Transmission system of Georgia and its regulationand its ...
Transcript of Transmission system of Georgia and its regulationand its ...
Georgian National Energy and Water Supply Regulatory CommissionGeorgian National Energy and Water Supply Regulatory Commission (GNERC)
Transmission system of Georgia and its regulationand its regulation
Irma Kavtaradze
1
Commissioner, GNERC
The Transmission Grid of Georgiag
The transmission grid of Georgia includes all transmission facilities operating above 110kV, including substations and transmission lines, also electricity circuits operating at 35 and 110kV, and relevant substations that are specifically identified in the Transmission License p yand are used for the system and inter-system transit of electricity. Other lines at 35 and 110 kV networks shall be part of distribution facilities.
Ministry of Energy of Georgia approves the list of transmission lines used for system and inter-system transit of electricity;used for system and inter system transit of electricity;
2
Transmission LicenseesTransmission Licensees
Transmission of Electricity is performed by two transmission y p ylicensees:
- “Sakrusenergo”, JSC“Sakartvelos Sakhelmcipo Electrosistema” LTD (Georgian State- Sakartvelos Sakhelmcipo Electrosistema , LTD (Georgian State Electricity System)
In the nearest future, one more transmission licensee will be established, as a construction of a new 500/400 kV Black Sea transmission line has begun.
Electricity Transmission Licensee“S k ” JSC“Sakrusenergo” JSC
Established in 1996
50% - state property, 50% - “Russian Electricity System”50% state property, 50% Russian Electricity System
Assets:500kV t i i li 871 k- 500kV transmission lines – 871 km
- 330kV transmission lines – 21 km
- 220kV transmission lines – 12 km
5
Total transmission lines – 904 km
Electricity Transmission Licensee“Sakartvelos Sakhelmcipo Electrosistema” LTDS ve os S e c po ec os s e
(Georgian State Electricity System)
Established in 2002100% state propertyAssets:
- 500kV substations -3 - 330kV substations -1- 220kV substations -17
110kV b t ti 24- 110kV substations -24 - 35 kV substations -44
220kV transmission lines 1 609 km- 220kV transmission lines – 1,609 km- 110kV transmission lines - 863.4 km- 35kV transmission lines – 537.4 km
Total transmission lines– 3,009.8 kmTotal substations - 89
Dispatch Licensee“Sakartvelos Sakhelmcipo Electrosistema” LTD
GSE DispatchDispatch of
E ESCOS k
p(Georgian State Electricity System)
neighboring countriesE ESCOSakrusenergo
e.p.j. sadispetCeroEnergo pro Dispatch Telavi Dispatch Generation companies
Telasi DispatchCommercial/industrial companies
International Energy Company Dispatch
Georgian Railways dispatch
Black Sea 500/400 kv Transmission Grid
The owner of the 500/400kV transmission grid is “Energotransi” LTD
100%-shareholder of the “Energotransi” LTD is State Electricity System of Georgia (GSE) LTD
“Energotransi” LTD is responsible for fulfillment of the project of the 500/400kV transmission grid g
8
Black Sea 500/400 kV Transmission Grid Assets/
400 kV transmission line “Meskheti” (34 km)
500 kV transmission line “Vardzia” (188km)
500 kV transmission line “Zekari” (59km)
500/400/220 kV substation Akhaltsikhe
10
Project ActivitiesProject Activities
Construction of 400 kV transmission line “Meskheti” from Akhaltsikhe to the border of TurkeyCompleting the construction of 500 kV transmission line “Vardzia”Completing the construction of 500 kV transmission line Vardzia from substation “Gardabani-500”Completing the construction of 500 kV transmission line “Zekari” f b i “Z h i 500”from substation “Zestaphoni-500”Construction of 400 kV DC line and the back-to-back converter station
11
Project Objectivej j
Strengthening of Georgia’s 500 kV transmission system
Ensuring proper export infrastructure for extra electricity produced in Georgia
Ensuring necessary infrastructure for energy trading in the Caucasus Regioneg o
12
Expected results of 500/400 kv Transmission Grid
Progress in stabilization of Georgia’s Transmission GridSupport of Georgia’s energy security Stimulating local production of clean energyExport Georgia’s excess hydro power to the high value
kmarkets Ability of neighboring countries to transit electricity through Georgiathrough Georgia
13
Existing Conditions in Cross-Border Trade of El t i itElectricity
The basic direction of export –Turkey (spring-summer period of hydro power overflow). Recently, exports to Russia and Armenia h l b t bli h dhave also been establishedThe basic direction of import – Russia, Azerbaijan (fall-winter peak periods)pe ods)Transit of electricity has not been realized yet.
