TPP- final
-
Upload
kiran-kumar -
Category
Documents
-
view
233 -
download
0
Transcript of TPP- final
-
8/3/2019 TPP- final
1/47
POWER GENERATION ANDDISTRIBUTION IN VIZAG
STEEL PLANT
N.SANTOSHSUSHMITA DAS
K.KIRAN KUMAR
J.SURESH KUMARV.UMA SOUJANYA
B.BHARATH KUMAR
P. V. JAGADEESH BABU
-
8/3/2019 TPP- final
2/47
VIZAG STEEL PLANT
Visakhapatnam Steel Plant (VSP), the firstcoast based Steel Plant of India is located,16 KM South West of city of Destiny i.e.Visakhapatnam.
VSP has an installed capacity of 3.3 millionTonnes per annum of liquid steel which willbe doubled by 2012.
VSP has become the first integrated SteelPlant in the country to be certified to all thethree international standards for quality(ISO-9001), for Environment Management
(ISO-14001) & for Occupational Health &
-
8/3/2019 TPP- final
3/47
INTRODUCTIONTO
THERMAL POWER PLANT Thermal power plant in VSP is a captive
power plant which is established in the year
1988.
It is established mainly to reduce the cost ofpower consumption.
TPP covers an approximate area of 20acres.
The fuel input of TPP is imported from
Bailadilla ores located in Chattisgarh and
-
8/3/2019 TPP- final
4/47
OBJECTIVES OF TPP
To Supply uninterrupted Cold Blast toBlast Furnaces as per Furnace
requirements .
To supply uninterrupted Essential
Power.
To supply 13 ata process steam for
other units of Steel Plant.
To supply quality De Mineralised water
to meet both internal and plant needs.
-
8/3/2019 TPP- final
5/47
POWER GENERATION &DISTRIBUTION
Constituent departments
Thermal Power Plant
Distribution Networks
-
8/3/2019 TPP- final
6/47
ENERGY CONSUMPTION
SPECIFIC POWER CONSUMPTION:
AVERAGE POWERDEMAND :
600-650 kwh/Ton of steel
227 MW
-
8/3/2019 TPP- final
7/47
POWER REQUIREMENT
Average Load : 227 MW
Peak Load : 260 MW
-
8/3/2019 TPP- final
8/47
SOURCES OF POWER
CAPTIVE POWER PLANT
STATE ELECTRICITY GRID
-
8/3/2019 TPP- final
9/47
CAPTIVE GENERATIONSOURCES
Thermal Power Plant
Back Pressure Turbine Station
Gas Expansion Turbine Station
-
8/3/2019 TPP- final
10/47
MAIN EQUIPMENTS OF TPP
Chemical Water Treatment Plant
Boilers
Turbo-Generators Turbo-Blowers
CDCP Boilers
Back Pressure Turbine Station Gas Expansion Turbine Station
-
8/3/2019 TPP- final
11/47
Chemical Water Treatment Plant(CWTP)
Water to the boilers and otherdepartments is fed from kanithi balancingreservoir.
Boilers require soft water failure of whichforms scales and sludges.
CWTP produces high purity de-mineralized water and soft water.
It has a total 6 De-mineralizing units of125cu m/hr each and 2 softening units of 125cu. m/hr each.
-
8/3/2019 TPP- final
12/47
BOILERSBoiler is an enclosed vessel in which
water is heated and circulated until the
water is turned in to steam at the required
pressure.
BOILERS 5(4 working +
1Standby)
CAPACITY 330 Tons/ Hr
PRESSURE 101ata
TEMPERATURE 540o
C
-
8/3/2019 TPP- final
13/47
All the boilers in VSP are of water tubetype and of BHEL make.
Boiler coal is imported from Bailadilla oresin Chattisgarrh and also from Orissa.
Coal is crushed and stored in RMHP.
Soft water is provided to the boilers whichis treated at chemical water treatmentplant and fed to the boilers through 7
boiler feed pumps each of 2.4MW. Boilers outlet flue gas is passed through
electro static precipitators to control air
pollution.
-
8/3/2019 TPP- final
14/47
TURBO GENERATORS
4 TGs : ( 3
60MW + 167.5MW )
Special features:
Electro Hydraulic Turbine GoverningSystem.
Controlled extraction at 13ata and 4atafor process steam needs. (Only in TG 1,2 &3)
Central admission of steam to reduceaxial thrust.
