TRANSPORT and ROAD RESEARCH LABORATORY Department of … ·
Transcript of TRANSPORT and ROAD RESEARCH LABORATORY Department of … ·
TRANSPORT and ROAD RESEARCH LABORATORY
Department of the Environment Department of Transport
SUPPLEMENTARY REPORT 532
SOME OBSERVATIONS OF MACHINE TUNNELLING AT THE KIELDER AQUEDUCT
by
T D O'Rourke (University of Illinois at Urbana-Champaign),
S D Priest* and B M New (Transport and Road Research Laboratory)
* Now at Imperial College, London
A shortened version of the text of this Report was presented to the 19th US Symposium on Rock Mechanics, Lake Taho,
Nevada, May 1978.
Any views expressed in this Report are not necessarily those of the Department of the Environment
or of the Department of Transport
Tunnels and Underground Pipes Division Structures Department
Transport and Road Research Laboratory Crowthorne, Berkshire
1979
ISSN 0305-1315
CONTENTS
Page
Abstract I
I. Introduction I
2. Geology 3
2.1 Discontinuity characteristics 3
2.2 Intact rock strength 4
2.3 Seismic velocity 5
3. Tunnelling procedure 6
4. Observed conditions and tunnelling performance in sandstone 7
4.1 Tunnel geology 7
4.2 Tunnelling performance 8
4.3 Comparison of seismic velocities with ground conditions 10
5. Observed conditions and tunnelling performance in limestone 10
5.1 Tunnel geology 10
5.2 Tunnelling performance 11
5.3 Comparison of seismic velocities with ground conditions 11
6. Observed conditions and tunnelling performance in mudstone 12
6.1 Tunnel geology 12
6.2 Tunnelling performance 13
6.3 Comparison of seismic velocities with ground conditions 14
7. Discussion 14
7.1 Tunnelling delays and geology 14
7.2 Machine construction and tunnelling performance 15
7.3 Seismic velocity measurements 16
8. Conclusions 17
9. Acknowledgements 19
10. References 19
(C) CROWN COPYRIGHT 1979
Extracts from the text may be reproduced, except for commercial purposes, provided the source is acknowledged.
Ownership of the Transport Research Laboratory was transferred from the Department of Transport to a subsidiary of the Transport Research Foundation on 1 st April 1996.
This report has been reproduced by permission of the Controller of HMSO. Extracts from the text may be reproduced, except for commercial purposes, provided the source is acknowledged.
SOME OBSERVATIONS OF MACHINE TUNNELLING AT THE KIELDER AQUEDUCT
ABSTRACT
The Kielder Water Scheme, currently under construction in north-east England, will consist of 32 km of tunnel to direct water from the Tyne to the Wear and Tees River Valleys. The project, which is promoted by the Northumbrian Water Authority, involves excavation through sedimentary strata using 3.5 m-diameter tunnel boring machines.
The Tunnels Division of the Transport and Road Research Laboratory (now the Tunnels and Underground Pipes Division) planned and implemented an observation programme during tunnel construction for the North Wear Drive, a portion of the Kielder tunnel system linking the River Wear with a companion tunnel drive from the Derwent Valley. The observations were performed with the assistance of Babtie, Shaw and Morton, the general engineering consultants for the Kielder Water Scheme.
Detailed observations and measurements were taken in the first 1600 m of the North Wear Drive, where the tunnel was driven through approximately equal lengths of sandstone, limestone and mudstone. This paper summarises the structure and material properties of the in-situ rock in each of the principal lithologies and compares the observed ground conditions with the machine advance rates and rock support adopted during tunnelling.
Attention is directed to the performance of the tunnel boring machine in light of the geological conditions, and improvements are suggested as an expedient to future machine excavation. In addition, the results of seismic scans, taken along the tunnel, are summarised and compared with detailed observations of the rock conditions.
I. INTRODUCTION
Many authors have recognised the importance of ground conditions in
contributing to rock displacement and overbreak, and in dictating the amount I-5
and types of support required in tunnels An appreciation of how various
ground conditions translate into support and excavation requirements is
especially important in the use of tunnel boring machines, where the nature
of machine construction can restrict the application of support at the tunnel
face, and deteriorating ground conditions can diminish the capacity for
machine thrust and manoeuvreability. To this end, case studies are
particularly useful in that they help to point out important characteristics
of the construction method and provide a basis for estimating machine
performance in various subsurface environments.
An evaluation of ground behaviour must, of course, be preceded by site
investigation so that the structure and engineering properties of the ground
can be determined. Various techniques are currently used for this purpose
that include logging vertical and inclined boreholes, mapping the surface
geology, stereo photography, and geophysical sensing.
Of the geophysical methods, measuring the seismic velocity of
compressional waves through in situ rock has been proposed and studied as
an indication of rock quality 6-9. Borehole measurements of seismic velocity
have been used at several sites10-11; to identify relatively large faults,
and seismic scans along a completed tunnel have been used to estimate the 12
in situ moduli of the rocks Judgements regarding the reliability of
the method will no doubt benefit from additional field studies where seismic
scans can be correlated in detail with rock structure and ground behaviour.
In the light of these considerations, the Tunnels Division of the
Transport and Road Research Laboratory planned and implemented an
observation programme during tunnel construction at the Kielder Water Scheme.
The Kielder Water Scheme 13 is promoted by the Northumbrian Water Authority
and will consist of 32 km of tunnel principally through sedimentary rock.
It was felt that the scale of the project and variety of tunnelling
conditions required close examination, and where appropriate, to report the
ground behaviour and construction performance to the tunnelling industry.
The site chosen for observation was the North Wear Drive, a portion of the
Kielder tunnel system linking the River Wear with a companion tunnel drive
from the Derwent Valley. The observations were performed with the assistance
of Babtie, Shaw and Morton, the general engineering consultants for the
Kielder Water Scheme. The Contractor for tunnel construction was Tyne-Tees
Tunnelling, an international consortium of three contractors. Excavation
was performed with a tunnel boring machine, manufactured by Demag
Verdictertechnik.
Detailed observations and measurements were taken in the first 1600 m
of the North Wear Drive, where the tunnel was driven through approximately
2
equal lengths of sandstone, limestone and mudstone. This report summarises
the structure and material properties of the in situ rock in each of the
principal lithologies and shows how these features influenced tunnel
construction. Attention is directed to the performance of the tunnel boring
machine in light of the geological conditions, and improvements are suggested
as an expedient to future machine excavation. In addition, the results of
seismic scans, taken along the tunnel, are summarised and compared with
detailed observations of rock conditions.
2. GEOLOGY
The general geology of the area along the line of the tunnel was determined
from surface mapping, site investigation boreholes and existing published 14
data The stratigraphy of rocks encountered during the sinking of a
borehole, approximately 600 m from the North Wear portal, and a diagrammatic
section based on the site investigation results are given in Figure I.
The rocks in the first 1600 m of the tunnel drive belong to the Middle
Limestone Group of the Lower Carboniferous Series. The drive takes the
tunnel into progressively younger strata, which dip at approximatly 1.5 °
along the tunnel route. The initial 500 m is in a strong, fine-grained
siliceous sandstone, followed by approximately 600 m in the Four Fathom
Limestone, a very strong, crystalline material. This grades through a
muddy limestone into a micaceous and carbonaceous mudstone which lasts for
another 600 m of the drive and ultimately gives way to the Quarry Hazle
Sandstone (a strong siliceous sandstone) followed by the Iron Post Limestone
(a strong, crystalline muddy sandstone). The predicted and actual geology
correlate remarkably well, considering the amount of site investigation
data available and the depth of the tunnel. Any discrepancies between them
are largely due to minor variations in the dip of the sedimentary strata.
