Training Report_khasa Kothi

download Training Report_khasa Kothi

of 33

Transcript of Training Report_khasa Kothi

  • 8/2/2019 Training Report_khasa Kothi

    1/33

    JAIPUR DEVELOPMENT AUTHORITY

    TRAINING REPORT

    ON

    KHASA KOTHI FLYOVER

    Submitted by:

  • 8/2/2019 Training Report_khasa Kothi

    2/33

    JDA at a Glance

    Strengthening Faith: Jaipur Development Authority

    Jaipur Development Authority (JDA) has been committed to workingfor the benefit of the citizens of Jaipur with planned implementation

    of development schemes and is consistently striving to take Jaipur at

    higher levels of progress. Jaipur is one of the most well-planned

    cities of its times and planned development has always been central

    to its ideology.

    Jaipur Development Authority came into existence by the

    Government of Rajasthan with a vision to combat and manoeuvre

    the growing requirements of a large city in wake of the increasing

    population and to help give Jaipur a planned look compatible and

    comparable to any metropolitan city of repute. JDA was authorised

    powers and a green signal to speed up the development and

    progressive growth of the entire city to rapidly change the face of

    Jaipur. To meet these important needs JDA sprang into action and

    started to understand the necessary needs of the city.

    According to the requisites, JDA has been working towards time-bound construction, creation and development of the western part of

    Jaipur based on major scientific and hi-tech strategies. Thus, Jaipur

    has been beautified intensively to augment the tourist attraction in

    the city and to raise the living standards to suit convenience of its

    citizens.

    The major undertaking of JDA includes the following:

    * Infrastructural development of Jaipur region by construction of

    flyovers, bridges, parking places.

    * Development of commercial projects and residential schemes,

    etc.

    * Development of basic amenities like community centres, parks,

    ring roads.

    * Development and rehabilitation of kacchi bastis etc.

  • 8/2/2019 Training Report_khasa Kothi

    3/33

    * Preparation and implementation of master plan.

    * Preparation and implementation of guidelines for colonisation.

    * Environmental development by planning and implementing

    roadside plantations and by developing eco-friendly schemes.

    * Development of rural area around Jaipur.

    * Development of transport facilities like Mass Rapid

    * Transport System (MRTS), Transport Nagar, and major sector

    roads.

    According to the promises and commitments of the Rajasthan

    Government, JDA has been time and again proving itself as a pioneer

    of development, creating a state-of-the-art city of substance. JDA

    has been working on widening all main roads, construction of over

    bridges, under bridges and flyovers to regulate the traffic on roads,

    minimize pollution, and ensure public convenience and safety. JDA

    firmly believes in bridging the gap and reaching out to its citizens

    and to provide them with quick and hassle-free service.

    JDA...where town planning is a tradition.

  • 8/2/2019 Training Report_khasa Kothi

    4/33

    Contents

    1. Introduction

    2. Components of flyover

    i) Foundation

    ii) Piers and abutments

    iii) Deck

    iv) Pre-stressed concrete

    v) Backfill and Reinforced earth wall

    3. Test reports

  • 8/2/2019 Training Report_khasa Kothi

    5/33

    KHASA KOTHI FLYOVER

    INTRODUCTION

    The Khasa Kothi flyover is being constructed at one of the busiest

    traffic junction in jaipur city. The flyover is being constructed on the

    road connecting the railway station to Sindhi Camp bus stand to

    facilitate the easy movement of traffic plying from station to Chandpole, M.I. road & Banipark area. The cost of project is Rs. 22.0 Crore

    and length of fly over 740.0 Mts.

    The work was commenced after the stone laying on 30.10.06. The

    work was stopped due to order passed by Honble high court on

    8.2.07 for maintaining status quo. This order was declared non

    operative by Honble high court on 30.05.07 and work restarted

    thereafter.

    The work worth Rs. 6.50 Crore has been done by 20th April 2009. The

    super structure work is in progress and 80% of reinforced earth wall

    panel has been casted. The work is proposed to be completed by

    August 2009.

    Salient Features

    Project Cost : Rs. 2200.00 Lacs

    Agency : M/s Harish Chandra (I) Ltd.

