TRANSPORT and ROAD RESEARCH LABORATORY Department of … · Inland waterways Pipelines Per cent of...
Transcript of TRANSPORT and ROAD RESEARCH LABORATORY Department of … · Inland waterways Pipelines Per cent of...
TRANSPORT and ROAD RESEARCH LABORATORY
Department of the Environment Department of Transport
SUPPLEMENTARY REPORT 592
PIPELINES CONSIDERED AS A MODE OF FREIGHT TRANSPORT: A REVIEW OF CURRENT AND POSSIBLE FUTURE USES
by
J G James
(The text of this Report was first published in the Journal 'Minerals and the Environment'
Vol. 2, No. 1, March 1980)
Any views expressed in this Report are not necessarily those of the Department of the Environment or of the Department of Transport
Transport Engineering Division Transport Systems Department
Transport and Road Research Laboratory Crowthorne, Berkshire
1980 ISSN 0305-1315
Ownership of the Transport Research Laboratory was transferred from the Department of Transport to a subsidiary of the Transport Research Foundation o n I st
April 1996.
This report has been reproduced by permission of the Controller of HMSO. Extracts from the text may be reproduced, except for commercial purposes, provided the source is acknowledged.
Abstract
1.
2.
3.
4.
.
6.
7.
CONTENTS
Introduction
Freight transport mode statistics
Major types of bulk freight currently conveyed in pipes
3.1 Water and sewage
3.2 Gas
3.3 Oil (both crude and refined products)
3.4 Coal
3.5 Ores
3.6 Clay and chalk
3.7 Other valuable minerals
3.8 Sand and gravel in maintenance and reclamation dredging
3.9 Aggregates
3.10 Mineral wastes
3.11 Concrete
Less common types of pipeline transport
4.1 Pneumatic conveying of granular solids
4.2 Pneumatic propulsion of capsules
4.3 Hydraulic propulsion of capsules
Other aspects of pipelines and conclusion
Acknowledgements
References
Page
1
1
2
3
3
4
5
6
9
10
12
13
15
16
19
19
19
20
22
23
23
24
(C) CROWN COPYRIGHT 1980 Extracts from the text may be reproduced, except for
commercial purposes, provided the source is acknowledged
PIPELINES CONSIDERED AS A MODE OF FREIGHT TRANSPORT: A REVIEW OF CURRENT AND POSSIBLE FUTURE USES
ABSTRACT
Pipelines are perhaps the least appreciated mode of freight transport. The unobtrusive distribution of many megatonnes of water, oil and gas in the UK annually is taken for granted and only the figures for oil appear in annual freight statistics. The transport of solids by hydraulic or pneumatic pipeline - either in free flow or packed into capsules - is technically more difficult and less common, but the practice is already well-established in certain specialised fields.
After a brief introduction to the statistics for various freight transport modes, the author reviews the current usage of pipelines for water, sewage, gas and oil, before examining at length hydraulic 'slurry' pipelines for a variety of minerals. The Report concludes with a brief note on capsule pipelines which, apart from small-bore in-house delivery systems, are still in the prototype stage. A bibliography of over 100 references is given.
1. INTRODUCTION
For at least two centuries the pros and cons of different freight transport modes have been hot ly debated. In the UK
until the end of the eighteenth century bulk freight, such as 'sea-coal ~ from Newcastle to London, travelled largely
round the coast in small ships. The canal boom of the late 18th and early 19th centuries improved inland waterway
facilities which were of particular value to the industrial midlands and shortened many routes considerably. In
early Victorian times the railway boom brought even more direct routes and much higher speeds. The railway
network grew rapidly and largely ousted canals until the mid-twentieth century by which time roads had begun to
rival railways as the dominant mode.
This simplified conventional view of transport trends overlooks the less obvious advance o f pipelines during
the same period. For various reasons current national transport statistics ignore all pipelines except the comparatively
recent trunk oil routes. The general public, and even most transport writers, take the vital water sewage and gas
networks for granted and forget that they have supplanted innumerable water-carts, 'night-soft' carts, coal-carts
and oil-shops.
Pipelines are obviously suited primarily to fluids but under some circumstances it is bo th technically and
economically feasible to convey solids through pipes. Granular solids may be blown along or pumped with water;
alternatively, solids of almost any sort may be packed into capsules to be swept along pipes by pneumatic or
hydraulic pressure. In the 1860s and again in the 1960s imaginative writers foresaw networks o f pipes, on the one
hand transporting bulk freight of all types across continents, and on the other hand delivering small packages to
every house. ,
The practical feasibility and economic viability of piping solids have been studied in most developed countries
over the last twenty-five years or so and this report comments on present usage particularly with regard to slurry
pipelines, many of which are now in operation. Before turning to these, however, the subject is introduced by a brief
review of existing freight transport modes and the types of freight (liquids and gases, as well as solids) which may
conveniently be handled by pipeline.
1
2. FREIGHT TRANSPORT MODE STATISTICS
Since World War 2 the UK, in common with most other developed countries, has published annual statistics of the
amounts o f freight conveyed by each of the major transport modes 1,2. Figure 1 presents these statistics graphically
to show the trends as reported, firstly in tonnes, secondly in tonne-kilometres, and thirdly in percentages of the total
tonne-kilometres. Because road freight transport is primarily used for short and medium journeys its share appears
somewhat smaller when considered as tonne-kilometres rather than tonnes but since the 1950s it has clearly become
the dominant mode. The most recent available figures, expressed as percentages of the total, are given in Table 1.
TABLE 1
Modal split for UK freight transport in 1976
Road
Rail
Coastal shipping
Inland waterways
Pipelines
Per cent of total tonnes
85.0
9.9
2.2
0.3
2.6
Per cent of total tonne-kilometres
67.3
16.2
14.0
0.1
2.3
It needs to be noted that the above statistics for waterways and pipelines are 'pessimistic': the former relate
solely to navigations under the jurisdiction of the British Waterways Board (ie they ignore rivers and the Manchester
Ship Canal for example 3) while the latter relate solely to major oil pipelines longer than 16 km and appear to include
only refinery products lines, not those carrying crude oil.
Reservations of this sort, due to non-uniformity in methods of gathering statistics, make international
comparisons even more difficult. Table 2 presents some examples from the United Nations Annual Bulletin for
Europe 4 to show the apparent diversity of freight transport practices.
TABLE 2
Modal spht for freight transport in selected countries in 1976, expressed as percentages of tonne-kilometres
Road
Rail
Inland waterways
Pipelines
UK
75.1
20.3
0.1
4.6
GFR
44.2
26.5
22.4
6.8
France
41.7
34.7
6.0
17.6
i Netherlands
29.5
5.2
56.7
8.5
GDR
22.9
68.1
3.2
5.8
USSR
7.6
72.5
5.0
14.9
USA
23
37
16
24
The UK figures in Table 2 differ from those in Table I mainly because the United Nations compilation neglects
coastal shipping. As might be expected, rivers and canals play a more important role in West Germany and the
Netherlands, while in Russia and East Germany railways remain dominant. USA national figures, added from another
2
source 5 for comparison, show a surprisingly low percentage of road freight but US statisticians gather only long-
distance inter-city traffic figures and omit the local urban and rural traffic which makes up the bulk of lorry usage.
These statistics also reveal USA as the major user of pipelines: this reflects the facts that USA consumes more
energy per capita than any other country and that oil is the primary source there. USA consumption of energy
doubled between 1950 and 1970 and it can be seen from Figure 2 that the reported pipeline usage also doubled.
The actual usage of pipelines in USA is even greater than these statistics show because (a) only the major inter-city
pipelines (longer than 50 kin) are included and (b) gas, which provides one-third of USA energy through a network
of over 2 million kilometres of pipes, is omitted entirely. The effect of recent and current changes in energy sources
on the UK transport pattern is discussed later.
3. MAJOR TYPES OF BULK FREIGHT CURRENTLY CONVEYED IN PIPES
3.1 Water and sewage
Before dealing with commodities more usually thought of as freight, reference must be made to water and
sewage because of the sheer magnitude of the quantities transported and the cost and complexi ty of their networks
which form the mainstay of the pipe industry.
In 1971 it was estimated 6 that total UK water sales amounted to 22 thousand million tonnes per annum
split as fol lows:-
direct industrial abstraction 22.7 per cent
Central Electricity Generating Board 55.0
public water supply 21.7
agriculture and miscellaneous 0.6
Presumably CEGB water, like the majority of industrial water supply, is abstracted directly f rom open-channel
waterways but the public water supply (amounting to about 5000 million tonnes) is almost entirely piped to the
users. For the most part it is then taken away by a secondary network of sewers which also deal with rainfall run-
off from paved and urban areas. Sewage is said to be 99.9 per cent water 7 and the two are frequently considered
as a joint subject.
Historically water and sewage were the first commodities to be conveyed by pipes in quantity: the length and
size of ancient Roman aqueducts and sewers made them world-famous. However in the UK the distribution of
water and the subsequent disposal of effluent and sewage was (with a few notable exceptions such as London 's
New River) a very local affair until Victorian times. In London for instance the early s team-pump-operated
waterworks merely raised water from the Thames, Lea and Ravensboume for distribution over a radius o f a few
kilometres. Sewage went on to the land or back into the rivers by the shortest path to nourish Whitstable oysters.
As London grew after 1800 it became necessary to go further afield for flesh water (to rural Fulham and
Hammersmith) and to introduce large reservoirs and cast-iron mains of unprecedented length and diameter. Much o f
the sewage was still taken away at night in armies of carts and fleets o f barges; in some foreign cities such as Athens
road tankers are still the primary sewage conveyors t o d a y . In mid-Victorian times Bazalgette finally installed
London 's great piped system with over 150 km of main interceptors discharging all sewage (after processing) into
the Thames well east of the city at Barking Creek and Erith (Figure 3). Other towns gradually followed suit and
thousands o f municipal waterworks and sewage works became established.
The increasing inadequacy o f natural waterways and canals to supply the required quantities at all times to
local storage reservoirs, and to .convey away the effluent, led to the installation of some notable long-distance
schemes: Welsh water for instance is piped to central England. In 1973, anticipating that the public water supply
would need to be doubled to 10,000 million tonnes annually by the year 2000, a scheme was published (Figure 4)
showing new major networks which would become necessary 8. These schemes will require about 600 km of
pipelines, mainly 1 to 2 metres in diameter, and 200 km of major carriers over 2 metres in diameter (and therefore
officially classified as tunnels).
In the mid-1970s the National Water Council was established to coordinate conflicting demands and one of
its first tasks was to improve the accuracy o f water and sewage statistics. It is now estimated that there exist
current ly over 500,000 km of public watermains and sewers of which probably over a quarter have a diameter of
300 mm or more. The current value of these pipelines is estimated at £26,000 million (one-third for water and two-
thirds for sewage). The required annual expenditure is estimated at £260 million, ie one per cent of the value 9.
This makes an interesting comparison with the UK public roads system which comprises 330,000 km and required
£276 million for maintenance in 1975.
If an average distance of say 10 km is assumed for piping the public water supply a total for 50,000 million
tonne-kilometres is obtained. If a similar figure is added to this for sewage the f'mal total is greater than that of all
UK road freight and thus, if water and sewage were considered as freight, the graphs in Figure 1 would be radically
altered.
3.2 Gas
After water and sewage the next greatest group of commodities, in terms of bulk transported, are the mineral
energy sources: coal, oil and gas. Present UK trends in the consumption of these are shown in Figure 5.
Historically, gas was Ftrst to be piped. Coal-gas production and its local distribution through underground
pipes followed closely behind the rapid development of waterworks and cast-iron water-mains in the early
nineteenth century. Relatively large district gasworks replaced individual-consumer plants soon after the start of
gas development and as early as 1821 cases were being brought against the London producers for destroying the
Thames fishing industry with their effluent. However there were no really long-distance gas pipelines in the UK
until recent times when natural gas began to be exploited.
In the early 1960s liquid natural gas was shipped from Algeria to Canvey Island on the Thames estuary and a
450 mm diameter pipeline was installed to carry it as far as Leeds. From the mid-1960s onward North Sea gas
supplies were tapped and a 500 km national network of high-pressure (up to 7 MN/m 2) 'transmission' pipelines has
now been created to deliver it f rom the coastal terminals to the existing medium and low pressure local 'distribution'
networks. Figure 6 shows how use of North Sea gas has grown while coal-gas production has dwindled almost to
4
zero. Figure 7 is a map of the high-pressure transmission grid: the diameters of these pipes range from 900 m m at
the coastal terminals to 450 mm in the west of England. The old medium and low pressure distribution mains have
also been extended to accommodate the new supply sources, their total length increasing f rom about 150,000 km
in 1960 to 220,000 km in 1977.
