Regional Transportation Plan for Klickitat County, Washington November 2018 Southwest Washington Regional Transportation Council Southwest Washington Regional Transportation Council

Transcript of Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed...

Page 1: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

 

Regional Transportation Plan for 

Klickitat County, Washington 

November 2018 

 

 

 

 

Southwest  Washington  Regional  Transportation  Council  Southwest  Washington  Regional  Transportation  Council  

Page 2: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional
Page 3: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

 

 

Regional Transportation Plan for  Klickitat County, Washington 

Klickitat County, Washington 

Published: November 2018 

Southwest Washington Regional Transportation Council 

Street Address Mailing Address1300 Franklin Street

Vancouver, WA 98660 P.O. Box 1366

Vancouver, WA 98666‐1366 

Phone: 564‐397‐6067

https://www.rtc.wa.gov 

 

Clark County 

Skamania County 

Klickitat County 

City of Vancouver 

City of Camas 

City of Washougal 

City of Battle Ground 

City of Ridgefield 

City of La Center 

Town of Yacolt 

City of Stevenson 

City of North Bonneville 

City of White Salmon 

City of Bingen 

City of Goldendale 

C‐TRAN 

Washington DOT 

Port of Vancouver 

Port of Camas‐Washougal 

Port of Ridgefield 

Port of Skamania County 

Port of Klickitat 

Metro 

Oregon DOT 

14th Legislative District 

17th Legislative District 

18th Legislative District 

20th Legislative District 

49th Legislative District 

Page 4: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Introduction  ii 

Regional Transportation Plan for Klickitat County 

Preparation of this Report was funded by grants from the Washington State Department of Transportation (WSDOT) and local funds from RTC member jurisdictions. 

 

 

RTC Respects Civil Rights RTC operates its programs without regard to race, color, national origin, religion, sex, sexual orientation, marital status, age or disability in accordance with applicable laws, including Title VI of the Civil Rights Act of 1964 and RCW 49.60. To request additional information on RTC’s Title VI nondiscrimination requirements, or if any person believes they have been aggrieved by an unlawful discriminatory practice under Title VI or other applicable law and would like to file a complaint, contact us at 564.397.6067 TTY 711 or email [email protected].  

Persons who do not speak or read English well may request language assistance, oral interpretation and/or written translation, at no cost. Contact RTC at 564.397.6067 TTY 711 or email [email protected]

Americans with Disabilities Act (ADA) Information: Individuals requiring reasonable accommodations may request written materials in alternate formats, sign language interpreters, physical accessibility accommodations, or other reasonable accommodations by contacting the ADA Coordinator, Mark Harrington at 546‐397‐5207 TTY 711, with two weeks advance notice.

Page 5: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Introduction  iii 

Regional Transportation Plan for Klickitat County 

Table of Contents Chapter 1: Introduction: RTP Vision, Purpose and Goals .......................................................... 1

Vision ...................................................................................................................................................................... 1Purpose ................................................................................................................................................................... 1Goals ....................................................................................................................................................................... 1

Management Plan for the Columbia River National Scenic Area ..................................................................... 3SR‐14 Corridor Management Plan ................................................................................................................... 3

Transportation Strategy .......................................................................................................................................... 3Guidelines and Principles ........................................................................................................................................ 3Scope ...................................................................................................................................................................... 4Transportation Issues Addressed in RTP ................................................................................................................. 5Statutory Requirements ......................................................................................................................................... 6

State ................................................................................................................................................................. 6Intergovernmental Coordination ............................................................................................................................ 9

Klickitat County Transportation Policy Committee ........................................................................................ 10Bi‐State Coordination ..................................................................................................................................... 11

Klickitat County Regional Transportation Plan: Work Plan ................................................................................... 11Outline of RTP Chapters ........................................................................................................................................ 11

Chapter 2: Land Use, Growth and Transportation .................................................................. 13Land Use and Transportation ............................................................................................................................... 13Growth and Development .................................................................................................................................... 14

Growth in Klickitat County ............................................................................................................................. 15General Land Uses in Klickitat County .................................................................................................................. 16Planned Land Use ................................................................................................................................................. 16Population and Employment Forecast.................................................................................................................. 17Demographic and Travel Trends ........................................................................................................................... 18

Chapter 3: Identification of Regional Transportation Needs .................................................. 21Current Functional Classification of the Regional Roadway System .................................................................... 21

Rural Principal Arterials .................................................................................................................................. 22Rural Minor Arterials ...................................................................................................................................... 22Rural Major Collector Roads .......................................................................................................................... 22Rural Minor Collector Roads .......................................................................................................................... 22Rural Local Roads ........................................................................................................................................... 23

Designation of the RTP Regional Transportation System ..................................................................................... 23All State Transportation Facilities and Services ............................................................................................. 23All Local Principal Arterials ............................................................................................................................. 24All Other Transportation Facilities and Services Considered Necessary to Complete the Regional Transportation Plan ....................................................................................................................................... 24Enhancements ............................................................................................................................................... 28

Page 6: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Introduction  iv 

Regional Transportation Plan for Klickitat County 

Growth in Traffic Volumes .................................................................................................................................... 28Future Travel Demand .......................................................................................................................................... 28Levels of Service .................................................................................................................................................... 29Level of Service Standards .................................................................................................................................... 30Capacity Analysis .................................................................................................................................................. 30Safety Analysis ...................................................................................................................................................... 31

Washington State Department Unstable Slopes ........................................................................................... 32Tunnels ........................................................................................................................................................... 33Trucks ............................................................................................................................................................. 33Recreational Parking ...................................................................................................................................... 33

Preservation and Maintenance Need ................................................................................................................... 34Hood River Bridge Replacement ........................................................................................................................... 34SR‐14 Bingen/White Salmon Circulation Study .................................................................................................... 35Enhancement Need .............................................................................................................................................. 35Economic Development Need .............................................................................................................................. 35Emerging Technology ........................................................................................................................................... 36

Chapter 4: Financial Plan ....................................................................................................... 37Overview ............................................................................................................................................................... 37Challenges and Accomplishments ........................................................................................................................ 37Revenue Sources ................................................................................................................................................... 38

Federal Funding ............................................................................................................................................. 38State Funding ................................................................................................................................................. 39Local Funding ................................................................................................................................................. 41Transit Revenues ............................................................................................................................................ 42

Revenue Assumptions .......................................................................................................................................... 42Cost Assumptions ................................................................................................................................................. 43Balancing Revenue and Cost ................................................................................................................................. 44

Chapter 5: System Improvement and Strategy Plan ............................................................... 47Overview ............................................................................................................................................................... 47Maintenance and Preservation ............................................................................................................................ 47Improvements ...................................................................................................................................................... 48Illustrative ............................................................................................................................................................. 48Miscellaneous Strategies and Solutions ............................................................................................................... 49

Bridge Deficiencies ......................................................................................................................................... 49Safety Deficiencies ......................................................................................................................................... 49Economic Development and Freight Transportation Deficiencies ................................................................. 49Non‐Motorized Transportation Deficiencies ................................................................................................. 50Transit Deficiencies ........................................................................................................................................ 50

Conclusion ............................................................................................................................................................ 50

Chapter 6: Performance Monitoring ...................................................................................... 53

Page 7: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Introduction  v 

Regional Transportation Plan for Klickitat County 

Overview ............................................................................................................................................................... 53Safety .................................................................................................................................................................... 53Capacity Analysis .................................................................................................................................................. 53Preservation and Maintenance ............................................................................................................................ 53Special Studies ...................................................................................................................................................... 54

Chapter 7: Plan Development and Implementation ............................................................... 55Public Involvement in Regional Transportation Planning Process ........................................................................ 55RTP Implementation ............................................................................................................................................. 55RTP Update Process .............................................................................................................................................. 55

Glossary ................................................................................................................................ 57

List of Figures Figure 1‐1: Map of Klickitat County Location .......................................................................................................... 5Figure 1‐2: Agency Structure ................................................................................................................................ 10Figure 1‐3: RTP Process ......................................................................................................................................... 12Figure 2‐1: Land Use/Transportation Cycle .......................................................................................................... 13Figure 2‐2: Population Housing and Employment Growth ................................................................................... 15Figure 2‐3: Population, Housing, and Employment Forecast ............................................................................... 17Figure 4‐1: Transportation Revenue and Cost ...................................................................................................... 45

List of Tables Table 2‐1: Klickitat Work Flow by County ............................................................................................................. 19Table 2‐2: Work Travel Mode ............................................................................................................................... 20Table 3‐1: Klickitat County Public Railroad Crossings ........................................................................................... 28Table 3‐2: Traffic Volumes 2004 to 2017 .............................................................................................................. 28Table 3‐3: Deficient Capacity Segment ................................................................................................................. 31Table 3‐4: Klickitat County Fatality and Serious Injury Factors, 2014‐2016 ......................................................... 32Table 3‐5: Priority Unstable Slope Project along SR 14 ........................................................................................ 33Table 4‐1: Projected Revenue ............................................................................................................................... 43Table 4‐2: Projected Cost ...................................................................................................................................... 44Table 5‐1: Klickitat County Transportation Improvement Projects ...................................................................... 51Table 5‐2: Illustrative Needs ................................................................................................................................. 51

Page 8: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Introduction  vi 

Regional Transportation Plan for Klickitat County 

Klickitat County Transportation Policy Committee 

Policy/Mission Statement TheCommitteesupportstheimprovementofsafetyandefficiencyoftheregionaltransportationsysteminKlickitatCounty.

TheCommitteesupportstransportationplanningandprojectdevelopmentthataddressestheimprovementofpublicsafetyalongtheregionaltransportationsystem.

TheCommitteesupportstheidentificationof“corridorsegments”throughouttheKlickitatCountyregion,whichshouldbethefocusoftransportationimprovement,enhancement,multimodal,andmobilityfunding.

TheCommitteesupportsthecoordinationbetweenagenciesinidentifyingandaddressing,whenpractical,theneedsofamultimodaltransportationsystem.

Klickitat County Member Jurisdictions KlickitatCountyCityofBingenCityofGoldendaleCityofWhiteSalmonPortofKlickitatWashingtonStateDepartmentofTransportation

Klickitat County Transportation Policy Committee Members JimSizemore Commissioner,KlickitatCountyBettyBarnes Mayor,CityofBingenLarryBellamy Administrator,CityofGoldendaleDavidPoucher Mayor,CityofWhiteSalmonMarcThornsbury Director,PortofKlickitatBartGernhart ActingSWRegionAdministrator,WSDOT

Staff (Member Agency and Coordinating Agencies) MichaelWilliams WSDOT,SWRegionDevinReck WSDOT,SWRegionGordonKelsey KlickitatCounty,PublicWorksSharonCarter KlickitatCounty,SeniorServicesDavidSpratt CityofBingenKevinEnglish CityofWhiteSalmonKarlEnyeart CityofGoldendaleKathyFitzpatrick Mid‐ColumbiaEconomicDevelopmentDistrictMichaelMcElwee PortofHoodRiverMattRansom RegionalTransportationCouncilDaleRobins RegionalTransportationCouncil

Page 9: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  1 

Regional Transportation Plan for Klickitat County 

Chapter 1: Introduction: RTP Vision, Purpose and Goals 

TheRegionalTransportationPlan(RTP)forKlickitatCountyistheregion’sprincipaltransportationplanningdocument.ItrepresentsaregionaltransportationplanforKlickitatCountyareadevelopedthroughacoordinatedprocessbetweenlocaljurisdictionsinordertodevelopregionalsolutionstotransportationneeds.ThefirstRTPforKlickitatCountywasadoptedinApril1995.ThisupdatetotheKlickitatCountyRTPwilluse2040asthehorizonyearandincorporatethelatestavailabledata.TheRTPisintendedtobeaplantomeetthetransportationneedsoverthenext20yearsbyimplementingaregionaltransportationplanningprocess.Thisintroductorychapterpresentsthevision,purpose,goals,scope,statutoryrequirements,anddecision‐makingprocessinvolvedindevelopmentoftheRTPforKlickitatCounty.

Vision TheRTPisacollectiveefforttoaddressthedevelopmentofasaferegionaltransportationsystemthatwillsupportplannedeconomicgrowthandmaintaintheregion’sruralqualityoflife.

Purpose TheRTPidentifiesfutureregionaltransportationsystemneedsandoutlinestransportationplansandimprovementsnecessarytomaintainadequatemobilityandsafetywithinandthroughouttheKlickitatCountyregion.Theregionmustplanforafutureregionaltransportationsystemthatadequatelyservesthepopulation,employment,andvisitorgrowthprojectedforKlickitatCounty.TheRTP’sgoals,objectives,andpolicieswillguidethevariousjurisdictionsandagenciesinvolvedinplanningandprogrammingoftransportationprojectsthroughoutKlickitatCounty.

Goals ThefollowinggoalswereusedtoguidethedevelopmentoftheKlickitatCountyRegionalTransportationPlan:

Page 10: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  2 

Regional Transportation Plan for Klickitat County 

Preservation:Maintainandpreservetheexistingregionaltransportationsystem.

SafetyandSecurity:Provideasafeandsecuretransportationsystem.

Economy:Provideatransportationsystemthatfosterseconomicdevelopment.

Finance:Provideforthedevelopmentofatransportationsystemthatefficientlyusesfinancialresources.

AccessibilityandMobility:Provideanintegratedandcoordinatedtransportationsystemthatincludesavarietyofmobilityoptions.

Environment:Provideatransportationsystemthatissensitivetothequalityoftheenvironmentandnaturalresources.

VisionandValues:Provideforviableandlivablelocalcommunities.

ManagementandOperations:Maximizeefficientmanagementandoperationofthetransportationsystem.

ThereisconsistencybetweenthegeneralRTPgoalsandthepoliciesestablishedbylocaljurisdictionsandagenciesaspartoftheirlocalcomprehensiveplanningprocess.TheRegionalTransportationPlan(RTP)forKlickitatCounty,whereapplicable,willalsoconsiderthegoalsestablishedintheManagementPlanfortheColumbiaRiverGorgeNationalScenicAreaandotherlong‐rangeplans.

Page 11: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  3 

Regional Transportation Plan for Klickitat County 

Management Plan for the Columbia River National Scenic Area 

Providetransportationfacilitiesthatmeettheneedsofthetravelingpublicandimplementthisplan’srecreationgoalsandobjectiveswhileprotectingscenic,natural,cultural,andrecreationresources.

Promotealternativemodesoftransportationtoimprovesafetyandenjoymentofthetravelingpublicandtohelpalleviatefuturetrafficdemand.

EnsurethatareplacementColumbiaRiverBridgebetweentheHoodRiverandBingen/WhiteSalmonUrbanAreasprovidesforregionaltransportationandpublicsafetyneedswhilebeingconsistentwithbothpurposesoftheScenicAreaAct.

SR‐14 Corridor Management Plan 

ImprovesafetyalongSR‐14withrespectfortheprotectionandenhancementofresources.

Enhancetheeconomyofcommunitiesalongthehighway.

DesignHighway14asanationalattractionbyprotectingandenhancingscenic,natural,cultural,andrecreationresourceswithinthehighwaycorridor,withrespecttolocalresidences,andbusiness.

ManagetheSR‐14Corridorinthemostefficientandeffectivemannerpossible.

Transportation Strategy TheRegionalTransportationPlanforKlickitatCountyistheregion’stransportationstrategy.