-
8/3/2019 TPP- final
15/47
Steam is admitted at 90 ata pressure and
500O C. Steam extracted at 13ata is used for valve
operations of the different equipments and
4ata is used for instrumentation purposes. Each turbo generator generates power at
11KV.
All the power generated from TG-1, 2 and3 is directly distributed at 11 KV foressential category loads of VSP.
-
8/3/2019 TPP- final
16/47
Excess power from TG- 1, 2 and 3 is
transferred to 220 KV plant grid throughthree 50/63MVA step up transformers atLBSS-5.
Turbo generators of VSP operate inparallel with state grid.
Excess generation over and above plant
load is exported to APTRANSCO. The short fall of power under certain
conditions is availed from APTRANSCO.
-
8/3/2019 TPP- final
17/47
TURBO BLOWERS
Turbo blowers are blowers which
produces compressed air with the help of
a steam based turbine.
BLOWERS 3( 2 Working + 1 Standby )
CAPACITY 6067 M3 /min each
-
8/3/2019 TPP- final
18/47
These blowers are of axial type and are
the largest blowers installed in India.
To meet the varying needs of Blast
Furnace, the blowers are provided with
adjustable stator guide blades.
Special Features :
-Constant Speed with EHTC- Inlet Guide Vane Control
- Axial type Largest blowers in India
-
8/3/2019 TPP- final
19/47
AUXILLIARY UNITS OF TPP
CDCP (COKE DRY COOLING PLANT)BOILERS - 16nos
Back Pressure Turbine Station -2 x 7.5
MW
Gas Expansion Turbine Station -2 x 12
MW
-
8/3/2019 TPP- final
20/47
COKE DRY COOLING PLANT(CDCP) BOILERS
Hot coke produced in the Coke Oven
Batteries is cooled by circulating Nitrogen.
Hot circulating nitrogen gas is passed
through Waste Heat Boilers in which steam
is produced at 40ata pressure and 440OC
temperature.
-
8/3/2019 TPP- final
21/47
BACK PRESSURE TURBINESTATION
The 40ata steam generated in CDCPBoilers is utilized for driving 2 Nos. of 7.5MW Back Pressure Turbines for
generation of Power.Steam is admitted at 40ata pressure and
440OC temperature and exhausted at
2.5ata pressure. It has a controlled extraction of 7ata
pressure.
The turbine and alternator are of BHEL
-
8/3/2019 TPP- final
22/47
-
8/3/2019 TPP- final
23/47
2.5ata exhaust steam is utilised forproduction of chilled water in CWP-1.
7ata extraction steam for processrequirements of CO & CCP zone.
These alternators run in synchronouswith the main generators and areconnected to LBSS-5 through a
220KV 31.5/40/50MVA three windingstep up transformer.
-
8/3/2019 TPP- final
24/47
GAS EXPANSION TURBINESTATION (GETS)
Hot flue gases from the blast furnaces isutilised as input to drive turbines in
GETS. The gas is first cleaned and heated to
140 OC before using it.
Each BF is connected to a turbine of12MW capacity.
7.5MW of power is expected at full
production level.
-
8/3/2019 TPP- final
25/47
-
8/3/2019 TPP- final
26/47
Special features
First of its kind in India.
Motor mode operation.At very low pressure or during
shutdown of blast furnaces, the
alternator takes input from the supplylines and acts as a synchronous motor(condenser) which helps in improving
the power factor of the grid. Water washing of stator & rotor blades. Variable stator vanes.
-
8/3/2019 TPP- final
27/47
POWER DISTRIBUTION IN VSP
Power distribution in VSP is categorized
as four types:
Extra High Voltage Distribution (220Kv)
High Voltage Distribution (33/11/6.6kv)
Medium Voltage Distribution (Below 650
V)
Low Voltage Distribution (250 V And
Below)
-
8/3/2019 TPP- final
28/47
EXTRA HIGH VOLTAGEDISTRIBUTION (220 KV)
Power from APTRANSCO is received atMain Receiving Station (MRS).
The entire plant is configured as five
electrical Load Blocks and Step downSub-Stations (LBSS 1-5) with 220 KVtransformers to step down for further
distribution. LBSS1 is connected to LBSS5 by two
radial lines.