    Consultant : Span Consultant Pvt Ltd.,

    Delhi

    Work order amount : Rs.19,63,69,312.00

    Stipulated date of commencement : 15.04.2006

  • 8/2/2019 Training Report_khasa Kothi

    6/33

    Stipulated date of completion : 14.10.2007

    Work Period : 18 Months

    Date of Start : 30.10.2006

    Physical Features

    Total Length : 740 Mts.

    Total Width : 16.75 Mts.

    Width of Roads : 2 X 7.5 Mts. (2 lanes each)

    Median Width : 1.00 Mts.

    Via Duct Length : 455 Mts.

    Approaches : 285 Mts.

    Nos. of Spans : 14

    Service Roads : 5.5 Mts. On either side

    The grade of concrete used in the construction is M-50.

  • 8/2/2019 Training Report_khasa Kothi

    7/33

    SOME IMPORTANT THINGS!!!

    1) Always wear a good quality helmet on the

    site.

    2) Always wear shoes on the site.

    3) Wear safety belts if required.

    4) Safety nets should be provided wherever it is

    necessary.

  • 8/2/2019 Training Report_khasa Kothi

    8/33

    MAJOR COMPONENTS OF FLYOVER

    FOUNDATION

    Since the bridge has to carry a big live load and its dead weight is

    also very large so we cannot go for simple foundation but pile

    foundation.

    Pile foundation is one type of deep foundation. It is used where the

    good soil is at higher depth (10 or 15m) or soil having low bearing

    capacity. Pile is also used for tall structures. In pile foundation the

    load coming from the super structure is taken by pile cap and

    equally distributed in no of piles, pile transfers this load into the soil.

    The Khasa Kothi flyover consists of 115 bored cast in situ piles with

    14 pile caps.

    The diameter of each pile is 1200 mm with depth 25 meters and

    different piers have different set of group of piles.

    Pile group under A1,P2,P3,P11,P12 and A2

  • 8/2/2019 Training Report_khasa Kothi

    9/33

    Pile group under P1,P4,P10 and P13 Pile group under

    P8

    Pile group under P5,P6 and P9 Pile group under P7

    A1 and A2 are Abutment 1 and 2; P1,P2,P3.. are Pier no 1,2,3..

    The depth of pile cap is 2 m which is 500 mm below ground level.

  • 8/2/2019 Training Report_khasa Kothi

    10/33

    INSTALLATION PROCEDURE OF PILES

    Step 1 --- Excavation of Pile Shaft

    The bored pile equipment set including hydraulic oscillator, hydraulic

    vibrator, hammer grab and rock chisel used in this project is very

    common and being widely used for shaft excavation.

    a. Set out the correct position of the bored pile on site.

    b. Excavate about 3 - 4m of the pile to remove shallow

    obstructions and then backfill, wherever necessary.

    c. Install the bottom section of temporary casing of required

    diameter into the ground by oscillating and jacking or byvibrating motion exerted by the oscillator and the vibrator

    respectively.

    d. Set up hydraulic oscillator or vibrator in conjunction with a

    crawler crane.

    e. Excavate within the casing by hammer grab and redrive the

    steel casing simultaneously by using the heavy duty casing

    oscillator / vibrator. Rock chisel in various types will beemployed for removal of obstruction or hard materials during

    the above process.

    f. Extend the steel casing by bolting or welding on additional

    casing during the excavation.

    g. Water will be pumped into the casing during excavation and

    constant water head will be maintained so as to prevent any

    ingress of material from the bottom of casing.

    h. Verticality of the casing will be monitored by means of spirit

    level from time to time.

    i. Continue the above procedure until the founding level of pile

    has been reached .

    j. Pile base enlargement will be formed by employing a bellout

    chisel or a reverse-circulation drill as indicated in the workingdrawings.

  • 8/2/2019 Training Report_khasa Kothi

    11/33

    Step 2 --- Cleaning of Pile Shaft

    Final cleaning will be carried out by the air-fitting method using high

    pressure air compressors. The slime and muddy water within the

    casing will be cleared and delivered into a desilting tank before

    discharge.

    Step 3 --- Tremie Concreting

    a. The pile shaft will be concreted by "Underwater Tremie

    Technique". The tremie pipe sections will be inserted and be

    jointed until it reaches the bottom of pile shaft. Concrete will be

    poured into the tremie pipe by using a concrete skip.

