Transmission System Projects - Central Arizona … Transmission System Projects Robert Moody...
Transcript of Transmission System Projects - Central Arizona … Transmission System Projects Robert Moody...
1
Transmission System ProjectsRobert Moody Director, Field Maintenance
CAP Transmission Capital Projects
1. Palo Verde to Morgan 500 kV Project• Palo Verde to Sun Valley 500 KV Transmission Line• Sun Valley Substation 500/230 KV• Morgan to Sun Valley 500 KV Transmission Line
2. Hassayampa Tap to Sun Valley to Hassayampa Plant Project• Hassayampa Tap 230 KV Switchyard rebuild• Hassayampa Plant 230 KV Switchyard modifications• Hassayampa Tap 230 KV Transmission Line re-conductor
3. Electrical District (ED2) to Saguaro Transmission Line Project• Rebuild ED2 to Saguaro Transmission Line
4. Valencia Substation to Black Mountain Spreader Yard Project• Black Mountain to Valencia Substation 115 KV Transmission Line • Valencia Substation Upgrades
FAP Agenda Number 4.
2
Palo Verde-Morgan 500 kV Project
• Project allows CAP to convey energy directly from NGS toCAP loads without having to contract-and pay-for capacityover other systems since there is a gap in the CAP system.
• Project improves reliability of the CAP transmission system byproviding a shorter direct line to the Hassayampa Pump Plantas well as providing an injection point into the Liberty/ParkerTransmission line which serves the western pump plants.
• Project provides direct link between Arizona’s primary tradinghub, Palo Verde, and Navajo Southern Transmission system.
• Project was approved at the February 7, 2013 CAWCD Boardmeeting for $40,524,300.
• CAWCD is a 10% owner of the project.
Palo Verde to Sun Valley Substation
Palo Verde
Delaney
Sun Valley
Hassayampa
4
Palo Verde - Sun Valley Transmission Line
Palo Verde to Morgan Project Schedule
Transmission Projects Schedule 2016 2017 2018 2019
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar
ED2 to Sagauro Rebuild Project (610475)
EA Study, Design, Spec
Purchase Equipment (GFE)
Construction Contract
Construction (ED2 to Picacho)
Summer Break
Construction (Picacho to Red Rock)
Summer Break
Construction (Red Rock to Saguaro)
Complete
Palo Verde to Morgan Project
Palo Verde to Delany
Delany to to Sun Valley
Sun Valley Substation
Morgan to Sun Valley
Hassayampa Tap Project (610480)
Develop
Design
Procurement
HAT Construction
HAP Construction
Sun Valley to HAP
Sun Valley to HAT
5
Palo Verde to Morgan Budget
CAP Transmission Projects Through 12/31/2015
2016 Forcast
Remaining Balance
Total Projected
Total Spending Authority Variance $ Variance %
Palo Verde to Morgan 500 KV Transmission Line Project $18,739.6 $1,800.9 $10,099.9 $30,639.5 $29,054.6 ($1,584.9) ‐5.5% A
Hassayampa Tap to Sun Valley to Hassayampa Plant 230 KV $1,363.3 $2,292.7 $9,083.7 $12,739.7 $13,545.5 $805.8 5.9%
Hassayampa Plant Breakers and Switchyard Modifications $0.0 $0.0 $1,000.0 $1,000.0 $2,500.0 $1,500.0 60% B
Transmission Line Rebuild ED2 to Saguaro $5,119.3 $2,280.3 $3,955.6 $11,355.2 $11,015.0 ($340.2) ‐3.1% C
Valencia Substation to Black Mountain Spreader Yard $0.0 $0.0
( A ) The full project variance is due to a change requirement from galvinized to painted steel poles on the on the Morgan to Sun Valley segment of the transmission line and the
addition of a 500 KV breaker position at Sun Valley Substation.
( B ) The full project variance is due to recent changes in the project scope and design
( C ) We current expect this project to complete at or just under budget
Hassayampa Tap 230 kV Project
• Project necessary to connect Palo Verde - Morgan 500 KVTransmission Line to the existing CAP Transmission System
• Project includes construction of new Hassayampa Tapswitchyard to include more robust protection systems
• Project connects Hassayampa Tap to Sun Valley Substationand re-conductors line. The existing towers are sufficient.
• Project connects Hassayampa Plant to Sun Valley Substation
• Project requires modification of the 230 KV Switchyard atHassayampa Pump Plant
• Project approved at the February 5, 2015, CAWCD Boardmeeting for $14,120,237.
