities, ABN 13 332 330 749, a partnership of:

    CKI Utilities Development Limited, ABN 65 090 718 880.

    HEI Utilities Development Limited, ABN 82 090 718 951.

    CKI Utilities Holdings Limited, ABN 54 091 142 380.

    HEI Utilities Holdings Limited, ABN 50 091 142 362.CKI/HEI Utilities Distribution Limited, ABN 19 091 143 038.

    each incorporated in The Bahamas

    1 Anzac Highway, Keswick, South Australia, 5035.

    2.0 BACKGROUND

    The responsibility for the installation of a trench for the installation of ETSA Utilitiesinfrastructure can be:

    The developer for land developments or a customer for network extensions andalterations to the ETSA electrical network.

    Council for Power Line Environment Committee (PLEC) projects.

    ETSA for capital works and, under specific arrangements, some customer works.

    ETSA Utilities may agree to provide a quotation for the installation of a trench on

    behalf of a customer or a developer. For access to the list of Civil Contractors utilised

    by ETSA Utilities refer to section 15.0.

    This Technical Standard is based on the Electricity (General) Regulations 1997. For

    any situation that is not covered by this Technical Standard, the requirements of

    AS/NZS 3000-2000 shall apply.

    Trenching needs to be undertaken in a workman-like manner and must meet therequirements in TS 085 and any other relevant specification. A Civil Works

    Compliance form is required prior to any Network connection. Refer to section 14.0

    for further information.

    Section 5.0 of the ETSA Utilities Terms and Conditions for External Contractor

  • 8/2/2019 Trenching for Underground Cables

    3/25

    Trenching & Conduit Technical Standard TS - 085

    A contractor should not work in the area where there is electrical infrastructure, even

    if the asset is de-energised without a high degree of due care as the cables can be

    easily damaged.To reduce the severity of damage to the outer sheath, all contractors who have to

    work in the area of the electrical infrastructure MUST utilise a safe edge (blunt

    nosed) shovel.

    This style shovel minimises cable damage if a contractor inadvertently comes in

    contact with a cable. Any damage to ETSA infrastructure will be at the cost of the

    responsible party. If any party is aware of any damage to the electrical infrastructure,ETSA or the electrical contractor undertaking an installation should be notified at the

    earliest opportunity. Early notice may reduce future repair costs.

    The trench containing the electrical works is a component of the asset inspection

    process and it is the responsibility of the developer/customer to ensure that the trench

    meets the specification. An ETSA Asset Compliance Officer may inspect the trench

    and any requirement for remedial work to a trench to ensure it satisfies this Technical

    Standard and any associated specification will be at the developer/customers cost.

    If there are any queries on this Technical Standard (TS 085) the Project Officer

    responsible for your project should be contacted.

    3.0 RETAINING WALLS

    A transformer can weigh from 2.0 tonnes for a 150 kVA transformer up to 6.2 tonnesfor a 2000 kVA transformer. There may be a requirement to establish a retaining wall

    to ensure the transformer has a stable footing. The involvement of a Certified

    Engineer may be required to verify the adequacy of any retaining wall installation.

    Council approval may also be required. ETSA Utilities reserves the right to request

    engineering calculations for any retaining wall.

    A retaining wall for a Padmounted Transformer or a Switching Cubicle will normally

    be installed in any location where there is a change in the natural (unchanged) ground

    level of 300 mm or more within two metres of the standard easement boundary for the

    electrical equipment.

    Any retaining wall above 1.0 metre in height will require engineering confirmation of

    the design and Council approval.

    A R t i i ll t b l t d i t th i t ll ti f d t d

  • 8/2/2019 Trenching for Underground Cables

    4/25

    Trenching & Conduit Technical Standard TS - 085

    The retaining wall and backfill must be designed to drain the area behind the wall

    completely and to continue to do so indefinitely without blockage, so that hydrostatic

    pressure is not exerted on the wall at any time.

    Retaining walls shall be constructed of concrete masonry materials. If interlocking

    style blocks are utilised, they must be of a pinned or socket and nib type. The two top

    courses shall pinned and glued with an epoxy style resin and the top course shall

    consist of a glued top capping

    Open style interlocking blocks may be acceptable provided the soil is retained. The

    use of Geo cloth type material may also be acceptable. To ensure the material to be

    utilised for a retaining wall will be acceptable to ETSA Utilities, please contact your

    ETSA Utilities Project Officer prior to installation. This style of retaining wall

    construction has the potential to require an easement larger than standard.

    ETSA Utilities will consider a submission from a certified engineer to a variation to

    the construction material utilised for a retaining wall as described in this section.