Guidelines and Principles In1994,theStateLegislaturepassedSubstituteHouseBill1928.ThislegislationrequiresRTPO’stoestablishGuidelinesandPrinciplesthatprovidedirectionforthedevelopmentofthetransportationelementsofcomprehensiveplans.Thefollowingrepresenttheseguidelinesandprinciples:

Identifyadequateareasforfuturecommercial,retail,andindustrialeconomicgrowth.Coordinateidentifiedeconomicgrowthareaswithanefficienttransportationsystem.

Page 12: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  4 

Regional Transportation Plan for Klickitat County 

Identifyadequatelandforresidentialdevelopmentanddensitywithinurbanareasthatiscoordinatedwiththetransportationsystem.

Provideatransportationsystemthatsupportstheeconomicvitalityoftheregion,andprovidesforlong‐termfreightmobilityneedsandportaccess.

Providearangeofnon‐motorizedopportunitieswithintheregionaltransportationsystem.

Worktowardthedevelopmentofacoresystemofall‐weatherroadsforfreighttravel.

Encouragereducingtherelianceonthesingleoccupantvehiclebyprovidingothermodesoftransportation.

Encouragepresentandfuturerailroadrightofwaytobeutilizedfortransportationpurposes.

Enhanceintermodalfreightconnections.

Scope TheRTPforKlickitatCountytakestheyear2040asitshorizonyear.Traveldemandfortheregionisforecastforthisfutureyearandimprovementstothetransportationsystemarerecommendedbasedontheprojecteddemand.

TheareacoveredbytheRTPisthewholeofKlickitatCounty.KlickitatCountyissituatedalongthenorthernbankoftheColumbiaRiverinsouth‐centralWashington.TheCountyliesonthesoutheastflankofMountAdams.Onthenorth,thecountyborderstheSimcoeHillsandcontainspartoftheYakamaIndianReservation.(SeeFigure1‐1).

Page 13: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  5 

Regional Transportation Plan for Klickitat County 

Figure 1‐1: Map of Klickitat County Location 

People and freight move throughout the regional transportation system withoutconsiderationforcity,county,andstateboundaries.Sincetransportationproblemsextend beyond jurisdictional boundaries, the RTP must analyze the futuretransportationneedsfortheentireregionwhilecreatingacooperativeframeworkforcoordinatingtheindividualactionsofvariousjurisdictions.

Transportation Issues Addressed in RTP 

Transportationsystemmaintenance,preservation,andsafety.

Developmentofcorridorstoimproveeconomicdevelopmentpotential.

AccessibilityacrosstheColumbiaRiverintermsofcapacity,economicdevelopment,corridorlocation,andconnectingroadways.

Federal,state,local,andprivatesourcesofrevenuefortransportationprojects.

Page 14: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  6 

Regional Transportation Plan for Klickitat County 

Accesstoports,airports,intermodaltransportationfacilities,majorfreightdistributionroutes,andrecreationareas.

Theneedtorelieveandpreventcongestionfromoccurringwhereitdoesnotyetoccur.

Theneedtoimprovecorridorswithsafetyproblems,includingfreightcorridors.

Theneedtoprovideamultimodaltransportationsystem;includingpedestrian,bicycle,bus,truck,rail,marine,andauto.

Theneedtoprovideenhancements(signs,viewpoints,kiosk,etc.),toassistvisitors.

Statutory Requirements 

State 

WithinWashingtonState,RegionalTransportationPlansareexpectedtobeconsistentwiththepolicyframeworkandobjectivesdescribedinthetransportationplanforWashingtonState.ThemostrecentWashingtonTransportationPlan,2035,wasdevelopedbytheWashingtonTransportationCommissionandadoptedinJanuary2015.WashingtonTransportationPlanPhase2–Implementation2017‐2040wasapprovedinApril2018.

TheWashingtonTransportationPlan2035isbasedonthefollowingtransportationpolicygoalsestablishedbytheLegislature:

EconomicVitality:Topromoteanddeveloptransportationsystemsthatstimulate,support,andenhancethemovementofpeopleandgoodstoensureaprosperouseconomy;

Page 15: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  7 

Regional Transportation Plan for Klickitat County 

Preservation:Tomaintain,preserve,andextendthelifeandutilityofpriorinvestmentsintransportationsystemsandservices;

Safety:Toprovideforandimprovethesafetyandsecurityoftransportationcustomersandthetransportationsystem;

Mobility:ToimprovethepredictablemovementofgoodsandpeoplethroughoutWashingtonState;

Environment:ToenhanceWashington’squalityoflifethroughtransportationinvestmentsthatpromoteenergyconservation,enhancehealthycommunities,andprotecttheenvironment;and

Stewardship:Tocontinuouslyimprovethequality,effectiveness,andefficiencyofthetransportationsystem.

TheWashingtonStateHighwaySystemPlan(HSP)istheelementofWashington’sTransportationPlan(WTP)thataddressescurrentandforecaststatehighwayneeds.TheHSPincludesacomprehensiveassessmentofexistingandprojected20‐yeardeficienciesonthestate’shighwaysystem.Italsolistspotentialsolutionsthataddressthesedeficiencies.TheHSPisupdatedperiodicallywitheachversionbuildingonthelast.Thedocumentcoversallissuesrelatedtothestate’shighwaysystem.The2007‐2026versionoftheHSPtakestheWTP’sinvestmentguidelines,andidentifiesthehighwaysystemneeds,strategiesandperformancemeasurementsassociatedwiththeguidelines.

WSDOT'sCorridorSketchInitiativeisasetofplanningactivitiesthatengagestheagency'spartnerstodeterminethecontextandperformanceofstatehighwaycorridorsandidentifieshigh‐levelstrategiesforaddressingperformancegaps.Theinitiativecomplementsandsupportsregionalplanningprocessesaroundthestate.

Inaddition,WSDOThascompletedanumberofModelPlansincludingplansforAviation,Bicycle&Pedestrians,Ferry,Freight,Rail,PublicTransportation,andUltra‐HighSpeedGroundTransportation.

RecentWSDOTplansaredocumentedonWSDOT’sPlanningsectionwebsite.

Washington State’s Regional Transportation Planning Program 

WashingtonState'sGrowthManagementAct,enactedin1990,approvedtheRegionalTransportationPlanningProgramwhichcreatedaformalmechanismforlocalgovernmentsandthestatetocoordinatetransportationplanningforregionaltransportationfacilities.TheGrowthManagementAct(GMA)authorizedthecreationofRegionalTransportationPlanningOrganizations(RTPOs)byunitsoflocalgovernment.SouthwestWashingtonRegionalTransportationCouncil(RTC)is

Page 16: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  8 

Regional Transportation Plan for Klickitat County 

thedesignatedRTPOforthethree‐countyareaofClark,Skamania,andKlickitat.In1994,furtherstatelegislationclarifiedthedutiesoftheRTPOoutlinedintheGMAandfurtherdefinedRTPOplanningstandards.

ThedutiesoftheRTPO,asoutlinedintheGMAandSHB1928,include:

Designationoftheregionaltransportationsystem.

DevelopmentofasixyearregionalTransportationImprovementProgram(TIP),includingregionallysignificantprojects.TheTIPmustincludeafinancialplan.

DevelopmentofaRegionalTransportationPlan(RTP),toincludearegionaltransportationstrategy,identificationofexistingandplannedfacilitiesandprograms,LevelofServicestandards,afinancialplan,assessmentofregionaldevelopmentpatternsandcapitalinvestmentusingaregionaltransportationapproach.TheconceptofleastcostplanningistobeusedindevelopmentoftheRTP.TheRTPmustbereviewedatleasteverytwoyearstoensurethatitiscurrent.

EstablishguidelinesandprinciplesfordevelopmentandevaluationofthetransportationelementsofGMAlocalcomprehensiveplans.

DeveloparegionalLevelofService(LOS)standardfortheregionalsystemasrequiredbytheLOSBill.

TheRegionalTransportationPlanningProgramisdesignedtobeintegratedwith,andaugment,thefederallyrequiredMetropolitanPlanningOrganization(MPO)program.TheRegionalTransportationPlanningProgramextendstransportationplanningbytheRTPO’storuralareasnotcoveredbythefederalprogram.TheRegionalTransportationPlanningProgramisalsointendedtotieinandbeconsistentwithlocalcomprehensiveplanning.

Theregionaltransportationplanningprocessshould:

Guidetheimprovementoftheregionaltransportationsystem.

Useregionallyconsistenttechnicalmethodsanddata.

Considerenvironmentalimpacts.

Ensureearlyandcontinuouspublicinvolvement.

Beconsistentwiththelocalcomprehensiveplanningprocess.

Beanongoingprocess.

Incorporatemultimodalplanningactivities.

Addressmajorcapacityexpansionandoperationalimprovementstotheregionaltransportationsystem.

Page 17: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  9 

Regional Transportation Plan for Klickitat County 

Beapartnership,includingfederal,state,andlocalgovernments,specialdistricts,privatesector,generalpublic,andothersduringconception,technicalanalysis,policydevelopment,anddecision‐making.

TocomplywithStatestandards,theRTPshallincludethefollowingcomponents:

Descriptionofthedesignatedregionaltransportationsystem.

Regionaltransportationgoals,policies,andstrategy.

Regionallandusestrategy.Existingandproposedlandusesdefinedonlocalandregionalcomprehensivelanduseplansdeterminetheregionaldevelopmentstrategy.

Identificationofregionaltransportationneeds.Aninventoryofexistingregionaltransportationfacilitiesandservices,identificationofcurrentdeficiencies,andforecastoffuturetraveldemandwillbecarriedout.

DevelopmentofLOSstandardsconsistentwithHouseBill1487.

Developmentoffinancialplanfornecessarytransportationsystemimprovements.

Regionaltransportationsystemimprovementandstrategyplan.Specificfacilityorserviceimprovementswillbeidentifiedandprioritiesdetermined.

Establishmentofaperformancemonitoringprogram.Theperformanceofthetransportationsystemwillbemonitoredovertime.Themonitoringmethodology,datacollection,andanalysistechniquestobeusedwillbeoutlined.

PlansforimplementationoftheRTP.

Intergovernmental Coordination InordertomaketheRTPnotonlyaPlantoprovidecarefullythought‐outsolutionstotransportationissuesandproblemsbutalsoaPlanthatalljurisdictionscanimplement,aregionaltransportationplanningcommitteestructurehasbeenestablished.Consistentwiththe1990GMAlegislation,athree‐countyRTCBoardofDirectorshasbeenestablishedtoservetheRTPOregion.IndividualCountyCommitteesandBoardsalsoplayapartintheregionaltransportationdecision‐making.TheKlickitatCountyTransportationPolicyCommitteecontinuestoguideKlickitatCountyregionaltransportationpolicy.Theroleof,andrepresentationon,theRTCBoardofDirectorsandindividualCountyPolicyCommitteesisdescribedintheBylawsofSouthwestWashingtonRegionalTransportationCouncil(lastamendedDecember2017)andInterlocalAgreementforEstablishmentofthe

Page 18: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  10 

Regional Transportation Plan for Klickitat County 

SouthwestWashingtonRegionalTransportationCouncil.TheregionaltransportationcommitteestructureisoutlinedinFigure1‐2.

Figure 1‐2: Agency Structure 

Klickitat County Transportation Policy Committee 

TheKlickitatCountyTransportationPolicyCommitteewasestablishedtoprovideafocusforKlickitatCountyregionaltransportationissuesandpolicies.ItiscomposedofrepresentativesofWashingtonStateDepartmentofTransportation(WSDOT),KlickitatCounty,CityofBingen,CityofGoldendale,CityofWhiteSalmon,andthePortofKlickitat.

TheKlickitatCountyTransportationPolicyCommitteecarriesoutregionaltransportationplanningactivitieswithinKlickitatCounty.Otheragenciesandorganizationsarewelcometoparticipateasnon‐votingmembersofthecommittee.Otherlocal/regionalagenciesandorganization(e.g.ColumbiaRiverGorgeCommission,U.S.ForestService,Mid‐ColumbiaEconomicDevelopmentDistrict,andPortofHoodRiver)arewelcometoparticipateasnon‐votingmembersofthecommittee.

Page 19: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  11 

Regional Transportation Plan for Klickitat County 

Bi‐State Coordination 

KlickitatCountyislocatedontheWashingtonsideoftheColumbiaRiverGorgeRegionandbi‐statetravelissignificantwithinthisregion.OregonandWashingtonjurisdictionsintheregionhaveahistoryofcoordinatingtheirtransportationandlanduseplans.Theseplanningeffortsensurethatregionallysignificantaspectsofthetransportationsystemareconsideredwithinabi‐statecontext.

RTCrepresentativesparticipateinbi‐statetransportationopportunitieswithOregonrepresentatives.ThisincludestheGorgeTransLinkgroup,bi‐statestudies,andotherbi‐stateopportunities.Inaddition,RTCwelcomesparticipationofOregonrepresentativesintheKlickitatCountytransportationplanningprocess.CoordinationbetweenWashingtonandOregononbi‐statetransportationneedswillcontinuethroughtheregionaltransportationplanningprocess.

Klickitat County Regional Transportation Plan: Work Plan AsafirststepinpreparationoftheKlickitatCountyRTP,aworkplanwasdeveloped.(SeeFigure1‐3).TheworkplanoutlinesmajortaskstobecoveredinthedevelopmentoftheRTP.TheRTPisdesignedasabenchmarkplantomeetRTPOelementsrequiredbythe1990GMAlegislationandSHB1928legislationof1994.

Outline of RTP Chapters Chapter1: Introduction:RTPVision,Purpose,andGoals.TheRTPisintroducedanditsgeneralgoals,policies,statutoryauthority,andpurposearedescribed.TheRTPprocessisoutlinedaswellasregionaltransportationcommitteestructureandintergovernmentalcooperationandcoordinationoftheRTP.

Chapter2: RegionalLandUseandGrowth.KlickitatCounty’sdemographicdata,developmenttrends,andregionaldevelopmentstrategyarediscussed.Existingandfuturelandusesanddevelopmentpatternsareidentified.

Chapter3: IdentificationofRegionalTransportationNeeds.Theregionaltransportationsystemisdesignatedanddefined.Thecharacteristicsandpatternsoftoday’sandfutureregionaltraveldemand,today’stransportationproblemlocations,andfutureregionalneedsaredescribed.Needscriteriasuchasaccessibility,levelsofservice,andsafetyareoutlined.

Chapter4: FinancialPlan.Revenuesourcesareidentifiedanddescribed,andaplanforfinancingtransportationsystemimprovementsispresented.

Page 20: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 1: Introduction: RTP Vision, Purpose and Goals  12 

Regional Transportation Plan for Klickitat County 

Chapter5: SystemImprovementandStrategyPlan.Recommendationsfordevelopmentoftheregionaltransportationsystemaremade.Regionaltransportationgoalsandpoliciesarereviewed.

Chapter6: PerformanceMonitoring.Performancemonitoringmeasuresaredescribed.MonitoringtheRTP’sconsistencywiththestatetransportationplan,localtransportationplans,landuseregulations,andregionaldemographicprojectionsareoutlined.

Chapter7: PlanDevelopmentandImplementation.ProvisionsfortheimplementationofthepublicindevelopmentoftheRTParedescribed.Provisionsfortheimplementationofregionaltransportationgoals,policies,andactionsestablishedbytheRTParedescribed.TheRTPreviewandamendmentprocessisoutlinedshouldchangingpolicies,financialconditions,orgrowthpatternswarrantamendmentofthePlan.TherequiredbiennialupdateoftheRTPisdescribed.

