Transport Coal or Transmit Electricity? Comparative Hybrid LCA

16
1 Transport Coal or Transmit Electricity? Comparative Hybrid LCA Joule Bergerson, Lester Lave, Chris Hendrickson, Scott Matthews, Alex Farrell Carnegie Mellon University Thursday September 25, 2003

description

Transport Coal or Transmit Electricity? Comparative Hybrid LCA. Joule Bergerson, Lester Lave, Chris Hendrickson, Scott Matthews, Alex Farrell Carnegie Mellon University Thursday September 25, 2003. US Coal Supply and Population. - PowerPoint PPT Presentation

Transcript of Transport Coal or Transmit Electricity? Comparative Hybrid LCA

  • Transport Coal or Transmit Electricity? Comparative Hybrid LCAJoule Bergerson, Lester Lave, Chris Hendrickson, Scott Matthews, Alex FarrellCarnegie Mellon UniversityThursday September 25, 2003

  • US Coal Supply and PopulationA ton of coal is shipped by rail an average distance of 800 miles

  • Life Cycle of Coal-Fired Electricity

    Transmission

    Distribution &Use

    Coal Mining

    Cleaning

    Transportof Coal

    -PM, CO and S-dust-erosion-waste-subsidence-safety issues

    -PM, CO and S -waste

    -coal dust-safety issues-road wear-coal losses

    -PM, CO2, SOx, NOx-thermal discharge-ash sludge-water consumption

    -resources (land, coal etc.)-equipment-labor

    -water-equipment-labor

    Generation

    -rail system-locomotives -freight cars-fuel consumption-labor

    -facility (materials, land etc.)-water-labor

    -EMF-noise

    -resources -structure materials-land -labor

  • ToolsLife Cycle Analysis SETAC Society of Environmental Toxicology and ChemistryBasic Framework for LCADisadvantage: Time consuming and costlyEIOLCA Economic Input-Output Life Cycle AnalysisUS I-O tables with Environmental ImpactsDisadvantage: AggregationIECM Integrated Environmental Control ModelCustomized power plant designDisadvantage: does not include all phases of life-cycle

    Solution: Hybrid Approach

  • EIOLCA example: Transmission Construction1.Determine total economic input from sectorPrices Vary but $1 billion is a rough estimate

    2.Find IO categoryOther new construction (110900) Major Group 16: Heavy Construction Other Than Building Construction ContractorsSIC 1623 Water, Sewer, Pipeline, And Communications And Power LineTransmission line construction-general contractors

    $ 1 Billion Other New Construction

    EIOLCA Model

    Output

  • EIOLCA OutputSource: www.eiolca.net

  • Base Case AssumptionsPower Plants identical (SUPC 40% efficiency, 75% capacity factor) Therefore base production ignored for comparison1000 MW (plus compensation for 7% transmission line losses)Approximately 1000 milesNo siting difficulties or grade crossing upgradesCapitalRail minimal new track capacity, new trainsTransmission new HVDC lines, substationsAmortized over life of investment (cost of capital 8%)

  • Base Case Economic Results

    Chart2

    1692

    6821

    83

    71

    991181113919

    Rail

    Transmission

    Annual Cost ($ million)))

    BCeconomics

    Rail-+Transmission-+

    Capital1692

    O&M6821

    Fuel/Coal83

    Externalities71

    Total991311118199

    BCeconomics

    00

    00

    00

    00

    001113919

    Rail

    Transmission

    Annual Cost ($million)

    BCenv

    0000

    0000

    0000

    0000

    Capital

    O&M

    Fuel/Coal

    Externalities

    Scenarios

    B-1 Summary of the Base Case Environmental Impacts for the Rail and Transmission Scenarios

    Rail Scenario - Summary (metric tonnes)

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    2500016000760001300010000110001100000088000550001500

    Transmission - Summary (metric tonnes)

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    520003600260005401700400004000000043000380800

    Scenarios

    2500052000

    160003600

    7600026000

    13000540

    100001700

    1100040000

    &L

    B-1

    Rail

    Transmission

    Emissions MT

    MorePower

    Rail-20%diff20%diffTransmissionTrans+/-20%Trans+20%0.2004662005

    Base Case98118-0.20053374

    New Construction011896.5144.321.526.3

    29880.1810.2000101021119.77783405840.200000465211896.5144.3New Construction

    511493.27271688280.2000001103139.33343582630.200000728211896.5144.3

    10129105.54547349580.1999998222157.6667686620.200000640411896.5144.3

    15146119.45456657510.199999825178.44460321660.200000880911896.5144.3

    20178145.6364292840.1999995537217.55575463440.200000905911896.5144.3

    Grade Crossings09880.18185494170.1999995461119.77783405840.200000465211896.5144.3

    512299.81828105570.1999990158149.11118398520.200000483811896.5144.3

    7132108.00001999360.1999998167161.33348365330.200000922411896.5144.3

    9140114.5455052040.1999995622171.11114478850.200000194811896.5144.3

    10146119.45456657510.199999825178.44460321660.200000880911896.5144.3

    11151123.54547774680.1999998141184.55571141190.200000836111896.5144.3

    Cost of Fuel$2/gallon108

    $4.5/gallon130

    $6/gallon143

    $7/gallon152118

    Cost of Capital3%9269

    4%9378

    5%9487

    6%9597

    7%97107

    Grade Crossing

    RailTransmission

    Carbon Mgmt$5/ton

    $10/ton

    $15/ton

    $20/ton

    Environmental ExternalitiesBase Case98118

    low est.102130

    mean est.127160

    high est.180207

    Env Externalities

    MorePower

    000000

    000000

    000000

    000000

    000000

    00000

    Rail

    Transmission

    Trans+/-20%

    Trans+20%

    -20%

    20%

    Fraction of System Requiring New Rail (%)