LBSS 2,3&4 are connected to MRS by
-
8/3/2019 TPP- final
29/47
POWER NETWORKEASTERN BUS 400 Kv
DC BACK TO BACK
SOUTHERN BUS 400 Kv
TO JAIPUR
(ORISSA)
TO VIJAYAWADA(NUNNA)
315MVA400/220 KvAUTO XMER
220 Kv
TO BOMMURU TO PENDURTHITO
GAJUWAKA
MRS 220 KvBUS 1
BUS 2
BUS 1
BUS 2
TPP 220 Kv
LBSS 1
LBSS 3 LBSS 4 LBSS 2
12.5 MVA
220/33 Kv XMER
TO CPRS
AL1 AL2
ML1ML2 ML3
BC
BC
T150/63MVA
T2
50/63
MVA
T350/63MVA
T5
90
MVA
T4
31.5/40/50
MVA
11 Kv
TG 1
60 MW
TG 2
60 MW
TG 3
60 MWTG 4
67.5 MW BPTG 1
7.5 MW
GETG 1
12 MW
BPTG 2
7.5 MWGETG 2
12 MW
MRS
LBSS 5
GSB 1 GSB 2 GSB 3
POWER GRID
SUB STATION
APSEB SWITCHING STATION
VSP
- BREAKER
LOAD BLOCK AND
-
8/3/2019 TPP- final
30/47
LOAD BLOCK ANDSTEPDOWN SUB-STATIONS
STATION DESIGNATION AREAS COVERED
LBSS1 (220/11/6.6 kV) RMHP, CO & CCP, Sinter Plant, BF
LBSS2 (220/11/6.6 kV)
(220/33 kV)
BF, SMS, ASP, CRMP, Comp. House-1
Ladle furnace in SMS
LBSS3 (220/11/11 kV) Medium Merchant Structural Mill
LBSS4 (220/11/11 kV)LMMM, WRM, Aux. Shops, Adm. Building and
Kanithi reservoir pump house.
LBSS5(220/11&220/11/11kV)
TPP, Plant essential category loads, KBR &Township pump houses & hospital.
MRS (220/33 kV) Plant, Township and construction network.
-
8/3/2019 TPP- final
31/47
HIGH VOLTAGE DISTRIBUTION(33/11/6.6KV)
220KV Power is stepped down to 11/6.6KV at each LBSS station.
This power is distributed to smaller LoadBlock Distribution Station (LBDS) locatedin each unit.
Cross-linked Poly Ethylene (XLPE)
cables are used for 11 KV distribution.
6.6 KV supply is mostly used for motorsof rating 200 to 2000 KW.
Medium Voltage Distribution(Below
-
8/3/2019 TPP- final
32/47
Medium Voltage Distribution(Below650v)
For medium and low voltage loads of
11KV/415 V Load Centre Sub-Stations(LCSS) are formed.
Power is fed from LCSS to Motor Control
Centre, Power Distribution Boards, LightingDistribution Boards.
PVC cables are used for medium voltage
distribution generally.Low Voltage Distribution (250 v and
below)
Consists of power supply on single phase
-
8/3/2019 TPP- final
33/47
ESSENTIAL CATEGORY LOADS
Some of the technological process/equipment requires all time availability ofelectricity.
These include exhausters in BF, SMS,rolling mills, kanithi reservoir pump house,TPP auxiliaries, hospital etc. which accountsto a total of 70MW.
Disturbance of supply may involvedangerous situation to equipment/ heavylosses to the plant.
Power is supplied to them from TPPenerator 11kv switch board and also from
LOAD BLOCK STEP DOWN
-
8/3/2019 TPP- final
34/47
LOAD BLOCK STEP DOWNSUBSTATION 5
This 220 KV Sub station serves as outdoorswitch yard for TPP. This substation
consists of 5 in no. 220 KV/11 KV
transformers connected to the 11 KV
generated switch board of TPP.
MRS and LBSS-5 are interconnected with
three numbers of 220 KV tie lines.
The TPP is synchronized with APTRANSCO
grid, supply at 220 KV/11 KV and
Power is fed from LBSS-5 to LBSS-1 at 220
GENERATOR SWITCH BOARD
-
8/3/2019 TPP- final
35/47
GENERATOR SWITCH BOARD(GSB-1)
GSB-1 is a 11 kV, 4500 Amp, 3 section boardlocated in ECR. Each 60 MW generator is
connected to one section of the board.
GSB-1 is provided with a normal bus coupler
and also a reactor bus coupler of 4500 Amp
reactor between section 1 & 2 as well as between
Sections 2 & 3.