Figure 1‐3: RTP Process 

Feedback

Feedback

RTP Vision, Purpose and Goals

MobilityEnvironmentalImpacts

CostsStateTransportationPlan

RegionalTransportationPlanningProgram

Implementation and MonitoringTransportationCommitteesRTCBoardofDirectorsMemberAgencies

Plan Recommendations and Adoption

SystemConceptHighway/Transit/Non‐MotorizedModes

AirQualityDemand/SystemManagement

Financing

Land Use and GrowthDevelopmentStrategyExistingLandUsePlannedLandUse

FuturePopulationandEmploymentForecast

Analysis of Needs and AlternativesRegionalTransportationSystem

TravelDemandAnalysis/EvaluationofAlternatives

FinancingOptions

Page 21: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 2: Land Use, Growth and Transportation  13 

Regional Transportation Plan for Klickitat County 

Chapter 2: Land Use, Growth and Transportation 

Land Use and Transportation Transportationplanningisaboutmeetingthetraveldemandsofpeopleandgoods.Thetransportationsystemmustconnectpeopletojobsandservicesandconnectfreightandgoodstomarketsandconsumers.Indevelopingaregionaltransportationplan,thefundamentalrelationshipbetweentransportationandlandusemustberecognized,andtheeffectthatlanduseandgrowthhaveontransportationmustbetakenintoconsideration.TheLandUse/TransportationcycleisillustratedinFigure2‐1.

Figure 2‐1: Land Use/Transportation Cycle 

Thelinkagebetweenlanduseandtransportationisacomplexissue,butonasimplelevel,thelinkagecanbethoughtofasworkingintwoways:

Page 22: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 2: Land Use, Growth and Transportation  14 

Regional Transportation Plan for Klickitat County 

1. Thespatialdistributionandtypeoflanduseactivityinfluenceboththedemandfortravelandtravelcharacteristics.Differenttypesoflandusegenerateandattractdifferingtrafficrates;forexample,retaillanduseswillgeneratemoretripsthanresidentiallanduses.

2. Improvingaccessbyexpandingthetransportationsystemallowsforthedevelopmentoflandthatwasformerlyinaccessible.

Landuseandtransportationareinter‐linkedbecauselanduseactivitieslargelydeterminetraveldemandanddesire.Whendifferentlandusesaresegmentedorsegregated,lengthoftripstendstoincrease.Forexample,peoplehavetotravelbetweentheirhomesandtheirworkplaces.Tomeetmobilityneeds,theselongertripsusuallyhavetobeservedbytheautomobile,thusreducingtheuseoftransportationalternatives,suchaswalkingortransit.

Growth and Development Sustainedeconomicdevelopmentandgrowthwithinaregionisdesirablebecauseoftheeconomicbenefitsthatincreasedemploymentandalargertaxbasecanbring.However,whilegrowthcancontributetothehealthofaregion’seconomy,itcanalsohavenegativeimpacts.Unmanaged,fastratesofgrowthcanhaveasevereimpactontheabilityofacommunitytoprovideneededinfrastructureandservices.

Theneedtomaintaineconomicviabilityandatthesametime,qualityoflife,isachallenge.Elementsthatcontributetoadesirablequalityoflifeincludejobopportunities,affordablehousing,ahealthyenvironmentwithcleanair,andrecreationalopportunities.Anefficient,safetransportationsystemcontributestothequalityoflifeforresidentsofaregionandcanactasanattractorforeconomicdevelopment.Conversely,atransportationsystemdependentondeterioratingandoutmodedfacilitiescanbeaninhibitortotheefficient,safemovementofpeopleandgoods.

Page 23: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 2: Land Use, Growth and Transportation  15 

Regional Transportation Plan for Klickitat County 

Growth in Klickitat County 

KlickitatCountyhasseenmoderategrowthinthelastfewdecades.TheU.S.CensusBureau,WashingtonState’sOfficeofFinancialManagement(OFM),andBureauofEconomicAnalysis(BEA)providedthefollowingdata.BEAemploymentincludesallwageandsalariedjobsaswellasproprietorsjobsthatincludessoleproprietor,self‐employed,andfarmemployment.

Aftersignificantgrowthintheearly2000’s,theUnitedStatesexperiencedasignificantrecessionbeginninginlate2007.Thisrecessionimpactedregionalpopulationandemploymentgrowthforapproximately5years.

Between1990and2010thepopulationofthecountyincreasedby22%from16,616to20,318,whilethenumberofhousingunitsincreasedby35%from7,238to9,786.TheincreaseinBEAemploymentwas39%from7,508in1990to10,430in2010(seeFigure2‐2).Muchofthegrowthoccurredbetween1990and2007,whilegrowthslowedbetween2007and2010.By2016,thecountypopulationhadincreasedto21,270people,with10,432housingunitsand10,775jobs.

Figure 2‐2: Population Housing and Employment Growth 

KlickitatCountyhasseenalargeincreaseinrecreationactivitydueinparttotheColumbiaRiverGorgeNationalScenicAreaandavarietyofotherrecreationalopportunities.Thegrowthinrecreationactivitiesseeninthecountyinthelastfewdecadeshasincreaseddemandsontheregionaltransportationsystem.

Developmentofatransportationpolicyplanmustconsiderhowtoplanforatransportationsystemthatcansupportincreasesintraveldemandcausedbygrowthinpopulation,employment,andrecreationalactivity.Atthesametime,thissystemhastobeaffordableandminimizeenvironmentalimpactstomaintainthe

0

5000

10000

15000

20000

25000

Population Housing Units BEA Employment

1990 2000 2010 2016

Page 24: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 2: Land Use, Growth and Transportation  16 

Regional Transportation Plan for Klickitat County 

qualityoflife.Asafe,efficienttransportationsystemcanworktoenhanceeconomicdevelopmentwithinaregion.

General Land Uses in Klickitat County KlickitatCountyisaruralcountylocatedinsouthcentralWashington.Approximatelytwo‐thirdsofKlickitatCountyresidentsliveinunincorporatedareas.ThethreeincorporatedpopulationcentersarelocatedinGoldendaleinthecentralpartofthecountyandinBingenandWhiteSalmoninthesouthwestcornerofthecounty.Thecountyis84mileslongandvariesbetween13and29mileswide.Thetotalareaofthecountyis1,904squaremiles.KlickitatCountyranks16thinsizeamongWashington’s39countiesand29thinpopulation.

Klickitat County’s economic base is tied to agriculture, timber and forestry, the Roosevelt Regional Landfill, aerospace and high technology, and wind power with a significant percentage of its work force in agriculture and manufacturing. In recent years, growth has been concentrated around the White Salmon/Bingen and Dallesport areas.

Theprovisionofpublicfacilitiesandservices,includingtransportation,isaprincipaldeterminantoflandusepatterns.LandusepatternsinKlickitatCountyhaveevolvedlargelyasaresultofitsresidents’dependenceontheautomobile.AlookatlanduseforKlickitatCountyindicatesthatresidentialdevelopmenthasoccurredmainlyalongstatehighwaysandmajorruralarterials.

Planned Land Use Comprehensiveplansarethemeansbywhichlocaljurisdictionscanplanfortheirfuturegrowthanddevelopment;theycanprovideaprocessforanticipatingandinfluencingtheorderlyandcoordinateddevelopmentofland.WithinWashingtonState,planningauthorityisdelegatedbythestatetolocalgovernmentsinRCW

36.70A,35.63and35A.63.Comprehensiveplansarerequiredtohavealanduseelementshowingthegeneraldistributionandlocationoflandforvarioususes,aswellasacirculationelementshowingthestreetsystemandtransportationroutes.KlickitatCountyandincorporatedcitiesofBingen,Goldendale,andWhiteSalmonallhavecurrentlyadoptedcomprehensiveplans.

Page 25: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 2: Land Use, Growth and Transportation  17 

Regional Transportation Plan for Klickitat County 

TheColumbiaRiverGorgeCommissionhasadoptedandisadministeringaColumbiaRiverGorgeManagementPlanpursuanttotherequirementsoftheNationalScenicAreaAct.WithintheColumbiaRiverGorgeNationalScenicArea,futureresidentialandcommercialdevelopmentisencouragedtooccurintheUrbanAreas,butthereisallowanceforsomeresidentialdevelopmentoutsidetheurbanareas.Inaddition,therearetwofederallydesignatedWildandScenicRiversegmentsthathaveadoptedmanagementplansareadministeredbytheForestService.

Population and Employment Forecast TheWashingtonStateOfficeofFinancialManagement(OFM)developspopulationforecastsforallcountiesintheStateofWashington.Theirforecastcontainsalow,medium,andhighestimate.The2017forecastdevelopedbyOFMfor2040populationinKlickitatCountyrangesfromalowof17,583toahighof26,954.ForthepurposeoftheRegionalTransportationPlan,amedium‐highforecastof24,442willbeused.The2040forecastrepresentsa20%or4,124increaseinpopulationfrom2010to2040.

HousingandemploymentforecastsforKlickitatCountyweredevelopedbyRTCbasedonOFMpopulationforecastandhistoricaltrends.Estimated2040housingis12,094units.The2040forecastrepresentsa24%or2,308increaseinhousingunitsfrom2010to2040.Estimated2040employmentis13,138.This2040forecastrepresentsa21%or2,131increaseinemploymentfrom2010to2040(seeFigure2‐3).

Figure 2‐3: Population, Housing, and Employment Forecast 

 

0

5000

10000

15000

20000

25000

30000

Population Housing Units BEA Employment

Page 26: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 2: Land Use, Growth and Transportation  18 

Regional Transportation Plan for Klickitat County 

Demographic and Travel Trends 

Growthinpopulationandemployment,development,andresultinglandusepatternstogetherwithitsdistributionallaffecttraveldemand.However,otherdemographicfactorsalsoinfluencetraveldemand.Thesefactorsincludehouseholdsize,workforceparticipation,employmentpatterns,andvehicleownership.

Householdsizeisonedemographicfactorsthatinfluenceslanduseanddemandfortransportationservices.Between1970and2010therewasatrendtowardsmallerhouseholdsizeinKlickitatCountyduetomoresingle‐personhouseholdsandsmallerfamilysize.Theaveragenumberofpersonsperhousingunitwas2.60in1970,buthadfallento2.08by2010.The2040forecastis2.02personsperhousingunit.

Thefuturepopulationisexpectedtobecomeolderwithahigherproportionofthetotalpopulationhavingdisabilities.Itisestimatedbetween2010and2040personsovertheageof65willincreasefrom18%ofthepopulationtoapproximately34%ofthepopulation.In2016,thosewithadisabilitymadeupapproximately19%oftheCountypopulationandthisisexpectedtoincreasetoover20%infutureyears.Withanagingpopulationandagrowingnumberofindividualswithdisabilities,futuredemandandtraveltrendsareexpectedtochange.

Anotherdemographictrendthataffectstraveldemandistheincreaseintwo‐workerhouseholds.Typically,thetwoworkersinthehouseholdeachuseanautotogettowork,usetheautoforworkpurposeswhileatwork,useittorunerrandsatlunchtimeandbeforeorafterwork,andiftheyhaveafamily,totaketheirchildrentoactivities.Allresultinpeople’sincreasedrelianceontheautomobilethatpeopleconsidertheirmostconvenienttransportationmode.

Employmentpatternshavealsobeenchanging,witharelativedeclineseeninthetraditionalindustrialortimberjobsandanincreaseinservicesectoremployment.Withmoderntechnology,therehasalsobeenarapidgrowthinworkerswhoareabletoworkathome.Inaddition,thereisatrendforasignificantnumberof

KlickitatCountyresidentstobeemployedinothercounties.The2010Censusshowsthat30.8%ofthecountyresidentsworkedoutsideofKlickitatCounty.Table2‐1showsdataofthoselivingand/orworkinginKlickitatCounty.

Page 27: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 2: Land Use, Growth and Transportation  19 

Regional Transportation Plan for Klickitat County 

Table 2‐1: Klickitat Work Flow by County 

Place of Residence  Place of Work  2000 2000 

Percent  2010 2010 

Percent 2000‐2010 Change 

Klickitat County  Klickitat County 5,632 73.5% 5,340 69.2%  ‐292

  Hood River Co., OR 688 9.0% 625 8.1%  ‐63

  Wasco Co., OR 680 8.9% 945 12.3%  265

  Skamania Co., WA 147 1.9% 340 4.4%  193

  Yakima Co., WA 104 1.4% 50 0.6%  ‐54

  Sherman Co., OR 73 1.0% 65 0.8%  ‐8

  Benton Co., WA 44 0.6% 10 0.1%  ‐34

  Other Washington 137 1.8% 153 2.0%  16

  Other Oregon 109 1.4% 154 2.0%  45

  Other  50 0.6% 32 0.4%  ‐18

Klickitat Co. Employed Workforce  7,664 7,714   50

Klickitat County  Klickitat County 5,632 84.8% 5,340 80.3%  ‐292

Hood River Co., OR    167 2.5% 255 3.8%  88

Wasco Co., OR    399 6.0% 245 3.7%  ‐154

Skamania Co., WA    205 3.1% 340 5.1%  135

Yakima Co., WA    82 1.2% 35 0.5%  ‐47

Other Washington    65 1.0% 259 3.9%  194

Other Oregon    92 1.4% 84 1.3%  ‐8

Other    2 0.0% 92 1.4%  90

Employment within Klickitat County  6,644 6,650   6

TraveldemandhasalsogrownasthenumberofpassengervehiclesinKlickitatCountyhasincreasedinthepastfewdecades.Aspopulationhasincreased,therehasbeenanincreaseinthenumberofvehiclesregisteredinKlickitatCountyaddingtothedemandsputonthetransportationsystem.In2010,therewere13,127registeredpassengervehicleswith69.3%oftheKlickitatCountyhouseholdshavingtwoormorevehiclesavailable.Therelationshipbetweenlanduseandtransportationshouldbecarefullyconsideredwhendevelopingavisionforfuturegrowthandfuturegrowthpatterns.

ThereareseveraltrendsthataffectseasonaltraveldemandwithinKlickitatCounty.First,isthetrendofadditionalretiredresidentswholiveinKlickitatCounty,butspendtheirwintersinawarmerclimate.Theseresidentsaddtothelocaltrafficfromspringtofall.Second,istheincreasedpopularityoftheColumbiaRiverGorgeareaasarecreationalattractor.SinceitsdesignationasaNationalScenicArea,summertrafficvolumeshaverapidlyincreased.

Table2‐2alsoprovidesinformationthatcompares2000and2010CensusJourneytoWorkdata.Thisdatadisplaysseveraltrendsimpactingthecommutertraveltimes.First,thedatashowsthatcommutetimeshavedecreasedbyover2minutes.Second,theuseofdrivealone,bicycleorwalk,andworkfromhomehaveincreased.

Page 28: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 2: Land Use, Growth and Transportation  20 

Regional Transportation Plan for Klickitat County 

Third,therehasbeenasignificantdeclineinthenumberofpeoplewhocarpoolontheirjourneytowork.

