TPP- final

download TPP- final

of 47

Transcript of TPP- final

  • 8/3/2019 TPP- final

    1/47

    POWER GENERATION ANDDISTRIBUTION IN VIZAG

    STEEL PLANT

    N.SANTOSHSUSHMITA DAS

    K.KIRAN KUMAR

    J.SURESH KUMARV.UMA SOUJANYA

    B.BHARATH KUMAR

    P. V. JAGADEESH BABU

  • 8/3/2019 TPP- final

    2/47

    VIZAG STEEL PLANT

    Visakhapatnam Steel Plant (VSP), the firstcoast based Steel Plant of India is located,16 KM South West of city of Destiny i.e.Visakhapatnam.

    VSP has an installed capacity of 3.3 millionTonnes per annum of liquid steel which willbe doubled by 2012.

    VSP has become the first integrated SteelPlant in the country to be certified to all thethree international standards for quality(ISO-9001), for Environment Management

    (ISO-14001) & for Occupational Health &

  • 8/3/2019 TPP- final

    3/47

    INTRODUCTIONTO

    THERMAL POWER PLANT Thermal power plant in VSP is a captive

    power plant which is established in the year

    1988.

    It is established mainly to reduce the cost ofpower consumption.

    TPP covers an approximate area of 20acres.

    The fuel input of TPP is imported from

    Bailadilla ores located in Chattisgarh and

  • 8/3/2019 TPP- final

    4/47

    OBJECTIVES OF TPP

    To Supply uninterrupted Cold Blast toBlast Furnaces as per Furnace

    requirements .

    To supply uninterrupted Essential

    Power.

    To supply 13 ata process steam for

    other units of Steel Plant.

    To supply quality De Mineralised water

    to meet both internal and plant needs.

  • 8/3/2019 TPP- final

    5/47

    POWER GENERATION &DISTRIBUTION

    Constituent departments

    Thermal Power Plant

    Distribution Networks

  • 8/3/2019 TPP- final

    6/47

    ENERGY CONSUMPTION

    SPECIFIC POWER CONSUMPTION:

    AVERAGE POWERDEMAND :

    600-650 kwh/Ton of steel

    227 MW

  • 8/3/2019 TPP- final

    7/47

    POWER REQUIREMENT

    Average Load : 227 MW

    Peak Load : 260 MW

  • 8/3/2019 TPP- final

    8/47

    SOURCES OF POWER

    CAPTIVE POWER PLANT

    STATE ELECTRICITY GRID

  • 8/3/2019 TPP- final

    9/47

    CAPTIVE GENERATIONSOURCES

    Thermal Power Plant

    Back Pressure Turbine Station

    Gas Expansion Turbine Station

  • 8/3/2019 TPP- final

    10/47

    MAIN EQUIPMENTS OF TPP

    Chemical Water Treatment Plant

    Boilers

    Turbo-Generators Turbo-Blowers

    CDCP Boilers

    Back Pressure Turbine Station Gas Expansion Turbine Station

  • 8/3/2019 TPP- final

    11/47

    Chemical Water Treatment Plant(CWTP)

    Water to the boilers and otherdepartments is fed from kanithi balancingreservoir.

    Boilers require soft water failure of whichforms scales and sludges.

    CWTP produces high purity de-mineralized water and soft water.

    It has a total 6 De-mineralizing units of125cu m/hr each and 2 softening units of 125cu. m/hr each.

  • 8/3/2019 TPP- final

    12/47

    BOILERSBoiler is an enclosed vessel in which

    water is heated and circulated until the

    water is turned in to steam at the required

    pressure.

    BOILERS 5(4 working +

    1Standby)

    CAPACITY 330 Tons/ Hr

    PRESSURE 101ata

    TEMPERATURE 540o

    C

  • 8/3/2019 TPP- final

    13/47

    All the boilers in VSP are of water tubetype and of BHEL make.

    Boiler coal is imported from Bailadilla oresin Chattisgarrh and also from Orissa.

    Coal is crushed and stored in RMHP.

    Soft water is provided to the boilers whichis treated at chemical water treatmentplant and fed to the boilers through 7

    boiler feed pumps each of 2.4MW. Boilers outlet flue gas is passed through

    electro static precipitators to control air

    pollution.

  • 8/3/2019 TPP- final

    14/47

    TURBO GENERATORS

    4 TGs : ( 3

    60MW + 167.5MW )

    Special features:

    Electro Hydraulic Turbine GoverningSystem.

    Controlled extraction at 13ata and 4atafor process steam needs. (Only in TG 1,2 &3)

    Central admission of steam to reduceaxial thrust.