2.1 ~iscontinuity characteristics
The general term 'discontinuity' is used in this report - avoiding any
generic connotations - to describe a mechanical break or interruption of
the properties of a rock 15. In this report the following terms are used to
described specific types of discontinuities:
16 Joint - fracture in rock along which there has been little or no movement
vein - tabular rock or mineral that fills and cements an open joint.
3
Features such as iron staining and calcite or clay infilling were taken
to indicate that the given discontinuity pre-dated tunnel excavation.
Fractures induced by the tunnelling procedure, notably the fractures that
were caused by expansion of the anchor pads, were ignored. Measurement of
veins was carried out, despite the fact that they did not form significant
mechanical breaks in the rock, to supplement orientation data obtained at
other locations in the tunnel.
Representative sections in each rock type were closely examined along
horizontal scanlines to determine discontinuity orientation, spacing,
continuity and width of opening and the nature of infill materials. This 17
method of sampling discontinuities is discussed by Priest and Hudson
Owing to the limited access in the tunnel, vertical scanlines were not
performed. Statistical data snmmarising the results of these measurements
are listed in Table 1.
The frequency of the most conspicuous and continuous (trace lengths
exceeding 1.5 m) was logged over 10 m lengths of tunnel. This was performed
in conjunction with seismic velocity measurements. Although the joints were
recorded along the springline of the tunnel, they were, in the great
majority of cases, continuous into the shoulders and crown. In many
instances, the joints logged at springline could be traced through their
mutual intersections in the roof where rock wedges were apparent.
Throughout all sections of the tunnel, the majority of the discontinuities
were vertically inclined. This was especially evident for the most continuous
joint sets in the sandstone and mudstone, as well as the calcite veins in the
limestone. In view of the vertical nature of the discontinuities it was
considered more appropriate to present orientation data in terms of strike
direction rather than dip direction, the strike of a plane being the azimuth
of a horizontal line in that plane. This strike information is presented
in the form of rose diagrams in Figure 2. The azimuth of the tunnel drive
is shown in each of the diagrams.
2.2 Intact rock strength
A measure of intact rock strength was obtained by using a Schmidt
rebound h~mmer (Type L). The hammer was used at axis level in the
horizontal mode, thus obviating the need to apply the angle corrections
described by Kolek 18. The results obtained from in situ testing of
natural rock should be viewed with caution as (a) the surface of the rock
was often uneven and (b) the presence of an open joint behind the test area
could give an artificially low rebound number.
In order to minimise the effect of these problems, at least five tests
2 were taken within an approximately 0.5 m area at each test location.
Experience has shown that, whilst it is possible to get an artificially low
rebound value due to the influence of open joints and fractures, it is very
rare to obtain an artificially high value. Consequently, the two lowest
values were discounted as a means of screening anomalously low readings, and
the mean of the three highest rebound numbers was taken as a measure of the
intact rock strength. Measurements were made at 10 m intervals along the
tunnel. Mean rebound nNmbers and ranges of compressive strength are
presented in Table 2 for the principal rock types encountered during
tunnelling. The compressive strengths were estimated from the rebound numbers
using a calibration curve in the operating handbook. The influence of
intact rock strength on the performance of the tunnelling machine in this
length of tunnel is discussed in a companion paper by Morgan et a119 using
the above data.
2.3 Seismic velocity
A Bison signal enhancement seismograph was used at 10 m intervals along
the tunnel to make velocity measurements over the intervening baselengths.
Owing primarily to the attenuative nature of the rock, 10 m was the maximum
range possible using the equipment in the manner described. A lesser
separation between hammer impact and geophone may have resulted in
anomalously high sensitivity to individual discontinuities, and the
resolution of the seismograph timing system would have proved inadequate.
A sledge hammer generated the seismic waves and a geophone was used as a
receiving transducer. An impact switch on the hammer triggered the cathode
ray tube sweep where the geophone output was displayed and held. An
electronic cursor was set by the operator at the first wave arrival and the
time elapsed since the impact was numerically displayed in milliseconds. The
system described was successful in the tunnel environment and the complete
survey was carried out during two eight hours shifts.
Certain problems inherent in the technique and others imposed by the
limited time and access to the tunnel must be considered when interpreting
the data. They are as follows:-
(a) The direct hammer impact on the sidewall tended predominantly to
generate shear and surface waves rather than the compressional waves
required. Thus, in highly attenuative rock masses, the first
observed arrivals may be those of the slower, but higher amplitude
shear or surface waves.
(b) The axis of sensitivity of the geophone was pointed towards the hammer
source to provide maximum sensitivity to compressive wave arrivals.
However, the time available in the tunnel did not allow rigid mechanical
coupling of the geophone to the rock. Consequently, the relatively low
signal to noise ratio may have further impaired discrimination of the
first wave arrivals.
Intact specimens of the three main rock types were taken and the
unconfined compressional wave velocities measured in a direction parallel
to the bedding. The results of these laboratory measurements are summarised
in Table 3.
3. TUNNELLING PROCEDURE
The tunnel was driven at an azimuth of 015°NE. The initial 127 m of
tunnelling were undertaken by drill and blast methods to form a D-shaped
opening, 3.85 m high and 3.80 m wide. Steel arches and posts were used
as primary support in the drill and blast section, with shotcrete applied
in a thickness of approximately 80 mm at the crown and side-walls. Starting
at chainage 127, excavation was performed with a full-face tunnel boring
machine of 3.5 m diameter.
A simplified diagram of the tunnel boring machine is presented in
Figure 3. The rotating cutting head was equipped with 17 triple disc
cutters. The rock debris, generated by the cutting process, was collected
behind gathering arms, or scrapers, that were spaced at quarter points
around the periphery of the cutting head. Near the springline of the
cutting head the debris was fed into an intake chute from which the
excavated material was directed on to a conveyor belt in the tunnel invert.
6
The opening of the intake chute was approximately 300 mm by 225 mm in plan
dimensions. Access to the cutting face was available through the access
corridor, which is shown in cross-section A-A. The access corridor was
approximately 0.75 m high and I m wide. Reaction for the forward thrust
to the cutting head was provided by two rear anchor pads that were expanded
laterally to obtain a bearing against the rock. The position of the cutting
head was continuously adjusted with respect to the line of horizontal
reaction at the rear anchor pads, thus providing a control on the gradient
of excavation. The application of pressure across the front anchor pads
helped stabilize the head during cutting and contributed to the control
of alignment. Tunnel support was installed from a working platform located
approximately 12 m from the tunnel face. As the working platform was
positioned less than 2 m below the crown, a rock bolt length of 1.85 m was
the maximum that could be placed from this location. The operator's cabin
was located immediately behind the working platform. This, in turn, was
followed by a section that carried the dust extractor equipment and an
elevated Malhauser conveyor.
4. OBSERVED CONDITIONS AND TUNNELLING PERFORMANCE IN SANDSTONE
4.1 Tunnel geology
From chainage 150 to 220* the tunnel was driven through mixed beds of
mudstone and sandstone, and from chainage 220 to 770 tunnelling was performed
principally in sandstone. A geological cross-section of this portion of
the tunnel is illustrated in Figure 4.
The principal sets of discontinuities in the sandstone included
bedding and two sets of nearly vertical joints (NE and NW joints). The
characteristics of these discontinuities are summarised in Table 4. All the
NW joints and some of the NE joints were filled in soft clay, the properties"
of which are listed in Table 5. In particular, the thick, infilled nature
of the NW joints contributed to instability by allowing rock blocks to slip
and rotate at their clay-filled boundaries. Samples of clay for testing
were taken from depths of 5 to 10 cm in several joints. The particularly
low shear strength reflects the remoulding of the material as well as the
likelihood of increased water content due to exposure near the tunnel wall.
