- 1 -
To: File No.: 02/18010013 NTA Metropolitan Mass Transit System Ltd. Date : 03/09/2018 Azrieli Center Building A 9th floor 26 HaroKm.in St. P.O box 1802, Holon
Israel 5885849 Attn: Adv. Zah Dahan -
Head of Insurance & Procurement [email protected]
Dear Sir,
UNDERWRITING INFORMATION FOR CONTRACT WORKS INSURANCE
Name of Principal :
NTA Metropolitan Mass Transit System (MTS) Ltd.
The Project : Construction of the Green & Purple Light Train Lines.
Telephone No. : +972-3-6366444 E-mail : [email protected]
Facsimile No. : +972-3-6366440
Web Site : https://www.nta.co.il/en/home
Surveyor : Shmuel Tossman -
Joint CEO MBA, B.Sc. Mech. Eng.
DISCLAIMER
In this report/survey we attempted to describe the subject matter, identify the relevant and main risks and/or hazards, all to the best of our professional ability, but we recognize the fact that it is impossible to include every detail, identify each and/or every risk and/or hazard nor is it possible to relate, in advance, to each and/or every warranted protection measure, process and/or procedure. We wish to state that our recommendations (where included) are given only as examples and all protection measures etc. should be carried out as per codes, standards and laws and the decision of their implementation rests with the Insured's management and/or with Insurers (or any other entity) – for whom this report/survey is intended.
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 2 -
Our report/survey was prepared, formulated and issued on the basis of information supplied by the Insured and/or by their Representatives and/or Consultants and/or Brokers and/or Agents and we therefore disclaim any responsibility for any errors and/or omissions and/or inaccuracies contained in this report/survey and we therefore deny any responsibility and/or legal liability for any loss and/or damage and/or any other matter resulting from the use of our report/survey or the use of any information contained in this report/survey, by any entity and/or anyone.
Executive Summary NTA Metropolitan Mass Transit System Ltd., a government company, is responsible for the design and construction of a mass transit system for the Tel Aviv metropolis. The Red Line, 24 Km. length, comprises of 12 Km. underground sections with 10 stations and 12 Km. at grade sections with a total of 24 stations, which is currently under construction, will be the first of a network of Light Rail Transit (LRT) to be operated by NTA. The Red Line is not the subject of this report!
The subject of this report is the construction of two (2) additional lines, the Green Line and the Purple Line, both of which are planned to be operational and used by the public at the end of 2024.
The Green Line is 39 Km. long, mostly at street level (at grade) with a 4.5 Km. underground section under the center of Tel Aviv, between the southern part of the inner ring (Holon), and northern part of the inner ring, (Rishon Lezion and Holon). The Green Line will cross four (4) municipalities, will have 58 stops, and four underground stations. The Green line will serve approximately 75 million passengers annually. The Purple line is 29 Km. long, an at street level LRT line between the eastern part of the inner ring, Giva't Shmuel, Ramat Gan, Yehud, and Tel Aviv. The Purple Line will cross eight (8) municipalities and will have approximately forty-Four (44) stops. The Purple Line will serve approximately 75 million passengers annually. The total project value, as stated by the Insured, before VAT, is some $ 8,663,632,000, which may be divided into the construction costs of each line as follows:
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 3 -
Description: Estimated Value - $
1. Estimated Construction Costs IRO the Green Line: 5,718,569,000
2. Estimated Construction Costs IRO the Purple Line: 2,945,063,000
_______________
Total Estimated Project Value: $ 8,663,632,000
• The Insured intend to carry out two (2) separate CAR Policies for the Infra 1 section only, one
(1) for the Green Line and the second for the Purple Line of the project, with Project Values as
follows:
1. Total Infra 1, Green Line: $ 620,032,000
2. Total Infra 1, Purple Line: $ 418,880,000
• The tunneling works in the Green Line are to be Insured by the Design Build contractor who will construct these;
• Starting the project works all along the project and completing construction and opening for public use of the entire Green Line:………………………………………………. 40 Months To the above we recommend adding a 12 months leeway, safety/buffer period;
• Starting the project works all along the project and completing construction and opening for public use of the entire Purple Line:………………………………………………. 72 Months
__________ Total Construction Period: 72 Months
To the above we recommend adding a 18 months leeway, safety/buffer period;
• The Insured intend to carry out two (2) separate CAR Policies for the Infra 1 section only, one
(1) for the Green Line and the second for the Purple Line of the project with Construction Periods,
including a 12 month leeway, safety/buffer period as hereunder:
1. Total Infra 1, Green Line: 72 Months
2. Total Infra 1, Purple Line: 66 Months
