TRANSPORT and ROAD RESEARCH LABORATORY Department of … · 9. Recommendations for overlay design...
Transcript of TRANSPORT and ROAD RESEARCH LABORATORY Department of … · 9. Recommendations for overlay design...
TRANSPORT and ROAD RESEARCH LABORATORY
Department of the Environment Department of Transport
TRRL LABORATORY REPORT 1043
EARLY PERFORMANCE OF SOME EXPERIMENTAL BITUMINOUS OVERLAYS IN KENYA
by
H R Smith and.C R Jones
The work described in this Report forms part of the programme carried out for the Overseas Development Administration,
but any views expressed are not necessarily those of the Administration.
Overseas Unit Transport and Road Research Laboratory
Crowthorne, Berkshire 1982
ISSN 0305--1293
Ownership of the Transport Research Laboratory was transferred from the Department of Transport to a subsidiary of the Transport Research Foundation on 1 st April 1996.
This report has been reproduced by permission of the Controller of HMSO. The work described in this report forms part of a programme carried out for the Overseas Development Administration, but the views are not necessarily those of the Administration. Extracts from the text may be reproduced, except for commercial purposes, provided the source is acknowledged.
CONTENTS
Abstract
1. Introduction
2. Objectives of the experiments
3. The design of the experiments
4. Tests and measurements made before overlaying
4.1 Pavement investigations
4.2 Surface condition assessments
4.2.1 Rut depths
4.2.2 Cracking and patching
4.3 Deflection measurements
4.4 Determination of overlay thicknesses
5. Construction of the overlays
5.1 Tack coats
5.2 Manufacturing and rolling temperatures
5.3 Laying and compaction
5.4 Sampling of the overlay materials
6. Post-construction measurements
6.1 Compaction of the overlays
6.2 Overlay thickness
6.3 Traffic loadings
6.4 Surface condition
6.4.1 Rut depths
6.4.2 Cracking
6.4.3 Surface roughness
6.5 Ageing of the bitumen in the overlays
Page
1
1
2
2
3
3
3
3
4
4
4
4
4
5
5
5
6
6
7
7
7
7
7
8
8
6.6 Deflection measurements
6.6.1 Strengthening effect of the overlays
6.7 Radius of curvature of deflected surfacing
6.7.1 Deflection-curvature relationships
6.7.2 Effect of temperature on deflection-curvature relationships
7. Performance of the overlays
7.1 General observations
7.1.1 S i te l
7.1.2 Sites 2 and 3
7.1.3 Site 4
7.1.4 Site5
7.1.5 Sites 6 and 7
7.1.6 Site8
7.2 Relationships between measured parameters and cracking
8. Discussion of results
9. Recommendations for overlay design in Kenya
10. Future work
11. Conclusions
12. Acknowledgements
13. References
14. Appendix: Adaption of British overlay design method for use in Kenya
14.1 Application of the method in Kenya
14.1.1 Roads with crushed stone roadbases
14.1.2 Roads with soil-cement roadbases
Page
9
9
10
10
11
11
12
12
12
12
12
13
13
13
14
15
15
16
17
17
58
58
58
58
© CROWN COPYRIGHT 1982 Extracts from the text may be reproduced, except for
cDmrnerJcial purposes, proyJded_the~our~e is_ackno~vledged
EARLY PERFORMANCE OF SOME EXPERIMENTAL BITUMINOUS OVERLAYS IN KENYA
ABSTRACT
This report describes the performance of bituminous overlays on roads in tropical and sub-tropical environments in. Kenya.
Considerable hardening of the binder occurred throughout the depth of the overlays during the first five to seven years, but negligible rutting developed. The main form of deterioration was cracking which was initiated at the surface of the overlays.
The reduction in pavement deflections produced by the overlays is shown to be only slightly less than those obtained in Britain despite the higher ambient temperatures in Kenya.
The performance of the overlays is shown to be primarily dependent on the properties of the overlay material itself. No correlation could be established between the development of cracking on each test section and the corresponding values of surface deflection and curvature, traffic loading or overlay thickness. However the overlays have remained serviceable for up to seven years and have carried up to 4.3 x 106 equivalent standard (80 kN) axles.
1. INTRODUCTION
Many of the paved roads in developing countries have, for sound economic reasons, been built on the
'stage construction' principle which requires that a road is strengthened periodically to match the growth
in traffic. Consequently in many countries substantial programmes are now required to reconstruct or
strengthen roads that have reached the end of their original design lives.
It is often more economical to strengthen a road when it has reacheda critical condition rather than
to allow it to fail, necessitating reconstruction of the whole or the upper layers of the pavement. Premixed
bituminous overlays provide a relatively rapid and convenient method of strengthening roads. However,
high quality bituminous materials are expensive and hence it is important that the method of design of
the overlay thickness should be as effective as possible and the 'life' o f the overlay should be predictable
with a high level of confidence.
1,2,3,4,5 Authorities in several countries use deflection techniques for evaluating the structural condition
of pavements and for designing the thicknesses of bituminous overlays. Most of the available overlay design
recommendations have been developed in countries with temperate climates and there is an urgent need to
develop similar recommendations for use in countries with tropical climates.
This report gives details of the construction and early performance of a number o f experimental
overlays placed on a variety of road pavements in the Republic of Kenya between 1973 and 1977 as part of
a cooperative study between the Kenya Ministry of Works and the Overseas Unit o f the Transport and
Road Research Laboratory.
2. OBJECTIVES OF THE EXPERIMENTS
The objectives of the experiments a r e : -
(a) to study the performance of different types and thicknesses of bituminous overlays in tropical and
sub-tropical environments;
(b) to determine the strengthening effect o f the overlays by comparing deflection measurements made
before and after overlaying;
(c) to develop bituminous overlay thickness design charts for use in tropical environments.
3. THE DESIGN OF THE EXPERIMENTS
The experiments comprise different types and thicknesses of premixed bituminous materials laid on different
types of pavement construction in a range of climatic zones.
The Kenyan Ministry of Works arranged for the construction of seven groups of experimental overlays
and an eighth small group was constructed on the Nairobi-Thika road in cooperation with the Nairobi City
Council. Details of the locations of the sites are given in Table 1. Summaries of the available rainfall data
recorded at meteorological stations near to the sites are given in Table 2.
A restriction placed upon the selection of the sites arose from the need to minimise costs by locating
the overlays near to road construction projects where premixed bituminous material was being manufactured.
The sites were chosen so that variations in road alignment and drainage conditions were kept to the minimum.
At each site a number of 100 metre long sections, separated by transitions, were overlaid with premixed
bi tuminous materials 6,7 to the specifications shown in Tables 3 and 4.
Details o f the types of bituminous mixes laid at each site togethe r with section numbers and thicknesses
o f material are indicated in Table 5.
The thicknesses o f the overlays at each site were selected on the basis o f available traffic loading data
and the results of deflection measurements made before overlaying. The mean deflection for each section
was calculated and an estimate of the overlay thickness required for a typical design life of eight years was
obtained f rom the design curves developed in the United Kingdom 8. (These design curves were revised in
19784 and now indicate longer lives for the overlays.)
At each site a 'design' thickness was chosen and each overlay material was laid on asection to this
thickness. In addition an asphaltic concrete mix was also laid on three other sections to thicknesses of
25 m m less than the design thickness and 25 and 50 mm more than the design thickness. A minimum
thickness o f 35 Or 40 m m was stipulated, depending upon the maximum size of stone in the aggregate.
Continuous cast in situ kerbs were constructed along two sections of sites 2 and 3 to determine
whether they provide any benefit by restraining the edges of the unbound roadbases: The kerbs extended
f rom below the roadbases to the surface o f the existing road. Drainage paths were provided from the bo t tom
2
of the roadbase through the kerbs and shoulders. At each site one of these sections was overlaid with the
design overlay thickness of 100 mm andthe other with 75 m m of the current (1973) nominal 20 m m
asphaltic concrete. The overlays extended over the kerbs.
At each site, except for site 1 where there was an insufficient length of uniform road, a 'control '
section of the existing road was included in the overlay monitoring programme.
4. TESTS AND MEASUREMENTS MADE BEFORE O V E R L A Y I N G
At each site the required number of 100m long.sections were marked out with twenty deflection test
points and forty-four levelling points as indicated in Figure 1.
4.1 Pavement investigations
At each site inspection holes were dug in all the transition zones to measure the thicknesses, in situ
CBR strengths and moisture contents of the pavement layers. Summaries of pavement layer thicknesses
and general descriptions of materials are given in Table 6.
Moisture contents and CBR strengths are summarised in Tables 7 and 8. Additional measurements
made after overlaying have been included in the tables.
The results of a number of dynamic cone penetrometer tests carried out on the subgrades and expressed
as equivalent in situ CBR values are summarised in Table 9. These tests were carried out to indicate if there
were any significant changes in subgrade strength with depth. The cone penetrometer had a cone angle of
90 °, and the driving impact was provided by a mass of 10 kg falling through 0.5m.
An illustration of the relationship obtained between in situ CBR and rate of penetration is given in
Figure 2. The equation of the regression line is:
L N (CBR) = 5.45 - 1.01 L N (Rate of penetration)
the regression coefficient r 2 is 0.85.
A large increase in strength with depth was recorded on site 7, whilst large decreases in strength
occurred on sites 4 and 8.
Samples of the subgrade materials were taken from the inspection holes and the results o f compaction,
CBR and Casagrande classification 9 carried out in the laboratory are summarised in Table 10. Samples of
subgrade materials from each site were generally bulked together before testing, but where dissimilar
materials occurred on a site, they were tested separately."
4.2 Surface condition assessments
4.2.1 R u t d e p t h s . Measurements of the depths of ruts in the wheelpaths were made at each deflection
test point, as indicated in Figure 1, by placing a 2m straightedge transversely to the centre-line o f the road
and over the test point. The results of these measurements are given later in this report.
3
4 . 2 . 2 Cracking and patching. Summaries of the surface conditions and of patching work carried out
on the sites before overlaying are given in Tables 11 and 12. The asphaltic concrete surfacing in the verge
side wheelpaths of site 3 had suffered severe fatigue cracking and some roadbase and sub-base failure had
also occurred. Extensive areas of cracked surfacing were cut out with a pavement saw and reinstated with
asphaltic concrete. Where roadbase failure and, in the case of section 1, severe displacement at the road
edge had occurred the roadbase and sub-base were replaced with cement-stabilised soil. Traffic was allowed
to run on the soil-cement patches within a few hours of construction. At a later date the top 50 mm of
these patches were cut out and replaced with bituminous material.
4.3 Deflection measurements
Transient deflection tests using the standard TRRL test method 10'11, were made on the twenty test
points o f each section as indicated in Figure 1. Additional tests were made to measure movement of the
feet of the deflection beam during deflection tests. This movement causes a change in position of the
original reference datum and an error in the dial gauge reading 10. Movement of the beam feet during
testing before and after overlaying were of similar magnitude and were generally small. Only on a few
test points on site 2 were movements large enough to cause the indicated deflection to be increased by as
much as 6 x 10 -2 mm. Corrections for feet movement have not been made to deflection readings referred
to in this report.
Provided that the feet of the deflection beam did not sink into 'rich' surface dressings, deflections
measured on the surface dressed sites were not dependent upon pavement temperature and only small
corrections were found to be necessary on a few test points on the other sites.
Deflection measurement made on areas of site 3 before and after patching showed little change in
magnitude. Small decreases were recorded on the full-depth patches and small increases on the asphaltic
concrete surfacing patches.
4.4 Determination of overlay thicknesses
Optical levelling was carried out on each section before overlaying as indicated in Figure 1 to determine
the thickness of overlay at each test point.
5. CONSTRUCTION OF THE OVERLAYS
All the overlays, with the exception of those on sites 5 and 8, were constructed under normal contract
conditions, using plant and methods employed in the main contract for surfacing work, the only difference
being that there was more control of rolling temperatures on the experimental sites. The overlays on sites
5 and 8 were constructed by direct labour.
5.1 Tack coats
Bitumen emulsion was applied at a rate o f approximately 1 litre/m 2 by hand lance to the existing
road surface. Where multiple layer overlays were completed during a second day's work, a very thin tack
coat was used. A discontinuous application of emulsion was made, which was spread by means of a
pneumatic-tyred roller to give a complete covering. It has been found that where this was done a more
reliable bond between the layers was obtained.
4
5.2 Manufacturing and rolling temperatures
Temperatures specified for manufacturing, delivery and rolling of the overlay materials are given in
Table 13. The temperature of each lorry load of material delivered to site was measured and recorded.
Approximately 75 per cent of the loads delivered to all the sites were within the specified temperature
range and only 5 per cent were more than i0°C outside of this range. A large number of loads of material
delivered to site 5 were below the specified temperature, but because of high ambient temperatures and
the relatively slow rate of delivery, compaction was completed at temperatures above the minimum specified
for rolling.
