Total Project Activities
-
Upload
adonis-kum -
Category
Documents
-
view
227 -
download
0
Transcript of Total Project Activities
PROJECT DEVELOPMENT
Pre-Feasibility Study
Feasibility Study
Development
Detailed Design
Construction
FEASIBILITY STUDY
Production of a detailed site plan.
Calculation of solar resource and environmental characteristics.
Assessment of shading (horizon and nearby buildings and objects).
Outline layout of areas suitable for PV development.
Assessment of technology options providing cost/ Benefit for the project location
Module type.
Mounting system.
Outline system design.
Calculation of shade and initial PV plant layout
Shading angles.
O&M requirements.
Module cleaning strategy.
Tilt angle and orientation.
Temperature and wind profiles of the site.
Cable runs and electrical loss minimisation.
Module selection.
Inverter selection.
Mounting frame or tracking system selection
Electrical cabling design and single line diagrams.
Electrical connections and monitoring equipment.
Grid connection design.
Full energy yield analysis using screened solar data and the optimised layout.
Application for outline planning permission.
Grid connection - more detailed assessment of likelihood, cost and timing.
Predicted energy yields
Financial modelling.
DEVELOPMENT PHASE
Preparation and submission of the permit applications for the proposed solar PV project.
Preparation and submission of a grid connection application.
Revision of the design and planning permissions.
Decision on contracting strategy (turnkey EPC contract or multi- contract).
Decision on the financing approach.
Preparation of solar PV module tender documentation.
Supplier selection and ranking.
Preparation of construction tender documentation.
Contractor selection and ranking.
Contract negotiations.
Completion of a bankable energy yield
assessment of inter-annual variation and yield confidence levels.
Consideration of site-specific factors
Full shading review of the PV generator
Detailed losses.
review of the proposed design ensure that parameters are within design tolerances.
Preparation of a financial model covering the full life cycle of the plant.
Completion of a project risk analysis.
Environmental impact assessment.
Production of a detailed project report.
Securing financing for the project.
PLANT DESIGN
Electrical Design
DC systems
Array(s) of PV modules.
Inverters.
DC cabling (module, string and main cable).
DC connectors (plugs and sockets).
Junction boxes/combiners.
Disconnects/switches.
Protection devices.
Earthing.
AC systems
AC cabling.
Switchgear.
Transformers.
Substation.
Earthing and surge protection.
Automatic data acquisition and monitoring technology
Mounting structures
Control building
Access roads
Site security systems
PERMITS AND LICENSING
Land lease contract.
Environmental impact assessment
Building permit/planning consent
Grid connection contract.
Power purchase agreement.
COMMISSIONING TESTS
Visual acceptance tests.
Pre-connection acceptance tests.
Post-connection acceptance test.
Performance ratio test
Availability test
OPERATIONS AND MAINTENANCE
Scheduled or preventative maintenance
Module cleaning.
Checking module connection integrity
Checking junction / string combiner boxes.
Thermographic detection of faults.
Inverter servicing.
Inspecting mechanical integrity of mounting structures.
Vegetation control.
Routine balance of plant servicing / inspection.
Unscheduled maintenance
Tightening cable connections that have loosened
Replacing blown fuses.
Repairing lightning damage.
Repairing equipment damaged by intruders or during module cleaning.
Rectifying supervisory control and data acquisition (SCADA) faults.
Repairing mounting structure faults.
Rectifying tracking system faults.
ECONOMICS AND FINANCIAL MODELING
Capital costs.
Operations and maintenance costs
Annual energy yield.
Energy price -.
Certified Emission Reductions
Financing assumptions
Sensitivity analysis -
FINANCING PV PROJECTS
Legal due diligence permits and contracts (EPC and O&M).
Insurance due diligence adequacy of the insurance policies
Technical due diligence:
Sizing of the PV plant.
Layout of the PV modules, mounting and/or trackers, and inverters.
Electrical design layout and sizing.
Technology review of major components(modules/inverters/mounting or trackers).
Energy yield assessments.
Contract assessments (EPC, O&M, grid connection, power purchase and Feed-in Tariff ( FiT) regulations).
Financial model assumptions.
DETAILED PROJECT REPORT
Site layout
Mounting frame and module layout.