Table 2‐2: Work Travel Mode 

Klickitat County  2000 2000 

Percent  2010 2010 

Percent 2000‐2010 

Growth 

2000‐2010 Percent Change 

2010 WA State 

Percent 

Drive Alone  5,505  71.8% 5,810 75.3% 305 5.5%  72.3%

Carpool  1,182  15.4% 854 11.1% ‐328 ‐27.7%  11.6%

Transit  51  0.7% 14 0.2% ‐37 ‐72.5%  5.6%

Bicycle or Walked  363  4.7% 465 6.0% 102 28.1%  4.3%

Motorcycle/Other  90  1.2% 65 0.7% ‐25 ‐27.8%  1.2%

Worked at Home  473  6.2% 525 6.8% 52 11.0%  5.1%

Totals  6,285  100.0% 7,666 100.0% 1,380 22.0%  100.0%

Mean Travel Time to Work (minutes)  21.9  n/a  19.5  n/a  ‐2.4  n/a  25.4 

Page 29: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  21 

Regional Transportation Plan for Klickitat County 

Chapter 3: Identification of Regional Transportation Needs 

Current Functional Classification of the Regional Roadway System Functionalclassificationisthegroupingofhighways,roads,andstreetsbythecharacterofservicetheyprovide.Comprehensivetransportationplanningusesfunctionalclassificationtodeterminehowtravelcanbechannelizedwithinthenetworkinalogicalandefficientmanner.Afunctionalclassificationdefinesthemajorrolethataroadorstreetserveswithinthetotalexistingandfutureroadwaynetwork.Insimpleterms,highways,streets,androadsfunctionasarterials,collectors,orlocalaccess.Arterialsprovidethehighestdegreeofmobilityandlimitedaccesstolocalproperty.Collectorsgenerallyprovideequalemphasisuponmobilityandlandaccess.Localroadsandstreetsemphasizelandaccessinlieuofmobility.

TheWashingtonStateDepartmentofTransportation(WSDOT)hastheprimaryresponsibilityfordevelopingandupdatingthehighwayfunctionalclassificationsystem.Theyworkcooperativelywithlocalandregionalagenciesindevelopingandupdatingthefunctionalclassificationsystem.TheFederalFunctionalClassificationsystemforKlickitatCountyroadshasbeencompletedandresultedinacountywideuniformclassificationsystem.Generally,facilitiesclassifiedasMajorCollectororaboveinruralareasareeligibleforfederalfunding.FurtherinformationonthefunctionalclassificationofroadscanbefoundonWSDOT’swebsite.Astatewidemapofthefederalfunctionalclassificationisavailable,allowingthezoomingintoKlickitatCountyandCitydetail.

ISTEAalsorequiredthatroadsbedesignatedasNationalHighwaySystem(NHS)facilities.CongressapprovedtheNHSSystemwithpassageoftheNationalHighwaySystemDesignationActof1995.InKlickitatCounty,theHoodRiverBridge,SR‐97,andSR‐14(betweentheSkamaniaCountylineandSR‐97)aredesignatedasNHSfacilities.

In1999,thestatelegislatureadoptedHighwaysofStatewideSignificance,fulfillingarequirementofHouseBill1487passedin1998.InKlickitat,SR‐97andSR‐14

Page 30: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  22 

Regional Transportation Plan for Klickitat County 

(betweentheSkamaniaCountylineandSR‐97)aredesignatedasHighwaysofStatewideSignificance.

Adescriptionoftheruralfunctionalclassificationcategoriesfollows:

Rural Principal Arterials 

Ruralprincipalarterialsaresub‐dividedintotwosets(1)interstatefacilitiesand(2)otherprincipalarterials.Ruralprincipalarterialsservecorridormovementshavingtriplengthandtraveldensitycharacteristicsofstatewideorinterstatetravel.Theyconsistofaconnectedruralnetworkofcontinuousroutes.

Rural Minor Arterials 

Inconjunctionwiththeprincipalarterials,theruralminorarterialsformaruralnetworkwhichlinkcitiesandlargertownstogetherwithothermajortrafficgenerators.Theprincipalarterialsandruralminorarterialsarespacedatsuchintervalsthatalldevelopedareasofthestatearewithinareasonabledistanceofanarterialhighway.Minorarterialsshouldbeexpectedtoprovideforrelativelyhighoveralltravelspeedswithminimuminterferencetothroughmovement.

Rural Major Collector Roads 

Ruralmajorcollectorsprovideservicetolargertownsnotdirectlyservedbythehighersystemsandtoothertrafficgeneratorsofequivalentimportance.Ruralmajorcollectorsservethemoreimportanttravelcorridorswithinthecounty.

Rural Minor Collector Roads   

Ruralminorcollectorsarespacedatintervals,consistentwithpopulationdensity,tocollecttrafficfromlocalroadsandprovidedevelopedareaswithreasonable

Page 31: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  23 

Regional Transportation Plan for Klickitat County 

distancetoacollectorroad.Ruralminorcollectorsprovideservicetotheremainingsmallercommunitiesandlinkthelocallyimportanttrafficgeneratorswithsurroundingruralareas.

Rural Local Roads 

Localstreetsprovidedirectaccesstoabuttinglandandaccesstothehigherclassificationfacilities.Theyofferthelowestlevelofmobility.Theyarenotintendedtocarrythroughtraffic;however,theydomakeupalargepercentageofthetotalstreetmileage.

Designation of the RTP Regional Transportation System Consistentwiththestate’sRegionalTransportationPlanningProgramPlanningStandards,theRTPregionaltransportationsystemhasbeendesignatedtoinclude:

1. Allstatetransportationfacilitiesandservices(includingstatehighways).

2. Alllocalprincipalarterials(thedefinitionofruralprincipalarterialscanbethesameasusedforfederalclassificationorberegionallydetermined).

3. Allothertransportationfacilitiesandservices,includingairports,transitservicesandfacilities,roadways,bridges,railfacilities,marinetransportationfacilities,etc.thattheRTPOconsidersnecessarytocompletetheregionalplan.

4. Anytransportationfacilityorservicethatisregionallyneededorimpactsplacesintheplan,asdeterminedbytheRTPO.

AdetaileddescriptionofthedesignatedRTPRegionalTransportationSystemfollows:

All State Transportation Facilities and Services 

InKlickitatCountythiscategoryincludesthefollowingStateRoutes:SR‐14,SR‐35,SR‐97,SR‐141,SR‐141Spur,SR‐142,andSR‐197.

SR‐14providesthemaineast‐westaccessfromtheSkamania/KlickitatCountylinetosouth‐eastBenton/KlickitatCountylinealongthenorthbankoftheColumbiaRiver.Thefacilityhasonelaneineachdirectionandextends88.76milesthroughKlickitatCountybetweenSkamaniaCountyandBentonCountylines.

SR‐35willprovideafuturelinkacrosstheColumbiaRivertoOregonintheBingen/WhiteSalmonarea.CurrentlytheHoodRiverBridgeisservingasthislink.

Page 32: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  24 

Regional Transportation Plan for Klickitat County 

SR‐97providesthemainsouth‐centralaccessfromtheColumbiaRiver(Oregon)tonorth‐centralYakima/KlickitatCountyline,throughGoldendalethecountyseat.Thefacilityhasonelaneineachdirectionandextends33.52milesthroughKlickitatCountybetweentheStateofOregonandYakimaCountyline.

SR‐141providesnorthandsouthaccessfromBingentotheSkamania/KlickitatCountylinenearTroutLake.Thefacilityhasonelaneineachdirectionandextends29.19milesfromSR‐14toitsendattheSkamania/KlickitatCountyline.

SR‐141SpurprovidesnorthandsouthaccessfromSR‐14neartheKlickitat/SkamaniaCountylinetoSR‐141northwestofWhiteSalmon.Thefacilityhasonelaneineachdirectionandextends2.16miles.

SR‐142providesaccessfromLyletoGoldendale.Thefacilityhasonelaneineachdirectionandextends35.29milesfromSR‐14(Lyle)toSR‐97(Goldendale).

SR‐197providesnorthandsouthaccessfromTheDalles,Oregon,acrosstheColumbiaRivertoSR‐14.Thefacilityhasonelaneineachdirectionandextends3.18milesfromtheColumbiaRivertoSR‐14nearDallesport,Washington.

All Local Principal Arterials 

InadditiontoStateRoutes,theonlyotherruralprincipalarterialinKlickitatCountyistheHoodRiverBridge.

TheHoodRiverBridgehasaverticalliftspanandcrossestheColumbiaRiverbetweenHoodRiver,OregonandWhiteSalmon,Washington.ItconnectsInterstate84/U.S.Route30ontheOregonsidewithWashingtonStateRoute14.Thefacilityhasonesubstandardlaneineachdirectionandisapproximatelyonemilelong.

All Other Transportation Facilities and Services Considered Necessary to Complete the Regional Transportation Plan 

Theseincludetransitservicesandfacilities,roadways,railfacilities,airports,marinetransportationfacilities,etc.

Rural Major Collectors 

Alllocalmajorcollectorsaredesignatedaspartoftheregionaltransportationsystem.MajorcollectorsincludesuchfacilitiesasMapleSt.,N.MainSt.,DockGradeRd.,DewaltDrive,EstesAv.,AlderdaleRd.,McKinleySpringsRd.,RooseveltGrade/EastRd.,BickletonHwy.,BZ‐GlenwoodHwy.,GlenwoodHwy.,TroutLakeHwy./SunnysideRd./WarnerRd.,SnowdenRd.,CanyonRd.,CentervilleHwy.,

Page 33: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  25 

Regional Transportation Plan for Klickitat County 

DallesportRd.,NWLoopRd.,SouthColumbusAv.,HorseshoeBendRd./SimcoeMtn.Rd,Mt.AdamsRd,W.DarlandRd.,RailroadAv.,S.RooseveltSt.,SimcoeDr.,andOldHwy8.

Port Facilities 

KlickitatCountyhasonePortDistrict,theKlickitatCountyPortDistrict#1.ThisPortDistrictisnotacountywideportdistrict,butdoesincludemostofwesternKlickitatCounty.TheportdistrictdoesexcludethecountyseatofGoldendale.ThePortofKlickitatownsandoperatestwobusiness/industrialparkswithinthecounty.First,theporthas142acresofcommercial/recreational/lightindustrialzonedproperty,whichfrontstheColumbiaRiveratRiverMile172,locatedtothesouthoftheCityofBingen.Thisbusinessparkincludesapproximately55acresofdevelopableproperty,30acresoflakeandwetland,a18acreboatbasin,andaboatlaunchandparkarea.Secondly,theporthasa660acreindustrialparkatDallesport.Theparkisservedbyallutilities,rail,andabargedockfacility.ThepropertyislocatedontheColumbiaRiveratRiverMile192,upriverfromTheDallesDam,andisadjacenttoSR‐197,onemilefromInterstate84inOregon,andonemilefromtheDallesportregionalairport.

TheregionaltransportationsystemincludesimportantPortroads,suchasMarinaWay,LarchSt.,BingenPointWay,DockRd.,DowRd.,andParallelAv.ThiswouldalsoincludethenewrailroadundercrossingthatWSDOTplanstoconstructin2020betweenSR‐14andMarinaWaytoimproveaccesstoBingenPoint.

Airport Facilities 

TherearetwopublicairfieldscurrentlyoperatinginKlickitatCounty.TheairfieldsarelocatedinGoldendaleandDallesport.TheairfieldinDallesport(TheColumbiaGorgeregionalAirport)isco‐ownedandoperatedbytheCityofTheDalles(Oregon)andKlickitatCounty.TheColumbiaGorgeRegionalAirportalsoincludesabusinesspark.TheGoldendaleMunicipalAirportisacityownedairportwithrunwayandtiedownarea.

Inadditiontopublicairfields,thereareseveralprivatelandingstripsinKlickitatCounty.ThenearestregionalairportwithdomesticandinternationalpassengerandfreightserviceisthePortlandInternationalAirport(PDX).PDXislocatedinPortland,Oregon,approximately70mileswestoftheBingen/WhiteSalmonarea.

Bridges 

AllpublicbridgesincludingColumbiaRiverbridgesaredesignatedaspartoftheregionaltransportationsystem.Allbridgesareimportanttothemovementofpeopleand

Page 34: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  26 

Regional Transportation Plan for Klickitat County 

goodswithintheregion.OfgreatimportancearethosebridgesthatcrosstheColumbiaRiver.

TherearethreebridgesinKlickitatCountycrossingtheColumbiaRiverbetweenWashingtonandOregon,connectingSR‐14toInterstate84.TheHoodRiverBridgeisatwolanedtollbridgeownedandmaintainedbythePortofHoodRiver,connectingHoodRiver,OregontoBingen/WhiteSalmon,Washington.TheSR‐197BridgeisatwolanedbridgeconnectingTheDalles,OregontoDallesport,Washington.TheSR‐197BridgeismaintainedbyODOT.TheSR‐97BridgeisatwolanedbridgeconnectingBiggsJunction,Oregon,andMaryhill,Washington.TheSR‐97BridgeismaintainedbyWSDOT.

Inaddition,theWashingtonStateLegislaturedesignatedanSR‐35corridorinthe1997legislativesession.TheSR‐35corridorwillprovideafuturelinkacrosstheColumbiaRivertoOregonintheBingen/WhiteSalmonarea.ADraftEnvironmentalImpactStatementforafuturerivercrossingintheSR‐35corridorwascompletedin2004,aTypeSizeandLocationStudywascompletedin2011,andaFinalEnvironmentalImpactStatementwillbethenextstepintheprojectdevelopmentprocess.

Columbia River 

Historically,theColumbiaRiverhasalwaysbeenanimportanttransportationcorridortoKlickitatCounty.TheColumbiaRiver,asatransportationcorridor,isusedtodaytomovegoodsbybargeandpeoplebyboat.TourboatsalsovisittheColumbiaRiveranddockwithintheregion.

 

Page 35: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  27 

Regional Transportation Plan for Klickitat County 

Public Transportation 

KlickitatCountySeniorServicesrunsMt.AdamsTransit.Mt.AdamsTransitoperatesageneraldemandresponsepublictransportationsysteminKlickitatCounty.Serviceincludesbothbusesandvolunteerdrivers.

Although,thedial‐a‐rideserviceprovidespreferencetoseniorsandpersonswithdisabilities,allCountyresidentsareeligible.Themajorityofsystemtripsareformedical,socialservices,shopping,andeducationalopportunities.Mt.AdamsTransportationgoestoallareasofKlickitatCounty,TheDalles,andHoodRiveronaregularbasis.Mt.AdamsTransportationoftengoestothePortland/VancouverandYakimaregionsformedicalservices.

Beginninginthesummerof2018Mt.AdamsTransitwillstarttwonewweekdayfixedbusroutesthatwillrunfromapproximately7amto7pm.OneroutewillconnectWhiteSalmonandBingentoHoodRiver,OregonandtheotherroutewillconnectGoldendaletoTheDalles,Oregon.TheWhiteSalmonroutewillconnecttoboththeHoodRiverCityRouteandtotheColumbiaGorgeExpressroute.TheseconnectionswillprovideKlickitatCountyresidentswithservicearoundtheCityofHoodRiver(ColumbiaAreaTransit)andtoCascadeLocks,MultnomahFalls,RoosterRockStatePark,andPortlandGatewayTransitCenter(ColumbiaGorgeExpress.

GrantsthroughtheWashingtonStateDepartmentofTransportationareessentialinmaintainingtheexistingservice.In1998,thevotersofKlickitatrejected,byasmallmargin,anincreaseinsalestaxtofundaPublicTransportationBenefitArea(PTBA).

