Transportation Capital Works Program and Capital Delivery Presentation to The Ontario Road Builders’ Association October 20, 2011 Peter Pilateris, M.A.Sc., P.Eng. Senior Engineer, Design and Construction Technical Services Division

Transcript of Transportation Capital Works Program and Capital Delivery Presentation to The Ontario Road...

Transportation Capital Works Programand Capital Delivery

Presentation to The Ontario Road Builders’ Association

October 20, 2011

Peter Pilateris, M.A.Sc., P.Eng.Senior Engineer, Design and Construction

Technical Services Division

Inventory of Assets

• 300 lane-km Expressways $1.0 B• 5,600 km Arterial and Local Roads $6.5 B• 970 Bridges & Major Culverts $2.2 B• 7,945 km Sidewalks $0.9 B• 2,159 Traffic Signals $0.6 B • 42 km Off-street Bike Trails $0.6 B

TOTAL $11.8B

Transportation Services Capital Budget

Year 2007 2008 2009 2010 2011 2012

Budget $170M $177M$174M $174M$230M $173M

Infrastructure Stimulus Funding (ISF)

• A $4 billion program established through Canada’s Economic Action Plan.

• Federal program to contribute 1/3 funding to construction-ready infrastructure projects.

• Included $56M for Toronto’s road rehabilitation projects.

• Projects need to be substantially complete by October 31, 2011.

State-of-good-repair Budget

ProgramMajor Roads

Local Roads

Bridges LanesSide-walks

FacilitiesTOTALSOGR

2009

2010

2011

2012proposed

$39.4M $32.7M $38.8M $2.0M $10.7M $1.0M $124.6M

$79.8M $55.3M $37.5M $4.6M $18.9M $3.2M $199.3M

$42.7M $37.6M $31.0M $1.5M $12.5M $4.2M $129.4M

$46.7M $41.9M $29.5M $1.8M $8.6M $1.0M $129.6M

2012 Major Road Projects

• Sherbourne St (Front St E to Gerrard St)

• Finch Ave W (Keele St to Dufferin St)

• Finch Ave E (Bayview Ave to Alamosa Dr)

• Wilson Ave (Dufferin St to Keele St) & George Appleton (401 to Wilson Ave)

• Danforth Rd (Midland Ave to McCowan Rd)

• Burnamthorpe Rd (Martin Grove to The East Mall)

2012 Major Road Projects (Con’t)

• Evans Ave (Islington Ave to CPR)

• Bloor St (Keele St to Clendenan Ave) & Keele St (Bloor St to Glanlake Ave)

• Keele St ( Westacres Dr to Falstaff Ave)

• Parklawn Rd (Lake Shore Blvd W to CNR)

• Sheppard Ave (Arrow Rd to Weston Rd)

Aging Infrastructure

Pavement Age

0

100

200

300

400

500

600

1905 1910 1915 1920 1925 1930 1935 1940 1945 1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010

Year of Construction

Len

gth

(K

m)

Locals Expressways Majors

1960

1980

2000

2010

• The backlog of repairs is currently estimated to be $300M.

• This represents approximately 2.5% of the value of our assets.

• The backlog is expected to increase to $430M by 2015.

Backlog of Repairs

Where do we go from here?

• Key Factors Affecting the Capital Program

– End of ISF

– Eglinton Crosstown Light Rail Project

– Utility Coordination

– Auditor General & Contract Requirements

– Infrastructure Enhancements

Where do we go from here?

• Improving Capital Delivery & Performance

– Major Capital Infrastructure Coordination & Portfolio Management and Support Groups

– 5 year coordinated Capital Plan & Program

– Contract Consistency

– Improved Contract Management & Professional Development (PMPs)

– Delivery Options

Thank you!