* Chainages are measured in metres.
7
There were three types of wedges that were potentially unstable during
tunnelling:
I. Tetrahedral wedges: These were formed at the shoulders of the tunnel;
they were bounded on top by a bedding plane, and on each side by a NE 3
and NW joint. Most tetrahedral wedges were from 0.25 to 0.50 m in 3
volume, however many wedges of I m were also observed. Plate I shows
a tetrahedral wedge that became unstable in the west tunnel wall.
2. Diamond-shaped wedges: These were formed at the crown by the
intersection of two NE and two NWjoints. Wedges of this type tended to
break at the bedding plane immediately above the crown. In locations
where the joint spacing was low for both principal joint sets, overbreak
occurred as far as the third and fourth bedding plane above the tunnel.
Plate 2 is a photograph of the crown near the intersection of a NE and
NW joint. In the picture, portions of several diamond-shaped wedges
can be seen.
. Wedges bounded by parallel joints: The NW joints frequently occurred
in pairs that were separated by less than 0.5 m. In these instances
the elongated slab of rock between the joints tended to fall from the
crown, thus leaving a void which extended to the first or second
bedding plane above the tunnel. Loosening at the edges of the void
led to slabbing of the intact rock and further deterioration.
4.2 Tunnelling performance
In Figure 4, joint frequency, volume of overbreak, rock bolt support
per metre run, advance rate and seismic velocity are plotted for chainages
150 to 770. The tunnelling advance rate is referenced to the location of
the support platform. Each advance rate is computed from the distances
tunnelled during several 11-hour working shifts divided by the time elapsed
during the shifts. As such, it includes the time required for all cutting,
mucking and support activity, as well as the time needed for repairs or
cutter changes during the working shift. It does not include the time
spent during scheduled maintenance periods.
Rock bolts were common to all methods of ground support except shot-
creting and were in particularly high use during the erection of steel
arches. In the latter case, arches were supported on steel beams that were
bolted to the tunnel wall with as many as six bolts per metre length of
beam.
Between chainages 200 and 250, some joint openings were as thick as
60 mm and the number of joints per 10 m length was approximately 30. The
low advance rates in this section are related to the high density of support
and to delays caused by a rock fall at chainage 235. With distance from the
portal, there was a decrease in joint frequency and, in particular, a
substantial decline in the number of NE joints. From chainage 525 to 575,
the spacing of NE joints was in excess of 10 m. Correspondingly, there was
a notable decrease in the number of tetrahedral and diamond-shaped wedges.
In addition, joint thickness diminished with distance from the portal so
that, from chainage 500 onward, the joints were rarely in excess of 15 to
20 mm thick.
In places, tunnelling progress was retarded by wedges of rock that
obstructed the intake chutes at the cutting head. When blockage occurred,
the machine had to be stopped until the chute was cleared. This problem
was persistent throughout the sandstone, but was especially bad between
chainages 150 and 450 where, in certain locations, the machine advance was
interrupted several times during a shift. For example, between chainages
300 and 400, an average delay of 8 hours per 10 m advance can be attributed
to blockages at the cutting head. In general, the blockages decreased as
both joint frequency and thickness declined. From chainage 480 to 580,
the delay caused by blockages had decreased to an average 2 hours per 10 m
length. The highest rates of advance in the sandstone were recorded along
this section of the tunnel. When seat earth was exposed in the crown,
between chainage 600 and 650, blockages at the cutting head caused an
average delay of 3 hours per 10 m length, whereas the installation of roof
support required from 6 to 20 hours per 10 m length.
Shotcrete was used in two areas. Between chainages 200 and 240 it was
sprayed directly from the machine. Long delays for cleaning, as well as
the potential for mechanical and electrical damage, discouraged further
application of shotcrete near the tunnelling equipment. When used again
between chainages 590 and 770, shotcrete was placed only after the machine
and conveyor system had advanced for their full length of 110 m beyond the
point of application. In this section shotcrete was used as additional
support for seat earth exposed in the crown. The seat earth was extremely
friable and showed substantial deterioration with time. The shotcrete,
applied in thicknesses of 60 to 100 mm, provided both support and insulation
for the seat earth.
In the sandstone the tunnel was advanced mainly under dry conditions,
although locally wet areas were encountered. In the vicinity of the rock
fall at chainage 235 the water inflow was approximately 250 m3/day.
4.3 Comparison of seismic velocities with ground conditions
The seismic velocities that were measured between chainages 250 and
550 show a bimodal structure, with upper and lower bounds of about 4000 m/sec
and 2500 m/sec. It is likely that much of the spread in the measurements
can be accounted for by the difference in velocity of compression (P) and
shear (S) waves. The upper velocities are very close to laboratory P-wave
velocities whilst the lower are similar to S-wave velocities calculated by
assuming a Poisson's ratio of 0.25. The attenuative nature of the rock in
this section made it difficult to interpret the time of first wave arrival
and, consequently to discriminate clearly between P and S wave arrivals. As
many as five or six hammer blows were required to achieve signal enhancement
sufficient to allow the first wave to be distinguished above the noise level
at the geophone.
From chainage 550 to 770 the decreased number of joints and diminished
joint thickness in the sandstone corresponds to a relatively high and
constant seismic velocity. This trend continues until chainage 850, where
seat earth was encountered at the springline. The average of the 22
velocities measured from chainage 550 to 850 was 4096 m/sec, giving a
ratio of in situ to intact seismic velocity of 0.96.
5. OBSERVED CONDITIONS AND TUNNELLING PERFORMANCE IN LIMESTONE
5.1 Tunnel geology
Between chainages 770 and 1130 the limestone was a hard, crystalline
material with relatively few impurities. From chainage 1130 onward an
increasing proportion of clay impurities was apparent as the limestone
graded into a nearly full face of mudstone at chainage 1270. A geological
cross-section of these portions of the tunnel is illustrated in Figure 5.
10
Bedding was apparent as stylolitic bands of impurities throughout the
limestone. Two well-defined sets of vertical veins were observed; one
striking at 335 to 345 ° NW, and the other at 60 to 75 ° NE. Owing to their
cemented nature, the bedding and vertical veins did not cause overbreak or
wedge movement.
5.2 Tunnelling performance
In Figure 5, joint frequency, volume of overbreak, rock bolt support
per metre run, advance rate, and seismic velocity are plotted for chainages
770 to 1270 in a manner similar to that for the tunnel section in sandstone.
The relatively low advance rates between chainages 770 and 900 were related
to shotcrete placement at the seat earth exposures between chainages 590
and 770. There, shotcrete operations blocked access to the machine, and
advance was not possible until the tracks had been cleared to allow free
communication for the muck cars between the machine and portal. From
chainage 900 to 1000, there was a gradual increase in advance rate. In this
section tunnelling was slowed by difficulties in changing several of the
cutters. Beyond chainage 1000, the average advance rate of 0.9 m/hr was
relatively close to the average cutting rate of 1.4 m/hr. The rock bolts
between chainages 810 and 1100 were used primarily to support the
ventilation equipment. Tunnelling in the limestone was performed under dry
conditions.
Throughout the limestone and shaly limestone, the intact nature of the
rock contributed to a conspicuously smooth bore, with little or no delay
caused by ground instability or support installation. In fact, the most
significant delays in this portion of the tunnel were associated with
support operations for the seat earth and difficulties in changing individual
cutters. Owing to the uniform ground conditions and lack of open jointing,
advance rates of a consistently higher value were sustained in comparison
to the rate predominant in the sandstone portion of the tunnel.
5.3 Comparison of seismic velocities with ground conditions
Between chainages 850 and 1270 the seismic velocities again show a
bimodal structure, with upper and lower bounds of 5600 m/sec and 3600 m/sec.