    Annual Cost ($ million)

    Sheet1

    000000

    000000

    000000

    000000

    000000

    000000

    Rail

    Transmission

    Trans+/-20%

    Trans+20%

    Fraction of Grade Crossings Requiring Upgrade (%)

    Annual Cost ($ million)

    00

    00

    00

    00

    Rail

    Transmission

    Annual Cost ($ million)

    Delivered Power (million MWh)Rail-20%20%Transmission-20%20%

    Base Case6.69817.8181400111.384616606421.7778340584-1.27272573511821.4545378461.384615569326.2223068309-1.2727253528

    Case 19.614025.4544947961.384616420931.1111447885-1.272726628617030.90896606531.384617487837.7777920808-1.2727270474

    Case 21928050.90898959191.384616420962.222289577-1.272726628627049.09069004921.38461770860.0001287056-1.2727259963

    Case 31201800327.27162331131.3846171411400.0017465759-1.27272467451600290.90832718761.3846167516355.55594044-1.2727266286

    Case 42303700672.72538760831.3846168438822.2244869025-1.27272563383300599.9980057471.3846171153733.3355400896-1.2727254821

    0021.777834058417.81814001126.222306830921.454537846

    0031.111144788525.45449479637.777792080830.9089660653

    0062.22228957750.908989591960.000128705649.0906900492

    00400.0017465759327.2716233113355.55594044290.9083271876

    00822.2244869025672.7253876083733.3355400896599.998005747

    Rail

    Transmission

    Delivered Power (million MWh)

    Annual Cost ($ million)

    nFuel Price ($6-7/gallon)

    nCost of Capital (3-4%)

    nDistance (~700 miles)

    nCarbon Management Tax (as little as $5/ton)

    ScenarioBase CaseBreak Even Value

    Fuel Price$0.9/gallon$6-7/gallon

    Cost of Capital8%3-4%

    Distance1000 miles~ 700 miles

    Carbon Tax$0as little as $5/ton

  • Scenario: New Rail Construction

    Chart2

    9811896.5144.300

    11411896.5144.380.181119.7778340584

    12911896.5144.393.2727168828139.3334358263

    14611896.5144.3105.5454734958157.666768662

    17811896.5144.3119.4545665751178.4446032166

    11896.5144.3145.636429284217.5557546344

    Rail

    Transmission

    Trans+/-20%

    Trans+20%

    -20%

    20%

    Percent of System Requiring New Rail (%)

    Annual Cost ($ million)))

    BCeconomics

    Rail+-Transmission+-

    Capital1692

    O&M6821

    Fuel/Coal83

    Externalities71

    Total991311118199

    BCeconomics

    00

    00

    00

    00

    001311199

    Rail

    Transmission

    Annual Cost ($million)

    BCenv

    0000

    0000

    0000

    0000

    Capital

    O&M

    Fuel/Coal

    Externalities

    Scenarios

    B-1 Summary of the Base Case Environmental Impacts for the Rail and Transmission Scenarios

    Rail Scenario - Summary (metric tonnes)

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    2500016000760001300010000110001100000088000550001500

    Transmission - Summary (metric tonnes)

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    520003600260005401700400004000000043000380800

    Scenarios

    2500052000

    160003600

    7600026000

    13000540

    100001700

    1100040000

    &L

    B-1

    Rail

    Transmission

    Emissions MT

    MorePower

    Rail-20%diff20%diffTransmissionTrans+/-20%Trans+20%0.2004662005

    Base Case98118-0.20053374

    New Construction011896.5144.321.526.3

    29880.1810.2000101021119.77783405840.200000465211896.5144.3New Construction

    511493.27271688280.2000001103139.33343582630.200000728211896.5144.3

    10129105.54547349580.1999998222157.6667686620.200000640411896.5144.3

    15146119.45456657510.199999825178.44460321660.200000880911896.5144.3

    20178145.6364292840.1999995537217.55575463440.200000905911896.5144.3

    Grade Crossings09811896.5144.3

    512211896.5144.3

    713211896.5144.3

    914011896.5144.3

    1014611896.5144.3

    1115111896.5144.3

    Cost of Fuel$2/gallon108

    $4.5/gallon130

    $6/gallon143

    $7/gallon152118

    Cost of Capital3%9269

    4%9378

    5%9487

    6%9597

    7%97107

    Grade Crossing

    RailTransmission

    Carbon Mgmt$5/ton

    $10/ton

    $15/ton

    $20/ton

    Environmental ExternalitiesBase Case98118

    low est.102130

    mean est.127160

    high est.180207

    Env Externalities

    MorePower

    000000

    000000

    000000

    000000

    000000

    00000

    Rail

    Transmission

    Trans+/-20%

    Trans+20%

    -20%

    20%

    Fraction of System Requiring New Rail (%)

    Annual Cost ($ million)

    0000

    0000

    0000

    0000

    0000

    0000

    Rail

    Transmission

    Trans+/-20%

    Trans+20%

    Fraction of Grade Crossings Requiring Upgrade (%)

    Annual Cost ($ million)

    00

    00

    00

    00

    Rail

    Transmission

    Annual Cost ($ million)

    Delivered Power (million MWh)RailTransmission

    Base Case6.698118

    Case 19.6140170

    Case 219280270

    Case 312018001600

    Case 423037003300

    00

    00

    00

    00

    00

    Rail

    Transmission

    Delivered Power (million MWh)

    Annual Cost ($ million)