    Material to be retained shall be classified in one of the 3 types listed below:

    Coarse grained soil without admixture of fine soil particles. Verypermeable (clean sand or gravel)

    Coarse grained soil of low permeability due to admixture of particles ofsilt size.

    Residual soil with stones, fine silty sand and granular materials withconspicuous clay content.

    Materials not acceptable include very soft or soft clay, organic silt or silty clays, and

    medium or stiff clay.

    Weep holes shall be provided in the retaining wall at the lowest points. An open drain

    shall be provided to remove water from the area of the toe of the wall. A more

    effective system of drainage consists of a continuous agricultural pipe located at the

    base of all retaining walls and be surrounded by gravel or crushed stone with a

    continuous vertical layer of granule material at least 300 mm thick covering the rear

    face of the wall area.

    Easement to be

    Area for ETSAEquipment (onstandardeasement, 3.5 x2.5 m).

    Retaining Wall

  • 8/2/2019 Trenching for Underground Cables

    5/25

    Trenching & Conduit Technical Standard TS - 085

    RETAINING WALL - FILL Figure 2Retainingwall

    ETSATransformer/switching cubicle

    300mmminm

    Granulated materialbehind all retainingwall sections

    Continuous agriculturalpipe the length all retaining

    wall sections plus externalweep holes on the lowestsection of the retaining Ground level

    NoteRetaining wall to be

    built up to the heightof the base

    Weep hole

    Suitable retaining

    Ground level

    300mmWeep hole

    Ag pipe to exit at thefront of the retaining wall

    Ground level

    Continuous agriculturalpipe the length all retainingwall sections plus externalweep holes on the lowestsection of the retaining

    RETAINING WALL - CUT Figure 3

    Retaining WallWith 100mm lipabove ground

    ETSATransformer/switching cubicle

    Groundlevel

    PreferredEasement

    Dispensation for the installation of a retaining wall can be granted by the relevant regional

    Network Manager when the following can be verified;

    The short and long term stability of the transformer will not be compromised.

    The easement site will not be impacted by erosion run off, i.e. it can be

    demonstrated that the site adjacent to the easement is well consolidated and

    /or there is other means of retainment or removal of any run off material.

  • 8/2/2019 Trenching for Underground Cables

    6/25

    Trenching & Conduit Technical Standard TS - 085

    There shall be a minimum separation of 50mm between direct laid ETSA cable

    circuits. The greater the cable circuit separation, the greater the current carrying

    capacity of the electrical cable. If the trench width is such that the minimumseparation can be increased and the 50mm clearance to the trench wall is met, then the

    separation should be increased. From time to time there may be a requirement for a

    specific separation that is greater then the minimum.

    Separation from a trench wall to any ETSA infrastructure will normally be a minimum

    of 50mm. This is to reduce any damage to electrical infrastructure from sharp edges,

    stones, etc. Under some circumstances ETSA may approve a lesser dimension if it canbe verified the trench edge is such that it will not damage the installed cables or if the

    installed conduit is medium or heavy duty.

    Dimensions for ETSA infrastructure in this standard are the minimum except where

    shown.

    The maximum depth of any length of trench or conduit should not be greater then 1.5

    metres unless ETSA has approved a section of trench/ conduit installation at a greater

    a depth. Any depth beyond this will be labelled an excavation and may require

    shoring to be installed. Refer to the Occupational Health, Safety & Welfare

    Regulations 1995.

    The Trench shall be located, when practicable, in accordance the publication A Code

    for the Placement of Infrastructure Services in New and Existing Streets (Services inStreets Code) prepared by the Public Utilities Advisory Committee (PUACC) and

    available from the Local Government Association.

    All variations to the Construction drawing mustbe noted by the installation contractor

    d i l d d th A C t t d ETSA d i

    Cables

    50mm

    Cable circuit separation50mm minimum (refer 4.1)

    25mm

    25mm

    Bottom of trench

    Conduit

    Bedding Sand

  • 8/2/2019 Trenching for Underground Cables

    7/25

    Trenching & Conduit Technical Standard TS - 085

    a development there is a requirement for spare conduits. Spare conduits installed at a

    road crossing will need to match the spare conduits in the primary trench. The road

    crossing conduits need to be continuous with the primary trench spare conduits.

    These conduits will be in addition to the conduits at a road crossing that will be

    utilised for a direct buried cable installation.

    A road crossing for a low voltage tee off (such as a common service trench) that is not

    part of a continuous run of cable only requires a conduit for a cable.

    Conduits installed at a road crossing that are for a direct buried cable installation shallextend the full width of the carriageway and extend 900mm into the footpath verge

    from the back of kerb.