5.3 Laying and compaction
Overlays of 75-125 mm thickness were laid in two layers, except on sites 2, 3 and 4, where 75 m m
thick layers were laid in one lift. Overlays of 150 mm thickness were laid in three 50 m m layers.
Usually one section was completed each day except for the 150 m m thick overlays where the third
layer was added on the second day. In a few instances where a layer was only laid on one lane, the centre-
line edge was cut back before completion of the second lane of the layer.
Typical compaction plant consisted of a tandem steel-wheeled roller of 8 Mg mass and a pneumatic-
tyred roller of 12 Mg mass. The same plant was used on sites 2, 3, 4, 6 and 7. The steel-wheeled roller
was used to do the initial 'break-down' rolling and finishing. Occasionally this method of compact ion was
found to cause shearing marks or cracks in the mat, some of which subsequently opened up during the
early lives of the overlays concerned. The steel-wheeled rollers also left a smooth surface texture.
On sites 3 and 4 the steel-wheeled roller was restricted as far as possible to the compact ion of the cerLtre-
line joint. An unballasted pneumatic-tyred roller, with tyre pressures of 310 kN/m 2 (45 psi) was used to do
the 'breakdown' rolling and a pneumatic-tyred roller of 14 Mg mass with tyre pressures of 620 kN/m 2 (90 psi)
was used to complete the main compaction. A coarse textured surface was formed which has remained
after trafficking.
5.4 Sampling of the overlay materials
Samples of overlay material were taken shortly after mixing and tested in th¢ site laboratory in
accordance with contract requirements. Additional samples for determination of aggregate gradings,
bitumen content and bitumen hardness were also taken.
Samples of the overlay materials were taken from the end of the paver feed screw, approximately 10m
after the beginning and 10m before the end of each section in each lane for all layers. A comparison was
made between different methods of sampling, which included taking samples from the paver hopper , the
end of the paver feed screw and from the laid mat. No significant differences were found between the
analyses of aggregate gradings and bitumen contents for the samples taken by the three methods.
Samples were tested for aggregate grading and bitumen content by the Road Note 10 extraction
bottle method 12. The most common extraction test used on site was the hot extractor method 13. It
was found that in this method tidier could pass the filter paper particularly where hydrated lime had been
used resulting in inaccurate determinations of fdier and bitumen contents. The cause o f this problem was
not investigated. In the Road Note 10 method a centrifuge is used to ensure that no filler is retained in the
extracted bitumen. 5
Bitumen contents for the asphaltic concretes and bitumen macadam basecourses are summarised in
Table 14, the aggregate gradings for the principal mixes laid on sites 1 - 6 are shown in Table 15 and the
analyses for the hot rolled asphalts are summarised in Table 16.
The results show that the gradings of the asphaltic concrete mixes on site 1 were deficient in sand-sized
material. This was a result o f the unavailability of suitable crushed rock and of the very long haul distance
and expense involved in bringing sand to the site.
The 'current ' 20 m m mix laid on sections 1, 2, 7, 8 and 10 on site 2 did not conform to the design mix.
This resulted from the use o f a high frees content sand, which had not been passed through the mixing plant
drier, for determining the laboratory design mix. Despite established procedures the sand grading had been
determined by dry sieving instead of by wet sieving. By chance, the same proportion of times was lost from
the asphalt plant drier during the manufacturing process as was underestimated by dry sieving of the sand,
so that analyses of the laid material gave the same aggregate gradings and bitumen contents as the design
mix specification. The aggregate in the laid material has a lower surface area than the laboratory design
mix and therefore the bi tumen content is effectively too high. This has provided an opportunity to study
the performance of a bitumen-rich mix which is 'critical' in that it is susceptible to deformation under traffic
but should have very good resistance to cracking.
On site 6, unavailability of suitable materials resulted in the dense bitumen macadams being very
similar in grading to the '20 ram' asphaltic concretes, but they contained approximately 0.5 per cent less
bitumen.
Samples of bi tumen were taken from the heater tanks during the construction periods so that changes
in the hardness of the bi tumens during the mixing process could be determined. This subject is referred to
again in Section 6.5 of this report.
6. POST-CONSTRUCTION MEASUREMENTS
In order to relocate the test spots on the overlays directly above those on the old surface, marker nails
were placed at the edge of the pavement before overlaying and the distances to the test points were recorded.
6.1 Compaction of the overlays
As part of the contract requirements cores were cut from the timished overlays to determine the degree
of compact ion achieved.
It was often impossible to cut integral cores from the overlays within a few days of construction
because distortion of the soft material and damage due to shearing at interfaces occurred. Only in a very few
cases was the density of cores less than 97 per cent of the Marshall design density, which was reported to
give air voids in the mixes of between 3 and 5 per cent. However the mean air voids contents of cores cut
f rom sections 1 - 4 and f rom 9--12 on site 5 were 7.4 and 5.7 per cent respectively.
Aggregates used in the overlays were absorptive with values of up to 4 per cent for the time aggregate
used at sites 2 and 3. Calculations of air voids based upon apparent relative density and the relative density
on an oven dried basis gave a difference in air voids content o f 3 per cent. It is recommended that where
aggregates have absorption values of more than one per cent a mean value o f the two relative densities is used 14.
6
It is apparent that accurate determinations of air voids in mixes, particularly with absorptive aggregates,
is a difficult part of the design process. Whilst contractual agreement on the method of calculation can be
reached, determination of the absolute air voids content to allow comparisons between different mixes
laid under different contracts is much more difficult.
6.2 Overlay thickness
The thicknesses of the overlays were determined by optical levelling which was checked by direct
measurement of cores cut at some levelling points in each section.
6.3 Traffic Ioadings
in order to obtain an estimate of the damaging effect of traffic on the sites, axle-load surveys were
carried out by the Kenya Ministry of Transport and Communications using a portable weighbridge developed
by the Overseas Unit of the Transport and Road Research Laboratory 15.
Factors derived from the AASHO Road Test 16 have been used to express all axle loads in terms of an
equivalent number of standard 80 kN axle loads. The equivalency factors used were calculated f rom the
following formula:
Equivalency factor = (axle load in kgf/8160 kgf) 4"5
A summary of the estimated cumulative number of equivalent standard axles carried by the overlays
is given later in this report.
6.4 Surface condition
6.4.1 Ru t d e p t h s . The measurement of rut depths beneath a 2m long straightedge have been made on all
test points. A summary of rutting measured before and after overlaying on site 2 is given in Table 17, whilst
the results for the other sites are given in Table 18. The results for site 2 are reported separately because
of the high bitumen content of the 'current 20 mm' mix. Rutting in this mix has however been minor and
negligible on all other overlays.
6 .4.2 Crack ing . Cracking was assessed by placing a one-metre square frame parallel to the road edge so
that the maximum amount of cracking was enclosed; the test point was within the square and the frame
did not cross the centre-line of the road. Centre-line cracks were included but were recorded separately
because this type of cracking is usually caused by poor construction practice rather than by the effects of
traffic.
In this study photographic records from which measurements can be taken are being compiled. A
35 mm camera and surveying tripod are set up so that the camera is vertically above the centre o f the frame
and transparencies of 'chalked-in' cracks are taken. The length of cracking can be measured f rom scaled
projections of the transparencies.
Coting surveys have been conducted to monitor changes in crack depths. The predominant mode
of failure has been cracking which has propagated down from the surface o f the overlays. Initiation and
development of cracks to the full depths of the overlays has been very variable, bo th within sections and
7
between the different sites. Measurements indicated that only those cracks which were 0.25 nun or more
in width were likely to be o f significant depth during the early lives of the overlays. Cracking measurements
referred to in this report are therefore for cracks which are 0.25 mm or more in width. Care had to be
taken with these measurements because it was found that the width of cracks could change between early
morning and afternoon when the maximum pavement temperature was reached. On site 5 crack widths
decreased during this period by up to 60 per cent, the mean change being approximately 25 per cent.
An indication of the rates of deterioration of the sections due to cracking is given in Table 19 and
Figure 3. Table 19 also gives details of the overlays and shows the number of test points which have
cracked and the mean cracking for the sections in 1978 and 1981. The results for 1978 are included
because until the oil pipeline was opened in 1978 the annual traffic loading on sites 2, 3, 4 and 5 in the
Mombasa direction was less than half of that in the Nairobi direction.
In Figure 3 the mean length of cracking in m / m 2 measured on the test points is plotted against time.
Sections which had mean cracking of less than 0.2 m/m 2 in 1981 are listed separately in the figure.
6 . 4 . 3 S u r f a c e r o u g h n e s s . The sections were not long enough to permit the use of a towed fifth wheel
bump integrator 17 on individual sections. An indication of the mean overall pavement roughness measured
in the four wheelpaths o f each site before and after overlaying for sites 1 to 7 is given in Table 20.
6.5 Ageing of the bitumen in the overlays
Samples of some o f the overlays have been taken periodically to measure changes in the hardness of
the bi tumens in the mixes. Samples f rom a given section have been taken from positions adjacent to each
other over a period of t ime and the bi tumens recovered using standard test methods 13,18.
Results o f penetration (at 25°C) and ring and ball tests are summarised in Figures 4, 5 and 6. The
results show that with the exception of the bi tumen rich mixes on site 2 which have not hardened
appreciably the bitumen in the overlays has hardened considerably. The rate of hardening is similar in
mixes which did and did not comply with aggregate grading specifications. The data shown in Figure 5
indicate that the bitumens were f rom a common source.
Comparisons are shown in Figure 6 of the penetrations of bitumens recovered from the top and
b o t t o m layers of two course overlays taken at various ages from all o f the sites. It can be seen that the
rate of hardening of the bi tumen in the bo t t om layers is only slightly less than in the top layer.
Bitumens recovered from the top 20 to 35 m m of samples taken in 1981 had very similar penetration
values to the full depth top layer samples taken in 1980.
The two most important results to come from this part o f the study are that firstly the bitumen in the
standard mixes hardened very quickly in contrast to the bitumen in the rich mixes and secondly the rich
mixes have remained uncracked despite carrying the heaviest traffic loading. Samples of bitumen recovered
in 1981 had penetrations significantly higher than 50 at 25°C. Additional work is needed to determine the
variability in rate of hardening within these mixes.
8
6.6 Deflection measurements
Transient deflection measurements were repeated on the overlays at the same test point locations as
were used before overlaying. Several surveys were made on the overlays during the first years of service,
the only exception being site 4 which could only be tested at six monthly intervals for 2 years and annually
thereafter.
Temperature-deflection tests were carried out so that, where necessary, deflections could be corrected
to standard deflections associated with a temperature of 35°C measured at a depth o f 40 m m below the
road surface. Details of the test method and typical results for temperature-deflection tests have been
given elsewhere 11.
6.6.1 Strengthening effect of the overlays. An indication of the strengthening effect o f an overlay
can be obtained by comparing the deflections measured on a test point before and after overlaying.
Ideally, deflection, surface condition and traffic loading surveys would be made on a road f rom the
time of construction. This historical data would help to determine the effects o f rainfall on pavement
strength and provide an indication of the rate, as well as the level, o f deterioration. The rate of deterioration
is important because a pavement which has deteriorated slowly may be basically stronger than one which
has deteriorated more rapidly, even though the levels of deterioration at a given t ime may be similar.
In the present study deflection surveys could only be made during a relatively short period of t ime
before the overlays were constructed. The exception was site 4 where surveys were made during a three year
period before overlaying.
Typical examples of the effect of rainfall upon pavement strength, as indicated by deflection
measurements have been given elsewhere 10,19. It is important to correct deflections for climatic effects
when comparing deflection surveys made at different times or when designing overlay thicknesses.
The results of deflection surveys carried out during periods which had similar ra infaUpat tems, have
been used to determine the reductions in deflection due to overlaying.
It was not possible to use this procedure for site 4 and corrections for the effects of rainfall have been
based upon the evidence obtained from tests on the 'control" section and from a similar 1 km long test
site located immediately adjacent to the overlay site 19. These corrections have been applied uniformly
to each wheelpath, but the actual effect of rainfall on pavement strength will vary, depending upon soil
properties, drainage and pavement condition.
The mean reductions in deflections obtained for complete sections of twenty test points are indicated
in Figure 7 where the mean deflection before overlaying is shown next to each symbol. The superimposed
lines were calculate~d from a multiple linear regression analysis, which gave a correlation coefficient (r 2) of
0.93, the equation for the relationship being
D A = 3.6 + 0.818 D B - 0.0027 DBT
where D A = deflection after overlaying
D B = deflection before overlaying
T = overlay thickness 9
Attempts to fit curved relationships resulted in only very minor deviations from the straight lines
shown in Figure 7.
The results for site 1 have not been included in the figure because the poorly graded mixes on this
site gave approximately 12 per cent less reduction in deflection than the mixes on the other sites.
Whilst there is considerable scatter in the results, the dense bitumen macadam base courses 7 laid on
sites 2, 3 and 4 gave approximately 6 per cent less reduction in deflection than the other mixes. These
results have also been omitted from Figure 7.
