Transmission System strengthening for potential solar ... for... · substation at Narela with 765...

45
Transmission System strengthening for potential solar energy zones (11.1GW) Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN). Page 1 of 11 Transmission System strengthening for potential solar energy zones (11.1GW) Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN). Transmission System for Solar Energy Zones (SEZs) in Rajasthan under Phase-II involving Hybrid system with EHVAC and VSC based HVDC was discussed and technically agreed in the 4 th NRSCT meeting held on 25/07/19. Accordingly, the details of the scheme, justification, estimated cost and its tariff impact, results of the system studies, study assumptions, stakeholder consultation/approval details etc. were uploaded on CTU website on 14/08/2019 and forwarded to stakeholders(Generators, STUs, RLDCs, SLDC & Distribution Licensees) for their observations by 28/09/2019. Subsequently, the transmission system was again taken up in 5 th NRSCT meeting held on 13/09/2019. During the meeting, various alternatives, viz. EHVAC system and Hybrid system with EHVAC and VSC based HVDC system were discussed. It was observed that it would be difficult to implement VSC based HVDC transmission system by Dec’21 matching with anticipated RE generation projects. Further, Hybrid of HVDC and AC system is found to be about Rs. 4500 5000 Cr. costlier compared to AC system. Considering above aspects as well as phased implementation of generation projects, EHVAC transmission system alongwith STATCOMs for reactive power control was agreed in 5 th NRSCT meeting (MOM awaited). Considering above, details of the revised scheme, justification, estimated cost and its tariff impact, results of the system studies, study assumptions, stakeholder consultation/approval details etc. are attached for stakeholders(Generators, STUs, RLDCs, SLDC & Distribution Licensees) observations, if any, latest by 05/10/2019 at mail ids [email protected]; [email protected].

Transcript of Transmission System strengthening for potential solar ... for... · substation at Narela with 765...

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 1 of 11

Transmission System strengthening for potential solar energy

zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS

and balance 3.0GW under Intra-State by RVPN).

Transmission System for Solar Energy Zones (SEZs) in Rajasthan under Phase-II

involving Hybrid system with EHVAC and VSC based HVDC was discussed and

technically agreed in the 4th NRSCT meeting held on 25/07/19. Accordingly, the

details of the scheme, justification, estimated cost and its tariff impact, results of the

system studies, study assumptions, stakeholder consultation/approval details etc.

were uploaded on CTU website on 14/08/2019 and forwarded to

stakeholders(Generators, STUs, RLDCs, SLDC & Distribution Licensees) for their

observations by 28/09/2019.

Subsequently, the transmission system was again taken up in 5th NRSCT meeting

held on 13/09/2019. During the meeting, various alternatives, viz. EHVAC system

and Hybrid system with EHVAC and VSC based HVDC system were discussed. It

was observed that it would be difficult to implement VSC based HVDC transmission

system by Dec’21 matching with anticipated RE generation projects. Further, Hybrid

of HVDC and AC system is found to be about Rs. 4500 – 5000 Cr. costlier compared

to AC system. Considering above aspects as well as phased implementation of

generation projects, EHVAC transmission system alongwith STATCOMs for reactive

power control was agreed in 5th NRSCT meeting (MOM awaited).

Considering above, details of the revised scheme, justification, estimated cost and its

tariff impact, results of the system studies, study assumptions, stakeholder

consultation/approval details etc. are attached for stakeholders(Generators, STUs,

RLDCs, SLDC & Distribution Licensees) observations, if any, latest by 05/10/2019 at

mail ids [email protected]; [email protected].

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 2 of 11

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

A. Project at a Glace

1. Title (Name of Scheme) Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

2. Objective / Justification

The objective of proposed Transmission System Strengthening for potential Solar Energy Zones (SEZs) (11.1GW) in Rajasthan (8.1 GW under ISTS & 3GW under Intra State by Rajasthan) is to facilitate integration of potential solar generation from the complexes of Bhadla, Fatehgarh, Bikaner & Ramgarh/Kuchheri in Western Rajasthan

3. Scope

i) Establishment of 400/220kV, 4x500 MVA pooling

station at suitable location near Ramgarh/Kuchheri

in Distt Jaisalmer (Ramgarh-II PS) with 2x125 MVAr

bus reactor.

ii) Ramgarh-II PS –Fatehgarh-II PS 400 kV D/c Line

(Twin HTLS*)

iii) Ramgarh-II PS – Jaisalmer-II (RVPN) 400 kV D/c

Line (Twin HTLS*)

iv) Establishment of 400/220kV, 6x500MVA pooling

station at suitable location near Bikaner (Bikaner-II

PS) with 2x125 MVAr bus reactor and with suitable

bus sectionalisation at 400 and 220 kV level.

v) Bikaner-II PS – Khetri 400kV 2xD/c line (Twin HTLS*

line on M/c tower)

vi) Removal of LILO of one circuit of Bhadla-Bikaner

(RVPN) 400kV D/c (Quad) line at Bikaner (PG).

Extension of above LILO section from Bikaner(PG)

upto Bikaner-II PS to form Bikaner-II PS – Bikaner

(PG) 400kV D/c(Quad) line)

vii) 1x80 MVAr Switchable line reactor for each circuit at

each end of Bikaner-II – Khetri 400kV 2xD/c line

viii) Establishment of 765/400kV, 2x1500 MVA S/s at

suitable location near Sikar (Sikar-II Substation) with

1x125 MVAr & 2x330 MVAr bus reactor at Sikar -II

ix) Sikar-II – Aligarh 765kV D/c line

x) Bhadla-II PS – Sikar-II 765kV 2xD/c line

xi) Sikar-II – Neemrana 400kV D/c line (Twin HTLS*)

xii) 1x330 MVAr Switchable line reactor for each circuit

at Sikar II end of Bhadla-II – Sikar-II 765kV 2xD/c

line

xiii) 1x240 MVAr Switchable line reactor for each circuit

at Bhadla-II end of Bhadla-II – Sikar-II 765kV 2xD/c

line

xiv) 1x330MVAr Switchable line reactor for each circuit

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 3 of 11

at each end of Sikar-II –Aligarh 765kV D/c line

xv) Augmentation with 765/400kV, 2x1500MVA

transformer (5th & 6th) at Fatehgarh-II PS

xvi) Fatehgarh-II PS – Bhadla-II PS 765kV D/c line (2nd)

xvii) 1x240 MVAr Switchable line reactor for each circuit

at each end of Fatehgarh-II – Bhadla-II 765kV D/c

line

xviii) Augmentation with 400/220kV, 4x500MVA

transformer (6th to 9th) at Fatehgarh-II PS with

suitable bus sectionalisation at 400 kV & 220 kV

xix) Augmentation with 765/400kV, 1x1500MVA

transformer (4th) at Bhadla-II PS.

xx) Augmentation with 400/220kV, 3x500MVA

transformer (6th to 8th) at Bhadla-II PS with suitable

bus sectionalisation at 400 kV & 220 kV

xxi) Khetri - Bhiwadi 400kV D/c line (Twin HTLS*)#

xxii) Power reversal on +500kV, 2500MW Balia –

Bhiwadi HVDC line upto 2000MW from Bhiwadi to

Balia in high solar generation scenario

xxiii) 220kV line bays for interconnection of solar

projects at Bikaner-II PS (10 nos.), Ramgarh-II PS (7

nos), Fatehgarh-II PS (7 nos) & Bhadla-II PS (4 nos)

xxiv) Establishment of 765/400 kV, 3X1500 MVA GIS

substation at Narela with 765 kV (2x330 MVAr) bus

reactor and 400kV (1x125 MVAR) bus reactor

xxv) Establishment Khetri – Narela 765 kV D/c line

xxvi) 1x330 MVAr Switchable line reactor for each

circuit at Narela end of Khetri – Narela 765kV D/c

line

xxvii) LILO of 765 kV Meerut- Bhiwani S/c line at

Narela

xxviii) Removal of LILO of Bawana – Mandola 400kV

D/c(Quad) line at Maharani Bagh/ Gopalpur S/s.

