VOLUME-I ISSUE-11
November 2016
www.chennaimetrorail.org
CORRIDOR-I:
In Elevated section from Airport to Saidapet ramp,
track work completed for the entire elevated section
for the length of 18695m with 23 turnouts and
commissioned for passenger services.
In underground section between Saidapet
ramp to Washermenpet, track work in progress from
Saidapet Ramp to Nandanam.
Chairman
Thiru Rajiv Gauba, I.A.S.,
SecretaryMinistry of Urban DevelopmentGovernment of India
Track Progress as on 30/11/2016 (ATA-01)
Track concreting in progress between Saidapet ramp to
Saidapet station
Track concreting in progress between Saidapet ramp to Saidapet
station
CORRIDOR-II:
DEPOT :
Track work completed for entire depot length of 14606m with 41 turnouts.
I n E l e v a t e d s e c t i o n b e t w e e n
Thirumangalam ramp and St. Thomas
Mount, track work completed for the
entire elevated section for length of
2 4 7 8 8 m w i t h 2 7 t u r n o u t s a n d
commissioned for passenger services.
In the underground section
between Thirumangalam ramp and
Chennai central, out of 19888m, Track
work completed for the length of 15981m with 5 turnouts from Thirumangalam
ramp to Nehru Park. For the balance length, track work in progress. Trial run with
rolling stock has been conducted from Thirumangalam to Nehru Park.
Chennai Metro Rail | News Letter 02
Central Vigilance Commission the apex body of vigilance of the country has announced the Observance of st th
Vigilance awareness week celebrations from 31 Oct 2016 to 5 Nov 2016 and the theme for this year is
“Public Participation in promoting integrity and eradicating corruption”.
Thiru B.Murugesh, DRO/CVO on 31 October 2016 at 11.00 am to
officers and staff of CMRL.
An essay competition was conducted for the students at Kendriya Vidyalaya, Anna
Nagar on 01-11-16.The topic for essay competition was “How to make India th thCorruption Free”. Several students from class 11 to 12 participated in the
competition with enthusiasm and prizes were distributed for the winners.
“Public Participation in
promoting integrity and eradicating corruption” Shri S Krishnan,
IAS, Principal Secretary to Government, PDSI Department, Government of Tamil
Nadu promoting integrity
and having a transparent approach towards contract management at CMRL
and eradicating corruption
Vigilance Awareness Pledge:
Essay and Elocution Competition for students at Kendriya Vidyalaya:
Seminar on :
To mark the occasion, Vigilance Awareness pledge was administered
by
To emphasis the importance of this year's theme on
, CMRL invited
as the Chief Guest who gave an enriching seminar on
on 02-11-16. MD, CMRL along with Directors and all
officers and staff of CMRL participated in this seminar.
promoting integrity and eradicating corruption
Vigilance Awareness Week Celebration 31st Oct - 5th Nov 2016
Chennai Metro Rail | News Letter 03
Vigilance Awareness Week Celebrations 31st Oct 2016 - 5th Nov 2016.
Vigilance Bulletin Released:
Prize distribution - Anti-Corruption Essay Competition for CMRL employees:
As part of Vigilance Awareness Week Celebrations, CMRL Vigilance
Bulletin was released during the celebrations held on 02-11-16 by the
Chief Guest Shri S Krishnan, IAS, Principal Secretary to Government,
PDSI Department, Government of Tamil Nadu and Shri Pankaj Kumar
Bansal, ,IAS., Managing Director , Chennai Metro Rail Limited along with
Chief Vigilance Officer, Shri B. Murugesh, DRO/LO,CMRL.
As part of Vigilance week celebrations, Posters and banners promoting
Anti-corruption were displayed at prominent locations of CMRL Admin
Building and all metro stations.
Vigilance department had recently conducted an essay competition with the title “Public
Participation in promoting integrity and eradicating corruption” as part of its
e n d e a v o r t o p r o m o t e i n t e g r i t y a m o n g C M R L e m p l o y e e s .
The awards were felicitated to the winners by the Chief Guest Shri S Krishnan, IAS,
Principal Secretary to Government, PDSI Department, Government of Tamil Nadu during the Vigilance week
celebrations held on 02-11-16.