This increased use of natural gas (an.d of oil, discussed in Section 3.3 below) has led to significant changes in
freight transport patterns since less coal movement is needed either to feed local gasworks or as direct fuel for
factories and houses. A large proportion of coastal shipping and rail freight traffic, both greatly dependent on coal
customers, has thus been transferred to pipelines.
As already noted, transport statistics invariably ignore gas pipelines: this is possibly because the quantities
are commonly expressed in energy units, such as the British Thermal Unit (Btu) or the Therm (100,000 Btu),
rather than tonnes, and because problems arise in considering the bulk handled due to compressibility. To obtain
relative quantities 'coal equivalents' and 'oil equivalents' based on energy content are sometimes derived. Here the
oil equivalent has been used, taking 1 million therms as equivalent to 2300 tonnes of petroleum. This provides a
national annual consumption equivalent to 36 million tonnes. If an average distance of say 100 km is assumed
for its transportation, the transportation total may be taken as 3600 million tonne-kflometres. If this were added
to the reported oil pipeline tonne-kilometrage shown in Figure 1 the national pipeline freight total would be more
than doubled.
3.3 Oil (both crude and refined products)
As noted in Section 2 above, USA leads in the use of oil pipelines. There the economic advantage of pipelines
over railways or roads for delivering crude from rural oilfields to city-based refineries was realised in the 1860s.
The first long-distance (100 km) line was completed in 1875 and another of 180 km in 187910. The US oil
pipeline network has thus had over a century of development although the very long (over 1000 km) pipelines of
large diameter (250 to 900 mm) grew up only during and after World War 2. These last are usually not for crude,
but for transporting the end products from refineries to customers.
The larger the pipe diameter the more cheaply per tonne may oil be pumped. On the other hand, the capital
cost of a large pipeline is so great that it must be operated continuously for economic viability. To ensure a through-
put sufficient for continuous operation of a large-diameter pipeline it is now common practice for several companies
to share the cost and with modern technology it is possible for several different products to be simultaneously
travelling along successive lengths of the same pipe. The 'Colonial Pipeline' from Houston to New York (about
2500 km long and 900 mm decreasing to 750 mm in diameter) is said to contain over 100 batches at any one t ime
en route to about 200 delivery points along it 11. The US oil pipeline network now totals about 300,000 km although
it may be remarked that the gas pipeline network, not reported in US transport statistics, is even greater and
estimated to comprise 420,000 km of transmission lines, 1,000,000 km of distribution mains, and 700,000 km of
small-bore 'service' pipes to individual properties.
Unlike water and gas, oil will clearly never be piped directly to every individual consumer but it is possible to
envisage a situation where most local petrol stations, domestic heating-oil depots, and factories are pipe-linked.
In Europe indigenous coal has long been the main energy source and, except for the 880 km Baku-Batum
pipeline (in 1907 the world's first refinery products line), very few oil pipelines existed until World War 2. In
western Europe until very recently most oil was brought by ocean-going tankers from Africa, Asia or America to
coastal ref'meries, from which the f'mal products were distributed by road, rail or inland waterway. During and just
after the war a few strategic pipelines (such as the famous PLUTO under the channel) were installed and these
provided the nucleus o f the stiU-growing network of both crude and refined product lines. A map published in
197312 showing most of the major oil lines in western Europe is reproduced with a few additions in Figure 8.
the UK pipelines shown on this map are all for refinery products.
A new stage was entered when mammoth tankers were built after the Suez Crisis of 1956. These required the
creation o f deep-water terminals, and crude-oil pipelines then had to be installed to connect these with existing
refineries in the 1960s. Finally in the 1970s has come the exploitation of North Sea oil necessitating further crude
oil pipelines f rom the North Sea fields to new terminals. Figure 9 is a map of existing major UK pipelines for both
crude and ref'med products: also shown are a few long pipelines carrying liquid petroleum derivatives such as
ethylene and propylene to chemical works.
The crtide oil pipelines range in diameter from 300 to 900 mm, the refinery-product pipes from 150 to
400 mm, and the olefme lines from 150 to 250 mm diameter. In 1975, before North Sea oil really began to flow,
the UK oil lines were reported to total 2658 km in length and to convey about 30 million tonnes, half crude and
half refined products. Because the refined products lines are longer than the crude lines only one-quarter of the
5,322 million tonne-kilometres total oil-pipeline freightage related to crude.
Current statistics are less certain because of recent rapid changes in oil supply sources. After the 1973
financial crisis ref'mery output fell slightly and has since remained relatively static but the amount of crude oil
piped has probably increased. The tonnage of North Sea oil used in the UK, a mere 1 million tonnes in 1975, rose
to 12 million in 1976 and to 37 million in 1977. The larger part of this (20 million tonnes) came from the Forties
field (see Figure 9). The total length of major UK oil-pipelines must now be well over 3,000 kin.
The additional olefme pipelines total about 1,000 km and their individual throughputs range from about
50,000 tonnes to 300,000 tonnes/year. These therefore probably add only a few hundred million tonne-kilometres
to the overall freight total.
3.4 Coal
In most cases oil and natural gas are more cheaply won from the earth than the third great energy source, coal:
they are also more cheaply transported and are more convenient to use. Consequently, although coal is more
abundant globally its share o f the energy market generally decreased during the present century. Only in the 1970s,
with recognition o f the finiteness of mineral resources and 'energy crisis' forecasts was the decline in coal
product ion halted (Figure 5).
In some areas o f North America coal exigts in massive deposits from which it may be extracted by relatively
easy open-cast methods but even there the cost of transportation made it unable generally to compete with oil
in the major energy-consuming regions. Coal may be burnt at source to produce electricity and conveniently
6
distributed long distances in this secondary form by cable. However this is not particularly efficient and long before
the energy crisis cheap transportation of coal was seen as the key to any at tempt to arrest its declining usage. In
view of the great early success of gas and oil pipelines in the USA it was inevitable that the first major at tempts to
pump coal through pipelines over long distances were made there in the 1950s.
That small quantities of coarse solids (fish, nuts and oranges) would pass successfully through a centrifugal
water pump without blocking it had been demonstrated a century earlier at the Great Exhibition of 185i. By the
1860s centrifugal pumps were developed sufficiently for them to be used for hydraulic dredging where large
quantities of sand and mud had to be raised. At about the time of World War 1 G G Bell used a 50 hp Gwynnes
centrifugal pump to convey 100 mm lump coal from Thames barges to an electricity-generating station at
Harnmersmith through a 200 mm diameter pipeline 600 metres long. This comparatively short and simple pipeline
operated for only a few years: from 1913 to 1924 according to Bell or from 1919 to 1922 according to the power-
station records 13.
Meanwhile it had been realised that positive-displacement (piston or plunger) pumps can also pass solids with
water providing that the particles are time enough for the mixture to be considered as mud or sludge. Although they
cannot pass coarse solids, such pumps are capable of developing high pressures and this feature suggested the
possibility of pumping solids in the form of fine slurries over long distances. In 1889 an American, W C Andrews,
filed a US Patent (granted 1891) for conveying finely ground coal as a water slurry 'hundreds of miles' using
'force-punps' and he exhibited a model at the Chicago World Fair in 1893. He was followed by W T Donnelly
who applied for a new patent in 1904 (granted 1906) with particular reference to an improved arrangement for
feeding coal slurries 14.
The feasibility of long-distance coal pumping was taken up again after World War I , and in 1921 articles
were published on American schemes such as one to pump 7M tonnes per year o f fine anthracite about 300 km
from Pennsylvania to New York through a 350 mm diameter pipe 15. These plans came to nothing but the use of
short pipelines (up to a few km long) to send coal times from washeries to lagoons became common in the 1920s
and 1930s establishing the basic technology.
Renewed interest in the subject came following the growth of large oil pipelines in World War 2. In the 1940s
Bell proposed piping 2.5M tonnes of coal annually 200 km from the Midlands to London using 350 m m diameter
pipe in 16 km stages. However the great practical breakthrough came in 1950/51 when an experimental test-rig
and then a pilot-scale plant were built in America to back up a proposal to pump 1M tonnes o f time coal annually
about 175 km from Cadiz at one end of the State of Ohio to Cleveland power-station at the other. Virtually none
of the scientific data obtained from these trials (reported to have cost two million dollars) was published but the
technical and economical viability of the project was proved sufficiently for construction of the pipeline (250 mm
diameter) to be sanctioned and started in 1954. It was completed late in 195616, became fully operational in 1958,
and ran successfully until September 1963 when it was closed down because of altered economic conditions.
In 1958 it was reported that the Ohio pipeline had cost between 12 and 14 million dollars and that the cost
of coal delivery was forecast to be 1.60 dollars per short ton compared with 2.40 dollars by rail. Several conflicting
reports were published subsequently some of which gave the rail cost as high as 3 to 4 dollars but the true figures
are uncertain. At the time of closure it was reported that the pipeline cost had proved to be 2.50 dollars per ton
while the railway had slashed their tender to 1.90 dollars.
Since its operation had forced the railway companies to lower their freight charges substantially, the pipeline
was regarded as having been an economic as well as a technical success, and it was preserved to safeguard against
any future re-imposition of higher charges. On the other hand, the general lowering of rail freight charges which
it had brought about made the viability of several other pipelines which had been planned dubious: the rapidly
booming interest in coal pipelines slumped sharply as was shown by a review of papers on this subject (Figure 10) 17.
An additional check to the growth of US coal pipelines was the tactical refusal of railway companies thereafter
to grant prospective pipeline users wayleaves to cross over or under their tracks. Some inconclusive legislative
battles ensued which came to a climax in 1977 when a Slurry Pipeline Bill was tabled in the House of Representatives:
after considerable discussion it was thrown out in 1978 but the battle still continues to be waged 18. An important
factor inhibiting governmental decisiveness is the reliance by many railway companies on coal traffic for their
survival and their possible strategic value in the future. Of equal importance has been the objection by the States
concerned to the simultaneous 'export ' of their water as mere carrier liquid.
Since the Ohio pipeline only one other large example has been completed in the USA: this is the 440 km
long, 450 mm diameter, Black Mesa line, across a comparatively deserted stretch of Arizona to the Mohave power
station in Nevada. It has a throughput of over 4M tonnes/year and came into operation in 197019. Currently
several more are planned (some over 1,000 km long) and with the resurgence of coal as the major long-term energy
source the future of coal pipelines seems assured once the necessary legislation has been passed. Some of the proposed
lines are shown in Figure 11.
From time to time since the late 1950s several reports of proposed long coal pipelines in USSR and other
eastern European countries have appeared but it is doubtful if any have in fact been constructed as yet. However
there is a very extensive literature in Russian on the subject of hydraulic pipelines for coal and rock and it is clear
that hydraulic coal-hoisting and hydraulic mine-waste disposal are extensively practised, probably to a greater degree
than in any other country. In 1970 Traynis 20 referred to fourteen hydraulic coalmines, three of which had 10 km
pipelines conveying their product to power stations or metallurgical plant. Some of the literature has been translated
into English by American agencies particularly since 1976 when the US Bureau of Mines commissioned an extensive
study o f East European pipelines 20.
In the 1950s most western European research on hydraulic pipelines was carried out in France and the UK.
Two important symposia were held in 1952, at Grenoble in June 21 and at London in November 22. The latter was
held under the auspices o f the National Coal Board (NCB) which had commissioned research from the British
Hydromechanics Research Association (BHRA). Later in the 1950s the main initiative shifted to the primary
customer for coal, the Central Electricity Generating Board (CEGB), whose team built their own test rig and
then installed a 2 km trial line from Walton Colliery to Wakefield in 196323.
In the UK there are many large coal-ftred power-stations, individually consuming up to 5M tonnes of coal per
year and therefore potentially suitable for feeding by pipeline. However there are few single collieries capable of
supplying such an output and most stations are fed from several sources byrailways and/or belt conveyors. In the
1960s feasibility studies were made by CEGB for supplying at least two proposed new power-stations by coal
pipeline but these schemes were never implemented.
8
When the British Railways network was being pruned in accordance with the Beeching Report (1963) over
60 per cent of BR's freight tonnage was coal. It was improbable that any pipe-v-rail wayleave controversy could
seriously have arisen as in the USA since (a) the railways had been nationalised and (b) a special Pipelines Act
had been passed in 1962, although primarily intended for oil and gas pipelines. Nevertheless, UK research on coal
pipelines largely ceased and from 1963 onward little can be traced until after 1970, in which year BHRA held the
lust of its international symposia on 'Hydrotransport '24. This coincided with a worldwide upsurge in environmental
consciousness, awareness of limitations in supplies of conventional mineral energy, and renewed interest in coal.
At this time the Transport and Road Research Laboratory also began to investigate the potential uses of pipelines.
In 1974 NCB resumed coal pipeline research although, in common with most recent studies in this field, the main
emphasis has been on hydraulic hoisting and short-distance conveyance to washeries rather than long-distance
transportation.
