TRANSNET SOC LTD DCT BERTHS 203 TO 205 - · PDF filetransnet soc ltd dct berths 203 to 205...

49
TRANSNET SOC LTD DCT BERTHS 203 TO 205 ‐ RECONSTRUCTION, DEEPENING AND LENGTHENING PORT OF DURBAN SPECIFICATION – CORROSION PROTECTION 1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B 21 APRIL 2017

Transcript of TRANSNET SOC LTD DCT BERTHS 203 TO 205 - · PDF filetransnet soc ltd dct berths 203 to 205...

 

 

 

 

 

TRANSNET SOC LTD 

DCT BERTHS 203 TO 205 ‐ RECONSTRUCTION, DEEPENING AND 

LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B 

21 APRIL 2017 

 

TRANSNET SOC LTD DCT BERTHS 203 TO 205 – RECONSTRUCTION, DEEPENING AND LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B  April 2017 

REVISIONS 

REV  DATE  DESCRIPTION DESIGNED 

BY 

CHECKED 

BY 

APPROVED 

BY 

T‐00  31 May 2016  Issue for Review  NW  MC  JZ 

T‐0A  18 November 2016  Issue for Tender  NW  MC  JZ 

T‐0B  21 April 2017  Annexure 3 added  NW  MC  JZ 

           

           

           

           

           

           

           

           

           

           

           

AUTHORISATION 

AUTHORISED BY  NAME  SIGNATURE  DATE 

DIRECTOR  J ZIETSMAN Pr Eng  

21 April 2017 

 

This document, including all design and information therein, is Confidential Intellectual Property of  

ZAA Engineering Projects and Naval Architecture (Pty) Ltd. 

Copyright and all other rights are reserved by ZAA Engineering. 

This document may only be used for its intended purpose. 

TRANSNET SOC LTD DCT BERTHS 203 TO 205 – RECONSTRUCTION, DEEPENING AND LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B  April 2017 

CONTENTS 

1.0  SCOPE   .................................................................................................................................................... 1 

1.1  Project ..................................................................................................................................................... 1 1.2  Scope ....................................................................................................................................................... 1 

2.0  NORMATIVE REFERENCES ........................................................................................................................ 1 

2.1  Reference Documents ............................................................................................................................. 1 2.2  Standard Specifications ........................................................................................................................... 1 2.3  Employer’s Project Specific Specifications and Standards ........................................................................ 1 

3.0  DEFINITIONS ............................................................................................................................................ 2 

3.1  Chart Datum Port ..................................................................................................................................... 2 3.2  Co‐ordinate System ................................................................................................................................. 2 3.3  Tidal Levels .............................................................................................................................................. 2 3.4  Method Statements ................................................................................................................................ 2 

4.0  REQUIREMENTS ....................................................................................................................................... 3 

4.1  Method Statement .................................................................................................................................. 3 4.2  Equipment ............................................................................................................................................... 3 4.3  Methods and Procedures ......................................................................................................................... 3 

4.3.1  Coatings ......................................................................................................................................... 3 

4.3.1.1  Extent of work ............................................................................................................................... 3 4.3.1.2  Coating and supply and application methodology ........................................................................ 3 4.3.1.3  Anodes fabrication, supply and application methodology ............................................................ 4 4.3.1.4  Repair of damaged coatings .......................................................................................................... 4 4.3.1.5  Quality Assurance Requirements and Quality Control .................................................................. 4 

ANNEXURE 1: ISINYITHI CATHODIC PROTECTION SPECIFICATIONS: PORT OF DURBAN BERTHS 203 TO 205 RETURN 

WALL STEEL PILES 5690/130999 EXTERNAL COATING SPECIFICATION ....................................................................... 1 ANNEXURE 2: ISINYITHI CATHODIC PROTECTION SPECIFICATIONS: PORT OF DURBAN BERTHS 203 TO 205 RETURN 

WALL STEEL PILES 5690/130999 GALVANIC ANODES SPECIFICATION ........................................................................ 2 ANNEXURE 3: DESIGN REPORT ZAA 1370‐RPT‐063.................................................................................................... 3 

 

TRANSNET SOC LTD DCT BERTHS 203 TO 205 – RECONSTRUCTION, DEEPENING AND LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B  April 2017 

 Page | 1 

1.0 SCOPE 

1.1 Project 

This specification is a project specific technical specification for the DCT Berths 203 to 205 Reconstruction, Deepening 

and Lengthening Project in the Port of Durban. 

1.2 Scope 

The scope of this specification covers the Employer’s requirements for the provision of corrosion protection  in the 

form of Epoxy glass flake coatings and sacrificial aluminium anodes for the Berth 205 circular straight steel sheet pile 

return quay. 

The specification details the requirements of Materials, Equipment and Procedures to be adopted by the Contractor 

to supply, apply and install the corrosion protection for the return quay. 

 

2.0 NORMATIVE REFERENCES 

2.1 Reference Documents 

The following Employer and industry standardized specifications are referenced in this specification and form part of 

the Works  Information.   Standard specifications referenced within the specifications  listed below also form part of 

the Works Information. 

Reference documents to be used by the Contractor shall include: 

a) This Specification. 

b) Industry Codes, Standards and Specifications as listed in Section 2.2. 

c) Project Drawings: 

─ 1370‐CO‐070 series of drawings – Return Quay 

─ 1370‐CO‐020 series of drawings – Dredging and Reclamation (anodes  installed after completion of 

local basin dredging). 

d) Employer’s Project Specific Technical Specifications as listed in Section 2.2. 

e) Method Statements prepared by the Contractor, as described in Section 4.1. 

2.2 Standard Specifications 

The  standard  specifications  listed  in  this  section  shall,  inter  alia,  be  read  in  conjunction  with  the  following 

specifications  

a) Recommended  Practice  DNV‐RP‐F103  –  Cathodic  Protection  of  Submarine  Pipelines  by  Galvanic  Anodes, 

2010 

b) Recommended  Practice DNV‐RP‐F106  –  Factory Applied  External  Pipeline  Coatings  for  Corrosion  Control, 

2011 

c) SANS ISO 15589‐2: 2009, Edition 1 (ISO 15589‐2:2004, Edition 1) – Petroleum and Natural Gas Industries – 

Cathodic Protection of Pipeline Transportation Systems – Part 2: Offshore Pipelines 

d) SANS 53509:2009, Edition 1 (EN 13509:2003, Edition 1) – Cathodic Protection Measurement Techniques 

e) Isinyithi Cathodic Protection ‐ 5690/130999  Port of Durban Berths 203 to 205 Return Wall Steel Piles 

External Coating Specification 

f) Isinyithi Cathodic Protection – 5890/130999 Port of Durban Berths 203 to 205 Return Wall Steel Piles 

Galvanic Anode Specification 

2.3 Employer’s Project Specific Specifications and Standards 

The specifications listed in this section shall, inter alia, be read in conjunction with this specification. 

a) 1370‐CO‐000‐C‐SPC‐0009 – Steel Sheet Piling. 

b) Environmental Management Plan (EMP).   