As was the case for most of the sandstone, this material was highly
attenuative. Correspondingly, there was difficulty in distinguishing whether
the first arrival was that of a P or S wave so that the spread in the
11
measurements was again related to the difference in velocity for the two
different wave types. By way of contrast with the sandstone, the joints in
the limestone were filled and well cemented with calcite. The anomalously
high attenuation in the limestone is most likely the result of multiple
reflection and scattering as the acoustic impedance of the calcite was
significantly different from that of limestone. A similar effect has been
noted in carboniferous limestone by McCann (personal communications).
6. OBSERVED CONDITIONS AND TUNNELLING PERFORMANCE IN MUDSTONE
6.1 Tunnel geology
A geological cross-section of the mudstone between chainages 1270 and
1600 is illustrated in Figure 6. The mudstone was fissile, showing a
marked tendency to split in horizontal planes parallel to the bedding. Its
slake durability index was 74 per cent, which indicates that the mudstone 20
was only moderately resistant to air and water slaking
Surficial slabbing was observed in all portions of the mudstone. The
over-break associated with the slabbing was up to 0.2 m deep. The surface of
the mudstone was subjected to at least two wetting and drying cycles and this
would have contributed to slaking of the rock. During cutting, the rock near
the face was saturated by the dust abatement spray. As the machine advanced,
the rock was dried by heat generated near the transformer. With further
advance, the decline of temperature and humid atmosphere caused condensation
which, in turn, was dissipated with time.
Most of the continuous joints (3.5 m) in the mudstone were calcite-filled.
Generally, the calcite was 2 to 3 mm thick with planar, smooth surfaces.
Bonding along the contact between the mudstone and calcite was weak. The
rock tended to break at this interface, thereby contributing to overbreak
and wedge movement.
Between chainages 1450 and 1480, a set of calcite-filled joints was
observed, striking nearly parallel to the tunnel axis at 15 ° to 30 ° NE.
Figure 7 contains a plan and profile view of the tunnel in the vicinity of
chainage 1472. As shown in the figure the subparallel joints contributed
both to the large overbreak at the east crown and to the displaced rock
at the west wall. Plate 3 shows the east crown and springline areas at
this location. The magnitude of overbreak can be judged relatiVe to the
12
protective cover of the tunnel boring machine, which marks the approximate
outline of intended excavation. These observations corroborate those of
Cording and Mahar 3 and Whittle 5 for similar conditions of subparallel
jointing in schistose gneiss and slate, respectively.
6.2 Tunnelling performance
In Figure 6 joint frequency, volume of overbreak, rock bolt support
per metre run, advance rate, and seismic velocity are plotted for sections
of the tunnel in mudstone.
From chainage 1270 to 1390 the mudstone was substantially intact with
a low joint frequency. Correspondingly, a relatively high advance rate is
shown. After chainage 1390, the conspicuous decline in advance rate is
consistent with the worsening ground conditions in the zones of faulting.
These, in turn, are reflected in the increased joint frequency, volume of
overbreak, and quantity of rock bolts.
The faults at chainages 1410 and 1570 were minor, involving down-throws
of approximately 2 and Im, respectively. By way of contrast, the fault at
chainage 1515 was more substantial, with a vertical offset of approximately
8 m and a zone of intensely fractured rock that was 20 m wide (McFeat-Smith,
personal communication). The nature of the rock in the fault zone not only
caused support problems, but interfered with the operation of the tunnel
boring machine. Plate 4 illustrates an important aspect of this interference
by showing the ground condition immediately adjacent to a rear anchor pad at
chainage 1512. The lateral overbreak and fractured quality of rock placed
severe limitations on the reaction force that could be sustained by the
anchor pads. As indicated in the picture, a suitable reaction could be
obtained only by 'packing out', or wedging, timber beams between the pad and
rock surface. Tunnel support at this location was accomplished by means of
steel arches or by steel beams that were bolted directly into the more
competent limestone and mixed beds beyond chainage 1520.
Excavation in the mudstone was mostly under dry conditions with one
notable exception at chainage 1575. At this location, holes drilled for
the rock bolts intercepted an aquifer approximately I m above the tunnel
crown. The ensuing water inflow of 1500 m3/day was eventually controlled by
diverting the water through hoses, which were socketed into the crown.
13
6.3 Comparison of seismic velocities with ground conditions
The mudstone was the least attenuative material to seismic waves. Often,
only I or 2 hammer blows were sufficient to produce clear P wave arrivals.
The general trend of the measurements shows fairly gradual changes in seismic
velocity probably due to changes in the in-situ modulus of the material.
At chainages 1420, 1520 and 1570, there is a sudden and distinct drop in
velocity. This is indicative of highly disturbed areas of rock and is
exactly correlated with observed areas of faulting. A reduction in velocity
was also noted between chainages 1455 and 1475. This corresponds to a zone
where frequent subparallel joints resulted in large overbreak (see figure
8 and Plate 3). In general, the measurements of in-situ seismic veloc&ty
were considerably higher than laboratory measurements on unconfined samples
from this section (see Table 3). This discrepancy is apparently related
to the in-situ confining stress and its compressional effect on the highly
laminated mudstone.
7. DISCUSSION
7.1 Tunnelling delays and geology 19
In a companion paper, Morgan et al have shown that, during machine
excavation in the first 1600 m of the North Wear Drive, it took an average
3.25 hours to excavate and support I m of tunnel. As an overall average,
20.3 per cent of the time was devoted to installation of support, 7.4 per
cent was caused by delays due to blockage of the intake chutes, and 6.1 per
cent was caused by delays resulting from problems such as rock falls and
water inflow. These percentages are the proportions of total time in
addition to the time required for rock cutting and, thus, do not reflect
the services performed concurrently with actual rock excavation.
In Table 6 are s,lmmarised the times for unit advance in each of the
main rock types together with the percentage of this time taken up by the
s,lmmed delays from the categories above. The record of tunnel delays shows
that progress was closely dependent on the local geology and in-situ rock
structure. The principal zones of delay correspond to portions of the
tunnel in highly jointed sandstone and mudstone. In particular, the high
percentage of delay time between chainages 1500 and 1600 was associated with
fault zones and an area of high water inflow. The high percentage delay
shown for the limestone, between chainages 770 and 890, did not result from
poor ground conditions near the face, but rather from shotcrete application
14
to the seat earth, which was a full 110 m behind the face of the machine.
Where the rock was self-supporting, the time for unit advance showed a
marked reduction. The low frequency of joints, and stable intact nature of
the clayey limestone, between chainages 1127 and 1270, contributed to an
environment where only 1.6 per cent of the tunnelling time was associated
with delays caused by ground support or mucking difficulty.
7.2 Machine construction and tunnelling performance
Blockages of the intake chute, which caused substantial delay at the 21
North Wear Drive, are not without precedent. Bennion reports that
similar difficulty in highly jointed andesite restricted progress during
construction of the Kaimai Tunnel.
If the exposed area at the periphery of the cutting head is larger than
the dimensions of the intake opening, blockages of the opening may occur.
This is illustrated in Figure 8 which shows a three-dimensional view of the
cutting head of the Demag machine. The gathering arms of the machine are
located at quarter points around the cutting head, and the distance
separating the dust shield and excavated face is approximately 1.25 m. At
the periphery of the cutting head, the spaces between the scraper arms are
open to penetration by relatively large blocks. Consequently, rock exceeding
the dimensions of the intake chute could be swept towards the intake opening
and wedged there.
The vulnerability of the cutting head to obstruction is evidenced by
the many delays caused by the blocked intake chute. The close relation
between blockages and rock structure is substantiated by the recorded
locations of the blockages. For example, obstructions of the intake chute
were negligible when excavating through full-face limestone and intact
mudstone. By way of contrast, the delay associated with blockage was highest
during initial tunnelling in the sandstone where the high frequency of
mud-filled joints contributed to loose rock and overbreak.