In countries where long-distance coal transportation by pipeline has been seriously examined one of the major
subjects for debate has been the relative economic efficiencies of rail and pipeline, and relative efficiency o f either
of these methods compared with generating electricity at the coalfield and transmitting this by cable. Each of the
three interested groups have produced figures to support their case and the matter seems likely to remain inconclusive
until several coal pipelines have been in existence for several years so that their true economic performance and
energy intensiveness may be established.
In the UK pipelines will probably be considered when new massive coal seams come to be exploited although
the extensiveness of the existing railway network will provide strong competition. In the long term it is possible
that coal imported from yet undeveloped sources in the third world could require pipelines running inland from
deep-water ports analogous to the crude oil pipelines.
3.5 Ores
In the comparative lull of interest in slurry pipelines following closure of the Ohio coal line in 1963
support was sustained by metal-smelting industries. In Japan and USA particularly, steel production underwent
great expansion with the result that the amount of ore shipped in bulk from less developed countries increased
remarkably (from 40 to 240 million tonnes) between 1960 and 197025. This growth also continued into the
1970s 26.
More than half of the ores supplied for smelting nowadays are in the form of 10 mm pellets made from finely-
ground concentrates. When extracting ores from deposits in virgin territory, particularly mountainous jungle, it is
easier and cheaper to instal grinding plant at the mine and to pipe the frees to a coastal pelleting plant than to build
a railway or road to convey lump ore. A pipeline of about 150 mm diameter can convey a million tonnes o f fines
per year and requires manning only at the terminals. In several cases such pipes have been cheaply slung across
spectacular gorges by cable. A dozen notable ore pipelines are listed in Table 3.
TABLE 3
Notable slurry pipelines transporting ores
l eng th I Diameter Annual throughput Date first Reference Site Ore (km) [ (mm) (Mt/year) operated
Creighton, Ontario
E1 Salvador, Chile
N. Stradbroke, Australia Savage River, Tasmania
Waipipi, New Zealand
Bougainville, Papua
West Irian, Indonesia
Hopa, Turkey
Pena Colorada, Mexico
Pinto Valley, Arizona
Las Truchas, Mexico
Ponta Uba, Brazil
Kudremukh, India
Ni/Cu
Cu
Ti/Zr Fe
Fe
Cu
Cu
Cu
Fe
Cu
Fe
Fe
Fe
"12
23
6
85
9
27
111
2x62
48
18
25
400
71
200
150
150
225
200+300
150
100
125
200
100
250
500
400+450
0.5
0.3
0.3
2
1
1
0.3
0.5
1.5
0.3
1 to 3.5
7 t o 12
3 to 7.5
1951
1959
1962
1967
1971
1972
1972
1973
i974
1974
1976
1977
due 1980
28
29
3O
31
' 32
33
34
35
108
109
110
111
In a few cases the slurry is shipped out in unpelletised form. One firm has developed a technique (the Marconaflo
process) for loading ships with slurry via pipelines to floating terminals and subsequently unloading them through
similar terminals by re-slurrying the settled ore in the ships' holds using rotating water jets, either installed in the
ships themselves or else lowered in by crane from the wharf. The Waipipi scheme listed in Table 3 provides a typical
example o f a loading installation. An elaborate unloading installation is at the Hirohata works in Japan 27.
During the 1960s and 1970s iron and steel production in the UK has declined rather than grown but we still
import about 15M tonnes of iron ore to supplement some 4M tonnes of native ore annually. A feasibility study
for an ore slurry terminal at Hunterston was made a few years ago but shelved. Almost all of the imported ore is
provided to. the UK as pellets and is unloaded by traditional grab methods.
No long pipelines carrying gold and silver bearing alluvium are known (apart from waste tailings lines,
discussed later) but mention should be made here of the fact that the technology of hydraulic mining was originally
developed in the mid-19th century goldfields o f Australia and America. Manual washing and panning soon gave
way to sluicing with mechanically-operated monitors and massive concentration plant, transportation by open-
channel flumes being common well over a century ago.
3.6 Clay and chalk
In the UK several major pipelines have been built to convey clays of various sorts and also chalk which,
blended with clay, forms the kiln-feed for cement manufacture.
Clays, by definition, are sedimentary rocks o f very small particle size. For most purposes they l~ve always
been processed with added water and they are obviously suited to pipeline transportation. Hydraulic mining of clay
was an early development from hydraulic mud-dredging, and short pipelines in china clay workings are among the
10
earliest known examples. Currently in Cornwall and Devon many millions of tonnes of china clay are annually
hosed from pit faces by hydraulic monitors, hoisted through pipes to washeries, and then pumped around ret-ming
and classifying processes. These in-house pipes are generally not more than a few hundred metres long but at least
two major examples have been reported. One carries about a million tonnes per year of refined china clay 18 km
from Trebal ref'mery to Par drying plant 36. The other is a 20 km network of pipes gathering some 2 million tonnes[
year of micaceous residues from several plants and conveying them to disposal lagoons 37. China clay is usually
shipped out dry but in 1978 additional shipping of china clay in slurry form began from Par harbour 38, thus
eliminating expensive drying.
Major china clay pipelines also exist in Georgia USA. One, dating from 1959, is 8 km long and 300 mm
diameter: two others are 18 and 26 km long and 200 mm diameter, all conveying over 1 million tonnes/year 39.
In south-east England a different type of clay is used for cement making. This industry was originally
established on the south side of the Thames using river mud mixed with the local chalk. In comparatively recent
times the numerous small manufacturing plants have been amalgamated at Northfleet where the kilns have an
output capacity of 4 million tonnes/year requiring 6 million tonnes of chalk and 1.6 million tonnes of clay. This
last is brought via an I 1 km pipeline 350 mm diameter from Ockenden, Essex to Swanscombe, Kent with a 1 km
section under the Thames. At Swanscombe the clay is blended with local chalk and the mixture then pumped a
further 3 km to the Northfleet works 40.
Chalk is a free-grained, relatively soft, form of limestone which is readily broken down by agitation in water
to form a creamy slurry.. Its suitability for slurry pumping has led to the installation of several pipelines by cement
manufacturers, the longest in the world being in the UK. One of the earliest such pipelines is said to have been
build in the 1940s at Montebello in Columbia, Central America, and to be 27 km long, but little is known about it.
In 1962 a 10 km pipeline was installed in Trinidad for a subsidiary of the British Rugby Portland Cement Co Ltd 41.
The success of this then led the parent company to construct in 1964 a pipeline to convey about 1.5 million tormes/
year of chalk 92 km from quarries at Kensworth, Bedfordshire, to their cement works at Rugby, Warwickshire,
with an additional spur of 15 km from Rugby to another plant at Southam 42. The pipe is 250 mm diameter
and it is reckoned that its throughput is capable of being increased to 4 million tonnes/year if required: at present
it only operates intermittently. The Rugby pipeline was the first to be sanctioned under the 1962 Pipeline Act.
In 1971 a 28 km limestone pipeline (180 mm diameter: 1.5 Mt/year) was completed from a quarry near
Vallecito to a cement works at San Andreas, in Calaveras County, California 43. Studies have been made for other
such lines in Australia but as yet none have been built.
An important point about pipelines of this type is that they are not merely a convenient substitute for
conventional modes of transport: they enable the end product to be made near the consumer rather than at the
raw material source. The radius of final distribution using lorries is thereby reduced, with consequent savings in
both energy and cash. This concept might be applicable to other industries such as brick-making, with clay being
piped instead of moving the bricks, although the siting of works near the consumer could provide environmental
problems.
11
3.7 Other valuable minerals
Slurry pipelines are used to transport a variety of other minerals. Long established American examples include
those carrying Gilsonite (a form of natural rock-asphalt) and phosphate rock.
Gilsonite is mined below ground hydraulically and is thus produced in a form very suitable for pumping.
From the mine'at Bonanza, Utah, it is sent to a ref'mery at Grand Junction, Colorado where fuel-oils are extracted.
This pipeline, operated since 1957, is 116 km long, 150 mm diameter, and conveys about 0.5 Mt/year 44. Phosphate
rock is extensively mined in Florida where hydraulic techniques are said to have been used since about 1900. At
several mines pipes up to 500 mm diameter are used to convey the material at rates up to 2000 m3/hour over
distances up to 8 km to the processing plants. This material, termed 'phosphate matrix', is a variable mixture of
clay and sand with pebbles up to 150 mm diameter requiring pumping in several stages by centrifugal pumps 45.
In Canada several feasibility studies have been made on the piping of potash of which over 10 Mt/year are
produced in Saskatchewan. These pipelines would run either about 1500 km to Vancouver for shipment to USA
or else in a direct line across the border but so far none has been built. A feature of this system would be that the
carder "water' would in fact be a supersaturated solution of KC146. Other Canadian products for which major
pipelines studies have been made are wood chips as feed for the paper industry 47, sulphur (1000 km from Alberta to
Vancouver for shipment) 48, and gypsum.
In South Africa uranium-bearing pyrites concentrate is pumped about 5 km through 125 mm diameter pipes.
In NE England a 15 km pipeline has been considered for conveying dolomite to the coast at Hartlepool for
manufacture o f magnesia by reaction with sea-water. By using sea-water as the carrier liquid, the two or three hours
spent in the pipeline could reduce the processing time necessary on arrival. Several hypothetical schemes for
pumping slurries with additives to promote chemical reaction en route have been mooted: one possibility is the
digestion o f woody organic matter ('biomass') as part of a conversion process to paper pulp or alcohol.
Soluble chemicals are among the most obvious for pipelining and the earliest mineral system of importance
was built in Bavaria in 1616/19 to convey brine from Reicherthall to Traunstein where fuel for evaporation and
purification was more plentiful. This line, containing 31 km of 80 ram-bore wooden pipes (plus lead for the
highest pressure points), operated for nearly two centuries until increased production was required. In 1807/17
it was replaced by a larger-bore pipeline and incorporated into a system over 100 km long, from Berchtesgaden via
Reicherthall to Traunstein and Rosenheim. In this the riatural brine springs were supplemented by specially-dissolved
rock salt, which hitherto had been conveyed by horse and cart. Over a dozen pumping-stations and large quantities
of cast-iron pipe were required for this classic installation.
Ammonia is also commonly handled in solution. A notable example of long-distance pumping is the recently
completed 800 km pipeline from Gorlovka to Odessa to provide ammonia as fertiliser for Ukraine farmlands. This
is planned ultimately to be three times this length and to have an annual throughput of 2½ million tonnes.
12
3.8 Sand and gravel in maintenance and reclamation dredging
Vast quantities of sand and gravel are dredged annually from shallow waters, harbours and rivers, some o f
which is pumped several kilometres by hydraulic pipeline.
Suction dredging with centrifugal pumps originated in the 1850s but it only came into widespread use in the
present century. Originally devised for deepening shipping channels at port entrances, it was customary until
comparatively recent times merely to dump the dredged spoil further out to sea. Nowadays it is common to place
some or all of the spoil, if its properties are adequate, on selected sites to reclaim coastal land. If the material is
of good quality it may be more profitably sold as aggregate for making concrete etc. Thus from simple 'maintenance
dredging' have grown new industries of 'reclamation dredging' and 'aggregates dredging' which are sometimes carried
on independently as the sole process. An extreme case is Japan where in 1975 127 million cubic metres were
dredged for land reclamation and harbour wharf extension compared with a mere 1.2 million for maintenance
dredging.
One hundred and fifty worldwide examples of dredging partly or wholly involving reclamation were analysed
by Herbich and Hubbard in 197749. They found that 39 per cent arose from regular maintenance, 24 per cent
from specific improvements to harbours and channels, and 20 per cent from creation of new harbours or channels.
The major uses of the reclaimed land were industrial and commercial (46 per cent), and beaches or wildlife reserves
(26 per cent).
From the scattered literature 50 typical examples are listed in Table 4. Table 4a presents the outstandingly
large reclamation projects, each involving the use of 100 Mm 3 or more of material (excluding spoil dredged but
merely dumped at sea): these jobs continued over many years and utilised numerous large dredgers simultaneously
(up to twenty in one case). Other very large schemes not yet realised include the construction o f new islands in
25m deep water in the North Sea (eg 1000 hectare islands requiring 250 Mm 3, proposed 1972), and the Maplin Sands
scheme intended primarily for a new air and sea port (7300 hectares, requiring over 250 Mm 3, shelved 1974 after
several years debate).
Table 4b lists some lesser examples which were nevertheless major construction jobs by normal standards.
These were mainly brought about in connection with the creation of new deep-water ports.