TRANSNET SOC LTD DCT BERTHS 203 TO 205 – RECONSTRUCTION, DEEPENING AND LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B  April 2017 

 Page | 2 

3.0 DEFINITIONS 

All definitions of responsibilities shall be in accordance with the NEC Engineering and Construction Contract (ECC) for 

the construction of the Works. 

Where  the standard specifications  referenced  in  this  specification  refer  to  the “Client”,  replace  this  term with  the 

term “Employer”. 

Where the standard specifications referenced in this specification refer to the “Engineer”, replace this term with the 

term “Supervisor”. 

For  the purpose of  this  specification,  the  technical  definitions  and abbreviations  given  in SANS 15589-2:2009/ISO

15589-2:2004, (approved 2009) together with the following definitions shall apply: 

3.1 Chart Datum Port 

Chart Datum Port refers to the reference level used in the Port of Durban, which is 0,900 m below Mean Sea Level. 

All levels referred to in this document are relative to Chart Datum Port (CDP). 

3.2 Co‐ordinate System 

The  co‐ordinate  system  to be used  for  all  setting out  and  survey  shall  be World Geodetic  System 1984  (WGS84), 

LO31, referred to as WG31. 

3.3 Tidal Levels 

The Astronomical Tide Predictions as defined by the SA Navy Hydrographer and Chart SAN 2006 are as follows: 

Table 3.1 – Tide Data 

Tide  Abbreviation  Level m, Chart Datum Port 

Highest Astronomical Tide  HAT  2.287 

Mean High Water Springs  MHWS  1.997 

Mean Level  ML  1.097 

Mean Low Water Springs  MLWS  0.197 

Lowest Astronomical Tide  LAT  ‐0.013 

3.4 Method Statements 

Method statements shall be compiled by the Contractor for all activities.  The method statements shall be submitted 

to the Supervisor for acceptance three weeks in advance of the particular activity being undertaken.  Full details of all 

proposed Equipment (including temporary works) and methods shall be provided for acceptance by the Supervisor. 

No activity shall commence until the method statement has been accepted by the Supervisor. 

Further details of the requirements of particular method statements are provided in Section 4. 

   

TRANSNET SOC LTD DCT BERTHS 203 TO 205 – RECONSTRUCTION, DEEPENING AND LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B  April 2017 

 Page | 3 

4.0 REQUIREMENTS 

4.1 Method Statement 

The Contractor shall prepare method statements that shall include, inter alia: 

a) Supply and application of corrosion protection in the form of Zip‐E Epoxy glass flake coatings for the Berth 

205 circular straight steel sheet pile return quay. 

b) Fabrication,  Supply,  installation  and  commissioning  of  corrosion  protection  in  the  form  of  sacrificial 

aluminum anodes for the Berth 205 circular straight steel sheet pile return quay. 

c) Quality Plans. 

 

4.2 Equipment 

The Contractor shall take full and entire responsibility for the sufficiency of his Equipment to Provide the Works. The 

Contractor shall submit details of all Equipment to be used to the Supervisor for acceptance at least 3 weeks prior to 

dredging and reclamation work commencing. 

4.3 Methods and Procedures 

4.3.1 Coatings 

4.3.1.1 Extent of work  

a) The extent of work, corrosion protection and levels are as shown on the 1370‐CO‐070 series of drawings. 

The following corrosion protection measures shall be undertaken in accordance with the specifications:  

─ Isinyithi Cathodic Protection specifications: Port of Durban Berths 203 to 205 Return Wall Steel Piles 

5690/130999 External Coating Specification and 

─ Isinyithi Cathodic Protection specifications: Port of Durban Berths 203 to 205 Return Wall Steel Piles 

5890/130999 Galvanic Anodes Specification 

b) Where  the  Contractor  proposes  using  alternative  proprietary  coating  systems  to  those  specified  in 

Annexure 1, the coating system proposed shall be designed in accordance with the design report provided 

in Annexure 3. 

c) The piles will  be  fully  coated on  the  sea  face  to  reduce CP current  requirements and enable  the 50‐year 

design life without anode replacement. 

d) The  top  section of  all  piles  shall  be  coated on both  faces  to 1m below  the  level  of  the  capping beam  to 

provide  supplementary  protection  in  the  intertidal  zone  and  prevent  localised  corrosion  of  the  steel 

adjacent to the encasement of the capping beam. 

e) The anodes shall only be installed after dredging of the basin (1370‐CO‐020 series of drawings) using bolted 

mounting brackets with the welded connections above the water line. 

f) All electrical connections between anodes and the pile SHALL be welded. NO bolted connections to the pile 

may be employed. 

4.3.1.2 Coating and supply and application methodology 

Coatings  supply  and  application  methodology  shall  be  in  accordance  with  the  requirements  of  Isinyithi  Cathodic 

Protection  specification:  Port  of  Durban  Berths  203  to  205  Return Wall  Steel  Piles  5690/130999  External  Coating 

Specification. 

Where  this  specification  states  in  Section  3.10  Material  Supplier:  “No  alternative  products  or  Suppliers  will  be 

considered”,  replace  this  with  “use  of  alternative  products  or  Suppliers  will  be  subject  to  the  approval  of  the 

Supplier”. 

TRANSNET SOC LTD DCT BERTHS 203 TO 205 – RECONSTRUCTION, DEEPENING AND LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B  April 2017 

 Page | 4 

4.3.1.3 Anodes fabrication, supply and application methodology 

Anodes  fabrication,  supply  and  application methodology  shall  be  in  accordance with  the  requirements  of  Isinyithi 

Cathodic Protection specification: Port of Durban Berths 203 to 205 Return Wall Steel Piles 5890/130999 Galvanic 

Anodes Specification 

4.3.1.4 Repair of damaged coatings 

Repair of damaged coatings during transportation and  installation shall be  in accordance with the requirements of 

Isinyithi  Cathodic Protection  specification: Port of Durban Berths 203  to  205 Return Wall  Steel  Piles 5690/130999 

External Coating Specification. 

4.3.1.5 Quality Assurance Requirements and Quality Control 

Quality Assurance and Control shall be undertaken in accordance with the specifications:  

a) Isinyithi  Cathodic  Protection  specifications:  Port  of  Durban  Berths  203  to  205  Return  Wall  Steel  Piles 

5690/130999 External Coating Specification; and 

b) Isinyithi  Cathodic  Protection  specifications:  Port  of  Durban  Berths  203  to  205  Return  Wall  Steel  Piles 

5890/130999 Galvanic Anodes Specification. 