    The electrical designer and contractor responsible for conduit installation at road

    crossings should ensure that the appropriate number of conduits are installed. Any

    road crossing excavation for continuous conduits needs to consider the cover and

    trench floor invert of the conduits that are to be installed in the road verge.

    4.3 Requirements for Transport SA Roads

    Transport SA have very specific requirements for any work being undertaken on a

    Transport SA (TSA) controlled road. The requirements include both excavation and

    traffic management and apply to overhead and underground works.

    The Transport SA specification for the Excavation and Reinstatement of RoadPavement is available from TSA on (tel 82268222). ETSA Utilities recommends that

    any contractor involved with the installation of either underground or overhead

    electrical works on a TSA road obtain the latest TSA Standard Specification and be

    fully conversant with all of the requirements.

    Roadside Significant Sites of an environmental or cultural significance must be

    considered by both the designer and the contractor. In country regions TSA have

    highlighted most TSA controlled roadside sites with a distinctive but discreet marker.Information and a list of Roadside Significant sites is available from the Land

    Development Account Manager at Keswick on 84045439.

    Some of the relevant sections of the specification dated February 2003 are detailed

    below

  • 8/2/2019 Trenching for Underground Cables

    8/25

    Trenching & Conduit Technical Standard TS - 085

    4.3.2. Trenchless method

    Multiple conduits can be passed through a single bore or tunnel. There is arequirement though for multiple bores to have a minimum spacing of 10D

    between individual bores.

    where D = the diameter of the largest conduit.

    The minimumdepth of a trenchless bore is 1.5 metres.

    4.3.3. TSA Notification

    The designer

    The electrical designer should submit any design to TSA for comment where

    any ETSA infrastructure, ie, poles, cable or conduit, will be running parallel

    to the kerb for some distance. This is to ensure any installation takes intoaccount any future road widening.

    The Constructor

    An electrical or civil contractor will need to submit a Notification of Works

    Impacting SA Roads form NICC-251 (refer to sect 15.0 for access) 5

    working days prior to the commencement of works. Any civil works that will

    be undertaken on a TSA road over a period greater then one day requires 4

    weeks notice.

    The notice is required for the following:

    Any work that requires traffic managementThis includes work on overhead mains

    A t h d t hl b i

    Minimum1.5 metres

    Ground level

    10 X 125mm =1.25m minimum100mm conduit

    125mm conduit

    Bore 1 Bore 2

  • 8/2/2019 Trenching for Underground Cables

    9/25

    Trenching & Conduit Technical Standard TS - 085

    There is a requirement that TSA receives within 3 days of the completion of

    works a log of any excavation with the construction date, location and depths

    and details of the reinstatement.ETSA Utilities also requires a copy of the installation details and who

    undertook the civil works with the Civil Works Compliance form. The

    form is a part the electrical works compliance and connection process.

    4.3.6 Emergency Work

    TSA requires verbal notification to the appropriate TSA representative at the

    earliest opportunity. This must be followed with the submission of the

    Notification of Works Impacting SA Roads form within 24 hours of the

    emergency.

    4.3.6. Maintenance Period

    The contractor undertaking the civil component of the electrical worksassociated with the TSA road crossing will be responsible for the cost of

    making good any settlement or other deteriation in the reinstated excavation

    for the maintenance period which is one year.

    4.4. Installation of Conduits Within Railway Boundaries

    Australian Standard AS4799 2000 Installation of underground utility services andpipelines within railway boundaries covers the requirements for both the design and

    installation of electrical infrastructure within a railway property.

    There is specific design information and approvals that are needed for right of entry as

    well as easement agreements.

    The form Application to Cross Railways With Electric Power Cables NICC-252

    (refer to sect 15.0 for access) must be filled out by the designer a minimum of 28working days prior to any work taking place and forwarded to;

    ETSA Utilities Easements Coordinator

    level 3, 1 Anzac Highway Keswick 5035

    Telephone 84045897 fax 84045193

  • 8/2/2019 Trenching for Underground Cables

    10/25

    Trenching & Conduit Technical Standard TS - 085

    An electrical conduit should be a minimum of 2metres deep under any rail line and for

    a 3metre distance beyond the outer rails. Conduits in other locations in a railwayproperty must have 1 metre minimum cover. A railway authority may approve a

    lesser depth, but the depth must not be less then the ETSA Utilities standard.