Mt.AdamsTransitparticipateswithGorgeTransLinkcoalition.TheGorgeTransLinkisanallianceoftransportationprovidersofferingpublictransportationservicesthroughouttheMid‐ColumbiaRiverGorgeareaaswellastodestinations,suchasPortlandandVancouver.ThegoalofthiscoordinationeffortistoimproveinterconnectivitybetweenthevarioustransitprovidersintheMid‐ColumbiaRiverRegioninbothOregonandWashington.

Rail Facilities 

ThereisonemainraillineinuseinKlickitatCountywhichprovidesfreightandpassengerservice.BurlingtonNorthernSantaFeRailroad(BNSF)ownstherailline.TheBNSFVancouver/EasternWashingtonlinehasonetrackingoodconditionwithapproximately60trainsoperatingonthemdaily.WithinKlickitatCounty,therearevitaltransfersiteslocatedatBingen,Dallesport,Roosevelt,andWishram.AMTRAKalsohasanagreementwithBNSFtooperatepassengerserviceonthefreightcarrier’sraillines.Sevendaysaweek,theAMTRAKEmpireBuildertravelsthroughKlickitatCountybotheastandwestbetweenPortland,OregonandChicago,Illinois,withstopsinBingenandWishram.

Alongthemainrailline,therearesevenpublicandnumerousprivateat‐graderailroadcrossingsinKlickitatCounty.Thepublicat‐graderailroadcrossingsarelistedinTable3‐1.

Page 36: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  28 

Regional Transportation Plan for Klickitat County 

Table 3‐1: Klickitat County Public Railroad Crossings 

Road  Warning System

Dock Grade (White Salmon) Warning Lights and Drawbars 

Walnut St. (Bingen) Warning Lights (Soon to be upgraded)

Maple St. (Bingen) Warning Lights and Drawbars 

Old Ferry Rd. (Dallesport) Warning Lights

Horsethief Park Stop Sign

Avery Rd.  Warning Lights

Stonehenge Rd. (Maryhill) Warning Light and Drawbars 

Enhancements 

Transportationenhancementsaredesignedaspartoftheregionaltransportationsystem.Enhancementsincludefacilitiesforbicyclesandpedestrians,scenicvistas,thematicsignage,reststops,touristinformation,androadsidebeautificationalongtheregionalroadnetwork.

Growth in Traffic Volumes Asaresultofsocio‐economicanddemographicchangesdescribedinChapter2,KlickitatCountyhasseenanincreaseintrafficvolumesinrecentyears,especiallyaroundthecommunitiesofBingen/WhiteSalmonandDallesport.WashingtonStateDepartmentofTransportationcompilestrafficcountdataalongStateRoutes.ExamplesofgrowthintrafficvolumesatselectedlocationsalongStateRoutesinKlickitatCountyarelistedinTable3‐2:

Table 3‐2: Traffic Volumes 2004 to 2017 

Location  Leg 2004 

Volumes 2017 

Volumes  % Increase 

SR‐14 at SR‐141 Spur E 6,600 8,400  27%

SR‐14 at Hood River Br. E 8,300 12,000  45%

SR‐14 at SR‐97  E 4,700 4,700  0%

SR‐14 at Benton Co. Ln. W 830 1,100  32%

SR‐197 at Columbia Rv. N 5,300 7,200  36%

SR‐97 at Columbia Rv. N 5,100 5,400  6%

SR‐97 at Goldendale N 4,800 5,200  8%

Future Travel Demand FutureautotraveldemandwasforecastedfortheKlickitatCountyregionbasedonhistorictrends,netchangesinlanduseandactivitylevels,applyingappropriate

Page 37: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  29 

Regional Transportation Plan for Klickitat County 

trafficgenerationrates,andthenusingtripdistributioninformationtodeterminethedirectionoftravel.

TheRTPnetworkisconsideredtobethesametransportationnetworkasexiststoday.Itisusedonlyasabasecasescenarioforforecastingfuturetraveldemandandpotentialtrafficvolumesonroadsegmentsanddoesnotconstitutearecommendednetwork.TrafficvolumescoulddiffersignificantlyfromthosethatresultfromthefuturetripassignmentontotheRTPnetworkifsignificantchangestothepopulation,landuse,ortransportationsystemoccur.

BurlingtonNorthernSantaFeoperatestheeast‐westrailroadroutealongtheWashingtonsideoftheColumbiaRiverGorgeandthroughKlickitatCounty.Thisrouteiscurrentlyexperiencingcapacityconstraintsandwillcontinuetointhefuturewithoutsomekindofexpansion.Withamoderateincreaseinpopulation,KlickitatCountyhasadequateairportfacilities.TheColumbiaRiversystemisanimportanttransportationcorridorforthemovementofgoods.Inordertomeetthetraveldemandassociatedwiththiscorridor,itwillbeessentialtopreserveappropriatechanneldepthsandwidthsforshippingandtomaintaincurrentlockhandlingcapacity.Walkingandbicyclingareintegralpartsofthetransportationsystem.Peoplewalkandbikeforvarioustrips.Walkingandbicyclingtripsareusuallyshortanddemandisgreaterinurbanareas.However,thereisademandforbicyclingfacilitiesalongmajorcorridorsandroutes.Publictransitisanimportantaspectofthetransportationsystem,especiallyforthosewithlimitedincome,elderly,anddisabled.Withanagingpopulationandpercapitaincomelowerthanthestateaverage,thedemandforpublictransitislikelytoincreaseinKlickitatCounty.

Levels of Service Levelsofservicestandardsrepresenttheminimumperformanceleveldesiredfortransportationfacilitiesandserviceswithintheregion.Theyareusedasagaugeforevaluatingthequalityofserviceonthetransportationsystemandcanbedescribedbytraveltimes,travelspeed,freedomtomaneuver,trafficinterruptions,comfort,convenience,andsafety.TheselevelsofservicearedesignatedAthroughF,frombesttoworst.LevelofserviceEdescribesconditionsapproachingandatcapacity.Foruninterruptedflowconditions,thefollowingdefinitions1apply:

LevelofServiceAdescribesfreeflowconditions,withlowvolumesandhighspeeds.Thegenerallevelofcomfortandconvenienceprovidedtothemotorist,passenger,orpedestrianisexcellent.

LevelofServiceBisintherangeofstableflowbutthepresenceofotherusersinthetrafficstreambeginstobenoticeable.Freedomtoselectdesiredspeedsisrelativelyunaffected,butthereisaslightdeclineinthefreedomtomaneuverwiththetrafficstreamfromLevelofServiceA.

1 From Highway Capacity Manual

Page 38: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  30 

Regional Transportation Plan for Klickitat County 

LevelofServiceCisstillintherangeofstableflow,butmarksthebeginningoftherangeofflowinwhichtheoperationofindividualusersbecomessignificantlyaffectedbyinteractionswithothersinthetrafficstream.Thegenerallevelofcomfortandconveniencedeclinesnoticeablyatthislevel.

LevelofServiceDrepresentshigh‐density,butstableflow.Speedandfreedomtomaneuverareseverelyrestricted,andthedriverorpedestrianexperiencesagenerallypoorlevelofcomfortandconvenience.

LevelofServiceErepresentsoperatingconditionsatornearthecapacitylevel.Allspeedsarereducedtoalow,butrelativelyuniformvalue.Comfortandconveniencelevelsareextremelypooranddriverorpedestrianfrustrationisgenerallyhigh.

LevelofServiceFdescribesforcedorbreakdownflow.Theseconditionsusuallyresultfromqueuesofvehiclesbackingupfromarestrictiondownstream.Operationswithinthequeuearecharacterizedbystop‐and‐gowaves,andtheyareextremelyunstable.

Level of Service Standards In1998,theWashingtonStateLegislaturepassedtheLevelofService(LOS)Bill.TheBillsetnewrequirementsrelatingtotransportationandgrowthmanagementplanning.Theintentofthelegislationwastoenhancethecoordinationofplanningeffortsandplanconsistencyatthelocal,regional,andstatelevel.Thekeyapplicableelementsinclude:

HighwaysofStatewideSignificance:TheStatemustgivehigherprioritytocorrectingidentifieddeficienciesontransportationfacilitiesofstatewidesignificance.DesignationofHighwaysofStatewideSignificance(HSS)wascompletedin1999.InKlickitatCounty,theHSSsystemincludesSR‐97andSR‐14,betweentheSkamaniaCountylineandSR‐97.WSDOThasestablishedanLOS‘C’forruralHSSfacilitieslikeSR‐14.

Non‐HighwaysofStatewideSignificance:Non‐HSSstatehighways,otherwiseknownasHighwaysofRegionalSignificance,inKlickitatCountyincludetheremainingportionofSR‐14,SR‐141,SR‐142,andSR‐197.TheRTPOhasestablishedanLOS‘C’forruralnon‐HSS.

Capacity Analysis TheHighwayCapacityManualmethodologywasusedtoanalyzeroadwaylevelofservicewithintheKlickitatCountyRegionbasedonP.M.peakhourtraffic.Inaddition,thereareseverallocationswithcapacitydeficienciesassociatedwithsubstandardcurvesandsteepgrades,whichcreateaparticularproblemonsome

Page 39: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  31 

Regional Transportation Plan for Klickitat County 

facilitiesduetothemixoftrucks,recreationalvehicles,andautos.DeficientsegmentsassociatedwithcapacityareincludedinTable3‐3.

Table 3‐3: Deficient Capacity Segment 

Road  Mile Post Deficient Capacity Segment  LOS

SR‐14  65.95‐66.96 Bingen C

SR‐14  100.2‐101.44 SR‐14 Maryhill Spur to SR‐97  C

Hood River 

Bridge 

Columbia 

River 

Hood River Bridge: between SR‐14 and I‐84 C

SR‐97  0.00‐12.67 Biggs Rapid Bridge to End Climbing Lane  C

SR‐97  20.29‐27.16 Allen Creek Road to Ski Lodge Road  C

SR‐97  30.80‐31.44 Satus Creek Bridge Vicinity C

Safety Analysis Improvingsafetyforallmodesoftransportationiscriticaltoimprovingqualityoflifeandimprovingaccessforallthecitizensoftheregion.WashingtonState’sStrategicHighwaySafetyPlan,TargetZero,establishesastatewidepolicyofzerofatalitiesandzerodisablinginjurycollisionsby2030.TargetZero,helpstoassessthesafetyneedsstatewide,encouragingandpromotinggoodsafetypracticesinthedesignandoperationofthetransportationsystem,aswellaspromotingsafetybysystemusers.TargetZerosetsstate‐widepriorities,providesaresourceforpotentialstrategies,andmonitorsoutcomeatastatewidelevel.

StatewidetrafficsafetyprioritieswereusedtodisplayKlickitatCountyfatalityandseriousinjurydata.Table3‐4showstheKlickitatCountyFatalityandSeriousInjuryFactorsbystatewideprioritiesbetweenyears2014‐2016.Sincemorethanonefactoriscommonlyinvolvedinmostcollisions,thefatalitiesandseriousinjuriesby

factordonotmatchthetotalsatthebottomofthetable.TheTotalsatthebottomofthetablerepresenttheactualnumberoffatalities(16)andseriousinjuries(58)overthethreeyearperiod.

Page 40: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  32 

Regional Transportation Plan for Klickitat County 

Table 3‐4: Klickitat County Fatality and Serious Injury Factors, 2014‐2016 

  Fatalities  Serious Injuries 

  # of People  % of Total  # of People  % of Total 

Priority Level One         

  Run Off the Road  5  71.4%  24  61.5% 

  Impaired Driver Involved  2  28.6%  11  28.2% 

  Distracted Driver Involved  1  14.3%  9  23.1% 

  Speeding Involved  1  14.3%  9  23.1% 

  Intersection Related  1  14.3%  4  10.3% 

  Young Driver Involved  0  0.0%  9  23.1% 

Priority Level Two         

  Unrestrained Vehicle Occupants  2  28.6%  8  20.5% 

  Motorcyclist  1  14.3%  4  10.3% 

  Unlicensed Driver Involved  1  14.3%  0  0.0% 

  Opposite Direction Multi‐vehicle  0  0.0%  5  12.8% 

  Pedestrian  0  0.0%  0  0.0% 

Priority Level Three         

  Older Driver 75+ Involved  2  28.6%  4  10.3% 

  Heavy Truck Involved  1  14.3%  5  12.8% 

Drowsy Driver Involved  0  0.0%  5  12.8% 

  Bicyclist  0  0.0%  1  2.6% 

  Wildlife  0  0.0%  1  2.6% 

  Vehicle‐Train  0  0.0%  0  0.0% 

  Work Zone  0  0.0%  0  0.0% 

  School Bus Involve  0  0.0%  0  0.0% 

Total  16    58   

WashingtonStateStrategicSafetyPlan,TargetZero,includesspecificobjectivesandstrategiestohelpreducetrafficfatalitiesandseriousinjuriesforeachoftheprimaryfactors. Within Klickitat County, the focus should be on implementing strategiesthataddressthehighestprioritizingfactors.

Washington State Department Unstable Slopes 

WashingtonStateDepartmentofTransportation(WSDOT)begantheirUnstableSlopeManagementSystemin1993.Thismanagementsystemincorporatedanumericalslopehazardratingsystem.Theratingsystemutilizesamatrixevaluatingelevencategories.In2004anenvironmentalassessmentofSR‐14

Page 41: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  33 

Regional Transportation Plan for Klickitat County 

unstableslopeswascompleted.Ofthesitesinvestigated,3priorityprojectswereidentifiedinKlickitatCounty.PriorityprojectshadanUnstableSlopeManagementSystemratinggreaterthan200.Thosewithratingsabove300totalpointsrepresentarelativelyhighhazardslope.ABenefittoCost(B/C)Ratioisthenusedtodetermineprojectpriority.Table3‐5liststhepriorityprojectsalongSR‐14inKlickitatCounty.

Table 3‐5: Priority Unstable Slope Project along SR 14 

Road  Mile Post Rating B/C Ratio Improvement 

SR‐14  68.75‐69.10 429 Remove debris/Euromesh/Reslope

SR‐14  73.18‐73.87 303 3.61 Rockfall ditch 

SR‐14  77.31‐77.67 525 2.03 Scaling/Fence/Euromesh 

Tunnels 

TherearetwotunnelsalongSR‐14inKlickitatCounty,nearLyle.Thesetunnelshavea24footpavementwidth,noshoulders,lighting,orbicyclewarningsystem.Thetunnelsarearchedwithacenterclearanceseveralfeethigherthanthe13.5footclearanceattheouteredgeofthepavement.Trucks,especiallythoseunfamiliarwiththetunnels,frequentlystraddlethecenterlinecreatingadangeroussituation.

Trucks 

Interstate84(I‐84)andStateRoute14(SR‐14)areparalleleast/westhighwaystravelingthroughthesouthernportionoftheKlickitatregion.I‐84isa4‐laneInterstatefacilitylocatedinOregonandSR‐14isarural2‐laneStateHighwaylocatedinWashington.Bothroutesarepublicroutesthatareopentoalllegaltrucks.Asaruralhighway,SR‐14islessconducivetothroughtrucktrafficbecauseofsharpcurves,steepgrades,andheightrestrictions.ThroughtrucktrafficshouldbeencouragedtouseI‐84toincreasemobilityandsafety.

TheOregonDepartmentofTransportationestimatesa4‐5%avoidanceoftheOregonWeightMileTaxstate‐wide.However,a1997SR‐14TruckSurveyfoundthat8%to13%ofthetrucksonSR‐14maybeavoidingtheOregonWeightMiletax.AslongasWashingtonandOregonStateshavedifferenttrucktaxationmethods,sometruckerswillchoosetouseSR‐14tolowertheiroverallcosts.