  • 8/3/2019 TPP- final

    15/47

    Steam is admitted at 90 ata pressure and

    500O C. Steam extracted at 13ata is used for valve

    operations of the different equipments and

    4ata is used for instrumentation purposes. Each turbo generator generates power at

    11KV.

    All the power generated from TG-1, 2 and3 is directly distributed at 11 KV foressential category loads of VSP.

  • 8/3/2019 TPP- final

    16/47

    Excess power from TG- 1, 2 and 3 is

    transferred to 220 KV plant grid throughthree 50/63MVA step up transformers atLBSS-5.

    Turbo generators of VSP operate inparallel with state grid.

    Excess generation over and above plant

    load is exported to APTRANSCO. The short fall of power under certain

    conditions is availed from APTRANSCO.

  • 8/3/2019 TPP- final

    17/47

    TURBO BLOWERS

    Turbo blowers are blowers which

    produces compressed air with the help of

    a steam based turbine.

    BLOWERS 3( 2 Working + 1 Standby )

    CAPACITY 6067 M3 /min each

  • 8/3/2019 TPP- final

    18/47

    These blowers are of axial type and are

    the largest blowers installed in India.

    To meet the varying needs of Blast

    Furnace, the blowers are provided with

    adjustable stator guide blades.

    Special Features :

    -Constant Speed with EHTC- Inlet Guide Vane Control

    - Axial type Largest blowers in India

  • 8/3/2019 TPP- final

    19/47

    AUXILLIARY UNITS OF TPP

    CDCP (COKE DRY COOLING PLANT)BOILERS - 16nos

    Back Pressure Turbine Station -2 x 7.5

    MW

    Gas Expansion Turbine Station -2 x 12

    MW

  • 8/3/2019 TPP- final

    20/47

    COKE DRY COOLING PLANT(CDCP) BOILERS

    Hot coke produced in the Coke Oven

    Batteries is cooled by circulating Nitrogen.

    Hot circulating nitrogen gas is passed

    through Waste Heat Boilers in which steam

    is produced at 40ata pressure and 440OC

    temperature.

  • 8/3/2019 TPP- final

    21/47

    BACK PRESSURE TURBINESTATION

    The 40ata steam generated in CDCPBoilers is utilized for driving 2 Nos. of 7.5MW Back Pressure Turbines for

    generation of Power.Steam is admitted at 40ata pressure and

    440OC temperature and exhausted at

    2.5ata pressure. It has a controlled extraction of 7ata

    pressure.

    The turbine and alternator are of BHEL

  • 8/3/2019 TPP- final

    22/47

  • 8/3/2019 TPP- final

    23/47

    2.5ata exhaust steam is utilised forproduction of chilled water in CWP-1.

    7ata extraction steam for processrequirements of CO & CCP zone.

    These alternators run in synchronouswith the main generators and areconnected to LBSS-5 through a

    220KV 31.5/40/50MVA three windingstep up transformer.

  • 8/3/2019 TPP- final

    24/47

    GAS EXPANSION TURBINESTATION (GETS)

    Hot flue gases from the blast furnaces isutilised as input to drive turbines in

    GETS. The gas is first cleaned and heated to

    140 OC before using it.

    Each BF is connected to a turbine of12MW capacity.

    7.5MW of power is expected at full

    production level.

  • 8/3/2019 TPP- final

    25/47

  • 8/3/2019 TPP- final

    26/47

    Special features

    First of its kind in India.

    Motor mode operation.At very low pressure or during

    shutdown of blast furnaces, the

    alternator takes input from the supplylines and acts as a synchronous motor(condenser) which helps in improving

    the power factor of the grid. Water washing of stator & rotor blades. Variable stator vanes.

  • 8/3/2019 TPP- final

    27/47

    POWER DISTRIBUTION IN VSP

    Power distribution in VSP is categorized

    as four types:

    Extra High Voltage Distribution (220Kv)

    High Voltage Distribution (33/11/6.6kv)

    Medium Voltage Distribution (Below 650

    V)

    Low Voltage Distribution (250 V And

    Below)

  • 8/3/2019 TPP- final

    28/47

    EXTRA HIGH VOLTAGEDISTRIBUTION (220 KV)

    Power from APTRANSCO is received atMain Receiving Station (MRS).

    The entire plant is configured as five

    electrical Load Blocks and Step downSub-Stations (LBSS 1-5) with 220 KVtransformers to step down for further

    distribution. LBSS1 is connected to LBSS5 by two

    radial lines.