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 4 -
Table of Contents
A. DATUM:…………………………………………………………………………………..…… 5
B. GENERAL:…………………..………………………………………………………..………. 5
C. TOPOGRAPHY & SOIL:……………………………………………………………….……. 8
D. PROJECT DESCRIPTION:……………………………………………………..…………..11
A. The Green Line:………………………………………………………………………..... 12
B. The Purple Line:………………………………………………………………………..... 23
C. Division of the works to Infra 1 & Infra 2:…………………………………………..…. 28
D. Construction Methods:…………………………………………………………………... 29
E. New Austrian Tunneling Method (NATM):…………………………………………….. 32
E. PROJECT VALUE – SUMS OF INSURANCE:…………………………….…...……….. 33
F. CONSTRUCTION PERIOD:………………………………………………………….….… 35
G. RISRK, HAZARDS & PROTECTION MEASURES:…………………………………….. 41
H. SUMMARY:………………………………………………………………………………….. 46
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 5 -
A. DATUM:
As per your request of January 2018, we carried out a Contractor All Risks Underwriting Information Report, concerning the project in caption which involves the design and construction of two (2) new additional LRT Lines, the Green and the Purple Lines. Additional information required for our assignment was received in our office in a later date via Email.
Our findings, and conclusions and recommendations are as hereunder:
B. GENERAL: NTA Metropolitan Mass Transit System Ltd. is the company responsible for the design and construction of a mass transit system for the Tel Aviv metropolis. NTA is a government company founded in 1997 for the purpose of providing appropriate solutions for the metropolis’ transit problems. The construction of the main public transportation system of the Gush Dan region is the largest and most complex transportation project ever executed in Israel. The Light Rail – Contributing to the Commuter, the Metropolis, and the Country: 1. Fast, Smooth, and Continuous Transit:
• Right of way at junctions and traffic lights; • Capacity: 250-750 passengers, depending on number of train cars; • Short stop time at stations: Many doors, ticketing at the platform, and rapid passenger
turnover; • High-frequency schedule: A train at the station on average every three to six (3-6) minutes; • Connections with other means of public transportation;
2. A City in Renewal:
• Savings of millions of work hours through shortened entry times into the metropolis; • An awakening of commercial opportunities all along the rail route; • Upgrade of the urban texture and the public arena; • Rise in real estate values near the mass transit lines and stations; • Renewal of city streets and rehabilitation of urban landscape;
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 6 -
3. Cleaner Air:
• Electric engines powered by overhead cables; • Quiet engines without pollution; • Reduction of air pollution levels in the metropolis; • Reduction of number of buses; • Immediate reduction in environmental noise pollution resulting from cars and buses;
The Red Line will be the first of a network of Light Rail Transit (LRT) to be operated by NTA. This line represents part of a comprehensive plan to improve the welfare and quality of life of Israel’s citizens. In 2010, the government passed a decision to transfer responsibility for execution of the project to NTA. Pursuant to the government's decision, NTA began extensive recruitment of professionals in the fields of engineering, design, and infrastructure for purposes of the project. The above government decision to transfer execution of the project to NTA became a turning point for the project. After a brief period of organization, a series of operations were initiated simultaneously to advance all LRT lines. Relocation of infrastructure, preparation of execution tenders, change of organizational structure, and innumerable operations performed simultaneously, characterized the current phase of the project life cycle. In 2012, the scope of operations reached its zenith, with NTA issuing some of the largest execution tenders ever issued in Israel. The list of tenders included the Prequalification phase (PQ) for the conventional NATM digging works tender, the TBM digging works tender together with the station complex tender, and the SDAG (the train system that is the heart and brain of the project) tender. The professional conferences held by the company met an active response and saw the participation of dozens of international firms, including some of the leading and largest companies. The companies came from 12 different countries, a clear vote of confidence in NTA, the project, and the State of Israel. At the conclusion of the process, 18 giant international companies, some in partnership with Israeli firms, submitted their proposals for participation in the tender. The Red Line currently under construction:
The Red Line is a LRT line, 24 Km.. length, comprises of 12 Km. underground sections with 10 stations and 12 Km. at grade sections with a total of 24 stations. The Red Line will cross five (5) local municipalities in the Tel Aviv Metropolitan Area and will serve approximately 90 million passengers annually. Rush hour frequency for the LRVs arrival will be every 3 minutes. This line is not the subject of this report!