Recreational Parking 

Thegrowthinrecreationhascreatedaparkingcapacityissueatpopularrecreationalsites,whichoftenleadstoillegalparkingandsafetyissuesonthetransportationsystem.

Page 42: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  34 

Regional Transportation Plan for Klickitat County 

Preservation and Maintenance Need Ofoverwhelmingimportanceintheplanningfortheregionaltransportationsystemistheneedtomaintainandpreservetheexistingsysteminordertoprotecttheheavyinvestmentsalreadymadeinthesystem.TheRTPsupportsprojectsprogrammedintheTransportationImprovementProgramtomaintainandpreservetheregionaltransportationsystem.

WashingtonStatehasdevelopedaBridgeManagementSystem,aproceduretovisuallysurveybridgeconditions.Thissystemisintendedtoassistwiththeprioritizationofbridgereplacementandmaintenance.ProjectswithimmediateneedsareprogrammedintotheStateorlocalSix‐YearTransportationImprovementProgram.Thereareseveralbridgesindeterioratingcondition,orofsubstandardwidththatneedtobereplacedwithinthenext20years.TheHoodRiverBridgeisregularlyinspectedbytheOregonDepartmentofTransportation.MaintenanceandrepairsaremadebythePortofHoodRiver,whoownsthebridge.

APavementManagementSystemhasbeendevelopedforpavementconditiononallstateroadfacilities.Thissystemisintendedtoassistwiththeprioritizationofpavementpreservationandtorespondtorecentlyobservedconditionsandpredictprobablefutureconditions.WSDOTandlocaljurisdictionsvisuallyinspectpavementconditionsoffacilitiestodetermineneededmaintenanceandpreservation.ProjectsthathavereachedaconditionthatwarrantsrehabilitationareprogrammedintotheStateandlocalTransportationImprovementPrograms.

BurlingtonNorthernSantaFeRailroadmaintainstheBNSFmainraillinethroughKlickitatCounty.ThePortofHoodRivermaintainstheHoodRiverBridge.TheGoldendaleandTheDallesmunicipalairportsareoperatedandmaintainedbytheCityofGoldendaleandKlickitatCounty/CityofTheDalles,respectively.UnderthedirectionoftheU.S.ArmyCorpsofEngineers,theColumbiaRiverismaintained.LocaljurisdictionsandWSDOTmaintainbicycleandpedestrianfacilities.

TheRegionalTransportationplansupportsadditionaltransportationdollarsforthepreservationandmaintenanceoftheregionaltransportationsystem.

Hood River Bridge Replacement 

TheHoodRiverBridgewasoriginallybuiltin1924andisoneofthreebridgestraversingtheColumbiaRiverintheColumbiaRiverGorgeNationalScenicArea.ThebridgeconnectsthecommunitiesofWhiteSalmonandBingen,Washington,withHoodRiver,Oregon.

TransportationagenciesfromWashingtonandOregonhavebeenevaluatingtheneedtoreplacethebridgesince1998.In2004,afeasibilityanddraftenvironmentalimpactstatementwerecompleted.In2011aType,Size,andLocationStudywascompleted.

Page 43: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  35 

Regional Transportation Plan for Klickitat County 

Thepreferredbridgealignmentislocateddirectlywestoftheexistingbridge.ThebridgewouldtieintotheexistingbridgeaccessroadontheOregonsideandwithanewintersectionatSR‐14.Thepreferredbridgealternativewouldbeatwolaneconcretesegmentalboxgirderbridge,withshouldersandamultiusepathway.Thenewbridgewouldnotneedaliftspan.

In2018,theregionalpartnerswillbegintheworktocompleteaFinalEnvironmentalImpactStatementforthereplacementoftheHoodRiverBridge.

SR‐14 Bingen/White Salmon Circulation Study In2017,SR14fromSR141AlttoalocationjusteastoftheeasternBingencitylimitswasstudiedtoidentifytransportationneedswithinthecorridor.TheStudyrecommendedpedestrian,intersection,andotherhighwayimprovementswhichcouldimprovetheoperationsandfunctionalityofSR‐14throughtheCitiesofBingenandWhiteSalmon.ThefinalStudyreportandrecommendationscanbefoundonRTC’swebsite.

Enhancement Need  Thereisaneedtodevelopandimprovefacilitiesforbicycles,pedestrians,scenicvistas,restareas,thematicsignage,roadsidebeautification,recreationalparkingandotherenhancementswithinKlickitatCounty.TheRegionalTransportationPlansupportscosteffectiveenhancementstothetransportationsystem.

Economic Development Need Theprosperityofaregionisdependentontheprovisionoftransportationinfrastructuretosupporteconomicdevelopment.Themovementofgoodsbyhighway,rail,water,andairareessentialtotheeconomyofKlickitatCounty.

TheRTPsupportsthedevelopmentofanall‐weatherroadnetworkforthemovementofpeopleandgoodswithintheregion.Thisall‐weatherroadnetworkshouldincludeallfacilitiesfunctionallyclassifiedasmajorcollectorsandabove.Thisall‐weatherroadnetworkwillprovidethetransportationinfrastructurenecessaryforthemovementofgoodstomarket,andwillstrengthenthelocaleconomy.

TheRTPsupportsthereplacementoftheHoodRiverBridge.TheHoodRiverBridgeisamajortransportationcorridorprovidingaccessbetweensouthwestKlickitatCountyandHoodRiver,Oregon.TheHoodRiverBridgeprovidestheprincipleaccessforsouthwestKlickitatCountytoemployment,services,andgoods.Thisfacilityisimportantforthemovementoflocalgoods(fruitandtimber)tomarket.Thisfacilityisessentialtotheregionsdiversificationbyprovidingaccessand

Page 44: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 3: Identification of Regional Transportation Needs  36 

Regional Transportation Plan for Klickitat County 

employmentopportunitiesrelatedtothetourism/recreationalsector.Theexistingfacilityisnarrowandinadequatetohandlethedemandsoftheregion.Thefacilityisagingandwilllikelyneedtobereplacedwithinthenext15‐20years.ThelocaleconomydependsheavilyontheHoodRiverBridge,ensuringanadequatereplacementfacilityisahighpriorityfortheregion.

TheRTPsupportsimprovedaccesstoportfacilitiessuchasBingenPointandDallesportIndustrialPark.ThiswouldalsoincludethenewrailroadundercrossingthatWSDOTplanstoconstructin2020toimproveaccesstoBingenPoint.

TheRTPsupportsimprovementstothetransportationsystemthatwillgiveprimeconsiderationtoeconomicdevelopmentandthesafe,efficientmovementofpeopleandfreight.Specifically,freightproducedbyormaterialnecessaryfortheoperationofbusinessesandindustrieswithinKlickitatCounty.

Emerging Technology 

Emergingtechnologyisageneraltermthatisusedtodescribedevelopmentsintransportationtechnology.Thiscouldincludeawiderangeoftechnologysuchasautomatedvehicles,connectedvehicles,carsharing,carhailing,travelerinformation,automatedtolls,andsmartcities.

Technologyisalreadybeginningtotransformthewaypeoplemove.Individualsareincreasinglyusingsmartphoneapplicationstohelpthemmaketraveldecisions.Ridesharingandhailingservicesarebecomingincreasinglypopularthroughouttheworld.Vehiclesafetytechnologyisbeingdevelopedtoensurethesafetyandsecurityofautomobiles.Thesetechnologychangesarelikelytohavesignificantimplicationsonhowpeopletravelinthefuture.

Page 45: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  37 

Regional Transportation Plan for Klickitat County 

Chapter 4: Financial Plan 

Overview PotentialtransportationimprovementprojectsproposedinthisPlanareintendedtomeettheRTPgoalsandpolicyobjectiveasoutlinedinChapterOne.Thesegoalsandpoliciesincludemakingthemostefficientuseofandenhancingtheexistingtransportationsystem.

Theavailabilityoffederal,state,andlocalmoneyswillhaveasignificantimpactontheabilitytofundproposedprojects.Thischapterdescribesrevenuesourcesanddiscusseschangestorevenuesourcesasaresultoffederalandstatelegislation.Theprojectionoffundingabilityisbasedonhistoricalfundinglevels.TheabilityoftheprojectedfundingtomeetRTPcostsisdetermined.

Transportationhastraditionallybeenfundedby“userfees”.Today,themajortaxsourcestofundtransportationarethegastax,vehiclelicenses,permits,andfees.Gastaxisimposedatthefederallevel($0.184pergallon)andattheStatelevel($0.494pergallon)andisdevotedtoroadwaypurposes.

Challenges and Accomplishments TheRTPfacesconsiderablechallengesforfundingthetransportationsystemintothefuture.Overthelastdecadefewerdollarshavebeenspentonthetransportationsystemastransportationrevenueshavedeclined.Asthetransportationsystemages,thecostofpreservingandmaintainingtheexistingtransportationsystemhasincreased.Thereisaneedtohaveapublicdiscussiononhowtransportationcostwillbepaidforinthefuture

TheRTPwaslastadoptedin2014;sincethattime,anumberofimprovementshavebeencompletedorwillsoonbecompletedalongtheregionalsystemwithinKlickitatCounty.Thecompletedimprovementsincludethereconstructionofseveralregionallysignificantcountyroads,safetyprojects,transportationenhancementsprojects,andthemaintenanceandpreservationprojects.

Inaddition,theBingenPointAccessprojectwasfundedthroughthe2015ConnectingWashingtonFundingPackage,andwillbeconstructedin2020.ThisprojectwillconstructaroundaboutonSR‐14atElmSt.whichwillprovideaccessundertheBNSFrailroadtrackstoaccessE.MarinaWaywithinthePort.

Page 46: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  38 

Regional Transportation Plan for Klickitat County 

Plannedfuturetransportationimprovementswillcontinuetomaintainandenhancetheexistingtransportationsystem.WithoutadditionalrevenuetherewillbelimitedopportunitiestoimprovetheKlickitatCountyregionaltransportationsystem.

Revenue Sources 

Federal Funding 

Thefederalgastaxandothertransportationfeesandtaxesarethemajorfederalrevenuesourcesfortransportationfunding.OnDecember4,2015,PresidentObamasignedintolawtheFixingAmerica’sSurfaceTransportation(FAST)Act.TheFASTActisthefirstfederallawinoveradecadetoprovidelong‐termfundingcertaintyforsurfacetransportationinfrastructureplanningandinvestment.TheFASTActauthorizes$305billionoverfiscalyears2016through2020forhighway,highwayandmotorvehiclesafety,publictransportation,motorcarriersafety,hazardousmaterialssafety,rail,andresearch,technology,andstatisticsprograms.Inaddition,theFASTActincludesanumberofprovisionsdesignedtoimprovefreightmovementinsupportofnationalgoals.

TheFASTActauthorizesasingleamounteachyearforalltheapportionedhighwayprogramscombined.ThatamountisapportionedamongtheStates,andtheneachState’sapportionmentisdividedamongtheindividualapportionedprograms.PartofWashingtonState’sapportionmentisthenallocatedtoregionssuchasKlickitatCounty,whoselectslocaltransportationprojectsforfunding.ThefollowingisabriefdescriptionofmajorFASTActfundingprograms:

Infrastructure For Rebuilding America (INFRA) 

TheFASTActestablishestheNationallySignificantFreightandHighwayProjectsprogramtoprovidenationallycompetitivegrantstonationallyandregionallysignificantfreightandhighwayprojects.TheActrequiresthataminimumof25%oftheINFRAgrantsgotoprojectsinruralareas.TheActalsostatesthatprojectsinanationalscenicareaareeligibleforINFRAgrant.TheUSDepartmentofTransportationselectsprojectsforfunding.

National Highway Performance Program (NHPP) 

TheFASTActcontinuestheNationalHighwayPerformanceProgram,whichwasestablishedunderMAP‐21.TheNHPPprovidessupporttoensurethatinvestmentsoffederal‐aidfundsinhighwayconstructionaredirectedtosupportprogresstowardtheachievementofperformancetargetsestablishedwithinastate’sassetmanagementplans.WSDOTselectsprojectsforfunding.

Page 47: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  39 

Regional Transportation Plan for Klickitat County 

Highway Safety Improvement Program (HSIP) 

TheFASTActcontinuestheHighwaySafetyImprovementProgram(HSIP)toachieveasignificantreductionintrafficfatalitiesandseriousinjuriesonallpublicroads,includingnon‐State‐ownedpublicroadsandroadsontriballands.TheHSIPrequiresadata‐driven,strategicapproachtoimprovinghighwaysafetyonallpublicroadsthatfocusesonperformances.WSDOTselectsprojectsforfunding.

Surface Transportation Block Grant (STBG) 

TheFASTActconvertsthelong‐standingSurfaceTransportationProgram(STP)intotheSurfaceTransportationBlockGrant(STBG)ProgramacknowledgingthatthisprogramhasthemostflexibleeligibilitiesamongalltheFederal‐aidHighwayprogramsandaligningtheprogram’snamewithhowFHWAhashistoricallyadministeredit.TheSTBGpromotesflexibilityinStateandlocaltransportationdecisionsandprovidesflexiblefundingtobestaddressStateandlocaltransportationneeds.

STBG‐Rural (STP‐Rural):FormulaallocationforprojectsoutsidetheUrbanAreaboundary.TheCountyselectsprojects.

STBG‐State (STP‐State):FormulaallocationtotheWashingtonStateDepartmentofTransportation,foruseonStatehighwayprojects.TheStateselectsprojects.

Transportation Alternatives (TA):TheFASTActreplacedtheTransportationAlternativesProgram(TAP)ProgramwithasetasideoftheSurfaceTransportationBlockGrant(STBG)Program.Theseset‐asidefundsincludeallprojectsandactivitiesthatwerepreviouslyeligibleunderTAP.RTCselectsprojectsfortheRTPOregion.

Community Development Block Grant (CDBG) 

CDBGfundsareadministeredbytheDepartmentofHousingandUrbanDevelopment(HUD).Fundscanbeusedforpublicfacilities,economicdevelopment,housing,andcomprehensiveprojectswhichbenefitlowandmoderateincomehouseholds.Projectsareselectedbythecounty.

Federal Lands Highways: 

TheFederalLandsHighwaysProgramprovidesfundsforprojectsthatimproveaccesswithinfederallands.

State Funding 

TheStateGasTaxistheprimaryStatesourceofhighwaymaintenanceandarterialconstructionfunds:

Page 48: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  40 

Regional Transportation Plan for Klickitat County 

Washington State Department of Transportation (WSDOT) 

TheWashingtonStateDepartmentofTransportationadministersstateandfederalfundedstatehighwayprojects.Statetransportationrevenuesaredividedintoseparateprograms.Thebudgetfortheseprogramsisdeterminedbythestatelegislature.WSDOTthenprioritizesprojectsanddetermineswhichprojectscanbeconstructedwithinthebudgetofeachprogram.

WSDOT Grant Programs 

WSDOTadministersmanytransportationrelatedgrantsthatareavailabletolocalagencies.However,mostoftheseprogramsaredependentonthelegislatureallocatingfundingandcanvaryfromyeartoyear.