    LBSS 2,3&4 are connected to MRS by

  • 8/3/2019 TPP- final

    29/47

    POWER NETWORKEASTERN BUS 400 Kv

    DC BACK TO BACK

    SOUTHERN BUS 400 Kv

    TO JAIPUR

    (ORISSA)

    TO VIJAYAWADA(NUNNA)

    315MVA400/220 KvAUTO XMER

    220 Kv

    TO BOMMURU TO PENDURTHITO

    GAJUWAKA

    MRS 220 KvBUS 1

    BUS 2

    BUS 1

    BUS 2

    TPP 220 Kv

    LBSS 1

    LBSS 3 LBSS 4 LBSS 2

    12.5 MVA

    220/33 Kv XMER

    TO CPRS

    AL1 AL2

    ML1ML2 ML3

    BC

    BC

    T150/63MVA

    T2

    50/63

    MVA

    T350/63MVA

    T5

    90

    MVA

    T4

    31.5/40/50

    MVA

    11 Kv

    TG 1

    60 MW

    TG 2

    60 MW

    TG 3

    60 MWTG 4

    67.5 MW BPTG 1

    7.5 MW

    GETG 1

    12 MW

    BPTG 2

    7.5 MWGETG 2

    12 MW

    MRS

    LBSS 5

    GSB 1 GSB 2 GSB 3

    POWER GRID

    SUB STATION

    APSEB SWITCHING STATION

    VSP

    - BREAKER

    LOAD BLOCK AND

  • 8/3/2019 TPP- final

    30/47

    LOAD BLOCK ANDSTEPDOWN SUB-STATIONS

    STATION DESIGNATION AREAS COVERED

    LBSS1 (220/11/6.6 kV) RMHP, CO & CCP, Sinter Plant, BF

    LBSS2 (220/11/6.6 kV)

    (220/33 kV)

    BF, SMS, ASP, CRMP, Comp. House-1

    Ladle furnace in SMS

    LBSS3 (220/11/11 kV) Medium Merchant Structural Mill

    LBSS4 (220/11/11 kV)LMMM, WRM, Aux. Shops, Adm. Building and

    Kanithi reservoir pump house.

    LBSS5(220/11&220/11/11kV)

    TPP, Plant essential category loads, KBR &Township pump houses & hospital.

    MRS (220/33 kV) Plant, Township and construction network.

  • 8/3/2019 TPP- final

    31/47

    HIGH VOLTAGE DISTRIBUTION(33/11/6.6KV)

    220KV Power is stepped down to 11/6.6KV at each LBSS station.

    This power is distributed to smaller LoadBlock Distribution Station (LBDS) locatedin each unit.

    Cross-linked Poly Ethylene (XLPE)

    cables are used for 11 KV distribution.

    6.6 KV supply is mostly used for motorsof rating 200 to 2000 KW.

    Medium Voltage Distribution(Below

  • 8/3/2019 TPP- final

    32/47

    Medium Voltage Distribution(Below650v)

    For medium and low voltage loads of

    11KV/415 V Load Centre Sub-Stations(LCSS) are formed.

    Power is fed from LCSS to Motor Control

    Centre, Power Distribution Boards, LightingDistribution Boards.

    PVC cables are used for medium voltage

    distribution generally.Low Voltage Distribution (250 v and

    below)

    Consists of power supply on single phase

  • 8/3/2019 TPP- final

    33/47

    ESSENTIAL CATEGORY LOADS

    Some of the technological process/equipment requires all time availability ofelectricity.

    These include exhausters in BF, SMS,rolling mills, kanithi reservoir pump house,TPP auxiliaries, hospital etc. which accountsto a total of 70MW.

    Disturbance of supply may involvedangerous situation to equipment/ heavylosses to the plant.

    Power is supplied to them from TPPenerator 11kv switch board and also from

    LOAD BLOCK STEP DOWN

  • 8/3/2019 TPP- final

    34/47

    LOAD BLOCK STEP DOWNSUBSTATION 5

    This 220 KV Sub station serves as outdoorswitch yard for TPP. This substation

    consists of 5 in no. 220 KV/11 KV

    transformers connected to the 11 KV

    generated switch board of TPP.

    MRS and LBSS-5 are interconnected with

    three numbers of 220 KV tie lines.

    The TPP is synchronized with APTRANSCO

    grid, supply at 220 KV/11 KV and

    Power is fed from LBSS-5 to LBSS-1 at 220

    GENERATOR SWITCH BOARD

  • 8/3/2019 TPP- final

    35/47

    GENERATOR SWITCH BOARD(GSB-1)

    GSB-1 is a 11 kV, 4500 Amp, 3 section boardlocated in ECR. Each 60 MW generator is

    connected to one section of the board.

    GSB-1 is provided with a normal bus coupler

    and also a reactor bus coupler of 4500 Amp

    reactor between section 1 & 2 as well as between

    Sections 2 & 3.