Extension of above LILO section from Maharani

Bagh/Gopalpur upto Narela S/s so as to form

Maharanibagh – Narela 400kV D/c(Quad) and

Maharanibagh -Gopalpur-Narela 400kV D/c(Quad)

lines.

xxix) STATCOMs:

Fatehgarh – II S/s : STATCOM : ± 600 MVAr,

4x125 MVAR MSC , 2x125 MVAr MSR

Bhadla – II S/s : STATCOM : ± 600 MVAr, 4x125

MVAR MSC , 2x125 MVAr MSR

Bikaner – II S/s : STATCOM : ± 300 MVAr, 2x125

MVAR MSC , 1x125 MVAr MSR

* with minimum capacity of 2200 MVA on each circuit at

nominal voltage

#Due to space constraints, 400kV bays at Bhiwadi S/s to

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 4 of 11

be implemented as GIS

Note: Suitable space provision to be kept at Ramgarh-II, Bikaner–II PS, Narela & Sikar-II S/s for spares & future expansion

Schematic enclosed at Exhibit-I.

4. Estimated Cost

About ₹ 12442 Crore

5. Estimated impact on tariff for next five years

₹ 2115 Crore/year*

6. System Study Discussed in 3rd NRSCT held on 24/05/2019, extract

of MOM attached at Annexure-I.

Discussed in Joint Study Meeting amongst CEA,

CTU, POSOCO, RVPNL, HVPNL, DTL, HPPTCL &

PSTCL on 17/06/2019 and 18/06/2019.

Discussed in Meeting amongst CEA, CTU,

POSOCO, RVPNL, HVPNL, DTL, HPPTCL, PTCUL

& PSTCL on 24/07/2019.

Discussed in 4th NRSCT held on 25/07/2019, extract

of MOM attached at Annexure-II.

Discussed and agreed in 5th NRSCT held on

13/09/2019 (MOM Awaited).

Studies enclosed at Exhibit-II

7. Approval of Scheme Agreed in 5th NRSCT held on 13/09/2019 (MOM Awaited).

To be taken up in forthcoming NRPC, NCT & ECT

meetings.

8. Time frame December, 2021 *Considering first year tariff @ 17% ** Levealised tariff may be in the range of 14 %

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 5 of 11

Transmission System strengthening for potential solar energy zones (11.1GW) –

Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-

State by RVPN)

1.0 TITLE (NAME OF SCHEME)

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -

II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by

RVPN)

2.0 ESTIMATED COST

The estimated cost of the proposed transmission system: about ₹ 12442 Cr.

3.0 TRANSMISSION SYSTEM FOR SOLAR ENERGY ZONES IN RAJASTHAN

Proposed transmission system includes following elements:

i) Establishment of 400/220kV, 4x500 MVA pooling station at suitable location

near Ramgarh/Kuchheri in Distt Jaisalmer (Ramgarh-II PS) with 2x125 MVAr

bus reactor.

ii) Ramgarh-II PS –Fatehgarh-II PS 400 kV D/c Line (Twin HTLS*)

iii) Ramgarh-II PS – Jaisalmer-II (RVPN) 400 kV D/c Line (Twin HTLS*)

iv) Establishment of 400/220kV, 6x500MVA pooling station at suitable location near

Bikaner (Bikaner-II PS) with 2x125 MVAr bus reactor and with suitable bus

sectionalisation at 400 and 220 kV level.

v) Bikaner-II PS – Khetri 400kV 2xD/c line (Twin HTLS* line on M/c tower)

vi) Removal of LILO of one circuit of Bhadla-Bikaner (RVPN) 400kV D/c (Quad) line

at Bikaner (PG). Extension of above LILO section from Bikaner(PG) upto

Bikaner-II PS to form Bikaner-II PS – Bikaner (PG) 400kV D/c(Quad) line)

vii) 1x80 MVAr Switchable line reactor for each circuit at each end of Bikaner-II –

Khetri 400kV 2xD/c line

viii) Establishment of 765/400kV, 2x1500 MVA S/s at suitable location near Sikar

(Sikar-II Substation) with 1x125 MVAr & 2x330 MVAr bus reactor at Sikar -II

ix) Sikar-II – Aligarh 765kV D/c line

x) Bhadla-II PS – Sikar-II 765kV 2xD/c line

xi) Sikar-II – Neemrana 400kV D/c line (Twin HTLS*)

xii) 1x330 MVAr Switchable line reactor for each circuit at Sikar II end of Bhadla-II –

Sikar-II 765kV 2xD/c line

xiii) 1x240 MVAr Switchable line reactor for each circuit at Bhadla-II end of Bhadla-II

– Sikar-II 765kV 2xD/c line

xiv) 1x330MVAr Switchable line reactor for each circuit at each end of Sikar-II –

Aligarh 765kV D/c line

xv) Augmentation with 765/400kV, 2x1500MVA transformer (5th & 6th) at

Fatehgarh-II PS

xvi) Fatehgarh-II PS – Bhadla-II PS 765kV D/c line (2nd)

xvii) 1x240 MVAr Switchable line reactor for each circuit at each end of Fatehgarh-II

– Bhadla-II 765kV D/c line

xviii) Augmentation with 400/220kV, 4x500MVA transformer (6th to 9th) at Fatehgarh-

II PS with suitable bus sectionalisation at 400 kV & 220 kV

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 6 of 11

xix) Augmentation with 765/400kV, 1x1500MVA transformer (4th) at Bhadla-II PS.

xx) Augmentation with 400/220kV, 3x500MVA transformer (6th to 8th) at Bhadla-II

PS with suitable bus sectionalisation at 400 kV & 220 kV

xxi) Khetri - Bhiwadi 400kV D/c line (Twin HTLS*)#

xxii) Power reversal on +500kV, 2500MW Balia – Bhiwadi HVDC line upto 2000MW

from Bhiwadi to Balia in high solar generation scenario

xxiii) 220kV line bays for interconnection of solar projects at Bikaner-II PS (10 nos.),

Ramgarh-II PS (7 nos), Fatehgarh-II PS (7 nos) & Bhadla-II PS (4 nos)

xxiv) Establishment of 765/400 kV, 3X1500 MVA GIS substation at Narela with 765

kV (2x330 MVAr) bus reactor and 400kV (1x125 MVAR) bus reactor

xxv) Establishment Khetri – Narela 765 kV D/c line

xxvi) 1x330 MVAr Switchable line reactor for each circuit at Narela end of Khetri –

Narela 765kV D/c line

xxvii) LILO of 765 kV Meerut- Bhiwani S/c line at Narela

xxviii) Removal of LILO of Bawana – Mandola 400kV D/c(Quad) line at Maharani

Bagh/ Gopalpur S/s. Extension of above LILO section from Maharani

Bagh/Gopalpur upto Narela S/s so as to form Maharanibagh – Narela 400kV

D/c(Quad) and Maharanibagh -Gopalpur-Narela 400kV D/c(Quad) lines.

xxix) STATCOMs:

Fatehgarh – II S/s : STATCOM : ± 600 MVAr, 4x125 MVAR MSC , 2x125 MVAr

MSR

Bhadla – II S/s : STATCOM : ± 600 MVAr, 4x125 MVAR MSC , 2x125 MVAr

MSR

Bikaner – II S/s : STATCOM : ± 300 MVAr, 2x125 MVAR MSC , 1x125 MVAr

MSR

* with minimum capacity of 2200 MVA on each circuit at nominal voltage

#Due to space constraints, 400kV bays at Bhiwadi S/s to be implemented as GIS

Note: Suitable space provision to be kept at Ramgarh-II, Bikaner–II PS, Sikar-II & Narela

S/s for spares & future expansion

The schematic of the proposed transmission system is shown at Exhibit-I.