    4.5 Clearances between Services.

    Comms

    plant pipe

    Comms

    plant pits

    Gas pipes ETSA LV

    power

    ETSA HV

    power

    Comms

    plant pipe

    150 150 200 100 300

    Comms

    plant pits

    150 1000 200 100 100

    Gas pipes 200 200 X 200 200

    ETSA LV

    power

    100 100 200 X X

    ETSA HV

    power

    300 100 200 X X

    X = undefined in this application. All clearances are in millimetres

    Comms = Telecommunications

    Note: These clearances are applicable for the full circumference of the service (360)

    These are minimum separations. For any other authority a minimum separation of150mm is required. Greater separation may be requested in the ETSA specification

    from time to time.

    To achieve these clearances it may be necessary to increase the cover on ETSA cables

    and/or conduit or increase the trench width.

    4.6 Changes in levels and directional changes

    The depth of any conduit installation in the carriageway should match that of any

    conduit installation on the road verge (footpath). If this is not achievable the cover at

    the end of a conduit at a road crossing should be at the same level as the conduit in the

    verge. Conduit bends may need to be installed to achieve this.

  • 8/2/2019 Trenching for Underground Cables

    11/25

    Trenching & Conduit Technical Standard TS - 085

    conduits. Appropriate bends with the smallest radius requirement to achieve a

    satisfactory clearance to other of services should be utilised.

    Retrospective undergrounding projects will provide challenges to the civil contractor

    from time to time when other service providers infrastructure is encountered within

    the trench. It will be the civil contractors responsibility to resolve these issues and the

    assistance of the Project Officer should be sought to ensure that a resolution is agreed

    on that is to the satisfaction of ETSA Utilitiespriorto construction.

    Below are some examples of conflict and possible solutions

    Preferredgradient rise/fall

    of conduit100mm per

    1metre

    ETSAconduit

    Note

    IfY > 1.5m it may bepreferreble to goover service.

    150mmminimumunder service.

    G.L.

    XSharp bends

    X Couplinglocation is notappropriate if there isany tension. This

    creates a lip whichcan damage cables

    `Y

    INCORRECT PREFERRED

    G.L.

    AlternativeConduit

    route

    The example shows an in-appropriate conduit coupling with tension applies to both a

    straight length of conduit and a bend.

    It is important that the developer and electrical contractor establish appropriate ground

    levels at the time of the installation of the electrical works to ensure that there is no

    requirement to alter ground levels by a third party after installation. Under theElectricity Corporations Act 1999 the SA Independent Regulator can impose a fine for

    any breach.

    Part 6 of this Act states the following:

    38. (1) A person must not, without the written authority of the electricity

  • 8/2/2019 Trenching for Underground Cables

    12/25

    Trenching & Conduit Technical Standard TS - 085

    A trench will normally be 600 mm wide but could be up to 1200 mm wide depending

    on soil type and footpath location. With consultation with the electrical contractor, a

    width of 450 mm may be acceptable. The design drawings should specify any non-typical width.

    Reference should be made to the Services in Streets Code for any trench location in

    a road reserve.

    The depth of the trench shall be such as to achieve a minimum cover of 750 mm above

    conduits and 1000 mm above all direct buried cables to finished ground level. A

    typical cross section of trench occupied by the underground mains, Telstra and Gas is

    shown below

    :

    Typical

    width

    (Refer to Services

    in Streets Code)

    50mm

    GAS

    TELSTRA

    750 mm

    450mm

    600mm

    FOOTPATH

    BEDDINGSAND

    Property

    line

    1600mm 600 mm

    COMMON SERVICE TRENCHmain Side

    KERB

    LV HV P/L

    50mm

    1000 mm

    Spare conduit

    Cables buried direct

    Top of

    bedding sand

    Notes

    Refer section 4.1

    50mm

    50mm

    GAS

    TELSTRA750 mm

    minm at the

    finished

    road service

    level at thekerb invert

    For a TSA

    road refer to

    sect 4.3

    450mm

    600mm

    BEDDING SAND

    600 mm

    COMMONSERVICE TRENCH - Road Crossing (non TSA road)

    Note

    Cover slabs or warning tape is

    to be placed 75 mm above

    ETSA plant if ETSA istheonly occupant of the road

    SPARE CONDUIT

    Notes

    Refer section

    4.1

    LV HV P/L

    road level

  • 8/2/2019 Trenching for Underground Cables

    13/25

    Trenching & Conduit Technical Standard TS - 085

    should be installed for any future cable installations. This method of installation

    minimises disruption to footpath and vehicular traffic and business premises.

    450 mm

    Additional conduit

    Refer 5.250mm

    Gas, when applicable

    Telstra, when applicable

    750mm

    600mm

    Kerb

    LV HV P/L 50mm

    Warning

    tape

    200mm

    maxm

    Property lineFootpath

    RETROSPECTIVE UNDERGROUNDING (PLEC)

    COMMON SERVICE TRENCH

    Bedding sandNotes

    Refer to

    section4.1

    Additional conduitRefer to 5.2.