  • Scenario: Grade Crossings

    Chart3

    9811896.5144.380.1818549417119.7778340584

    12211896.5144.399.8182810557149.1111839852

    13211896.5144.3108.0000199936161.3334836533

    14011896.5144.3114.545505204171.1111447885

    14611896.5144.3119.4545665751178.4446032166

    15111896.5144.3123.5454777468184.5557114119

    Rail

    Transmission

    Trans+/-20%

    Trans+20%

    Percent of Grade Crossings Requiring Upgrade (%)

    Annual Cost ($ million)))

    BCeconomics

    Rail+-Transmission+-

    Capital1692

    O&M6821

    Fuel/Coal83

    Externalities71

    Total991311118199

    BCeconomics

    00

    00

    00

    00

    001311199

    Rail

    Transmission

    Annual Cost ($million)

    BCenv

    0000

    0000

    0000

    0000

    Capital

    O&M

    Fuel/Coal

    Externalities

    Scenarios

    B-1 Summary of the Base Case Environmental Impacts for the Rail and Transmission Scenarios

    Rail Scenario - Summary (metric tonnes)

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    2500016000760001300010000110001100000088000550001500

    Transmission - Summary (metric tonnes)

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    520003600260005401700400004000000043000380800

    Scenarios

    2500052000

    160003600

    7600026000

    13000540

    100001700

    1100040000

    &L

    B-1

    Rail

    Transmission

    Emissions MT

    MorePower

    Rail-20%diff20%diffTransmissionTrans+/-20%Trans+20%0.2004662005

    Base Case98118-0.20053374

    New Construction011896.5144.321.526.3

    29880.1810.2000101021119.77783405840.200000465211896.5144.3New Construction

    511493.27271688280.2000001103139.33343582630.200000728211896.5144.3

    10129105.54547349580.1999998222157.6667686620.200000640411896.5144.3

    15146119.45456657510.199999825178.44460321660.200000880911896.5144.3

    20178145.6364292840.1999995537217.55575463440.200000905911896.5144.3

    Grade Crossings09880.18185494170.1999995461119.77783405840.200000465211896.5144.3

    512299.81828105570.1999990158149.11118398520.200000483811896.5144.3

    7132108.00001999360.1999998167161.33348365330.200000922411896.5144.3

    9140114.5455052040.1999995622171.11114478850.200000194811896.5144.3

    10146119.45456657510.199999825178.44460321660.200000880911896.5144.3

    11151123.54547774680.1999998141184.55571141190.200000836111896.5144.3

    Cost of Fuel$2/gallon108

    $4.5/gallon130

    $6/gallon143

    $7/gallon152118

    Cost of Capital3%9269

    4%9378

    5%9487

    6%9597

    7%97107

    Grade Crossing

    RailTransmission

    Carbon Mgmt$5/ton

    $10/ton

    $15/ton

    $20/ton

    Environmental ExternalitiesBase Case98118

    low est.102130

    mean est.127160

    high est.180207

    Env Externalities

    MorePower

    000000

    000000

    000000

    000000

    000000

    00000

    Rail

    Transmission

    Trans+/-20%

    Trans+20%

    -20%

    20%

    Fraction of System Requiring New Rail (%)

    Annual Cost ($ million)

    000000

    000000

    000000

    000000

    000000

    000000

    Rail

    Transmission

    Trans+/-20%

    Trans+20%

    Fraction of Grade Crossings Requiring Upgrade (%)

    Annual Cost ($ million)

    00

    00

    00

    00

    Rail

    Transmission

    Annual Cost ($ million)

    Delivered Power (million MWh)RailTransmission

    Base Case6.698118

    Case 19.6140170

    Case 219280270

    Case 312018001600

    Case 423037003300

    00

    00

    00

    00

    00

    Rail

    Transmission

    Delivered Power (million MWh)

    Annual Cost ($ million)

  • Scenario Analysis - Other

  • Air Emissions (30 years)

    Chart3

    2500026000

    160001800

    7600013000

    13000270

    10000850

    1100020000

    Rail

    Transmission

    Emissions MT l

    NewLosses

    B-1 Summary of the Base Case Environmental Impacts for the Rail and Transmission Scenarios

    Rail Scenario - Summary (metric tonnes)

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    2500016000760001300010000110001100000088000550001500

    RailTransmission

    11537465RailGWP1155722440369372

    39905570.304TransmissionCO21140391640288238

    CH47915438963

    0.289119159N2O849345

    Transmission - Summary (metric tonnes)3.4587815055CFCs1645707

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    26000180013000270850200004000000043000380800

    &L

    B-1&CAppendix B - Base Case - Environmental Impact

    NewLosses

    00

    00

    00

    00

    00

    00

    &L

    B-1

    Rail

    Transmission

    Emissions MT

    B

    0000

    0000

    CO2

    CH4

    N20

    CFCs

    Emissions (MT CO2 eq.)

    Comparison of GHG Emissions - Base Case - Project

    B-1

    Appendix B - Base Case - Environmental Impact

    This includes:

    B-1 Summary of the Base Case Environmental Emissions for the Rail and Transmission Scenarios

    B-2 Description of the data used for the environmental emissions rail scenario base case

    B-3 Description of the data used for the environmental emissions transmission scenario base case

    B-4 Estimating the Environmental Externalities for the Base Case

    B-1 Summary of the Base Case Environmental Impacts for the Rail and Transmission Scenarios

    This section takes the sum of the analysis in each scenario in order to compare the environmental emissions.

    These emissions include greenhouse gases and conventional pollutants

    The eiolca software was used to calculate all of these emissions excluding the power plant emissions (from the extra capacity required in the transmission scenario) and the combustion of the fuel in the rail scenario.

    For the power plant emissions - IECM1 was used

    For the diesel combustion the IPCC2 guidelines were used for the greenhouse gases and EPA emission factors3 were used for the conventional pollutants. (Note: various methods were used to estimate the emissions from diesel combustion. The results varied

    Note: for these two cases some of the emission values are missing. The compounds that are missing are not considered to have a significant impact on the results.

