VOLUME-I ISSUE-11 November 2016 www.chennaimetrorail.org CORRIDOR-I: In Elevated section from Airport to Saidapet ramp, track work completed for the entire elevated section for the length of 18695m with 23 turnouts and commissioned for passenger services. In underground section between Saidapet ramp to Washermenpet, track work in progress from Saidapet Ramp to Nandanam. Chairman Thiru Rajiv Gauba, I.A.S., Secretary Ministry of Urban Development Government of India Track Progress as on 30/11/2016 (ATA-01) Track concreting in progress between Saidapet ramp to Saidapet station Track concreting in progress between Saidapet ramp to Saidapet station CORRIDOR-II: DEPOT : Track work completed for entire depot length of 14606m with 41 turnouts. In Elevated section between Thirumangalam ramp and St. Thomas Mount, track work completed for the entire elevated section for length of 24788m with 27 turnouts and commissioned for passenger services. In the underground section between Thirumangalam ramp and Chennai central, out of 19888m, Track work completed for the length of 15981m with 5 turnouts from Thirumangalam ramp to Nehru Park. For the balance length, track work in progress. Trial run with rolling stock has been conducted from Thirumangalam to Nehru Park.

Transcript of Track Progress as on 30/11/2016 (ATA-01) - Chennai...

VOLUME-I ISSUE-11

November 2016

www.chennaimetrorail.org

CORRIDOR-I:

In Elevated section from Airport to Saidapet ramp,

track work completed for the entire elevated section

for the length of 18695m with 23 turnouts and

commissioned for passenger services.

In underground section between Saidapet

ramp to Washermenpet, track work in progress from

Saidapet Ramp to Nandanam.

Chairman

Thiru Rajiv Gauba, I.A.S.,

SecretaryMinistry of Urban DevelopmentGovernment of India

Track Progress as on 30/11/2016 (ATA-01)

Track concreting in progress between Saidapet ramp to

Saidapet station

Track concreting in progress between Saidapet ramp to Saidapet

station

CORRIDOR-II:

DEPOT :

Track work completed for entire depot length of 14606m with 41 turnouts.

I n E l e v a t e d s e c t i o n b e t w e e n

Thirumangalam ramp and St. Thomas

Mount, track work completed for the

entire elevated section for length of

2 4 7 8 8 m w i t h 2 7 t u r n o u t s a n d

commissioned for passenger services.

In the underground section

between Thirumangalam ramp and

Chennai central, out of 19888m, Track

work completed for the length of 15981m with 5 turnouts from Thirumangalam

ramp to Nehru Park. For the balance length, track work in progress. Trial run with

rolling stock has been conducted from Thirumangalam to Nehru Park.

Chennai Metro Rail | News Letter 02

Central Vigilance Commission the apex body of vigilance of the country has announced the Observance of st th

Vigilance awareness week celebrations from 31 Oct 2016 to 5 Nov 2016 and the theme for this year is

“Public Participation in promoting integrity and eradicating corruption”.

Thiru B.Murugesh, DRO/CVO on 31 October 2016 at 11.00 am to

officers and staff of CMRL.

An essay competition was conducted for the students at Kendriya Vidyalaya, Anna

Nagar on 01-11-16.The topic for essay competition was “How to make India th thCorruption Free”. Several students from class 11 to 12 participated in the

competition with enthusiasm and prizes were distributed for the winners.

“Public Participation in

promoting integrity and eradicating corruption” Shri S Krishnan,

IAS, Principal Secretary to Government, PDSI Department, Government of Tamil

Nadu promoting integrity

and having a transparent approach towards contract management at CMRL

and eradicating corruption

Vigilance Awareness Pledge:

Essay and Elocution Competition for students at Kendriya Vidyalaya:

Seminar on :

To mark the occasion, Vigilance Awareness pledge was administered

by

To emphasis the importance of this year's theme on

, CMRL invited

as the Chief Guest who gave an enriching seminar on

on 02-11-16. MD, CMRL along with Directors and all

officers and staff of CMRL participated in this seminar.

promoting integrity and eradicating corruption

Vigilance Awareness Week Celebration 31st Oct - 5th Nov 2016

Chennai Metro Rail | News Letter 03

Vigilance Awareness Week Celebrations 31st Oct 2016 - 5th Nov 2016.

Vigilance Bulletin Released:

Prize distribution - Anti-Corruption Essay Competition for CMRL employees:

As part of Vigilance Awareness Week Celebrations, CMRL Vigilance

Bulletin was released during the celebrations held on 02-11-16 by the

Chief Guest Shri S Krishnan, IAS, Principal Secretary to Government,

PDSI Department, Government of Tamil Nadu and Shri Pankaj Kumar

Bansal, ,IAS., Managing Director , Chennai Metro Rail Limited along with

Chief Vigilance Officer, Shri B. Murugesh, DRO/LO,CMRL.

As part of Vigilance week celebrations, Posters and banners promoting

Anti-corruption were displayed at prominent locations of CMRL Admin

Building and all metro stations.

Vigilance department had recently conducted an essay competition with the title “Public

Participation in promoting integrity and eradicating corruption” as part of its

e n d e a v o r t o p r o m o t e i n t e g r i t y a m o n g C M R L e m p l o y e e s .

The awards were felicitated to the winners by the Chief Guest Shri S Krishnan, IAS,

Principal Secretary to Government, PDSI Department, Government of Tamil Nadu during the Vigilance week

celebrations held on 02-11-16.

