Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

download Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

of 36

Transcript of Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    1/36

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    2/36

    Workshop on Metropolitan Governance andPlanning:

    Experience of Mumbai and Rio de Janeiro

    Presentation on

    Comprehensive Transportation Plan for MMR andResource Generation under MumbaiTransformation

    29thJune 2012

    LEA International Ltd., CanadaLEA Associates South Asia Pvt. Ltd.

    MMRDA

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    3/36

    Structure of Presentation

    Major Challenges in InfrastructureDevelopment

    Current Travel Scenario in MMR

    CTS for MMR Study: Proposed TransportInfrastructure

    Technical Assistance Project: Infrastructure

    Investment Needs and Potential Sources ofFunding

    Steps taken so far

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    4/36

    Map of India

    Map of MMR

    District Map ofMaharashtra

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    5/36

    Mumbai

    Thane

    Vasai-Virar

    Bhiwandi

    Kalyan

    Khopoli

    Pen

    Alibag

    Mira-Bhayander

    UlhasnagarAmbernath

    Badlapur

    Panvel

    Uran

    Matheran

    Karjat

    Navi Mumbai

    Thane Dist.

    Raigad Dist.

    Sub-urbanDist.

    Area 4355 sq.km.

    Population About 22.2 million

    (2011)

    Districts in MMR 1. Mumbai2. Suburban3. Thane4. Raigad

    Corporations in MMR 1. Greater Mumbai2. Thane3. Navi Mumbai4. Ulhas Nagar5. Kalyan-Dombivali6. Mira Bhayandar7. Bhiwandi- Nizampur8. Vasai-Virar

    Municipal Councils inMMR

    1. Ambernath2. Kulgaon-Badlapur3. Alibaug

    4. Pen5. Uran6. Matheran Hill Station7. Panvel8. Karjat9. Khopoli

    Villages 1000

    Urbanisation 94% Urban Population6% Rural Population

    Mumbai Metropolitan Region (MMR)

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    6/36

    Major Challenges in Infrastructure Development

    Physical Challenges

    Difficult Landform and Geography Scarcity of Developable Land Inadequate transportation system capacity and unacceptable

    levels of safety

    Social Challenges

    Re-housing Slums

    Economic Challenges

    Increasing Job Opportunities and Incomes Global Competitiveness

    Institutional Challenges

    Multiplicity of agencies and lack of coordination Lack of Institutional Framework/setup Inadequate Technical Resources to implement large scale

    projectsFinancial Challenges

    Huge Gap in Demand and Supply of Infrastructure Resource Mobilization and Fiscal Management

    Others

    Encroachments & Resettlement

    Environmental Degradation and Protection Traffic congestion resulting from private vehicle growth

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    7/36

    Current Travel Scenario in MMR

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    8/36

    Vasai

    Navgarh-Manikpur

    Nalasopara

    Virar

    Greater Mumbai

    Mira Bhayandar Bhiw andi

    Kalyan

    Am be rn at h

    Ulhasnagar

    A li ba g

    Uran

    Khopol i

    Bhiw andi

    Thane

    Kalyan

    Am be rn at h

    Ulhasnagar

    Navi Mumbai

    Dombivl i

    Pen

    Nhave

    Sheva

    Uran

    PanvelMatheran

    Kar jat

    Khopol i

    GreaterMumbai

    NavgarhManikpur

    Nalasopara

    Virar

    Mira Bhayandar

    Vasai

    Badlapur

    Covers entire Mumbai,Parts of Thane and RaigadDistricts

    4,355 sq.kms area

    20 Urban Local Bodies (7Municipal Corporationsand 13 MunicipalCouncils)

    MMR Study Area

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    9/36

    MMR and its Sub-regions

    Total population = 20.8 mil

    Total Employment = 7.6 mil

    Pop (m) Emp (m)

    Greater Mumbai 12.86 4.7

    Region 7.94 2.9

    Base Year (2005)