    The mining required for the additional coal in the rail scenario has been subtracted from the transmission scenario in order to reflect the net impact from the mining.

    Each of these sections show the eiolca.net emissions expected for $1 million of activity in each of the sectors shown. These emissions are then multiplied by the actual amount spent in each of these sectors for the base case. However, the amount spent i

    A total project duration of 30 years was used to calculate the emissions for the lifetime of the project.

    B-2 Description of the data used for the environmental emissions rail scenario base case

    This section is split into two sections - conventional pollutants and greenhouse gases

    B-3 Description of the data used for the environmental emissions transmission scenario base case

    This section is split into two sections - conventional pollutants and greenhouse gases

    1 IECM. Integrated Environmental Control Model User Documentation, www.iecm-online.com; Center for Energy and Environmental Studies, Carnegie Mellon University: Pittsburgh, PA, 2001.

    2 Intergovernmental Panel on Climate Change. Revised 1996 IPCC Guidelines for National Greenhouse Gas Inventories: Workbook. 1.5 - 1.8

    3 U.S. Environmental Protection Agency, Office of Mobile Sources. Locomotive Emission Standards: Regulatory Support Document, April, 1998.

    4 Carnegie Mellon Green Design Initiative, Economic Input-Output Life Cycle Assessment. (http://www.eiolca.net/).

    &L

    B&CAppendix B - Base Case - Environmental Impact

    B-2-1

    B-1 Summary of the Base Case Environmental Impacts for the Rail and Transmission Scenarios

    Rail Scenario - Summary (metric tonnes)

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    2500016000760001300010000110001100000088000550001500

    RailTransmission

    11537465RailGWP1155722440369372

    39905570.304TransmissionCO21140391640288238

    CH47915438963

    0.289119159N2O849345

    Transmission - Summary (metric tonnes)3.4587815055CFCs1645707

    SO2CONO2VOCPM10GWP (millions MT CO2e)CO2CH4N2OCFCs

    520003600260005401700400004000000043000380800

    &L

    B-1&CAppendix B - Base Case - Environmental Impact

    B-2-1

    00

    00

    00

    00

    00

    00

    &L

    B-1

    Rail

    Transmission

    Emissions MT

    Comparison of Emissions - Base Case - Project

    B-2-2

    0000

    0000

    CO2

    CH4

    N20

    CFCs

    Emissions (MT CO2 eq.)

    Comparison of GHG Emissions - Base Case - Project

    B-3-1

    B-2-1 Description of the data used for the environmental emissions rail scenario base case

    Conventional Pollutants

    Rail Capital Investment

    (all in metric tonnes)$ 1 millionActual

    SO2CONO2VOCLeadPM10ActualSO2CONO2VOCLeadPM10

    Rail Equipment3.74.42.40.940.00160.511696297394141590.2686

    Coal Transport$ 1 millionActual

    SO2CONO2VOCLeadPM10ActualSO2CONO2VOCLeadPM10

    Fuel Consumption - burning the fuel68834124023842888.8(million gallons)6883412402384288

    (oeko method)2379.525294000000ton km

    Fuel Consumption - before the fuel is burned6.25.26.92.60.0002871.27.9494154200.00239.2

    Maintenance$ 1 millionActualLong Way

    SO2CONO2VOCLeadPM10ActualSO2CONO2VOCLeadPM10SO2CONO2VOCLeadPM10

    Rail Equipment (yearly investment in new trains etc.)3.74.42.40.940.00160.5111414827100.0175.680949825224260342

    Other New Construction1.33.02.70.430.0006873.981124213.40.00531

    Materials and other costs (steel foundries)3.48.23.11.30.00601.551741156.50.0307.5eiolca

    Engineering Services0.700.700.570.180.0000890.09242.82.82.30.730.0003560.37Rail Related Services ($ 1million)3.323356.42177119.4260451.3856910.0002991.576698

    SO2CONO2VOCLeadPM10for $36.6 million122235711510.01094358

    Total (yearly no capital)81050025004300.06340

    Total Project (30 years)SO2CONO2VOCLeadPM10

    25000160007600013000210000

    Note: Mining is not included in this scenario because the amount of extra mining that is required in this scenario (due to losses during rail transport) has been subtracted from the losses in the transmission scenario.

    total for base case

    61

    Salaries and Benefits24.82

    Equipment and Other Rents8.40

    Capital Investment7.7919.74

    Fuel and Utilities8.65

    Materials and Supplies3.37

    Other Costs7.96

    &L

    B-2-1&CAppendix B - Base Case - Environmental Impact

    B-3-2

    B-2-2 Description of the data used for the environmental emissions rail scenario base case

    Greenhouse Gases

    Rail Capital Investment

    MT$ 1 millionActual

    GWPCO2CH4N2OCFCsActualGWPCO2CH4N2OCFCs

    Rail Equipment676615600.500.651691142331039131012585110

    Coal Transport$ 1 millionActual

    GWPCO2CH4N2OCFCsActualGWPCO2CH4N2OCFCs

    Fuel Consumption - burning the fuel (oecd)35284135041761318108.86436000000ton km35284135041761318100

