Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head...

21
www.csn.es 8 th Meeting of the Representatives of Competent Authorities Early Notification and Assistance Conventions 6-10 June 2016 IAEA -Vienna 1 Eighth Meeting of the Representatives of Competent Authorities Early Notification and Assistance Conventions Vienna, 6 10 June 2016 Training and Exercises in Spain Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN

Transcript of Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head...

Page 1: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

1

Eighth Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

Vienna, 6 – 10 June 2016

Training and Exercises in Spain

Juan Pedro GARCIA CADIERNO

Head of Emergency Operations Coordination

Nuclear Safety Council

SPAIN

Page 2: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Requirements2

1.- GSR Part 7 (IAEA)

Requirement 25: Training, drills and exercises for emergency preparedness and

response

The government shall ensure that personnel relevant for emergency response shall take

part in regular training, drills and exercises to ensure that they are able to perform their

assigned response functions effectively in a nuclear o radiological emergency.

2.- Nuclear Emergency Plan (RD 1546/2004)

Title IV: “Preparedness for nuclear emergency response : effective implementation

for the level of external response and maintenance their effectiveness”

The object is to achieve and maintain adequate preparation to act in emergency

situations. This will require a program to develop and implement systematically:

theoretical and practical training of the responders

Page 3: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Training on Nuclear Emergencies (NPP Personnel)3

Training in emergencies let to the Emergency Response Organization to maintain

an adequate grade in emergency preparedness and response

Also, training probes and upgrades the emergency procedures

To do this, a set of scheduled actions is made (Drills & Courses). Its cover specific

and partial aspects of the On-site and Off-site Emergency Plan.

Page 4: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Annual Theoretical Training in NPP4

Name Duration

Initial training course 5 h

Training on DBA 14 h / 4 h

Training on Severe Accidents 21 h / 7 h

Radiological Surveillance (Plant & Personnel) 4 h / 2 h

Surveillance on-site 2 h / 2 h

Basic training on Radiological Surveillance Plan in Emergencies 5 h / 5 h

Radiological Consequences Assessment 14 h / 2 h

Sampling in Emergencies 7 h / 2 h

Additional training on Radiological Surveillance Plan in Emergencies 35 h / 35 h

Page 5: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Drills on Emergencies in NPP5

1. Assessment, identification and classification of initiating events.

2. Communications and notifications.

3. Assistance to affected workers. First aids and decontamination.

4. Assessment and radiological surveillance of the Emergency.

a) Off-site Radiological Assessment.

b) Radiological surveillance of the personnel and the plant.

c) On-site radiological surveillance.

5. Sampling in emergencies.

6. Headcount and Access Controls.

7. Coordination with authorities, external support center and other services.

8. Fires

9. Severe Accident Management Guides

10. Activation of the on duty organization

Page 6: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

ORE’s Training (Nuclear Safety Council)6

• Level 1– Objective: To know Emergency Response Organization (ERO) and Emergency Action

Plan (EAP)

– Recipients: All CSN’s members

– Responsible: SEP

• Level 2– Objective: To know ERO, EAP, Regulations and Emergency Plans

– Recipients: ERO’s members

– Responsible: SEP

• Level 3– Objective: To know tools and procedures of each operational groups

– Recipients: Operational Groups members

– Responsible: Heads of Operational Groups

• Seminars for the Chairman and Commissioners of the CSN

Page 7: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Military Unit for Emergencies Training7

It exists a protocol of collaborationbetween UME and UNESA (Union ofElectrical Companies) to act in somespecial cases of emergency situationwhere it can be ordered it interventioninside the nuclear power plant

Page 8: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Off-Site Drills8

In coordination with personnel of the Direction of Emergency (Government Delegation), the

Radiological Intervention Unit of the CSN makes some drill in each Off-Site Nuclear Emergency

Plan

These drills are focused in:

1. Control access

2. Actions in Classification and Decontamination Stations

The drills have an annual periodicity, and a calendar is stablished at the beginning of each year

Page 9: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Examples of Off-Site Nuclear Emergency Drills9

During 2015 different exercises on the five off-site nuclear emergency plans in activities primarily related to

radiological controls access and classification and decontamination stations were performed by the

Radiological Group of the Off-Site Plan.

Some of these exercises were developed in collaboration with other operating groups of off-site plans, such as

the Group of Citizen Public Order and Safety for control access drills; and the Health Group and Municipal

Organizations in classification and decontamination stations drills.