 

TRANSNET SOC LTD DCT BERTHS 203 TO 205 – RECONSTRUCTION, DEEPENING AND LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B  Annexures   April 2017 

 Page | A1 

ANNEXURE 1: ISINYITHI CATHODIC PROTECTION SPECIFICATIONS: PORT OF 

DURBAN BERTHS 203 TO 205 RETURN WALL STEEL PILES 5690/130999 EXTERNAL 

COATING SPECIFICATION 

   

C O N F I D E N T I A L R E P O R T

CLIENT : ZAA Engineering Projects & Naval Architecture

PROJECT : Port of Durban Berths 203 - 205 Return Wall Steel Piles

SCOPE : EXTERNAL COATING SPECIFICATION

DATE : October 2015

REF : 5690/130999 Draft for comment

Responsibility rests with the reader to verify that this is the latest revision

Report by: _____________________

N C Webb

Internal Review: _____________________

V Sealy-Fisher

Isinyithi Cathodic Protection (Pty) Ltd Page 2 of 20 5690130999 Confidential Report

Reports are submitted to clients on a confidential basis;

No reference to the work or test results in any manner will be discussed or made public without

written authorisation from the client;

All work is considered proprietary property of the client and is maintained by ICP as such.

Disclaimer: Responsibility rests with the reader to verify the latest revision of the report.

Isinyithi Cathodic Protection (Pty) Ltd Page 3 of 20 5690130999 Confidential Report

DOCUMENT CONTROL

Job Title Port of Cape Town Berth 203-205

Document title Wall Pile Coating Specification

Project Number 130999

Document Reference 5690

Revision Date Revision Description Issued for comment

0 28/10/2015 Prepared By Checked by

Name N C Webb V Sealy-Fisher

Signature

Revision Date Revision Description

Prepared By Checked by

Name

Signature

Revision Date Revision Description

Prepared By Checked by

Name

Signature

Isinyithi Cathodic Protection (Pty) Ltd Page 4 of 20 5690130999 Confidential Report

TABLE OF CONTENTS

1 INTRODUCTION ........................................................................................................................ 5

2 SURFACE PREPARATION & COATING APPLICATION .......................................................... 9

3 QUALITY ASSURANCE REQUIREMENTS ............................................................................. 13

4 REFERENCE DOCUMENTS AND STANDARDS .................................................................... 16

5 SURFACE PREPARATION & EXTERNAL COATING APPLICATION OF SITE REPAIRS ..... 17

6 EXTERNAL COATING SYSTEM SUMMARY .......................................................................... 20

7 SITE REPAIR COATING SYSTEM SUMMARY ....................................................................... 20

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 5 of 20 5690130999 Confidential Report

1 INTRODUCTION

1.1 Application of Specification

Unless otherwise agreed by the Engineer in writing, the materials and specifications used shall

follow strictly the clauses of this specification.

1.2 Supervision of Work

All work shall be carried out under the constant supervision of a qualified supervisor. At least one

supervisor shall be present at all times and at no period will unsupervised work be permitted.

1.3 Materials Delivered to Site or Shop

All coatings in the system shall be sourced from the specified supplier unless otherwise agreed

and be brought to site in new unopened containers. Containers shall be clearly marked with the

relevant material type, code and production batch numbers.

1.4 Approval of Manufacturer

Only approved materials may be utilised for the corrosion protection work. Therefore, the

successful Tenderer shall obtain the Engineer's prior approval of materials and manufacturer, prior

to the commencement of work.

1.5 Coating Defects

All coating application shall be free of runs and other paint film defects. All painted surfaces shall

be free from dust, dirt, blasting media, sand and salt contamination.

1.6 Cleaning

In the case of site coating, the surface shall be prepared as indicated in this specification.

No blast cleaning or coating application shall take place during inclement weather or when

conditions are such as to cause contamination of coatings. It is the Contractor's responsibility to

provide screens, covers, trestles or any other equipment necessary to minimise stoppage time

through the conditions mentioned.

No early morning or late evening coating shall take place when steel surfaces are wet owing to

overnight and early evening dew formation.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 6 of 20 5690130999 Confidential Report

1.7 Contamination During Coating Application

The Contractor shall take adequate precautions to protect areas being coated against

contamination and fall out during painting operations, should this become necessary.

All staff involved with coating to be issued with clean disposable over shoes and over cloth

disposable overalls. A clean work area shall be maintained around the piles.

1.8 Oil or Grease Surface Contamination

No coating shall be applied to any surface contaminated by oil, grease or salt deposits. Any

contaminated surfaces are to be cleaned down by means of one or more of:

a. Potable water and bristle brush,

b. A suitable water emulsifiable degreaser,

c. High pressure water washing,

d. Hot water washing

Followed by blast-cleaning

1.9 Time Limit to Coating Blast Cleaned Surfaces

After blast cleaning, operators handling the steel shall wear oil free and lint free gloves. Handling

equipment that contacts the surface shall be dry and free from oil and grease.

Blast cleaned steel shall be coated on the same day as the blast cleaning, within the time specified

in Table 1.

TABLE 1 MAXIMUM TIME INTERVAL BETWEEN BLAST CLEANING AND COATING

Ambient Relative Humidity Maximum Time (Hours)

Up to 70% 70 - 80% Over 80%

6 2

Coating not permitted - Reblast and coat when R.H. below 80%

1.10 Freedom from Weld Spatter and Ragging

All drilled holes are to be free from drilling rag and all punched holes are to be ground free of

punching ridges. All welds shall be deslagged and all weld spatter removed prior to blast cleaning.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 7 of 20 5690130999 Confidential Report

1.11 Repairs to the Coating System Damaged During Transport, or Other Site Activities.

If in the opinion of the Engineer, the coating system is excessively damaged during transport or

other site activities, it shall be repaired by the following procedure:

1.11.1 Test the coating surface for cure using MEK in accordance with ASTM 5402.

1.11.2 If the test indicates that the surface is not fully cured (sticky), the damaged region should be

repaired as follows:

a. Abrade the damaged area with medium grade abrasive paper (220 or 150 grit) to

clean exposed steel to a white metal finish. Abrade the coating surface for not less

than 25mm on each side of the damaged area and feather smoothly into the sound

coating

b. Remove all dust and debris.

c. Wipe the area with solvent and recoat.

1.11.3 If the test indicates that the surface is fully cured (not sticky), the damaged region should be

repaired as follows:

a. Sweep blast the damaged area to clean exposed steel to a white metal finish.

Abrade the coating surface for not less than 25mm on each side of the damaged

area and feather smoothly into the sound coating

b. Remove all dust and debris.

c. Recoat

1.12 Application Method

Application shall be by brush, or spray as recommended by the manufacturer.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 8 of 20 5690130999 Confidential Report

1.13 Ambient Conditions

No steel shall be coated when the surface temperature exceeds 40C.

No coating or final blast cleaning shall take place when the ambient temperature is below 5C or

relative humidity above 80%.