• Western Area Power Administration is the Project Manager
7
Hassayampa Tap Project Schedule
Transmission Projects Schedule 2016 2017 2018 2019
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar
ED2 to Sagauro Rebuild Project (610475)
EA Study, Design, Spec
Purchase Equipment (GFE)
Construction Contract
Construction (ED2 to Picacho)
Summer Break
Construction (Picacho to Red Rock)
Summer Break
Construction (Red Rock to Saguaro)
Complete
Palo Verde to Morgan Project
Palo Verde to Delany
Delany to to Sun Valley
Sun Valley Substation
Morgan to Sun Valley
Hassayampa Tap Project (610480)
Develop
Design
Procurement
HAT Construction
HAP Construction
Sun Valley to HAP
Sun Valley to HAT
Hassayampa Tap Project Budget
CAP Transmission Projects Through 12/31/2015
2016 Forcast
Remaining Balance
Total Projected
Total Spending Authority Variance $ Variance %
Palo Verde to Morgan 500 KV Transmission Line Project $18,739.6 $1,800.9 $10,099.9 $30,639.5 $29,054.6 ($1,584.9) ‐5.5% A
Hassayampa Tap to Sun Valley to Hassayampa Plant 230 KV $1,363.3 $2,292.7 $9,083.7 $12,739.7 $13,545.5 $805.8 5.9%
Hassayampa Plant Breakers and Switchyard Modifications $0.0 $0.0 $1,000.0 $1,000.0 $2,500.0 $1,500.0 60% B
Transmission Line Rebuild ED2 to Saguaro $5,119.3 $2,280.3 $3,955.6 $11,355.2 $11,015.0 ($340.2) ‐3.1% C
Valencia Substation to Black Mountain Spreader Yard $0.0 $0.0
( A ) The full project variance is due to a change requirement from galvinized to painted steel poles on the on the Morgan to Sun Valley segment of the transmission line and the
addition of a 500 KV breaker position at Sun Valley Substation.
( B ) The full project variance is due to recent changes in the project scope and design
( C ) We current expect this project to complete at or just under budget
8
ED2 to Saguaro Rebuild Project
• ED2 to Saguaro serves Brady, Picacho, Red Rock. The line was built in 1984 and has experienced numerous age and reliability issues costing over $750,000 over the past 5 years.
• Project replaces 35.6 miles of conductor and 400 wood poles with 252 steel poles
• Construction begins in Q4 2016 and is scheduled to complete in Q1 2019.
• Project approved at the May 2, 2013, CAWCD Board meeting for $11,785,000
• Western Area Power Administration is the project manager
ED2 to Saguaro Rebuild Project
10
ED2 to Saguaro (Steel Poles)
ED2 to Saguaro Project Schedule
Transmission Projects Schedule 2016 2017 2018 2019
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar
ED2 to Sagauro Rebuild Project (610475)
EA Study, Design, Spec
Purchase Equipment (GFE)
Construction Contract
Construction (ED2 to Picacho)
Summer Break
Construction (Picacho to Red Rock)
Summer Break
Construction (Red Rock to Saguaro)
Complete
Palo Verde to Morgan Project
Palo Verde to Delany
Delany to to Sun Valley
Sun Valley Substation
Morgan to Sun Valley
Hassayampa Tap Project (610480)
Develop
Design
Procurement
HAT Construction
HAP Construction
Sun Valley to HAP
Sun Valley to HAT
11
ED2 to Saguaro Project Budget
CAP Transmission Projects Through 12/31/2015
2016 Forcast
Remaining Balance
Total Projected
Total Spending Authority Variance $ Variance %
Palo Verde to Morgan 500 KV Transmission Line Project $18,739.6 $1,800.9 $10,099.9 $30,639.5 $29,054.6 ($1,584.9) ‐5.5% A
Hassayampa Tap to Sun Valley to Hassayampa Plant 230 KV $1,363.3 $2,292.7 $9,083.7 $12,739.7 $13,545.5 $805.8 5.9%
Hassayampa Plant Breakers and Switchyard Modifications $0.0 $0.0 $1,000.0 $1,000.0 $2,500.0 $1,500.0 60% B
Transmission Line Rebuild ED2 to Saguaro $5,119.3 $2,280.3 $3,955.6 $11,355.2 $11,015.0 ($340.2) ‐3.1% C
Valencia Substation to Black Mountain Spreader Yard $0.0 $0.0
( A ) The full project variance is due to a change requirement from galvinized to painted steel poles on the on the Morgan to Sun Valley segment of the transmission line and the
addition of a 500 KV breaker position at Sun Valley Substation.
( B ) The full project variance is due to recent changes in the project scope and design
( C ) We current expect this project to complete at or just under budget
Valencia to Black Mountain Spreader Yard
• Provides for construction of a 2.7 mile 115 KV transmissionline from Arizona Electric Power Cooperative’s (AEPCO)Valencia Substation to CAP Black Mountain Spreader Yard.
• Improves reliability of the CAP transmission system byproviding a secondary 115 KV loop feed to the Tucson Bpumping plants from the Valencia Substation.
• Project eliminates need to address the .7 mile gap in theRattlesnake to Del Bac Transmission Line and eliminates theneed for Del Bac Switchyard.
• Project was approved at the August 4, 2016 Board meetingfor $1,785,000 and AEPCO will serve as the project manager.