The curves have been extrapolated in Figure 8 and are recommended for densely graded bituminous
overlays where it is desired to reduce pavement deflections to a given value.
6.7 Radius of curvature of deflected surfacing
It is generally accepted that the measurement of longitudinal radius of curvature together with
deflection provides a better indication of the structural condition of a pavement than the measurement of
deflection alone 20'21. On a surface-dressed roadbase supported directly on the subgrade the radius of
curvature is sensitive to changes in the modulus of the roadbase, whilst deflection is sensitive to changes in
moduli of both the roadbase and subgrade. The product of radius of curvature and deflection (Rd) is
proportional to the modular ratio of the roadbase and subgrade.
Whilst there are considerable differences between the simple model on which these conclusions are
based and the actual trial sections on which there were considerable variations in thickness, quality and
condition of the pavement layers, combined measurements of radius of curvature and deflections would
be expected to give a better representation of pavement strength than would deflection alone.
Radius o f curvature should be dependent upon the modulus of the overlay and would be expected to
give a good indication o f the tensile strains induced in the overlays 22. This in turn should provide some
correlation with the propagation of cracks in a given overlay.
Reliable measurements of radii of curvature were obtained on the sections early in 1979 and again in
1980. Deflection beams were fitted with linear variable differential transformers (LVDTs) in place of the
dial gauges and their output was fed into a chart recorder driven by a pulse generator so that an influence
line was produced from which a measure of radius of curvature could be obtained. The radius of curvature
obtained in this manner is not an absolute one, it is based upon the difference between the maximum
deflection and the deflection obtained when the loading wheels are 125 mm away from the position of
maximum deflection during the transient deflection test where:
L 2 Radius of curvature = _ _ (m)
2d
L = 125 mm
d = differential deflection (x 10 -2 ram)
6.7.1 Deflection-curvature relationships. Regression lines for values of radius of curvature against
deflection for the verge side wheelpaths of the 'control" sections which were not overlaid are shown in
Figure 9. Values o f the regression coefficient r 2 were in the range 0.67 to 0.90, except for site 6, where a
small range of values was recorded. 10
It can be seen from Figure 9 that a wide range of pavement strengths, as indicated by the range of
values of deflection and radius of curvature, can occur within 100 metre long sections. There are also
considerable differences in the deflection-curvature relationships of some of the sites.
An indication of the changes in the deflection-curvature relationships brought about by overlaying
are given in Figures 10 to 12. These figures show for each site a comparison between measurements made
in 1980 on the control section and on a section which, before being overlaid, had deflection characteristics
similar to those of the control section at that time.
Regression analyses of deflections against radius of curvature for all overlays gave correlation
coefficients of r 2 of greater than 0.5 in 85 per cent of cases. The remaining correlations all applied to
cases where a small range of values was measured.
The .results show that for a given overlay, deflection and radius of curvature correlate well enough
to expect that either parameter might correlate With pavement performance and that the lack of curvature
measurements before 1979 should not seriously affect any deflection-performance assessments.
6.7.2 Effect of temperature on deflection-curvature relationships. The effect o f surfacing
temperature on deflections and curvature are indicated in Figure 13 and mean values of deflection,
curvature and their product Rd, for a wheelpath of a section, are shown plotted against the temperature
measured at a depth of 40 mm. These results were obtained from two surveys carried out in 1980 On
consecutive days at different surfacing temperatures.
Deflections do not decrease with increasing temperature but the value of Rd does, indicating that
the radius of curvature is more sensitive to temperature change than is deflection. It can be seen in
Figure 13 that large changes in Rd values can occur, implying large changes in the modular ratio between
the upper and lower (including the subgrade) pavement layers.
From the limited results available it appears that there might be a relationship between the rate of
change of Rd with temperature and the magnitude of Rd. However the gradients o f the Rd-temperature
relationships for overlays thicker than 50 mm are similar up to Rd values of 130 irrespective of
thickness. The exception is the example shown for site 2 which shows that the Rd value for this
bitumen-rich ~ is very sensitive to temperature change.
Radius of curvature appears to give a better indication than deflection of the differences between the
properties of the bitumen-rich mix and the more conventional mixes. However the occurrence of plastic
flow during transient deflection tests 11 gave a similar indication of differences.
7. PERFORMANCE OF THE O V E R L A Y S
The pavements were generally in good structural condition before overlaying in that only a moderate
amount of rutting had occurred. Part of site 2 exhibited the largest mean rut depths but these ruts had
developed over a long period of time, indicating a basically sound pavement. Some failures had occurred
on site 3 as referred to in Section 4.2.2 of this report.
11
It has been suggested that a roughness value of 3,750 mm/km, measured with a towed bump
integrator, is the level of roughness at which overlaying or reconstruction should be carried out on trunk
roads in Kenya 23. Sites 2, 4 and 5 had levels of roughness within 600 mm[km of this value. There are
likely to be many sections of the paved road network in Kenya where the main requirement will be to
reduce the roughness of the road surface.
It has been shown elsewhere 19 that rougtmess can be more indicative of surfacing failure and the
quality of patching work than of serious structural deterioration. It is more appropriate to overlay a road
which only requires the restoration o f riding quality than it i s t o reconstruct it.
7.1 General observations
7.1.1 Site 1. Traffic restrictions imposed because of pavement failure elsewhere along the road on
which the overlays were situated resulted in little or no traffic being carried by the overlays for a period
o f approximately two years from 1977 to 1979.
The particle size distribution of the asphaltic concretes on this site did not conform to the specifications
(see Section 5.4) and for this reason the performances of the overlays are not directly comparable with
those of the asphaltic concrete overlays on the other sites.
The overlay of dense bi tumen-macadam basecourse is extensively cracked. This 75 mm thick
overlay was laid in two layers on separate days, without a tack coat and a very poor bond was achieved
between the two layers. This lack of bond allowed excessive flexure of the top layer of the overlay to
occur under traffic, causing it to crack. There is a good bond between the original road surface and the
bo t tom layer o f the overlay which, in the few locations investigated, is in good condition. This overlay
would have performed much more satisfactorily if it had been placed in one layer or at least had a thin
tack coat applied between layers.
7 . 1 . 2 S i tes 2 a n d 3. The two hot-rolled asphalt overlays, which were expected to have long lives, have
cracked quite extensively. These mixes derive their strength from the sand-Idler-bitumen matrix and
because a softer bi tumen than is recommended for UK conditions was used it was thought that a higher
filler to binder ratio should be used to resist deformation under traffic at high pavement temperatures.
A f'fller to binder ratio of approximately 1.7:1 in the mixes appears to have reduced their resistance to
cracking.
On all the sites where dense bi tumen macadam basecourse material has been laid some segregation has
occurred. This has resulted in cracking in these overlays because of the low strength of accumulations of
coarse aggregates with normal bi tumen contents.
7 . 1 . 3 S i t e 4 . The filler to binder ratio for the hot rolled asphalts was approximately 1.15:1. Only one
test point in the two sections with this more flexible mix has cracking at the surface after 3 years service.
There is also no significant deformation on these sections.
7 . 1 . 4 S i t e 5. Cracks formed very soon after construction in asphaltic concretes of up to 150 mm
thickness. The appearance o f the cracks suggested reflection cracking from the soil-cement roadbase but
the cracks developed f rom the surface of the overlays and inspection of the surface of the~roadbase under
12
the cracked overlay failed to identify any cracks which might cause this behaviour; in fact sound blocks
of roadbase were cut from beneath cracked surfacing. A factor which may have contributed to the
development of these cracks was the generally higher voids content o f the overlay materials, as stated
in Section 6.1 of this report. The higher voids content may well have resulted in a reduction in the tensile
strength of the material 24.
During cycles of thermally induced movement the asphalt expanded against material which had
been blown into the cracks from the shoulders of the road, resulting in attrition at the edges of the cracks.
Where the cracks have propagated down to the old surface dressing, movement of the edges of the
asphalt has caused the surface dressing to crack. Two areas in section 2 now require patching as a result of
water penetrating through cracks formed in this way. Without the overlay the original surface dressing
would not have cracked at this time. To prevent the cracks widening and water penetrating to the
roadbase an application of a seal soon after construction of the overlay would have been necessary.
7 .1 .5 Si tes 6 and 7. The traffic loadings on these sites were reduced to a very low value with the cessation
of traffic to and from Zambia and Tanzania approximately one and three years respectively after
construction of the overlays. Traffic on site 6 is almost solely generated by the transportation of sugar
cane to the factory at Ramisi. There is negligible traffic on site 7.
7 .1 .6 Si te 8. It was not possible to manufacture continuously graded mixes to specification with the
materials available at this site. The hot rolled asphalt was by comparison, very easy to manufacture and
control. The dense bitumen macadams laid on sites 2, 3 and 4 were very similar but a much greater
variation in aggregate gradings and a greater variation in bitumen content occurred on site 8. In general
the mix has a higher percentage of filler and of aggregate finer than 300/~m, and approximately 0.5 per
cent more bitumen. In the slow lane the mixes have a 'rich' appearance and the DBM mixes have not
suffered the type of cracking caused by segregation which has occurred on the other sites. In the lightly
trafficked fast lane the mixes have a 'drier' appearance and some cracking has occurred, particularly in the
hot rolled asphalt.
7.2 Relationships between measured parameters and cracking
Twenty-eight of the overlay sections were uncracked or had mean cracking of less than 0.2 m / m 2
in early 1981. For the remaining forty overlay sections no correlation had been found between deflection,
radius of curvature or traffic loading and the development of cracking.
Examples are given in Figures 14 and 15 of comparisons between traffic (esa) carried before test
points reached a nominal 'critical' condition (defined as 0.2 m/m 2 of cracking wider than 0.25 ram) and
the predicted number of equivalent standard axles carried to a critical condition obtained from design
charts used in the United Kingdom 4. These design charts relate overlay thickness and deflection before
overlay to the traffic carrying capability of the overlay for different types of pavement.
It can be seen that no pattern is discernible in Figures 14 and 15. This is not surprising because of the
way in which the overlays in Kenya have deteriorated, where cracks have propagated from the surface of
the overlays at varying rates even at individual test points. This is quite different from the normal form of
failure in Britian, which is deformation. This behaviour has made it impossible to define a meaningful
'critical condition' for the Kenyan overlays.
13
There has been no consistent relationship between traffic loading and the development of cracking.
The data in Table 19 shows that on sites 1, 2 and 5 more cracking has generally developed in the more
heavily trafficked lane whilst for sites 3, 4 and 8 the reverse tends to be true.
On site 1 there has been a tendency for linear cracking to develop more rapidly as overlay thickness
decreases. It has taken longer for cracks to penetrate through the full depth of the thicker overlays. On
site 5 where cracks have formed the maximum rate of penetration for eight of the overlays has been of the
order of 22 m m per year, but this particular rate of penetration is unique to this site.
8. DISCUSSION OF RESULTS
The outstanding features of the behaviour of the overlays have been the initiation of cracking from the
surface, the hardening of the binder through the depth of the overlays and the importance of the properties
of the overlay materials.
Cracking has occurred very early in the lives of overlays up to 160 mm in thickness. Similar
behaviour has been observed elsewhere 25 but whilst in this latter case thick overlays with lower deflections
cracked first the development of cracking in the overlays in the Kenya study has been more random. The
occurrence of cracks which have developed from or near to the top of bituminous surfacings has recently
been reported in the United Kingdom 26.
No satisfactory explanation for this behaviour can be given at present. The effect which temperature
may be having upon the overlays is indicated by the way in which crack widths change considerably during
diurnal cycles. It is possible that the application of particular wheel loads and configurations at certain
pavement temperatures coupled with hardening o f the binder at the surface can be more significant in
causing this cracking than the cumulative equivalent standard axles carried by the pavement.
The importance of the properties of the overlay materials has been indicated in several examples.
Hot rolled asphalts laid on sites 2 and 3 with 'high' filler to binder ratios cracked at a very early age.
Similar materials but with lower filler to binder ratios laid on sites 4, 6 and the slow lane of site 8 have
been much more resistent to cracking. Dense bitumen macadam basecourses laid on sites 1, 2, 3 and 4
have not been very durable, whilst the denser, richer mixes on site 8 have performed well.
A most important indication is given by the bitumen-rich mix on site 2. This mix has been very
resistant to cracking and there is a marked tendency for any fine cracks to be full of bitumen. Significantly
this is the only mix which has not suffered hardening of the bitumen binder.
It appears that low air voids are required to reduce bitumen hardening, but as in the case on site 2
the b i tumen film thickness around the aggregate will increase as air voids are filled with bitumen. The
thicker bi tumen film should make the mix more tolerant of induced tensile strains and reduce the
likelihood of cracking.
A mix of the type used on site 2 offers good resistance to cracking, however this mix is at the
upper limit for bi tumen content beyond which severe rutting could be expected. The tolerances required
to reproduce this mix would be too restrictive for normal production methods.