No coating or final blast cleaning shall take place if the steel temperature is less than 5°C above

dew point.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 9 of 20 5690130999 Confidential Report

2 SURFACE PREPARATION & COATING APPLICATION

2.1 Abrasive Blasting

Abrasive blasting shall be carried out using equipment suitably designed for this purpose.

2.1.1 All blast cleaning shall be conducted as per the Coating Manufacturer’s Specifications,

Data Sheet SP1 “Surface Preparation” (Procedure 6/30) or PC1 “Pipe Coating” (Procedure

6/15).

2.1.2 Prior to blast cleaning commencing :

a. All welds shall be free of slag, slag inclusions and undercutting.

b. Adjacent areas shall be free of weld spatter and such splatter shall be removed by

grinding and/or chipping.

c. All oil and grease deposits shall be removed. In this regard, special attention shall

be paid to drillings, bolt holes, etc.

2.1.3 Blasting Conditions

Where possible the blasting shall be carried out in a controlled environment. Where

blasting is carried out in open conditions no blast cleaning shall take place during inclement

weather conditions.

2.1.4 Air Dryness

All air used for blasting shall be free from all oil and water. Suitable moisture traps shall be

incorporated on air lines to ensure that air is dry.

2.1.5 Blasting Media

Blast cleaning may be carried out using steel grit and a wheel abrator, or as approved by

the Engineer. Fresh grit shall be added daily to ensure that the required profile is achieved.

Irrespective of the material used for blasting, in all cases it shall be free of all foreign matter

such as clay, humus, chlorides, bitumen etc. The particle size distribution of the abrasive

shall be suitable to produce the specified profile.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 10 of 20 5690130999 Confidential Report

2.1.6 Standard of Blast Cleaning

All items of structural steelwork shall be blast cleaned in accordance with the Swedish

Code of Practice ISO 8501-1 to Grade A Sa3.

An average profile of 80μm with a minimum profile of 60μm is required.

2.1.7 After the initial pre grit blast, test for retained metallic salts, to levels below 70mg/m², or

especially in the base of pits marks, using the ISO salt mix equivalent conductivity test

method.

(Wattman Potassium Ferricyanide papers may be used for preliminary screening)

Should metallic salts be identified, a decontamination cycle shall be undertaken:

A decontamination cycle will consist of

blast,

wash

re-blast

re-test.

The decontamination cycle may have to be repeated.

a. If decontamination is required, this shall be conducted using Chlor*Rid

decontamination solution (100:1 for spray) to remove metallic salts. If metallic salts

are above 70 mg/m2, repeat the decontamination procedure. Experience has shown

that each Chlor*Rid wash will approximately halve the salt concentration.

b. If required, a second grit blast shall be performed in accordance with ISO 8501-1 SA

3, white metal, maintaining a minimum roughness profile of 60 microns.

2.1.8 The entire surface of the pile to be coated is to be blasted. The blast cleaning programme

will depend on rate of coating application, environmental conditions and use of de-

humidification equipment.

2.1.9 The spent grit must be removed quickly, and preparations should be made to apply the

coating as soon after blasting as possible.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 11 of 20 5690130999 Confidential Report

2.1.10 100% of the surface area of the pile to be coated shall be vacuumed, to remove micro dust.

Blowing down the surface of the pile with compressed air is not an acceptable method of

dust removal.

2.1.11 The surface shall be checked in accordance with SABS 769, maximum 0.3%, to verify the

level of cleanliness.

2.2 External Coating Application

2.2.1 The external coating shall be applied in accordance with the manufacturer’s specifications.

2.2.2 Verify that the relative humidity is below 80% and that the steel is at least 5ºC warmer than

the dew point temperature of the air before and during application. If required

dehumidification shall be used to maintain RH.

2.2.3 Spray operation shall be set up as per the manufacturer’s application data sheet.

2.2.4 All staff involved with coating to be issued with clean disposable over shoes and over cloth

disposable overalls, clean work area to be maintained around the pile.

2.2.5 The first coat of the coating material shall be spray applied to a DFT of 750 microns

nominal as per manufacturer’s data sheet.

2.2.6 Spray apply the second coat once the first coat has gelled sufficiently to carry the weight of

the second coat.

2.2.7 A total DFT of typical 1.5mm minimum average thickness shall be achieved for the ZipE

coating. For QC purposes the minimum thickness of any one test location (spot

measurement) in terms of SSPC PA2 is therefore 1.2mm.

2.2.8 Allow coating 24 hours to ambient cure

2.2.9 After full cure (time to be confirmed), the ZipE coating shall be tested using a 10kV high

voltage spark test, using a calibrated pulsed DC instrument, or calibrated AC instrument.

2.2.10 All holidays, pinholes and potential defects shall be marked up and repaired as per

standard procedure using flat bottomed drill and coating plug method. Applying further

material over the top of a pinhole is not permitted.

2.2.11 All repairs shall be re-spark tested at 10kV volts to ensure integrity of lining as per

manufacturer’s data sheet.

2.2.12 DFT tests shall be made using electronic non-destructive test instruments.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 12 of 20 5690130999 Confidential Report

2.3 Masking of Areas to be Left Uncoated

2.3.1 Any areas which require not to be coated shall be suitably masked prior to coating

operations.

2.3.2 Ends of piles which may be welded on site shall be free of coating for a distance of 200mm

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 13 of 20 5690130999 Confidential Report

3 QUALITY ASSURANCE REQUIREMENTS

3.1 Contractor Qualification

The Engineer may, at his discretion, require a Quality Audit of the coating sub-contractor to ensure

that he has the management facilities, skilled staff, and quality control facilities to carry out quality

control during application of coatings to ensure compliance with the specification.

The contractor shall accept full responsibility for the quality of his work and of materials used,

irrespective of any quality surveillance that may be carried out by the Engineer or his

representative.

3.2 Quality Control

The Contractor shall have the necessary equipment and staff knowledgeable in test procedures to

carry out all the quality control required to ensure compliance with the specification. The contractor

will be required to produce a quality plan and a program for carrying out the work. The Contractor

shall maintain quality control records of all stages of the work, batch numbers of materials used,

environmental conditions, as required by the specification. Quality control shall be inclusive in the

Contractor’s tender price.

No coating procedures may commence until Quality Plan has been submitted and approved

by the Client, the Coating Supplier and the Engineer.

3.3 Quality Surveillance

Independent surveillance - The Engineer may employ an independent technically qualified

organisation to carry out quality surveillance of the work on his behalf

Program - The Contractor shall advise the Engineer timeously, in writing, when and where the

following processes will be carried out :

a. Completion of fettling or dressing prior to release for coating operations.

b. Blast cleaning and application of the coatings.

c. Repairs.

