Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
-
Upload
dln-aditya -
Category
Documents
-
view
214 -
download
0
Transcript of Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
1/36
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
2/36
Workshop on Metropolitan Governance andPlanning:
Experience of Mumbai and Rio de Janeiro
Presentation on
Comprehensive Transportation Plan for MMR andResource Generation under MumbaiTransformation
29thJune 2012
LEA International Ltd., CanadaLEA Associates South Asia Pvt. Ltd.
MMRDA
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
3/36
Structure of Presentation
Major Challenges in InfrastructureDevelopment
Current Travel Scenario in MMR
CTS for MMR Study: Proposed TransportInfrastructure
Technical Assistance Project: Infrastructure
Investment Needs and Potential Sources ofFunding
Steps taken so far
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
4/36
Map of India
Map of MMR
District Map ofMaharashtra
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
5/36
Mumbai
Thane
Vasai-Virar
Bhiwandi
Kalyan
Khopoli
Pen
Alibag
Mira-Bhayander
UlhasnagarAmbernath
Badlapur
Panvel
Uran
Matheran
Karjat
Navi Mumbai
Thane Dist.
Raigad Dist.
Sub-urbanDist.
Area 4355 sq.km.
Population About 22.2 million
(2011)
Districts in MMR 1. Mumbai2. Suburban3. Thane4. Raigad
Corporations in MMR 1. Greater Mumbai2. Thane3. Navi Mumbai4. Ulhas Nagar5. Kalyan-Dombivali6. Mira Bhayandar7. Bhiwandi- Nizampur8. Vasai-Virar
Municipal Councils inMMR
1. Ambernath2. Kulgaon-Badlapur3. Alibaug
4. Pen5. Uran6. Matheran Hill Station7. Panvel8. Karjat9. Khopoli
Villages 1000
Urbanisation 94% Urban Population6% Rural Population
Mumbai Metropolitan Region (MMR)
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
6/36
Major Challenges in Infrastructure Development
Physical Challenges
Difficult Landform and Geography Scarcity of Developable Land Inadequate transportation system capacity and unacceptable
levels of safety
Social Challenges
Re-housing Slums
Economic Challenges
Increasing Job Opportunities and Incomes Global Competitiveness
Institutional Challenges
Multiplicity of agencies and lack of coordination Lack of Institutional Framework/setup Inadequate Technical Resources to implement large scale
projectsFinancial Challenges
Huge Gap in Demand and Supply of Infrastructure Resource Mobilization and Fiscal Management
Others
Encroachments & Resettlement
Environmental Degradation and Protection Traffic congestion resulting from private vehicle growth
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
7/36
Current Travel Scenario in MMR
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
8/36
Vasai
Navgarh-Manikpur
Nalasopara
Virar
Greater Mumbai
Mira Bhayandar Bhiw andi
Kalyan
Am be rn at h
Ulhasnagar
A li ba g
Uran
Khopol i
Bhiw andi
Thane
Kalyan
Am be rn at h
Ulhasnagar
Navi Mumbai
Dombivl i
Pen
Nhave
Sheva
Uran
PanvelMatheran
Kar jat
Khopol i
GreaterMumbai
NavgarhManikpur
Nalasopara
Virar
Mira Bhayandar
Vasai
Badlapur
Covers entire Mumbai,Parts of Thane and RaigadDistricts
4,355 sq.kms area
20 Urban Local Bodies (7Municipal Corporationsand 13 MunicipalCouncils)
MMR Study Area
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
9/36
MMR and its Sub-regions
Total population = 20.8 mil
Total Employment = 7.6 mil
Pop (m) Emp (m)
Greater Mumbai 12.86 4.7
Region 7.94 2.9
Base Year (2005)
