11
U.Gasparini 10/04/03 1 Toward Physics TDR Barrel Muon week, Bologna, 9-12 April 2003 S (Computing&Core Software) schedule 2003-2005 - Computing TDR (due 2004) - Physics TDR (2005) st-DAQ TDR activity ta challenges’ alysis groups and Physics TDR

description

Toward Physics TDR. Barrel Muon week, Bologna, 9-12 April 2003. CCS (Computing&Core Software) schedule 2003-2005 - Computing TDR (due 2004) - Physics TDR (2005) - Post-DAQ TDR activity ‘Data challenges’ - Analysis groups and Physics TDR. CCS schedule. - PowerPoint PPT Presentation

Transcript of Toward Physics TDR

Page 1: Toward Physics TDR

U.Gasparini 10/04/03 1

Toward Physics TDR

Barrel Muon week, Bologna, 9-12 April 2003

- CCS (Computing&Core Software) schedule 2003-2005 - Computing TDR (due 2004) - Physics TDR (2005)

- Post-DAQ TDR activity

-‘Data challenges’

- Analysis groups and Physics TDR

Page 2: Toward Physics TDR

U.Gasparini 10/04/03 2

• 2003– June Switch from CMSIM to OSCAR– July Start full-scale 5 month production of GEANT4 events– Sept Baseline software for DC04 / C-TDR / Physics TDR

• 2004– April DC04 complete– April First Draft C-TDR– Oct Computing-TDR Submission

• 2005– April DC05 complete (LCG-3 validation)– Dec Physics-TDR Submission

• 2006– April DC06 complete (ready for real data)

CCS schedule

“data challenges”

Page 3: Toward Physics TDR

U.Gasparini 10/04/03 3

CCS and PRS Tasks and Milestones (V33) IDJ F M A M J J A S O N D J F M A M J J A S O N D

2003 2004

Preparations for DC04 pre-challenge phase1st draf t Physics Model (key Computing Model parameters) 1st draf t Physics Model (key Computing Model parameters)

1st draf t Computing Model (overall scope and resources) 1st draf t Computing Model (overall scope and resources)2nd draf t Physics Analysis Model (PRS tasks for DC04 def ined) 2nd draf t Physics Analysis Model (PRS tasks for DC04 def ined)

Physics-validated GEANT4 simulation of CMS CP-1067

LCG: General release of hybrid event store LCG

Fully func. f ramew ork & data management systems CS-1056

Tools for measuring and simulating the Computing Model Tools for measuring and simulating the Computing ModelProduction systems ready (50 kSI95, 50% using LCG-1)

DC04 Pre-Challenge PhaseDC04 simulation (50 million events CMKIN / OSCAR) DC04 simulation (50 million events CMKIN / OSCAR)2nd draf t Computing Model (overall design and DC04 def inition) 2nd draf t Computing Model (overall design and DC04 def inition)Fully func. detector & physics object reconstruction CP-014

Fully functional user analysis environment CS-026

Delivery of baseline core SW for CCS&Physics TDR's CS-1039

DC04 digitisation (luminosity of 2.10**33) DC04 digitisation (luminosity of 2.10**33)DC04 sample f inalisation (data moving, etc.) DC04 sample f inalisation (data moving, etc.)3rd draf t Computing Model (w / results of system modelling) 3rd draf t Computing Model (w / results of system modelling)

DC04 Data ChallengePRS analysis using COBRA, AOD's, OO anal. tools CP-1068

DC04 operation DC04 operationDC04 collation / interpretation of results DC04 collation / interpretation of resultsDC04 com plete CS-1041

Computing TDR CompletionFirst draf t Computing TDR CS-1040

Finalised Computing Model for TDR (w ith results f rom DC04) Finalised Computing Model for TDR (w ith results f rom DC04)Computing TDR submission CS-1042

CCS schedule (detailed 2003-2004)

CMSIM

OSCAR

development of first “full off-line” analyses (i.e. beyond HLT) onpredefined benchmark channels

Page 4: Toward Physics TDR

U.Gasparini 10/04/03 4

Post DAQ TDR activity

After completion of DAQ TDR (Dec.2002), main emphasis this year will be on:

- switch to GEANT4 simulation, reproducing/improving in OSCAR+ORCA (full C++) chain the known HLT results from CMSIM + ORCA - by- products: - new Detector Description Database (DDD) system - refine sub-detectors geometries (when needed)

[ e.g. for BMU: - insert proper staging between SL - insert chimneys - include “+ve” “-ve” chamber readout ]

- have consistent ORCA code between MC and TestBeam data analysis environment

MB2.2.4(courtesy ofM.Benettoni)