Inverter locations and foundations/housings.
Security measures.
Buildings and other infrastructures.
Initial electrical layouts:
Schematics of module connections through to the inverter.
Single line diagrams showing anticipated cable routes.
Grid connection and potential substation requirements.
Bill of materials for major equipment.
Energy yield analysis.
Losses assumed with regard to the energy yield forecast.
Financial model inputs including:
Long term O&M costs and contingencies.
Availability assumptions.
Degradation of module performance assumptions.
Spare parts inventory cost.
Connection cost for electricity and services.
Details of the permitting and planning status.
Environmental impact assessment, restrictions and mitigation plans.
DETAILED DESIGN
Detailed layout design.
Detailed civil design
Buildings
Foundations
Access roads
Drainage
Water supply
Electrical detailed design.
Overall single line diagrams.
MV & LV switchgear line diagrams.
Protection systems.
Interconnection systems and design.
Auxiliary power requirements.
Control systems.
Revised energy yield.
Construction plans.
Project schedule.
Interface matrix.
Commissioning plans.
PLANT DESIGN
Technology Selection
Modules
Quality Benchmarks
Product guarantee -
Power guarantee
Lifetime
Inverters
Quality Benchmarks
Incorrect polarity protection for the DC cable.
Over-voltage and overload protection.
Islanding detection for grid connected systems
Insulation monitoring.
Mounting Structures
Concrete piers cast in-situ -
Pre-cast concrete ballasts
Driven piles -
Earth screws
Layout and Shading
General Layout
Tilt Angle
Inter-Row Spacing
Orientation
Electrical Design
DC systems
PV Array Design
Inverter Sizing
Cable Selection and Sizing
Cable Management
Module and String Cables
Main DC Cable
Junction Boxes
Connectors
String Fuses
DC Switching
DC Switches/Disconnects
DC Circuit Breaker
Quality Benchmarks
AC systems
AC Cabling.
AC Switchgear.
Sizing and Selecting Transformers
Substation
Metering
Data Monitoring/SCADA
Auxiliary equipment
LV power supplies.
Back-up power supplies.Uninterruptible power supply (UPS) batteries. Diesel generators.Auxiliary transformers and grid connections.Telephone and internet connections.Lighting.Heating Ventilation and Air Conditioning (HVAC).
Water supplies.Drainage.
Fire and intruder alarms.
Earthing and surge protection.
Array frame earthing.
System earthing (DC conductor earthing)
Inverter earthing.
Lightning and surge protection.
Quality Benchmarks
Infrastructure
Office
LV/MV station
MV/HV station
Communications
Quality Benchmarks
Site Security
visibility of the power plant
fence with anti-climb protection
Security cameras, lights and microwave sensors
Quality Benchmarks
Anti-theft module mounting bolts
Anti-theft module fibre systems
guarding station with security guard
alarm system fitted to power plant gate
alarm system in the medium voltage station
alarm system in the metering station
alarm system in the portable cabins
Monitoring and Forecasting
Monitoring Technology
On-site weather stations -
Meteorological data gathered from weather satellites
Local weather stations
Forecasting Technology
Quality Benchmarks
Optimising System Design
Design Documentation Requirements
Datasheets of modules, inverters, array mounting system and other system components
Wiring diagrams
Layout drawings
Mounting structure drawings
Mounting structural calculations
detailed resource assessment and energy yield prediction.
design report
PERMITS AND LICENSING
Permitting, Licensing and Regulatory Requirements - General
Land lease contract.
EIA.
Building permit/planning consent.
Grid connection contract.
Power purchase agreement.
Social and Environmental Sustainability
Permitting, Licensing and Regulatory Requirements - India
Project Start-up
Ministry of New and Renewable Energy
State Nodal Agencies
Ministry of Civil Aviation
Ministry of Defence
Power Purchase Agreement (PPA)
Land Agreement
Project Development and Implementation
District Advisory Committee
Planning Department
Archaeological Department - Consultation and
approval from the relevant archaeological department will confirm that the land acquired for the project is not of historical significance.
Fire Safety Authority -
Forest Authority -
Pollution Control Board -.
Irrigation Department -.