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    10/36

    Surveys/ Studies ConductedNo. Primary Survey Extent

    1 Home Interview Survey (HIS) 66,000 Households

    2 Classified Volume count and OD Survey at Outer CordonLocations

    24 Hr., 9 Locations

    3 Classified Volume count and OD Survey at Sub-regionalcordons

    24 Hr., 20 Locations

    4 Classified Volume count at Inner Cordon Locations 16/24 Hr., 33 Locations (OD Survey at 3 Loc.)

    5 Screen Line Points 16 Hr., 3 Locations

    6 Mid-Block Locations 16 Hr., 11 Locations

    7 Level Crossing Locations 16 Hr., 5 Locations

    8 Sub-urban Rail Passenger Surveys 6.17%9 Sub-urban Rail Passenger Surveys, Alighting Survey: Stations 16%

    10 Operational Characteristics of Bus and Rail TransportNetworks

    5700 Bus Routes and 1767 Train Services

    11 IPT (Auto and Taxi) Surveys 50 Locations

    12 Bus Terminal Surveys 13 Bus Terminals

    13 Airport Terminal Surveys 2000 air passengers14 Goods Terminal Surveys 20 Goods Terminals

    15 Speed-Flow Studies 16 Carriageway Types

    16 Journey Speed and Delay Studies 550 Kms

    17 Network Inventory 2,300 kms.

    18 Pedestrian Surveys 50 Locations

    19 Parking Surveys 50 Stretches20 Workplace Based Surveys 4000 respondents

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    11/36

    Train Bus Taxi

    RickshawTwo WheelerCar

    11

    Where and How People Travel in Mumbai -2005(Morning Peak Period: 6:00 to 11: AM)

    http://upload.wikimedia.org/wikipedia/commons/2/29/India.Mumbai.02.jpg
  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    12/36

    Per Capita Trip Rate With walk: 1.65

    Without walk: 0.65

    Trips per day (2005)

    Total Region

    ModeTrips

    (ml)

    Mode Split with

    Walk

    Mode Split without

    Walk

    Walk 14.85 52.4% -

    Train 6.98 24.6% 51.8%

    Bus 3.55 12.5% 26.3%

    Auto 1.05 3.7% 7.8%

    Taxi 0.23 0.8% 1.7%

    Two Wheeler 1.05 3.7% 7.8%

    Car 0.63 2.2% 4.6%

    Total (with Walk) 28.33 100.0% 100.0%

    Total (withoutWalk) 13.48

    78%

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    13/36

    Andheri

    Bandra

    Thane

    Kurla

    ChurchgateCST Mumbai

    Vashi

    Panvel

    Borivali

    Dadar

    Kalyan

    Dombivali

    Titwala

    Ulhasnagar

    Mumbai Central

    Morning Peak Period (6:00 to 11:00 AM)Crowded Sections or Links(in Lakhs)

    Vile Parle

    Sion

    Mira Rd.

    Bhyander5517(12 Car Rake)

    3725

    (9 Car Rake)

    Ghatkopar

    TN

    Chembur

    4852(9 Car Rake)

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    14/36

    Average Standees Per Coach 12 pass/sq.m.

    US Federal Transit Administration Report(1996)

    Totally Intolerable 5 pass/sq.m.

    Unacceptable 8 pass/sq.m.

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    15/36

    Per Capita Trip Rate With walk: 1.65

    Without walk: 0.65

    Trips per day (2005)

    Total Region

    ModeTrips

    (ml)

    Mode Split with

    Walk

    Mode Split without

    WalkWalk 14.85 52.4% -

    Train 6.98 24.6% 51.8%

    Bus 3.55 12.5% 26.3%

    Auto 1.05 3.7% 7.8%

    Taxi 0.23 0.8% 1.7%

    Two Wheeler 1.05 3.7% 7.8%

    Car 0.63 2.2% 4.6%

    Total (with Walk) 28.33 100.0% 100.0%

    Total (withoutWalk) 13.48

    78%

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    16/36

    Mode Split: Major Cities across the World

    3

    7

    10

    24

    28

    37

    49

    68

    72

    78

    97

    93

    90

    76

    72

    63

    51

    32

    28

    22

    0 10 20 30 40 50 60 70 80 90 100

    Los Angles

    Washing Ton

    New York

    London

    Paris

    Singapore

    Tokyo

    Shanghai

    Hong Kong

    Mumbai

    Public Transport Private Vehicle 16

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    17/36

    Vision - TranSforM MMR

    Transforming MMR into a world class metropoliswith a vibrant economy and globally comparablequality of life for all its citizens.

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    18/36

    CTS for MMR Study:

    Proposed TransportInfrastructure

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    19/36

    Population, Employment and Vehicular Growth

    Population

    20.0 mil

    34.0 mil

    Employment

    7.6 mil

    15.3 mil

    VehicularPopulation

    2.0 mil

    9.0 mil

    9.9

    13.4

    18.5

    22.4

    27.0

    34.0

    0

    5

    10

    15

    20

    25

    30

    35

    1981 1991 2001 2011 2021 2031

    7.6 mil 15.3 mil

    0

    1,000,000

    2,000,000

    3,000,000

    4,000,000

    5,000,000

    6,000,000

    7,000,000

    8,000,000

    1996

    1998

    2000

    2002

    2004

    2006

    2008

    2010

    2012

    2014

    2016

    2018

    2020

    2022

    2024

    2026

    2028

    2030

    2032

    2005

    2031

    Population

    Employment Vehicular Growth

    20 Lakhs90 Lakhs

    4.5 times

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    20/36

    Long Term (2031)

    Metro and Sub-urban Network

    YearCumulative Length (km)