The Winners of the Essay Competition are as follows;st1 Prize - K. Sai Krishna Charan , CMA- Trainee (Finance Department)nd2 Prize - T. Sampath Kumar, AM(F&A), Emp.No 1121nd2 Prize - A. Sujatha Shenoy, Ps to Director (Project), Emp no. 1195rd3 Prize – T. Hayanan , DM(RS) Emp no. 1215

Chennai Metro Rail | News Letter 04

Underground Sections & Tunneling Work Progress as on 30.11.2016

Package TBM From ToTunnelling

length in mtrCompleted

in mtr

Percentage completed

UAA 01 TBM 1 Washermenpet Metro Egmore Metro 4445 4445 100

TBM 2 Washermenpet Metro Egmore Metro 4445 4223 95.0

TBM 3 May Day Park Central Metro 2080 2080 100

UAA 02 TBM 1 May Day Park AG-DMS 3616 1967 54.4

TBM 2 May Day Park AG-DMS 3616 1946 53.82

UAA 03 Saidapet Metro AG-DMS 5736 5736 100

UAA 04 Egmore Metro Shenoy Nagar 6776 6776 100

UAA 05 Shenoy Nagar Thirumangalam 5594 5594 100

UAA 08 Washermenpet Korukkupet 2000 - 0

Total 38308 32767 85.54

Underground Work progress Gallery

Work in progress in Anna Nagar East Metro Station

Work in progress in Shenoy Nagar Metro StationWork in progress in Anna Nagar Tower Station

Work in progress in Thirumangalam Metro Station

Chennai Metro Rail | News Letter 04

Rolling Stock Work Progress as on 30.11.2016

Trains delivered to depot:

Trains commissioned and conditionally accepted by CMRL

Trains under testing at CMRL facility:

Maintenance of CMRL trains:

A total of 37 trains including

the 9 trains of import category, have been delivered to CMRL

Koyambedu Depot. Train 38 were delivered to CMRL Depot thon 07 Nov 2016 respectively.

¯ Nine trains have been issued with completion

certificate and seven among these nine trains have

been conditionally accepted by CMRL in June 2015.

The remaining two trains were conditionally

accepted in May and June 2016.

¯ Further, 6 trains have been conditionally accepted in

September and October 2016.

¯ The total accepted 15 trains are put under revenue

service of Stage-1 and Stage – 1A sections of CMRL.

¯ Maintenance activities on these 15 trains are carried

out by CMRL Rolling Stock Maintenance Team and

the warranty obligation is done by the contractor.

All other trains delivered to CMRL are under various stages of testing and commissioning in CMRL depot and mainline.

¯ Preventive maintenance activities on these 15 trains are carried out by CMRL Rolling Stock Maintenance Team and corrective maintenance is done by the contractor.

¯ Preventive maintenance activities include 72 hrs inspect ion, monthly maintenance, quarter ly maintenance, half yearly maintenance and annual maintenance.

Trains under manufacturing at Sricity:

¯ Trains 39 to 42 are under various stages of production

and testing, as per the schedule, at Alstom factory,

Sri City.

05

Employee of the Month Award

November 2016

Thiru A.Abdul Sathar Technician/Electrical

,

¯ RE-railing equipment mock-up was successfully thcompleted on 25 Nov 2016. During the mock up,

functioning and working of Re-railing equipment such as Power packs, Hydraulic Jacks, Spreader, cutter, Airbags, . are checked for proper functioning

Rescue Trolley etc

Thiru A.Abdul Sathar,Technician/Electrical has been nominated as the “Employee of the Month” of Nov 2016, for his valuable contributions towards the replacement of HVAC filter( Return air and mixed air filters),Wheel flange lubrication sticks replacement,Internal doors inspection, Rolling stock Functional checks and raising job cards to Alstom /Corrective maintenance. Well contributed in the commissioning of train wash and bogie wash plant ,when he worked under DM division and made wash plant operational for exterior cleaning or trains.

06

Awards and Rewards

0406Chennai Metro Rail | News Letter

Editor Tmt. Tamil Mozhi Amuthu, PRO

Sub-EditorSelvi. Shruti Shambavi. R, AM (PR)

Published by :Chennai Metro Rail Limited.

Please address all correspondence to:

The Editor, Chennai Metro Rail News Letter,

Chennai Metro Rail Limited, "Administration Building",

CMRL Depot, Poonamallee High Road, Koyambedu, Chennai - 600 107. [email protected]

1 1143 Abbas. H Manager (UG)

RDSO Trails-Stage 1A section, CMRS

inspection-Stage1&1A including depot &

Commissioning of Depot major and minor

machine

2 5207 Madhan Mohan. S.K JE/SC/TO

3 5214 Thaveethu Durairaj. P JE/SC/TO

4 5161 Elangovan. M SC

5 5221 Karthikeyan. T JE/SC/TO

6 5153 Nagendiran. C Station Controller

7 5193 Ramarajan. P Train Operator

8 5005 Gayathri. P Station Controller

9 5140 Vaithiyanathan. A Train Operator

10 5220 Ganesh. K JE/SC/TO

11 5025 Shanmuganathan. A Train Operator

12 5234 Jayashree. S Technician (Mechanical)

Rolling Stock Annual Maintenance

acitivities, 72hrs inspection and train

fitness for revenue service and

preparedness of trains during stage 1A

inauguration

Dedication and Devotion towards Stage 1A

Stations Commissioning

The Following Officers and Staffs have been awarded for their outstading performance for the month

of November 2016

Emp. No. Awarded towardsSl.No DesignationName

(Thiru / Tmt / Selvi)

Publicity initiatives for St Thomas Mount Metro Station

To create awareness to the public on the facilities and safety features of the newly opened St Thomas Mount Metro Station.Students volunteers of NSS from Kendriya Vidhayala , Anna Nagar,Anna University , Valliammai College of Engineering participated in the distribution of pamphlets to the public and explained to them the features and fare information of the St Thomas Mount Metro Station.