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
10/36
Surveys/ Studies ConductedNo. Primary Survey Extent
1 Home Interview Survey (HIS) 66,000 Households
2 Classified Volume count and OD Survey at Outer CordonLocations
24 Hr., 9 Locations
3 Classified Volume count and OD Survey at Sub-regionalcordons
24 Hr., 20 Locations
4 Classified Volume count at Inner Cordon Locations 16/24 Hr., 33 Locations (OD Survey at 3 Loc.)
5 Screen Line Points 16 Hr., 3 Locations
6 Mid-Block Locations 16 Hr., 11 Locations
7 Level Crossing Locations 16 Hr., 5 Locations
8 Sub-urban Rail Passenger Surveys 6.17%9 Sub-urban Rail Passenger Surveys, Alighting Survey: Stations 16%
10 Operational Characteristics of Bus and Rail TransportNetworks
5700 Bus Routes and 1767 Train Services
11 IPT (Auto and Taxi) Surveys 50 Locations
12 Bus Terminal Surveys 13 Bus Terminals
13 Airport Terminal Surveys 2000 air passengers14 Goods Terminal Surveys 20 Goods Terminals
15 Speed-Flow Studies 16 Carriageway Types
16 Journey Speed and Delay Studies 550 Kms
17 Network Inventory 2,300 kms.
18 Pedestrian Surveys 50 Locations
19 Parking Surveys 50 Stretches20 Workplace Based Surveys 4000 respondents
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
11/36
Train Bus Taxi
RickshawTwo WheelerCar
11
Where and How People Travel in Mumbai -2005(Morning Peak Period: 6:00 to 11: AM)
http://upload.wikimedia.org/wikipedia/commons/2/29/India.Mumbai.02.jpg -
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
12/36
Per Capita Trip Rate With walk: 1.65
Without walk: 0.65
Trips per day (2005)
Total Region
ModeTrips
(ml)
Mode Split with
Walk
Mode Split without
Walk
Walk 14.85 52.4% -
Train 6.98 24.6% 51.8%
Bus 3.55 12.5% 26.3%
Auto 1.05 3.7% 7.8%
Taxi 0.23 0.8% 1.7%
Two Wheeler 1.05 3.7% 7.8%
Car 0.63 2.2% 4.6%
Total (with Walk) 28.33 100.0% 100.0%
Total (withoutWalk) 13.48
78%
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
13/36
Andheri
Bandra
Thane
Kurla
ChurchgateCST Mumbai
Vashi
Panvel
Borivali
Dadar
Kalyan
Dombivali
Titwala
Ulhasnagar
Mumbai Central
Morning Peak Period (6:00 to 11:00 AM)Crowded Sections or Links(in Lakhs)
Vile Parle
Sion
Mira Rd.
Bhyander5517(12 Car Rake)
3725
(9 Car Rake)
Ghatkopar
TN
Chembur
4852(9 Car Rake)
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
14/36
Average Standees Per Coach 12 pass/sq.m.
US Federal Transit Administration Report(1996)
Totally Intolerable 5 pass/sq.m.
Unacceptable 8 pass/sq.m.
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
15/36
Per Capita Trip Rate With walk: 1.65
Without walk: 0.65
Trips per day (2005)
Total Region
ModeTrips
(ml)
Mode Split with
Walk
Mode Split without
WalkWalk 14.85 52.4% -
Train 6.98 24.6% 51.8%
Bus 3.55 12.5% 26.3%
Auto 1.05 3.7% 7.8%
Taxi 0.23 0.8% 1.7%
Two Wheeler 1.05 3.7% 7.8%
Car 0.63 2.2% 4.6%
Total (with Walk) 28.33 100.0% 100.0%
Total (withoutWalk) 13.48
78%
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
16/36
Mode Split: Major Cities across the World
3
7
10
24
28
37
49
68
72
78
97
93
90
76
72
63
51
32
28
22
0 10 20 30 40 50 60 70 80 90 100
Los Angles
Washing Ton
New York
London
Paris
Singapore
Tokyo
Shanghai
Hong Kong
Mumbai
Public Transport Private Vehicle 16
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
17/36
Vision - TranSforM MMR
Transforming MMR into a world class metropoliswith a vibrant economy and globally comparablequality of life for all its citizens.
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
18/36
CTS for MMR Study:
Proposed TransportInfrastructure
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
19/36
Population, Employment and Vehicular Growth
Population
20.0 mil
34.0 mil
Employment
7.6 mil
15.3 mil
VehicularPopulation
2.0 mil
9.0 mil
9.9
13.4
18.5
22.4
27.0
34.0
0
5
10
15
20
25
30
35
1981 1991 2001 2011 2021 2031
7.6 mil 15.3 mil
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
1996
1998
2000
2002
2004
2006
2008
2010
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
2005
2031
Population
Employment Vehicular Growth
20 Lakhs90 Lakhs
4.5 times
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
20/36
Long Term (2031)
Metro and Sub-urban Network
YearCumulative Length (km)
Metro Sub-urban
2016 208 237
2021 318 237
2031 450 248
Sub-urban Network: 2005
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
21/36
Long Term (2031)Highway Network
Year Cumulative Length (km)
2016 982
2021 1,229
2031 1,739
Highway Network: 2005 (2,600 kms)
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
22/36
17 Inter-State/ Inter-City Bus
Terminals
6 Inter-City rail Terminals
5 Major Truck Terminals and 10
Mini Truck Terminals
13 Passenger Water Transport
(PWT) Terminals
Proposed Terminals
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
23/36
Candidate RoadsforBus Rapid Transit/ EBL/ Mono Rail
On Proposed New Roads
Panvel
Vashi
Uran
Dronagiri
Ulwe
On Existing Roads
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
24/36
Multi-Modal Corridors
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
25/36
Right of Way Requiremen
100
100
100
80
80
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
80
100
100100
The Right of Way (ROW) shown
for each segment of the
proposed Regional Road
Network is the preferred ROW
width.