    50mm

    750 mm

    Bedding sand

    Kerb

    LV HV P/L 50mm

    Warning tape

    Property line Footpath

    RETROSPECTIVE UNDERGROUNDING (PLEC)

    ETSA ONLY TRENCH

    200mm

    maxm

    Notes

    Refer

    section 4.1

    4.8.1 Pit Installations

    There are a number of pits of increasing size that are available and the pit that is to be

    installed needs to be appropriate for the purpose. The designer also needs to be mind-full of other services.

    When conduits are installed into the body of a pit, the conduit needs to be 25 50mm

    inside the body. All conduit edges are to have no sharp edges. All conduit entries are

    to be capped by the contractor to stop the entry of foreign material between the time of

  • 8/2/2019 Trenching for Underground Cables

    14/25

    Trenching & Conduit Technical Standard TS - 085

    Note1 Refer to E1921 sht 2.1

    for standard arrangements2 Refer to E1921 sht 6.1 to 6.4

    for assembly details3 A P5 pit is preferred for LV

    cable junctions and servicearrangements for approvedbelow ground connections

    Conduit to finish25mm - 50mm inside pit

    CABLE & CONDUIT ENTRY INTO JUNCTION PITS

    Extended P5 pit(1 Standard body plus oneshortened body or collar)at preferred 985mm invert

    Preferred 0 40mm to pitbottom for low voltagecable entry to ensureappropriate room forcable cones

    5.0 CONDUIT REQUIREMENTS

    5.1 General

    Cables shall be installed in conduits in the following circumstances:

    Road crossings

    Full length of pathways with restricted access ie, a pathway betweenfenced allotments)

    Cables installed through easements.

    Public lighting cables

    Retrospective undergrounding (i.e. PLEC Projects)

    On private property where cables vest in ETSA Utilities (Refer to section

    6.0 for all options)Earth cables do not need to be installed in conduits

    Where there will be access roads, driveways and footpath crossings greater then 2.5

    metres in width, conduits for a cable installation as well as spare conduit requirements

    may need to be included in a design.

    Full details of the conduits must be included on a design drawing and the As

    Constructed drawing must reflect the actual installation. Any breaks in a continuous

    conduit installation must be noted as must any changes in the as installed conduit size.

    11kV cables must not be installed in the same conduit as low voltage cables

    5.2 Spare conduit provision

  • 8/2/2019 Trenching for Underground Cables

    15/25

    Trenching & Conduit Technical Standard TS - 085

    For the high voltage: 3x 80mm VLD conduit

    Note: Where one LV circuit consists of two or more parallel bundles of

    cables, a spare conduit must be provided for each bundle of cables.

    5.2.2 When a cable is installed in a conduitTo ensure future access to ETSA infrastructure is kept to a minimum there is

    a requirement where cables are to be installed in conduit for additional

    conduits.

    Unless specified differently in the ETSA specification the requirement is:

    A PLEC project One spare conduit forallof the low voltage circuits

    One spare conduit forallof the high voltage circuits up to

    and including 300mm2.

    One spare conduit per phase for any 630mm2 high voltage

    installation

    A Customer project ( ie, through any easement)For every 3 conduits (or part there of) installed that are to be occupied by

    cables, there is one additional conduit included in the installation.

    As an example,

    There are 3 cable circuits installed in conduits made up of 2 low voltage

    circuits in 2 x 80mm (or 100mm) conduits and one 300mm2 high voltage

    cable with one phase installed in a each of 3 x 80mm conduits.

    Note: Any public lighting cable installed in a medium or heavy duty conduit

    is excluded from the requirements of 5.2.2

    There are a total of 5 conduits with cables. With a requirement of one spare

    conduit per 3 occupied conduits, or part thereof, there will need to be 2

    additional conduits included in the installation.

    5.2.3. Road crossings

    There is a requirement for spare conduits as well as the conduits that are to be

    utilised at the time of the cable installation at road crossings. Refer to section

    4.2 of this standard for details.

    5.3 Spare Conduit and Bend Requirements

  • 8/2/2019 Trenching for Underground Cables

    16/25

    Trenching & Conduit Technical Standard TS - 085

    The requirement for bends will need to be assessed at the time of installation as well

    as at the time of trench design layout.

    5.4 Conduit Sizes

    While the chart specifies minimum conduit sizes, a larger conduit may be installed on

    the proviso that the conduit can be made continuous with any existing or future

    continuous conduit installation.