4.0 OBJECTIVE AND JUSTIFICATION

Government of India has set a target for establishing 175 GW renewable capacity by

2022, which includes 100 GW from Solar and 60 GW from Wind. MNRE vide its order

dated 08.06.2018 had constituted a Sub-Committee to identify ISTS connectivity for

renewable energy projects from potential solar energy zones (SEZs) and potential wind

energy zones (WEZs) of about 50 GW and 16.5 GW respectively. SEZs and WEZs

envisaged in 7 RE rich states (Tamil Nadu, Andhra Pradesh, Karnataka, Gujarat,

Rajasthan, Maharashtra and Madhya Pradesh) were identified by SECI in association

with MNRE in consultation with RE power developers.

To ease implementation of transmission infrastructure, it was proposed to bifurcate these

requirements in two phases. A total of 20 GW solar & 9 GW wind projects has been

planned in Phase-I (up to Dec’2020) and 30 GW solar & 7.5 GW wind has been planned

for Phase-II (Dec’ 2021). For Northern Region, the same translates into a requirement of

10 GW solar in Phase-I (up to Dec’2020) and 10 GW solar in Phase-II (Dec’2021)

totaling to 20 GW. The details of SEZs in Northern Region are given below:

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 7 of 11

Solar Energy Zones

State/District Ph-1 (GW) Ph-2 (GW) Total

2020 2021 Rajasthan Jaisalmer (S: Ramgarh, Fatehgarh) 5 3 8 Jodhpur (S: Phalodi) 2 1 3 Bikaner (S: Kolayat/Pugal) 3 1 4 Barmer (S: Barmer) 0 5 5 Subtotal 10 10 20

MNRE has subsequently revised Solar Potential complexes details in Rajasthan

for development by 2020/2021 in two phases, which is as under:

District Taluk/Tehsil Ph-1(GW) 2020 Ph-2(GW)

2021 Total

Jaisalmer Kuchhri - 4.00 4.00

Fatehgarh 3.50 2.20 5.70

Jodhpur Phalodi/Bhadla 3.55 1.75 5.30

Bikaner Koyalat /Pugal 1.85 3.15 5.00

Total 8.90 11.1 20

Out of total 20 GW REZ [Solar] in Rajasthan, transmission system for 8.9 GW in

Bhadla (3.55 GW), Fatehgarh (3.5 GW), Bikaner (1.85 GW) complexes under

Phase-I, has been taken up for implementation. Out of this, Stage-II connectivity

and LTA applications have been received for about 8 GW and 6 GW respectively.

In the 3rd meeting of NRSCT held on 24/05/2019, the transmission system for

integration of balance 11.1 GW solar potential in Rajasthan [Phase –II :11.1GW]

(Out of total 20 GW REZ [Solar]) from Ramgarh/Kuchheri (4 GW), Bikaner (3.15

GW), Bhadla (1.75GW) & Fatehgarh (2.2 GW) was deliberated. RVPNL

highlighted that the intra-state EHV transmission in Western Rajasthan is

sufficient to evacuate about 10 GW RE projects (7.4 GW already commissioned

and 1.3 GW under implementation). In addition to this, 2 GW, 2.1 GW and 2.211

GW of RE capacity addition is expected in the year 2020-21, 2021-22 and 2022-

23 respectively. For evacuation of this additional 6.3 GW RE capacity,

upgradation of 400kV Jodhpur (Kakani) S/s to 765kV level along with its

interconnections with Phagi 765/400 kV GSS and 400kV interconnections.

It is to mention that additional RE capacity of 4.1 GW (3.1 GW Solar & 1 GW

wind) in time frame of 2021-22 is planned by Rajasthan in Intra state, which

includes 3 GW Solar located in Jaisalmer (2.1 GW), Jodhpur (0.7 GW) & Bikaner

Area (0.2 GW). Therefore after accounting for development of above Solar

generation (3 GW) in Intra state network in similar pockets, transmission system

for only 8.1 GW (Ramgarh/Kuchheri (1.9 GW), Bikaner (2.95 GW), Bhadla

(1.05GW) & Fatehgarh (2.2GW) of RE potential is required to be planned under

ISTS as compared to 11.1 GW system that has been proposed earlier and it was

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 8 of 11

decided that that a joint study meeting would be convened to further deliberate on

the scheme.

A joint study meeting was convened on 17/06/2019 & 18/06/2019 at

POWERGRID, Gurgaon, wherein, the representatives from CTU, POSOCO,

Haryana, Punjab, Himachal Pradesh, Rajasthan and Delhi were present. No

representative from UPPTCL, PTCUL and JKPDD attended the meeting. All the

State representative furnished their load generation balance as well as existing

and planned RE generations in their respective states. The comments furnished

by the constituents were discussed and accordingly the load flow study was

revised. Subsequently, PTCUL representative also got updated the network

pertaining to them.

As advised by the constituents during above joint study meeting two alternatives,

viz (i) AC Transmission system (ii) Hybrid Transmission system involving VSC

based HVDC were proposed for evacuation of 8.1 GW under ISTS as part of

Phase-II. During 4th NRSCT meeting, after detailed deliberations, considering

technical advantages of Hybrid Transmission system involving VSC based HVDC

were agreed for evacuation of 8.1 GW under ISTS as part of Phase-II.

Subsequently, the transmission system was again taken up in 5th NRSCT

meeting held on 13/09/2019. During the meetings, various alternatives, viz.

EHVAC system alternatives and Hybrid system with EHVAC and VSC based

HVDC system alternative were discussed. It was observed that it would be

difficult to implement VSC based HVDC transmission system by Dec’21 matching

with anticipated RE generation projects. Further, Hybrid of HVDC and AC system

is found to be about Rs. 4500 – 5000 Cr. costlier compared to AC system.

With regard to EHVAC transmission system, it was discussed that as per

technical standards of CEA, Renewable Generators shall be capable of supplying

dynamically varying reactive power support so as to maintain power factor within

limits of 0.95 lagging to 0.95 leading. Assuming length of dedicated line as 50 km,

reactive power loss of about 30 MVAr is envisaged for 300 MW on 220kV S/c

line. Accordingly, in the absence of proper reactive power support to transmission

system, compensation is required to be provided near RE Generation Pooling

Stations.

During fault conditions in the absence of conventional generator & low short

circuit levels in close proximity, grid/voltage stability would be a major concern.

Due to persistence of low voltage in the network, there could be cascading effect

of multiple RE generation tripping due to breach of LVRT triggers. This could lead

to further fall in system voltage due to generation loss and may lead to voltage

collapse in the system. In view of above, dynamic reactive power support at ISTS

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 9 of 11

pooling station is required to maintain Grid parameters within acceptable limits

with variation in generation.

It is also observed from simulation studies that many line & bus reactors are

required to be switch off to operate the grid in high RE scenario. Considering

large scale integration of Renewable Energy Sources (both State & ISTS)

expected in Western Rajasthan, Ramp up/down of generation is envisaged to be

very fast. In such a scenario, manual switching ON/OFF of Reactors may not be

practically feasible & STATCOM controllers may be used for switching in/out

nearby Reactors.

Considering above aspects as well as phased implementation of generation

projects, EHVAC transmission system alongwith STATCOMs for reactive power

control was agreed in 5th NRSCT meeting as “Transmission System Strengthening

for potential Solar Energy Zones (SEZs) - Phase-II in Northern Region” to cater to the

future potential (8.1 GW) at the complexes in Ramgarh, Fatehgarh,

Bhadla/Phalodi & Bikaner.

Considering power transfer from Solar potential of various complexes in Western

Rajasthan i.e. Ramgarh, Fatehgarh, Bhadla/Phalodi & Bikaner, the technically

agreed transmission system includes establishment of 400/220kV pooling station

near Ramgarh/Kuchheri in Distt Jaisalmer (Ramgarh-II PS) and near Bikaner

(Bikaner-II PS). The scheme also includes augmentation of transformation

capacity at Fatehgarh-II PS, Bhadla-II PS and Bikaner (PG).