    IPCC method1129411525TJ

    7008348

    Fuel Consumption - upstream13161236750.753.67.91039397685915.929

    Maintenance$ 1 millionActual

    GWPCO2CH4N2OCFCsActualGWPCO2CH4N2OCFCs

    Rail Equipment676615600.500.6511743567646595.57.1

    Other New Construction374339340.330.858299527122732.76.8

    Materials and other costs (steel foundries)783707740.540.9053915353637235

    Engineering Services188168190.150.184752674770.610.71

    GWPCO2CH4N2OCFCs

    Total3783323738712585182848

    Total ProjectGWPCO2CH4N2OCFCs

    110001100000088000550001500

    Contributions to GWP%Contribution to GWP

    Equipment Manufacture1038.4810388727CO21000007333333

    Fuel Consumption99063.9019603856CH4800

    Maintenance4117.5124088182N2O500

    Total104219.895408077CFCs13.6363636364

    Total101314

    &L

    B-2-2&CAppendix B - Base Case - Environmental Impact

    B-4

    B-3-1 Description of the data used for the environmental emissions transmission scenario base case

    Conventional Pollutants

    Transmission Line Construction

    metric tonnes$ 1 millionActual

    SO2CONO2VOCLeadPM10ActualSO2CONO2VOCLeadPM10

    Engineering, Architectural and Surveying Services0.700.700.570.180.0000890.092$74.2525242140.0077

    Trucking and Courier Services, except air1.528224.80.0002020.90$11.117306245530.00210

    Iron and Steel Forgings4.35.93.40.720.00340.63$15628550100.0499

    Aluminum Rolling and Drawing10204.71.50.00371.1$575711124265880.2161

    Plastics Materials and Resins4.44.04.62.10.00100.792$3.4415141670.0033

    Ready-mixed Concrete8.15.49.81.10.0005631.9$19.0153103187210.01136

    Electrical Industrial Apparatus, n.e.c.2.23.02.80.700.000920.48$2124606285991490.20103

    Plumbing Fixtures Fittings and Trim2.83.62.00.730.00440.43$2.8810620.0121

    Lighting Fixtures and Equipment2.23.42.20.700.00110.38$1.234310.0010

    Other New Construction1.33.02.70.430.0006873.9$32.6449687140.022128

    Total1384242314993590.52358Long Way

    4076586861020759

    Additional Capacity$ 1 millionActual

    SO2CONO2VOCLeadPM10ActualSO2CONO2VOCLeadPM10eiolca

    Other New Construction1.33.02.70.430.0006873.9$184246545493790.13721Rail Related Services ($ 1million)3.323356.42177119.4260451.3856910.0002991.576698

    Coal Mining2.72.43.00.530.0003391.2$2.15.65.06.31.10.00071192.6for $36.6 million122235711510.01094358

    Emissions from Additional Coal Burning16617841661784

    Maintenance$ 1 million

    SO2CONO2VOCLeadPM10ActualSO2CONO2VOCLeadPM10

    Other New Construction1.33.02.70.430.0006873.9$5.06.715132.10.003420

    SO2CONO2VOCLeadPM10

    Total (not including capital investment)1674208043.30.004122

    Total ProjectSO2CONO2VOCLeadPM10

    520003600260005400.771700

    Note: The coal mining required in the rail scenario ($0.9 million) has been subtracted from the transmission scenario to reflect the net mining impact of the transmission scenario

    Note: Some of the emissions due to burning coal have not been included in this analysis

    51839.953561.229877791926099.9450832212535.61675385211745.5926263276

    &L

    B-3-1&CAppendix B - Base Case - Environmental Impact

    B-3-2 Description of the data used for the environmental emissions transmission scenario base case

    Greenhouse Gases

    Transmission Line Construction

    metric tonnes$1 millionActual

    GWPCO2CH4N2OCFCsActualGWPCO2CH4N2OCFCs

    Engineering, Architectural and Surveying Services188168190.150.18$74139481249814261113

    Trucking and Courier Services, except air185216681813.00.54$1120534184942007336.0

    Iron and Steel Forgings1066972920.651.3$15155001413313331018

    Aluminum Rolling and Drawing942850900.621.4$57535444831851123579

    Plastics Materials and Resins141512861010.8128$3.4486544193462.897

    Ready-mixed Concrete146013191381.22.1$19277232503726242239

    Electrical Industrial Apparatus, n.e.c.634573600.520.91$21213454612157712666111192

    Plumbing Fixtures Fittings and Trim547494510.470.47$2.8155013991451.31.3

    Lighting Fixtures and Equipment573518520.462.0$1.2683618620.62.4

    Other New Construction374339340.330.85$33121991104811121128

    Total28509225754026832238477

    Additional Capacity$ 1 millionActual

    GWPCO2CH4N2OCFCsActualGWPCO2CH4N2OCFCs

    Other New Construction374339340.330.851846888662387628161157

    Coal Mining852780710.510.622.1178916371491.11.3

    Emissions from Additional Coal Burning1330186133018613301861330186

    Maintenance$ 1 millionActual

    GWPCO2CH4N2OCFCsActualGWPCO2CH4N2OCFCs

    Other New Construction374339340.330.855187216951711.74.3

    GWPCO2CH4N2OCFCs

    Total (not including capital)1333846133351832036

    Total ProjectGWPCO2CH4N2OCFCs

    400000004000000043000380800

    &L

    B-3-2&CAppendix B - Base Case - Environmental Impact

    B-4 Estimating the Environmental Externalities for the Base Case

    Base Case -Emissions (30 year project) tonnesExternal Costs ($)

    Mean Estimated External Cost ($/tonne)*RailTransmissionRailTransmission

    CO5201600036008.3E+061.9E+06

    NOx280076000260002.1E+087.3E+07

    SO2200025000520005.0E+071.0E+08

    PM1043001000017004.3E+077.3E+06

    VOC1600130005402.1E+078.6E+05

    CO2e1311000000400000001.4E+085.2E+08

    Total (1992$)4.8E+087.1E+08

    Total (2000$) - using discount rate of 8%8.8E+081.3E+09

    Annual Cost2.9E+074.4E+07

    Base Case -Emissions (30 year project) tonnesExternal Costs ($)