    A conduit of a higher classification can be utilised then those specified.The minimum size of a conduit for a specific cable size are as follows:

    Cable Circuit Conduit Size Conduit Bend

    LV Main & Service

    bundled

    1 x 80mm VLD 1800 radius, Light duty

    HV 35mm2 1 x 80mm VLD 1800 radius, Light duty

    HV 95mm2 1 x 100mm VLD 1800 radius, Light dutyHV 300mm2 and

    630mm2

    3 x 80mm VLD 1800 radius, Light duty

    Public Lighting 1 x 32mm HD 312 radius, Heavy duty

    CBD installation No x 125mm VLD

    The ETSA standard class 4.5 is equivalent to very light duty (VLD)

    The ETSA standard class 6.0 is equivalent to light duty (LD)

    Care must be taken in joining conduits. Different grades have different internal

    diameters and the resultant raised internal edge has the potential to damage the outer

    layer of cable during cable pulling.

    5.5 Compliance to Australian Standard

    Conduits and couplings shall be uPVC material and meet the requirements of AS/NZS

    2053 Parts 1 and 2 for Rigid Plain designation. The conduit will be marked with the

    word electrical, the conduit size and class, eg ELECTRICAL DUCTING 100 mm

    4.5 class. No other form of rigid conduit is permitted without the approval of the

    Network Standards Manager .

  • 8/2/2019 Trenching for Underground Cables

    17/25

    Trenching & Conduit Technical Standard TS - 085

    c)be light orange in colour. Black conduit with orange stripes may be utilisedwith the approval of the project officer if orange conduit is not available.

    d)be of size and characteristics to allow the cable to achieve its current rating.e) Be anchored at conduit entry/exit appropriately to maintain its horizontal

    profile. The polyethelyne material has a memory and will attempt to coil

    up. This will introduce stress at conduit transition locations and at the

    start/end of a directional boring conduit installation.

    5.8 Design of Conduit Installation

    Conduit designs shall be prepared to ensure that pulling tensions do not exceed the

    maximum permissible as required by the Construction Standard TS 087.

    Installation details and techniques for cable pulling through conduits are in E1906.

    Reference to an indication of cable pulling tensions is listed in E1910 sheet 4.2

    5.9 Conduit Installation

    Conduits shall be laid on an evenly bedded 50mm thick layer of well-graded sand

    b i ll f f l d i l h i di i i f 6

    Floor of trench /opening for bore

    Edge ofentry/exithole

    Securing the end of directional boring conduit

    Directionalboring conduit

    End of polyethylenepipe to be concreteencased orsandbagged

  • 8/2/2019 Trenching for Underground Cables

    18/25

    Trenching & Conduit Technical Standard TS - 085

    For spare conduits in a group, the position of the ends shall not vary by more than

    300mm. Where conduits are installed in layers, the ends shall be positioned

    horizontally.

    Conduits between new and existing subdivisions must be joined together.

    Cable markers are required wherever ETSA conduits/ cables pass through private

    property. Refer to E1979 for installation details.

    5.10 Sealing of Conduits

    For a cable Installation

    Where cables have been installed in conduits, a conduit end shall be adequately sealed

    to prevent the entrance of dirt, stones, white ants and moisture into the conduit by the

    use of polyethylene expanded foam applied in accordance with the manufacturer's

    instructions.

    The expanding foam should not encroach into the conduit any further then 75mm.This will ensure that the foam/cable can be easily removed if the need arises.

    Sealing of conduits with cables

    For conduits with no cables

    The use of end caps is a requirement for any conduit that is to remain vacant. This

    includes the installation of end caps on a temporary basis on a conduit that will not

    have a cable installed immediately.

    Description Stock Item NoCap, push on 40mm for consumers conduit

    Cap, push on 50mm for consumers conduit NC 6462

    Cap, push on 80mm NC 6470

    Cap, push on 100mm NC 6501

    Scrunched plastic ornewspaper

    Cable

    Approx 75mm

    Expanding foam

  • 8/2/2019 Trenching for Underground Cables

    19/25

    Trenching & Conduit Technical Standard TS - 085

    Diagram C Install cables buried direct at a depth of 1000 mm. Spare conduits as

    section 5 are required for the cable circuits that are to be installed. Polymeric cover

    slabs are still to be installed. Warning tape is required in all cases.

    The general trench configuration shall be in accordance with the following diagrams.

    50mm

    BEDDING

    SANDPL LV Spare HV

    200 mm

    maxm

    WARNING

    TAPE

    50mm

    1000mm

    50mm

    750 mm

    minm.