Reactor bus couplers are employed to opposesudden changes in current while coupling the
buses.
All essential category loads of plant are served
directl from GSB-1.
-
8/3/2019 TPP- final
36/47
GSB-2 & GSB-3 11kV SWITCHBOARD
GSB-2 is connected to BPTS and GETSgenerators-1 where as GSB-3 is
connected to the generators-2. No outgoing feeders are connected in
both these board.
These generators are connected tosystem through a three winding220/11/11KV 31.5/40/50MVA Transformer
-
8/3/2019 TPP- final
37/47
SWITCH GEAR IN LBSS-5
CIRCUIT BREAKERS:A circuit breaker is a piece of equipmentwhich can
make or break a circuit either manuallyor by remote control under normalconditionsbreak a circuit automatically under fault
conditionsAll the incoming feeders are provided with4500A SF6 gas type and outgoing feedersare provided with 2000A MOCB typecircuit breakers.
-
8/3/2019 TPP- final
38/47
INSTRUMENT TRANSFORMERS:The function of these instrument
transformers is to transform voltages orcurrents in the power lines to values which
are convenient for the operation of
measuring instruments and relays.There are two types of instrumenttransformers
Current transformer (C.T.) Potential transformer (P.T.)
-
8/3/2019 TPP- final
39/47
The use of instrument transformerspermits the following advantages:
They isolate the measuring instrumentsand relays from high-voltage powercircuits.
The leads in the secondary circuits carryrelatively small voltages and currents.This permits to use wires of smaller sizewith minimum insulation.
All the PTs and CTs of LBSS-5 are ofBHEL make.
LIGHTNING ARRESTER
-
8/3/2019 TPP- final
40/47
LIGHTNING ARRESTERA lightning arrester or a surge diverter is a
protective device which conducts the highvoltage surges on the power system to the
ground.
Under normal operation, the lightningarrester is off the line i.e. it conducts nocurrent to earth or the gap is non-conducting.
On the occurrence of overvoltage, the airinsulation across the gap breaks downand an arc is formed, providing a low
resistance path for the surge to ther n .
-
8/3/2019 TPP- final
41/47
In LBSS-5 lightning arrestors are ofMACHAS make. These are heavy duty
station class type. A total no. of 24lightning arresters are provided each hasrated voltage of 198KV and rated current
10KA.ISOLATOR
Isolator is a switch used to make sure that
an electrical circuit can be completely de-energized for service or maintenance.
Isolator is an off-load device intended to
be opened only after current has been
FREQUENCY BASED
-
8/3/2019 TPP- final
42/47
FREQUENCY BASEDISOLATION OF TPP
To isolate the plant from over/underfrequency conditions of the AP Transcogrid, three frequency relays are provided
in each section of GSB-1 Each relay has four frequency based
operation elements.
Rate of change of frequency(df/dt) with astarting under frequency of 47.7 Hz andsustained over frequency of 51.5 Hz for0.15 sec are the extremities for isolation
of load.
-
8/3/2019 TPP- final
43/47
Frequency based isolation scheme is
provided in three stages:
Stage-I Frequency isolates plant form Grid at 220
kV after a sustained under frequency of
47.5 Hz for 0.5 sec.
Stage-II
Frequency isolates the GSB from 220 kV
network by tripping the 63 MVA
transformers after a sustained under
frequency of 46.9 Hz for 1 sec.
-
8/3/2019 TPP- final
44/47
Stage-III
Frequency isolates some of the selected
loads from GSB-1 after a sustained under
frequency of 46.0 Hz for 0.15sec.
-
8/3/2019 TPP- final
45/47
POWER TARIFF The APTRANSCO Power tariff for VSP is a
two part tariff. Contracted Maximum Demand =135MVA
Energy charges are divided into
i. General industrial loadii. Lighting & fan load
Where lighting & fan load cannot be
segregated, 15 % of total energy accountedas lighting & fan load.
Power factor of VSP shall not be less than
0.95 lag.
-
8/3/2019 TPP- final
46/47
CONCLUSION
We had learnt about the process ofgeneration of power in a thermal powerplant and also using a gas expansion
turbine, which is a useful recovery ofwaste energy.
The applications of various electrical
equipments used in sub-stations for safetransmission of power are clearlyobserved.
The overall plant line diagram has helped
-
8/3/2019 TPP- final
47/47
THANK YOU