Lastly Table 4c lists some 'beach nourishment' schemes which range from the restoration of eroded areas of old
beaches to the creation of totally new ones either for coastal protection or for pleasure purposes, usually both. The
quantities involved in this type of work range typically from 0.5 to 5 Mrn 3 although two jobs involving over 10M are
listed. A third large scheme was a proposal made in 1974 to restore 16 km of Miami beach using 10 Mm 3 but it is not
known if this was implemented. The large Hook of Holland scheme listed was a special case involving major coastal
protection. In the pioneering Los Angeles scheme of 1947 the sand was obtained from inshore sand-hills by sluicing
with monitors but this is not typical. In most schemes the sand is suction-dredged off-shore and shipped to the site.
The hopper dredgers used may themselves be capable of pumping the material ashore via a floating pipeline but
commonly they merely deposit it in shallow water just off-shore. From there one or more secondary dredge-pumps
pump it along the shore via a pipeline which is gradually extended. The diameter of pipes used here ranges typically
from 250 to 900 mm but in the larger reclamation schemes listed in Tables 4a and 4b the pipes are rarely less than
750 mm in diameter and may be over 1000 mm.
13
a.
TABLE 4
Some reclamation-dredging contracts involving pipelines
Extremely large schemes
Site
Fort Peck Dam, USA West Amsterdam, Holland West Rotterdam, Holland Antwerp, Belgium Fos (Marseilles), France Chiba Prefecture, Japan
Dates*
1933-39 1945-67 1947-68 1957-72
1960s 1960s
Approximate quantity
(Mm 3)
100 100 450 100
Approximate area
(hectares)
8000 5000
13000
Maximum pumping distance (km)
11 12 6
* Note. At all of these sites except the first work still continues: the last date cited merely represents the date when the figures given were reported.
4b. Other major schemes
Hiroshima, Japan Okayama, Japan Rainham, UK Kingston, Jamaica New York, USA Zoetermeer, Holland Sydney, Australia Saldanha, South Africa Teesside (Seal Sands), UK Honolulu, Hawaii Ghent, Belgium Singapore Airport Memphis, Tennessee, USA* Port Rashid, UAE Abu Dhabi, UAE Dubai, UAE Jubail, Saudi Arabia Dammam, Saudi Arabia
1960s 1960s 1961- 1963-
1963-75 1970- 1971-
1973-76 1973-74 1973-75 1975-79
1976-- 1977
1967-72 1 1970-78 1976-79 1975-79 1975-79
over 15 40 30
8 12 28 10 15 48 41 10
about 50
20 45
720 1370 200
over 550
120
250 310
750
I t ; m
3
12
2
8
4 10
* Note. At Memphis the material was pumped example of this type of application known.
4c. Beach improvement or creation schemes
directly into place as Fdl for a new highway: this is the largest
Los Angeles, Calif, USA Nordemey, Germany Norfolk, Na, USA Sea Girt, N.J, USA Monte Carlo, Monaco Redondo, Cal, USA Treasure Island, Fla, USA Pompano, Fla, USA Goeree, Holland Copacabana, Brazil Bournemouth, UK Hook of Holland PortobeUo, UK Monaco Carrara, Italy Scheveningen, Holland Kirra, Australia Corpus Christi, Tex, USA San Diego, Cal, USA
1 9 4 7 - 4 8 1951-52
1962- 1966
1966-67 1968 1969 1970
1969-73 1970
1970-75 1971 1972 1972
1972-73 1975 1975 1977 1977
11 1.8 3 0.2 0.1 1 0.6 0.8 4.5 3.5 1.5
19 0.2 5
0.5 0.4 0.5 5
15 10
4O
100 15 22
20
6 5 1.2 0.7
0.3 0.7 2.5 6.5 4.2 2 3.5 1
7
3
10
14
3.9 Aggregates
After water and fuel, the materials produced and transported In greatest quantities in the UK are sand gravel
and crushed rock, used mainly as aggregates in the building and road construction industries. This is shown in
Figure 12 which compares trends in production and consumption of aggregates with trends for other materials.
Despite the recession since 1973 the annual total of sand gravel and crushed rock produced in the UK is still over
200 million tonnes.
In the last twenty years a noticeable change in the pattern of production has occurred, primarily due to
demand in SE England, the most concentrated construction area. There is no hard quarryable rock here and it was
largely dependent on the output of sand and gravel from local shallow deposits until the construction boom of the
1960s accelerated the depletion of workings with the necessary planning permission. The obvious alternatives were
crushed rock brought from further afield (mainly Mendip limestone or Leicestershire 'granite') and marine gravel
dredged from the North Sea. Crushed rock had always been brought to London in relatively small quantities for
special purposes and small-scale dredging of aggregates had begun in the 1920s for use in coastal towns.
Whereas a typical Home Counties gravel pit has deposits a few metres thick and produces a few hundred tonnes
per day despatched by lorry, a modem limestone quarry - perhaps a hundred metres deep - may despatch a dozen
1000-tonne train-loads per day and produce over 5 million tonnes per annum. Equally efficient, a modern hopper
dredger can suck up a 5000-tonne load of sea-bed gravel and discharge it within a few hours. In the 1960s, integration
of the rival crushed rock and gravel industries had not progressed far and great competition ensued 51.
Both types of operation require large capital investment and in the last few years the crushed-rock industry
has been particularly assisted by government grants (made under Section 8 of the 1974 Railways Act) to establish
suitable railheads. By transferring heavy freight which might otherwise be carried by lorry onto rail, and by
removing land-intensive gravel workings from the London area, this encouragement of crushed rock movement is
seen as environmentally beneficial.
No similar financial assistance has been granted to the marine aggregates industry to establish coastal and
riverside wharves, and the exploitation of marine deposits has been restricted by the conflicting requirements of
fisheries, shipping lanes and the owners of submarine cables or pipes. Nevertheless the growth of this industry,
which invested heavily in new dredgers in the 1960s, has been maintained to some extent by exportation of part
of its output to the continental countries: some of these are equally short of crushed rock and there are few good
gravel deposits under the eastern half of the North Sea.
Figure 13a gives the official UK production figures 52 although it is cemmonly believed that the total amount
taken from UK waters is higher due to extensive unlicensed dredging 53. For comparison, the annual figures for
aggregates rail-hauled to SE England 54 are plotted in Figure 13b. This rail traffic currently forms about half of the
reported total tonnage of freight in BR's 'Earth and Stone' category which also includes glass-making sands, ballast
etc.
15
Following a review of the problems associated with the growing tonne-kilometrage of aggregates transport in
1971 the Transport and Road Research Laboratory formulated proposals for research into the possibility of using t
pipelines. Their relative unobtrusiveness made them appear attractive ~.f the technical and economic difficulties of
conveying comparatively large particles did not prove to be insuperable. Obviously their use would be limited, but
several possible applications could be identified such as:-
i) Extending the distribution range of marine aggregates with pipelines running inshore from wharves.
~) Delivering aggregates by pipeline from barges in the Thames to replenish selected gravel pits which are now
worked out but which are well-sited as permanent local redistribution centres.
iii) Transference by pipeline of aggregates won from pits or quarries located in environmentally sensitive areas to
screening and despatching plants sited elsewhere.
iv) Transport of aggregates by pipeline from new super-quarries located in remote (and therefore unobtrusive)
areas to coastal wharves for despatch by sea to the south-east or the continent.
The government's Advisory Committee on Aggregates (the Verney Committee) was set up in 1972 largely in
response to environmental pressures, and this recommended inter alia that pipeline research should proceed 55.
In addition to initiating and maintaining a review of pipeline usage (of which this report provides a partial
summary), TRRL commissioned reviews of existing practice in hydraulic-slurry transportation and pneumatically-
propelled capsule pipelines, and embarked on practical research in both of these fields in 1974. The research will
not be discussed here but it may be noted that the first report on conveying aggregates up to 50 mm in size
hydraulically has appeared 56, and the TRRL pneumatic capsule pipeline research programme (which involved
construction of a 0.5 km test loop of 610 mm diameter pipe) is largely completed.
A few feasibility studies have been made but as yet there are no aggregates pipelines in the UK apart from
existing short lengths within the workings of sand and gravel pits which employ suction-dredging methods.
Probably the longest of these is the 0.5 km sand pipeline which has been operated for over 25 years by
Marley Tiles Ltd at Poole, Dorset: this is 150 mm diameter and handles between 100,000 and 150,000 tonnes per
annum (weekday working only).
3.10 Mineral wastes
Vast quantities of mineral wastes arise as residues from collieries and china clay works, slags from metal
smelting, and ash from coal-burning power stations. Since the 1950s the Transport and Road Research Laboratory
and the Building Research Establishment have studied possible applications of such wastes in place of specially-won
aggregates for the construction industries 57'58. A joint report was contributed to the Verney Advisory Committee
on Aggregates in 1972 and subsequently published 59. Following the UK lead an international survey has been
published by an OECD committee 60.
The major mineral wastes in the UK are listed in Table 5.
16
TABLE 5
Approximate quantities of major mineral wastes in the UK
Type
Colliery spoil*
Power-station ash**
China clay waste***
Slate waste
Spent oil shale
Iron and steel slag
Quantity already existing
(Mt)
3000
Hundreds
Current annual production
(Mt)
50
10
300
300
300
under 50
20
1
0
10
Current annual usage (Mt)
5
5
1
negligible
under 5
10
Notes: * At some collieries each torme of coal raised is accompanied by a tonne of spoil.
** At a power-station burning 5 Mt/yr of coal, 1 Mt/yr ash may be produced.
*** At some pits for each tonne of saleable clay, 5 tonnes of sand, 1 tonne of stony waste ( ' s tent ' ) and 3 tonnes of unusable clay and mica may be produced.
Iron and steel slags provide valuable aggregates and demand now exceeds supply, but for all other wastes the
annual usage is only a small proportion of the output. Most attention has been directed towards colliery spoil,
power-station ash (sub-classified into 'pulverised fuel ash' and 'furnace bo t tom ash'), and china clay waste, the
outputs of which are continually increasing. All three materials have a variety of potential uses ranging from simple
fill to the manufacture of aggregates or building bricks but the cost o f transportation f rom source to consumer
prohibits much further increase in.their exploitation. Consequently these materials continue to be stockpiled in
heaps or dumped in lagoons as near to their sources as practicable. Already over 10,000 hectares o f land are
estimated to be covered with colliery spoil heaps and about 1000 hectares with china clay waste.
Pulverised fuel ash (pfa) is of particular interest here since it is a fine-particle waste (median size 0.1 m m or less)
which has long been removed from power-stations as a slurry in water. Considerable quantities are sold as cement
additives, converted into building blocks, or put to other construction uses; but where output outstrips demand
disposal is by stockpiling (as at Gale Common in West Yorkshire) or more commonly by lagooning. In the latter
case the ash may still be gainfully employed by piping it to fill disused mineral workings as at Peterborough, or to
reclaim new coastal land as at Longannet on the Firth of Forth. At Peterborough over 2 Mt/yr f rom three power-
stations is being absorbed and eventually over 250 hectares of old brick-clay pits will have been returned to arable
land use 61. In the Longannet scheme the ash from two power-stations is piped into bunded lagoons of f the north
shore of the Forth to create 160 hectares of new grazing land. These ash pipelines are about 500 m m diameter
and up to 13 km long.
About half of the china clay waste consists of white sand of about 1 mm median diameter. This too might be
pumped distances up to about 10 km using methods similar to those of the dredging schemes described earlier in
Section 3.8. Unfortunately, since this waste is located entirely in Cornwall and Devon, the quantities which can be
absorbed locally are very limited. A study of the possibility of conveying it to SE England by various transport modes
was made in 197262 but the cost was shown to be prohibitive without subsidy. Stockpiling therefore continues
17
although planning permits now require ultimate landscaping and grassing of the tips. If for environmental reasons
cessation of tipping should be required in the future, the cheapest solution to the disposal problem could be to pipe
the sand to the coast and transport it by hopper barge for selected beach improvements. The material has a grading
very similar to that of the marine sand used to replenish Boumemouth beach and its light colour is not unattractive.
Following this suggestion, details for a trial beach at Portmellon were planned by Hydraulics Research Station in
1972 but the scheme was never implemented 63.
Colliery spoil is recognised to provide the most pressing problem, partly because of the enormous output,
which increases annually as poorer seams are worked, and partly because of its more widespread distribution
nationally, much in environmentally sensitive areas. Since the Aberfan disaster, colliery-spoil tips are made flatter
and sloped more gently but this safety precaution results in greater coverage of land. In 1974 the exemption which
many collieries had from close planning controls was withdrawn and, particularly in some parts of Yorkshire,
provision of future tipping space is causing some concern.
The involuntary fluidisation of the Aberfan tip in 1966, due to natural water percolation, immediately suggests
that such materials (largely composed of soft shales and mudstones) are well-suited to transportation by hydraulic
pipeline and this was one of the considerations which led to the original programme of research on pipeline transport
at TRRL. The first experimental results have already been reported in reference 56.