    Max Estimated External Cost ($/tonne)*RailTransmissionRailTransmission

    CO10501600036001.7E+073.8E+06

    NOx950076000260007.2E+082.5E+08

    SO2470025000520001.2E+082.4E+08

    PM10162001000017001.6E+082.8E+07

    VOC4400130005405.7E+072.4E+06

    CO2e2311000000400000002.5E+089.2E+08

    Total (1992$)1.3E+091.4E+09

    Total (2000$) - using discount rate of 8%2.5E+092.7E+09

    Annual Cost8.2E+078.9E+07

    Base Case -Emissions (30 year project) tonnesExternal Costs ($)

    Min Estimated External Cost ($/tonne)*RailTransmissionRailTransmission

    CO11600036001.6E+043.6E+03

    NOx22076000260001.7E+075.7E+06

    SO277025000520001.9E+074.0E+07

    PM109501000017009.5E+061.6E+06

    VOC160130005402.1E+068.6E+04

    CO2e211000000400000002.2E+078.0E+07

    Total (1992$)7.0E+071.3E+08

    Total (2000$) - using discount rate of 8%1.3E+082.4E+08

    Annual Cost4.3E+067.9E+06

    * Matthews, H.S. Lave, L. Applications of Environmental Valuation for Determining Externality Costs. Environmental Science and Technology. Vol. 34. pp. 1390-1395. 2000.

    &L

    B-4

  • Comparative Annual Energy Consumption

    Chart1

    1.35

    46.5

    8.31.55

    Rail

    Transmission

    Energy, CO2 Emissions, Fuel Costs)

    Sheet1

    Energy (10^12 BTU)CO2 (10^5 tons)Fuel Costs ($ 10^6)

    Rail1.348.3

    Transmission56.51.55

    10133.1

    Sheet1

    00

    00

    00

    Rail

    Transmission

    Comparative Annual Energy Consumption

    Sheet2

    Sheet3

    MBD00912336.xls

    BaseCase

    A-1 Base Case - Cost Estimates

    RailTransmission

    1000 MW plant

    Cost TypeCostDetailsCost TypeCostDetails

    Capital Cost for New Track (million)$53Capital Cost Transmission Line Construction (million)$942

    Capital Cost for New Trains$124Captial Cost Additional Capacity Required (million)$184

    Total Capital Cost (million)$176Total Capital Cost (million)$1,126

    Interest Rate0.08compounded annuallyInterest Rate0.08compounded annually

    Amortization Period30Amortization Period50FuelEnergyCO2$ millions spent on fuel

    Amortized Annual Cost (million)$16Amortized Annual Cost (million)$92Coal - Base (million tons)Diesel (million gallons)Coal (BTU)Diesel (BTU)Total BTU(million tons)

    Coal Required (base amount - tons)3290000Coal Required (base amount)3290000tonsTotal Power Plant + Transport/TransmitRail3.39.25.60E+131.30E+125.80E+138.784

    Cost of Coal at Utility (million)$763290000Cost of Coal at Utility (million)$16Transmission3.9-6.70E+13-6.70E+139.720

    Additional Coal Required (to compensate for losses)611000tonsJust energy to transport /transmitRail-9.2-1.30E+121.30E+120.48.3

    Cost of Additional Coal (million)$3Transmission0.61-1.00E+13-1.00E+131.33.1

    Sub Total (million)$91Cost of Operating and Maintenance$5

    Fatalities Expected (operation)0.00

    Cost of Fatalities (million)0.0Sub Total (million)$117

    Fatalities Expected (rail deaths)1.17Fatalities Expected0.196

    Cost of Fatalities (million)$6Cost of Fatalities (million)$1.02

    Total Cost of Case 2 - Rail Scenario (million)$97Total Cost of Case 1 - Transmission Scenario (million)$118

    Length (miles)Fraction LostRequiredTotal lineNet CapacityExtra Capacity Cost

    10000.13911391160145184

    9000.12611261150136173

    8000.111140127161

    7000.11120109138

    6000.087110091115

    4000.06210605469

    2000.03710302735

    LengthRailTransmission

    100091117

    90091110

    80090104

    7008897

    6008887

    5008778

    4008775

    2008362

    &L

    A-1&CAppendix A - Base Case - Costs, Assumptions and Data

    900 miles

    A-1 Base Case - Cost Estimates

    RailTransmission

    1000 MW plant

    Cost TypeCostDetailsCost TypeCostDetails

    Capital Cost for New Track (million)$53Capital Cost Transmission Line Construction (million)$877

    Capital Cost for New Trains$124Captial Cost Additional Capacity Required (million)173

    Total Capital Cost (million)$176Total Capital Cost (million)$1,050

    Interest Rate0.08compounded annuallyInterest Rate0.08compounded annually

    Amortization Period30Amortization Period50

    Amortized Annual Cost (million)$16Amortized Annual Cost (million)$86

    Coal Required (base amount - tons)3290000Coal Required (base amount)3290000tons

    Cost of Coal at Utility (million)$76Cost of Coal at Utility (million)$16

    Additional Coal Required (to compensate for losses)611000tons

    Cost of Additional Coal (million)$3

    Sub Total (million)$91Cost of Operating and Maintenance$5

    Fatalities Expected (operation)0.00

    Cost of Fatalities (million)0.0Sub Total (million)$110

    Fatalities Expected (rail deaths)1.17Fatalities Expected0.196

    Cost of Fatalities (million)$6Cost of Fatalities (million)$1.02

    Total Cost of Case 2 - Rail Scenario (million)$97Total Cost of Case 1 - Transmission Scenario (million)$111