    Concreting will be carried out in one continuous operation until

    the required level has been reached.

    b. As concreting proceeds, the level of the concrete relative to theground level will be monitored by measuring with weighted

    tape after each skip of concrete is placed.

    c. The base of the tremie pipe will be kept with a minimum depth

    of approximate 1 to 2m below the surface of the concrete.

    d. The temporary casing will be extracted simultaneously by the

    oscillator in the course of concreting. A head is always

    maintained between the top of concrete and the bottom ofsteel casing.

  • 8/2/2019 Training Report_khasa Kothi

    12/33

    Step 4 --- Installation of Reinforcement

    After the completion of concreting, dowel bars of required length

    and numbers will be installed into the pile shaft and down to the

    predetermined level before the extraction of bottom steel casing.

    PIERS & ABUTMENTS

    The Khasa Kothi flyover has 15 piers including two abutments.

    The maximum height of the pier is about 6 m.

    http://www.cse.polyu.edu.hk/~ctpile/insta/i-bpile/i-tc1.jpg
  • 8/2/2019 Training Report_khasa Kothi

    13/33

    A typical Expansion joint used in bridge

    DECK

    The Khasa Kothi bridge is of box girder type bridge which is

    comprised of prestressed concrete. The box is typically of

    trapezoidal in cross-section. Compared to I-beam girders , box

    girders have a number of key advantages and disadvantages.

    Box girders offer better resistance to torsion, which isparticularly of benefit as the bridge deck is curved in plan.

  • 8/2/2019 Training Report_khasa Kothi

    14/33

    Additionally, larger girders can be constructed, because thepresence of two webs allows wider and hence stronger flanges

    to be used. This in turn allows longer spans.

    On the other hand, box girders are more expensive to fabricate,and they are more difficult to maintain, because of the need for

    access to a confined space inside the box.

    The span length is of range of 25 m to 50 m.

    The box girders are made of concrete and were casted in place

    using falsework supports. First 75 m span is of solid type deck and

    then it consists of box girders i.e. from A1 to P3 and P11 to A2 the

    deck is solid with the depth 1.2 m.

    The depth of box girder is different as per load requirement. From P3

    to P6 and P9 to P11 it is 2.2 m and from P6 to P9 it is 2.5 m.

    The slope of the deck is 1 in 29 m. The total width of the deck is

    16.75 m including 1m wide median and two crash barrier of width

    0.375 m.

  • 8/2/2019 Training Report_khasa Kothi

    15/33

    Reinforcement pattern for box girder.

    Pre-stressed Concrete

    The technique of pre-stressing eliminates cracking of concrete under

    all stages of loading and enables the entire section to take part in

  • 8/2/2019 Training Report_khasa Kothi

    16/33

    resisting moments. As dead load moments are neutralized and the

    shear stresses are reduced, the sections required are much smaller

    than in reinforced concrete.

    Prestressing can be accomplished in three ways: pre-tensionedconcrete, and bonded or unbonded post-tensioned concrete.

    Pre-tensioned concrete

    Pre-tensioned concrete is cast around already tensioned tendons.

    This method produces a good bond between the tendon and

    concrete, which both protects the tendon from corrosion and allows

    for direct transfer of tension. The cured concrete adheres and bonds

    to the bars and when the tension is released it is transferred to theconcrete as compression by static friction. However, it requires stout

    anchoring points between which the tendon is to be stretched and

    the tendons are usually in a straight line. Thus, most pretensioned

    concrete elements are prefabricated in a factory and must be

    transported to the construction site, which limits their size. Pre-

    tensioned elements may be balcony elements, lintels, floor slabs,

    beams or foundation piles.