The National Coal Board has recently started important practical research in this field by constructing a pilot
pipeline (250 mm diameter and 1.7 krn long) to dispose of 200 Mt/hr of spoil from Horden colliery on the Durham
coast 64. In 1978, its first year of operation, about 0.2 Mt were pumped through it. Long-term prospects are the
possibilities of using colliery spoil like power-station ash for filling old mineral workings and for coastal land
reclamation. Some small projects have already been carried out and several proposals for very large reclamation
schemes have been examined includi.ng Maplin (1973:400 Mr), Spurn Head (1974:1000 Mr), and Pyewipe Flats,
Grimsby (1978:80 Mt65), although these have not all necessarily proposed to use pipeline transport.
Similar schemes have also been proposed for Scotland, to dispose of both colliery spoil and spent shale from
the defunct shale-oil industry. Some old oil-shale tips contain over 10 Mt each. For the most recently proposed
scheme 30 Mt of such material from tips between Edinburgh and Grangemouth is to be used to reclaim 615 hectares
of coastal land at Grangemouth. From consideration of various modes of transport it has been concluded that
hydraulic pipeline is cheapest and most efficient. As planned, the main pipeline for this scheme would be 10 km
long 66.
Pipelines are well established in the mining industry for conveying a great variety of free residues ('railings')
to disposal lagoons and a world review of tailings-disposal practices was recently made by Down and Stocks 67,68.
In South Africa several large pipelines for handling gold-mine tailings have been reported: one 35 km long conveys
1 Mt/yr and other shorter examples convey several Mt/yr. The longest reported railings pipeline is in Japan,
conveying copper-mine tailings 70 km 69.
The idea of pumping tailings and other mine spoil down the shaft to back-fall mine workings was exploited in
Silesia over 75 years ago 70 and today this has become a recognised branch of slurry-handling technology 71.
However these pipelines are invariably short in-house installations and do not warrant further mention here. The
18
converse operation of hoisting minerals hydraulically from mines has already been mentioned but another variant is
the hydraulic removal of tunnelling spoil in road or railway construction. A 150 m m diameter pipeline was used to
remove over 100,000 tonnes of spoil during excavation of the first Dartford-Purfleet tunnel under the Thames in
the 1950s and a similar line would be suitable for removing the chalk from the Channel tunnel if its construction
goes ahead. Such water-borne chalk may be used either for cement or land-fdl: in 1979 200,000 m 3 of dredged
chalk were pumped to reclaim 6 hectares at Ramsgate. Hydraulic removal of tunnel spoil is actively under develop-
ment in Germany and USA 72 and its use is expected to spread because of the convenience and safety of a pipe
compared with trucks or belt conveyors in conjoined spaces.
3.11 Concrete
Concrete is often conveyed from site mixer to placement area by pipeline 73. However only very limited
distances are practicable because of the high viscosity of the material. Pumping is inevitably done at a comparatively
low velocity and, even if several stages were used to extend the distance, a secondary constraint arises because of
the limited handling time available. Concrete was reported to have been pumped 420 metres on one job but it is
unlikely that this has been much exceeded 74. In the case of concrete therefore, piping can hardly be regarded as a
mode of transport: for longer distances belt conveyors or ready-mixed concrete trucks have to be used.
4. LESS COMMON TYPES OF PIPELINE TRANSPORT
So far this review has dealt with conventional single-phase flow pipelines for liquids and gases, and with the less
familiar but well-established two-phase flow pipelines for conveying particulate solids as slurries with water.
Other methods of conveying solids along pipes include (a) 'air slurries' or pneumatic conveyance of particulate
solids, (b) movement of solids as compressed slugs or packed into capsules blown pneumatically, (c) slugs or capsules
moved hydraulically, ie with a liquid carrier. So far these methods have only achieved limited or pilot-scale
application.
4.1 Pneumatic conveying of granular solids
Granular materials may be blown or sucked along pipes as in the familiar processes of sand-blasting or vacuum-
sweeping. On a larger scale pneumatic conveying was used to move materials around processing plants early in
the 20th century and it is now common in certain industries, eg for in-house handling of grain, pelletised plastics,
cement and many other powders. Pneumatic loading and unloading of ships holds and silos is also widely
practised. An extensive literature and text books are now available 75.
Lump coal is commonly delivered from lorry to bunker in the UK by blowing it through a flexible hose 76.
In the early 1970s this technique was extended to hoist coal 100 m from a Canadian mine and in 1977 an even larger
installation began operation at Shirebrook colliery in the UK. In the latter system 25 m m run-of-mine coal is
blown at the rate of about 60 t/h up a 300 mm diameter vertical pipe 326 m long and then 54 m horizontally 77.
Pneumatic conveyance is also used for removing domestic refuse from large blocks of flats (eg Lisson Green,
London, 1972) 78 and it has been proposed to extend this practice to whole estates and even towns. A test-rig was
built at the Building Research Station in the early 1970s to obtain practical data and the design know-how obtained
is now being commercially marketed 79.
19
In 1971/72 a feasibility study was made for conveying daily 1500 tonnes of London's refuse 64 km from
Hendon to the Bedfordshire brickfields by various methods, including water slurry and 'air slurry' pipelines. The
latter was concluded to be barely practicable and more expensive than any other method 80.
The conclusion from the London-Bedfordshire study was in agreement with the findings of most other
investigators regarding long-distance applications of pneumatic conveying of discrete solids (as opposed to capsules).
It has been concluded generally that power requirements are high and that closely-spaced booster pumps would be
necessary. However this viewpoint has recently been challenged in lllinois by Professor Soo and his colleagues 81 .
They have concluded that, by carefully optimising flow conditions to obtain the minimum practicable velocity,
and b y using a 'telescope' pipe of gradually increasing diameter, the power requirements might be reduced to as little
as one-fiftieth o f that calculated in previous US government-sponsored studies. For distances up to 8 krn Soo typically
envisages 50 mm coal travelling at velocities up to 45 m/s, but for very long distances he advocates using coal no
larger than 6 mm with veolocity reduced to between 16 and 20 m/s. Proposed pressure is typically about 10
atmospheres. A 6 km pilot plant has been designed but not yet built. It is notable that Soo makes no mention
o f the major problems of coal size degradation en route and pipe-wall wear which have figured largely in other studies.
Useful data on these points are emerging from the Shirebrook hoisting scheme but at present the use of this form
of conveyance over distances long enough for it to be considered a proper transport mode seems dubious.
4.2 Pneumatic propulsion of capsules
The lethal dart-blowpipe and its toy derivative, the pea-shooter, ate of great antiquity. More elaborate uses
o f pneumatic power were investigated by Hero of Alexandria ( ls t century AD) and Papin in France (late 17th and
early 18th centuries): In 1799 and 1800 a London engineer, George Medhurst, patented forms of compressed air
engines for "driving carriages without the use of horses'. From there he went on to develop in pamphlets (1810 and
1812) the idea o f using stationary compressors to blow mail packets at high speed through small-bore pipes and even
wheeled freight trucks and passenger-carriages through 2 m diameter tubes.
Medhurst was followed by John VaUance of Brighton who patented such a system in 1824. He also issued
pamphlets over the next decade and actually built a demonstration length about 50 m long x 2 m diameter although
the 3 km/h achieved fell somewhat short of the 100 to 200 km[h anticipated by Medhurst.
For the next half century writings about pneumatic transport systems proliferated, particularly in connection
with the 'atmospheric railways' so extensively tried in the 1840s. In these, full-sized railway trucks were propelled
along not inside pipes but by being connected to a 'piston' located in a modest-sized pipe at track level. The air was
exhausted from the pipe so that operating pressure was less than one atmosphere. Some of these systems operated
commercially for several years, eg St Germain (1847-60) and Dublin (1844-54) 82.
Partly because of difficulties in maintaining an adequately air-tight seal between the truck and the piston there
was a return of interest to the simpler idea of smaller containers within pipes. In 1848 a 1 m diameter 'tubular
railway', presumably pneumatic, was proposed to convey coal 144 km from Port Carbon to Philadelphia. In the UK
J L Clark, then engineer to the Electric and International Telegraph Company, took out patents in 1854 and 1857
for a pneumatic pipeline to convey letters and parcels in what he called 'capsules'. With this company he installed
lines up to 57 mm diameter and 1.2 km long.
20
Clark was followed by T W Rammell who favoured larger, wheeled, capsules within pipes and who took out at
least sixteen patents between 1856 and 1886. Rammell proposed an underground pneumatic pipeline network for
London's goods in 1857 and then a passenger line on the bed of the Thames from Waterloo to Whitehall: a 200 m
demonstration length for the latter was installed at Crystal Palace in 1864. However it was the light freight system
which created most commercial interest and this was specifically applied to a postal service by the Pneumatic Despatch
Company, formed in 1859 with Clark and Rammell as joint engineers 83. A trial length of 413 m at Battersea in 1861
was re-layed and extended to 548 m between Euston Station and Mornington Crescent sorting office in 1863. A
second larger line (1.4 m wide instead of 0.8 m) was then laid from Euston to Holbom (2.8 km opened 1865) and
on to the post office at St Martin-le-Grand (1.5 km opened 1869). The whole system was abandoned in 1874,
the GPO preferring its widely established horse-and-cart network.
Only the less ambitious small-packet tubes (up to 75 mm diameter) proved permanently successful in London
and others followed in Paris, Berlin, Vienna and Hamburg. In 1885 J B Berlier proposed a pneumatic parcels link
between Paris and London with 475 km of twin 300 mm pipe. In the 1890s several postal lines up to 200 m m
diameter and up to 3 km long were installed in USA 84. However by then electric underground railways were
being developed and large bore pneumatic systems were temporarily forgotten.
In the first half of the 20th century small in-house pneumatic delivery systems nevertheless became common
for shops, hospitals, factories and offices 85. These were relatively cheap to construct, with small-bore pipes, non-
wheeled capsules and few mechanical problems. The largest UK installation of this type is owned by the British
Steel Corporation at Scunthorpe. This has a network of over 30 km of 115 mm pipe, handling metallurgical
samples as well as documents, via 48 'stations'. The impressive extent o f this system has been emphasised by
superimposing its plan on a map of London (Figure 14). Other large complexes exist at London, Hamburg and
Schiphol Airports which also have some 300 mm pipes with non-wheeled capsules weighing up to 10 kg.
The current wave of interest in larger pneumatic pipelines began in the early 1960s with the construction of
the first 1.8 km of a projected 16 km line for the Hamburg Post Office. This had twin 450 mm diameter pipes
and wheeled capsules weighing about 50 kg (although up to 110 kg experimentally). Since then large-bore
experimental pneumatic pipelines have been built in several countries and, using data from these lines, feasibility
studies have been made for a number of larger commercial installations (Table 6).
The largest known operational pneumatic capsule pipeline is 1 m diameter and carries gravel 2.2 km to a
concrete plant near Tbilisi in Georgia USSR. In this the capsules are despatched as trains of six totalling about
25 tonnes. A proposal to extend this line to 50 km has lain dormant for several years. An 11 km line (twin 1200 m m
pipes) to convey domestic refuse from Leningrad to a processing plant is now nearing completion and is forecast to
be in operation in 1980.
In the UK research on this topic has been undertaken by the Transport and Road Research Laboratory for
the last five years. In conjunction with the British Hydromechanics Research Association and an industrial
consortium a pneumatic pipeline test-loop 550 m long and 600 mm in diameter was built at Milton Keynes in
1976.
21
TABLE 6
Pneumatic capsule pipelines
Site
Battersea
Euston North
Euston South
London-Paris*
Hamburg
New York-Philadelphia*
Paris
Croydon
Atlanta Georgia, USA
Shulaver, Georgia, USSR
Tokyo
Scunthorpe
Hendon-Stewartby*
Len~h [ Diameter Date , (km.) [ (m)
1 8 6 1 i 0 . 4 0 . 8 + i
1863 0.55 0.8 +
1865[69 4.3 1.4 +
1885 475 0.3
1961 1.8 0.45
1965 136 2.9
1967 0.3 0.6
1969 0.12 0.25 I
1970 0.43 0.9
1971 2.2 1.02
1972 1.5 0.9
1972 34 0.12
1972 64 0.45
1973 10 0.6
1974 60 0.9
1975 i l l 0 0.45
1976 0.55 0.6
1980 11 1.2
Castle-an-Dinas*
Ardrossan*
Humberside*
Milton Keynes
Leningrad, USSR
Notes: * Proposal or feasibility study only
+ Non-circular cross-section
t Non-wheeled capsules
Capsule weight loaded (kg)
2x1000
2x1000
4x2500
lOt
50-100
240
l0 t
205
6x4160
225
2 t
100
780
3520
380
1200
6x4000
Cargo
Experimental
Mail i !