However , an absolute minimum
width of 80 m is required.
Finalisation of the ROWsrequire, detailed feasibility
studies specific to each corridor.
MetropolitanRegional Roads
ROW, 100 m100
LEGEND
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
26/36
Summary of Preliminary Cost EstimatesProposed Transport Networks
Horizon Years 2031, 2021 and 2016
Component
2008- 2031 2008- 2021 2008- 2016
Lengthkm
CostRs Crores
Lengthkm
CostRs Crores
Lengthkm
CostRs Crores
Metro System 450 1,10,095 316 82,707 204 59,623
Sub-Urban Railway System 241 30,978 231 28,670 231 27,920
Highway System 1660 57,412 1114 44,844 836 31,173
Highway Corridors withEBL
77 1,670 111 2,000 147 11,079
Bus System 4,280 2,150 1,104
Passenger Water Transport 480 480 480
Truck Terminals, Inter-Busand Rail Terminals
3,040 2,038 1,126
Total 2,429 2,07,956 1,772 1,62,890 1,418 1,32,504US $ 50.72 Billion US $ 39.73 Billion US $ 32.32 Billion
Note:
1. The cost estimates are @ 2005-06 prices
2. The metro system cost includes the cost of rolling stock
3. The sub-urban railway system cost includes the cost of rolling stock for new lines, capacity enhancement of the to the
existing sub-urban railway system
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
27/36
Funding Sources
Sl.
No. Transport System
EstimatedTotal Cost
(Rs. Crore)@ 2005-06Prices
Inter
GovernmentalTransfer (%)
Development
Charges(%)
Borrowing
(%)
Private
Investment (%)
I Metro System 1,10,095 15 25 0 60
II Sub-Urban Railway System 30,978 30 30 40 0
III Highway System 57,412 25 25 30 20
IVHighway Corridors with
Exclusive Bus Lanes (EBL) 1,670 25 25 30 20
V Bus System 4,280 25 25 30 20
VI Passenger Water Transport 480 12 12 16 60
VII Terminals 3,040 21 21 28 30
Total Investment, Average % FundingSources
2,07,956 20 28 12 40
Potential Need forRe-allocation from Privateto Development ChargesParticularly for Metro
Creation of Dedicated Fund (MMR Transport InfrastructureFund) for implementation of Proposed Transport Infrastructure in MMR
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
28/36
Infrastructure Investment Needs and
Potential Sources of Funding
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
29/36
Infrastructure Investment Need in MMR
85% of the Infrastructure Investment Need is Transport Infrastructure
Sl. No. SectorInvestment
Needs by 2021
(INR million)
InvestmentNeeds by 2031
(INR million)
1 Regional Water Resource Development 168,640 193,430
2 Transit Development 1,641,740 1,874,860
3 Road development + Terminals 610,500 809,510
4 Regional Drainage 23,920 27,4405 Land, Real estate & Housing 146,160 167,650
6 Thakurli Power Plant 25,000 25,000
7 Regional Landfill Sites 30,000 34,410
8 Matheran Funicular Railway 2,000 2,000
9 Nirmal MMR Abhiyan 2,400 2,400
Total Metropolitan Infrastructure 2,650,360 3,136,690
@ 2009-10 Prices
US$ 53 billion US$ 63 billion
I f t t F di
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
30/36
Funding Source Percent Share INR million
Inter-Government Transfer 4.6% 144,288
MMRDA Resources 18.5% 580,290Borrowings 43.2% 1,355,054
Private Investment + SPV partner
other than Government 33.7% 1,057,068
Total 100% 3,136,700
Infrastructure Funding
Sl.
No.