    BEDDING

    SAND

    P/L LV Spare HV

    POLYMERIC

    COVER SLAB

    50mm

    75mm

    maxm

    Diagram A cable in conduit at 1000 mm Diagram B Cable in conduit at 750mm

    750 mm

    minm

    1000 mmPOLYMERIC

    COVER SLAB

    5mm thick

    50mm75mm

    maxm

    Diagram C

    Cable buried direct

    N t

  • 8/2/2019 Trenching for Underground Cables

    20/25

    Trenching & Conduit Technical Standard TS - 085

    Spare conduit

    Cables buried direct

    Public lighting can be

    in conduit or buried

    direct

    50mm

    1000 mmBEDDING

    SAND

    50mm

    750mm

    Notes

    Refer section 4.1

    ROAD VERGE -

    SINGLE CUSTOMER

    Any ETSA cable system that needs to be located under a road needs to satisfy either the

    requirements detailed in section 4.5. for common service trenches or section 4.3 if it is a

    Transport SA road

    In situations where public lighting circuits within conduits are to be located in a trench

    alone, (eg no adjacent power circuits or spare conduits), the minimum cover shall be

    600mm with warning tape installed at 400 mm.

    Any public lighting network that is a Customer Lantern Energy Rate (CLER) or is fed

    from a metered supply point requires a minimum separation of 150mm from any

    ETSA infrastructure.

    8.0 EXCAVATION FOR VAULTS

    The excavation for vaults shall be as follows:

    (a) Padmount Transformer Vaults:

    the dimensions are in the order of 1850 long x 1000 wide x 1250 deep, totalling

    approximately 2.5 m of spoil to be excavated.

    (b) Switching Cubicle Vaults:

    the dimensions are in the order of 2250 long x 1000 wide x 1175 deep, totallingapproximately 2.7 m of spoil to be excavated.

    The spoil requiring excavation for the above two cases allows working room for

    the placement of cables in conjunction with installation of the vaults.

  • 8/2/2019 Trenching for Underground Cables

    21/25

    Trenching & Conduit Technical Standard TS - 085

    Some common sand types are designated as DS4B and PM64. The specification for these

    types differs from the ETSA standard. It is the contractors responsibility to ensure the

    installed sand meets the ETSA specification.

    TEST METHOD TEST PERMITTEDTEST VALUES

    Grading Percent Passing

    AS1141.11 Sieve Sizes mm

    AS1152 4.75 100

    2.36 98 - 100

    1.18 94 - 100

    0.6 85 - 100

    0.425 55 - 100

    0.3 25 - 100

    0.15 5 - 40

    0.075 0 - 10

    AS1289 C3.1 Plasticity Index Maximum 6

    (non plastic)

    10.0 POLYMERIC CABLE COVERS / MARKER TAPE

    The stock item for the 5mm polymeric cable cover is RN 0202 which is supplied as a

    15 metre long roll, 300mm wide. To satisfy AS/NZS 3000 the strip must be placed no

    more than 75mm above ETSA infrastructure and must overlap the ETSA

    infrastructure by 40mm per side.

    Marker tape is a requirement for PLEC projects. For any other installation, if the

    conduits installed for electrical infrastructure are not a light orange in colour, marker

    tape will be required to be installed not more then 200mm above the conduits. If

    polymeric cable covers have been installed marker tape is not a requirement

  • 8/2/2019 Trenching for Underground Cables

    22/25

    Trenching & Conduit Technical Standard TS - 085

    Backfilling material must be clean and completely free from all fibrous and vegetable

    matter and other material which may attract or be attacked by termites.

    Excavated material from the trench may be used as backfill above the bedding sandprovided that this material is predominantly soil. If the material does contain any

    metal or rocks, then it may only be used if :

    the amount of metal and rocks is less than 20% of the material (by volume)

    the metal and rocks pass through a 50 mm screen.

    Where conduits are laid beneath other buried services, the backfill beneath suchservices is adequately compacted such that :

    (a) no voids between conduit layers, and

    (b) the other buried service(s) is adequately supported to prevent damage.

    Consolidation of the backfilled excavations will be in accordance with the local

    Council or Transport SA specifications as appropriate.

    12.0 CIVIL WORKS

    12.1 Applicants Responsibilities

    The Applicant or an agent of the applicant shall be responsible for:

    Ensuring that all allotment pegs, including any replacement pegs, easementpegs and level pegs are correctly placed, clearly visible, and numbered to

    show allotment numbers, reserves, easements etc.

    Carrying out and co-ordinating all the pegging, trenching, backfilling,reinstatement, levelling, and associated work including retaining walls,

    necessary for the installation of cables, transformers and switching stations,

    service pits and pillars and lighting columns.