At Kielder the Demag machine was equipped with front anchor pads whose
forward movement was controlled independently of the movement of the
central shaft. Thus, as the cutting head was pushed\forward, the front
anchor pads remained stationary, providing stability for the cutting head
15
and alignment for the machine. At the end of the cutting stroke, the front
pads were retracted and moved forward to a new position. If steel arches
had been erected immediately behind the cutting head, it would have first
been necessary to retract the front pads far enough to move them past the
recently erected arches. For Demag machines greater than approximately 4 m
diameter, it is possible to design for this operation. However, the space
restraints imposed by a 3.5 m diameter tunnel preclude this capability.
Consequently, the machine construction was not compatible with installation
of support ~mmediately behind the cutting head. Instead, the support
platform was located behind both the front and rear anchor positions at
12 m from the excavated face. In view of the average 3.25 hours per metre
advance, the location of the support platform represents some one to two
days without rigid support. As it is well established that delay in
supporting the excavated rock will frequently contribute to higher support
loads and overbreak this aspect of the machine construction must be
carefully considered when evaluating the tunnelling performance.
7.3 Seismic velocity measurements
The seismic velocities obtained between chainages 250-550, corresponding
to sandstone with a high frequency of clay-filled, continuous joints, and
chainages 850-1300, corresponding to a limestone with a high frequency of
continuous, calcite veins, were not useful as a measure of rock quality.
However, they have interesting geophysical implications.
Figures 9a and 9b show waveforms typical of those received in areas
of rock with moderate and high attenuative properties, respectively. The
amplitude of the shear and surface wave arrivals was at least three times
that of the P wave arrivals as shown in Figure 9a. This is in accord with 22
estimates made by Miller and Pursey that for a surface source producing
small strains, the energy is divided between wave types as follows:-
(I) Rayleigh surface waves
(2) Shear waves
(3) Compressional waves
67%
26%
7%
It should be noted that the energy in a wave is proportional to the square
of its amplitude. Areas of moderate attenuation required relatively low
16
signal amplification and only one or two hammer blows for good signal
fidelity. However, areas of high attentuation required high electronic
gain (this also amplifies the noise) and as many as six hammer blows to
achieve a suitable signal. As a result, the P wave signal to noise ratio
was severely degraded and settings could only be made on the later wave
arrivals (see Figure 9b). Further signal enhancement did not noticeably
improve this situation. The wave forms shown illustrate the best and worst
case of amplitude profiles. The received wave forms in highly attenuative
rock usually lay somewhere midway between the best and worst case, making
accurate field measurement extremely difficult. At certain locations in the
tunnel this resulted in the tendency toward a bimodal distribution of
velocity measurements related to P and S wave velocities. Had more time
been available, the measurement technique could have been improved by
drilling holes in the tunnel sidewall at each measuring point. This would
have allowed for rigid geophone coupling to the rock, and, by striking a pin
located in such a hole, a greater proportion of the hammer energy would have
transmitted into P waves travelling toward the geophone.
Whereas the measurement of seismic velocity in rock with a high frequency
of continuous, infilled joints or veins was inconclusive with respect to rock
quality, the measurements in other areas of the tunnel have given a much
better indication of the existing ground conditions. From chainages 550 to
850 and from 1270 to 1400, the measurements of consistently high values of
seismic velocity correspond to areas of infrequently jointed sandstone and
mudstone, respectively. Most notable are the measurements associated with
areas of faulting in the mudstone. At the location of each fault, there was
a prominent drop in the seismic velocity. Furthermore, the extent of this
drop was related to the intensity of fracturing associated with each fault.
The minor faults at chainages 1413 and 1570 correlate with seismic velocities
decreased to approximately one-half the velocities in adjoining sections of
the tunnel. The larger fault at chainages 1510-1530 correlates with a seismic
velocity decreased to approximately one-fourth of the velocities in
adjoining sections of the tunnel.
8. CONCLUSIONS
Observations during the first 1600 m of machine tunnelling at the North
Wear Drive indicate the rate of advance was closely dependent on the nature
of the rock jointing and variations in the local geology. These aspects of
17
the tunnel environment affected both the support and mucking operations,
thereby exerting a dominant influence on the tunnelling progress.
The time required for placement of support and delays associated with
blockages of the cutting head, rock falls, and water inflow amounted to
between 55 and 60 per cent the time for unit advance through sections of
highly jointed sandstone and faulted mudstone. In contrast, the time loss
from rock support and difficulties related to local geology was insigni-
ficant through sections of clayey limestone and intact mudstone. In the
former case, the machine progress was relatively insensitive to the time
required to cut, or bore, a unit length of ground. In the latter case,
progress was very sensitive to the cuttability of the rock, as the average
time per unit advance was relatively close the the average time per unit
cutting.
Two specific features, which show the inter-dependence between ground
conditions and machine performance at the North Wear Drive, are worthy of
comment :
I. Blockage of the intake chute was a frequent difficulty. Observations
regarding the in-situ rock structure and locations of frequent blockage
suggest that this problem should be anticipated in ground with two or more
sets of relatively open and closely spaced joints unless the periphery of
the cutting head is designed to prevent the penetration and subsequent
movement of large blocks toward the intake area.
2. The relatively large distance separating the excavated face and working
platform at the North Wear Drive left the rock without rigid support for
long periods of time. Without support, loosening and dislocation of the
rock, especially under conditions of open jointing, led to high overbreak
in some areas and increased support requirements. Consequently, there is
considerable advantage in designing so that support can be placed immediately
behind the cutting head.
In sandstone and limestone with a high frequency of continuous,
infilled joints and veins, respectively, the measurement of seismic
velocity was inconclusive with respect to rock quality. However, seismic
velocity was shown to reliably indicate the presence of faults in mudstone.
18
Moreover, the velocity decrement associated with each fault zone was related
to the degree of rock fracturing in the fault. Whereas seismic scans will
generally have little practical application once the excavation has been
performed, they may be useful for providing information during horizontal
probing in advance of tunnelling. Further research and development will be
needed to improve the technique and to build a body of experience in various
geological environments.
9. ACKNOWLEDGEMENTS
The work described in this report forms part of the programme of research
on tunnels at the Transport and Road Research Laboratory.
The Laboratory wishes to thank the Northumbrian Water Authority, the
consulting engineers Babtie, Shaw and Morton, and the contractors Tyne
Tees Tunnelling for permission to carry out and their co-operation in these
studies.
The authors wish to thank Mr J G W Brown, Mr D Fawcett and
Mr H S Eadie (Babtie, Shaw and Morton), Mr K Milow and Mr S Keis for their
helpfulness and assistance on site and their colleagues Dr J A Hudson,
Mr J M Morgan and Mr D A Barratt for their assistance with the study.
I.
10. REFERENCES
BREKKE, T L and T R HOWARD. Stability problems caused by seams and
faults. Proc. North American Rapid Excavation and Tunnelling Conf.
ed Lane and Garfield. Vol I, 25-64 (AIME, Chicago, 1972).
2. CORDING, E J and D U DEERE. Rock tunnel supports and field measure-
ments. Proc. North American Rapid Excavation and Tunnelling Conf.
ed Lane and Garfield. Vol I, 601-622. (AIME, Chicago, 1972).
. CORDING, E J and J W MAHAR. The effects of natural geologic
discontinuities on behaviour of rock in tunnels. Proc. North
American Rapid Excavation and Tunnelling Conf. ed Pattison and
D'Appolonia. Vol I, 107-138 (AIME, San Francisco, 1974).