Transportation Improvement Board (TIB) Programs 

TheWashingtonStateLegislaturecreatedtheTransportationImprovementBoard(TIB)tofosterstateinvestmentinqualitylocaltransportationprojects.TheTIBdistributesgrantfunding,whichcomesfromtherevenuegeneratedbythreecentsofthestatewidegastax,tocitiesandurbancountiesforfundingtransportationprojects.TheTIBidentifiesandfundsthehighestrankingtransportationprojectsbasedoncriteriaestablishedbytheBoardforeachprogram.

Small City Arterial Program (SCAP):Fundingprovidedtopreserveandimprovethearterialroadwaysystemforcitiesunder5,000population.Alocalmatchof5%orgreaterisrequired;ajurisdictionwithapopulationunder500needs0%localmatch.

Small City Pavement Preservation Program (SCPPP):Providesfundingforrehabilitationandmaintenanceofthesmallcityroadwaysystem.

Relight Washington:ProvidesfundingforcitiesconvertingtomoreenergyefficientLEDstreetlights.

Complete Streets:Thisprogramfundslocalgovernmentarterialretrofitstoimprovesafeaccessforallusers:pedestrians,bicyclists,motorists,publictransportationusers,andtruckdrivers.

Federal Match:Fundingprovidedtomeetthelocalmatchofsomefederallyfundedprojectsinsmallcities(populationunder5,000).TheTransportationImprovementBoardfundsaremadeavailablefollowingapprovaloffederalfunds.

 

Page 49: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  41 

Regional Transportation Plan for Klickitat County 

County Road Administration Board (CRAB) 

TheCountyRoadAdministrationBoard(CRAB)wascreatedbytheLegislaturein1965toprovidestatutoryoversightofWashington’sthirty‐ninecountyroaddepartments.CRABmanagestwograntprogramstoassistcountiesinmeetingtheirtransportationneeds.

Rural Arterial Program (RAP):Thisisastatefundforfinancingarterialroadimprovementsinruralareas.RAPfundscannotbeusedforright‐of‐way.Projectsareratedbyfivecriteria.ProjectsareselectedbytheCountyRoadAdministrationBoard.

County Arterial Preservation Program (CAPP):Fundingisprovidedforthepreservationofexistingpavedcountyarterials.FundingisprovidedtocountiesasdirectallocationbasedonpavedarteriallanemilesbytheCountyRoadAdministrationBoard.

Washington State Recreation and Conservation Office (RCO) 

TheRCOmanagesninegrantprograms,includingthelargestparkgrantprograminthestateofWashington.RTOcreatesandmaintainsopportunitiesforrecreation,protectsthebestofthestate’swildlands,andcontributestothestate’sefforttorecoversalmonfromthebrinkofextinction.

Community Economic Revitalization Board (CERB):   

CERBwasestablishedbythelegislaturetomakeloansand/orgrantsforpublicfacilities,includingroads,whichwillstimulateinvestmentandjobopportunities,reduceunemployment,andfostereconomicdevelopment.TheCommunityEconomicRevitalizationBoardselectsprojects.

Local Funding 

Localrevenuecomesfromavarietyofsourcessuchasgastax,propertytax,salestax,permits,fees,andprivatedevelopment.

Local Gas Tax Revenue 

Thisisthedistributionofthestategasolinetaxtothecitiesandcountiesbasedoneachjurisdiction’spopulation.

Road Improvement District (RID) 

RID’scanbeformedandfundedbypropertiesbenefitingfromanimprovement.Theyareusuallyformedattherequestofpropertyowners.Localgovernmentwillbuildtheprojectusingrevenuebondsfromtheroadimprovementdistrict.

Page 50: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  42 

Regional Transportation Plan for Klickitat County 

Frontage Improvement Agreements 

Developmentsareoftenrequiredtoconstructfrontageimprovementsasaconditionoftheirdevelopment.Incaseswherethedevelopmentabutsaproposedroadimprovementproject,itmaybebeneficialforthedevelopertopaylocalgovernmentfortheirshareofthefrontageimprovementandforlocalgovernmenttoconstructtheimprovementaspartoftheoverallcapitalproject.

Transit Revenues 

Revenuesourcesthathavebeendescribedpreviouslyaregenerallyintendedforroadwayimprovements.Thetransitsystemisgenerallyfundedbyfareboxproceeds,federalandstategrants,Medicaid,andotherlocalfunds.

Fare Box 

PatronsoftheMountAdamsTransportationServicepayafaretousetheservice.Thefarerevenuespayforaportionoftheoperatingcost.

Consolidated State and Federal Grants 

TheWashingtonStateDepartmentofTransportationisresponsiblefordistributingavarietyofstateandfederalgrantsforpublictransportationprograms.WSDOTcreatedaconsolidatedapplicationprocessthatisusedforbothstateandfederalpublictransportationgrants.Applicantsonlyneedtosubmittheirproposalsfortransitfundingeverytwoyears.

Medicaid 

EligiblemedicaltripsarefundedbyMedicaid.

Local Funds 

SeniorTransportationisfundedinpartbytheSouthwestAgencyonAgingandKlickitatCounty.Inaddition,UnitedWayprovidesadditionalpublictransitfunding.

Revenue Assumptions SHB1928requirestheRTPbe‘fiscallyconstrained’or“includeafinancialplandemonstratinghowtheregionaltransportationplancanbeimplemented,indicatingresourcesfrompublicandprivatesourcesthatarereasonablyexpectedtobemadeavailabletocarryouttheplan,andrecommendinganyinnovativefinancingtechniquestofinanceneededfacilities,services,andprograms.”Theremustbeabalancebetweenforecastrevenuesandcostsofidentifiedtransportationsystemimprovements.Withlimitedrevenuesavailableforfundingtransportationimprovements,themostcost‐effectivetransportationsolutionsmustbeidentified

Page 51: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  43 

Regional Transportation Plan for Klickitat County 

andselected.ThefollowingoutlinestheassumptionsandmethodologyusedfortheRTPrevenueforecast.

WSDOTprovidedhistoricaldatafortransportationrevenuesforyears2003through2014(12‐yearperiod).

Totaltransportationrevenuewasestimatedfora22‐yearperiodthrough2040,usingthefollowingapproach:1)calculatedannualKlickitatCountytransportationrevenueforyears2003‐2014;2)increasedannualrevenueby10%toreflectagrowingeconomy;3)multipliedtransportationrevenueby85%toreflecttherevenueavailablefortheregionaltransportationsystem;4)multipliedaverageannualregionaltransportationrevenueby22years;5)Add$22millionfromtheConnectingWashingtonstatewidetransportationfundingpackage;6)Added$22millionfromafuturestatewidetransportationpackage.

TheregionalrevenueestimateaccountsforthetrendthatKlickitatCountyreceivesa$1.42returnforeverydollarcontributedbyKlickitatCountyresidents.

Included$22millionfromthe2015ConnectingWashingtonTransportationPackage.

Assumedtheequivalentofanewstatewidetransportationfundingpackageof10centspergallon.WithKlickitatCountyreceivingapproximately$25milliondollarsoverthe22‐yearperiod.

TheRTPassumesrevenuesandcostsin2015dollars.

Table4‐1containsprojectedtransportationrevenuesfortheregionaltransportationsystem.Basedonthisestimate,theKlickitatCountyregionwouldhaveapproximately$238.9millionintransportationrevenueavailableoverthenext22years.

Table 4‐1: Projected Revenue 

Revenues  Annual Average 22 Year Forecast

Transportation Revenue $9,312,000 $204,854,000

2015 Connecting Washington $1,000,000 $22,000,000

New State Revenue Package $1,136,000 $25,000,000

TOTAL $11,448,000 $249,854,000

Cost Assumptions Thefollowingoutlinestheassumptionsandmethodologyusedtoestimatecosts:

WSDOTprovidedhistoricaldatafortransportationexpendituresforyears2005through2014(10‐yearperiod).

Page 52: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  44 

Regional Transportation Plan for Klickitat County 

Futuremaintenanceandpreservationcostswerebasedontrendsfromyears2005‐2014.Thefullmaintenanceandpreservationneedissignificantlyhigherthantheavailablecost.

Costfortransportationimprovementsarebasedonplanninglevelcostestimates.

Costforothermodessuchasrail,air,andriverareassumedtobemetoutsideoftheRTP.

Table4‐2containsprojectedtransportationcostfortheregionaltransportationsystem.Basedonthisestimate,theKlickitatCountyregionwouldhave$183.8millioninmaintenanceandpreservationcost,$66.1millioninimprovementcost,and$242.7millioninillustrativeneedscostoverthenext22years.

Table 4‐2: Projected Cost 

Cost Type  22‐Year Forecast 

Maintenance & Preservation  $183,800,000 

Improvement Projects  $66,100,000 

Illustrative Needs  $245,700,000 

Balancing Revenue and Cost The“fiscallyconstrained”testfocusesonassuringthatthereisareasonableexpectationthatrevenueswillbeavailabletoprovideforthetransportationimprovementsidentifiedintheRTP.Basedontherevenueassumptionsdescribedinthischapter,thereareinsufficientresourceswithintheregiontomeetthemaintenance,preservation,andimprovementneedsoftheregionaltransportationsystem.Ifadditionalresourcesarenotobtained,therewillbeinadequatefundsforallofthetransportationimprovementneeds.ThefundingandcostdifferenceisillustratedinFigure5‐1.TomeetthefinancialconstraintsoftheRTP,someimprovementneedshavebeenmovedtoanillustrativelist.

Page 53: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  45 

Regional Transportation Plan for Klickitat County 

Figure 4‐1: Transportation Revenue and Cost 

$183.8 $66.1 $245.7

$249.9

0 100 200 300 400 500

Costs

Revenues

Millions of Dollars

Maintenance and Preservation

Improvement Projects

Illustrative Needs

Transportation Revenue

Page 54: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 4: Financial Plan  46 

Regional Transportation Plan for Klickitat County 

Page 55: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 5: System Improvement and Strategy Plan  47 

Regional Transportation Plan for Klickitat County 

Chapter 5: System Improvement and Strategy Plan 

Overview Thischaptersummarizesthesolutionsandstrategiesneededtoprovideanadequatelevelofregionalmobilityoverthenext20years.Awiderangeofsolutionsandstrategiesareneededtomeettheregionaltraveldemand.Therearestrategiestoaddressthetraveldemandsideaswellastransportationsystemsupplysideandstrategiestoincreasetheefficiencyoftheexistingregionaltransportationsystemaswellasstrategiestoprovideforasafertransportationsystem.ThesolutionsandstrategiesoutlinedinthischapterwillprovideKlickitatCountyresidentswithawell‐maintained,structurallysound,saferegionaltransportationsystem.Indevelopingabalancedregionaltransportationsystem,itisnotonlycapacityandsafetydeficienciesthatmustbeaddressedbutalsopreservationandmaintenanceoftheexistingregionaltransportationsystem.Thischapterconcludeswithaprioritizedlistoftransportationsystemimprovements.

ThesolutionsandstrategiesfortheKlickitatCountyregionaltransportationsystemhavebeendividedintosubheadings.Maintenanceisthedailyoperationsthatkeepthetransportationsystemsafe,clean,andefficient.Preservationisaninvestmentthatprolongsthelifeofthetransportationsystem.Improvementsaremodificationsthatincreasethesafety,mobility,andeffectivenessofthetransportationsystem.Miscellaneousincludesspecificimprovementswhichmaybeincludedunderoneoftheothersubheadingsoristiedtoaspecificfundingsource,thusnocostestimateisprovidedforthesestrategies.Illustrativeincludesadditionaltransportationprojectsthathavebeenidentifiedandcurrentlylacksourcesoffunding.

Maintenance and Preservation Ofprimeimportanceintheplanningfortheregionaltransportationsystemistheneedtomaintainandpreservetheexistingtransportationsystem.

Maintenancewilladdresstheday‐to‐dayactivitiesneededtokeepthetransportationsystemingoodworkingorder;dailyoperationsthatkeepthesystemsafe,clean,reliableandefficient.Suchactivitiesincludefillingpotholes,repairing

Page 56: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 5: System Improvement and Strategy Plan  48 

Regional Transportation Plan for Klickitat County 

bridges,repairingdrainageditches,repairingguardrails,replacingdamagedsigns,plowingsnow,removingrocks,andefficientlyoperatingtrafficsignals.Preservationcanprolongthelifeoftheexistingtransportationsystemthroughsuchprojectsasrepavingroads,rehabilitatingbridges,androckfallprotection.

TheWashingtonStateDepartmentofTransportation(WSDOT)andlocaljurisdictionsmonitortheconditionandoperationoftheexistingsystemandprogramprojectstomaintainandpreservethesystem.TheRTPsupportstheroutine,regularly‐scheduled,andnecessarymaintenanceandpreservationworkidentifiedbylocalandstateagencies.TheRTPsupportsmaintenanceandpreservationbeinggivenhighpriorityintheprogrammingoftransportationfunds.Theestimated22yearpublicmaintenanceandpreservationexpenditurefortheregionaltransportationsystemis$183.8million.Thisdoesnotreflectthefullmaintenanceandpreservationneed.

Improvements Inaddition,theRegionalTransportationPlanrecommendstransportationimprovementsneededtoprovideanadequatelevelofsafetyandregional.Improvementsshouldberelatedtoanidentifieddeficiency,asidentifiedinChapter3(safety,capacity,economicdevelopment,non‐motorizedmode,andbridge).Improvementswouldincludeaddinglanes,removingadangerouscurves,intersectionimprovements,gradeseparation,addingtransportationenhancements,improvingsightdistance,addingaclimbinglane,realignmentofaroadway,andaddingalternativemodesoftransportation.Theestimated22yearimprovementcostis$66.1million.

Illustrative Projectsthataddressanidentifieddeficiency,butdonothaveidentifiedrevenue,arecontainedintheIllustrativeProjectslist.Theseprojectsareconsidered“financiallyunconstrained,”becauseestimatedresourceswouldnotcoverprojectcosts.

TheIllustrativeProjectshave“conceptualimprovements”indicatedandestimatedcostsidentified.Theseconceptualimprovementswillnotbecomecommittedprojectsuntilfurtherstudyiscompleted;includingmovingthroughtheregionaltransportationplanningprocessandpotentialrevenuehasbeenidentified.Inmanycases,theIllustrativeprojectswillrequirefurtherstudyoffeasiblealternatives.Theestimated22yearimprovementcostis$245.7million.

Page 57: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 5: System Improvement and Strategy Plan  49 

Regional Transportation Plan for Klickitat County 

Miscellaneous Strategies and Solutions TheRTPsupportsstrategiesforbridges,safety,economicdevelopment,non‐motorizedmodes,andtransitthatwillsupportthemobilityofpeopleandgoodswithinKlickitatCounty.

Bridge Deficiencies 

Maintenance,preservation,andreplacementprojectsrequiredonbridgesareidentifiedthroughtheBridgeManagementSystem(BMS)administeredbyWSDOT.

Theregionhasidentifiedthelong‐termneedtoreplacethefunctionallyobsoleteHoodRiverBridge.Theregionmustcontinuetoworkcollaborativelyonthislong‐termneed.

Safety Deficiencies 

Accidentsandtheirnumber,location,andtypearemonitoredbyWSDOTandlocaljurisdictions.Ifthereisdeemedtobeasafetydeficiency,thencountermeasuresareconsideredandcorrectiveactiontaken.

Economic Development and Freight Transportation Deficiencies 

Theprosperityofaregionisdependentontheprovisionoftransportationinfrastructuretosupporteconomicdevelopment.EconomicdevelopmentemergedasaprimeevaluationcriterionforprioritizingprojectsfortheRegionalTransportationPlan.