For interconnection of above new pooling stations with existing/under

construction transmission system and to strengthen existing transmission system,

Ramgarh-II PS –Fatehgarh-II PS 400 kV D/c(Twin HTLS), Ramgarh-II PS –

Jaisalmer-II (RVPN) 400 kV D/c(Twin HTLS), Fatehgarh-II PS – Bhadla-II PS

765kV D/c(2nd ), Bikaner-II PS – Khetri 400kV 2xD/c(Twin HTLS), Bikaner-II PS –

Bikaner (PG) 400kV D/c(Quad) have been agreed. For onward dispersal of

power, development of high capacity corridors viz. Khetri - Bhiwadi 400kV

D/c(Twin HTLS), Khetri - Narela 765kV D/c, Bhadla-II – Sikar-II 765kV 2xD/c,

Sikar-II – Neemrana 400kV D/c(HTLS) and Sikar-II – Aligarh 765 kV D/c also

been agreed. The scheme also envisages establishment of 765/400 kV Narela

S/s, LILO of Meerut – Bhiwani 765kV S/c line at Narela S/s, Maharanibagh –

Narela 400kV D/c(Quad) and Gopalpur-Narela 400kV D/c(Quad) lines. Further,

STATCOMs have been agreed at Bikaner(± 300 MVAr, 2x125 MVAR MSC , 1x125

MVAr MSR), Bhadla-II (± 600 MVAr, 4x125 MVAR MSC , 2x125 MVAr MSR) and

Fatehgarh-II (± 600 MVAr, 4x125 MVAR MSC , 2x125 MVAr MSR) for reactive power

support & dynamic stability enhancement.

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 10 of 11

For optimal utilization of transmission system, it was agreed to reverse the

conventional power flow of Balia – Bhiwadi HVDC, i.e 2000 MW power from

Bhiwadi to Balia.

In addition, suitable reactive compensation in the form of Bus reactor at above

substations as well as switchable line reactors on EHV AC lines are also agreed.

5.0 COST-BENEFIT ANALYSIS INCLUDING LONG TERM ECONOMIC ADVANTAGE

The annual transmission charges for the subject scheme at an estimated cost of

about Rs. 12442 Cr would be about Rs. 2115 Cr. The above transmission

system shall enable transfer of power from 8100 MW solar capacity. Such

quantum of power shall translate into annual energy of about 17739 MU [Energy in

MU = (8100x0.25*xx8760) / 103]. If we consider rate of energy as Rs. 2.5 per unit on

the conservative side then the total annual energy cost works out to be about Rs.

4435 Crs.

In other words, the system proposed under the subject scheme whose annual

transmission charges is Rs. 2115 Crs shall enable ISTS grid to handle energy

amounting to Rs. 4435 Crs.

In addition to the above tangible benefits, the development of proposed

transmission scheme shall also provides intangible benefits in the way of

providing vital transmission system for evacuation of clean & green solar energy.

This shall also go a long way in nation’s energy security & sustainability at

affordable prices along with addressing climate change concerns.

* Solar CUF@25% has been considered as per SECI information.

6.0 TIME FRAME / PHASING OF THE IMPLEMENTATION OF THE SCHEME The transmission scheme was envisaged based on the potential of Solar Energy

in Western Rajasthan and Government of India target for establishing 175 GW

renewable capacity by 2022. In a meeting regarding prioritization of transmission

system associated with 66.5GW potential RE capacity already planned held on

30.08.2019 at CEA, SECI stated the transmission schemes associated with RE

capacity addition in Rajasthan , needs to be taken up on priority. Minutes of the

Meeting are attached at Annexure-III. Accordingly, the scheme is required to be

completed by December, 2021.

7.0 CONSENT OF BENEFICIARIES

The scheme was discussed with the stakeholders in 3rd & 4th meeting of NRSCT

held on 24/05/2019 and 25/07/2019 respectively. Subsequently, Transmission

System Strengthening for potential solar energy zones (8.1GW) –Phase -II in

Transmission System strengthening for potential solar energy zones (11.1GW) –Phase -II in Northern Region (8.1GW under ISTS and balance 3.0GW under Intra-State by RVPN).

Page 11 of 11

Northern Region was agreed in the 5th meeting of NRSCT held on 13/09/19 by

the stakeholders (MOM Awaited). Results of the system studies carried out with

the proposed scheme for various scenarios is enclosed at Exhibit-II. Assumption

and inputs considered in above system studies is also enclosed in Annexure -IV.

Annexure-I

File No.CEA-PS-11-21(19)/1/2019-PSPA-I Division-Part(1)I/6067/2019

68

File No.CEA-PS-11-21(19)/1/2019-PSPA-I Division-Part(1)I/6067/2019

69

File No.CEA-PS-11-21(19)/1/2019-PSPA-I Division-Part(1)I/6067/2019

70

File No.CEA-PS-11-21(19)/1/2019-PSPA-I Division-Part(1)I/6067/2019

71

File No.CEA-PS-11-21(19)/1/2019-PSPA-I Division-Part(1)I/6067/2019

72

Minutes of 4th meeting of NRSCT held on 25.7.2019

Minutes of 4th Meeting of Northern Region Standing Committee on Transmission (NRSCT) held on 25.7.2019 List of participants is enclosed as Annexure I. Member(PS), CEA welcomed the participants to the meeting and stated that main agenda for the meeting is finalization of the transmission system for evacuation of power from Solar Energy Zones in Rajasthan under Phase-II. He further stated that Government of India has set a target of 175 GW of RE generation by 2021-22 and in order to meet the same, the transmission infrastructure is required to be constructed in advance keeping in view of short gestation period of RE generations. Chief Engineer (PSPA-I), CEA stated that the transmission schemes for evacuation of 8.9 GW of RE generations in Rajasthan under Phase-I were agreed in the 2nd meeting of NRSCT and presently under bidding process. The transmission scheme for evacuation of RE generations in Rajasthan under Phase-II was discussed in the 3rd meeting of NRSCT however it was decided that the scheme needs further review and joint meeting needs to be conducted. Accordingly, the transmission schemes proposed in present meeting has been evolved after consultation with NR constituents. He then requested Director, PSPA-I(CEA) to take up the agenda for discussions.

1.0 Confirmation of the Minutes of the 3rd meeting of Northern Region Standing Committee on Transmission held on 24.05.2019.

1.1 CEA stated that the 3rd meeting of Northern Region Standing Committee on Transmission (NRSCT) was held on 24.05.2019 and the minutes of the meeting were issued vide CEA letter no. File No.CEA-PS-11-21(19)/1/2019-PSPA-I Division-Part (1) dated 17.7.2019. CEA further stated that the following observations were received from CVPPL and POSOCO:

1.2 CVPPL vide its letter CVPPL/Plg/2019/264 dated 23.07.2019 has furnished its observations regarding para no 2.3 and 2.9.1 of minutes: Para no.2.3 of the MoM

2.3 CVPPL informed that ----------------Long term Access for Pakal Dul HE Project (1000 MW) has been submitted to CTU on 14.05.2019 -----------------------.

May be modified as 2.3 CVPPL informed that ----------------Long term Access for Pakal Dul HE Project (1000 MW) has been submitted to CTU on 21.05.2019 -----------------------.

Para no.2.9(i) of the MoM

2.9 After deliberations, following was agreed:

i) CVPPL to apply for connectivity to CTU-----------------. M/s CVPPL to phase the implementation of the dedicated line as per the implementation timelines of the HEPs.

May be modified as 2.9 After deliberations, following was agreed:

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

21Annexure-II

Minutes of 4th meeting of NRSCT held on 25.7.2019

(iii) A separate meeting be convened with CEA, CTU, POSOCO and PSTCL to finalise the interim arrangement at Moga substation for the intermediate period between commissioning of Bikaner-Moga 765 kV D/c line and implementation of 400kV bus splitting at Moga.