14
9. RECOMMENDATIONS FOR O V E R L A Y DESIGN IN K E N Y A
The mechanism by which the cracking is initiated in the overlays is not fully understood and this prevents
the recommendation of a simple,reliable design method.
Very few conventional overlays can be expected to carry more traffic than that predicted f rom design
curves used in Britain 8 before developing 0.2 m/m 2 of cracking wider than 0.25 mm. Significant areas
of such an overlay can be expected to crack at an early stage and require resealing.
There has been little difference in the performances of the various types of asphaltic concretes laid
in this study provided they were within specification. The hot rolled asphalts which had frier to binder
ratios close to unity have performed well and are recommended for further consideration in areas, such as
the coastal strip, where sand of the correct grading is available and good quality aggregate is scarce.
Dense bitumen macadam basecourse mixes have not been as durable as the denser materials, but
have nonetheless given over six years of service on heavily trafficked roads and are still serviceable. These
mixes, if surface dressed as part of the construction process, may offer a cost-effective method of overlaying.
The dense bitumen macadam wearing course mixes can be expected to give better performance.
Examination of Tables 6 to 9 and of data published elsewhere 19,27,28 will show the wide variations
which occur in pavement layer thicknesses and strengths. The indications are that to design overlays on
the basis of variations in in situ pavement properties will not be precise in most developing countries
because the amount of work and expense which would be involved is prohibitive. Sufficient testing must
however be made to provide the engineer with a good indication of pavement strength and yariability.
The maximum use of surface condition assessments (particularly of historical data as discussed in Section 6.6.1
of this report) backed up with deflection-curvature measurements and pavement investigation pits still
appears to be the only practical means of assessing the present condition of a pavement.
It will be seen that in Figure 8 a minimum overlay thickness of 25 m m has been indicated. Overlay
thickness should be regarded as being in addition to any regulation of the existing road surface.
It is recommended that for the immediate future deflection measurements and curves published in
Britain 4 (or others which give similar thickness design) are used to determine overlay thicknesses and that
provision is made to reseal where cracks occur.
Where asphaltic concrete is designed by the Marshall test method the emphasis should not be placed
on attaining high stabilities, which imply lower bitumen contents. Where the requirement for thick overlays
is indicated the use of an unbound crushed rock regulating course should be considered, particularly on
roads with soil-cement roadbases. This could be cost-effective and may also prevent reflection cracking
from the roadbase.
10. FUTURE W O R K
During future overlay programmes monitoring of changes in surface condition should be undertaken
together with coring on cracked areas to monitor deterioration. Further work to determine a more effective
combination of overlay materials appears to offer the best improvement in overlay design at the present time.
15
The design of a crack resistant overlay material should be attempted. Such a material could be a
'bi tumen-rich' gap or semi-gap graded asphalt into which precoated chippings could be rolled. A 25 mm
thick layer of this material laid on a more stable, cheaper mix would be to some extent self-limiting in
terms o f possible rutting and may prevent the initiation of cracking.
A 'rich' asphaltic concrete may also be a feasible alternative. The specification of a bitumen content
above the Marshall op t imum for this thin wearing course can be checked in relation to the sensitivity of
the Marshall properties to bitumen content. The behaviour of the mix during compaction trials will
provide a valuable assessment of the material. Compaction of this type of mix with steel-wheeled rollers is
likely to produce a very smooth finish. More use of pneumatic-tyred rollers should be seriously considered
in an a t tempt to acquire a coarse surface texture for anti-skid properties.
Lower Idler contents than those found in the asphaltic concrete overlays laid in the current trials
may result in more durable mixes.
11. CONCLUSIONS
. The overlays have been effective in providing good riding quality and have now remained serviceable
for up to seven years under heavy traffic despite cracking which appeared early in the lives of some
of the overlays.
. Cracking has been the predominant form of deterioration of the overlays. Rutting has been
negligible even on or near areas which were heavily repaired before overlaying.
3. Cracking of asphalt overlays up to 160 mm in thickness has occurred after very short service lives.
4 . A feature of the cracking has been its development from the surface down through the overlays at
varying rates even in a nominally uniform overlay.
. Temperature changes can cause crack widths to vary considerably during a day. This behaviour can
lead to considerable attrition of the edges of the cracks.
. Crack propagation down through the thinner overlays (less than 50 mm) has been quite rapid,
occurring within 2 years. On site 5 cracking in the overlay has eventually broken through the
original surface dressing which would have remained intact had the overlay been omitted.
7. No correlations have been found between deflection measurements (and by inference radius of
curvature), overlay thickness, traffic loading and cracking in the overlays.
. Considerable hardening of the bitumen in the overlays occurred. Samples of nominally 80 -100
penetration grade bitumens taken from the heater tanks and recovered after mixing had
penetrations of 70--83 and 43--60 respectively.
Bitumen recovered from the overlays five years after construction had penetrations in the
range 16 -25 . Hardening occurred throughout the depth of two layer overlays of 100 mm thickness.
The bitumen-rich mix laid on site 2 had not hardened significantly after 6 years in service.
1 6
. Care must be exercised to prevent shear cracks forming in the overlay during compaction with steel-
wheeled rollers. Pneumatic-tyred rollers avoided this type of cracking and provided a very good
surface texture.
Compaction trials at the beginning of a surfacing contract are essential to ensure that mix properties
are correct and that the compaction method is satisfactory.
10. The overlays were effective in reducing deflections despite high pavement temperatures. The dense
asphaltic concretes and hot roiled asphalts were the most effective mixes in reducing deflections.
11. Conventional overlays whose thicknesses have been derived from deflection-overlay thickness design
charts similar to those used in the United Kingdom should give satisfactory performance provided
that resealing is carried out if cracks occur at an early stage. It is important that resealing is carried
out before cracks have penetrated to the full depth of the overlay and before crack widening due to
attrition has occurred.
12. Further work is required to design an overlay system and materials which resist cracking at the surface.
12. ACKNOWLEDGEMENTS
The authors are indebted to the Government of the Republic of Kenya for allowing and organising the
construction of the overlay experiments.
Particular thanks are due to Mr S J Mbugua, Permanent Secretary, Ministry of Transport and
Communications and his staff especially those in the Roads and Materials Branches, for the help and
cooperation given during this study.
The work described in this report forms part of the research programme of the Overseas Unit
(Unit Head: Mr J N Bulman) of the Transport and Road Research Laboratory.
13. REFERENCES
. HIGHWAY RESEARCH BOARD. Design of overlays and pavement rehabilitation. Highway
Research Record 300. Washington, I969.
. HIGHWAY RESEARCH BOARD. Evaluation of pavements by deflection studies for maintenance
purposes. Highway Research Record 129. Washington, 1966.
. CANADIAN GOOD ROADS ASSOCIATION. A guide to the structural design of flexible and rigid
pavements in Canada. Canadian Good Roads Association Pavement Design and Evaluation Committee.
Ottawa, 1965 (Canadian Good Roads Association).
. KENNEDY, C K and N W LISTER. Prediction of pavement performance and the design of overlays.
Department of the Environment Department of Transport, TRRL Report LR 833. Crowthorne,
1978 (Transport and Road Research Laboratory).
17
.
.
.
.
.
10.
11.
12.
13.
14.
15.
16.
17.
ORGANISATION FOR ECONOMIC COOPERATION AND DEVELOPMENT. Road Strengthening.
A report prepared by an OECD road research group. Paris, 1976 (Organisation for Economic
Cooperation and Development).
BRITISH STANDARDS INSTITUTION. Rolled asphalt (hot process) for roads and other paved
areas. British Standard No. 594 : 1973. London, 1973 (British Standards Institution).
BRITISH STANDARDS INSTITUTION. Coated macadam for roads and other paved areas.
British Standard No. 4987 : 1973. London, 1973 (British Standards Institution).
LISTER, N W. Deflection criteria for flexible pavements and the design of overlays. Proc. 3rd
International Conference on the Structural Design of Asphalt Pavements, Vol. 1, 1972 (University
of Michigan, Ann Arbor), pp 1206--26.
BRITISH STANDARDS INSTITUTION. Methods of test for soils for civil engineering purposes.
British Standard No. 1377 : 1975. London, 1975 (British Standards Institution).
SMITH, H R and C R JONES. Measurement of pavement deflections in tropical and sub-tropical
climates. Department of the Environment Department of Transport, TRRL Report LR 935.
Crowthorne, 1980 (Transport and Road Research Laboratory).
JONES, C R and H R SMITH. Deflection-temperature relationships for bituminous road surfacings
in Kenya. Department of the Environment Department of Transport, TRRL Report LR 936.
Crowthorne, 1980 (Transport and Road Research Laboratory).
ROAD RESEARCH LABORATORY. Rapid methods of analysis for bituminous road materials.
Ministry of Transport, RoadNote 10. Second Edition. London, 1967 (H M Stationery Office).
BRITISH STANDARDS INSTITUTION. Specification for sampling and examination of bituminous
mixtures for roads and other paved areas. Part 2. Testing. British Standard No. 598 : Part 2 : 1974.
London, 1974 (British Standards Institution).
BRITISH STANDARDS INSTITUTION. Methods for sampling and testing of mineral aggregates,
sands and Idlers. Part 2. Physical properties. British Standard No. 812 : Part 2 : 1975.
London, 1975 (British Standards Institution).
POTOCKI, F P. A portable wheel-weighing unit and data recorder. Department of the Environment, RRL Report LR 391. Crowthorne, 1971 (Road Research Laboratory).
HIGHWAY RESEARCH BOARD. The AASHO Road Test Report 5. Pavement Research. Highway Research Board Special Report 61E. Washington DC, 1962 (National Research Council).
JORDAN, P G and J C YOUNG. Developments in the calibration and use of the Bump-integrator
for ride assessment. Department o f the Environment Department of Transport, TRRL Report SR 604. Crowthorne, 1980 (Transport and Road Research Laboratory).
1 8
18.
19.
20.
21.
22.
23.
4.
25.
26.
27.
28.
INSTITUTE OF PETROLEUM. IP standards for petroleum and its products. Part 1 : Methods of
analysis and testing. London, 1978 (Institute of Petroleum), 37th Edition.
SMITH, H R, T E JONES and C R JONES. Performance of sections of the Nairobi to Mombasa
road in Kenya. Department of the Environment Department of Transport, TRRL Report LR 886.
Crowthorne, 1980 (Transport and Road Research Laboratory).
LEGER, Ph and P AUTRET. The use of deflection measurements for the structural design and
supervision of pavements. Proc. Third Int. Conf. on the Structural Design of Asphalt Pavements.
London, 1972. Ann Arbor, 1972 (University of Michigan).
NATIONAL INSTITUTE FOR ROAD RESEARCH. The measurement of deflection and curvature
of road surfaces. CSIR Manual K16, Pretoria, South Africa, 1970.
HUANG, Y H. Deflection and curvature as criteria for flexible pavement design and evaluation.
Paper presented at 50th Annual Meeting. Highway Research Board. Washington DC, 1971.
HODGES, J W, J ROLT and T E JONES. The Kenya Road Transport Cost Study: research on road
deterioration. Department of the Environment, TRRL Report LR 673. Crowthorne, 1975 (Transport
and Road Research Laboratory).
MONISMITH, C L. Design considerations for asphalt pavements. Proc. of the 1st Conf. on Asphalt
Pavements for South Africa. July 28 - August 1st 1969. CAPSA, Durban.
GRANT, M C, C P MARAIS and D GUYS. An investigation of an asphalt overlay on a lightly
trafficked road showing premature cracking. Proc. Third Conf. on Asphalt Pavements for Southern
Africa University of Natal, Durban, South Africa 1979.
THROWER, E N. A parametric study of a fatigue prediction model for bituminous road
pavements. Department of the Environment Department of Transport, TRRL Report LR 892.
Crowthorne, 1979 (Transport and Road Research Laboratory).
JONES, C R and H R SMITH. Tensile and compressive strength Of some stabilised road bases in
Kenya. Department of the Environment Department of Transport, TRRL Report SR 623.
Crowthorne, 1980 (Transport and Road Research Laboratory).
BULMAN, J N and H R SMITH. Pavement performance and deflection studies on Malaysian roads.
Department of the Environment Department of Transport, TRRL Report LR 795. Crowthorne,
1977 (Transport and Road Research Laboratory).