Mail !
Passengers
Mail (Exptl)
Electrical goods
Experimental
Gravel
Experimental
Documents +sampie.,
Refuse
Crushed granite
Iron ore
Colliery spoil + pfa
Experimental
Domestic refuse
Reference number
83
83
83
84
87
88
89
90
91
92
86
80
93
94
95
96
4.3 Hydraulic propulsion of capsules
Capsules may be propelled through pipelines by liquids instead of air. A liquid provides considerable
buoyancy and most studies in this field have postulated non-wheeled capsules. By using empty compartments in
the capsules it would be possible to trim them to the same density as the liquid if found desirable. Obvious dis-
advantages are the lower velocity range which would be practicable, the higher pressures which would be necessary,
and the need to seal the capsules against water for some cargoes.
The most advantageous situation for installation of such a system would be where oil or water is being
pumped along an identical route. The practicability of this possibility was demonstrated in 1965 when a 230 kg
capsule, 1.2 x 0.4 m, was sent 175 km through an existing oil pipeline from Edmonton to Hardisty in Canada 97.
Extensive theoretical and experimental studies of hydraulic capsule systems have been made in Canada since
about 1960 and, following this practical trial, a test-loop 1200 m long of 100 mm diameter pipe was constructed at
Edmonton in 196798 .
22
Instead of capsules it would be possible to convey compressed moulded or extruded, spherical or cylindrical,
slugs or ingots of such materials as sulphur, metals, plastics, and baleable wastes. Commodities such as wheat might
be packed and sealed in plastic 'sausage skins'. Similarly natural articles of suitable shape such as logs could be
conveyed and, in one of the few known practical applications so far, pit-props have been sent down a mine
hydraulically. The 'slug' concept has been extended by Berkowitz, also in Canada, to the study of coal-water
paste cylinders in an oil carrier liquid 99.
The centre of hydraulically-propelled capsule research remains Canada, where the scientific papers of M E Charles,
H S Ellis and their associates, of the Alberta University and Research Council respectively, now form an extensive
series 100. As yet however no commercially-operated hydraulic capsule line has been built.
5. OTHER ASPECTS OF PIPELINES AND CONCLUSION
This review has deliberately been restricted to general aspects of pipeline transport: the scientific, technical and
economic aspects which are the subject of most of the research in this field have barely been mentioned since there
is no shortage of literature. Summaries of the science and technology of slurry pipelines are provided in the
Colorado and Ottawa surveys 101 and in the textbooks of Bain and Bonnington 102, Zandi 103, Govier and Aziz 104,
and Wasp et a1105. Further details of particular topics may be traced via the given references, particularly the
Conference Proceedings 17,24, and the quarterly publication of abstracts 106. For pneumatic pipelines there are
similar short- cut s 81 c,81 d,106.
The most difficult aspect of the subject is economics. The operating costs may, for anygiven project, be
determined with reasonable accuracy. But most pipeline systems (excepting the small-bore pneumatic capsule
delivery installations) are capital-intensive and the overall costs depend on how the primary installation is funded
and spread over the hypothetical life of the system. In some cases it is also difficult to establish the capital cost
very accurately because of the exploratory state of some of the technology. Even in fine-coal slurry pipelines,
several of which have now been documented, debate continues over the expensive terminal equipment such as the
best method of crushing, feeding and de-watering. In the case of coarse-solid slurries, there is wide possible choice
between pumping systems and type of pipe (cheap renewable, or expensive durable), and scant data on life
expectancy of systems conveying a wide range of materials. The costs of large-bore wheeled-capsule pipeline systems
are at present only available as hypothetical computer projections with numerous variables: this state of affairs
will continue until a commercial installation has been built and operated for some years.
Despite the continuing world-wide recession, which has inhibited the installation of many pipelines which
were projected in the early 1970s, interest in the subject is currently greater than ever as shown by the growing
frequency of conferences. It seems likely that the next great practical step forward will come with the next
generation of large coal pipelines which many see as inevitable within the next decade 107.
6. ACKNOWLEDGEMENTS
This Report has been prepared within the Transport Engineering Division of the Transport Systems Department of
the Transport and Road Research Laboratory.
23
7. REFERENCES
1. CENTRAL STATISTICAL OFFICE. Annual abstract of statistics 1979. London, 1978 (H M Stationery Office).
2. BRITISH ROAD FEDERATION. Basic road statistics 1978. London, 1979 (British Road Federation).
. BALDWIN, M. A survey of waterway freight transport in Britain. IWA Waterways No. 122, 1978 (Spring/
Summer), 22--4.
.
.
UNITED NATIONS ECONOMIC COMMISSION FOR EUROPE. Annual bulletin of transport statistics 1977.
New York, 1977 (United Nations).
SHONKA, D Bet al. Transportation energy conservation data book. Edition 2, Tennessee, 1977 (Oak Ridge
National Laboratory for the US Department of Energy).
.
.
.
CENTRAL ADVISORY WATER COMMITTEE. The future management of water in Englahd and Wales.
London, 1971 (H M Stationery Office).
WORKING PARTY ON SEWAGE DISPOSAL. Taken for granted (Report of the Working Party). London,
1970 (H M Stationery Office).
WATER RESOURCES BOARD. Water resources in England and Wales. London, 1973 (H M Stationery Office).
.
10.
STANDING COMMITTEE ON SEWERS AND WATER MAINS. Sewers and water mains - a national
assessment. London, 1977 (National Water Council).
PETROLEUM ECONOMICS LTD. Pipelines for crude petroleum and liquid petroleum products. London,
1971 (Petroleum Economics Ltd for the Department of the Environment).
11. BAGWELL, M V. Pipeline transportation in the 70s. Transportation Engineering J of ASCE, 1973, 99 (TEl),
5-15.
12. BAYLAC, B, H H AHRENS and A GROSS. The Central European Pipeline System, Pipeline Engineering
Convention. Londgn, 1973: reprinted in Pipes and Pipelines International, 1973, 18 (11), 30-38. The
CEPS network relates only to oil. For a description and map of the European gas grid see BRECHT C.
Gas supplies into continental Europe, Pipes and Pipelines International, 1979, 24 (June), 9-15.
13. a) TAYLOR, R A A. The hydraulic transportation of coal. Fluid Handling, 1952, 26 (March), 70-74.
b) ANON. Death of a power station. Engineering, 1966, 202 (23 Dec), 1092-3.
14. NARDI, J. Pumping solids through a pipeline. Pipeline News, 1959 (August), 26-33.
15. THOMAS, C H. Pumping coal from mine to seaboard. Scientific American, 1921,124 (7), 126, 139.
24
16. DAUBER, C A. Pipeline transportation of coal. Proc Amer Power Conf, 1957, 19,328-36.
17. THORNTON, W A. The hydraulic transport of solids in pipes - a bibliography. Cranfield, 1970
(British Hydromechanics Research Association).
18. a) CAMPBELL, T C and S KATELL. Long-distance coal transport: unit trains or slurry pipelines.
Information Circular 8690, Washington, 1975 (US Bureau of Mines).
b) ANON. Increasing coal demand - slurry versus rail. Cargo Systems, 1977, (Nov), 26-9.
19. a) COFFEY, R C, H G LYONS and A C OAKES. Mohave Generating Station design features. Amer Power
Conf, 1969, (offprint).
b) DINA, M L. Operating experiences at the Mohave Generating Station. Proc 1st Internat Techn Conf on
Slurry Transp, Columbus, Ohio, 1976 (Battelle Memorial Inst).
20. The bibliography has yet to be published but translations of four major books have already appeared from
Terraspace Inc, Rockville, Md:
a) POKROVSKAYA, V N. Means for increasing the effectiveness of hydrotransport, 1977.
b) SMOLDYREV, A Y and Y K SAFONOV. Pipeline transport of concentrated slurries, 1979.
c) TRAYNIS, V V. Parameters and flow regimes for hydraulic transport of coal, 1977.
d) TURCHANIVO, S P. The life of hydrotransport pipelines, 1979.
21. Proceedings of the 2nd Conference of the Soci~te Hydraulique de France, Grenoble, June 1952.
22. Proceedings of a colloquium on the hydraulic transport of coal. London, November 1952 (National Coal
Board).
23. BAIN, A G. Getting working data on coal pipelines. Engineering, 1963, 196 (Sept), 322-3.
24. Proceedings of HYDROTRANSPORT 1 (1st international conference on the hydraulic transport of solids in
pipes), Coventry, 1970.
Subsequent conferences were 2 Coventry 1972; 3 Golden, Colorado 1974; 4 Banff, Alberta 1976;
5 Hanover 1978; 6 Canterbury 1979; all proceedings published Cranfield (British Hydromechanics Research
Assoc).
Following the success of these symposia, independent annual conference in USA have been organised by the
US Slurry Transport Assoc, Washington DC, the 4th being in 1979: these are published as Proc Internat
Tech Conf on Slurry Transportation, Las Vegas (Slurry Transport Assoc).
25. OYLER, J F and D R RATHBURN. A review of the handling of dry bulk or slurried materials at ocean ports.
Minerals Transportation 1, 1972, 77-119.
26. ANON. North American iron ore: launching a rescue mission for a steel-short economy. Engng & Mining J,
1974, 175 (11), 83-162.
25
27. a) GALLOWAY, R M and D R RATHBURN. In-plant materials handling using the Marconaflo system concept.
Proc Hydrotransport 2, 1972, pp K1-K16.
b) FUJITA, K and T CHIBA. Handling iron ore slurry at Hirohata steel works. Minerals Transportation 2,
1974, 340-63.
28. FRASER, D A. Pipeline transportation of concentrates. Mining Congress J, 1960, 46 (March), 44-8.
29. a) MANNING, J P. Concentrates handling, Min Engng, 1960, (April), 370.
b) CONSTANTINI, R." Basic considerations for long-distance solids pipelines in the mineral industries.
Trans Amer lnst Min Engrs, 1961,220, 261-70.
30. DAVISON, C N. Concentration and hydraulic transport of heavy mineral concentrate with automatic control.
Proc Austr lnst Min & MetaU, 1962, 204, (Dec), 1-57.
31. a) GRIESSHABER, H E and T C AUDE. First long-distance iron slurry pipeline. Civ Engng ASCE, 1969, 39
(Jan), 66-9 .
b) ANON. Success of world's longest high-solids pipeline. Austr Civ Engng, 1969, 10 (June), 28-31.
32. DOWNER, H C. The impact of marine slurry transportation on world mineral development. Minerals
Transportation 1,1972, 244-65.
33. COALE, R D, T L THOMPSON and R P EHRLICH. BougainviUe copper concentrate slurry pumping system.
Trans Soc Min Engrs of AIME, 1976, 260 (Dec), 289-97.
34. McNAMARA, E J. Operational problems with a 69-mile copper concentrate slurry pipeline. Proc Hydro-
transport 4, 1976, F31-F40.
35. NOYAN, K et al. The KBI parallel pipelines for sulfide concentrates. Proc Hydrotransport 3, 1974, B21-B26.
36. ANON. Eleven mile pipeline for conveying slurries. Quarry Managers J, 1974, 58 (April), 125.
37. SAMBELLS, D F. A practical solution to pumping an abrasive slurry. Proc Hydrotransport 3, 1974, J1-J15.
38. ANON. China clays: slurry solution to dust. Cargo Systems, 1978, 5 (9), 93.
39. COi.Z)RADO SCHOOL OF MINES. The transportation of solids in steel pipelines, 1963, pp 99-101.
40. a) BLUE CIRCLE GROUP. Northfleet Works, 1972.
b) ANON. Slurry pipeline schemes nearing completion. Mining & Min Engng, 1970, 6 (Jan), 7.
c) ANON. Thames pipeline crossing. Cement lame & Gravel, 1970, 46 (Aug), 216.
41. WALKER, J R D and R C WORSTER. Hydraulic transport of solids: Trinidad Cement Ltd's 6-mile 2000
PSI pipeline. Proc Pipes Pipelines Pumps & Valves Convention, London, 1962.
26
42. a) WALKER, J R D. A year's experience with a 57-mile solids pipeline. Cement Lime & Gravel, 1966, 42
(Nov), 363-6.
b) SWISS, M. Piping solids and viscous fluids. International Construction, 1970, 9 (12), 22-3.
43. CLARK, W B and W P FULLER. Quarry to mill by pipeline. California Geology, 1973, 26 (Sept), 207-213.
44.
45.
46.
47.
FULKERSON, E F and J E RINNE. Gilsonite solids pipeline. Proc ASCE Pipelines Division, 1959, 85 (PL. 1),
35-46.
a) HARDY, H B and S A CANARIIS. Hydraulic transportation of Florida phosphate matrix: Introduction.
b) SMITH, M R. Achan and Noralyn mines.
c) CUSTRED, U K. Sydney mine.
d) WESTER, J L. Tenoroc mine.