3.0 Transmission System for evacuation of Power from potential solar energy zones Phase -II in Northern Region.

3.1 CEA stated that Govt. of India had set a target for establishing 175 GW renewable capacity by 2022, which includes 100 GW Solar, 60 GW Wind generation capacity. MNRE vide its order dated 08.06.2018 had constituted a Sub-Committee to identify ISTS connectivity for renewable energy projects from potential solar energy zones (SEZs) and potential wind energy zones (WEZs) of about 50 GW and 16.5 GW respectively. SEZs and WEZs envisaged in 7 RE rich states (Tamil Nadu, Andhra Pradesh, Karnataka, Gujarat, Rajasthan, Maharashtra and Madhya Pradesh) were identified by SECI in association with MNRE in consultation with RE power developers.

To ease implementation of transmission infrastructure, it was proposed to bifurcate these requirements in two phases. A total of 20 GW solar & 9 GW wind projects has been planned in Phase-for Phase-10 GW solar in Phase- 10 GW solar in Phase-totalling to 20 GW. The details of SEZs in Northern Region are given below:

Solar Energy Zones

State/District Ph-1 (GW) Ph-2 (GW) Total

2020 2021 Rajasthan Jaisalmer (S: Ramgarh, Fatehgarh) 5 3 8 Jodhpur (S: Phalodi) 2 1 3 Bikaner (S: Kolayat/Pugal) 3 1 4 Barmer (S: Barmer) 0 5 5 Subtotal 10 10 20

MNRE has subsequently revised Solar Potential complexes details in Rajasthan for development by 2020/2021 in two phases, which is as under:

District Taluk/Tehsil Ph-1(GW) 2020

Ph-2(GW) 2021 Total

Jaisalmer Kuchhri - 4.00 4.00 Fatehgarh 3.50 2.20 5.70 Jodhpur Phalodi/Bhadla 3.55 1.75 5.30 Bikaner Koyalat /Pugal 1.85 3.15 5.00 Total 8.90 11.1 20

The details of connectivity/LTA granted are as follows: Sl no.

Location St-II connectivity LTA

Applied Granted/Agreed Applied (MW) Granted (MW)

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

26

Minutes of 4th meeting of NRSCT held on 25.7.2019

3.2 Out of total 20 GW REZ [Solar] in Rajasthan, transmission system for 8.9 GW in Bhadla (3.55 GW), Fatehgarh (3.5 GW), Bikaner (1.85 GW) complexes under Phase-I, was technically agreed in the 2nd meeting of Northern Region Standing Committee on Transmission (NRSCT) held on 13.11.2018.

3.3 In the 3rd meeting of NRSCT held on 24.5.2019 the transmission system for integration of balance 11.1 GW solar potential in Rajasthan [Phase II :11.1GW] (Out of total 20 GW REZ [Solar]) from Ramgarh/Kuchheri (4 GW), Bikaner (3.15 GW), Bhadla (1.75GW) & Fatehgarh (2.2 GW) was deliberated. In the meeting RVPNL highlighted that the intra-state EHV transmission in Western Rajasthan is sufficient to evacuate about 10 GW RE projects (7.4 GW already commissioned and 1.3 GW under implementation). In addition to this, 2 GW, 2.1 GW and 2.211 GW of RE capacity addition is expected in the year 2020-21, 2021-22 and 2022-23 respectively. For evacuation of this additional 6.3 GW RE capacity, 765/400 kV Jodhpur GSS (Hingola) along with its interconnections with Phagi 765/400 kV GSS has been planned. Subsequently, RVPNL has provided the modified proposal for evacuation of additional RE capacity. The plan comprised upgradation of 400kV Jodhpur (Kakani) S/s to 765kV level along with its interconnections with Phagi 765/400 kV GSS and 400kV interconnections.

An additional RE capacity of 4.1 GW (3.1 GW Solar & 1 GW wind) in time frame of 2021-22 has been planned by Rajasthan in Intra state, which includes 3 GW Solar located in Jaisalmer (2.1 GW), Jodhpur (0.7 GW) & Bikaner Area (0.2 GW). Therefore, after accounting for development of above Solar generation (3 GW) in Intra state network in similar pockets, transmission system for only 8.1 GW (

) of RE potential was required to be planned under ISTS as compared to 11.1 GW system that has been proposed earlier and it was decided that that a joint study meeting would be convened to further deliberate on the scheme.

MoP vide its OM dated 14.6.2018 had notified the long term RPO trajectory, solar and non-solar, uniformly for all the States, wherein, RPO (%) (of total consumption Excluding Hydro) 10.5% for Solar and 10.5% for non- solar has been mentioned for 2021-22. However, RPO (%) as per the State Electricity Regulatory commission for 2021-22 furnished by respective State are as follows:

S. State RPO (%) of Total Consumption Excluding

(MW) for Grant (MW) 1 Bhadla 3380

(13 nos.) 3380 3380

(13 nos.) 3380

2 Bhadla-II 1280 (2 nos.)

300+980 (agreed)

980 -

3 Fatehgarh 2050 (7 nos.)

1700+350 (Agreed)

1200 (4 nos.)

850+350 (Received)

4 Fatehgarh-II 2200

(5 nos.) 2200 2200

(5 nos.) 2200

5 Bikaner 1790 (5 nos.)

1290+500 (agreed)

1290 (4 nos.)

600+690 (agreed)

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

27

Minutes of 4th meeting of NRSCT held on 25.7.2019

No Hydro (as per SERC) for 2021-22

Solar Non-Solar

1 Punjab 6.5 8

2 Haryana 8 3

3 Rajasthan 8.5 9.8

4 Uttar Pradesh 4 6

The study file was circulated to all the Northern region constituents to send their comments on the transmission system proposed as well as the on load flow file based on which the transmission system for evacuation of power from 8.1 GW RE (solar) projects has been proposed.

A joint study meeting was convened on 17.6.2019 & 18.6.2019 at Powergrid, Gurgaon, wherein, the representatives from CTU, POSOCO, Haryana, Punjab, Himachal Pradesh, Rajasthan and Delhi were present. No representative from UPPTCL, PTCUL and JKPDD attended the meeting. All the State representative furnished their load generation balance as well as existing and planned RE generations in their respective states. The comments furnished by the constituents were discussed and accordingly the load flow study was revised. Subsequently, PTCUL representative also got updated the network pertaining to them.

3.4 Incorporating the comments of the constituents the following alternatives are proposed for evacuation of power from 8.1 GW potential RE generation in Northern Region (

i) Establishment of 400/220kV 4x500 MVA pooling station at suitable location near

Ramgarh/Kuchheri ii)

iii)

iv)

v)

vi) vii) viii) ix) x) xi) xii) xiii) xiv)

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

28

Minutes of 4th meeting of NRSCT held on 25.7.2019

xv) xvi) xvii) xviii) xix) xx) xxi) xxii)

xxiii)

xxiv)

xxv) xxvi)

xxvii)

xxviii)

xxix)

xxx)

xxxi)

xxxii)

1.

i) Establishment of 400/220kV 4x500 MVA pooling station at suitable location near Ramgarh/Kuchheri

ii)

iii)

iv) v) vi) vii) viii) ix) x) xi) xii) xiii)

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

29

Minutes of 4th meeting of NRSCT held on 25.7.2019

xiv)

xv) xvi)

xvii)

xviii)

2.

i) +400kV, 5000 MW HVDC terminal at Pooling point near ii) +400kV, 5000 MW HVDC terminal at Pooling point in suitable location (near

Aliganj) between Bareilly and Mainpuri iii) +400kV HVDC line (Quad) between Bhadla-II PS and suitable location (near

Aliganj) between Bareilly and Mainpuri

i)

ii) iii) iv)

i) ii) iii) iv)

3.5 CEA

i)

ii)

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

30

Minutes of 4th meeting of NRSCT held on 25.7.2019

iii)

iv)

v)

a)

b) c) d)

vi)