    Metro Sub-urban

    2016 208 237

    2021 318 237

    2031 450 248

    Sub-urban Network: 2005

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    21/36

    Long Term (2031)Highway Network

    Year Cumulative Length (km)

    2016 982

    2021 1,229

    2031 1,739

    Highway Network: 2005 (2,600 kms)

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    22/36

    17 Inter-State/ Inter-City Bus

    Terminals

    6 Inter-City rail Terminals

    5 Major Truck Terminals and 10

    Mini Truck Terminals

    13 Passenger Water Transport

    (PWT) Terminals

    Proposed Terminals

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    23/36

    Candidate RoadsforBus Rapid Transit/ EBL/ Mono Rail

    On Proposed New Roads

    Panvel

    Vashi

    Uran

    Dronagiri

    Ulwe

    On Existing Roads

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    24/36

    Multi-Modal Corridors

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    25/36

    Right of Way Requiremen

    100

    100

    100

    80

    80

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    80

    100

    100100

    The Right of Way (ROW) shown

    for each segment of the

    proposed Regional Road

    Network is the preferred ROW

    width.

    However , an absolute minimum

    width of 80 m is required.

    Finalisation of the ROWsrequire, detailed feasibility

    studies specific to each corridor.

    MetropolitanRegional Roads

    ROW, 100 m100

    LEGEND

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    26/36

    Summary of Preliminary Cost EstimatesProposed Transport Networks

    Horizon Years 2031, 2021 and 2016

    Component

    2008- 2031 2008- 2021 2008- 2016

    Lengthkm

    CostRs Crores

    Lengthkm

    CostRs Crores

    Lengthkm

    CostRs Crores

    Metro System 450 1,10,095 316 82,707 204 59,623

    Sub-Urban Railway System 241 30,978 231 28,670 231 27,920

    Highway System 1660 57,412 1114 44,844 836 31,173

    Highway Corridors withEBL

    77 1,670 111 2,000 147 11,079

    Bus System 4,280 2,150 1,104

    Passenger Water Transport 480 480 480

    Truck Terminals, Inter-Busand Rail Terminals

    3,040 2,038 1,126

    Total 2,429 2,07,956 1,772 1,62,890 1,418 1,32,504US $ 50.72 Billion US $ 39.73 Billion US $ 32.32 Billion

    Note:

    1. The cost estimates are @ 2005-06 prices

    2. The metro system cost includes the cost of rolling stock

    3. The sub-urban railway system cost includes the cost of rolling stock for new lines, capacity enhancement of the to the

    existing sub-urban railway system

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    27/36

    Funding Sources

    Sl.

    No. Transport System

    EstimatedTotal Cost

    (Rs. Crore)@ 2005-06Prices

    Inter

    GovernmentalTransfer (%)

    Development

    Charges(%)

    Borrowing

    (%)

    Private

    Investment (%)

    I Metro System 1,10,095 15 25 0 60

    II Sub-Urban Railway System 30,978 30 30 40 0

    III Highway System 57,412 25 25 30 20

    IVHighway Corridors with

    Exclusive Bus Lanes (EBL) 1,670 25 25 30 20

    V Bus System 4,280 25 25 30 20

    VI Passenger Water Transport 480 12 12 16 60

    VII Terminals 3,040 21 21 28 30

    Total Investment, Average % FundingSources

    2,07,956 20 28 12 40

    Potential Need forRe-allocation from Privateto Development ChargesParticularly for Metro

    Creation of Dedicated Fund (MMR Transport InfrastructureFund) for implementation of Proposed Transport Infrastructure in MMR

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    28/36

    Infrastructure Investment Needs and

    Potential Sources of Funding

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    29/36

    Infrastructure Investment Need in MMR

    85% of the Infrastructure Investment Need is Transport Infrastructure

    Sl. No. SectorInvestment

    Needs by 2021

    (INR million)

    InvestmentNeeds by 2031

    (INR million)

    1 Regional Water Resource Development 168,640 193,430

    2 Transit Development 1,641,740 1,874,860

    3 Road development + Terminals 610,500 809,510

    4 Regional Drainage 23,920 27,4405 Land, Real estate & Housing 146,160 167,650

    6 Thakurli Power Plant 25,000 25,000

    7 Regional Landfill Sites 30,000 34,410

    8 Matheran Funicular Railway 2,000 2,000

    9 Nirmal MMR Abhiyan 2,400 2,400

    Total Metropolitan Infrastructure 2,650,360 3,136,690

    @ 2009-10 Prices

    US$ 53 billion US$ 63 billion

    I f t t F di

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    30/36

    Funding Source Percent Share INR million

    Inter-Government Transfer 4.6% 144,288

    MMRDA Resources 18.5% 580,290Borrowings 43.2% 1,355,054

    Private Investment + SPV partner

    other than Government 33.7% 1,057,068

    Total 100% 3,136,700

    Infrastructure Funding

    Sl.