    &L

    A-1&CAppendix A - Base Case - Costs, Assumptions and Data

    800 miles

    A-1 Base Case - Cost Estimates

    RailTransmission

    1000 MW plant

    Cost TypeCostDetailsCost TypeCostDetails

    Capital Cost for New Track (million)$53Capital Cost Transmission Line Construction (million)$812

    Capital Cost for New Trains$106Captial Cost Additional Capacity Required (million)$161

    Total Capital Cost (million)$159Total Capital Cost (million)$973

    Interest Rate0.08compounded annuallyInterest Rate0.08compounded annually

    Amortization Period30Amortization Period50

    Amortized Annual Cost (million)$14Amortized Annual Cost (million)$80

    Coal Required (base amount - tons)3290000Coal Required (base amount)3290000tons

    Cost of Coal at Utility (million)$763290000Cost of Coal at Utility (million)$16

    Additional Coal Required (to compensate for losses)611000tons

    Cost of Additional Coal (million)$3

    Sub Total (million)$90Cost of Operating and Maintenance$5

    Fatalities Expected (operation)0.00

    Cost of Fatalities (million)0.0Sub Total (million)$104

    Fatalities Expected (rail deaths)1.17Fatalities Expected0.196

    Cost of Fatalities (million)$6Cost of Fatalities (million)$1.02

    Total Cost of Case 2 - Rail Scenario (million)$96Total Cost of Case 1 - Transmission Scenario (million)$105

    &L

    A-1&CAppendix A - Base Case - Costs, Assumptions and Data

    700 miles

    A-1 Base Case - Cost Estimates

    RailTransmission

    1000 MW plant

    Cost TypeCostDetailsCost TypeCostDetails

    Capital Cost for New Track (million)$53Capital Cost Transmission Line Construction (million)$747

    Capital Cost for New Trains$88Captial Cost Additional Capacity Required (million)$138

    Total Capital Cost (million)$141Total Capital Cost (million)$885

    Interest Rate0.08compounded annuallyInterest Rate0.08compounded annually

    Amortization Period30Amortization Period50

    Amortized Annual Cost (million)$12Amortized Annual Cost (million)$72

    Coal Required (base amount - tons)3290000Coal Required (base amount)3290000tons

    Cost of Coal at Utility (million)$763290000Cost of Coal at Utility (million)$16

    Additional Coal Required (to compensate for losses)611000tons

    Cost of Additional Coal (million)$3

    Sub Total (million)$88Cost of Operating and Maintenance$5

    Fatalities Expected (operation)0.00

    Cost of Fatalities (million)0.0Sub Total (million)$97

    Fatalities Expected (rail deaths)1.17Fatalities Expected0.196

    Cost of Fatalities (million)$6Cost of Fatalities (million)$1.02

    Total Cost of Case 2 - Rail Scenario (million)$94Total Cost of Case 1 - Transmission Scenario (million)$98

    &L

    A-1&CAppendix A - Base Case - Costs, Assumptions and Data

    600 miles

    A-1 Base Case - Cost Estimates

    RailTransmission

    1000 MW plant

    Cost TypeCostDetailsCost TypeCostDetails

    Capital Cost for New Track (million)$53Capital Cost Transmission Line Construction (million)$682

    Capital Cost for New Trains$88Captial Cost Additional Capacity Required (million)$115

    Total Capital Cost (million)$141Total Capital Cost (million)$797

    Interest Rate0.08compounded annuallyInterest Rate0.08compounded annually

    Amortization Period30Amortization Period50

    Amortized Annual Cost (million)$12Amortized Annual Cost (million)$65

    Coal Required (base amount - tons)3290000Coal Required (base amount)3290000tons

    Cost of Coal at Utility (million)$763290000Cost of Coal at Utility (million)$16

    Additional Coal Required (to compensate for losses)611000tons

    Cost of Additional Coal (million)$3

    Sub Total (million)$88Cost of Operating and Maintenance$5

    Fatalities Expected (operation)0.00

    Cost of Fatalities (million)0.0Sub Total (million)$90

    Fatalities Expected (rail deaths)1.17Fatalities Expected0.196

    Cost of Fatalities (million)$6Cost of Fatalities (million)$1.02

    Total Cost of Case 2 - Rail Scenario (million)$94Total Cost of Case 1 - Transmission Scenario (million)$91

    &L

    A-1&CAppendix A - Base Case - Costs, Assumptions and Data

    500 miles

    A-1 Base Case - Cost Estimates

    RailTransmission

    1000 MW plant

    Cost TypeCostDetailsCost TypeCostDetails

    Capital Cost for New Track (million)$53Capital Cost Transmission Line Construction (million)$617

    Capital Cost for New Trains$71Captial Cost Additional Capacity Required (million)35

    Total Capital Cost (million)$124Total Capital Cost (million)$652

    Interest Rate0.08compounded annuallyInterest Rate0.08compounded annually

    Amortization Period30Amortization Period50

    Amortized Annual Cost (million)$11Amortized Annual Cost (million)$53

    Coal Required (base amount - tons)3290000Coal Required (base amount)3290000tons

    Cost of Coal at Utility (million)$763290000Cost of Coal at Utility (million)$16

    Additional Coal Required (to compensate for losses)611000tons

    Cost of Additional Coal (million)$3

    Sub Total (million)$87Cost of Operating and Maintenance$5

    Fatalities Expected (operation)0.00

    Cost of Fatalities (million)0.0Sub Total (million)$78

    Fatalities Expected (rail deaths)1.17Fatalities Expected0.196

    Cost of Fatalities (million)$6Cost of Fatalities (million)$1.02

    Total Cost of Case 2 - Rail Scenario (million)$93Total Cost of Case 1 - Transmission Scenario (million)$79