Failure of the Contractor to advise the Engineer of his program may result in rejection of the work.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 14 of 20 5690130999 Confidential Report

3.4 Access For Surveillance

For the purpose of carrying out quality surveillance, the Engineer or his representative shall be

granted access to any part of the Contractor's premises relevant to the work being carried out, at

any reasonable time. The Contractor shall provide, at his own cost, any equipment or labour

necessary to gain access to surfaces which are coated, to be coated or are in the process of being

coated

3.5 Samples

The Engineer or his representative may remove or call for any reasonable samples of materials to

be used in the coating application for quality checks. Rejection of the sample will place a hold on

the use of materials of the same batch number and may lead to rejection of all that batch of

material and the reworking of any components that have already been coated with rejected

material.

Sample plates, 300mm x 300mm, shall be blast cleaned and coated alongside the pile lengths

being coated. Sample plates shall be identified and coating operation witnessed by the

independent inspector. Two (2) sample plates shall be prepared for each shift of coating work or if

a different batch number is used in a single shift.

3.6 Destructive Testing

The Engineer or his representative will carry out reasonable tests on the samples provided to

ascertain compliance with the specification.

3.7 Cost Of Quality Surveillance

Cost of Quality Surveillance shall be borne by the Employer, except when surveillance results in

rejection of the lot or when notice by the Contractor results in a fruitless trip, in which case the cost

of Surveillance shall be debited against the Contractor's account

3.8 Quality Control Records

Proper and adequate quality control records shall be maintained by the Contractor for all stages of

the work. These records shall be available for inspection by the Engineer or his representative at

the time of Quality Surveillance. Incomplete, inaccurate or inadequate records shall be regarded

as non-compliance with the specification, and the cost of surveillance will be back charged to the

Contractor.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 15 of 20 5690130999 Confidential Report

3.9 Data Sheets, Specifications And Codes Of Practice

The Contractor shall have available the latest issues of manufacturer's data sheets for materials to

be used, National Specifications and Codes of Practice relevant to the work to be carried out, as

well as a copy of this specification, all of which shall be available to the Contractor's Quality Control

Manager.

3.10 Material Supplier

No alternative products or suppliers will be considered.

3.11 Dry Film Thickness Measurements

SSPC-PA2

The Engineer will check, at his discretion, the dry film thickness of the total coating system as

specified. The inspection procedure and acceptance criterion shall be in accordance with SSPC

PA2.

Thickness testing shall be carried out using a suitable electro-magnetic non-destructive thickness

testing instrument calibrated in accordance with SSPC-PA2

The coating system is applied wet-on-wet to ensure intercoat adhesion. In the event of inadequate

coating thickness, the Engineer may instruct the Contractor to remove the coating system and re-

apply to the correct thickness at no cost to the client.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 16 of 20 5690130999 Confidential Report

4 REFERENCE DOCUMENTS AND STANDARDS

4.1 Determination of Cleanliness After Abrasive Blast Cleaning Pictorial Standards:

ISO 8501:1:1988 Acceptance criteria: Sa3

4.2 Determination of Surface Profile

SABS Test Method 772. Acceptance criteria: 60µm minimum or as directed by the supplier.

4.3 Solvent Resistance of Organic Coatings

ASTM D 5402 - 06.

4.4 Freedom from Dust and Debris

ISO 8502-3 Preparation of steel substrates before application of paint and related products –

Tests for the assessment of surface cleanliness -Part 3: Assessment of dust on steel surfaces

prepared for painting (pressure sensitive tape method).

4.5 Soluble Metal Salts Test

ISO equivalent salt mix: Acceptance criteria <70mg/sqm

4.6 Dry Film Thickness Measurement (See 4.11)

SSPC-PA2 - Measurement of Dry Paint Thickness with Magnetic Gauges

4.7 Corrocoat Procedures / Data Sheets

SP1 Surface Preparation

SP4 Surface Preparation - Metallic Salts Decontamination & Measurement

PC1 Pipe Coating

Spark Testing

ZipE – Health & Safety

ZipE

Repair of ZipE

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 17 of 20 5690130999 Confidential Report

5 SURFACE PREPARATION & EXTERNAL COATING APPLICATION OF SITE REPAIRS

5.1 Prewashing

5.1.1 All piles shall be prewashed prior to coating.

5.1.2 All pre-washed piles shall be tested for soluble salts as per Corrocoat data sheet SP4.

Check point no 2 – absorption method, should be between 25-70 mg/sqm, where 70 is the

maximum allowable limit, Decontaminate using CHLORID SOLUTION, where necessary:-

5.2 Visual Inspection of Piles

5.2.1 After washing, piles may NOT stand overnight before blasting and coating.

5.2.2 Prior to blast cleaning commencing all circumferential welds shall be inspected:

a. All welds shall be free of slag, slag inclusions and undercutting.

b. Adjacent areas shall be free of weld spatter and such splatter shall be removed by

grinding and/or chipping

(Corrocoat data sheet 6/40 Weld Finish).

5.3 Masking

Mask off area to be prepared using suitable tape to ensure neat working area. This shall be a minimum of 200mm from the edge of the coated area on either side of the weld.

5.3.1 The blasting area shall overlap onto the existing coating to provide a mechanical key.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 18 of 20 5690130999 Confidential Report

5.4 Abrasive Blasting

Abrasive blasting shall be carried out using equipment suitably designed for this purpose.

5.4.1 Standard of Blast Cleaning

All items of structural steelwork shall be blast cleaned in accordance with the Swedish

Code of Practice ISO 8501-1 to Grade A Sa3.

An average mechanical peak to valley profile of 80μm shall be achieved, with a minimum

profile of 60 μm.

Feather blast onto the exposed pile coating to ensure a surface roughness sufficient for

subsequent coating adhesion.

5.4.2 Blasting Conditions

No blast cleaning shall take place during inclement weather conditions.

5.4.3 Air Dryness

All air used for blasting shall be free from all oil and water. Suitable moisture traps shall be

incorporated on air lines to ensure that air is dry.

5.4.4 Blasting Media

Blast cleaning shall be carried out using Blastrite Microblast or equivalent, or as approved

by the Engineer. In all cases the blast material shall be free of all foreign matter such as

clay, humus, chlorides, bitumen etc. The particle size distribution of the abrasive shall be

suitable to produce the specified profile.

5.4.5 Surface Cleanliness

Remove all residual grit and debris from the surface by means of a vacuum.

5.4.6 Check for soluble salts as per Corrocoat data sheet SP4. Check point no 2 – absorption

method, should be between 25-70 mg/sqm, where 70 is the maximum allowable limit,.

Decontaminate using CHLORID SOLUTION, where necessary.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 19 of 20 5690130999 Confidential Report

5.4.7 Record Keeping:

All relevant environmental conditions are to be tabulated including ambient temperature,

relative humidity, dew point, surface temperature as well as the batch numbers of the base

and catalyst components of the ZIP E.

5.5 EXTERNAL COATING APPLICATION

5.5.1 This REPAIR coating specification is issued on the basis that the coating will cure for a

minimum of 72 hours. For installation prior to this period, pre- and post-heating may be

required – refer to manufacturer for specific procedures.

