Tracking behaviour in time of the bridge over the Danube ...
Transcript of Tracking behaviour in time of the bridge over the Danube ...
![Page 1: Tracking behaviour in time of the bridge over the Danube ...](https://reader030.fdocuments.net/reader030/viewer/2022012602/6198c8ba82bdbc75d428411b/html5/thumbnails/1.jpg)
Tracking behaviour in time of the bridge over the Danube - Black Sea
Channel from Cernavoda
DUMITRU ONOSE , ADRIAN SAVU,
AUREL NEGRILĂ
Faculty of Geodesy
Technical University of Civil Engineering Bucharest
B-dul Lacul Tei, nr. 122-124, sector 2, Bucharest
ROMANIA
[email protected]; [email protected]; [email protected]
Abstract: The article presents the theoretical considerations in the tracking behaviour of bridges and their
application in practice. For the bridge over the Danube-Black Sea Channel from Cernavoda was made a
tracking network consisting of 9 studs and 5 marks, and in the bridge structure: pillars, ledges, decks were
embedded 130 tracing marks. The results of the first stage of measurement are also presented.
Key-Words: Monitoring, Geodetic, Tracking Network, DATUM, Fischer Test, STUDENT (“t”) Test
1 Introduction The bridge over Danube-Black Sea Channel in
Cernavoda (Fig. 1) was inaugurated in 2003 as an
objective of vital importance for the city of
Cernavoda and as any work of art it requires
tracking behaviour and creating a tracking network.
Fig. 1
2 General principles In general, the network design principles are
applicable to the tracking network and the special
characteristics that must be followed further on are:
the results that depend on the period of observation,
the major features that are the precision of points,
not the characteristics of the points themselves. We
must make the distinction between support points
and object points, the networks having limited
scope and being dependent on the existence of
areas with stable points.
Outside the followed target, better said, outside the
deformation target a number of support points must
be present which can be considered in terms of
technique and construction as stable. In this case
we speak about an absolute tracking model, if the
movements of construction are determined from the
outside support points.
The number and the arrangement of the network
tracking points are given by certain rules that
should be set according to the specific problem of
tracking; the goal is to solve the following issues:
the choice of representative points and the
delimitation of the field influenced by deformation.
Equally important as the choice of the
representative points is the setting time (time of
observation). For stabilizing the moment of
measurements we must study the annual
movements that can be caused by the water level or
the variation of temperature and the possible daily
movements resulting from temperature. Choosing
randomly the moments of measurement for
deformation, has led, after a few steps, to a wrong
practice model; practice showed that such
measurements must be determined vith a view to be
included in the maximum and minimum stages of
the construction. The bridge from Cernavoda is
composed of three independent parts, i.e.: the
viaduct on the right bank, the viaduct on the left
bank and the main bridge (metal) (Fig. 1). The
viaduct on the right bank sits on the ledge and two
pillars, the viaduct on the left bank sits on the ledge
and seven pillars, the main bridge sits on the last
Proceedings of the 11th WSEAS International Conference on Sustainability in Science Engineering
ISSN: 1790-2769 207 ISBN: 978-960-474-080-2
![Page 2: Tracking behaviour in time of the bridge over the Danube ...](https://reader030.fdocuments.net/reader030/viewer/2022012602/6198c8ba82bdbc75d428411b/html5/thumbnails/2.jpg)
pillar of each viaduct. To create the tracking
network of the time behaviour of the bridge, in the
bridge stable areas were planted six studs with
concrete foundation, three studs embedded in the
infrastructure of the pillars (fig. 2), and five marks
of reinforced concrete type A.
In the platform of support the studs were embedded
by levelling benchmarks (Fig. 3).
The object points have been materialized in parts of
the bridge (ledges, pillars, decks, the main metal
structure) by tracking marks with a diameter of 50
mm (Fig. 4).
On the pillars number 2, 3, and 4, the right bank
pillar and the left bank pillar, were placed four
tracking marks, two on the up stream face and two
on down stream face. On the pillars 1, 5, 6 and 7
were placed four tracking marks on the channel
side. On the two ledges were placed four marks on
the superior part, where the decks merge. On the
nine decks of the viaducts were placed forty
tracking marks, thirty on the left bank viaduct and
ten on the right bank viaduct (fig.5) The position of
tracking marks was chosen to define the possible
movements and deformations which may occur in
the constructive elements of the bridge. On the
main bridge were installed 16 tracking marks, eight
down stream and eight up stream (Fig. 6) taking
into consideration its metal structure and the fact
that much higher deformations and movements
may appear in comparison with other elements of
the bridge.
