Town Center Project Monthly Report June 2009

Transcript of Town Center Project Monthly Report (June 2009)

Town Center Project Monthly Report

June 2009

The monthly activities surrounding the development and construction of the Town Center have centered on the following:g

Site Work Preparation - Community Center

Preparation of Foundation Walls Community CenterPreparation of Foundation Walls – Community Center

Preparation for Concrete Flooring – Community CenterConcrete Pour - Community Center Floor

Site Work for Pond

Preparation of Underground Electrical ServicePreparation of Underground Electrical Service

Preparation of Foundation Walls & FFooters

Sleeves for Utility ProvidersSleeves for Utility Providers

Concrete Floor Preparation &Concrete Floor Preparation & Pouring – Community Center

Foundation Walls & Preparation of C FlConcrete Floor

Preparation of Concrete FloorPreparation of Concrete Floor

Preparation of Concrete FloorPreparation of Concrete Floor

Preparation Concrete Pour-4 004:00am

Supervision C P 4 00Concrete Pour- 4:00am

Concrete Pour-Floor Area –Ph 1Photo 1

Concrete Pour-Floor Area –Ph 2Photo 2

Concrete Pour-Floor Area –Ph 3Photo 3

Concrete Pour-Floor Area –Ph 4Photo 4

Concrete Pour-Floor Area L S d M hiLaser Screed Machine

Completed Concrete FloorCompleted Concrete Floor

Pond Construction

Pond EntrancePond Entrance

DrainageP d EPond Entrance

Pond EntrancePh 2Photo - 2

Pond Retaining Wall

Pond Area

Pond AreaPh 2Photo 2

Financial ReportFinancial Report

Monetary BalancesMonetary Balances

Balance Type

Time Period Amount

Opening May 2009 $19,007,025.38Opening May 2009 $19,007,025.38

Closing June 2009 $18,288,016.44