    Bonded post-tensioned concrete

    Bonded post-tensioned concrete is the descriptive term for a method

    of applying compression after pouring concrete and the curing

    process (in situ). The concrete is cast around plastic, steel or

    aluminium curved duct, to follow the area where otherwise tension

    would occur in the concrete element. A set of tendons are fished

    through the duct and the concrete is poured. Once the concrete has

    hardened, the tendons are tensioned by hydraulic jacks that reactagainst the concrete member itself. When the tendons have

    stretched sufficiently, according to the design specifications (see

    Hooke's law), they are wedged in position and maintain tension after

    the jacks are removed, transferring pressure to the concrete. The

    duct is then grouted to protect the tendons from corrosion. This

    method is commonly used to create monolithic slabs for house

    construction in locations where expansive soils (such as adobe clay)

    create problems for the typical perimeter foundation. All stresses

  • 8/2/2019 Training Report_khasa Kothi

    17/33

    from seasonal expansion and contraction of the underlying soil are

    taken into the entire tensioned slab, which supports the building

    without significant flexure. Post-tensioning is also used in the

    construction of various bridges; both after concrete is cured after

    support by falsework and by the assembly of prefabricated sections,

    as in the segmental bridge.

    The advantages of this system over unbonded post-tensioning are:

    1. Large reduction in traditional reinforcement requirements as

    tendons cannot destress in accidents.

    2. Tendons can be easily 'weaved' allowing a more efficient

    design approach.

    3. Higher ultimate strength due to bond generated between the

    strand and concrete.

    4. No long term issues with maintaining the integrity of the

    anchor/dead end.

    Unbonded post-tensioned concrete

    Unbonded post-tensioned concrete differs from bonded post-

    tensioning by providing each individual cable permanent freedom of

    movement relative to the concrete. To achieve this, each individual

    tendon is coated with grease (generally lithium based) and covered

    by a plastic sheathing formed in an extrusion process. The transfer

    of tension to the concrete is achieved by the steel cable acting

    against steel anchors embedded in the perimeter of the slab. Themain disadvantage over bonded post-tensioning is the fact

    that a cable can destress itself and burst out of the slab if

    damaged (such as during repair on the slab).

  • 8/2/2019 Training Report_khasa Kothi

    18/33

    The advantages of this system over bonded post-tensioning are:

    1. The ability to individually adjust cables based on poor field

    conditions (For example: shifting a group of 4 cables around an

    opening by placing 2 to either side).

    2. The procedure of post-stress grouting is eliminated.

    3. The ability to de-stress the tendons before attempting repair

    work.

    In Khasa Khothi flyover the method used for pre-stressing is

    unbonded post tensioning system. In this system first of all high

    tensile steel cables/wires (also known as strands or tendons)

    encased in sheathing pipes were laid as per design and then

    concreting is done. After the hardening of concrete the stretching of

    wires was done by means of hydraulic jacks. The jacking was done

    from both ends. The wires were jacked a few percent above their

    specified initial pre-stress in order to minimize creep in steel and toreduce frictional loss of pre-stress.

    The wires are anchored to concrete after stretching by wedge action

    producing a friction grip on wires.

  • 8/2/2019 Training Report_khasa Kothi

    19/33

    Cables left for stressing before concrete is poured

    We can see that the cables are in a grouped in every pipe. In the

    above picture there are 19 cables in one group.

  • 8/2/2019 Training Report_khasa Kothi

    20/33

    Sheathing pipes carrying cables.

    We can see in above picture that the cables are curved as per

    design requirement.

  • 8/2/2019 Training Report_khasa Kothi

    21/33

    Stretching of cables by hydraulic jack after hardening of concrete

    The jack used in above picture has the capacity to stretch 4 cables

    at a time. This jack can perform both operations i.e. stretching of

    wire as well as tightening of wedges.

  • 8/2/2019 Training Report_khasa Kothi

    22/33

    Calibrated pressure gauge to read directly the amount of tension

    applied

    It is however the practice to measure the elongation of steel so that

    the magnitude of pre-stress can be calculated independently and

    checked against the gauge reading.

  • 8/2/2019 Training Report_khasa Kothi

    23/33

    Covering of cables after grouting

    The cables are covered by concrete to prevent corrosion. The

    grouting is done through the hole as seen in above picture (in red

    circle) and then the hole is then bolted as shown (in blue circle).

  • 8/2/2019 Training Report_khasa Kothi

    24/33

    PROBLEMS LIKELY TO CAUSE DURING OR AFTER CONCRETING

    1. Segregation : Segregation of concrete can be defined as

    separation of coarse aggregate from mortar, resulting in their

    non-uniform distribution. Improper mix proportion resulting in

    large proportion of coarse particles as compared to small

    proportion of fine particles caused the separation of coarse

    particles from mortar. Segregation is also caused by incorrect

    handling of mixed concrete during transportation and

    placement, and also by over-compaction.