19
TABLE 1
Locations of overlay sites
Site No. Road No. Location Date overlaid
1 A104 90 km North of Nakuru at Timboroa September 1973
December 1974 to 2 A109 2 km North of C97-A109 Junction
March 1975
3 A109 2 km South of C97-A109 Junction January - February 1975
4 A109 132 km South of Nairobi near Emali January 1977
5 A109 356 krn South o f Nairobi at Maungu September 1973 to January 1974
6 A 14 62 km South of Mombasa at Ramisi February 1974
7 A14 75 km South of Mombasa October 1973
8 A 2 Thika-bound carriageway at Ruaraka August 1975
TABLE 2
Summary of rainfall data
Annual rainfall at the experimental sites t
Site No. mm
i 1973 I 1974 1975 1976 1977 1978 1979 1980
1 1240 1450 1940 650 1930 1110 1990" 1370
790 2 and 3 480 740 520 350 820 770 490*
4 - 580 340 470 820 1100 1080 410
5 307 360 120 40 340 530 240 260
6 1500 890 1000 850 1470 1710 3100 845*
7 930 920 840 1010 1350 1660 1720 873*
8 600 880 660 660 1470 1080 960 900
t Supplied by Kenya Meteorological Department * Excluding rainfall in December 1980
2 0
TABLE 3
Specification for modified hot rolled asphalt 6
in.
BS sieve size
l n l l l
1 25.4
¾ 19.1
½ 12.7
3/16 4.8
No. 7 2.4
No. 25 0.6
No. 72 0.2
No. 200 0.075
Coarse Aggregate
Grading of aggregates per cent passing sieve size
Fine Aggregate
100
85-100
0-60
100
95-100
75-100
15-60
0-5
Bitumen content
Mortar only Stability (kN) Flow (mm)
Coarse aggregate content (per cent)
Voids in mix (per cent)
Voids filled with bitumen (per cent)
From Marshall tests on mortar only
3.6 minimum 2.5--4
45-50 (see Table 16)
4-10
60 minimum
Filler to bitumen ratio 1.3:1
21
TABLE 4
Specifications for asphaltic concretes and dense bitumen macadam
Nominal maximum size stone and per cent passing sieve
Kenya Ministry of Transport Dense bitumen- and Communications macadam basecourse 7
Asphaltic concrete
BS 1621: BS 4987: BS sieve size Current (1973) Old (pre 1973) 1961" 1973
specification specification Table 5 Table 25
in. m m 20 mm 13 mm 20 mm 13 mm 19 mm 20 mm
28 1 25.4
20 ¾ 19.1
14 ½ 12.7
10 3/8 9.5
¼ 6.4 6.3
3/16 4.8 3.35
1/8 3.2 No. 7 2.4 No. 14 1.2 No. 36 0.43
0.30 No. 200 0.075
100
8 5 - 1 0 0
75--90
65--80
4 5 - 6 5
3 5 - 5 5 30---45 2 0 - 3 3
100
8 5 - 1 0 0
7 5 - 9 5
50--70
40--60 33 - 5 0 21--35
100
85--100
75--90
65--80
45--65
3 0 - 5 0
10--22
100
85 -100
75-95
5 0 - 7 0
3 5 - 5 5
12-23
100
9 5 - 1 0 0
7 0 - 9 0
55 -75 40--60
25--40
15 -30
100
95 -100
65 -85
52-72
39-55
32-46
7 -21 2 - 8 4 - 1 0 4--10 4--8 4 - 8 3---6
Bitumen content Designed by Marshall method 4 . 4 - 4.6 t - (per cent) (50 blow test) 5.4 5.4
Voids in mix 3 - 5
(per cent)
Voids in mineral aggregate 19 maximum (per cent)
Voids Idled with bitumen 7 5 - 8 2 (per cent)
Stability (kN) 3.6 minimum
Flow (mm) 2--4
* Laid on site 1 only.
t 0.5 per cent higher than in BS 4987 : 1973
22
O
2~
, , ' -N . .1
< o
O
O
£
0 0 0 ~ 0 0
E - E
N
#
O
N
I
Z
O
I I I I
I. I 1 1
I I I I
0
1 1 ' 1 1
Ox
0 " . - . '
~ o
~.~ ~.
# E
0
I
I I
O
I
O O
I
O O
1
I
O
I
O O
I
O O
I
O O
I
1
O
I t'¢3
O
I t',l
O O O O
I I
O O
I
O O
I
O O
I I
O O
I
O O
I
O O
I
[..~ [--~
I I I
I I
I )
~ ' ) 0 0 0
Lr ) '~0 t ~.- o o
I I
I I
I I
I I
o = ~ , ~ O ~ ~
c~l 0.)
0
" 0
" 0
o
2 3
TABLE 6
Details of existing roads
Site No.
2
3
4
Surfacing Roadbase Sub-base Fill material
Type
Multiple surface dressing
Multiple surface dressing
Asphaltic concrete
Multiple surface dressing
Multiple surface dressing
Asphaltic concrete
Asphaltic concrete
Multiple surface dressing
Thickness Material
LilTle
20 stabilised { gravel
Crushed 26
rock
27 Quartzitic gravel
Cement 27 stabilised
gravel
Cement 37 stabilised
gravel
Cement 28 stabilised
gravel
Cement 27 stabilised
gravel
Cement 17 stabilised
gravel
Thickness (ram)
Mean] Range
121 113-128
185 160-220
132 80--155
150 130-16G
132 110-163
124 109-137
116 100-127
138 120-159
Material
LilTle
stabilised gravel
Gravel
Cement stabilised gravel
Gravel
Comp- ! acted subgrade
Gravel
Gravel
Gravel
Thickness (mm)
Mean I Range
121 93--193
212 153--280
137 107-180
109 80--170
131 83--180
125 111-160
134 103-177
i99 135-225
Material
Gravel 156
rhickness(mm)
Mean Range
50-223
"~ The pavement was constructed on top of an existing road, details of which are given below.
Site No.
Surfacing
Thickness Type
1TI1TI
Surface [ _ dressing
i
Roadbase
Material
Cement stabilised gravel
Thickness (mm)
Mean Range
132 90- i87
Sub-base
Material
Gravel
Thickness (mm)
Mean Range
135 87-200
Fill material
Thickness(mm) Material
Mean Range
Clay 156 47-500 subgrade
2 4
. .1 o
I ~o
°~ o ~ o-,
I t-:
~ ~ ÷ ~ I t ~ + . - I
I I I I I I
+ 0 0
I
I I I I
.9.
¢-~ J O~ , -~ t~. t¢~ , - , O . ,..-,
o ~
÷ + & + 0 0 & ÷ 0
83
0 + -I- .4- + ~' 0 0 0 0 ~ o t o o o ,-., , ~ I I I
- I I I I
e ~
o-, o o , , o-, o-, o o o
Z
I
E
u, _~ o ,
I
O~
°~ o ~
I'
0 .4-
¢I1 ~ +
Z
26
TABLE 8
In situ properties of subgrades
Site No. Number o f
tests
CBR (per cent)
Mean Range
Moisture content (per cent)
Mean Range
1 42 29 21 --47 31.1 26 .7 -35 .3
2 48 10 5 - 1 9 18.3 11.0-26.1
3 37 7 2 - 1 2 30.2 23 .1-35.4
11 --31 19.8 18.5-22.6
17 -85 7.8 4 .2-11.8
15--94 6.4 3 .5-10.8
6 - 6 4 5.1 4 .2-5 .8
8 - 5 4 25.8 19.5-28.4
4 29 20
5 69 47
6 47 42
7 24 39
8 14 22
TABLE 9
In situ subgrade strengths measured with a penetrometer
Site No. Number of
tests
CBR at subgrade surface (per cent)
Mean Standard deviation
Range
CBR at 0.5m below subgrade surface (per cent)
Mean Standard deviation
Range
1 17 20 5.1 15-35 15 8.2 6 - 3 2
2 27 8 3.7 4 - 1 6 9 3.9 3 - 1 5
3 21 6 2.2 4 - 1 1 7 2.8 3 - 1 7
4 20 19 11 -35 9 4.2 5 -25 5.4
39.9 5 11 59 22 -155 - - -
6 -12 34 17.3 10--66 27 17.4 10--66
7 8 27 5.1 2 1 - 3 5 48 7.5 39--64
8 5 22 7.2 13-31 8 2.5 6 - 1 2
2 6
n n
b
O
b
r ~
• i v ~ ¢~'1 , ~ ~ ~ - ~ ~t" C~ ~ o o ~t '
b ~
N
¢.)
¢..)
~ )
z z
o
¢)
27
T A B L E 1 1
Condi t ion of road surfaces before overlaying
Site No. Condi t ion o f road surface before overlaying
1 6 pa tches o f 26m 2 to ta l area. Negligible cracking.
2 No patching, negligible cracking, some large deformat ions .
Considerable areas o f asphalt ic concre te surfacing, roadbase and sub-base layers 3
rep laced (see Table 12). Widespread fatigue cracking in verge side wheelpaths.
Surface dressing severely cracked before par t ia l resealing in 1974. Section 7, ch 85 4 to the end o f Sec t ion 10 was no t resealed, the old surfacing was extensively cracked.
Loose mate r ia l was replaced w i th asphalt ic concrete before overlaying.
5 Uncracked b i tumen- r i ch surface dressing.
6 Minor cracking. Sect ions 2 and 3 had areas o f 6 and 5m 2 respectively o f fine cracking.
7 Fine cracks. Mean cracking app rox ima te ly 0.3 m / m 2 in the wheelpaths.
8 Extensive fine cracking in the slow lane. One or two small areas o f crazed surfac ingin each sec t ion rep laced wi th b i tuminous mater ia l before overlaying.
TABLE 12
Pre-overlay patching on site 3
Area re ins ta ted (per cent)
Sec t ion No. Roadbase Surfacing
Towards M o m b a s a Towards Nairobi Towards Mombasa Towards Nairobi
1 - 4 . 6 - 2.0
2 - 3.7 0.1 2.7
3 -- 1.2 -- --
4 -- -- -- 2.6
5 -- -- -- 0.2
6 -- 1.5 1.8 0.9
7 -- 7.0 3.7 1.4
8 -- -- 8.3 2.0
9 -- -- 3.2 2.0
10 - - 1 . 0 6.5 1.7
1 1 " - - - - 6 . 5 2 . 9
* Not over la id
2 8
TABLE 13
Temperatures specified for manufacture and rolling of bituminous materials
Material
Asphaltic concrete 80-100 penetration bitumen
Dense bitumen macadam 80-100 penetration bitumen
Modified hot rolled asphalt 60-70 penetration bitumen
Mixing
Aggregate Bmder
Mill. Max.
140 160
120 140
150 175
Temperature °C
Delivery
Min. Max.
120 140
115 135
125 150
Mill. Max.
140 150
130 160
150 165
Rolling
Min.
85
80
90
29
TABLE 14
Summary of analysis results
Site No.
2
4
6
Overlay material
Current (1973) 20 m m AC Current (1973) 13 m m AC Old (pre 1973) 20 mm AC DBM BS 1621 1961
Current (1973) 20 m m AC Current (1973) 13 m m AC Old (pre 1973) 20 m m AC DBM BS 4987 1973
Current (1973) 20 m m AC Current (1973) 13 mm AC Old (pre 1973) 20 m m AC DBM BS 4987 1973
Current (1973) 20 m m AC Current (1973) 13 m m AC Old (pre 1973) 20 m m AC DBM BS 4987 1973
Current (1973) 13 m m AC Old (pre 1973) 13 m m AC Bitumen -- Gravel
Current (1973) 20 m m AC Current (1973) 13 m m AC Old (pre 1973) 20 m m AC DBM BS 4987 1973
Specified bitumen content
(per cent)
6 . 0 ± 0 . 4 6 . 8 ± 0 . 4 5 . 6 ± 0 . 4 4 . 9 ± 0 . 5
5 . 9 ± 0 . 4 6 . 2 ± 0 . 4 6 . 2 ± 0 . 4 5 . 0 ± 0 . 4
5 . 9 ± 0 . 4 6 . 2 ± 0 . 4 6 . 2 ± 0 . 4 5 . 0 ± 0 . 4
5 . 5 ± 0 . 4 5 . 3 ± 0 . 4 5 . 0 ± 0 . 4 5 . 0 ± 0 . 4
6 . 9 ± 0 . 4 6 . 7 ± 0 . 4
6 . 0 ± 0 . 4 5 . 9 ± 0 . 4 5 . 8 ± 0 . 4 5 . 0 ± 0 . 4
7 Current (1973) 20 m m AC 6.0 + 0.4
8 DBM BS 4987 i973 4.9 + 0.5
Number of samples
Mean
14 6.0 5 6,7 4 5.5 4 4.7
23 5.6 4 6.1 4 6.1 4 4.9
24 5.9 4 6.0 4 5.9 4 5.0
25 5.4 5 5.2 6 4.9 6 4.8
35 7.3 5 6.2
18 6.7
16 6.0 2 2 4 5.5
Actual bitumen content (per cent)
Range
5.5--6.3 6 .4-7 .2 5.3-5.7 4.4-5.1
5.0--6.3 6.0--6.2 5,8--6.4 4 .9-5 .0
5.7-6.7 5.8-6.3 5.7--6.0 4 .6-5 .4
5.0-5.7 5.2-5.3 4.6-5.1 4 .7-5 .0
6 .0-8 .0 5.6-7.5 5 .4-8 .4
5.5--6.6 5.9, 5.9 5.9, 6.2 4 .8-5 .9
No samples taken at this site
6 5.4 [ 5 .1-5.7
30
TABLE 15
Summary of grading analyses for current (1973) asphaltic concretes
Current Mix type Current nominal 20 mm nominal
1 3 m m
Site No. ] 1 2 3 4 6 5
No. samples [ 13 23 24 26 15 35
BS sieve size (in) (mm)
1 25.4
¾ 19.1
½ 12.7
3/8 9.5
3/16 4.8
No. 7 2.4
No. I4 1.2
No. 36 0.43
No. 200 0.075
Percentage of aggregate passing sieve size
100
100
90 -96
80 -90
65 - 8 4
47 -59
32--40
16-22
4 - 7
100
95 -100
83 - 9 4
76 -86
58-71
4 6 - 5 8
39 -48
25 -33
6 - 1 3
100
9 3 - i 0 0
8 5 - 9 3
7 8 - 8 6
64 -71
52-61
3 9 - 4 6
2 2 - 3 0
7 -1 1
100
9 9 - 1 0 0
8 5 - 9 4
73 - 8 5
5 6 - 6 8
4 7 - 5 6
3 9 - 4 8
2 4 - 3 0
6 - 1 0
100
90--100
75--85
68--81
51--69
42--53
34--44
22--27
6--9
100
9 6 - 1 0 0
8 2 - 9 6
4 9 - 7 8
3 9 - 6 0
3 2 - 4 9
2 4 - 3 5
7 - 1 1
31
TABLE 16
Summary of analysis results for hot rolled asphalt
Site No. 2 3
Number of samples 4 5
Mix constituents
Coarse aggregate (per cent)
Filler (per cent)
Bitumen content (per cent)
Filler: Bitumen ratio
Actual Target
Mean Range
48 44.6 42.7--46.0
7.7 9.9 8.5--10.0
5.9 6.1 6 .0 -6 .2
1.3
Correctedt
Mean Range
48
9 . 6 8 .2 -10 .2
5.8 5 .7 -5 .9
1.7
Target
48
7.7
5.9
1.3
Actual Correctedt
Mean Range Mean Range
45.3 42.7---47.5 48 -
10.0 9 .1-10.3 9.7 8.8-10.0
6.1 6 .0-6 .3 5.8 5 .7-6 .0
- 1 . 7 -
Site No.