LEDGE 2
PILLAR 1LEDGE 1
Dan
ube - B
lack S
ea
PILLAR 1LEDGE 1
PILLARLEFT BANK
PILLAR 1LEDGE 1
Ch
an
nel
PILLAR 1
PILLAR 7
PILLAR 7
PILLAR 2
PILLARRIGHT BANK
PILLAR 3
PILLAR 5PILLAR 4
PILLAR 6
PILLAR 3PILLAR 2 PILLAR 5 PILLAR 6PILLAR 4 LEDGE 2
PILLAR 7PILLAR 5 PILLAR 6
RIGHT BANKPILLAR
RIGHT BANKPILLAR
LEFT BANKPILLAR
LEFT BANKPILLAR
PILLAR 2 PILLAR 3 PILLAR 4 PILLAR 5 PILLAR 6 PILLAR 7 LEDGE 2
Fig. 2
Fig. 3
Fig. 4
Fig. 5
Proceedings of the 11th WSEAS International Conference on Sustainability in Science Engineering
ISSN: 1790-2769 208 ISBN: 978-960-474-080-2
![Page 3: Tracking behaviour in time of the bridge over the Danube ...](https://reader030.fdocuments.net/reader030/viewer/2022012602/6198c8ba82bdbc75d428411b/html5/thumbnails/3.jpg)
A8V
A4VA5V A3V A2V
A7V
A6V
A1V
A8M
A4MA5M A3M A2M
A7M
A6M
A1M
Fig. 6
3 Principles of measurement There are two distinct possibilities in determining
the constructions movements and strains:
a. with measuring devices installed inside the
building;
b. with measuring devices installed outside the
building.
In the second case the measurements will be
reported to a network of fixed points located
outside the influence zone of factors acting on the
object pursued and the land on which it is located.
Through this process we determine absolute values
of horizontal or vertical movements, in this
category also entering the geodesic methods.
To realize the tracking network for the bridge of
Cernavoda the last method was used:
measurements of horizontal directions and zenith
angles of each stud were performed to the visible
tracking marks with a total station Leica TCR
1102; the difference between the levelling marks
embed in the studs with NI 007 level. In Fig. 7 the
planimetric tracking network is shown in which the
measured directions and ellipse errors obtained
after processing are highlighted, and in Fig. 8
altimetry tracking network, with routes and
levelling closure in polygons are presented.
Proceedings of the 11th WSEAS International Conference on Sustainability in Science Engineering
ISSN: 1790-2769 209 ISBN: 978-960-474-080-2
![Page 4: Tracking behaviour in time of the bridge over the Danube ...](https://reader030.fdocuments.net/reader030/viewer/2022012602/6198c8ba82bdbc75d428411b/html5/thumbnails/4.jpg)
Dan
ube - B
lack S
ea
Ch
an
el
Fig. 7
Main Bridge
P1C1
PF2
1.5501 - level difference (m)
- number of stations
- polygon closure (m)
1
Right Bank Viaduct
-21.08938
CUI
PF1
2- 4
.121
21.55011
PMD
-5.3
55
73
4.04
18
10
24.8939
PF3
PA5
1. 6
29
42
3
PF4
P4P3P2 - 1.4123
BA11
4.2788
Left Bank Viaduct
4.2
705
2.91431
4
PF8
PMS
2.04
874
1
BA142
P7
10.39
89
P5
C2
2.2
252
2
1.3180
PA6
Dan
ube
- B
lack
Sea
Ch
ann
el
- 2.91831
0.9
534
- 4.4
923
BA9
2
1
PF7
2
BA13
BA12
4- 7.5373
STUD
MARK
Fig. 8
4 Results of measurements
Measurements made at the t0 were processed
independently for planimetry and altimetry by
using indirect measurements. The results obtained
from processing are:
Proceedings of the 11th WSEAS International Conference on Sustainability in Science Engineering
ISSN: 1790-2769 210 ISBN: 978-960-474-080-2
![Page 5: Tracking behaviour in time of the bridge over the Danube ...](https://reader030.fdocuments.net/reader030/viewer/2022012602/6198c8ba82bdbc75d428411b/html5/thumbnails/5.jpg)
1. for planimetry
Number of points of the network 15
Mode of compensation network free
Horizontal directions measured 62
Zenith angles measured 62
Average standard deviation “a
priori” 1 cm
Average standard deviation “a
posteriori” 0.65 cm
STANDARD
DEVIATION
Min. Max. Average
on X 0.18 0.86 0.47
on Y 0.24 0.62 0.39
(cm) (cm) (cm)
2. for levelling
Number of points of the network 15
Mode of compensation network free
Difference level measured 62
Zenith angles measured 42
Average standard deviation “a
priori” 1 mm
Average standard deviation “a
posteriori” 1.01 mm
STANDARD
DEVIATION
Min. Max. Average
0.28mm 0.89mm 0.61mm
After performing the measurements for stage t1,
with global matching test we can determine
whether the network, measured at different stages,
forms or not congruent figures. The difference
between the network parameters points to
determine the two stages of measurement must fall
within a "safety limit", being based on the
empirical standard deviation of measurements. If
this difference does not fall within the "safe limit",
the comparison indicates that the network has
deformations.
For both stages of the same measure provisional
coordinates should be introduced with a view to
refer to the same DATUM.