All in Min Engng 1961,13 (March), 274-281.
SMITH, L Get al. Experimental studies on solids pipelining of Canadian commodities, Saskatchewan Research
Council, 1973. (An abridgement of the potash paper is in Proc Hydrotransport 2, 1972, K29-K44.)
ELLIOTT, D R and W H de MONTMORENCY. The transportation o f pulpwood chips in pipelines.
Pulp & Paper Res Inst Canad Tech Rep 334, 1963.
48. VOCADLO, J J and M E CHARLES. Transportation of slurries. Canad Min & Met Bull, 1972, 65 (Oct), 113--22.
49.
50.
51.
52.
53.
54.
HUBBARD, S B and J B HERBICH. Productive land use of dredged material: international literature review.
Texas Engng Expt Stn Report CDS 199, Texas, 1977.
The main sources of information are the following journals:-
World Dredging & Marine Construction, International Dredging & Port Construction, Terra et Aqua, and
International Dredging Abstracts. Additional sources are the Proceedings of the World Dredging Conferences
(WODCON) held every 18 months since 1967.
INSTITUTE OF QUARRYING. Proc Symposium on Aggregates for London, 1971, reprinted in Quarry M'gers J, 1972, 56 (3) and (4), 89-138.
DEPARTMENT OF THE ENVIRONMENT. Production of aggregates in Great Britain. Published anntmlly
(H M Stationery Office). Until 1971 the title (and content) was merely Sand and Gravel Production.
HESS, H D. Marine sand and gravel mining industry of the UK. National Oceanic and Atmospheric
Administration (NOAA) Technical Report ERL 213-MMTC 1, Boulder, Colorado (US Department of
Commerce), 1971.
a) STANDING CONF ON LONDON & SE REGIONAL PLANNING Report SC86. Sand and Gravel
Extraction: the development of rail-served aggregate depots. London, 1974 (SCLERP).
b) ALLEN, G F. Aggregates by raft. Modern Railways, 1978 (August), 365-9.
27
55. ADVISORY COMMITTEE ON AGGREGATES. Aggregates: the way ahead, 1975 (H M Stationery Office).
A Preliminary Report was circulated in 1973 and several of the committee's recommendations in fact had
already been acted upon by 1975.
56. a) JAMES, J G and B A BROAD. Conveying limestone aggregates and colliery spoil by hydraulic pipeline:
trials with a 156 mm diameter pipe. Department of the Environment Department of Transport, TRRL
Report SR 354. Crowthorne, 1978 (Transport and Road Research Laboratory).
b) CARLETON, A J and R J FRENCH. Hydraulic transport of limestone aggregates and colliery spoil.
Department of Industry, Warren Spring Laboratory Report LR 290. Stevenage, 1978 (Warren Spring
Laboratory).
57. SHERWOOD, P 1~ et al. The use of waste and low-grade materials in road construction. Department of the
Environment series of TRRL Reports LR 647 (general guide), LR 649 (colliery shale), LR 686 (pulverized
fuel ash), LR 728 (incinerator refuse), LR 817 (china clay sand), LR 818 (oil shale), LR 819 (miscellaneous).
Crowthorne, 1974-78 (Transport and Road Research Laboratory).
58.
59.
0.
61.
LAWSON, E M and P J NIXON. A survey of the locations disposal and prospective uses of by-products and
waste materials. Department of the Environment, BRE Current Papers CP19[74 (England and Wales) and
CP50/78 (Scotland), Garston 1974 and 1978 (BRE).
AGGREGATES AND WASTE MATERIALS WORKING GROUP. Report to the Advisory Committee on
Aggregates, Department of the Environment, BRE Current Paper CP31 [73, Garston, 1973 (BRE).
ORGANISATION FOR ECONOMIC COOPERATION AND DEVELOPMENT. Use of waste materials and by-
products in road construction. Paris, 1977 (OECD: English edition available from H M Stationery Office).
BROWN, J and P R WALTON. Hydraulic disposal of pfa from CEGB Midland Region power stations.
Proc Hydrotransport 6, 379-88, 1979.
62. CORNER, D C and D C STAFFORD. China clay sand: liability or asset? Exeter, 1972 (Devon County Council).
63. NEWMAN, D E. Beach replenishment. Proc Inst Civ Engrs, 1976, 60 (August), 445-60.
4.
65.
66.
67.
28
PATERSON, A C and N WATSON. The National Coal Board's pilot plant for solids pumping at Horden
Colliery. Proc Hydrotransport 6 ,353-66 , 1979.
STRATEGIC CONF OF COUNTY COUNCILS OF YORKSHIRE AND HUMBERSIDE. Reclamation of
Pyewipe using waste from the Yorkshire coalfield. Wakefield, 1979 (SCOCC).
BROWN, D W. The possible use of industrial waste and its transportation for reclamation purposes.
Proc Land Reclamation Conf, Grays, Essex, 1976 (Thurrock Borough Council).
DOWN, C G and J STOCKS. The environmental problems of tailings disposal at metal mines. Department of
the Environment, Research Report 17. 1976 (Department of the Environment).
68. DOWN, C G and J STOCKS. Methods of tailings disposal etc. Mining Mag 1977,136 (May), 345-59 and
137 (July, Sept), 25-33,213-23.
69. COURATIN, P. Tailing disposal. World Mining 1969, (May).
70. SCHREIBER, . Filling by water-flushing system in Silesian collieries. Gluckauf, 1904, ,59.
71. a) STEWART, R M. Hydraulic fill slurries. Canad Min & Metallurg Bull, 1960, 53 (Sept), 687-702.
b) Proc Jubilee Symposium on Mine Filling, Queensland, Austrafia, 1973 (Australian Instute of Mining and
Metallurgy).
72. FADDICK, R R and J W MARTIN. Materials handling research for tunnelling. Underground Space, 1977, 2
(2), 121-27.
73. ILLINGWORTH, J R. Movement and distribution of concrete. 1972 (McGraw Hill).
74. ANON. Extensive concrete pumping operation for Spanish dry dock. Internat Constr, 1970, 9 (8), 2-12.
75. a) KRAUS, M N. Pneumatic conveying of bulk materials. New York, 1968 (Ronald Press).
b) STOESS, H A. Pneumatic conveying. New York, 1970 (Wiley).
76. SPROSEN, J C, W A GRAY and J HAYNES. Pneumatic transport of coal. Proc Pneumotransport 3,
pp A57-73, 1976.
77. a) ANON. How Shirebrook eliminated a winding bottleneck. Mine & Quarry, 1977, 6 (Oct), 23-4 . ,.
b) PETERS, T W. Shirebrook pneumatic coal transport scheme. Colliery Guardian, 1977, 225 (Nov), 853-6.
78. AITKEN, I M E and W H G HAMILTON. Piped refuse collection at Lisson Green. Proc Pneumotransport 3,
pp A95-113, 1976.
79. CHARNOCK, A. Small bore refuse system gets airborne. New Civ Engr 1979 (2 Aug), 22-3 .
80. PENCOL ENGINEERING CONSULTANTS. Transport of municipal solid wastes by pipeline. London,
1972 (Pencol). A summary of this was also published by NOLAN, H G B and K L D FLINTOFF in
Pipes & Pipelines Internat, 1973, 18 (Sept) 33-6, (Oct) 25-36.
81. a) SOO, S L, J A FERGUSON and S C PAN. Feasibility of pneumatic transport of coal. Proc Atlanta
Intersociety Conf on Transportation, New York, 1975 (Amer Soc Mech Engrs).
b) RIEBER, M and S L SO0. Pneumatic transport. Vol 7 of Comparative coal transport costs. Bureau of
Mines Report OFR 146 (7)-77, Washington, 1977 (US Department of Commerce).
82. a) CLAYTON, H. The atmospheric railways. 1966 (Clayton).
b) HADFIELD, C. Atmospheric railways. 1967 (David & Charles).
29
83. LEE, C E. The Pneumatic Despatch Company's Railways. Trans Newcomen Soc, 1973, 45, 67-88.
84. a) BERLIER, J B. The pneumatic transmission of messages and parcels between Paris and London, 1885 (Spon).
b) BATCHELLER, B C. A pneumatic dispatch-tube system for rapid transportation of mails in cities.
Tram ASMechE, 1899, 20,373-403.
85. WHITING, J. Handling papers and small articles by pneumatic tubes. Paper MH-51-10. Trans ASME, 1929,
97--102.
86. DIALLED DESPATCHES Ltd. (a) Paper link in action at British Steel Corporation; (b) Paper link in action
at Heathrow Airport, n.d. (1970s), Gosport (Dialled Despatches Ltd).
87. HAUSSMANN, G. Erfahrungen vom 2e Bauabschnitt der Grossrohrpost Hamburg, Fordern und Heben,
1970, 20 (17), 1003--6.
88. EDWARDS, L K. High-speed tube transportation. Scientific American, 1965,213 (2), 30--40.
89. SIMPER, J I and P J BAKER. Pneumatic pipeline capsule systems - the future potential. Proc Pneumo-
transport 2, 1973, F31-39.
90. LIVESEY, R. Capsule-in-tube transport cuts out slow messengers. Engineer, 1971,233 (28 Oct), 33.
91. ANON. More than a pipe-dream. Transportation & Distribution Management, 1972 (June), 50-1.
92. ANON. New Civil Engineer, 1973 (26 April), 9: and New Scientist, 1975, 67 (11 Sept), 589.
93. FARAHAR, R M. Transport of aggregates by the pneumatic capsule pipeline. Proc Pneumotransport 3, 1976,
A115-126; also summarised in Bulk Storage Movement Control, 1976, 2 (July/Aug), 40-5.
94. BAKER, P J e t al. Pipeline transport of waste materials in the Yorkshire and Humberside region. Report
RR1311. Cranfield, 1975 (BHRA).
95. BUNCE, J A. Pneumatic capsule pipelines. Construction, 1978 (June), 31-3.
96. BOGDANSKIY, S E. l~neumosystem containers, Stroit i Arkhit Leningrada, 1979 (Aug), 20-1 (in Russian).
97. a) ANON. Capsule pipelining gets boost. Chem Engng, 1965, 72 (12 April), 83--4.
b) HODGSON, G Wet al. Edmonton-Hardisty trunkline test, J Canad Petrol Techn, 1967, 6 (1), 1-5.
98. JENSEN, E J and J G BRUCE. Capsule pipelining - a feasibility assessment. Proc Hydrotransport 1, 1970,
C1--27.
30
99. a) BERKOWITZ, N. Some newer concepts of solids pipelining. Fluid Handling, 1963, 164 (Sept), 324-7
and (Oct), 345-8.
b) BERKOWlTZ, N, R A S BROWN and E J JENSEN. The pipeline flow of paste slugs. Canad J Chem Engng,
1965, 43 (Dec), 280-5.
100. ELLIS, H Set al. The pipeline flow of capsules Parts 1 to 8, Canad J of Chem Engng, 1963, 41 (April) 43-51;
1964, 42 (Feb) 1-8, (April) 69-76, (Aug) 155-161,168-173, (Oct) 201--6; 1965, 43 (Aug), 197-205.
Part 9, J Fluid Mech, 1967, 30 (3), 513-31. Part 10, Proc Hydrotransport 1, 1970, C1-99.
Many more unnumbered papers have been published by the same group of workers in later Hydrotransport
Proceedings and in other scientific and technical journals.
101. a) COLORADO SCHOOL OF MINES RESEARCH FOUNDATION. The transportation of solids in steel
pipelines, Golden, Colorado, 1963 (CSMRF).
b) JOB, A L. Transport of solids in pipelines; a literature survey. Canadian Department of Energy Mines
and Resources Information Circular IC230, Ottawa, 1969 (Mining Research Centre).
102. BAIN, A G and S T BONNINGTON. The hydraulic transport of solids by pipeline. 1970 (Pergamon).
103. ZANDI, I. Advances in solid-liquid flow in pipes. 197 ! (Pergamon).
104. GOVIER, G W and K AZIZ. The flow of complex mixtures in pipes. 1972 (Van Nostrand).
105. WASP, E J, J P KENNY and R L GHANDI. Solid-liquid flow: slurry pipeline transportation. 1977 (Trans
Tech Publ).
106. Solid-liquid flow abstracts. Cranfield (Quarterly publication by British Hydromechanics Research Association
since 1970).
107. WASP, E J. Coal slurry pipelines for the next decade. Mech Engng, 1979, 101 (Dec), 38-45.
108. PITTS, J D and T C AUDE. Iron concentrate slurry pipelines. Trans Soc Min Engrs, 1977, 262 (June), 125-33.
109. BREWlS, A A C. The Sicartsa Project. Mining Mag, 1976, 135 (Oct), 318-30.
110. HILL, R A and M E JENNINGS. Samarco's 246 mile slurry pipeline. Engng and Mining J, 1978, 179 (Aug),
74-9.