5.5.2 The coating shall be tested for full cure using the indent and solvent rub (MEK) tests. Both

tests must pass before concrete overcoating may follow.

5.5.3 Verify that the relative humidity is below 80% and that the steel is at least 5ºC warmer than

the dew point temperature of the air before and during application.

5.5.4 Apply the ZIP E – Epoxy Glass Flake using an airless pump with ratio of 45:1.Refer to ZIP

E Technical data sheet for specifics on application.

5.5.5 Apply until the coating thickness is the same as that of the adjacent pile coating. Note: The

area to be coated is approximately 4 m², the volume of ZIP E necessary for each joint is

estimated at 8 litres, given that the wastage on the exterior field joint is higher than normal.

5.5.6 The surface temperature during the cure cycle may not fall below 10°C. To achieve this,

heating blankets may be required.

Port of Cape Town Berth 203-205 Return Wall Pile Coating Specification

Isinyithi Cathodic Protection (Pty) Ltd Page 20 of 20 5690130999 Confidential Report

6 EXTERNAL COATING SYSTEM SUMMARY

Surface Preparation Blast clean Sa 3, 60μm min, non-metallic grit <70mg/m2 salts

Coating System Zip E Supplied by

Corrocoat SA (Pty) Ltd Contact:: Louis Pretorius Tel: 011 845-4247 Email: [email protected]

Thickness: 1.5mm minimum – SSPC PA2 methodology

Quality Control Witness & Hold

Surface preparation Coating thickness 100% spark test, samples subjected to destructive testing Independent Quality Surveillance Inspection

7 SITE REPAIR COATING SYSTEM SUMMARY

External Field Joints Surface Preparation Blast clean Sa 3,

60μm min, non-metallic grit <70mg/m2 residual salts

Coating System Zip E Epoxy Glass Flake Supplied by

Corrocoat SA (Pty) Ltd Contact:: Louis Pretorius Tel: 011 845-4247 Email: [email protected]

Thickness: as per mainline, minimum average 1.5mm SSPC PA2

Quality Control Witness & Hold

Surface preparation Coating thickness 100% spark test, Independent Quality Surveillance Inspection

TRANSNET SOC LTD DCT BERTHS 203 TO 205 – RECONSTRUCTION, DEEPENING AND LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B  Annexures   April 2017 

 Page | A2 

ANNEXURE 2: ISINYITHI CATHODIC PROTECTION SPECIFICATIONS: PORT OF 

DURBAN BERTHS 203 TO 205 RETURN WALL STEEL PILES 5690/130999 GALVANIC 

ANODES SPECIFICATION 

   

C O N F I D E N T I A L R E P O R T

CLIENT : ZAA Engineering Projects & Naval Architecture

PROJECT : Port of Durban Berths 203 - 205 Return Wall

SCOPE : SACRIFICIAL ANODE SPECIFICATION

DATE : JUNE 2016

REF : 5890/130999 For construction

Responsibility rests with the reader to verify that this is the latest revision

Report by: _____________________ F L Bradfield

Internal Review: _____________________

N C Webb

Isinyithi Cathodic Protection (Pty) Ltd Page 2 of 8 5890130999.docx Confidential Report

Reports are submitted to clients on a confidential basis;

No reference to the work or test results in any manner will be discussed or made public without

written authorisation from the client;

All work is considered proprietary property of the client and is maintained by ICP as such.

Disclaimer: Responsibility rests with the reader to verify the latest revision of the report.

Isinyithi Cathodic Protection (Pty) Ltd Page 3 of 8 5890130999.docx Confidential Report

DOCUMENT CONTROL

Job Title Port of Durban Berth 203 - 205 Return Wall – Cathodic Protection

Document title Sacrificial Anode Specification

Project Number 130999

Document Reference 5890

Revision Date Revision Description Issued for comment

0 20/06/2016 Prepared By Checked by

Name N C Webb V Sealy-Fisher

Signature

Revision Date Revision Description

Prepared By Checked by

Name

Signature

Revision Date Revision Description

Prepared By Checked by

Name

Signature

Isinyithi Cathodic Protection (Pty) Ltd Page 4 of 8 5890130999.docx Confidential Report

TABLE OF CONTENTS

1. INTRODUCTION ........................................................................................................................................ 5 2. SUMMARY OF PARAMETERS ................................................................................................................. 6 3. SELECTION OF APPLICABLE STANDARDS ........................................................................................... 7 4. DESIGN SUMMARY OF CORROSION PROTECTION SYSTEM ............................................................ 8

Port of Durban Berth 203 - 205 Return Wall– Cathodic Protection

Isinyithi Cathodic Protection (Pty) Ltd Page 5 of 8 5890130999.docx Confidential Report

1. INTRODUCTION

The Return Wall for the Port of Durban Berth 203 - 205 deepening comprises cellular coffer dam

type caissons formed from steel sheet piles. The majority of the piles will be driven through existing

soils, after which the sea face will be dredged.

The caissons are 23m outer diameter, using 508mm straight sheet piles. The total pile length is

31m. The top 3,2m of the sheet pile will be encased in a concrete capping beam which extends to

500mm below LAT.

The corrosion protection system will comprise a combination of sacrificial steel corrosion

allowance, glass flake reinforced epoxy coating and sacrificial anode cathodic protection.

This specification covers the supply of Aluminium - Zinc - Indium anodes for cathodic protection.

Port of Durban Berth 203 - 205 Return Wall– Cathodic Protection

Isinyithi Cathodic Protection (Pty) Ltd Page 6 of 8 5890130999.docx Confidential Report

2. SUMMARY OF PARAMETERS

a. The design life of the corrosion protection system is 50 years.

b. Sacrificial anode material selection favours Aluminium anodes rather than Zinc anodes due

to both cost and weight considerations.

c. All electrical connections between anodes and the pile will be welded. Bolted connections

are only for mounting purposes.

d. As the anodes can only be installed after dredging, angle mounting brackets are proposed

with a welded electrical connection above the water line.

e. Anodes will be installed prior to casting of the pile cap.

f. The piles will be fully coated on the sea face to reduce CP current requirements and enable

the 50-year design life without anode replacement.

g. The top section of all piles will be coated on both faces to 1m below the level of the capping

beam to provide supplementary protection in the intertidal zone and prevent localised

corrosion of the steel adjacent to the encasement of the capping beam.

Port of Durban Berth 203 - 205 Return Wall– Cathodic Protection

Isinyithi Cathodic Protection (Pty) Ltd Page 7 of 8 5890130999.docx Confidential Report

3. SELECTION OF APPLICABLE STANDARDS

The cathodic protection design is based on the requirements of SANS ISO 15589-2 and EN ISO

13174 for harbour installations and takes into consideration the requirements for protection against

ALWC (Accelerated Low Water Corrosion)

For this application, bareness and breakdown factors are used for coated steel which has been

subject to piling. This is an unusual requirement as the piles are being installed prior to dig-out.