Also, in several occasions the drills were preceded by sessions prior to acting training group.

DRILL ECD DRILL CA

PEN Date and Place Participation UAIR Date Participation UAIR

PENBU 22 de noviembre (M. de Ebro) 10 de mayo x

PENCA 1 de julio (Trujillo) x 16 de junio x

PENGUA 16 de marzo (Sacedón) 6 de octubre

PENTA 16 de febrero (Amposta) x 14 de septiembre x

PENVA 29 de noviembre (Ayora) 27 - 28 septiembre

4 - 5 de octubre

Page 10: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

On-Site NPP Exercises10

In order to verify the operability of the On-Site Emergency Plan, it’s must performed an exercise once

per year and nuclear power plant.

During the realization of annual exercise, activities will take place to check the availability of

resources in different areas:

Evaluation and classification of events.

Notification and communication to SALEM & CECOP.

Activation of External Technical Support.

Notice to personnel and measures of protection and assistance.

Monitoring and evaluation of the simulated events.

Corrective actions required for the development of the simulation.

Exercise Plan includes a sequence with scheduled times to check the performance staff and

implementing procedures and methods provided.

Page 11: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Control Access Drills11

Page 12: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Radiological Control Access12

Page 13: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Logistic Device for Radiological Control Access13

Page 14: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Classification and Decontamination Stations14Entrance

Triage

Classification Decontamination

Men

Decontamination

Women

Dressing

room

Shower Baths

Waste

Store

Store

Dressing

room for

first

responders

women

Office

Exit to waiting area

No classification

Clean

Contaminated

Legend

Shower Baths

Dressing

room

Waste

Store

Dressing

room for

first

responders

men

Page 15: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Radiological surveillance drills in CDS15

Page 16: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Internal Dosimetry Mobile Unit16

Page 17: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Recollection of liquid radioactive waste Drill17

Page 18: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Surveillance & Decontamination of Responders18

Page 19: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Decontaminations of vehicles19

Page 20: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

NPP Exercise Calendar20

Nuclear

InstallationShort description of the exercise

El CabrilPit overflow drains Auxiliary Conditioning Building. There is a leakage outside this building. During control operations, the contamination

of a person occurs.

Vandellós IIIt’s based on an event of loss indicator panels in the Control Room. This event is coincident with a major fire motivated by a transient

stage negatively evolve to loss of containment integrity and large external radiological impact.

Sta. Mª de

Garoña

Fire involving the cooling capacity of the fuel pool, whose integrity will be compromised by falling load. The event will declare PEI

Category II and to perform various mitigation strategies, during which workers become injured and contaminated externally and

internally.

TrilloIt’s based on a physical security incident affecting the NSSS and requires entry in SAMGs. The evacuation of site personnel and

activation of the new emergency management center will be made.

José CabreraFire in the area under control of the operator, with a duration greater than 10 minutes, which affects areas containing radioactive material

and causing environmental levels of radioactive contamination

Almaraz

Based on an accident affecting the NSSS its evolution leading to core melt into one unit, and use of the Extensive Damage Mitigating

Guidelines. There is radioactive release to the atmosphere. The follow up of the CSN for this emergency will be from the backup SALEM

(SALEM-2)

Juzbado Earthquake it is affecting the installation, causing release of radioactivity to the outside, with several injured workers

Ascó

Long-term scenario will be developed the relief from some positions of emergency management is foreseen (NPP and SALEM). The

initiating event is a LOOP, affecting both units and that one of them will progress to SBO, with core melting, loss of containment and

release of radioactive material to the atmosphere. In this exercise, the activation and participation of the UME is expected.

CofrentesThe initiating event is a LOCA .It is expected radiological to environment. In this exercise, the use of extensive damage mitigation

guidelines is also expected.

Page 21: Training and Exercises in Spain - Nucleus Documents/CAM 2016... · Juan Pedro GARCIA CADIERNO Head of Emergency Operations Coordination Nuclear Safety Council SPAIN. ... Category

www.csn.es

8th Meeting of the Representatives of Competent Authorities

Early Notification and Assistance Conventions

6-10 June 2016

IAEA -Vienna

Exercise in SALEM-221

The layout of SALEM-2 is not the same

than the SALEM, but its functionalities

are the same