3.6

3.7

Salient features of a VSC based HVDC

i) Best suitable option for integration of intermittent RE sources ii) Active and reactive power modulations possible to improve the stability of the

connected AC System iii) Supports connected AC system due to its steady state and dynamic voltage and

reactive power support iv) Reverse power transmission is feasible up to rated capability depending on the

requirements v) Four Quadrant Operation is possible vi) Controllability of power compared to AC transmission vii) Grid Connection to weak/islanded AC Networks viii) Independent Control of Active and Reactive power ix) Supply of passive Networks and Black Start Capability x) Can be used as STATCOM even without active power transmission xi) Less foot print area compared to conventional HVDC system xii) In symmetric monopole configuration, standard transformers are required instead

of converter transformers

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

31

Minutes of 4th meeting of NRSCT held on 25.7.2019

xiii) Generally, no/very little amount of harmonics thus reduces requirement of AC/DC filters

3.8

3.9

3.10 for evacuation of power from 8.1 GW potential RE

generation, under Phase-II, in Northern Region (

Transmission schemes for Solar Energy Zones (SEZs) in Rajasthan (8.1 GW) under Phase-II

A.

i) Establishment of 400/220kV 4x500 MVA pooling station at suitable location near Ramgarh/Kuchheri

ii)

iii)

iv)

v)

vi)

vii) viii) ix) x) xi) xii) xiii)

xiv) xv)

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

32

Minutes of 4th meeting of NRSCT held on 25.7.2019

xvi)

xvii) xviii)

xix)

xx) xxi) xxii)

xxiii)

xxiv)

B. 1)

i) +400kV, 5000 MW HVDC terminal at Pooling point near ii) +400kV, 5000 MW HVDC terminal at Pooling point in suitable location

near Modipuram iii) +400kV HVDC line (Quad) between Bhadla-II PS and suitable location near

Modipuram (on M/c tower)

Pooling point in suitable location near Modipuram

2) 3) 4) 5) 6)

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

33

Minutes of 4th meeting of NRSCT held on 25.7.2019

4.0 Modifications in the Transmission schemes for Solar Energy Zones (SEZs) in Rajasthan (8.9 GW)

4.1 transmission system for Solar Energy Zones (SEZs) in Rajasthan (8.9 GW) under Phase-I, was technically agreed in the 2nd meeting of Northern Region Standing Committee on Transmission (NRSCT) held on 13.11.2018. which inter-alia includes Length of this transmission line was estimated to be approx 100 km (as the estimated length of Fatehgarh-Bhadla transmission line was also about 100 km). Hence no reactive compensation was proposed for this line. However, it has come to notice that the route length for which Fatehgarh Bhadla Transmission Limited has got approval for Fatehgarh-Bhadla 765 kV D/c line is 145 km rather that earlier estimated 100 km. Also, survey for Fatehgarh II- Bhadla II has been done by BPC which indicated the route length to be 187 km in view of the proposed extension in the boundaries of the protected area for Great Indian Bustard. Therefore, reactive compensation needs to be provided for

Further LILO of

File No.CEA-PS-11-21(19)/2/2019-PSPA-I DivisionI/6424/2019

34

60002130
Typewritten Text
Annexure-III

Annexure-IV Study Assumptions

1. Studies has been carried out for various load generation scenarios i.e. solar

maximized scenario (for 8.1 GW SEZ based on future potential in Rajasthan) as

well as peak demand scenario for 2021-2022 time frame.

2. All India Demand is considered as per the 19th EPS of CEA (2021-22). For peak

demand scenario, regional demand has been considered as per the 19th EPS.

Based on the discussions & past trends, for solar maximized scenario, demand

has been considered as about 90% of the peak demand of 19th EPS for various

regions except for Northern region where it is considered as about 95% of the

peak demand.

3. In the studies, all India transmission network up to 220kV level has been

simulated. This includes, existing and well as under construction transmission

network incl. high capacity transmission corridors and Green Energy Corridors.

4. Considering envisaged RE (wind & solar) capacity addition and to achieve Load-

generation balance, Thermal generation dispatch is reduced upto 55%, wherever

required. At some of the locations, thermal generation is even needed to be

backed down.

5. For RE (Solar) maximized scenario, Solar generation dispatch in Rajasthan ISTS

SEZ is considered as 100%, whereas Rajasthan wind generation dispatch is

considered as 30% (Intra Solar is considered as 80%). In peak demand scenario

(evening), no Solar generation is considered whereas Rajasthan wind generation

dispatch is considered as 70%.

Jaisalmer (RVPN)

Jaipur(Phagi)

Bhadla (PG) (Ph-I: +1.05GW)

Fatehgarh

(Ph-I:+1.2GW)

To Jhatikara

From Banaskantha

Chittorgarh

Ajmer

Chittorgarh (RVPN)

Ajmer (RVPN)

To Moga

Bhadla (RVPN)

Ph-I : 8.9 GW

Transmission for Rajasthan SEZ: 20 GW (Ph-I: 8.9GW, Ph-II :11.1GW)

KHETRI

Fatehgarh-2 (Ph-I: 2.3GW) (Ph-II: 2.2GW)

Bhadla-2 (Ph-I : 2.5GW) (Ph-II:1.05GW)

Sikar (PG)

Jaisalmer (near Ramgarh/Kuchheri)

(Ph-II : 1.9GW)

Bikaner (Ph-I:+1.85GW) Bikaner-2

(Ph-II: 2.95GW)

To Bhiwani

To Gwalior

To Anta

Bhiwadi (Reversal of

Balia-Bhiwadi HVDC link)

Ph-II: 11.1 GW*

Narela

Bhiwadi

To Balia

* Out of 11.1 GW, 3 GW to be evacuated by RVPN through its planned/existing transmission system

Aligarh

To Meerut

To Bhiwani

To Mandola

To Bawana

To Maharanibagh

To Gopalpur

Bikaner (RVPN)

Sikar-II

Neemrana

Exhibit-I

167458BIKANER-NW

774.0

164480FATEHG-2

400.0

167459BHADLA PG

767.6

1000.0

0.0H

164460FATEHGARH

400.5

1100.0

0.0

1100.0

0.0

164459BHADLA PG

398.5

162498BHADLA-2

218.6

3550.0

398.8

137703MOGA-PG

767.8

167774KHETRI

771.1

776.6

147704BHIWN-PG

765.1 2337.9

2337.9

42.1

850.0

0.0H

399.6

1913.0

357.5

164404BHADLA

398.8

352.1

16.7

351.4

43.8

43.8

1320.8

164.7 1320.8

164.7

218.2

571.6

768.5

164774KHETRI

401.2

122.0 76.3

76.3

300.5

31.3

300.5

31.3

162359BHADLA-PG

217.3

3347.0

464.7

250.0

0.0H

162397ADANI

218.2

124.5

0.2

124.5

0.2

500.0

0.0H

162398SOURYA

218.9

248.0

7.6

248.0

7.6

0.0H

162399ESSEL

221.6

361.1

65.1

361.1

65.1

738.5

97.0

731.5

99.1

1361.1

12.1

1455.1

24.9

402.5

1551.9

325.5

764.8431.5

81.0

1483.7

103.4

798.8

15.4

1215.7

118.2

167498BHADLA-2

778.8

993.4

70.2

1000.0

0.0H

999.9

127.2

4500.0

164498BHADLA-2

400.0

4224.1

2070.9

162480FATEH-2

750.0

164451JAIPUR_RS

296.7

167417AJMER-NW

94.1 738.3

784.6

154463JHATIKALA-PG

399.9

804.9

157708JHATI-PG

164458BIKANER-NW

TO KANKROLI

164417AJMER-NW

7.4

TO BHINMAL

94.1

162458BIKANER

167773JAIPURR

409.9

351.4

TO BHILWARA

TO DEENWANATO HEERAPURA

TO BIKANER(RVPN)

TO BAP

TO BADISID

TO KANASAR

402.0

134423MOGA

TO KOTPUTLI

42.1

218.1

TO Gr. NOIDA

TO BAMNOLI

TO DWARKA

TO Sikanderabad

TO JALJIVI

623.8

TO KASHIPUR

TO MURADABAD

TO LUCKNOW

TO SHAHAJAHANPUR

TO MEERUT

TO BARELY(UP)