Although underwater coating repairs are possible, the extent and efficacy of these repairs cannot

be predicted.

Port of Durban Berth 203 - 205 Return Wall– Cathodic Protection

Isinyithi Cathodic Protection (Pty) Ltd Page 8 of 8 5890130999.docx Confidential Report

4. DESIGN SUMMARY OF CORROSION PROTECTION SYSTEM

Refer to drawing 1370-CO-070-C-DWG-0003-01

a. Each anode is 2000mm long x 190/140mm wide (trapezoidal) x 120mm thick cast onto an

offset steel "I" strap 50 x 6mm

b. The anode straps are designed to bolt onto brackets welded to each sheet pile.

c. A 50 x 6 x 4450mm continuity strap is welded to the top of the insert after casting the anode

in order to provide electrical continuity to the pile.

d. There is one anode per pile for each pile exposed to the sea.

e. The anode is installed such that the top of the anode is 1m below the bottom of the capping

beam.

f. The rear face of the anode as well as the protruding steel sections shall be coated with the

same epoxy/glass flake coating as the external surface of the pile.

g. The total net anode mass requirement is 95kg per pile with a utilisation factor of 80%.

h. Anodes will be manufactured in accordance with SANS ISO 15589-2: 2009 (sled anodes)

i. Electrochemical capacity: 2300 A.hrs/kg

ii. Driving potential: 1050mVAg/AgCl

i. Quality control requirements will be:

i. Chemical analysis: each heat

ii. Dimensional tolerance: each anode

iii. Electrochemical testing: prequalification plus 1 per 15 tonnes

iv. Destructive testing: prequalification plus 1 per 15 tonnes.

TRANSNET SOC LTD DCT BERTHS 203 TO 205 – RECONSTRUCTION, DEEPENING AND LENGTHENING 

PORT OF DURBAN 

SPECIFICATION – CORROSION PROTECTION 

1370‐CO‐000‐C‐SPC‐0017 Rev T‐0B  Annexures   April 2017 

 Page | A3 

ANNEXURE 3: DESIGN REPORT ZAA 1370‐RPT‐063 

 

 

 

 

 

 

 

 

 

 

 

TRANSNET SOC LTD 

DEEPENING OF BERTHS 203 TO 205 

PORT OF DURBAN 

CORROSION PROTECTION DESIGN REPORT 

 

ZAA 1370 | RPT | 063 REV A 

30 October 2015 

 

TRANSNET SOC LTD DEEPENING OF BERTHS 203 TO 205, PORT OF DURBAN 

 CORROSION PROTECTION DESIGN REPORT 

ZAA 1370 | RPT | 063 Rev A  October 2015

REVISIONS 

REV  DATE  DESCRIPTION DESIGNED 

BY 

CHECKED 

BY 

APPROVED 

BY 

A  30 October 2015  Issue to Client  NW  NW  JZ 

           

           

           

           

           

           

           

           

           

           

           

AUTHORISATION 

AUTHORISED BY  NAME  SIGNATURE  DATE 

DIRECTOR  J ZIETSMAN Pr Eng 

 

30 October 2015 

 

 

This document, including all design and information therein, is Confidential Intellectual Property of ZAA Engineering.  

Copyright and all other rights are reserved by ZAA Engineering.   

This document may only be used for its intended purpose. 

 

C O N F I D E N T I A L R E P O R T

CLIENT : ZAA Engineering Projects & Naval Architecture

PROJECT : Port of Durban Berths 203 - 205 Return Wall

SCOPE : CATHODIC PROTECTION DESIGN REPORT

DATE : October 2015

REF : 5687/130999[1] For approval

Responsibility rests with the reader to verify that this is the latest revision

Report by: _____________________

F L Bradfield

Internal Review: _____________________

N C Webb

Isinyithi Cathodic Protection (Pty) Ltd Page 2 of 9 5687130999 [1] Confidential Report

Reports are submitted to clients on a confidential basis;

No reference to the work or test results in any manner will be discussed or made public without

written authorisation from the client;

All work is considered proprietary property of the client and is maintained by ICP as such.

Disclaimer: Responsibility rests with the reader to verify the latest revision of the report.

Isinyithi Cathodic Protection (Pty) Ltd Page 3 of 9 5687130999 [1] Confidential Report

DOCUMENT CONTROL

Job Title Port of Cape Town Berth 602 – Cathodic Protection

Document title Cathodic Protection Design

Project Number 130999

Document Reference 5687

Revision Date Revision Description Issued for comment

0 26/10/2015 Prepared By Checked by

Name N C Webb V Sealy-Fisher

Signature

Revision Date Revision Description Disambiguation of Required Anode Quantities

1 28/10/2015 Prepared By Checked by

Name F L Bradfield N C Webb

Signature

Revision Date Revision Description

Prepared By Checked by

Name

Signature

Isinyithi Cathodic Protection (Pty) Ltd Page 4 of 9 5687130999 [1] Confidential Report

TABLE OF CONTENTS

1. INTRODUCTION ...................................................................................................................... 5

2. SUMMARY OF PARAMETERS ................................................................................................ 6

3. SELECTION OF APPLICABLE STANDARDS .......................................................................... 7

4. DESIGN SUMMARY OF CORROSION PROTECTION SYSTEM ............................................. 8

APPENDIX 1: Table of Calculations ................................................................................................ 9

Port of Cape Town Berth 602 – Cathodic Protection

Isinyithi Cathodic Protection (Pty) Ltd Page 5 of 9 5687130999 [1] Confidential Report

1. INTRODUCTION

Isinyithi Cathodic Protection (Pty) Ltd (ICP) was requested by ZAA Engineering Projects & Naval

Architecture (Pty) Ltd to undertake the corrosion protection design for the Return Wall steel caissons

for the Port of Durban Berth 203 - 205 deepening.

The relevant aspect of the project comprises cellular coffer dam type caissons formed from steel

sheet piles. The majority of the piles will be driven through existing soils, after which the sea face

will be dredged.

The caissons are 23m outer diameter, using 508mm straight sheet piles. The total pile length is 31m.

The top 3,2m of the sheet pile will be encased in a concrete capping beam which extends to 500mm

below LAT.

Advanced Low Water Corrosion (ALWC) has been identified as a significant risk in harbour

installations. The design therefore provides for protection against this form of corrosion by means of

coatings and suitable cathodic protection polarisation levels. The presence of SRB can be assumed

as the piles will be in the mud/silt, the South African coastal silts are known to have active SRB and

the harbour environment will be relatively contaminated with organic matter and low in oxygen.

ALWC was in fact first identified in Cape Town in 1934.

The corrosion protection system will comprise a combination of sacrificial steel corrosion allowance,

glass flake reinforced epoxy coating and sacrificial anode cathodic protection.