19
. WARD, W H, D J COATS and P TEDD. Performance of tunnel support
systems in the Four Fathom Mudstone. Proc. Symp. Tunnelling 76,
London, 1976 (Institution of Mining and Metallurgy).
. WHITTLE, R A. Geotechnical aspects of tunnel construction for the
Dinorwic power station. Ground Engng. 1977, 10, 15-20.
. ONODERA, T F. Dynamic investigation of foundation rocks in situ.
Proc. Symp. Rock Mech., 5th Minnesota, New York, 1963 (Pergamon).
. DEERE, D U, A J HENDRON Jr, F D PATTON and E J CORDING. Design of
surface and near surface construction in rock. Proc 8th Symp on
Rock Mechanics, Minnesota, 1966 (AIME).
8. DEERE, D U. Indexing rock for machine tunnelling. Proc. Conf. on
Rapid Excavation: Problems and Progress, 32-38. (Society of Mining
Engineers of America, Institute of Mining, Metallurgy and Petroleum
Engineers) 1968.
. HUDSON, J A, E J W JONES and B M NEW. P-wave velocity measurements
in a machine-bored chalk tunnel. Quart. J Engng. Geol. (in press).
10. MOSSMAN, R W and G E HEIM. Seismic exploration applied to undergound
explorations. Proc. North American Rapid Excavation and Tunnelling
Conf. ed Lane and Garfield. Vol I, 169-192 (AIME, Chicago, 1972).
11. CRATCHLEY, C R, P GRAINGER and D M McCANN. Some applications of
geophysical techniques in engineering geology with special reference
to the Foyers hydro-electric scheme. Proc. 24th Internation Geological
Congress, Section 13, 1972, 163-175.
12. MURPHY, V J. Seismic velocity measurements for moduli determinations
in tunnels. Proc North American Rapid Excavation and Tunnelling
Conf. ed Lane and Garfield. Vol I, 209-216 (AIME, Chicago, 1972).
13. BURSTON, U T and D J COATS. Water resources in Northllmhria with
particular reference to the Kielder Water Scheme. J. Instn Water
Engrs, 1975, 29 (July), 226-51.
20
14. CARTER, P G and D A C MILLS. Engineering geological investigations
for the Kielder tunnels. Quart. J. Engng Geol., 1976, 9 (2),
125-41.
15. FOOKES, P G and B DENNESS. Observational studies on fissure patterns
in Cretaceous sediments of south-east England. Geotechnique 1969,
19, 4, 493-7.
16. PRICE, N J. Fault and joint development in brittle and semi-brittle
rock. Oxford, 1966 (Pergamon Press).
17. PRIEST, S D and J A HUDSON. Discontinuity spacings in rock. Int J.
Rock Mech. Min. Sci and Geomech Abstr. 1976, Vol 13, 135-148.
18. KOLEK, J. An appreciation of the Schmidt rebound hammer. Mag.
Concrete Research 1958, 10, 28, 27-36.
19. MORGAN, J M, D A BARRATT and J A HUDSON. Tunnel boring machine
performance and ground properties. Report on the initial I% km of
the North Wear Drive, Kielder Aqueduct. Department of the Environment
Department of Transport, TRRL Report SR 469. Crowthorne, 1979
(Transport and Road Research Laboratory).
20. FRANKLIN, J A and R CHANDRA. The Slake-Durability Test. Int. J. Rock
Mech, Min Sci. and Geomech. Abstr, 1972, 9, 325-344.
21. BENNION, J D. The Kaimai tunnel, New Zealand - a case history.
Proc. Symp. Tunnelling 76. London, 1976 (Institution of Mining
and Metallurgy).
22. MILLER, G F and H PURSEY. On the partition of energy between elastic
waves in a semi-infinite solid. Proc. Royal Society, ]955, 233,
55-69.
23. TERZAGHI, K and R B PECK. Soil Mechanics in Engineering Practice.
1967, New York (John Wiley and Sons Inc).
21
TABLE 1
Discontinuity data from scanline surveys
Chainage (m)
339- 369
525- 575
1052-1170
1210-1280
1315-1345
1405-1425
1455-1467
1555-1566
Rock Type
Sandstone
Sandstone
Limestone*
Calcareous Mudstone
Mudstone
Mudstone
Mudstone
Mudstone
Number of
Values
96
39
(177)
18
32
64
39
Mean discontinuity
spacing (m)
0.31
0.79
(0.67)
3.89
0.94
0.31
0.30
57 0.19
Discontinuity spacing, standard deviation
(m)
0.38
1.11
(0.67)
3.64
1.13
0.29
0.23
0 .19
* Calcite veins
22
O~
O N 0
0
H
o
tO -,-I
~ • O ~ E i
-,-I 0 4a
0
o
0 1~ -,4
1.4 ~ 0 ~ O CO 0 ,el ,Cl 0 ,'0 -,-4 • 0 ,-4
rd ~0 ~ , c l
c o b . t~ O rO • • ..cl •
0 "el , ~ ~ 0
,--I 0 I~ O
~0 0 ..Cl ..Cl 0 :~ El m 0 ~
0 0
0
o 0
o t~
.~_j v
,.c: 0
1"~ o co ~ ~o
I
C~
t 'M
r ~ ~z
T ' -
cxl
o
C"l
,'~ 0 0 (X) 4-~ • • 0 ~I
,.el 0 o 0 ~ 0 o 0 • ~ ~ ~ I~ ca ~ • 4.~ ~ ~ ~ 0 0 0 o
o o~ c0
I o
o
c~
T c~
o o
L/h
T--
o
~o
T o o
i./-1
23
TABLE 3
Seismic velocities in intact rock specimens
(Unconfined)
*P-Wave Rock type Seismic velocity
m/sec
Sandstone 4280
Limestone 5550
Mudstone 3580
* Note: All velocity measurements were performed parallel to the bedding
24
o
0
-H
o
4=) -H
~o
0 o
0
o -H
o
o t~
t~
0
o o
u]
t~
o
-,.4
.O -H
A
O 0
o ~i
0~
O -H -IJ
-H
O
0 -,-I 4J
-H
O
,-¢
c01::: = ~ o ~ O • i::: -,.4 O~ = O,>
~ -~ ,.~ N -,~ ,-4 -I-) 0 ~ ~-~ "~ ",~ I'4 0 0
"- •
0 ~ ~ $4 I -H
).4 ,-4 ~) ..C ,--I •
0-,
O cq
I
o )..o
A
(~1 I! I
t o cq • •
o ~
Z
O
t
-H
O
D~
-H 'D
o
0-~ 0
m 0 o,-~ ~ m > o
,..~ H ~
o - H 0 (0 ,.)
~ . ~ ~ ~ ~ - ~ I~ ~
I
,--I •
u)
O o co I
..O o o Z
- H I " ' O ~ o ~ o .iJ ~n -~1 c0
.IJ
-H O
Z
-,4 O
4J u~ O
G) O >
"- •
:~ o - , ~ O t~ .$-) 1'4 I - H
~ 4J ~
o
I o
>,11/') ~-t •
o A
o
II I
c~
Z O o
O co
oo~ Z
-H o ,.O ~ ~o
O "F'-I
z
-H O
25
TABLE 5
Properties of clay infill
Property Value
Water content 58%
Liquid limit 67%
Plasticity index 41%
Undrained shear strength* 4 kN/m 2
* Determined from laboratory
shear vane tests
26
TABLE 6
Summary of advance rates and delays
caused by ground conditions
Rock
type Chainage (m)
Unit advance time (hrs/m)
% Unit advance time caused by delay
from ground conditions
124- 309 8.24 56.2
Sandstone 309- 599 2.96 18.6
599- 770 3.04 15.8
770- 890 4.11 32.4
Limestone 890-1127 1.86 10.8
1127-1270 1.25 1.6
1270-1397
1397-1500
1500-1600
124-1600
Mudstone
1.28 3.9
2.07 31.9
4.28 59.1
3.25 33.8 TOTALS
27
i 0
U-
0 ¢-.