Number of samples
Mix constituents
Coarse aggregate (per cent)
Filler (per cent)
Bitumen content (per cent)
Filler:Bitumen ratio
4 (Section 2)
Actual Correctedt Target
Mean Range Mean Range
45 40.2 39.1--43.2 45 -
8.2 7.3 6 .9 -8 .3 6.8 6 .5 -7 .8
6.3 6.3 6 .1 -6 .4 5.8 5 .7 -5 .9
1 . 3 - - 1 . 2 - -
Target
45
8.2
6.3
1.3
4 (Section 3)
Actual
Mean Range Mean
43.3 41 .6-44 .0 45
6.2 5 .9-6 .6 6.1
5.9 5.8-6.1 5.7
- 1.1
Correctedt
Range
5.8-6.3
5 .6-6 .0
Site No. 6 8
5 4 Number of samples
Mix constituents
Coarse aggregate (per cent)
Filler (per cent)
Bitumen content (per cent)
Filler:Bitumen ratio
Target
50
7.7
5.9
1.3
Actual
Mean R a n ~
~ . 4 39.2--53.8
5.4 3 .5 -8 .9
5.5 4 .9 -5 .8
Correctedt Target
45
8.1
6.2
1.3
Actual
Mean Range
50
5.1 2 .6 -7 .9
5.1 4 . 6 - 6 . 0
1.0
Mean Range Mean
44.0 39.6-50.0 45
6.8 6 .2-7 .6 6.7
6.5 6.0-7.1 6.5
- 1 . 0
Correctedt
Range
6.3 --7.2
6.2~6.7
? In accordance wi thBS 5946.
3 2
TABLE 17
Rut depth measurements on site 2
Rut depth under a 2m long straightedge (ram)
Before overlay September 1974
Section Towards Towards Mombasa Nairobi
Verge Off Off Verge Verge Off Off side side side side side side side
No.
1" Mean 1 1 . 2 5.8 3.4 12.4 Range 8 - 1 6 2 - 8 0 -11 9--15
After overlay After overlay November 1975 January 1981
Towards Towards Towards Towards Mombasa Nairobi Mombasa Nairobi
Verg~ Verge Off Off Verge side side side side side
0.4 0.8 0 1 . 4 3.0 0--2 0--2 -- 0--3 0--4
Mean 9.4 5 .2 3.2 10.2 0 0 0 0.8 3.6 2*
Range 5 - 1 3 0 - 8 2 - 5 2 - 2 2 -- - - 0--2 2 - 5
Mean 9.0 7.2 6.2 14.8 0 0.4 0.4 0 0 3
Range 6 - 1 1 6 - 8 5 - 8 6--24 - 0 - 2 0--2 -- -
Mean 7.4 6.8 3.6 13.8 0 0 . 4 0 2.4 0.8 4
Range 5 -11 6 - 1 0 2 - 5 13-15 - 0 - - 2 - 0--4 0 - 2
Mean 2.4 5.6 1 .6 3 . 2 0 0 . 4 0.4 0.6 0.8 5
Range 0 - 5 2 - 8 0--4 0--8 - 0 - 2 0 . 2 0 - 3 0 - 2
7*
Mean 4.8 4.0 1.8 6.4 0 0.4 0.4 0 2.2 Range 2 - 7 2 - 6 0 - 5 2 - 9 - 0 - 2 0 - 2 - 0 - 3
Mean 10.2 4.2 3.4 7.0 2.4 0.8 0.4 1 . 4 7.0 Range 3 - 1 5 2 - 7 0 - 6 5 - 1 0 2--4 0 - 2 0 - 2 0 - 4 5 - 9
Mean 7.4 2.2 3.0 5.0 2.6 1.8 0 0.8 7.6
3.0 0.8 4.4 2--4 0--2 3--7
4.2 0.6 3.6 4--5 0--3 0--7
0.8 0.8 0.4 0--2 0 - 2 0--2
0.8 0 4.8 0 - 2 - 4 - 6
0.4 0.4 2.6 0 - 2 0 - 2 0--4
0 0 0.8 - - 0 - 2
4.8 2.2 5.0 3--7 2 - 3 3 - 7
5.8 1.4 4 .8 8*
Range 6 - 9 0 - 5 0 - 7 4 - 6 2---3 0--3 -- 0 - 2 6 - 8 4 - 7 0 - 3 3 - 8
Mean 8.8 2.4 4 . 4 11.6 0 0 0.8 0 Range 5 - 1 3 0 - 5 2 - 7 8 - 1 7 - - 0 - 2 -
0 0.4 0.8 0.6 - 0--2 0--2 0 - 3
10" Mean 10.0 2.4 1.6 10.0 0.4 0 0 0
Range 7 - 1 4 0 - 6 0 - 4 7 - 1 3 0 - 2 - - -- 6.0 5.4 1.2 1.0 5 - 7 4--7 0--2 0 - 3
i1"* Mean 7.4 5.8 5.2 5.4 Range 0 - 1 2 2 - 8 0 - 9 2 -11
8.6 5.6 6.4 4.6 1 1 . 8
0 - 1 4 3--9 3--10 0 - - 1 2 4 - 1 9
6.4 8.6 7.8 3--10 6 - - 1 4 2--16
* Bitumen-rich mixes ** Not overlaid
3 3
TABLE 18
Rut depth measurements before overlay
Site No. Rut depth under a 2m straightedge (mm)
Towards Eldoret Towards Nakuru
Mean Range
Mean 3
Range
4 Mean Range
Mean Range
Mean 6
Range
Mean 7
Range
Mean 8
Range
Verge side
7.5 3 -19
Off-side
4.4 2 - 1 t
Towards Mombasa
Verge side [ Off-side
2.9 0 -12
4.3 0 -19
6.7 2--21
0.2 0 -3
2.5 0 -7
5.2 0-13
Off-side Verge side
5.2 9.1 0 -12 3-18
Towards Nairobi
Off-side Verge side
0 0
2.7 0-10
6.0 0-23
6.8 0-23
2.7 0-12
7.1 0-23
Towards Mombasa Towards Lunga-Lunga
Verge side Off-side Off-side Verge side
1.8 0 - 4
3.0 0--10
1.3 0 -5
0.4 0 - 4
Off-side
Slow lane
2.0 0 -9
0.2 0 - 4
4.5 0-15
0.7 0 -4
Fast lane
Off-side Verge side
1.2 0.6 0 -5 0 -3
Verge side
1.8 0-14
1.3 0 - 8
3 4
TABLE 19
Site No.
Type of roadbase
Lime stabilised
gravel
Crashed rock
Crashed gravel on cement stabilised sub-base on old road
Section No.
1
2
3
4
5
6
7
1
2
3
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
Type of overlay
Current 20 m m AC
Old 20 mm AC
Current 13 m m AC
DBM
Current 20 m m AC
Current 13 m m AC
Current 13 mm AC
Old 20 m m AC
HRA
DBM
Current 20 m m AC
Current 20 mm AC
Current 13 mm AC
Old 20 mm AC
HRA
DBM
Current 20 m m AC
Current 20 mm AC
Direction
Eldoret Nakum
Eldoret Nakuru
Eldoret Nakuru
Eldoret Nakum
Eldoret Nakuru
Eldoret Nakum
Eldoret Nakum
Mombasa Nairobi
Mombasa Nairobi i
Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
f Mombasa Nairobi
Mombasa Nairobi ,
J Mombasa Nairobi
I Mombasa Nairobi :
Mombasa Nairobi
i Mombasa Nairobi
i Mombasa Nairobi
Mean thickness overlay
m m
51 52
76 93
107 106
86 88
62 66
100 92
53 54
70 70
111 110
115 112
101 103
104 96
101 106
79 69
112 109
166 160
122 129
76 75
115 121
106 106
102 100
108 107
104 100
105 111
163 172
128 133
71 76
Estimated Cracking in 1978 Est imated
traffic Number traffic loading cracked Mean loading
cracking by 1981 by 1978 test m / m 2 ESA x 106
ESA x 106 points t i i
0.3 1 0.05 0.68 0.2 6 1.0 0.37
i i i
0.3 2 0.2 0.68 0.2 0 0 0.37
i i i
0.3 1 0 0.68 0.2 0 0 i 0.37
i i i
0.3 3 0 0.68 0.2 2 0.05 0.37
i i i
0.3 3 0.35 0.68 0.2 6 ' 0.15 0.37
i [ i
0.3 10 3.05 0.68 0.2 9 3.75 0.37
i i i
0.3 8 0.7 0.68 0.2 6 0.25 0.37
i i i
0.8 0 0 2.0 2.4 0 0 4.2
i i i
0.8 0 0 2.0 2.4 1 0 4.2
i | i
0.8 0 0 2.0 2.4 0 0 4.2
i i i
0.8 0 0 2 .0 2.4 1 < 0 . 0 5 4.2
i i i
0.8 ~' 3 - 0.05 2.0 2.4 ] 7 0.35 4.2
i i i
0.8 ] 3 0.1 2 ~0 2.4 2 0.05 4.2
i i i
0.8 0 0 2.0 2.4 0 0 4.2
i i i
0.8 0 0 2.0 2.4 i 0 0 4.2
i i i
0.8 0 0 2.0 2.4 0 0 4.2
i i i
0.8 0 0 2.0 2.4 ~ 0 ~ 0 i 4.2
0.8 0 0 2.0 2.2 0 0 3.8
i i i
0.8 0 0 2.0 2.2 1 0.1 3.8
i i i
0.8 0 0 2.0 2.2 O 0 3.8
f f i
0.8 0 0 2.0 2.2 0 0 I 3.8
i I 1 . 0 2.0 0.8 10
2.2 1 0.05 3.8 i i i
0.8 2 0.15 2.0 2.2 1 < 0 . 0 5 3.8
i i 1
0.8 3 0.05 2.0 2.2 0 0 3.8
1 i i 0.8 2 0.15 2.0 2.2 0 0 3.8
i i f
0.8 2 0.15 2.0 2.2 0 0 3.8
i i i
0.8 2 0.1 2.0 2.2 ~ 0 0 3.8
Cracking in 1981
Number Mean
cracked cracking
test m / m 2 points
i 9 1.3 8 1.1
i 7 0.3 1 < 0 . 0 5
i
5 0.5 0 0
i 6 0.3 2 0.1
t 6 1.4 7 0.8
10 [ > 3 (5 pts failed) 10 > 4 (8 pts failed)
8 > 3 (4 pts failed) 8 1.4
0 0 0 0
i
0 0 2 I 0.1
O 0 0 0
i i
0 0 3 0.2
i i
4 0.05 7 0.5
i i
6 0.5 4 0.2
i i
0 0 0 0
i i
0 0 0 0
i i
0 0 1 0 . 1
i i
0 0 0 0
i i
2 0.4 5 ; 0.4
i i
0 0 3 0.2
i i
1 < 0 . 0 5 3 0.I
i i
0 0 2 0.1
i i
10 0.9 i 1 < 0 . 0 5
i 3 0.2 7 0.7
i 3 0.2 1 < 0 . 0 5
t 5 0.4 3 0.2
i 7 0.5 2 < 0 . 0 5
i
5 0.4 4 0.3
35
TABLE 19 (continued)
Site No.