14
Export-Import Is Fulfilled through the Inter-system of Transmission LinesInter system of Transmission Lines
Inter-system transmission lines:y- 500kV transmission line ”Kavkasioni”- 330kV transmission line ”Gardabani”- 220kV transmission line ”Alaverdi”- 220kV transmission line ”Adjaria”
220kV transmission line ”Salkhino” (Russian occupied)- 220kV transmission line Salkhino (Russian-occupied)- 110kV transmission line ”Dariali”- 110kV transmission line ”Djava” (Russian-occupied)j ( p )- 110kV transmission line ”Lalvari”- 110kV transmission line ”Ninotsminda”
15
Georgian Energy System 220-500 kV net map-scheme
soxumhesi
soxumi
kavkasioni
pirobiTi aRniSvnebi:
500kv qvesadgurebi
220kv qvesadgurebi
lajanurhesi
vardnilhesi
IV III II I
I II
tyvarCelsresi
engurhesi
zugdidi 110kv -
dariali
k q g
110kv qvesadgurebi
Tbosadgurebi
hidrosadgurebi
500kv egx-ebi
500kv egx-ebi perspeqtiva
330kv egx
220kv egx-ebi
110k bi
varcixehesebi
gumaThesi
rionhesi
Saorhesi
Zevrulhesi
wyaltubo
varcixehesi
IV III II I
menji
d. quTaisi Jinvalhesi
gorixaSuri
d. zestafoni
zahesi
java
yazbegi
110kv egx-ebi
awhesi
qsani
baTumi
gurjaani
d. navTluRi
didube
lisi 220
rusTavi 220
gldani
orTaWalhesi
azenergo
xofa
alazanhesi
awhesi
Tbilsresimarneuli
xramhesi I
xramhesi II sadaxlo weva 110
Nninowmimda 110
borCxa
16
Existing Abilities For Capacity Flow From G i T N i hb i E S tGeorgia To Neighboring Energy Systems
Neighbor Energy system
Inter-system connections Maximum capacity, MW
Name of transmission lines
Nominal circuit, kv export import
Russia
kavkasioni 500 600 600
salkhino 220 50 110
nakaduli 110 30 30
dariali 110 40 25
java 110 10 10
Azerbaijan gardabani 330 320 320
l erdi 220 150 170
Armenia
alaverdi 220 150 170
lalvari 110 25 20
ninotsminda 110 20 20
Turkey adjaria 220 150 120
17
Turkey adjaria 220 150 120
Total existing capacity: export – 1395 MW import – 1425 MW
Export-Import Dynamics, 2005 – 2010Export Import Dynamics, 2005 2010
Electricity import in 2005‐2010 (thousand kwh)
1400000
16000001398638
1000000
1200000
1400000
777568649048
400000
600000
800000 433264
254802 277800
0
200000
2005 2006 2007 2008 2009 2010
18
Electricity export, 2005‐2010. (thousand kwh)
1 158 7001200000000
629470 679559 749 429800000000
1000000000
400000000
600000000
2006
82 642
2007 2008 2009 20100
200000000
19
2010
Regulation of the transmission activityRegulation of the transmission activity
Ministry of Energy Regulator (GNERC)Ministry of EnergyIssues Electricity (capacity) Market Rules, which regulate functioning of the electricity
Regulator (GNERC)Issues licenses (transmission, dispatch, etc.)Monitors licenseesfunctioning of the electricity
market…, Technical, commercial and legal issues with regard to electricity transmission,
Monitors licenseesApproves tariff methodology and sets tariffs (transmission, dispatch etc )y ,
dispatch…., import, export, parallel operation of energy systems, etc.
dispatch, etc.)Solves disputes between the licensees, and licensees and consumersconsumers
Regulation of transmission activitiesRegulation of transmission activities
Licenses TariffsLicensesTransmission and dispatch licenses shall be issued for
TariffsTransmission and dispatch tariffs shall be set per kWh
indefinite termElectricity import activity can be carried over by any
as a fixed rateImport tariffs shall be calculated according to thecan be carried over by any
person without licenseElectricity export activity
calculated according to the formula, set by the regulator
can be carried over by any person without license
Export tariffs are deregulated
Third party accessThird party access
Transmission licensee is obliged to transport electricity of entities g p ythat are authorized to sell electricity to customersFor this activity, transmission licensee shall charge the tariff, set by th l tthe regulatorCurrently, existing transmission lines in Georgia are underutilizedand only a theoretical probability exists that congestion will occur in a d o y a t eo et ca p obab ty e sts t at co gest o w occuthe near future. Consequently, there are no congestion management rules yet, but it i f h h l ill b i d d i hi h lis foreseen that such rules will be introduced within the next couple of years
Connection to the GridConnection to the Grid
Fee for the connection to the transmission grid shall be setFee for the connection to the transmission grid shall be set by the regulator
Such fee shall be paid to the transmission licensee
Fee shall be set individually for each connection
Transmission Tariffs (1)Transmission Tariffs (1)
Current tariff methodology in the electricity sector wasCurrent tariff methodology in the electricity sector was approved in 1998;
This methodology is based on the cost plus principle;
Incentive-based tariff methodology is in the process of development;development;
Transmission Tariffs (2)Transmission Tariffs (2)
Transmission Tariffs are set for the following voltageTransmission Tariffs are set for the following voltage groups: 500-330 kV, 220-110-35 kV and 10-6 kV;Transmission Tariffs shall be determined according to gpeak energy volumes to pass through the network;Value of normative losses are included in Transmission TariffsAmount of normative losses shall be set by the regulator
Transmission Tariffs (3)Transmission Tariffs (3)
Annual company revenue requirements are determinedAnnual company revenue requirements are determined during tariff setting;All reasonable expenses, related to the licensed activity, shall be included in the revenue requirement and, thus, in the tariffRequested Revenue includes the following components:EExpenses; Taxes; Profit;Profit;
TransitTransit
The Law on Electricity and Natural Gas does not extend toThe Law on Electricity and Natural Gas does not extend to interstate transitGNERC is not charged to regulate interstate transit g gRevenues from transit shall be taken into account when setting transmission tariffsg
Thank You For Your Attention
Irma KavtaradzeCommissionerCommissioner
Georgian National Energy and Water Supply Regulatory Commission26 Chechelashvili streetKutaisi 4600, Georgia
28