Project Net Revenuepotential
(INR million)
1 Sale of Lands: Bandra Kurla Complex 389,0002 Sale of lands: Wadala Truck Terminal 174,780
3 MMR Growth Areas & Growth Centres 25,000
Total 588,780
MMRDA Sources:
Potential of Development Charges for the period (2010-2031): 1,160,000 to2,100,000 million
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
31/36
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
32/36
Scenario
2010-2021 2022-2031 2010-2031
INR million
US $
billion INR million US $ billion INR million
US $
million
Base: DC on New Growth &Redevelopment (MMRDA: 7.0% and
ULB: 3.0%)
1,240,000 27.6 860,000 19.0 2,100,000 46.6
Scenario AAverage building values are
lower and unit sizes are smaller than
Base case):
DC on New Growth & Redevelopment
(MMRDA: 7.0% and ULB: 3.0%)
990,000 22.1 710,000 15.9 1,710,000 37.9
Scenario B (Average building value and
unit size are same as in Scenario A):DC
on New Growth & Redevelopment: 5%
Residential (MMRDA: 3.5% & ULB:
1.5%), 10% Non-Residential (7%MMRDA
& 3% ULBs)
650,000 14.3 510,000 11.3 1,160,000 25.6
[1]Assum pt ions for Base Scenar io:Building Value: Rs. 2,000 to 40,000/sq.ft.Average Unit Size of the Building: 600 to 1000 sq.ft.Average Office, Industrial and Other Building Costs: Rs. 30,000, Rs. 8,000 and Rs. 13,000/sq.ft.
[2]Assumptions forScenar io A&B :Building Value: Rs. 1,600 to 32,000/sq.ft
Average Unit Size of the Building : 540 to 900 sq.ftAverage Office, Industrial and Other Building Costs: Rs. 24,000, Rs. 6,400 and Rs. 10,400/sq.ft
Potential of Development Charges
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
33/36
Source of Revenue Revenue Generated by Time Period (in INR Crores)20102021 2022 - 2031 20102031
Cess (5%) on Property 2,300 2,800 5,100
Cess on Fuel 2 %
3 %
2,500
3,800
4,000
6,400
6,500
10,200
Annual Renewal of Vehicle
license: Option (i)*
Option (ii)**
6,800
10,400
9,700
14,700
16,500
25,100
One-Time cess on New
Vehicle Purchases (2 %
Cess)
1,000 1,400 2,400
Employment Tax 9,300 to 18,300 16,900 to 30,400 26,200 to 48,700
Sale of Advertising Rights Tbd
Depends on items
included
Tbd
Depends on
items included
Tbd
Total 21,900 to 35,800 34,800 to 55,700 56,700 to 91,500
*Option (i): Annual renewal fee: two wheelers INR 500, cars INR 2,000, trucks INR 3,000
**Option (ii) Annual renewal fee: two wheeler INR 1000, cars INR 3,000, trucks INR 3,000
Revenue Sources for O&M Shortfalls
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
34/36
Steps taken so far. Implementation of Two metro corridors and one monorail corridor is under
progress;
MMRDA initiated the DPR for Phase II and Phase III metro corridors ofMumbai Metro Master Plan:
MMRDA completed the DPR study for Metro corridor from Siddhi Vinayak-
Sewri-Kharkopar-Dhutum-Dushmi (about 50 kms);
MMRDA initiated the process for Techno-Economic Feasibility Study ofMulti-Modal Corridor from Virar-Alibag Study (140 kms) which covers someof the higher order highway corridors as well as some metro corridors asproposed in the CTS study;
Process initiated for Common Ticketing and Fare Integration, Dialogue withvarious operators/ ULBs is in progress;
UMMTA established under Chairmanship of Chief Secretary. Legal
Framework for UMMTA is in progress;
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
35/36
Steps taken so far.
All the ULBs requested to include the proposed arterial roads and higherorder highway corridors, metro corridors, sub-urban rail corridors,
monorail corridors in the Development Plans for the reservation of RoW;
ULBs have created Traffic & Transportation units;
The study on Monorail Master Plan for MMR is completed;
Initiated Technical Assistance project for implementation of CTS andBusiness Plan proposals. The focus of this TA shall be on preparatoryactions that are needed on priority related to the projects which have to beimplemented by 2016/2021 with specific attention to sustainability;
MMRDA has submitted proposals on Development Charges to GoM;
Project Preparatory works are in progress for implementation of MumbaiTrans Harbour Link (MTHL) and Colaba-Bandra-SEEPZ metro corridor.
-
8/13/2019 Transport Plan for MMR and Resourse Generation Plan Under Mumbai Transformation
36/36
Thank you