0 m
>.
0 Q;
0 rr
(-
o
-C} "m
E 0~ l-
,9o
(I) (P (-- Q,) e=" (" (U ~--
o o o .
no E r X -~
NNNN (i~ 0 (..)
II
I I I I I I I I I
(LU) ale0s le0!~JaA
I 0 0
z
E 0
'̧ o
0,)
.......... ....... . _ (=.
0 o ~ o~ ~- g o
¢ ~ . _ - -
- - 0
0 0
0 0 0 m.-
0 - - 0
I-0
0 0 0
0 _ 0
A E
¢- (...
I -
I.I.
13: U.I ==o =< =~, " J N
m Z
I I I I I
0
z
~o r0
J3
8
: o
c o
~ ~ ~ . ~_
z ~ 8, .u
£ ¢
o ~
~ ' ~ ~
O o ~ o
k- z
° ~ ~ < ~ - - 0
o E 0~ ~ -~ : ~
~- o
z ~ ~ ~ o ~
~ ~ o ~ . -
0
~ o o o~ s o
~- ~ > "~ . o o
z ~ o ~ z _~ >~ ~o ~° z~ ~=> ,~°° <: ,~ o ~ z ~- >. ~" < ~ '~
'- ,~ uo ~ ua ~ Z m ~ Z
~ ~ o . ~ - = = ~ ~ o 4-- ~ ~ o Z ~ o >
. < . ~ o ~ .~ : o ~ ~ ~ ~ ~ ~ o o
o ~ ~ ~ o ~ = o o ~ o ~ ~ ~
• E
E c C E c ~ c ~
~, ~ ~ ~ ~ ~ ~ 0 2 ~ o o ~ ~
¢xl ~ ' ~ uO ~ r ~ CO 0 3 0 ~ ~ ~ 0
- - I
Z Z
I , -
O
I L l - - I
,'T O
- - 1
O
(D O . J
I Ill --.~ I i i i I ~ : I ~ ~ ~ - 7 ~ - o , ..... I V ~ - : - - ~ 1 ! ! 1 ! I ~ ~ / k i - - - - ~ : = ~ _ ~ " 2
e - i o
5
f f
a .~o 0 .w~
o
i ii! i
~ z o N 0 U
I I I I I
I I
~p w ~ o N O - -
I I q
0 ' ,
I I P r I I I I
o
Tunnel dr ive d i rec t ion
3 ~ o 3so o ,o / ,o 3~°..~1~ \ k l i l i I/7"-7.t ,,o..~U~ I';'; 7T
:~ t~X~ ~4~-~/-zT/Y,~/-~/Xt ° " ° z X ~ $ . ' ~ o W,,//~/~,o ,oo~~~\~ j j i /? , f f~ /~o , oo - , , o
,,o _ -o. ,o , , o ~ _ ~ ~ , o
2 6 0 ~
i i l l l l \ \ , = o ~ / / / ~ ~ >~,o ~ , o ~ / / ~ \ ~ , o ~'°"<-LJ / / I / / \ ~.>.-'~,o , , o ~ / ~ ~n i~ \ i,/,5o
200 ~ 1 6 0 200 160 190 180 170 190 180 170
Chainage 250--300m 32 values Chainage 339--369m 97 values
~ \ ~ t i " l / / 320 40
3 ~ ~ / / O ~ 50 ~ l ~ O / J .J~/~j 3103 ~ ' ~ ~ 20%/ ' -~
280 _ ~76°/ 8O 2 8 ( ~ 270 - ' ~ ~ 90 270
2 6 0 ~ 1 0 0 260
. o - . < j / / ~ \ \ ~ , , o .o 210"--~/ / I I I \ \ ~--~50 22°210"'~///I ! II \ "~ / / / 7 - ~ - ~
200 ~ 1 6 0 2 0 0 - " ' ~ _ J _ _ . ~ 190 180 170 190 180 170
Chainage 422- -479m 30 values Chainage 545--575m
100
0
, ~ , o 1"° 160
38 values
3 5 0
3 0 0 ~ _ _ ~
2 7 0 ~
250 ~ J ~ //~////
190
0 10 ) 3
L\II//I/7,/O~" ~ 5o 6o l\ lJJT/llD'oJ;&
, 120 0 -o
50 180 170
Chainage 1025--1200m 61 values
Fig. 2 D I S C O N T I N U I T Y ROSE D IAGRAMS
340
~ o ~
28O 2 7 0 ~ 260 25O
240 230
220
190 180 170
Tunnel drive direction
200
~ . ~ 340 330 40 50 60 310-^:~320~
300 70 2 9 0 ~ , 8O 28O 9O 270 100 260
~ 110 2514 ~ 120 ~ 24O ~ 0 ~ 130
140 220 160 2O0
3O
! 110 120
130
150 190 180 170
Chainage 1210--1345m 48 values Chainage 1405--1440m 73 values
350 0 10 3~^ 3 ~ s T T ~ -
3 , o z ~ \ ~ \ \ III I / I 300 I I I
2 8 0 ~ 270 260
~ o - . < . / / / ~ \
1~ 180 170
Chainage 1455-1467m
350 0 10 I0 3 ~
280 ~"~o
270
~ i O0 260 0 250
1~140 2 2 0 ~
160 190 180 170
39 values Chainage 1555--1566m
0 30
' ° °
0 1~20
130
150
57 values
Fig. 2 (cont.) DISCONTINUITY ROSE DIAGRAMS
0~
. E (J (.-
r r
A
..Q
" o ( - (o
x
"O
.m.
O r r
A
0o O
o l ~" ~- O
(J
2
O i i
co {3.
8 o E
o i i
E
o l ( -
JE
(3 _ ~'~::::~iii~iii~iiiiiii~iiii~iii~:~;~~ ,
r '"09"8 -
E LO
E 0 C~
A
• - . ~ ~.. 4 -
~ o
m r j o 0 .j co r- ~.
I
Z O
i-- ( J W 00
b 0 00 o n,-
( J
E
O
/ /
E LO
i i i >
C¢
ILl
3: I-- n -
O
z I.-
i i i
z "T- (.1
(.9 Z
O
. - I LU
z z
D.-
o l i i
E O
O.