    2. Honeycombing : The separation of coarse aggregate frommortar leaves voids in coarse aggregate unfilled and this

    phenomenon is called honeycombing. Honeycombing causes

    decrease in the density of concrete and hence reduction in the

    strength of the concrete.

    3. Bleeding : Bleeding is a form of segregation in which water in a

    concrete mix rises to the surface during placing it. It is because

    more water is present than is necessary for the cement pasteto lubricate the aggregate particles and the solid constituents

    of the mix are able to hold all the mixing water when they

    settle down. Thus the water rises up and appears on the

    surface of the compacted concrete. Sometimes, finer particles

    such as cement are also carried with the rising water. The

    water trapped by the superimposed concrete results in a

    porous weak and the non-durable concrete. If the rising water is

    trapped on the underside of reinforcement, then a zone of poorbond is created. This water form voids on evaporation and

    makes the concrete weaker.

    PRECAUTION TO BE TAKEN DURING PLACING OF CONCRETE:

    1. Under no circumstances, the water should be added to the

    concrete during its passage from mixer to the formwork

  • 8/2/2019 Training Report_khasa Kothi

    25/33

    2. The formwork or the surface which is to receive the fresh

    concrete should be properly cleaned prepared and well-

    watered.

    3. As far as possible, the concrete should be placed in singlethickness. In case of deep sections, the concrete should be

    place in successive horizontal layers and proper care should be

    taken to develop enough bonds between successive layers.

    4. The concrete should be thoroughly worked around the

    reinforcement and tapped in such a way that no honeycombed

    surface appears on removal of the formwork.

    5. The concrete should be place on the formwork as soon as

    possible.

    6. During placing, it should be seen that all edges and corners of

    concrete surface remain unbroken, sharp and straight in line.

    7. The placing of concrete should be carried out uninterrupted

    between predetermined construction joints.

    CONSOLIDATION OF CONCRETE:

    The main aim of consolidation of concrete is to eliminate air bubbles

    and thus to give maximum density to the concrete.

    In Khasa Kothi flyover the Internal or Immersion vibrators are used

    for consolidation of concrete. These vibrators consist of a steel tubewhich is inserted in fresh concrete. This steel tube is called the poker

    and it is connected to an electric motor. The poker vibrates while it

    is being inserted. The internal vibrators should be inserted and

    withdrawn slowly and they should be operated continuously while

    they are being withdrawn. Otherwise holes will be formed inside the

    concrete.

  • 8/2/2019 Training Report_khasa Kothi

    26/33

    BACKFILL AND REINFORCED EARTH WALL

    Reinforced earth is a composite material formed by the friction

    between the earth and the reinforcement. By means of friction the

    soil transfers to the reinforcement the forces built up in the earth

    mass. The reinforcement thus develops tension and the earth

    behaves as if it has cohesion. Reinforced members are composed of

    thin wide strips also called as ties.

    For reinforcement the GI strips are used which are 40 mm wide and

    5 mm thick and the length varies as according to the tensile stresses

    at various place and levels.

    The facing elements for backfill are precast concrete panels having

    dimension 1.5m x 1.5m with some aesthetic appearance.

    The dry density of the compacted soil was kept 1.85 to 1.9 gm/cc

    and the moisture content was kept at 8 to 9%.

    Procedure

    Place and compact initial lifts of select Granular backfill up to bottom

    row of panel tie strips. The level of the compacted backfill should be

    50mm above the tie strips. In order to avoid pushing the brace

    panels out of alignment, initial lifts of backfill are neither placed nor

    compacted against the back of the panels. Compact each backfill lift

    using a large smooth-drum vibratory roller except within a 100 cm

  • 8/2/2019 Training Report_khasa Kothi

    27/33

    zone directly behind the panels where a small hand-operated

    vibratory compactor must be used to avoid undue panel movement.

    After compaction has taken place, check wall alignment visually and

    with a level adjust panels as necessary.

    A drainage system is made near panels by laying 20mm coarse

    aggregates near panels up to a width of 60 cm throughout the depth

    and at the bottom a semi perforated pipe is used to drain out the

    water.