The Winners of the Essay Competition are as follows;st1 Prize - K. Sai Krishna Charan , CMA- Trainee (Finance Department)nd2 Prize - T. Sampath Kumar, AM(F&A), Emp.No 1121nd2 Prize - A. Sujatha Shenoy, Ps to Director (Project), Emp no. 1195rd3 Prize – T. Hayanan , DM(RS) Emp no. 1215
Chennai Metro Rail | News Letter 04
Underground Sections & Tunneling Work Progress as on 30.11.2016
Package TBM From ToTunnelling
length in mtrCompleted
in mtr
Percentage completed
UAA 01 TBM 1 Washermenpet Metro Egmore Metro 4445 4445 100
TBM 2 Washermenpet Metro Egmore Metro 4445 4223 95.0
TBM 3 May Day Park Central Metro 2080 2080 100
UAA 02 TBM 1 May Day Park AG-DMS 3616 1967 54.4
TBM 2 May Day Park AG-DMS 3616 1946 53.82
UAA 03 Saidapet Metro AG-DMS 5736 5736 100
UAA 04 Egmore Metro Shenoy Nagar 6776 6776 100
UAA 05 Shenoy Nagar Thirumangalam 5594 5594 100
UAA 08 Washermenpet Korukkupet 2000 - 0
Total 38308 32767 85.54
Underground Work progress Gallery
Work in progress in Anna Nagar East Metro Station
Work in progress in Shenoy Nagar Metro StationWork in progress in Anna Nagar Tower Station
Work in progress in Thirumangalam Metro Station
Chennai Metro Rail | News Letter 04
Rolling Stock Work Progress as on 30.11.2016
Trains delivered to depot:
Trains commissioned and conditionally accepted by CMRL
Trains under testing at CMRL facility:
Maintenance of CMRL trains:
A total of 37 trains including
the 9 trains of import category, have been delivered to CMRL
Koyambedu Depot. Train 38 were delivered to CMRL Depot thon 07 Nov 2016 respectively.
¯ Nine trains have been issued with completion
certificate and seven among these nine trains have
been conditionally accepted by CMRL in June 2015.
The remaining two trains were conditionally
accepted in May and June 2016.
¯ Further, 6 trains have been conditionally accepted in
September and October 2016.
¯ The total accepted 15 trains are put under revenue
service of Stage-1 and Stage – 1A sections of CMRL.
¯ Maintenance activities on these 15 trains are carried
out by CMRL Rolling Stock Maintenance Team and
the warranty obligation is done by the contractor.
All other trains delivered to CMRL are under various stages of testing and commissioning in CMRL depot and mainline.
¯ Preventive maintenance activities on these 15 trains are carried out by CMRL Rolling Stock Maintenance Team and corrective maintenance is done by the contractor.
¯ Preventive maintenance activities include 72 hrs inspect ion, monthly maintenance, quarter ly maintenance, half yearly maintenance and annual maintenance.
Trains under manufacturing at Sricity:
¯ Trains 39 to 42 are under various stages of production
and testing, as per the schedule, at Alstom factory,
Sri City.
05
Employee of the Month Award
November 2016
Thiru A.Abdul Sathar Technician/Electrical
,
¯ RE-railing equipment mock-up was successfully thcompleted on 25 Nov 2016. During the mock up,
functioning and working of Re-railing equipment such as Power packs, Hydraulic Jacks, Spreader, cutter, Airbags, . are checked for proper functioning
Rescue Trolley etc
Thiru A.Abdul Sathar,Technician/Electrical has been nominated as the “Employee of the Month” of Nov 2016, for his valuable contributions towards the replacement of HVAC filter( Return air and mixed air filters),Wheel flange lubrication sticks replacement,Internal doors inspection, Rolling stock Functional checks and raising job cards to Alstom /Corrective maintenance. Well contributed in the commissioning of train wash and bogie wash plant ,when he worked under DM division and made wash plant operational for exterior cleaning or trains.
06
Awards and Rewards
0406Chennai Metro Rail | News Letter
Editor Tmt. Tamil Mozhi Amuthu, PRO
Sub-EditorSelvi. Shruti Shambavi. R, AM (PR)
Published by :Chennai Metro Rail Limited.
Please address all correspondence to:
The Editor, Chennai Metro Rail News Letter,
Chennai Metro Rail Limited, "Administration Building",
CMRL Depot, Poonamallee High Road, Koyambedu, Chennai - 600 107. [email protected]
1 1143 Abbas. H Manager (UG)
RDSO Trails-Stage 1A section, CMRS
inspection-Stage1&1A including depot &
Commissioning of Depot major and minor
machine
2 5207 Madhan Mohan. S.K JE/SC/TO
3 5214 Thaveethu Durairaj. P JE/SC/TO
4 5161 Elangovan. M SC
5 5221 Karthikeyan. T JE/SC/TO
6 5153 Nagendiran. C Station Controller
7 5193 Ramarajan. P Train Operator
8 5005 Gayathri. P Station Controller
9 5140 Vaithiyanathan. A Train Operator
10 5220 Ganesh. K JE/SC/TO
11 5025 Shanmuganathan. A Train Operator
12 5234 Jayashree. S Technician (Mechanical)
Rolling Stock Annual Maintenance
acitivities, 72hrs inspection and train
fitness for revenue service and
preparedness of trains during stage 1A
inauguration
Dedication and Devotion towards Stage 1A
Stations Commissioning
The Following Officers and Staffs have been awarded for their outstading performance for the month
of November 2016
Emp. No. Awarded towardsSl.No DesignationName
(Thiru / Tmt / Selvi)
Publicity initiatives for St Thomas Mount Metro Station
To create awareness to the public on the facilities and safety features of the newly opened St Thomas Mount Metro Station.Students volunteers of NSS from Kendriya Vidhayala , Anna Nagar,Anna University , Valliammai College of Engineering participated in the distribution of pamphlets to the public and explained to them the features and fare information of the St Thomas Mount Metro Station.