WSDOThasadoptedaStatewideFreightandGoodsTransportationSystem,whichcategorizeshighwaysandlocalroadsaccordingtothetonnageoffreighttheycarry.WashingtonStatealsocreatedtheFreightMobilityStrategicInvestmentBoard(FMSIB)withamissiontocreateacomprehensiveandcoordinatedstateprogramtofacilitatefreightmovementbetweenandamonglocal,national,andinternationalmarketsthatenhancestradeopportunities.

TheWashingtonStateLegislaturehasdefinedthepurposeofthestate’sfreightrailprogramandplanningactivitiesandestablishedacomprehensivefreightrailpolicy.ThispolicydirectsWSDOTtomaintainandimprovethestatefreightrailsystemthroughbetterfreightrailplanning,bettercooperationtopreserveraillines,andincreasedfinancialassistancefromthestate.

WashingtonandOregonhaveidentifiedthedeepeningofthelowerColumbiaRiverchannelto43feetasessentialforthemovementoffreight.Thisimprovementwillhelpkeeptheregioneconomicallycompetitiveinthefuture.

Page 58: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 5: System Improvement and Strategy Plan  50 

Regional Transportation Plan for Klickitat County 

Non‐Motorized Transportation Deficiencies 

Thedevelopmentofnon‐motorizedtransportationmodesisastrategythatwillmaximizethecapacityoftheexistingtransportationsysteminurbanareas.Reducedrelianceonautomobilesislargelydependentonthedevelopmentofadequatesidewalksandbikeways.Pedestrianandbicycleneedsaremostappropriatelyidentifiedatthelocallevel.

Transportationdemandmanagement(TDM)strategiestoreducevehicletripsontheregionaltransportationsystemcanincludeuseoftransit,carpooling,vanpooling,workingofflex‐hoursand/orcompressedworkweek,andworkingfromhomewithuseofcommunicationstechnology.

Transportationsystemmanagement(TSM)isalsoastrategytomaximizetheefficiencyoftheexistingtransportationsystem.TSMmeasuresincludeawiderangeofstrategies,mostofwhicharerelatedtotheuseofintelligenttransportationsystems.Theseincludeincidentresponseprograms,programstomonitortravelconditions(weather/congestion),variablemessagesignagetoalertmotoristoftravelconditions,andIntelligentVehicle/HighwaySystems.OtherTSMelementsincludeminorcapitalupgradessuchaschannelizationatintersections.

Transit Deficiencies 

Transitisimportantinmeetingthemobilityneedsofthetransitdependent;thoseunabletodriveautomobilesbecauseofage,infirmity,disability,orlowincome.Transitcanalsomeetthemobilityneedsforcommutetripstoandfromemploymentcenters.

Conclusion TheRTPprovidesforstrategiesandsolutionstomeetregionaltraveldemandandtodevelopabalancedregionaltransportationsystemoverthe22‐yearplanningperiod.ProjectsareidentifiedintheRTPandthenprogrammedinthelocalTransportationImprovementProgram.Table5‐1providesalistingofneededimprovementsfortheregionaltransportationsystem.Thistableincludesalistofprojectsforwhichregionalneedhasbeenidentifiedandforwhichthereisstrongregionalcommitment.Thelistfocusesonsafetyimprovementssincethesearetheprojectsthataremostreadilyneeded.Thelistalsoidentifiesawiderangeoftransportationsystemimprovementsthatwillcontributetothedevelopmentofabalancedregionaltransportationsystem.

Aprioritizationprocesshelpstheregiontomakemosteffectiveuseoflimitedtransportationfundingtomeettransportationsystemimprovementneeds.TheprojectslistedinTable5‐1wereprioritizedbasedontheregionalprioritizationprocess.Thefollowingkeyissueswereconsideredintheprioritizationprocess:1)Safety,2)EconomicDevelopment,3)Congestion,4)Connectivity,5)Support,and6)Cost/Funding.

Page 59: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 5: System Improvement and Strategy Plan  51 

Regional Transportation Plan for Klickitat County 

Table 5‐1: Klickitat County Transportation Improvement Projects 

Rank  Facility  Mile Post  Location  Existing Condition  Improvement Cost*

(millions) 

Unranked  All  N/A  Klickitat County Existing transportation system 

Preservation and Maintenance  Ongoing

Unranked  All  N/A  Klickitat County Existing transportation system 

Safety Improvements  Ongoing

Unranked  All  N/A  Klickitat County Existing transportation system 

Transportation Enhancements  Ongoing

Unranked  All  N/A  Klickitat County Existing transit system Maintain and improve public transit 

Ongoing

Fully Funded 

SR‐14  66‐67  Port of Klickitat: Bingen Point 

At‐grade crossing at Maple St. 

Grade‐separated RR crossing  $22.0

1  SR‐35  N/A  White Salmon to Hood River 

Hood River Bridge Bridge replacement:  design and right‐of‐way 

$10.0

2  N/A  N/A  Klickitat County Existing rural arterials Reconstruct to all‐weather roads $20.0

3  SR‐14  66.41  Oak (SR‐141) to Maple Intersections Roundabouts or Signalized  $0.5

4  SR‐14  65.5‐66.4  Downtown Bingen One lane each direction Radar Speed sign, pedestrian crossings, sidewalk 

0.4

5  SR‐97/ SR‐14 

2.3‐2.8  Maryhill Spur SR‐97/SR‐14 Offset intersections Study: Intersection improvement 

$1.0

6  SR‐97  25.4‐27.2  Brooks Park to Ski‐Lodge Rd 

One lane each direction Study Passing lane  $0.8

7  SR‐14  63.5‐77.7  SR‐14 within Klickitat Co. Existing rockfall locations Rockfall protection  $5.0

8  SR‐14  63.5‐64.8  SR‐141 Alt. to Dock Grade Narrow two‐lane road Study: Improve width and grade $1.0

9  SR‐14  75.8‐76.3  Lyle  Uncontrolled access Design sidewalk and curbs  $0.3

10  SR‐97  14.5‐21.3  Little Klickitat Rv ‐ Allen Cr One lane each direction Study: Passing lanes  $1.8

11  SR‐141  2.0‐6.9  White Salmon to Northwestern Lake Rd. Vic. 

Sharp curves Study: Realignment of curves  $2.0

12  SR‐197  0.8‐1.2  Dallesport Rd. to Dock Rd. Intersections Add left turn pocket, acceleration and deceleration lane 

$1.0

13  SR‐141  0.8‐1.2  Ash St. to SE 10th St. Uncontrolled access Design Sidewalk and curbs  $0.2

14  SR‐142  12.3‐13.6  Klickitat Av. to Durkee Rd. Uncontrolled Access Design Sidewalk and curbs  $0.1

Total      $66.1

*Theseareplanninglevelestimatesandadditionalworkwillbeneededtodetermineactualcost.

Table5‐2providesalistingofneededimprovementsalongtheregionaltransportationsystemthatdonothaveanidentifiedrevenuesource.Theseprojectswillbeaddedtothecommittedlistwhenadequatefinancialresourcesareidentified.

Table 5‐2: Illustrative Needs 

Rank  Facility  Mile Post  Location  Existing Condition  Improvement Cost*

(millions) 

1  SR‐35  N/A  White Salmon to Hood River Hood River Bridge Bridge replacement (WA Share) $105.0

2  SR‐97  2.3‐2.8  Maryhill Spur SR‐97/SR‐14 Offset intersections Intersection improvement  $68.0

3  SR‐97  25.4‐27.2  Brooks Park to Ski‐Lodge Rd One lane each direction Passing lane  $8.0

4  SR‐14  63.5‐64.8  SR‐141 Alt. to Dock Grade Narrow two‐lane road Improve width and grade  $12.0

5  SR‐14  75.8‐76.3  Lyle  Uncontrolled access Add sidewalk and curbs  $2.7

6  SR‐97  14.5‐21.3  Little Klickitat Rv ‐ Allen Cr One lane each direction Passing lanes  $18.0

7  SR‐141  2.0‐6.9  White Salmon to Northwestern Lake Rd. Vic. 

Sharp curves Realignment of curves  $26.0

8  SR‐14  0.8‐1.2  Ash St. to SE 10thSt. Uncontrolled access Sidewalk and curbs  $3.0

9  SR‐142 12.3‐13.6 Klickitat Av. to Durkee Rd. Uncontrolled Access Design Sidewalk and curbs $3.0

Total      $245.7

*Theseareplanninglevelestimatesandadditionalworkwillbeneededtodetermineactualcost.

Page 60: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 5: System Improvement and Strategy Plan  52 

Regional Transportation Plan for Klickitat County 

Page 61: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 6: Performance Monitoring  53 

Regional Transportation Plan for Klickitat County 

Chapter 6: Performance Monitoring 

Overview Thetransportationplanningprocessrequiresthatmonitoringofsystemperformancetakesplace.Monitoringoftheregionaltransportationsystem’sperformanceisanongoingactivity,whichataminimum,willoccuraspartofthereviewoftheRegionalTransportationPlan(RTP).TheRTPmustbereviewedatleasteverytwoyears.Severalelementsofsystemmonitoringactivitiesaredescribedbelow.

Safety Monitoringofcollisiondataandrockfallisanongoingactivityoftheregionaltransportationsystem.CollisiondatawillbecollectedandstudiedbasedonathreeyearcollisionrateaspartofeachRTPupdate.Thecollisionrateswillbeusedtoidentifytheperformanceofthetransportationsystembyidentifyingdeficientroadsegments.Highcollisionlocationswillbeusedasatoolforidentifyingimprovementstrategiestoalleviateasafetyproblem.

Inaddition,WSDOTwillmonitorrockfall.FutureupdatesoftheRTPwillcontainthemostrecentrockfallinformation.Rockfalllocationswillbeusedasatoolforprioritizingrockfallimprovements.

Capacity Analysis Trafficvolumeswillbeusedasatoolformonitoringtrafficcongestionandforidentifyingimprovementstrategiestoalleviatethecongestion.TheHighwayCapacitySoftwarewillbeusedtoanalyzethelevelofservicealongtheregionaltransportationnetwork.Deficientsegmentswillbeanalyzedtoidentifyimprovementstrategiestoalleviatecongestion.

Preservation and Maintenance Local,regional,andstatetoolsarebeingusedtomonitorpreservationandmaintenanceneeds.WashingtonStatehasdevelopedaBridgeManagementSystem

Page 62: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 6: Performance Monitoring  54 

Regional Transportation Plan for Klickitat County 

andPavementManagementSystemtoidentifydeficientconditionsalongroadwaysandbridges.Thesetoolsalongwithothertoolsareongoingactivitieswhichmonitorpreservationandmaintenanceneedsoftheregionaltransportationsystem.

Special Studies Localandstatestudiesandplansareoccasionallyundertakenwhichmonitortheperformanceofthetransportationsystem.Asthesespecialstudiesorplansarecompleted,theassociatedinformationwillbeincludedinthenextupdateoftheRegionalTransportationPlan.

Page 63: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 7: Plan Development and Implementation  55 

Regional Transportation Plan for Klickitat County 

Chapter 7: Plan Development and Implementation 

Public Involvement in Regional Transportation Planning Process SouthwestWashingtonRegionalTransportationCouncil(RTC)hasanadoptedPublicParticipationPlanoutliningthepublicinvolvementeffortsinthedevelopmentofregionaltransportationplansandprograms.CopiesofthePublicParticipationPlanareavailablefromRTC’sWebsiteoroffice.AllRTCBoardmeetingsandtheKlickitatCountyTransportationPolicyCommitteemeetingsareopentothepublic.Publicinvolvementeffortsbuildfromthosecarriedoutatthelocallevelindevelopmentoflocalplansandprogrammingoftransportationprojects.

ApublicmeetingisheldtoadopttheKlickitatCountyRegionalTransportationPlan.AmendmentstotheRTParepresentedtoboththeKlickitatCountyTransportationPolicyCommitteeandtheRTCBoardofDirectorsfortheirconsiderationandadoption.Transportationissues,studies,plans,andprogramsareoutlinedandreportedonRTC’swebsiteathttp://www.rtc.wa.gov.

RTP Implementation Implementationofregionaltransportationgoals,policies,andactionsestablishedbytheKlickitatCountyRegionalTransportationPlan(RTP)arecarriedforwardthroughalocalandregionaldecision‐makingprocess.ThroughthelocaldevelopmentofaTransportationImprovementProgram(TIP),transportationneedsidentifiedintheRTPareprogrammedforreceiptoffunds.

RTP Update Process TheRTPistobereviewedatleasteverytwoyearsandhasbeenupdatedoramendedmanytimesovertheyears.Shouldchangingpolicies,financialconditions,orgrowthpatternswarrant,anRTPupdateoramendmentwilloccur.

Page 64: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Chapter 7: Plan Development and Implementation  56 

Regional Transportation Plan for Klickitat County 

ResultsandrecommendationsfromtransportationstudiesandimprovementswillbeincorporatedintofutureRTPupdates.ThenextreviewtotheRTPisanticipatedin2020,withthenextupdateby2022.

Page 65: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Glossary  57 

Regional Transportation Plan for Klickitat County 

Glossary 

Abbreviation  Description

B/C  Benefit Cost Ratio

BEA  U.S. Bureau of Economic Analysis

BNSF  Burlington Northern Santa Fe Railroad

BMS  Bridge Management System 

CAPP  County Arterial Preservation Program (CRAB Grant Program) 

CDBG  Community Development Block Grant (HUD Grant Program) 

CERB  Community Economic Revitalization Board

CRAB  County Road Administration Board

FAST  2015 Fixing America's Surface Transportation Act

FMSIB  Freight Mobility Strategic Investment Board

GMA  Growth Management Act  

HSP  State Highway System Plan

HSIP  Highway Safety Improvement Program (Federal Funding Program) 

HSS  Highways of State‐wide Significance

HUD  Department of Housing and Urban Development

INFRA  Infrastructure For Rebuilding America

LOS  Level of Service 

MCEDD  Mid‐Columbia Economic Development District

MPO  Metropolitan Planning Organization 

NHS  National Highway System (Federal Funding Program)

NHPP  National Highway Performance Program (Federal Funding Program) 

OFM  Washington State’s Office of Financial Management

Scenic Area  Columbia River Gorge National Scenic Area

NHPP  National Highway Performance Program (Federal Funding Program) 

NHS  National Highway System 

PTBA  Public Transportation Benefit Area

RAP  Rural Arterial Program (CRAB Funding Program)

RID  Road Improvement District

RTC  Southwest Washington Regional Transportation Council  

RTP  Regional Transportation Plan

RCO  Washington State Recreation and Conservation Office 

RTPO  Regional Transportation Planning Organization 

SCAP  Small City Arterial Program (TIB Grant Program)

SCPPP  Small City Pavement Preservation Program (TIB Grant Program) 

SHB  Senate House Bill

SR‐  State Route

STBG  Surface Transportation Block Grant (Federal Funding Program) 

STP  Surface Transportation Program 

TA  Transportation Alternatives Program

TDM  Transportation Demand Management

Page 66: Transportation for Klickitat County, Washington · 2018. 11. 7. · Klickitat County area developed through a coordinated process between local jurisdictions in order to develop regional

Glossary  58 

Regional Transportation Plan for Klickitat County 

Abbreviation  Description

TIB  Transportation Improvement Board

TIP  Transportation Improvement Program 

TSM  Transportation System Management

WSDOT  Washington State Department of Transportation 

WTP  Washington Transportation Plan