    No.

    Project Net Revenuepotential

    (INR million)

    1 Sale of Lands: Bandra Kurla Complex 389,0002 Sale of lands: Wadala Truck Terminal 174,780

    3 MMR Growth Areas & Growth Centres 25,000

    Total 588,780

    MMRDA Sources:

    Potential of Development Charges for the period (2010-2031): 1,160,000 to2,100,000 million

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    31/36

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    32/36

    Scenario

    2010-2021 2022-2031 2010-2031

    INR million

    US $

    billion INR million US $ billion INR million

    US $

    million

    Base: DC on New Growth &Redevelopment (MMRDA: 7.0% and

    ULB: 3.0%)

    1,240,000 27.6 860,000 19.0 2,100,000 46.6

    Scenario AAverage building values are

    lower and unit sizes are smaller than

    Base case):

    DC on New Growth & Redevelopment

    (MMRDA: 7.0% and ULB: 3.0%)

    990,000 22.1 710,000 15.9 1,710,000 37.9

    Scenario B (Average building value and

    unit size are same as in Scenario A):DC

    on New Growth & Redevelopment: 5%

    Residential (MMRDA: 3.5% & ULB:

    1.5%), 10% Non-Residential (7%MMRDA

    & 3% ULBs)

    650,000 14.3 510,000 11.3 1,160,000 25.6

    [1]Assum pt ions for Base Scenar io:Building Value: Rs. 2,000 to 40,000/sq.ft.Average Unit Size of the Building: 600 to 1000 sq.ft.Average Office, Industrial and Other Building Costs: Rs. 30,000, Rs. 8,000 and Rs. 13,000/sq.ft.

    [2]Assumptions forScenar io A&B :Building Value: Rs. 1,600 to 32,000/sq.ft

    Average Unit Size of the Building : 540 to 900 sq.ftAverage Office, Industrial and Other Building Costs: Rs. 24,000, Rs. 6,400 and Rs. 10,400/sq.ft

    Potential of Development Charges

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    33/36

    Source of Revenue Revenue Generated by Time Period (in INR Crores)20102021 2022 - 2031 20102031

    Cess (5%) on Property 2,300 2,800 5,100

    Cess on Fuel 2 %

    3 %

    2,500

    3,800

    4,000

    6,400

    6,500

    10,200

    Annual Renewal of Vehicle

    license: Option (i)*

    Option (ii)**

    6,800

    10,400

    9,700

    14,700

    16,500

    25,100

    One-Time cess on New

    Vehicle Purchases (2 %

    Cess)

    1,000 1,400 2,400

    Employment Tax 9,300 to 18,300 16,900 to 30,400 26,200 to 48,700

    Sale of Advertising Rights Tbd

    Depends on items

    included

    Tbd

    Depends on

    items included

    Tbd

    Total 21,900 to 35,800 34,800 to 55,700 56,700 to 91,500

    *Option (i): Annual renewal fee: two wheelers INR 500, cars INR 2,000, trucks INR 3,000

    **Option (ii) Annual renewal fee: two wheeler INR 1000, cars INR 3,000, trucks INR 3,000

    Revenue Sources for O&M Shortfalls

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    34/36

    Steps taken so far. Implementation of Two metro corridors and one monorail corridor is under

    progress;

    MMRDA initiated the DPR for Phase II and Phase III metro corridors ofMumbai Metro Master Plan:

    MMRDA completed the DPR study for Metro corridor from Siddhi Vinayak-

    Sewri-Kharkopar-Dhutum-Dushmi (about 50 kms);

    MMRDA initiated the process for Techno-Economic Feasibility Study ofMulti-Modal Corridor from Virar-Alibag Study (140 kms) which covers someof the higher order highway corridors as well as some metro corridors asproposed in the CTS study;

    Process initiated for Common Ticketing and Fare Integration, Dialogue withvarious operators/ ULBs is in progress;

    UMMTA established under Chairmanship of Chief Secretary. Legal

    Framework for UMMTA is in progress;

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    35/36

    Steps taken so far.

    All the ULBs requested to include the proposed arterial roads and higherorder highway corridors, metro corridors, sub-urban rail corridors,

    monorail corridors in the Development Plans for the reservation of RoW;

    ULBs have created Traffic & Transportation units;

    The study on Monorail Master Plan for MMR is completed;

    Initiated Technical Assistance project for implementation of CTS andBusiness Plan proposals. The focus of this TA shall be on preparatoryactions that are needed on priority related to the projects which have to beimplemented by 2016/2021 with specific attention to sustainability;

    MMRDA has submitted proposals on Development Charges to GoM;

    Project Preparatory works are in progress for implementation of MumbaiTrans Harbour Link (MTHL) and Colaba-Bandra-SEEPZ metro corridor.

  • 8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation

    36/36

    Thank you