Industrial Development Corporation -
Local Governing Bodies
Construction power requirements -
Environmental Impact Assessment -
POWER EXPORT
Grid Connection -
Electrical Inspectorate -
CONSTRUCTION
Introduction
Interface Management
Programme and Scheduling
Scheduling
Tasks and durations.
Restrictions placed on any task
Contingency of each task.
Milestones and key dates.
Interdependencies between tasks
Parties responsible for tasks
Project critical path.
Actual progress against plan.
Risk Management
Programme
Site access.
Security.
Foundation construction
Module assembly.
Mounting frame construction
Substation construction.
Electrical site works.
Grid interconnection works.
Commissioning and testing
Cost Management
Earned value management
Completion certificates
Snagging lists
Take-Over certificates
Contractor Warranties
Warranty Duration
Quality Management
Environmental Management
General
Air Emissions and Ambient Air Quality
Energy Conservation.
Wastewater
Water Quality
Water Conservation
Hazardous Materials Management
Wastewater and Waste Management.
Noise Emissions
Contaminated Land.
Health and Safety Management
General Facility Design and Operation
Communication and Training.
Physical Hazards.
Chemical Hazards.
Biological Hazards.
Personal Protective Equipment (PPE).
Special Hazard Environments.
Monitoring.
Community Health and Safety
Water Quality and Availability.
Structural Safety of Project Infrastructure
Life and Fire Safety (L&FS
Traffic Safety.
Transport of Hazardous Materials
Disease Prevention
Emergency Preparedness and Response.
DESIGN REVIEWS
Design basis statements
Studies/investigations
Design specifications
Design of structures
Drawings (all revisions)
Calculations
Execution plans
Risk assessments and method statements
Quality plans
Safety plans/reports
Material and equipment selection
O&M manuals
Test reports.
COMMISSIONING
General
Module strings.
Inverters.
Transformers.
Switchgear.
Lightning protection systems.
Earthing protection systems.
Electrical protection systems.
Grid connection compliance protection and disconnection systems.
Monitoring systems (including irradiation sensors).
Support structure and tracking systems
Pre-Connection Acceptance Testing
Open Circuit Voltage Test.
Short Circuit Current Test.
Grid Connection
Post Connection Acceptance Testing
DC current test.
Performance ratio test.
Availability Test
Provisional Acceptance
Handover Documentation
OPERATION AND MAINTENANCE
Scheduled/Preventative Maintenance
Module Cleaning
Module Connection Integrity
Junction or String Combiner Box
Hot Spots
Inverter Servicing
Structural Integrity
Tracker Servicing
Balance of Plant
Vegetation Control
Unscheduled maintenance
Tightening cable connections that have loosened
Replacing blown fuses
Repairing lightning damage
Repairing equipment damaged by intruders.
Repairing equipment damaged during module cleaning.
Rectifying SCADA faults.
Repairing mounting structure faults
Rectifying tracking system faults.
Spares
Performance Monitoring, Evaluation and Optimisation
Contracts
Purpose
Contractor Services and Obligations
Obligations on the Owner
Standards, Legislation and Guidelines
Payment
Warranties
Legal
Insurance
Term of Agreement
Response Time
Selecting a Contractor
ECONOMICS AND FINANCIAL MODEL
Economic Benefits and Costs