    Reactor bus couplers are employed to opposesudden changes in current while coupling the

    buses.

    All essential category loads of plant are served

    directl from GSB-1.

  • 8/3/2019 TPP- final

    36/47

    GSB-2 & GSB-3 11kV SWITCHBOARD

    GSB-2 is connected to BPTS and GETSgenerators-1 where as GSB-3 is

    connected to the generators-2. No outgoing feeders are connected in

    both these board.

    These generators are connected tosystem through a three winding220/11/11KV 31.5/40/50MVA Transformer

  • 8/3/2019 TPP- final

    37/47

    SWITCH GEAR IN LBSS-5

    CIRCUIT BREAKERS:A circuit breaker is a piece of equipmentwhich can

    make or break a circuit either manuallyor by remote control under normalconditionsbreak a circuit automatically under fault

    conditionsAll the incoming feeders are provided with4500A SF6 gas type and outgoing feedersare provided with 2000A MOCB typecircuit breakers.

  • 8/3/2019 TPP- final

    38/47

    INSTRUMENT TRANSFORMERS:The function of these instrument

    transformers is to transform voltages orcurrents in the power lines to values which

    are convenient for the operation of

    measuring instruments and relays.There are two types of instrumenttransformers

    Current transformer (C.T.) Potential transformer (P.T.)

  • 8/3/2019 TPP- final

    39/47

    The use of instrument transformerspermits the following advantages:

    They isolate the measuring instrumentsand relays from high-voltage powercircuits.

    The leads in the secondary circuits carryrelatively small voltages and currents.This permits to use wires of smaller sizewith minimum insulation.

    All the PTs and CTs of LBSS-5 are ofBHEL make.

    LIGHTNING ARRESTER

  • 8/3/2019 TPP- final

    40/47

    LIGHTNING ARRESTERA lightning arrester or a surge diverter is a

    protective device which conducts the highvoltage surges on the power system to the

    ground.

    Under normal operation, the lightningarrester is off the line i.e. it conducts nocurrent to earth or the gap is non-conducting.

    On the occurrence of overvoltage, the airinsulation across the gap breaks downand an arc is formed, providing a low

    resistance path for the surge to ther n .

  • 8/3/2019 TPP- final

    41/47

    In LBSS-5 lightning arrestors are ofMACHAS make. These are heavy duty

    station class type. A total no. of 24lightning arresters are provided each hasrated voltage of 198KV and rated current

    10KA.ISOLATOR

    Isolator is a switch used to make sure that

    an electrical circuit can be completely de-energized for service or maintenance.

    Isolator is an off-load device intended to

    be opened only after current has been

    FREQUENCY BASED

  • 8/3/2019 TPP- final

    42/47

    FREQUENCY BASEDISOLATION OF TPP

    To isolate the plant from over/underfrequency conditions of the AP Transcogrid, three frequency relays are provided

    in each section of GSB-1 Each relay has four frequency based

    operation elements.

    Rate of change of frequency(df/dt) with astarting under frequency of 47.7 Hz andsustained over frequency of 51.5 Hz for0.15 sec are the extremities for isolation

    of load.

  • 8/3/2019 TPP- final

    43/47

    Frequency based isolation scheme is

    provided in three stages:

    Stage-I Frequency isolates plant form Grid at 220

    kV after a sustained under frequency of

    47.5 Hz for 0.5 sec.

    Stage-II

    Frequency isolates the GSB from 220 kV

    network by tripping the 63 MVA

    transformers after a sustained under

    frequency of 46.9 Hz for 1 sec.

  • 8/3/2019 TPP- final

    44/47

    Stage-III

    Frequency isolates some of the selected

    loads from GSB-1 after a sustained under

    frequency of 46.0 Hz for 0.15sec.

  • 8/3/2019 TPP- final

    45/47

    POWER TARIFF The APTRANSCO Power tariff for VSP is a

    two part tariff. Contracted Maximum Demand =135MVA

    Energy charges are divided into

    i. General industrial loadii. Lighting & fan load

    Where lighting & fan load cannot be

    segregated, 15 % of total energy accountedas lighting & fan load.

    Power factor of VSP shall not be less than

    0.95 lag.

  • 8/3/2019 TPP- final

    46/47

    CONCLUSION

    We had learnt about the process ofgeneration of power in a thermal powerplant and also using a gas expansion

    turbine, which is a useful recovery ofwaste energy.

    The applications of various electrical

    equipments used in sub-stations for safetransmission of power are clearlyobserved.

    The overall plant line diagram has helped

  • 8/3/2019 TPP- final

    47/47

    THANK YOU