    The safety of the open trench and any liability arising from the Applicant'sworks. This includes ensuring that there is suitable clearance between any

    excavation and existing ETSA infrastructure, including poles and footings. A

    financial penalty can be applied by the industry Regulator for any unlawfull

    interference

  • 8/2/2019 Trenching for Underground Cables

    23/25

    Trenching & Conduit Technical Standard TS - 085

    Damage caused to vaults and associated equipment during backfilling andcompaction

    13.0 CONTAMINATED SOIL

    Where ETSA Utilities constructs the Works, it is the Applicant's responsibility to

    ensure that the soil is free from any contaminants that may be a risk to the health of

    ETSA Utilities distribution workers. Written assurance may be required to

    demonstrate that the soil is free from contamination and if necessary a report detailing

    known contamination and steps taken to alleviate the health risks. Further testing may

    be required before ETSA Utilities agrees to work on the site.

    14.0 CIVIL WORKS COMPLIANCE

    Part of ETSA Utilities regulatory requirements includes an undertaking that any

    electrical installation is compliant. Civil works and conduit installation forms a part of

    the ETSA electrical asset and must be at a standard that satisfies all of the relevant

    ETSA Utilities standards and specifications.

    To assist in the verification that the civil works are to standard a Civil Work

    Compliance form is required from the civil contractor as part of the electrical

    compliance.

    There is a spreadsheet that details responsibilities for both the Civil Works

    Notification form and the Civil Works Compliance form in appendix A of this

    specification.

    14.1 Civil Works Notification

    Civil works form a component of the asset inspection and vesting process. The Civil

    Works Notification form NICC-453 (refer to sect 15.0 for access to the form) must be

    submitted to the appropriate ETSA Utilities representative. The following notice is

    required:A section (contestable projects) 10 working days notice

    B section 5 working days notice

    14.2 Civil Works Compliance

  • 8/2/2019 Trenching for Underground Cables

    24/25

    Trenching & Conduit Technical Standard TS - 085

    www.etsautilities.com.au for external users. Open services/business services/Network Information

    Any ETSA Utilities employee has access via the Intranet index and opening upNetwork/Quality Management Systems/Network Information.

    Some of the information that is relevant to this technical standard include the

    following;

    Civil Contractors Utilised by ETSA Utilities - NICC-203

    For a TSA road: The Notification of Works Impacting SA Roads - NICC-251

    For a railway line: Application to Cross Railways With Electric Power CablesNICC-252

    Civil Works Notification form NICC-453

    Civil Works Compliance form NICC-452

    Terms & Conditions for Network Installation by a Contractor

    Trenching & Conduit Standard Technical Standard TS 085

  • 8/2/2019 Trenching for Underground Cables

    25/25

    Trenching & Conduit Standard Technical Standard TS - 085

    Issued: April 05 TS -085 Authorised: J Ali 11/04/05 Appendix A

    CIVIL WORKS NOTIFICATION & COMPLIANCE RESPONSIBILITY

    CaMS / BSO

    (minor works only)

    CaMS / ContractSvisor (minor &

    major project)

    CPO

    (major projects only)

    Customer (whenresponsible for

    trenching)

    Civil Contractor

    Civil Works notification form NICC - 453 Intranet: Network/QMS/Network Information

    Customer doing thetrenching

    1. Fill in B:Contract Supervisor/ TSW8

    2. Issue to customer

    1. Insert point ofcontact:Compliance Co-ord

    2. Issue to customeras part of

    information pack

    Customer to forwardform to the contractedcivil contractor

    Return form to:A for a contestable

    projectB for all other projects

    (Contract

    Supervisor / TSW8)

    ETSA doing thetrenching

    1. Fill in B:Contract Supervisor/ TSW8

    2. Issue to civilcontractor

    Return form to:Contract Supervisor/ TSW8

    Civil Works Compliance form NICC - 452 Intranet Network/QMS/Network Information

    Customer doing thetrenching

    1. Insert name ofContract Supervisor/ TSW8

    2. Issue to customer

    1. Highlight point ofcontact as electricalcontractor

    2. Issue as part ofinformation pack

    1. Customer to insertelectrical contractordetails

    2. Forward form tocivil contractor

    Return form to:Electrical contractor.If unknown, thecustomer

    ETSA doing the

    trenching

    1. Fill in ETSAContract Supervsor/ TSW8

    2. Issue to civilcontractor

    Return form to:Electrical contractor.If unknown, Contract

    Supervisor / TSW8

    Note: The Civil Works Compliance form must be completed for all projects with a trenching component as

    it is a prerequisite to acceptance of the Certificate of ETSA Utilities Electrical Compliance