111. SESHADRI, G R. Kudremukh iron ore, Mining Mag, 1978, 138 (Jan), 26- 31.
31
1700 m
R o a d
1600
1500
1400
1300
1200
1100
~ 1000
8 c 900 0
800 -
700 -
600
500
400
300 "-
200
' 1 0 0 -
1950
1800
Pipeline
Coastal
I / shipping
- -""--===:~=7. In&nd
1960 1970 1980 Year
(a) TONNES
t_
E O
C e-
£ t- O °~
m
t-
O ¢-
100
90
80
70
60
50
40
30
20
1 0 -
0
1950
Roa
I Pipeline
Inland I ~ ' ~ ' T ' ~ " ~ ' ~ I ~ " wat e rway
1960 1970 1980 Year
(b) TONNE-KI LOMETRES
O
70
60
50
40
30
20
10
0
1950
Roa~
~ ~ /Coastal ~ - - ~ s h ~ p p i n g
/ P i p e l i n e
/ / ' / In land I ~ I ~wate rway
1960 1970 1980
Year
(c) PERCENTAGE OF TONNE KILOMETRES
Fig. 1 TRENDS IN UK FREIGHT TRANSPORT MODES (Data largely from A n n u a l Abstracts of Statistics, H M S O )
E O
$ t- ¢- o
t- O
r-
-1 O t- F-
1500,
1400 t
1300
1200
1100
1000
900
800
700
600
50O
400
300
200
100
0
1950
Rail
Pipeline Road
I n land waterway
I I
1960 1970 1980 Year
(a) T O N N E - K I LOMETRES
100
90
8O
~ 70
~ 60
50
"6 40 Q)
~ 30
~ 20
Rail
Pipel ine
__ ~ Road I
~ ~ - ~ ' - - In land w a t e r w a y I
10
0 I I
1950 1960 1970 Year
1980
(b) PERCENTAGE OF TONNE- -K ILOMETRES
Fig. 2 TRENDS IN USA F R E I G H T T R A N S P O R T MODES (Data from Transport Energy Conservation Data Book,
US Dept of Energy 1977) ~
i , Intercepting sewers - - Main sewers
Storm relief sewers
Principal sewers only are shown
• Sewage pumping stations and outfall works
O Storm water pumping stations
~1= Out county drainage
27 km
, I . I I~ ~ I I s L I ~ T H
". .
4
i O~L~A
M O C ~ T'OTt INs,~L~ ~L~ • " t ~ GiIEN
NOITx iaSt l lN IDGI ~ SlOl.,~ IIILIEt
4b ~ HACK~Y
LuDO~! LIvl l / 14~
= - - - ~ , I " "%.
I ,.-,,.., ...... T SEWER No I
UANCH SOUtNill SIW|I $1Wll •
STOIM crlsTAL l | t i f
~LET1TCN
DEPTPOID P S
mGH [EVIL SEWlR No 2 IUSc'IE ¥ rJ~EN
• t t Wt SZ~tt I I K H UW|R
V~EST NA~
a~t,t$ P 5.
NORTH OOGS S lA~H WOOtWlCH P 5
r" .'%=.!
WI~.WllOI
I , [ |
' I i
~ . . . . . . . . . J
Fig. 3 MAP OF LONDON'S PRINCIPAL SEWERS, COMPARABLE WITH THE FAMILIAR 'TUBE' R A I L W A Y NETWORK (From J.Venables. The main drainage of London,
Underground Services, 1973 1(2),25-28)
" OUI~ALt
N
?
b 16o
| s
bo °
FY LDE/PRESTON I
Water sources
• Water deficient sites
Links
SUNDERLAND
IITEESSIDE
SIDE ...... SHEFFIELD/
-~ ) ~ ~ .,.~.o~oo~ LEICESTER I
CARDIFF ,#SOUTH ESSEX I LONDON
Fig. 4 PROPOSED WATER RE-DISTRIBUTION NETWORK (from Water Resources of England
and Wales 1973)
9
TotaJ 7 -
6 -
5 -
4 -
3 -
2 -
1 -
I ol 1950
o O
Oil
/ ~.-.-Coal
~ Gas
Nuclear + Hvdr~
1960 1970 1980
Year
o
~J
(3.
80
70
60
5O
40
30
20
10
C
1950
~ Oil Coal
Gas
~ ~ 1 Nuclear + Hydr~ 1960 1970 1980
Year
Fig. 5 TRENDS IN UK ENERGY SOURCES (Data from Digests of UK Energy Statistics)
15
~ 1 0
O ° _
"O t - t~
O t -
I- 5 ~
North sea gas
Imported gas
Petroleum gases purchased
Coke oven gas purchased
Water gas and other gas made
Oil gas made
Coal gas made
1978=15.8
t /
1960 1962 1964 1966 1968 1970 1972 1974
Year
Fig.,6 GROWTH IN UK CONSUMPTION OF NATURAL GAS (From 1975 Digest of UK Energy Statistics)
FRIGG
=ST FERGUS
) ABERDEEN
• Stations
N LIVERPOOL
WREXHAM •
• NEWCASTLE ; \ ~l l l lq lb MIDDLESBROUGH
ROUGH
THEDDLETHORF
WEST SOLE ~1 VIKING
HEWETT ! ~ • INDEFATIGABLE
LEMAN
~ BACTON |
~ORWICH
~o J
200km
EXETERI
Fig. 7 NATIONAL GAS TRANSMISSION SYSTEM IN UK
.... " % , . . ' % . s
"t', .2 S
V
.- / .
ITRAPIL] /'~"~Eo~s
OR L~ANS
0
SAINT NAZAIRE ~
CEPS pipelines and depots I ~ . m - - - Other pipelines
0 100 200k m I
CHALON SUR • SAONE
MARSEILt
%
STRASBOURG
F R A N K F U R T I WURZBURG
% LUDWIGSHAFEN
Fig. 8 MAP SHOWING THE " C E N T R A L EUROPEAN PIPELINE S Y S T E M " A N D SOME OF THE OTHER DISTRIBUTORS OF P E T R O L E U M IN N O R T H WEST EUROPE
(From BAYLAC, AHRENS and GROSS, 1973, ref 12 with additions)
Oilfields in production or under development Other oil finds
6 Oil refineries
Crude oil pipelines
• =~ Refinery products
-=, . . . . Petrochemicals
MAGNUSA••• MURCHISON
DUNLIN~ ~ THISTLE TERN • ~ h
CORMORANT fSTATFJORD I~:RRENT
HEATHER • HUTTON
SULLOMV~ A~ BERYL
• CRAWFORD
,,o~, ~ ~ ~'~RAE ,WEB
~ e=.~F RUCHAN • •
Q _-~? A - -
°° ,OL:::~
• MAUREEN ANDREW
~ I EKOFISK
'ARGYLL
GRANGEMOUTH
b 160
N
f
N D R % ~ ~
/:.E,,.ELO__ ~;O0" RUNCORN * ~ ~.
ELLEBMERER" "~OR?"~"~L p NO~,"G"~ / STANLOW I - #
ele ee / ~ - t~°URR°R~ ~ ~ / j I s . ...~" J ~"'~v~Lc: ,lco,ocoj'41°" j
PEMBROKE L L A N ~ R I ~ I ~ - I~HEATHROWig LONOOONiI'~I~ISLE'(~rGRAIN
. _ _ - - - J "~ A,OER'M~'O.~----i __J J .% s" I = ~ U l F
~ L E Y ~
Fig. 9 M A I N O IL N E T W O R K IN UK (from Gt. Britain 1978, HMSO, with additions)
25
20
Q.
"o
~- 15 oo
(lo
10
_Q
E :3 z
5
0 I L
50 52 54 56 58 60 62 64 66
Year
68 70
Fig. 10 NUMBER OF ARTICLES ON COAL SLURRY PIPELINES APPEARING EACH YEAR, SHOWING SHARP DECLINE
AFTER CLOSURE OF OHIO PIPELINE IN 1963 (from THORNTON, 1970, Ref. 17)
~ N <~O.,0" / / 4~" % INTERPROVINCIAL LAKEHEAD SYSTEM )/
'<>il, o-~N ov<.. ., ..... . ~ ,
% 1o .. . . . .
( ' 7 " - " %• TRANSPORTATION ~,~ OH O,~ GULF INTERSTATE NORTHWEST / ~ I , SYSTEMS INC. ~ ..........
NEVADA POWER TEXAS EASTERN i% / ~ % I '1 . . . . . . 2 - '= ..... w,L,~,,.o ~ % % FLORIDA GAS " 1 '_ ~ '% ~ '~ COMPANY
" ~ BLACK MESA % - '% ~ ( • I " ~
I .x .o , 1 s , , . . . . co .~, . . ~ .....
Fig. 11 SOME EXISTING AND PROPOSED COAL SLURRY PIPELINES IN NORTH AMERICA
(Data largely from Proc. 4th Int. Conf. on Slurry Transportation, 1979)
I B Production of crude minerals C Consumption of construction materials A Consumption of mineral energy sources D Production of basic foods
200
ides im )orts 150
£ 10O ! and g .....
stone
I ;l ~ oil equivalent)
1960 1980 1960 1980 1960
Year Year Year
Ready mixed
Liravel and hoggin
1 Concrehng sand
road
Bricks
1980
D
Cereals Is ~ M i l k I Fodder
Beer Potatoes Vegetables
ineSand spirits
1960 1980
Year
Fig. 12 TRENDS IN UK PRODUCTION AND USAGE OF SOME MAJOR MINERALS, CONSTRUCTION MATERIALS, AND FOOD STUFFS
(Data largely from Annual Abstracts of Statistics, HMSO)
20 20
c- t - O
t - O
15
10
5
o
1960 1970
T o t a l
I m p o r t
E x p o r t
1980 "
Year
(a) MARINE AGGREGATES PRODUCED IN UK
t - O
c- O . _
15
10
0
1960
A p p r o x i m a t ~
I
1970 1980 Year
(b) AGGREGATES TRANSPORTED BY RAI L TO SOUTH EAST
ENGLAND
Fig. 13 GROWTH IN MARINE AGGREGATES PRODUCTION AND USE OF RAIL- -HAULED AGGREGATES IN UK
Fig. 14 BRITISH STEEL CORPORATION'S PNEUMATIC CAPSULE NETWORK AT SCUNTHORPE SUPERIMPOSED UPON A MAP OF LONDON
(from Dialled Despatches Ltd. Ref. 86)
(992) Dd0536380 1,500 6/80 H P L t d S o ' t o n G1915 PRINTED IN ENGLAND
ABSTRACT
PIPELINES CONSIDERED AS A MODE OF FREIGHT TRANSPORT: A REVIEW OF CURRENT AND POSSIBLE FUTURE USES: J G James: Department of the Environment Department of Transport, TRRL Supplementary Report 592: Crowthorne, 1980 (Transport and Road Research Laboratory). Pipelines are perhaps the least appreciated mode of freight transport. The unobtrusive distribution of many megatonnes of water, oil and gas in the UK annually is taken for granted and only the figures for oil appear in annual freight statistics. The transport of solids by hydraulic or pneumatic pipeline - either in free flow or packed into capsules - is technically more difficult and less common, but the practice is already well-established in certain specialised fields.
After a brief introduction to the statistics for various freight transport modes, the author reviews the current usage of pipelines for water, sewage, gas and oil, before examining at length hydraulic 'slurry' pipelines for a variety of minerals. The Report concludes with a brief note on capsule pipelines which, apart from small-bore in-house delivery systems, are still in the prototype stage. A bibliography of over 100 references is given.
ISSN 0305-I 315
ABSTRACT
PIPELINES CONSIDERED AS A MODE OF FREIGHT TRANSPORT: A REVIEW OF CURRENT AND POSSIBLE FUTURE USES: J G James: Department of the Environment Department of Transport, TRRL Supplementary Report 592: Crowthorne, 1980 (Transport and Road Research Laboratory). Pipelines are perhaps the least appreciated mode of freight transport. The unobtrusive distribution of many megatonnes of water, oil and gas in the UK annually is taken for granted and only the figures for oil appear in annual freight statistics. The transport of solids by hydraulic or pneumatic pipeline - either in free flow or packed into capsules - is technically more difficult and tess common, but the practice is already well-established in certain specialised fields.
After a brief introduction to the statistics for various freight transport modes, the author reviews the current usage of pipelines for water, sewage, gas and oil, before examining at length hydraulic 'slurry' pipelines for a variety of minerals. The Report concludes with a brief note on capsule pipelines which, apart from small-bore in-house delivery systems, are still in the prototype stage. A bibliography of over 100 references is given.
ISSN 0305-1315