TO MANESAR

TO MERTA

TO MERTA

TO SOHAWAL

177707MERUT-PG

TO LUCKNOW

TO RAMPUR

TO NOIDA

TO JAWAHARPUR TPS

TO CHITTORGARH

TO ANTA

TO GWALIOR

TO BABAI

TO DHANONDA

TO PATNA

TO NAUBATPUR

TO BIHAR SHARF

TO MAU

TO RASRA

TO TALWANDI SABO

TO JALANDHAR

TO NOKADAR

TO FATEHBAD

TO KISHENPUR

TO HISSAR

TO HISSAR

TO MAHARANIBAGH

TO GOPALPUR

TO BASSI

TO BASSI

TO TEHRI POOL(FSC)

TO MUNDKA

TO AGRA

TO SIKAR

TO BHIWANI

Transmission Scheme for Rajasthan SEZ PH-II

TO GURGAON

TO SIKAR

405.4

164110JAISALMER-2

337.4

105.8

7135.3

898.6

1200.0

0.0H

337.4

164403RAMGARH

403.3

257.3

22.0

257.3

22.0

164401AKAL-4

406.1

23.5

7.6

23.5

7.6

288.8

53.3

164402BARMER-4

402.4

303.5

17.8

294.6

26.2

176.3

10.7

402.6

324.6

4.2

402.7

641.2

27.2

108.6

38.5

158.2

34.0

220.6

81.1

92.1

86.1

242.1

39.5

242.1

39.5

346.0

15.4

346.0

15.4

528.0

202.5

105.8

401.1

158.4

38.0

917.8

4.4

398.1

386.7

20.5

164461RAMG-II

403.5

726.9

94.4

726.9

94.4

400.0

31.6

27.6

31.6

27.6

164921BHIWADI

400.0

954.2

2.5371.9

24.3

274.4

80.5

274.4

80.5

41.6

71.3 41.5

71.4

235.9

135.0

15.9

135.0

15.9 91.7

14.4

260.0

72.1

36.0

623.0

36.0

174483BAREILY

404.7

424.0

245.5

40.9

623.0

92.7

2.5

954.2

214.7

15.6

214.7

15.6139.9

25.0

23.1

220.1

164434JODH KANKANI

403.3

164757POKARAN

220.1

23.1

382.2

39.5

382.2

39.5

736.0

84.8

84.8

736.0

1981.4

563.2

11.9

540.0

3.7

47.2 238.6

238.6

47.2

381.5

54.4

381.5

54.4

443.3

7.7

475.9

53.9

475.9

53.9

134325MALKANA

399.8

440.4

17.5

397.5

240.4

17.5

21.3

0.6

43.6

20.8

43.6

374.5

4.4 391.0

1.9

164495BIKANER-II

174266GNOIDAUP

401.6

780.4

27.9

76.0

81.3

76.0

81.3

98.2

14.8

98.2

14.8

215.9

66.6

215.9

66.6

63.9

1004.5

184.9

1004.5

184.9396.7

1170.6

752.5

62.9

623.8

70.2

174410BAREL-PG

404.8

212.0

125.5

212.0

125.5

33.7

15.8

34.1

15.4

194.2

42.8

162.0

97.6

97.6

194.2

42.8

188.6

0.8

188.6

0.8

54.6

18.7

54.6

18.7

111.8

22.4

109.0

17.6

109.0

17.6

88.2

94.2

798.8

15.4

162.0

154708JHATIKARASP

2398.1

90.9 263.4

38.1

263.4

38.1

378.4

530.1

13.7

41.2

164433JODH SURPURA

164430PACHPADRA

402.7

293.0

67.7

97.1

50.8

641.2

27.2

572.5

41.4

460.4

55.6

234.4

30.4

154501NARELA ISTS

399.3

1866.3

193.7

557.0

27.9

557.0

27.9

375.5

8.0

375.5

8.0

174475BAL74-PG

400.0

1308.8

172.2

70.5517.7

70.5

574.8

39.6

574.8

39.6

586.2

102.4

27.8

17.2

80.7

19.880.7

19.8

164445NEEMR-PG

517.7

586.2

102.4

4.2

13.3

4.2

13.3

20.8

134438MOGA SPLT

164413RAJWEST

917.8

4.4

164497SIKAR NEW

399.9

1701.1

1.0

840.6

62.6

840.6

62.6

707.3

93.3

771.0

26.8

892.1

861.0

341.9

1138.7

229.3

1336.4

132.7

861.0

341.9

1336.4

132.7

892.1

26.8 229.3

1914.5

111.8

357.5

1914.5

167480FATEH-2

132.2

198.0

1821.6

1571.0

1367.6

76.21367.6

198.0

768.1

1336.4

132.7

1336.4

132.7

1138.7

142.3

1542.4

76.2

423.1

261.5

1821.6

1199.0

212.7 1186.4

173.8

770.3

167799JODH KANKANI

221.8

31.3

221.8

177265GNOIDAUP

768.5

375.3

3.7

1883.3

133.2

322.3

14.8

83.0

366.9

177806BAREILLY

157001NARELA ISTS

767.6

1599.8

169.6

1332.7

166.1

1332.7

166.1

802.1

5.3

31.3

167497SIKAR NEW

767.2

1367.9

4.3 1367.9

4.3 1367.9

4.3

1367.9

4.3

177718RAMPUR_765

1

1885.2

104.6

1885.2

14.1

262.3

162.7

177882KANPURPG

177258ORAI

778.2

953.9

29.5

5.1

90.55.1

90.5

423.8

89.8

187.2

145.4

220.3

561.7

30.8

626.0

5.0

243.7

16.7

193.4

10.9

222.5

10.2

92.7

1269.3

16.2

162361RAMG-II

220.4

1900.0

0.0H

218.8

2950.0

314.3

4500.0

0.0

0.0

1880.0

0.0

2950.0

483.0

62.5

0.0H

887.9

4.2

1899.8

224.7

150.1

31.6

10.4

1144.0

0.0H

160.0

0.0H72.3

18.2

72.3

18.2

144.2

37.2

138.1

35.7

162285BHADLA-S

243.2

13.3

624.7

162403RAMGARH_RE

222.4

595.6

0.0H

139.5

162280AKAL-2

223.6

774.8

164416AJMER

408.0

0.0H

177512ALIGARH

0.0

133.2

23.5

7.2

0.0H

0.0H

56.0

64.0

0.0H

18.9

6.2

133.2

60.0

106.9

5.4

161047BHADLA

161240KHETUSAR

32.2

341.2

170.5

25.8

341.2

50.6

22.6

528.7

193.4

41.9

3550.0

214.950.6

162495BIKANER-2

177706AGRA-PG

1642.8

65.6

1642.8

65.6

1006.2

462.7

962.0

514.7

1006.2

462.7

962.0

514.7

721.7

35.3 708.7

61.0

721.7

35.3 708.7

61.0

0.0

241.1

C10.0

125.0

C20.0

125.0

C10.0

125.0

C20.0

125.0

C30.0

125.0

0.0

12.8

0.0

-59.7

C10.0

125.0

1

60002130
Text Box
EXHIBIT-II(A) Off Peak - RE Maximum

167458BIKANER-NW

769.2

164480FATEHG-2

398.8

167459BHADLA PG

764.9

164460FATEHGARH

398.1

0.1

55.0

0.1

57.0

164459BHADLA PG

401.1

162498BHADLA-2

220.0

0.0

0.0

137703MOGA-PG

771.1

167774KHETRI

763.1

773.4

147704BHIWN-PG

761.5

160.3

160.3

156.0

400.2

62.7

109.1

164404BHADLA

402.2

146.7

14.2

146.5

4.6

4.6

149.5

2.2

149.5

2.2

219.30.0

759.8

164774KHETRI

402.3

175.4

17.8

58.8

17.8

58.8

34.1

59.2

34.1

59.2

162359BHADLA-PG

220.8

0.0

30.0

162397ADANI

220.8

0.0

2.9

0.0

2.9

162398SOURYA

220.8

0.0

2.9

0.0

2.9

162399ESSEL

221.3

0.0

9.3

0.0

9.3

912.7

127.8

904.1

129.7

338.2

71.1

361.2

81.5

403.8

985.9

68.1

762.9 36.9

14.8

579.8

106.3

165.5

60.0

19.1

116.4

167498BHADLA-2

770.9

332.0

12.3

0.0

0.0

0.0

164498BHADLA-2

400.0

33.9

102.1

162480FATEH-2

164451JAIPUR_RS

90.7

167417AJMER-NW

122.7

780.3

154463JHATIKALA-PG

397.8

100.3

157708JHATI-PG

164458BIKANER-NW

TO KANKROLI

164417AJMER-NW

166.1

TO BHINMAL

162458BIKANER

167773JAIPURR

407.5

146.5

TO BHILWARA

TO DEENWANA TO HEERAPURA

TO BIKANER(RVPN)