?_,
.Q
E Z
i .Q
o
I ~ Sandstone ~ Seat earth ]
L, .L . : ' ,~ , , , ' " , " . ' . , ' " " . ' , , " , . , . , . , . ' • ' ~ '
i - - , ~ 1 " , . . t . . . . . " , ' , , . . , • ' - . , . . . . I M u d s t O n e & I I t "~, " ' , " ' ' " , ' " ' ' ' • " , • ' " I m i x e d b e d s i i ) , : ~ , _ - ~ _ ~ " , ' • " ' . , ' " ' ' , ' , • ' . ." '
40 I 30
20
10
0
ii~i: Iii!i~ !iiii
F -
E -
D -
C -
B
A
I A = O D = > 4 ' ~ < 6 m ~ I
oJ b. 16 F -'~ F'- Placement of steel arches
~ 8
! o | ii:,illi: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ::.:::::: :: : :::i:;::: ::: : : [ ::: ::" i : : " : ": ::::: ::" : : :: : : .: I r r
-- 1.25 I
10' E •
0.50
<~ o.25o ................ ,,:~:, ,i~, ~ : ~: ' ~ ~
6000
~- 5000 E "~ 4000
3000
,~ 2000 E .~ 1000
0
O 0 O 0 O 0 0 0 0 0 0 0 0 0 0 0 0 I O 0 • • • •
• • O 0 • • O 0 • O 0 0 0 O 0 0 0 0 0 0
I I I I I I I |
150 200 300 400 500 600 700 770
Chainage (m)
Fig. 4 S U M M A R Y OF D A T A F O R T U N N E L L I N G IN S A N D S T O N E
E o
o
E Z
o
E
"5 ,.Q
if-
r r - - n Sands tone ~ Seat earth l i it L i m e s t o n e
E:~:,~:~:~:'::~ Sha ley l i m e s t o n e ~ M u d s t o n e
.... ~i~i~i~i~i i~#~ ~ : #~. - - - - --t ..................................................... ii.:.::~:~.~._.-_. ~
..... ! i i ~
30 P r e d o m i n a n t l y ca lc i te veins
1 0
0
F
E
D
C
B
A
I A = 0 D = >4, ~ 6 m 3 / I
B = >0, ~2m ~ E = >6, ~8m 3 C = > 2 , ~ 4 m ~ F = >8m 3
B e r n o l d sheets
iiiiiiiiiiiiiiiiii:,iiiiiiii
12
, iiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiii
E
c
"1o <
1 .25
1.0
0 . 7 5
0 . 5 0
0 . 2 5
0
iiiiiiil - i~i;i~it
iiiiiiililililiiiiiii!iiiiiii!iiiiiiiii;i;ii;t - , ....................... i~:i:~i~i:~i~.i::i::ili::iii::iiiiiiiiii~i;ii;iii::iiiiiiiiiiiiiiiiiiiiiii!iii ::iiiiiii:.!iiiii!iiiiiiiiiiiiiii!iiiilili::ili ::::~:::: :: :: ............................... ::i :.!:: :: :: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
i ii!i;iiiii }iii!i!i!i i i iii i iii iiii: iiiiii iii!i!: iiiiiiiiiiii iiiii :iiiii::i: i::?iiiiii i :i :i iiiii iiii iiiiii}iiiiiiiiiiiii!iiiiiiiiiiiiiiiii iiii i: :i i i i i iiiiiiiiiiiiiii!iiiiiiii!i i!ii i iX) :::::::::::::::::::::::: ~::~::s::~:.:.:.ii:::iii )::iii::i::ii i iiiiii::i i iiiii? i i ;iiiil);iiiii)::i::)iiiiiiiiiiiiiiiiiiiiiiiiiiiiii::iiii!:J:;::iii!ili i iiiiiiiiiiiii)iiiiiiiii!i!ilililili!ililiiii ;ii;i);iiiiiiii; i)ii i i i i::ii ;iiiiiiiiiii i ii;i::i::i::ii i iii):ii:::: iiiii;i)iiiiil)iiiii::::iil i:: i iiiiii!)Ziiii;ii::i::i::iiii)!iiiiiiii;i)i!iiiiii:.i::ili:.i!i !iiiii;i i i i i!? ili iiiiiii!ii! iiiiiil}:.il;iilmi:.iii
6 0 0 0
5 0 0 0 E
4 0 0 0
3 0 0 0
.~ 2 0 0 0 E
1 0 0 0
0
• , & A & A • • A • • & A & A A A & &
0 0 0 0 0 0 A A • • A • • • • & & •
- • • t Se ism ic ve loc i t i es • • ~ in seat ear th
& &
& & A V,
I I I I I I 770 8 0 0 9 0 0 i 0 0 0 1100 1200
Chainage (m)
Fig. 5 S U M M A R Y O F D A T A F O R T U N N E L L I N G I N L I M E S T O N E
i 1270
1 ~ Mudstone ~ Shaley limestone ~ ] Limestone I
E O
E
O
.Q
E
k_
30
20
10
0
Limestone
Mixed beds
Fault zone
J3
o
t~
.D
O 6E
E
r0
E
-(3 <
F
E
D
C
B
A : : i
16 L 12 8
4
0 1.25
1.0
0.75
0.50
0.25
0
Placement of steel arches -~ I ~-
L
A-0
B - >0 , ~<2m ~
C = >2 , ~4m ~
I D = >4 , <~6m ~
E - >6 , <~8m ~
F - >8m ~
6000 A
5000 E v
4000
3000
.9 2000 E
1000
0
• • V V • V • • V '~
• •V V v • • F • v • • • •
t I I I I 1270 1300 1400 1 500 1600
Chainage (m)
Fig. 6 S U M M A R Y OF D A T A FOR T U N N E L L I N G IN M U D S T O N E
N
T 1 Td??e~e
Subparallel
(a) PLAN VIEW
A
Subparallel joints
(b) PROFILE, SECTION A--A
Fig. 7 ROCK M O V E M E N T A N D O V E R B R E A K RELATED TO SUBPARALLEL JOINTS
Intake chute
Block dislodges from
Rotation direction
"U
Fig. 8 T H R E E - - D I M E N S I O N A L V I E W OF BLOCKAGE AT THE C U T T I N G HEAD
Compressional (p) waves Shear (S) and surface waves
J Hammer impact
starts sweep
Cursor
- I I II ID Jl__.
X Digital display
(a) MODERATELY A T T E N U A T I V E M A T E R I A L
Seismic + electrical noise
Cursor at first discernible wave arrival \
q
Time (milliseconds)
/ X
Digital display
--I I - - I I _1. _1 I
(b) HIGHLY A T T E N U A T I V E M A T E R I A L
Fig. 9 CRT DISPLAYS OF TYPICAL WAVE A R R I V A L S
Neg. No. R1590/76/18
Plate 1 UNSTABLE WEDGE A T S I D E W A L L IN S A N D S T O N E
Neg. No. R1590/76/20
Plate 2 JOINTS AT CROWN IN S A N D S T O N E
Neg. No. R1590/76/16
Plate 3 0 V E R B R E A K RELATED TO S U B P A R A L L E L JOINTS
Neg. No. R1590/76/1 5
Plate 4 PACKING OUT REAR ANCHOR PADS IN A F A U L T E D SECTION OF MUDSTONE
(2221) Dd0536361 1,500 11/79 H P L t d So ' ton G1915 PRINTED IN ENGLAND
ABSTRACT
SOME OBSERVATIONS OF MACHINE TUNNELLING AT THE KIELDER AQUEDUCT: T D O'Rourke, S D Priest and
B M New: Department of the Environment Department of Transport, TRRL Supplementary Report 532: Crowthorne, 1979 (Transport and Road Research Laboratory). The Kielder Water Scheme, currently under construction in north-east England, will consist of 32 km of tunnel to direct water from the Tyne to the Wear and Tees River Valleys. The project, which is promoted by the Northumbrian Water Authority, involves excavation through sedimentary strata using 3.5 m-diameter tunnel boring machines.
The Tunnels Division of the Transport and Road Research Laboratory (now the Tunnels and Underground Pipes Division) planned and implemented an observation programme during tunnel construction for the North Wear Drive, a portion of the Kielder tunnel system linking the River Wear with a companion tunnel drive from the Derwent Valley. The observations were performed with the assistance of Babtie, Shaw and Morton, the general engineering consultants for the Kielder Water Scheme.
Detailed observations and measurements were taken in the first 1600 m of the North Wear Drive, where the tunnel was driven through approximately equal lengths of sandstone, limestone and mudstone. This paper summarises the structure and material properties of the in-situ rock in each of the principal lithologies and compares the observed ground conditions with the machine advance rates and rock support adopted during tunnelling.
Attention is directed to the performance of the tunnel boring machine in light of the geological conditions, and improvements are suggested as an expedient to future machine excavation. In addition, the results of seismic scans, taken along the tunnel, are summarised and compared with detailed observations of the rock conditions.
ISSN 0305-1315