Training 1 01

download Training 1 01

of 37

Transcript of Training 1 01

  • 8/2/2019 Training 1 01

    1/37

    Simulation Based Production

    Planning, Scheduling, andControl

    Johannes Krauth

    Sim-Serv

  • 8/2/2019 Training 1 01

    2/37

    Overview

    Planning Steps

    Methods Applied

    The Contribution of SimulationExamples

    The Future

  • 8/2/2019 Training 1 01

    3/37

    Planning Steps

    Production Programme Planning /

    Plant or Process Design

    (time horizon: years)Production Planning (months / weeks)

    Detailed Scheduling (days / hours)

    Control

  • 8/2/2019 Training 1 01

    4/37

    Overall Planning Objectives

    Maximise Capacity Utilisation

    Minimise DelaysMinimise Throughput Times

    Minimise Work in Progress

    Note: Conflicting Objectives!!

  • 8/2/2019 Training 1 01

    5/37

    Facility Planning

    Based on assumed demand

    Searches optimal match of needed

    and available capacityPlanning horizon: years

    Not an ongoing activity

  • 8/2/2019 Training 1 01

    6/37

    Optimal Match

    Needed per year:

    10,400 h milling

    ______________

    8,500 h welding

    Available per year:

    4 machines = 5376 h

    (1 shift, 80% utilis.);

    = 10752 h (2 shifts)

    __________________

    4 workers = 8400 h5 workers = 10080 h

    ?

  • 8/2/2019 Training 1 01

    7/37

    Limitations

    no interdependencies taken intoaccount

    based on estimated / experienceddegrees of capacity utilisation

    adequate for strategic, long-termplanning, when little information isavailable

  • 8/2/2019 Training 1 01

    8/37

    Production Planning

    Based on (expected) customer orders

    Using fixed throughput times per step

    (based on experience or assumptions)Accepts / rejects orders and fixes startand end dates

  • 8/2/2019 Training 1 01

    9/37

    Example: Assumed and Real Durations

    Department Estimated

    Throughput Time

    Process

    Time

    Lathing 20 days 1 hour

    Machining 5 days 20 hours

    Surface Treatm. 7 days 1.5 hours

    Polishing 7 days 10 hours

    Assembly 15 days 20 hours

    Total 54 days 52.5 hours

  • 8/2/2019 Training 1 01

    10/37

    Limitations

    Capacity assumed available

    Actual shop floor status not taken into

    accountWaiting times included and thereforefixed

    Applicable only when long deliverytimes are acceptable

  • 8/2/2019 Training 1 01

    11/37

    Production Scheduling

    Planning Horizon: 1 week 1 day

    Based on confirmed orders and

    actually available resourcesMust take into account technicalrestrictions

    Finds exact sequence of operations perwork station

  • 8/2/2019 Training 1 01

    12/37

    Production Scheduling

    Must be fit for reality!

  • 8/2/2019 Training 1 01

    13/37

    Contribution of Simulation

    Detailed models

    Exact representation of all processes,

    all needed resourcesRealistic transition times, based oncurrent shop floor status

    All kinds of rules and constraints canbe taken into account

  • 8/2/2019 Training 1 01

    14/37

    Ways to Use Simulation:

    MRP /ERP

    System

    Simulation Modelcontrols

    feeds

    back

    1. Offline, from outside

  • 8/2/2019 Training 1 01

    15/37

    Ways to Use Simulation

    2. Online, as part of planning toolbox

    MRP / ERP System:

    Long Term Planning Module_____________________

    Medium Term Planning Module___________________

    Scheduling Module:Simulation Model

    Shop Floor

  • 8/2/2019 Training 1 01

    16/37

    Typical Leitstand / APS tool

  • 8/2/2019 Training 1 01

    17/37

    Contribution of Optimisation

    Can use a large variety of criteria foroptimal solutions

    Finds very good schedules quicklyTakes away hours of routine work fromthe planners

    Allows them to focus on the essentials

  • 8/2/2019 Training 1 01

    18/37

  • 8/2/2019 Training 1 01

    19/37

    Examples

    2 Examples: Simulation helps optimise

    planning tool and process4 Examples: Simulation andOptimisation modules as part ofplanning toolbox

  • 8/2/2019 Training 1 01

    20/37

  • 8/2/2019 Training 1 01

    21/37

  • 8/2/2019 Training 1 01

    22/37

  • 8/2/2019 Training 1 01

    23/37

  • 8/2/2019 Training 1 01

    24/37

  • 8/2/2019 Training 1 01

    25/37

  • 8/2/2019 Training 1 01

    26/37

  • 8/2/2019 Training 1 01

    27/37

  • 8/2/2019 Training 1 01

    28/37

  • 8/2/2019 Training 1 01

    29/37

  • 8/2/2019 Training 1 01

    30/37

  • 8/2/2019 Training 1 01

    31/37

  • 8/2/2019 Training 1 01

    32/37

  • 8/2/2019 Training 1 01

    33/37

  • 8/2/2019 Training 1 01

    34/37

  • 8/2/2019 Training 1 01

    35/37

  • 8/2/2019 Training 1 01

    36/37

    Conclusion from Examples:

    Broad range of industry sectors

    Leitstand / APS tools can complementexisting MRP / ERP tools or run stand-alone

    Typical benefits include Higher capacity utilisation

    Less WiP

    Less delays, shorter throughput times Payback often within a few months!!

  • 8/2/2019 Training 1 01

    37/37

    Summary

    Simulation Based Scheduling andControl offers substantial advantages

    Many approaches available for differentspecial requirements

    Also useful for SMEs

    Sim-Serv assists with selection of bestsuited approach