Type of roadbase
Cement stabilised gravel
Cement stabilised gravel
Section No.
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Type of overlay
HRA
Old 20 mm AC
DBM
Current 13 mm AC
Current 20 mm AC
Current 13 mm AC
Current 13 mm AC on bitumen-gravel
Old 13 mm AC on bitumen-gravel
Current 13 nun AC
Old 13 mm AC
Direction
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa
Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mombasa Nairobi
Mean thickness overlay
mm
101 100
104 103
103 97
102
99
96 101
146 157
121 126
102 110
79 80
33 25
45 42
71 71
95 87
155 144
114 118
108 110
119 114
88 86
75 70
41 40
34 32
35 33
Estimated Cracking in 1978
traffic Number Mean loading cracked cracking by 1978 test I m/m2
ESAx 106 points
0.3 0 0 0.8 0 0
0.3 0 0 0.8 0 0
0.3 0 0 0.8 0 0
0.3 1 0.05
0.8 0 0
0.3 0 0 0.8 0 0
0.3 "0 0 0.8 0 0
0.3 2 <0.05 0.8 2 0.1
0.3 0 0 0.8 0 0
0.3 0 0 0.8 0 0
1.1 4 0.45 2.7 8 1.1
1.1 10 2.25 2.7 6 0.7
1.1 3 0.65 2.7 7 1.15
1.1 9 1.4 2.7 10 1.2
1.1 8 0.95 2.7 10 1.2
1.1 1 <0.05 2.7 6 0.6
1.1 6 0.7 2.7 3 0.1
1.1 0 0 2.7 2 <0.05
1.1 2 0.15 2.7 8 0.55
1.1 5 0.45 2.7 10 1.05
1.1 7 1.1 2.7 9 1.35
1.1 8 1.0 2.7 7 0.5
1.1 0 0 2.7 5 0.4
Estimated Cracking in 1981
traffic Number Mean loading cracked
cracking by 1981 test m/m2
ESA x 106 points
1.4" 1 <0.05 2.3. 0 0
1.4 0 0 2.3 0 0
1.4 5 0.4 2.3 2 0.1
1.4 4 0.7 (1 pt > 5 m/m 2)
2.3 3 0.1
1.4 0 0 2.3 0 0
1.4 2 0.2 2.3 0 0
1.4 5 0.4 2.3 2 0.2
1.4 3 0.1 2.3 ' 0 0
1.4 0 0 2.3 1 0.1
2.3 7 0.7 4.3 10 1.5
2.3 10 2.6 4.3 9 1.1
2.3 4 0.7 4.3 9 1.5
2.3 10 1.8 4.3 10 1.7
2.3 8 1.2 4.3 10 1.3
2.3 3 0.06 4.3 6 0.9
2.3 7 1.1 4.3 5 0.3
2.3 0 0 4.3 2 0.1
2.3 4 0.3 4.3 9 1.2
2.3 5 0.6 4.3 10 1.9
2.3 9 1.3 4.3 9 1.4
2.3 8 1.1 4.3 10 0.7
2.3 4 0.2 4.3 8 1.0
36
TABLE 19 (continued)
Site No.
6
Type of roadbase
Cement stabilised gravel
Cement stabilised gravel
Cement stabilised gravel I
Section No.
1
2
3
4
5
6
7
8
9
10 (40 test points)
Range for 6 similar sections
1
2
3
Type of overlay
DBM
HRA
DBM
Old 20 mm AC
Current 13 nun AC
Current 20 mm AC
Current 20 mm AC on base-course
Current 20 mm AC
DBM
HRA
Direction
Mombasa Lunga- Lunga
Mombasa Lunga- Lunga
Mombasa Lunga- Lunga
Mombasa Lunga- Lunga
Mombasa Lunga- Lunga
Mombasa Lunga- Lunga
Mombasa Lunga- Lunga
Mombasa Lunga- Lunga
Mombasa Lunga- Lunga
Mombasa Lunga- Lunga
Mombasa
Lunga- Lunga
Fast lane Slow lane
Fast lane Slow lane
Fast lane Slow lane
Mean thickness oveday
45
48
47
50
47
52
45
53
45
52
35
41
46
48
65
69
86
96
40
46
40
40
56 61
71 55
59 62
Estimated Cracking in 1978
traftie Number Mean loading cracked
cracking by 1978 test m/m2
!ESA x 106 points i i
0.18 0 0
0.12 i 1 0 i
0.18 0 : 0
0.12 0 0
0.18 0 0
0.12 0 0
1 0.18 0 0
0.12 2 0.05
0.18 0 0
0.12 0 0 i i
0.18 2 0.05
0.12 3 0.05
0.18 6 0.1
0.12 0 0
0.18 1 . 0
0.12 9 0.95
0.18 0 ! 0
0.12 9 0.55
0.18 6 0.15
0.12 6 i - 0.05 i i
0.25-- 0.19 5--9
0.65
0 .7 - 0.13 I 9--10 1 . 5 5
i i
0.33 1 0.05 1.30 1 0.05
i i
0.33 0 0 1 . 3 0 0 0
i i
0.33 8 0.5 1 3 0 0 0
Estimated traffic loading
by 1981 ESAx 106
0.19
0.15
0.19
0.15
0.19
0.15
0.19
0.15
0.19
0.15
0.19
0.15
0.19 7
0.15 6
Cracking
Number cracked
test points
0.19 5
0.15 9
0.19 3
0.15 10
0:19 9
0.05 5 i i
0.19 ! 4--8
0.13 9--10 i i
0.7 2.9
i i
0;7 2 2.9 0
i
0.7 8 2.9 0
in 1981
Mean cracking
m/m 2
0.1
0.1
4 0.1
0 0
1 <0 .05
4 OA
<0.05
0
0.3
0.1
0.2
0.2
0.2
0:9
0.1
0.8
0.2
0.1
0.2-- 0.6
0.9T 1.6
4 0.1 2 0.1
<0.05 0
0.6 0
37
TABLE 20
Mean pavement roughness before and after overlaying
SRe No.
1
2
3
4
5
6" 7
Roughness (ram/kin)
Before overlaying
2700
3400
1600
3300
3200
2300
After overlaying
1400
1600
1400
1900
1800
1700
1800
3 8
0 - - ~ - ( 3
X X X X
0 0
X X X
0 0
X X
0
x X
I
o.
A v
0
A v
C
0
E
0 ° _
e -
I--
k _ - N -
~o~ ° _
° _
, ¢ " ~ ' J e -
x
l oox
0 ° ~
0
0
.-I
I.L
A +-* ¢--
03 ¢J
¢:L
er"
a 3
¢-.
100
80
60
50
40
30
20
10
i
D
m
B
P
D
. 5.4 _ 1 .0 , , N , r a t e of enetrat,on,
• z~C~',~c~c~D~m~
-• % ' ~ •
=0 R,.~O
O
• a ~ ' \ I
c] 8 AUL
I I I I I I I I I I I I I i 1
10 20 30 4 0 50 6 0 8 0 1 0 0
Rate of penetration (ram/blow)
Fig. 2 Relationship between in-si tu subgrade C.B.R. and rate of cone penetration
A
E E E O . B
t ~
r -
e . )
t - t ~
2.o
1.5
1.0
0.5
0
Site 1
'74 "75
Note: 7(54) indicates section No. and overlay thickness (mm)
'76
3.4 3.9
~-J 6(96) / (D.B.M. /
1(52)
5(64)
All asphaltic concretes
'77 '78 '79 '80 '81
Survey date
1.0
0.5
0.5
0
Site 2 B
Sections with < 0.2 m/m2 mean cracking in 1981
1 (7O) A.C. 2 (110) A.C. 3 (114) A.C. 4 (102) A.C. 7 (74) A.C. 8 (111) A.C. 9 (163) A.C.
10 (126) A.C.
I I I I I I I '75 '76 '77 '78 '79 '80 '81
6(104) (D .B.M.)
5(100) (H.R.A.)
Site 3 Sections with ~0.2 m/m2 mean cracking in 1981
2 (118) A.C. 3 (106) A.C. 4 (101) A.C. 7 (108) A.C.
- 7 ~ D ~ 5(108)(H.R.A.) / - ~ 6(102)(D.B.M.)
/ All asphaltic ~ I(0~6)4, / concretes /I-,,
~_ 4 ~ 8(168) i / ~ 9(131)
'75 "76 '77 '78 "79 '80 '81 Survey date
Fig. 3 Rate of d e v e l o p m e n t of surface crack ing
E E
v
t -
O
o 3 ¢ -
2.0
1.5
1.0
0.5
Note: 5 (101) indicates section No. and overlay thickness (ram)
Site 4
Sections with < 0.2 m/m2 mean cracking in 1981
2 (101) H.R.A. 3 (104) H.R.A. 6 (99) A.C. 7 (152) A.C. 9 (106) A.C.
10 (80) A.C.
O
'76.
~ 5(101) D.B.M .i 8(124) 4(100)
I '77 '78 '79 "80 '81
Survey date
2.0
Site 5 Section 8(117) < 0.2m/m2 mean cracking in 1981
4(91 )
1.5
/ f / ~ 10(73) jI/,, :,1: 1.0 y / ~ ~ ~ - ~ 1(29)
9(87) 7(109)
13(34)
0.5 6(116)
0 '74 "75 '76 "77 '78 '79 '80 '81
Survey date
Fig. 3(cont) Rate o f development o f surface cracking
E E E O , B
Q .
O} t -
2.0
1.5
1.0
0.5.
0
Site 6
Sections with < 0.2 m/m2 mean cracking in 1981
1 (47) D.B.M. ~ 2 (49) H.R.A. 3 (50) D.B.M. ~ 4 (49) A.C. 5 (48) A.C.
10 (43) A.C.
Actually similar to A.C.s but with lower bitumen content
All asphaltic concretes
-- 8(67)
9(91)
" O
"~ 6(38) 7(47)
I '75 '76 '77 '78 '79 '80 '81
Survey date
1.C
0.5
0.5
Site 7
O
'73 '74 '75
~ 6
2
All 40mm thick asphaltic concrete
I I I I I I I
'76 '77 '78 '79 "80 '81
Site 8 Sections with < 0.2 m/m2 mean cracking in 1981
1 (59) D.B.M. 2 (63) D.B.M.
, , ~ 3(61 ) ~ H.R.A.
O /
i I ~ 1 I I I I I I
"73 '74 '75 '76 '77 '78 '79 '80 '81
Survey date
Fig. 3 (con t ) Rate o f deve lopment o f surface c rack ing
O.
E o
t-
O.
E
Q~
x o~
E t-
t~ °_
c
E 0_ t~
x °_
E
-8
u_
0
¢0
E t-
I P P l I I I
( , , , tu) ~)oCji~ :i.e ua,,,n:l.!q aq:l. j.o uop.eJ~.auad
0
0
A
"0
Q.
E
c
0
<
¢I}
E °i
,.C
°I
E
0i
"10
cSA >.
C
~E ,_o 04-
C 0
Gb
t,~v
I.I.
O
0
z~
80/100 60/70 80/100 60/70 80/100 60/70
~enetration grade bitumen sampled from heater tank )enetration grade bitumen sampled from heater tank ~enetration grade bitumen recovered after mix ing ~enetration grade bitumen recovered after mix ing )enetration grade bitumen recovered from overlays up to 5 years old )enetration grade bitumen recovered from overlays up to 5 years old
A
E E (J o L~ ¢N
r
.o
o ~ t -
Q .
90
80
70
60
50 -
4 0 -
30 -
20 -
10
O 0
0 0
0
• []
m o ~
Az~
A • AM~
n
0 I I I I I I 0 20 30 40 50 60 70
Softening point ( °C )
8 0
Fig. 5 Re la t ionsh ip between pene t ra t ion and r ing and ball values f o r samples o f b i t u m e n s
D
e e
O)
+ Q. o c- CD Q.
o.