    Immediate gradation and moisture testing is required if either

    excessive panel movement or backfill pumping occurs during

    construction.

    Compaction: Large smooth-drum vibratory rollers are used to

    accomplish mass compaction of backfill materials, except for fine

    sands.

    Sheep foot rollers are never to be used for compaction of backfill.

    Fine uniform sands, which contain more than 60 percent passing a425 sieve used for backfill, must be compacted using a smooth

    drum static roller.

    Vibratory compaction equipment should not be used to compact fine

    uniform sands.

    Moisture content of backfill material during placement should be

    approximately 1% to 2% more than its optimum moisture content.

    Reinforcing Strips:-

    Place reinforcing strips on the compacted backfill. Position strips

    perpendicular to the facing panels, unless otherwise shown on the

    plans. Reinforcing strips are supplied in lengths as shown on plans.

    Connect each reinforcing strip to the embedded panel tie strip by

    inserting the end of the reinforcing strip into the gap between the

    two exposed ends of the tie strip. Match the three holes and push a

  • 8/2/2019 Training Report_khasa Kothi

    28/33

    bolt through the holes from below, threading on a nut and

    tightening.

    Dump backfill onto the reinforcing strips so that the toe of the

    backfill pile is 3-4 ft from the panels. Spread the backfill by pushingthe pile parallel to the panels.

    Metal tracks of earthmoving equipment must never come in contact

    with the reinforcing strips. Rubber-tired vehicles, however, can

    operate directly on the exposed strips if backfill conditions permit

    and care is exercised.

    At the joints of panels a special type of semi permeable textile

    known as geo-textile is used to stop the backfill from slipping out ofthe panels.

  • 8/2/2019 Training Report_khasa Kothi

    29/33

    Spreading of backfill

    In the above picture we can see the arrangement of panels. No

    binding material is used to join the panels they are interlocked with

    each other.

  • 8/2/2019 Training Report_khasa Kothi

    30/33

  • 8/2/2019 Training Report_khasa Kothi

    31/33

    GRADATION FOR COARSE AGGREGATE

    TYPE OF AGGREGATE 20mm Date:- 30-05-09

    TOTAL WEIGHT TAKEN 2922 Gms

    SieveSize

    WeightRetained

    %Retained

    %Cumulative

    Retained

    %Passing Remarks

    25 0 0.00 0.00 100.0020 172 5.89 5.89 94.1110 2662 91.10 96.99 3.01

    4.75 68 2.33 99.32 0.68Pan 20

    TYPE OF AGGREGATE 10mm Date:- 30-05-09

    TOTAL WEIGHT TAKEN 2957 Gms

    SieveSize

    WeightRetained

    %Retained

    %Cumulative

    Retained

    %Passing Remarks

    12.5 0 0.00 0.00 100.0010 268 9.06 9.06 90.94

    4.75 2514 85.02 94.08 5.922.36 120 4.06 98.14 1.86Pan 55

    SieveSize

    For 20 mm For 20 mm

    Combined

    Grading

    As per IS 383

    %Passing

    %Passing

    %Passing

    %Passing

    Lower

    LimitUpperLimit

    20 100% 63% 100% 37%10 94.11 59.29 100 37.00 96.29 95 100

    4.75 3.01 1.90 90.94 33.65 35.54 25 55Pan 0.68 0.43 5.92 2.19 2.62 0 10

  • 8/2/2019 Training Report_khasa Kothi

    32/33

    GRADATION FOR COARSE AGGREGATE

    TYPE OF AGGREGATE SAND Date:- 30-05-09

    TOTAL WEIGHT TAKEN 531 Gms

    Sieve

    Size

    Weight

    Retained

    %

    Retained

    %Cumulati

    veRetained

    %Passin

    g

    Remark

    s

    Zone II

    4.75 12 2.26 2.26 97.74 90-100

    2.36 28 5.27 7.53 92.47 75-100

    1.18 65 12.24 19.77 80.23 55-90

    0.6 190 35.78 55.56 44.44 35-59

    0.3 157 29.57 85.12 14.88 8-30

    0.15 69 12.99 98.12 1.88 0-10

    PAN 10

    AS PER IS 383 SAND IS IN ZONE II

  • 8/2/2019 Training Report_khasa Kothi

    33/33