The specification for the glass flake reinforced epoxy coating is reported under separate cover.

This report covers the corrosion protection design for the project.

Port of Cape Town Berth 602 – Cathodic Protection

Isinyithi Cathodic Protection (Pty) Ltd Page 6 of 9 5687130999 [1] Confidential Report

2. SUMMARY OF PARAMETERS

a. The design life of the corrosion protection system is 50 years.

b. Impressed Current Cathodic Protection has not been selected as the method of cathodic

protection for the piles, for the following reasons:

c. ICCP requires significantly higher maintenance than sacrificial anodes.

d. ICCP is more likely to cause interference with other structures and vessels.

e. Sacrificial anode material selection favours Aluminium anodes rather than Zinc anodes due

to both cost and weight considerations.

f. An SRB (Sulphate Reducing Bacteria) environment has been assumed to calculate the

optimal anode sizes.

g. Anode mass determines the life of the anode and the anode surface area determines the

current output by the anode used in the cathodic protection process.

h. The anode dimensions have been selected based on standard anode sizes available.

i. All connections between anodes and the pile MUST be welded. Absolutely NO bolted

connections to the pile may be employed.

j. As the anodes can only be installed after dredging, slotted brackets are proposed with a

welded connection above the water line.

k. The piles will be fully coated on the sea face to reduce CP current requirements and enable

the 50-year design life without anode replacement.

l. The coating breakdown factors are based on the recommendations of EN 1374.

m. The top section of all piles will be coated on both faces to 1m below the level of the capping

beam to provide supplementary protection in the intertidal zone and prevent localised

corrosion of the steel adjacent to the encasement of the capping beam.

Port of Cape Town Berth 602 – Cathodic Protection

Isinyithi Cathodic Protection (Pty) Ltd Page 7 of 9 5687130999 [1] Confidential Report

3. SELECTION OF APPLICABLE STANDARDS

In general, there have been two (2) commonly accepted international standards on which cathodic

protection calculations for marine application can be based. There are other company specific

standards as well (e.g. Shell, BP, Saudi Aramco )

The DNV standards were amongst the first to be developed and have been in use in excess of 30

years. Recent reviews and industry experience agree that the DNV standards were overly

conservative, particularly in the area of coating breakdown rates. The result has been operating

systems extending significantly beyond their design life.

An ISO revision was undertaken in early 2000’s which has less conservative design parameters..

South Africa has adopted the ISO standard for cathodic protection of offshore pipelines. Recently

the EN document for harbour installations has been published which takes into account the more

onerous and variable conditions of a harbour environment and specifically addresses sheet piling

and ALWC.

The CP system design is determined from the standards, relative to the salinity, temperature and

depth characteristics of the environment to which the steel will be exposed.

DNV ISO EN

Initial current density 170 200

Final current density 110 140 100

Mean current density 80 80 130

Sediment current density 20 20 50/30

f1 0.02 0.005 .25

f2 .0120 0.0002 .001

Aluminium capacity 2000 2500 2500

Anode output -1050 -1050 -1050

For this application, bareness and breakdown factors are used for coated steel which has been

subject to piling. This is an unusual requirement as the piles are being installed prior to dig-out.

Although underwater coating repairs are possible, the extent and efficacy of these repairs cannot be

predicted.

Port of Cape Town Berth 602 – Cathodic Protection

Isinyithi Cathodic Protection (Pty) Ltd Page 8 of 9 5687130999 [1] Confidential Report

4. DESIGN SUMMARY OF CORROSION PROTECTION SYSTEM

Design calculations are given in the appendix

4.1 Each anode is 2000mm long x 190/140mm wide (trapezoidal) x 120mm thick cast onto an offset steel Tee strap 50 x 6mm

4.2 The anodes straps are designed to slot into pockets welded to the pile prior to driving to facilitate underwater installation.

4.3 There is one anode per pile for each pile exposed to the sea.

4.4 The anode is installed such that the top of the anode is 1m below the bottom of the capping beam.

4.5 As each pile is fitted with an anode, no continuity welding is required between piles.

4.6 A continuity strap is fitted to the anode bracket which is brought above the water line and welded to the pile.

4.7 The full extent of the external surface of all piles exposed to seawater is coated with 1.6mm of glass flake reinforced epoxy.

4.8 The top 4.2m of all piles is coated on both sides to prevent corrosion due to tidal movement of the water table and the concrete/soil interface.

4.9 The 3 sections of the piles, being the submerged coated steel, the buried coated steel below the scour protection level and the steel encased in the capping beam are treated as a common cathode system, protected by the single anode located below the capping beam.

4.10 The current allocation per pile for each of these sections is as follows:

a. Coated submerged steel: 0.342A

b. Coated buried steel: 0.059A

c. Reinforced concrete: 0.002A

d. Total (per pile) 0.434A

4.11 The total net anode mass requirement is 95kg per pile with a utilisation factor of 80%. Thus, in total for the entire installation there will be 489 off 95kg zinc anodes.

4.12 The steel brackets of the bracelets will be coated to the same specification as the piles after fabrication.

4.13 Anodes will be manufactured in accordance with SANS ISO 15589-2: 2009

Port of Cape Town Berth 602 – Cathodic Protection

Isinyithi Cathodic Protection (Pty) Ltd Page 9 of 9 5687130999 [1] Confidential Report

APPENDIX 1: Table of Calculations

GRE submerged GRE buried GRE Encased

factor k1 0,25 0,25 0,25

factor k2 ,00100 ,00100 ,00000

design life 50 50 50

Anode thickness 100 100 100

Anode frequency 1 1 1

length 16,5 11,3 3,2

width 0,58 0,58 1,16

wall

coating 1,6mm 1,6mm 1,6mm

weight thick 0 0 0

temp

design life 50 50 50

sea temp 18

anode open/buried open open open

sea resistivity 0,23 0,23 0,23

max anode sp 16,5 11,3 3,2

area per midp 10 7 4

factor k1 0,25 0,25 0,25

factor k2 ,00100 ,00100 ,00000

av fact 0,275 0,275 0,25

final fact 0,3 0,3 0,25

mean current density 100 30 2

final current density 130 30 2

avge current 0,342 0,054 0,002

final current 0,373 0,059 0,002

An thick 0,12 0,12 0,12

length 1,691 0,267 0,009

width 0,165 0,165 0,165

Pot -900 -900 -900

Anode -1050 -1050 -1050

Driving 150 150 150

Capacity 2300 2300 2300

Util 0,8 0,8 0,8

Anode mass requd 81 13 0

Density 2700 2700 2700

Vol 0,030 0,005 0,000

Cross section 0,020 0,020 0,020

Calculated length 1,523 0,241 0,008

Applied length 1,967 0,44

Anode dimension 1,066 0,370

Resist 0,108 0,119

final current 1,391 1,259