Page 5: Toward Physics TDR

U.Gasparini 10/04/03 5

Post DAQ TDR activity

-develop first full off-line analyses down to O(10-5-10-7) Hz rate on few relevant benchmark signals

- significant training/test of the software + computing system

HLT outpupt, di-mu stream ( 3 Hz)Low lumi (DAQ TDR, ch.15)

H WW 22(see M.Zanetti’s talk)

Page 6: Toward Physics TDR

U.Gasparini 10/04/03 6

Post DAQ TDR activityCurrent choises for full analyses within PRS/mu:

- H ZZ* 4

2-mu topologies: - H WW 2(=> - challenging for background rejection; - hot channel in the early days of LHC )

- Z ’ 2in the 1-2 TeV region (=> - challenging for pT resolution; - impact of alignment; - showering muons ....)

These will likely to go in the “Volume 1” of the Physics TDR(=> devoted to detector response, reconstruction of physics objects, calibrations, detector parameterization), under responsability of PRS groups=> benchmark for any “fast/parametrized” simulation/reconstruction

“Volume 2”: High-level analyses, like Higgs, Supersymmetry, Exotic physics, etc.=> “physics reach”of CMS , scan of models’ parameters space.... (responsability of new analyses groups)

next slide...

Page 7: Toward Physics TDR

U.Gasparini 10/04/03 7

SM Higgs searches

Compare Tevatron:

H WW 2l

H ZZ* 4l

Run II A Luminosity

They are here

140 GeV

Page 8: Toward Physics TDR

U.Gasparini 10/04/03 8

“Data challenge” preparation

In Febr.’04, CMS will perform its first significant “Data Challenge” (DC04)i.e. large scale test of computing and analysis model:

Inject into the system a “sustained data-taking rate of 25 Hz at luminosity 2 1033 for 1 month” ( =>50 107 events), filter and analize them down to “physics plots”(+ calibration/alignment activity...)

prepare 50 M ev datasample (=> pre-data challange phase, MC production 10 times larger than for DAQ TDR; huge effort, GEANT4 training on big MC simulation (timing, crashes,...), Grid training, ect...): it will last 6 months, 2nd half of 2003

finalize HLT code for “Tier0” operations (50 M ev will be at HLT output)

use the 50 M ev for preliminary Physics TDR analysis (this will last presumably all 2004, after the DC04 itself)

see Silvia’s talk for PRS/mu details

Page 9: Toward Physics TDR

U.Gasparini 10/04/03 9

Analisys groups

New “analysis groups”:

1. Heavy Ions Bolek Wyslouch (MIT)2. Higgs Sasha Nikitenko (IC)3. Standard Model Joachim Mnich (Aachen)4. SUSY/other Beyond the SM Luc Pape (CERN)

Convenor

First meetings during next CPT week (5-9 May)

New CPT week layout to allocate time for the new groups

Page 10: Toward Physics TDR

U.Gasparini 10/04/03 10

New CPT layout:

Start Time Monday Tuesday Wednesday Thursday Friday

8.30 Tracker Muons b/tau CPT Plenary CPT Plenary Break Break Session 1 Session 3

10.30 Higgs SUSY and Beyond SM 14:00 ECAL HCAL PRS Steering e/gamma JetMET Committee CPT Plenary CPT Plenary Break Break Break Session 2 Session 4 16:30 Standard Heavy Ions CPT JTB Model (Joint Technical Board)This time (5-8 May): Physics Workshop on Thursday 8th May (whole day)

(see: http: //cmsdoc.cern.ch/cms/PRS/www/CPTweek_PRS_schedule.html )

Page 11: Toward Physics TDR

U.Gasparini 10/04/03 11

Higgs Physics/Symmetry breakingOverview of CMS results and current work (15') Sasha Nikitenko10:15 Higgs to sparticles and Higgs in cascade decays (25') Filip Moortgat10:45 Higgs in SM and MSSM (I) (30') Michael Spira11:15 Higgs in SM and MSSM (II) (30') Abdelhak Djouadi11:45 WW scattering (30') Ezio MainaSUSY and other beyond SMOverview of CMS results and current work on SUSY (25') Alessia Tricomi14:25 SUSY benchmarks (25') John Ellis14:50 Comparison of SUSY generators (25') Sabine Kraml15:15 Extra Dimensions and black holes (25') Gian Giudice 15:40 Radions (20') Daniele Dominici Standard ModelOverview of CMS results and current work (25') Michael Dittmar 16:55 Top quark, electroweak physics etc (TBC) (30') Michelangelo Mangano 17:25 QCD (TBC) (30') James Stirling Heavy IonsHigh-Pt probes in Heavy-Ion Collisions (30') Urs Wiedemann

CMS Physics workshop

CERN, 8th May 2003