TO BAP

TO BADISID

TO KANASAR

405.5

134423MOGA

TO KOTPUTLI

156.0

220.1

TO Gr. NOIDA

TO BAMNOLI

TO DWARKA

TO Sikanderabad

TO JALJIVI

167.2

TO KASHIPUR

TO MURADABAD

TO LUCKNOW

TO SHAHAJAHANPUR

TO MEERUT

TO BARELY(UP)

TO MANESAR

TO MERTA

TO MERTA

TO SOHAWAL

177707MERUT-PG

TO LUCKNOW

TO RAMPUR

TO NOIDA

TO JAWAHARPUR TPS

TO CHITTORGARH

TO ANTA

TO GWALIOR

TO BABAI

TO DHANONDA

TO PATNA

TO NAUBATPUR

TO BIHAR SHARF

TO MAU

TO RASRA

TO TALWANDI SABO

TO JALANDHAR

TO NOKADAR

TO FATEHBAD

TO KISHENPUR

TO HISSAR

TO HISSAR

TO MAHARANIBAGH

TO GOPALPUR

TO BASSI

TO BASSI

TO TEHRI POOL(FSC)

TO MUNDKA

TO AGRA

TO SIKAR

TO BHIWANI

Transmission Scheme for Rajasthan SEZ PH-II

TO GURGAON

403.2

164110JAISALMER-2

16.9

46.8

237.6

310.9

16.9

164403RAMGARH

398.9

157.0

10.9

157.0

10.9

164401AKAL-4

401.0

46.8

39.2

46.8

39.2

172.2

42.2

164402BARMER-4

403.5

53.2

31.2

51.6

37.8

15.8

59.9

407.0

108.6

56.5

406.4

89.2

103.7

27.6

18.7

40.2

4.7

8.0

30.8

366.5

86.3

157.7

73.4

157.7

73.4

25.2

25.7

25.2

25.7

642.0

202.5

46.8

402.8

28.8

38.2

24.8

82.8

400.0

34.9

11.6

164461RAMG-II

400.8

119.0

76.4

119.1

33.6

400.0

31.4

2.4

31.4

2.4

164921BHIWADI

400.0

47.9

10.7

3.7

8.4

230.4

9.8

230.4

9.8

103.2

46.4 102.9

46.6

115.2

166.9

36.9

166.9

36.9 113.4

0.3

298.3

69.5

3.3

167.2

3.3

174483BAREILY

404.4

104.0

274.2

118.8

167.2

38.9

10.7

47.9

63.3

59.8

63.3

59.8 132.8

42.0

37.1

118.8

68.4

119.0

164434JODH KANKANI

401.6

164757POKARAN

229.6

19.1

229.6

19.1

237.7

45.0

45.0

237.7

758.5

130.9

94.3

125.5

98.2

87.0 36.9

36.9

87.0

9.8

15.3

9.8

15.3

44.7

15.1

231.7

89.2

231.7

89.2

134325MALKANA

399.7

469.1

5.7

401.0

300.4

61.1

88.0

18.5

22.6

111.1

22.6

32.8

25.6 143.2

58.7

164495BIKANER-II

174266GNOIDAUP

399.6

678.3

45.2

258.9

29.2

258.9

29.2

108.3

14.3

108.3

14.3

28.1

3.1

28.1

3.1

54.3

613.4

100.2

613.4

100.2394.2

657.0

490.2

52.7

167.2

12.3

174410BAREL-PG

404.5

52.0

137.4

52.0

137.4

107.5

18.6

108.6

18.2

93.4

81.8

55.9

105.5

105.5

93.4

81.8

55.1

18.5

55.1

18.5

4.0

12.1

4.0

12.1

61.0

8.8

34.9

37.1

34.9

37.1

76.3

83.8

165.5

60.0

55.9

154708JHATIKARASP

161.0

191.847.3

8.4

47.3

8.4

8.5

44.1

54.9

79.0

164433JODH SURPURA

164430PACHPADRA

406.1

162.9

79.8

0.9

46.0

89.2

103.7

79.6

109.5

119.6

127.7

134.3

45.4

154501NARELA ISTS

394.7

868.3

47.2

281.3

2.4

281.3

2.4

152.7

26.4

152.7

26.4

174475BAL74-PG

400.0

1085.8

31.1

78.4 50.7

78.4

267.0

13.8

267.0

13.8

235.0

59.2

20.7

50.7

75.5

52.1 75.5

52.1

164445NEEMR-PG

50.7

235.0

59.2

3.1

3.0

3.1

3.0

111.1

134438MOGA SPLT

164413RAJWEST

24.8

82.8

164497SIKAR NEW

401.2

255.5

17.7

127.5

58.3 127.5

58.3

450.6

22.4

766.3

6.7

88.8

159.7

158.3

189.7

28.2

15.0

95.3

159.7

158.3

15.0

95.3

88.8

6.7

28.2

139.7

100.5

100.5

139.7

167480FATEH-2

35.0

343.2

157.1

528.9

50.7

87.550.7

343.2

766.9

15.0

95.3

15.0

95.3

189.7

26.6

519.2

87.5

415.0

4.9

157.1

80.6

67.780.6

67.7

772.6

167799JODH KANKANI

281.1

34.1

281.1

177265GNOIDAUP

765.5

483.0

68.4

677.3

228.4

925.5

219.2

664.2

48.1

177806BAREILLY

157001NARELA ISTS

753.4

266.8

144.7

170.7

63.4

170.7

63.4

260.3

282.3

34.1

167497SIKAR NEW

768.0

8.7

111.78.7

111.78.7

111.7

8.7

111.7

177718RAMPUR_765

10.0

487.4

145.1

119.6

145.1

119.6

467.3

124.7

177882KANPURPG

177258ORAI

778.8

410.5

26.9

605.9

46.8605.9

46.8

272.7

62.0

695.5

128.7

221.5

220.5

36.3

510.1

47.2

332.2

14.7

38.0

30.3

272.5

32.4

22.1

231.9

23.9

162361RAMG-II

220.5

220.0

0.0

0.0

0.0

0.0

0.0

0.0

0.0

711.7

41.7

219.1

161.6

0.0

0.0

168.3

9.6

13.1

37.1

3.7

37.1

3.7

75.1

6.5

58.0

3.1

162285BHADLA-S

312.2

5.2

213.5

162403RAMGARH_RE

219.9

595.6

91.5R

139.5

162280AKAL-2

220.0

770.7

164416AJMER

408.3

21.4R

177512ALIGARH

8.4

132.1

12.0

4.1

18.4

6.1

132.1

23.9

8.7

161047BHADLA

161240KHETUSAR

27.1

250.8

125.3

21.7

250.8

42.6

0.5

94.4

161.2

44.8

0.0

157.942.6

162495BIKANER-2

177706AGRA-PG

137.6

267.3

137.6

267.3

15.7

41.315.7

41.3

15.7

41.3

15.7

41.3

1006.2

506.8

962.0

514.7

1006.2

506.8

962.0

514.7

0.0

-21.9

L10.0

124.2

L20.0

124.2

0.0

91.8

L10.0

125.0

L20.0

125.0

0.0

-21.9

1

60002130
Text Box
EXHIBIT-II(B) Peak - Reduced RE