Local Economic Benefits and Costs
National Economic Benefits and Costs
Benefits to Developers
CERC Cost Benchmarks
Capital Cost
Tariff Structure
Operations and Maintenance
Financial Model
Capital Costs
Annual Energy Yield
Energy Price
Certified Emission Reductions (CERs)
Financing Assumptions
Project Economics and Financial Modelling Results
Sensitivity Analysis
FINANCING PV PROJECTS
Project Financing
Financing Alternatives
Lender Evaluation of Project
Risks
General Business Risks
Interest Rates
Leverage
New Business Start-up
Technical Risks
Solar Module
Inverters and Cabling
Technology Failure
Solar Irradiation Risk
Solar Module Degradation
Pre Completion Risks
Cost Overrun
Delay in Completion
Permits, Grid Applications and Feed-in Tariff
Grid Connection
Delay in Obtaining an Operating Permit
Post Completion Risks
Market Risk
Change of Legislation
Operational Considerations
Insurance
Introduction
General Liability Insurance
Property Risk Insurance
Environmental Risk Insurance
Business Interruption Insurance1 MILESTONE-1: MODULE TO PCU OUTPUT- DETAIL DESIGN
2 DETAILED DESIGN OF GROUND PREPARATION FOR OTHER
3 STRUCTURE DESIGN
4 DETAILED DESIGN OF FOUNDATION FOR STRUCTURE
5 DETAILED DESIGN OF DC NETWORK
6 DETAILED DESIGN FOR LAYOUT OF PCU ROOM ALONGWITH FOUNDATIONS. CABLE ENTRY CUT OUT ETC (INCLUDING DOWNSTREAM AND UPSTREAM CONNECTIONS)
7 MILESTONE-2: DC SIDE
8 SUPPLY OF 50 MWp CRYSTALINE MODULES
9 SUPPLY OF 500KW Cd-Te THIN FILM MODULES
10 SUPPLY OF 500 KW A-Si THIN FILM MODULES
11 SUPPLY OF STRING MONITORING SYSTEM
12 SUPPLY OF SOLAR DC CABLE
13 SUPPLY OF INVERTERS FOR 9 MW
14 SUPPLY OF 8MW FIXED STRUCTURES
15 SUPPLY OF 1MW SINGLE AXIS TRACKER
16 MILESTONE-3: AC SIDE
17 SUPPLY OF TRANSFORMERS 1.25 MVA, 330 KV/11KV
18 SUPPLY OF TRANSFORMERS 12.5 MVA, 11 KV/66KV
19 SUPPLY OF 11KV PANEL
20 SUPPLY OF AC CABLE
21 SUPPLY OF SWITCHYARD ITEMS 66 KV
22 MILESTONE-4: SUB SYSTEM
23 SUPPLY OF SCADA SYSTEM
24 SUPPLY OF SOLAR OBSERVATORY AND WEATHER SYSTEM
25 SUPPLY OF PLANT SECURITY SYSTEM
26 BUILDINGS AND MATERIALS
27 SUPPLY OF MODULE WASHING SYSTEM
28 SUPPLY OF FIRE FIGHTING EQUIPMENT
29 SUPPLY OF DRAINAGE SYSTEM
30 SUPPLY OF AUXILIARY POWER SYSTEM/ DC EMERGENCY SYSTEM
31 SUPPLY OF HVAC SYSTEM
32 MILESTONE-5: ERECTION OF ALL SYSTEM
33 FOUNDATION WORKS
34 ERECTION OF STRUCTURES FIXED 50 MWp
35 ERECTION OF 50 MWp SINGLE AXIS TRACKER
36 ERECTION OF 50 MWp MODULES
37 ERECTION OF 500 KW Cd-Te THIN FILM MODULES
38 ERECTION OF 500 KW A-Si THIN FILM MODULES
39 INSTALLATION OF STRING MONITORING SYSTEM
LAYING OF SOLAR DC SYSTEM,
LAYING OF SOLAR DC CABLE
40 INSTALLATION OF INVERTERS FOR 50 MWp
41 INSTALLATION OF TRANSFORMERS 1.25 MVA, 330/11 KV
42 INSTALLATION OF TRANSFORMERS 12.05 MVA, 11/66 KV
43 INSTALLATION OF 11 KV PANEL
44 LAYING OF AC CABLE
45 INSTALLATION OF SWITCHYARD ITEMS
46 INSTALLATION OF SCADA SYSTEM
47 INSTALLATION OF SOWS
48 INSTALLATION OF PLANT SECURITY SYSTEM
49 INSTALLATION OF BUILDINGS
50 INSTALLATION OF MODULES WASHING SYSTEM
51 INSTALLATION OF FIRE FIGHTING SYSTEM
52 INSTALLATION OF DRAINAGE SYSTEM
53 INSTALLATION OF AUXILIARY POWER/ DC EMERGENCY SYSTEM
54 INSTALLATION OF HVAC SYSTEM
55 MILESTONE-6: TESTING AND COMMISSIONING
56 PRE-COMMISSIONING
57 COMMISSIONING/ SYNCHRONISATION
58 RELIABILITY TESTING/ PG TESTING
59 HANDING OVER