After processing the measurements we obtain the
following items which will be used to the global
matching test:
- t0 phase measurements:
1
∧
X +−
= 1
1
1 NQxx 01s (1)
- t1 phase measurements:
2
∧
X +−
= 2
1
2 NQxx 02s (2)
1
∧
X = Vector of parameters in stage t0
2
∧
X = Vector of parameters in stage t1
1xxQ = Cofactor matrix in stage t0
2xxQ = Cofactor matrix in stage t1
01s = Empirical standard deviation in stage t0
measurements
02s = Empirical standard deviation in stage t1
measurements
Determination of movements and deformations will
be done under the scheme below.
4.1 Global matching test: ∧∧
−= 12 XXd (3)
21 xxxxdd QQQ += (4)
+++= 21 NNQdd (5)
2
02
2
010 sss +±= (6)
2
0sh
dQdF dd
T
⋅
⋅⋅=
+
(7)
d = Discrepancy vector
Qdd = Cofactor matrix of the model of deformation
0s = Empirical standard deviation of the model of
deformation
F = Calculated Fischer test value
h = Rank of the Qdd matrix
Etapa 1 Etapa 2
11,LL
QL 22 ,
LLQL
2
01111 ,,,ˆ sfQX xx
2
02222 ,,,ˆ sfQX xx
ddQd ,
TG≡
Da Nu
Localizare Stop
DATUM
Stage 1 Stage 2
Localization
NO YES
Proceedings of the 11th WSEAS International Conference on Sustainability in Science Engineering
ISSN: 1790-2769 211 ISBN: 978-960-474-080-2
![Page 6: Tracking behaviour in time of the bridge over the Danube ...](https://reader030.fdocuments.net/reader030/viewer/2022012602/6198c8ba82bdbc75d428411b/html5/thumbnails/6.jpg)
Decision of the Fischer test: F = Calculated Fischer test value
Flim = Theoretical value of Fischer test
α = confidence coefficient (safety threshold),
%5=α
1. If
α,,lim fhFFF =≤ ⇒ hypothesis )( 0H true (9)
=
∧∧
21 XEXE ⇒We don’t have
deformations (10)
2. If
α,,lim fhFFF => ⇒ hypothesis )( 0H false (11)
hypothesis )( 1H true (alternative hypothesis)
≠
∧∧
21 XEXE ⇒We have deformations(12)
Decision determined by the application test is true
within the safety threshold α. The global matching
test discloses that the two networks are matching or
not, if deformation exist, they were not emphasized
(not localized). The localization is made by
applying other specific statistical tests.
4.2 Locating deformations using STUDENT
TEST ( "t"):
This test checks each parameter of the vector d
and if the discrepancy falls within the safety limit
established.
jjj Qss0
= (13)
With the above formula we can determine the
practice of statistics "t" to point j.
j
j
js
dt = (14)
α−= 1,lim ftt (15)
js = Individual empirical standard deviation (each
point j)
jt = Calculated value of the localization
deformation test
limt = Theoretical value of the localization
deformation test
At this test the points that have the empirical
standard deviation smaller than the individual
standard deviation of the empirical model of
deformation are considered stable.
Decision of the test:
1. If
lim1, ttt fj =≤−α ⇒ hypothesis )( 0H true (16)
{ } 0=jdE ⇒ dj point considered stable (17)
2. If
lim1, ttt fj =>−α ⇒ hypothesis )( 0H false (18)
hypothesis )( 1H true (alternative hypothesis)
{ } 0≠jdE ⇒ dj point considered unstable (19)
This test is not quite stable (under the hypothesis
H0 should have most stable points),and it gives
good results if the number of points moved is much
smaller than the number of fixed points, the test not
taking into account also the correlations that
appear.
4.3 Locating deformations using Multiple
STATISTICAL TEST "F"
With this test we check the situation of each
component point of the network, whether or not the
points are moved.
k
k
kdy
dxd =
yykyxk
xykxxk
ddk QQ
QQQ = (20)
k = 1,2 ... n / 2
We calculate the test by analogy with the global
practice of matching statistics with the relationship:
22
0 ⋅=
+
s
dQdF
kddk
T
k
k (21)
k = 1,2 ... n / 2
Flim = F2,f,1-α (22)
Decision of the test:
1. If
Fk ≤ Flim = F2,f,1-α ⇒ hypothesis (H0) true (23)
E{dk} = 0 ⇒ k point is stable (24)
2. If
Fk > Flim = F2,f,1-α ⇒ hypothesis (H0) false (25)
- hypothesis (H1) true
E{dk} ≠ 0 ⇒ k point is unstable (26)
It gives good results when we have many stable
points, when we consider the coordinates of a point
and not take into account the correlation between
points, providing information about points and not
with the X, Y, H; it can be tested at several points
in the network, which forms a group.
Proceedings of the 11th WSEAS International Conference on Sustainability in Science Engineering
ISSN: 1790-2769 212 ISBN: 978-960-474-080-2