II
E 0
..0 d H
I I I I I ! ! 0 1.0 ~ LO 0 1.0 O
( O o C ~ :l.e t u w ) JaAe I d o ] . woJJ . paJaAOOaJ u a w n ~ . ! q :1.o uo!:l.eJ~.aUacl
0 " LO
- N
O
- N
O
- - LO
N o O
A
O U~
E E
E
O
E 9
O
r
E .~_ e~
c- O . _
¢-
° ~
E E
O
E O
O
C t~
O . O
E 2
" D
O
C
E o ~ , .O
O
° ~
0 e',
C 0
~0
U ,
0 " - (D
+.J In ~--" t-- ¢-- . - - .~ .o_ ~' P: ~
- o . - N ==.---
~ o o ~ o e @
+./~/++ ~" ® ~ ® m / • •
,~ CO r-- ~" ¢D / "
D • - /" • + / " • ~ 0 / == / •
o / . / =~- / 'F "~- / =~]
," _ " m - / = °m ~ _ m ~ = / ~" + / $ , . - _ - / + ~ " ~ N "+
, , - j _]j..+-+, .+ Y®
• m ~ .~ ~ @
® Psi p,,,
0 CO t - -
I I I I I I I I t O 'rap C~I CD CO ( D ' ~ C~l
(Will) AIZlJaAO JO SSaU>I::>!LI/
CD f.,.
C , - - ( D
_ + o
_ 0
CD
CD
A
E E
c q I O +,..
X
t -
> -
<D
O
c"
.o
<D
m I -
>, .
m
0 J
O 0,} +- ,l .a
> .
0~
.o~ e'-
e- O
0,P ,.4-.
+,-
t- O
- , l
rv-'
I " , ,
i i
O OO T--
I ~ / / I I I I / / . * " / i! ~
/ / / . . " ,
/ / / I / / / t
I I I I I I I
((.uuJ) A e l J e A o ~o s s e u ~ o ! L i l
I .E .-~
I I
0 0
0
0 ¢,D
A
E E
0 0
X v
¢-
0
o ~ ' ~ e--
0 . _
. _
0
0
r-
E e= o
° ~
c
U ° ~ o= o e=
° ~
¢0 m
~D
O
e=
=O 3~
=O =O
° ~ e= U
C O
U
"C3 C
C O
U
" O
C
E ° ~
"0 C
E E 0 U
e "
1 0 0 0 900
800
700
600
500
400
300
R x D ( x l 0 3 m m 2)
.o\
Verge-side wheelpaths on ly
7 . . . i nd i ca tes Site No.
A
E
P
> -I
n-
200
100 --
9 0 -
8 0 -
70 -
60 -
50 -
40 -
30 -
20 -
10 10 20
I I I I I I I I 30 40 50 60 70 80 90100
Transient deflection (x lO-2mm)
200
Fig. 9 Re la t i onsh ips be tween rad ius o f c u r v a t u r e and d e f l e c t i o n o n the c o n t r o l sec t i ons
1000
900
800
700
600
500
400
300
200
E P
co ,> = 100 -
9 0 -
• -~ 8 0 -
r r 70 -
60 -
50 -
40 --
30 --
20 --
10 10
R x D ( x 103mm 2)
%
- \
I
20
I Site 2 • = " ~ ~ Site 3
Overlays
I I I I I I I I
30 40 50 60 70 80 9 0 1 0 0
Transient def lect ion (x 10-2mm)
200
F ig . 1 0 D e f l e c t i o n - c u r v a t u r e r e l a t i o n s h i p s . f o r t h e " C o n t r o l " s e c t i o n and a 9 0 - 1 0 9 m m t h i c k o v e r l a y
1000 ~ . O O R x D (x 103mm 2) 900
800
700
600
500
Site 5 i Site 4
400
300
200 Overlays
A
E
- i
? 100
N 90
N 80 "O
-~ 70
60
50
40
30
20
10 I 10 20
I I ! I I I I I 30 40 50 60 70 80 90100 200
Transient deflection (x 10-2mm)
Fig. 11 Deflection-curvature relationships for "Control" sections and 90-109mm thick overlays
1 0 0 0 900
800
700
600
500
400
300
200 --
E P 2
-" 100 - ¢J
9 0 - -
~5 80 -- O3
oc 70 --
60 --
50
40 - -
30 - -
20
R x D ( x l O 3 m m 2)
10 I
10 20
Site 7 Site 8
,Overlays
I I I I I I I I 30 40 50 60 70 80 90 100
Transient deflection (x 10"2ram)
200
Fig, 12 D e f l e c t i o n - c u r v a t u r e r e l a t i o n s h i p s f o r "Con t ro l " sec t ions and 40 and 5 0 m m t h i c k o v e r l a y s
A
E E
%
v t -
O om
N--
"O
"O t -
.=
"O o a .
200
180
160
140
120
100
80
60
40 - -
2 0 -~
0 2O
Q ~ 3 (150) denotes Site No. thickness
0)
4(150)
5(86) 5(121)
4(100) 4(75) 5(33)
I I 30 40
Surfacing temperature at depth 40ram (°C)
50
Fig. 13 Relat ionships between the p roduc t o f radius o f curvature and def lect ion and overlay temperature
O0
"5 e E = o_ "~ o --
z~ ~J
N o o c .>__ I-- I - - "~
-~ oO
I
O"
._I
CO
I I I I I
(901 x "V'S'=I ) 6u!~oeJo ~.o~uJ/uJ~" 0 o:l aj! I len~ov
0
0 0
0
• 0 0
0
0
0
0
0
0
(N
0
O0
A
X
<
LU
c-
O
"0
0
~*="
o o~
0.
i 0
0
i i=.
o
w-
o A
W=
o
E
E
d v
.J
a~
e-
w=
n~ t= 0~
o
e-
e- O"J °i
~P
n~
E e "w
.J
n
o e*
o .m
e~
E o
oi
I.I=
6,1
~ o
I ~ ~ =- I __ "O
/ -~ o ,, J ~ ~ i ~ -~ ~ / ""
, "
".~
8 c
I " - . n • • "0
. ' . . t ° 0
(901. x " V ' S ' 3 ) 6u!~:)eJo ].o Z : w / w ~ ' o o:1. aJ.!l len~-oV
o t,D
o ~
0 0 CO
I I I I I
\ \ ~ \ \ \ \ \ \~1 \ \ " , . \ \ \ ~ ! , . \ \ x ~ ~ \ \1
- " " . \ x \ \ \ \ ~i \ ' \ ' \ x - \ \ \
\ \ \ \ \ I E E
v > . ¢o
0
P o Q}
..(3
0
nO
O}
E 03 OB
\ \ \ \
- - 00
~ -->~
.E t - ¢.}
I 0 I.O
I I I 0 0 0 0 LO 0
(uJuJ) ss~u>lo!ql AelJe^ 0
I 0 1.0
0
_ 0
L~
_ 0
0
C~ 0~
1.0
_ 0 0
_ 0 __.~
- ~
¢~ e'- co
"I C)
- q
0 ("4
m
_ q
- - °
0
- - o 0
d
0 0
p .
e -
E ?
r -
o
~ . J ~
>.~ ¢ 0 - -
> ¢g
o ~
o- - L L
\ \ \
m
m
B
B
O C~ O')
I I ! I I O O O LO O L"*) _
o \ \ \ \ \ \ \ x \ \ \ \ \ \ \ "i --
N \" \\ \ \ \ \I - x\ \ . \ \ \ \ \ N - o\\ \\ \ ,. \ \
\ \ \ \ - \ 0~
0
P o
0
0 ~p
0,)
o3 E 0~
(o O.
\ \ \ I
m
B
m
m
I 0 £"N
I I I I 0 0 0 LO 04
(uJuJ) sseu>10!ql AelJa^ 0
0 0 ¢~ LO
u
I -
o
i o
O'J
.E o .-
OJ
E Q)
O C
CO x o3 I..
o ~ o-o
O ~=¢2
• =~ °m
o ~ ~o
I.= r.-
o O cn c~ r~
o )
M=
O T=.
OO
O
£O
O
LO
O
c~
14. APPENDIX
ADAPTION OF BRITISH OVERLAY DESIGN METHOD FOR USE IN KENYA
In LR 8334 a method of designing overlay thicknesses for roads in the United Kingdom is described and
charts are provided which relate the traffic loading to be carried, pavement deflection before overlay and
overlay thickness. Two levels of probability of achieving the design life are also given.
The method incorporates an estimate of the remaining useful life of a road before the onset of
'critical conditions' which are deemed. This uses 'criteria' curves which have been developed for roads in
t h e United Kingdom. These are basically deflection-performance (surface condition) histories which are
used to predict the future behaviour o f roads of similar construction. The design charts relate to the use of
hot rolled asphalt as the overlay material but conversion factors for bitumen macadams are given.
14.1 Application of the method in Kenya
For Kenyan conditions dense bitumen macadam wearing course material and asphaltic concretes
can be assumed to be equivalent to hot rolled asphalt for thickness design purposes.
It is unlikely that criteria curves of the type referred to in LR 833 will be available. Areas of roads
which are to be overlaid will almost always have reached a 'critical' condition at the time of overlaying.
It is very important that badly damaged areas are dug out and reconstructed and that drainage
deficiencies are rectified before overlaying.
14.1.1 Roads with crushed stone roadbases. Two levels of probability of achieving a given overlay life are provided in thedesign charts two of which are reproduced as Figures 16 and 17. The results of the
present study show that these levels o f probability are not meaningful for Kenyan conditions because of
the possibility o f cracking during the early life of the overlay. The charts do however provide two
acceptable levels of strengthening. It is suggested that the chart for the 0.5 probability level is used in
areas receiving less than 1000 mm of rainfall per annum and that the chart for the 0.9 probability level is
used in wetter areas until more experience of overlay performance is acquired from future overlay contracts.
14.1.2 Roads with soil-cement roadbases. These pavements present special problems in that the
nature and strength of the roadbase at the time of overlaying largely determines the performance of the
overlay. A stabilised roadbase which has cracked into individually strong slabs will probably cause reflection
cracking in the overlay with subsequent failure due to the ingress of water. A stabilised roadbase which has
become highly fragmented will behave more like a granular roadbase. There are many stages of deterioration
between these two examples where it will be difficult to determine whether reflection cracking will occur.
Evidence reported elsewhere 19 has shown the importance of maintaining an unbroken seal throughout the
life o f this type o f road structure and o f the influence of patching work upon serviceability. Surface
dressings are likely to provide the cheapest seals and should be used for as long as possible before overlaying.
A surface dressed bitumen macadam or, for thick overlays or regulating courses, a composite overlay o f crushed rock with an asphalt surfacing will be more effective in resisting reflection cracking than would
the same thickness of a dense asphalt.
58
In the current study the overlays on site 4 have now performed well for four years and whilst the
evidence is far from conclusive the indications are that deflections greater than 50 x 10 -2 mm and a
radius of curvature (as measured in the study) o f less than 60m measured on a surface dressed pavement
indicate a well fragmented roadbase.
It is recommended that the overlay thickness design charts proposed for granular roadbases are also
used for roads with cement-stabilised roadbases but that the use of overlay systems indicated above are
considered as alternatives to dense asphalt overlays.
5 9
(758) Dd8041301 1,400 4/82 H P L t d S o ' t o n G1915 PRINTED IN ENGLAND
ABSTRACT
Early performance of some experimental bituminous overlays in Kenya: H R SMITH and C R JONES: Department of the Environment Depar tment o f Transport , T R R L Laboratory Report 1043: Crowthorne, 1982 (Transport and Road Research Laboratory) . This report describes the performance o f b i tuminous overlays on roads in tropical and sub- tropical environments in Kenya.
Considerable hardening of the binder occurred th roughou t the dep th o f the overlays during the first five to seven years, but negligible rut t ing developed. The main form o f deterioration was cracking which was initiated at the surface o f the overlays.
The reduction in pavement deflections produced by the overlays is shown to be only slightly less than those obtained in Britain despite the higher ambient t empera tures in Kenya.
The performance of the overlays is shown to be primarily dependen t on the propert ies of the overlay material itself. No correlation could be established be tween the deve lopment o f cracking on each test section and the corresponding values o f surface def lect ion and curvature, traffic loading or overlay thickness. However the overlays have remained serviceable for up to seven years and have carried up to 4.3 x 106 equivalent s tandard (80 kN) axles.
ISSN 0305 -1293
ABSTRACT
Early performance of some experimental bituminous overlays in Kenya: H R SMITH and C R JONES: Department of the Environment Depar tment o f Transport , T R R L Laboratory Report 1043: Crowthorne, 1982 (Transport and Road Research Laboratory) . This report describes the performance of b i tuminous overlays on roads in tropical and sub- tropical environments in Kenya.
Considerable hardening of the binder occurred t h roughou t the dep th o f the overlays during the first five to seven years, but negligible rut t ing developed. The main form o f deterioration was cracking which was initiated at the surface o f the overlays.
The reduction in pavement deflections produced by the overlays is shown to be only slightly less than those obtained in Britain despite the higher ambient t empera tures in Kenya.
The performance of the overlays is shown to be primarily dependen t on the propert ies of the overlay material itself. No correlation could be established be tween the deve lopment o f cracking on each test section and the corresponding values o f surface def lect ion and curvature, traffic loading or overlay thickness. However the overlays have remained serviceable for up to seven years and have carried up to 4.3 x 10 O equivalent s tandard (80 kN) axles.
ISSN 0 3 0 5 - 1 2 9 3