    &L

    A-1&CAppendix A - Base Case - Costs, Assumptions and Data

    400 miles

    A-1 Base Case - Cost Estimates

    RailTransmission

    1000 MW plant

    Cost TypeCostDetailsCost TypeCostDetails

    Capital Cost for New Track (million)$53Capital Cost Transmission Line Construction (million)$552

    Capital Cost for New Trains$71Captial Cost Additional Capacity Required (million)$69

    Total Capital Cost (million)$124Total Capital Cost (million)$621

    Interest Rate0.08compounded annuallyInterest Rate0.08compounded annually

    Amortization Period30Amortization Period50

    Amortized Annual Cost (million)$11Amortized Annual Cost (million)$51

    Coal Required (base amount - tons)3290000Coal Required (base amount)3290000tons

    Cost of Coal at Utility (million)$763290000Cost of Coal at Utility (million)$16

    Additional Coal Required (to compensate for losses)611000tons

    Cost of Additional Coal (million)$3

    Sub Total (million)$87Cost of Operating and Maintenance$5

    Fatalities Expected (operation)0.00

    Cost of Fatalities (million)0.0Sub Total (million)$75

    Fatalities Expected (rail deaths)1.17Fatalities Expected0.196

    Cost of Fatalities (million)$6Cost of Fatalities (million)$1.02

    Total Cost of Case 2 - Rail Scenario (million)$93Total Cost of Case 1 - Transmission Scenario (million)$76

    0.14

    &L

    A-1&CAppendix A - Base Case - Costs, Assumptions and Data

    200 miles

    A-1 Base Case - Cost Estimates

    RailTransmission

    1000 MW plant

    Cost TypeCostDetailsCost TypeCostDetails

    Capital Cost for New Track (million)$53Capital Cost Transmission Line Construction (million)$422

    Capital Cost for New Trains$35Captial Cost Additional Capacity Required (million)35

    Total Capital Cost (million)$88Total Capital Cost (million)$457

    Interest Rate0.08compounded annuallyInterest Rate0.08compounded annually

    Amortization Period30Amortization Period50

    Amortized Annual Cost (million)$8Amortized Annual Cost (million)$37

    Coal Required (base amount - tons)3290000Coal Required (base amount)3290000tons

    Cost of Coal at Utility (million)$763290000Cost of Coal at Utility (million)$16

    Additional Coal Required (to compensate for losses)611000tons

    Cost of Additional Coal (million)$3

    Sub Total (million)$83Cost of Operating and Maintenance$5

    Fatalities Expected (operation)0.00

    Cost of Fatalities (million)0.0Sub Total (million)$62

    Fatalities Expected (rail deaths)1.17Fatalities Expected0.196

    Cost of Fatalities (million)$6Cost of Fatalities (million)$1.02

    Total Cost of Case 2 - Rail Scenario (million)$90Total Cost of Case 1 - Transmission Scenario (million)$63

    &L

    A-1&CAppendix A - Base Case - Costs, Assumptions and Data

  • Some Alternatives

    Coal to Methane or HydrogenCoal Slurry PipelineAC TransmissionHigh Temperature SuperconductorsBarge and Rail

  • ConclusionsFrom the current case there is no economic/environmental gain in switching to minemouth generationSome scenarios change this resultCost and environmental emissions from existing system are significantOther methods of transporting energy should be investigatedContribution has been made from developing a method to compare alternative transport/transmission scenarios in terms of economic and environmental impact

  • Thanks to Support from.

    My research looks at the economic and env differences between rail transport and electricity transmission and I used a hybrid comparative Life Cycle Analysis framework (which I developed) to do thisPut source on this!One of the major contributions of this paper is the development of the method for comparative LCA LCA important to look at all the impacts associated with a process or productTraditional life cycle analysis inputs/outputs mass and energy balanceHybrid approach makes use of eiolca to estimate some of the upstream impactsQuickly/easily get results defficiencies made up by more specific data e.g. IECMAssumptions made to build the two casesCosts estimatedCosts used in eiolca model to determine env. Impacts (links economic activity and emissions)Comparative Analysis cut things down even more Comparing two processes therefore anything that is the same can be left outCoal mining, cleaning and use phases will be the same regardless- because same coal, processed in same place-electricity consumed in TexasFinally, in both Tx and Wy, the strictest of env and water restrictions are expected for a new power plant, therefore the impacts and costs are expected to be the same. Therefore, this analysis focuses on the transport and transmission phases of the life cycle.

    SETACInventoryImpactImprovement

    EIOLCAlinksUS gov puts out IO tables 480 x 480UPSTREAM EMISSIONS FULL PICTURE

    IECM Cost (Capitol, Operational)Technology (e.g. boiler type, efficiency, combustion type)Environmental ControlsWater consumptionHYBRID APPROACH combines best of all worldsThis method combines the benefits associated with the EIOLCA (Economic Input-Output Life Cycle Analysis) method as well as the traditional SETAC approach. The cost and environmental impact data available at a national, aggregated level (by industrial sector) is used in conjunction with a product analysis of more specific electricity generation scenarios.

    Few of many these studies are full of assumptions therefore, these will be discussed furtherThese and other assumptions helped to build a base case-cost and environmental impacts were estimated -context of 1000 MW in terms of Texas % capacity and coal capacity - 55MW summer peak demandA little more than is currently connected to non ERCOT Expect 4% growth this is close to 2%

    CapitalO&MSocial just construction and railTotal not practically different (within error)

    Suggestions for breakdown of variable, fixed, marginal to fit this into the real world

    % of 1000 miles new rail Base case 15 milesUpper and lower boundsBetween 10 to 15%

    600 rail crossings from WY to TX Base case assumes 0Close to 10%

    Change to table

    ParameterNominalBreak Even ValueFuel etc.Remind audience of comparative