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 7 -
The Green and the Purple Lines are the subject of this report. Green line: The Green Line is 39 Km. long, mostly at street level (henceforth: at grade) with a 4.5 Km. underground section under the center of Tel Aviv, between the southern part of the inner ring (Holon), and northern part of the inner ring, (Rishon Lezion and Holon). The Green Line will cross four (4) municipalities, will have 58 stops, and four underground stations. The Green line will serve approximately 75 million passengers annually. Purple Line The Purple line is 29 Km. long, an at street level LRT line between the eastern part of the inner ring, Giva't Shmuel, Ramat Gan, Yehud, and Tel Aviv. The Purple Line will cross eight (8) municipalities and will have approximately forty-Four (44) stops. The Purple Line will serve approximately 75 million passengers annually.
The Three (3) Light Train Lines – The Red Line (already under construction), Green & Purple Lines
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 8 -
C. TOPOGRAPHY & SOIL:
The construction of both lines will be carried out in the Tel Aviv metropolitan area as well as in its surrounding cities and areas. Owing to the above, there is a diversity of soil conditions along the lines paths.
The lines' erection area – in the Tel
Aviv Metropolitan and its surrounding
cities and areas – NOT TO SCALE!
Additionally, the construction involves numerous types of buildings and structures, e.g. tunneling, excavating and various construction works of underground structures, the erection of bridges stations, depots etc.), which is to be carried out in many types of locations, e.g. under the city streets, inside densely populated areas, sometimes in open areas. The above mandates extensive investigation of the areas in which the works are to be carried out in as well as the soil conditions in these. As the soil investigation (for pavements, structures and environmental aspects) is still going on, and some of the work areas are still not accessible, no soil investigation reports are available as of yet. However, in each of the construction areas a soil report will be prepared and/or the soil conditions are to be addressed prior to the construction work. Based on our experience and involvement with the Red Line works we can report as follows regarding the soil conditions and the groundwater levels: Soil Conditions: The region where the works will be carried out is a roughly flat region comprising sand dunes. Coarse Sand (Kurkar) layers appear at shallow depths, emerging on surface occasionally. The highest areas in the local topography are located some 25 m. above sea level, with some places having the altitude of some thirty to forty meters (30 m. - 40 m.) above sea level. The works will be carried out along sand dunes, red clay sand, Kurkar formations and final alluvial clay. In few places, some material of organic origin can be found. The layers thickness ranges from a few meters of clay or clayey sand layers, up to some ten (10) m. of sand and Kurkar layers. The Kurkar can be found deeper in the Tel Aviv area, as it can reach the depth of some one hundred to a hundred and fifty meters (100 m. - 150 m.) below ground level.
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 9 -
Generally speaking, the Kurkar and the soils in the region have little or no cohesion, but an angle of friction of 35 to 40 degrees. The number of SPT strokes in the Kurkar is found usually between 25 and 35 strokes in formations with a lower bearing capacity, generally at more superficial levels, and values between 40 and 50 strokes in formations with greater capacity, generally in deeper levels. Ground Water:
The water table is at around the same level as the sea water or higher. The Stations have most of their cross-sections submerged. The TBM and NATM tunnels and main parts of the C&C Structures and Stations are submerged. Measures to prevent water ingress during construction and for the final stage are required. Given the high permeability of material, it is expected that dewatering works will be effective. The soil reports will cover the following: » Description of the soil conditions, as well as the ground water levels prevalent of site, either
based on soil investigations, i.e. test boreholes with Standard Penetration Tests (SPT) carried out in these and soil samples taken for analysis, excavations, and/or on information from previous soil investigation in the area, is to be carried out along all paths of the constructed lines;
» Aspects relating to ground water including required dewatering, protection against flooding and water damage etc.;
» Foundations for the following structures constructed in the project by various methods and
including soil replacement:
• Drainage tunnels and ducts;
• Various support walls including:
• Conventional (excavation and refill) support walls;
• Terre Armée support walls;
• Water culverts of various types;
• All Tunnels along the path of the lines as well as the tunneling methods;
• Embankments for lines etc.;
• All Bridges along the path of the lines as well as the bridging methods;
• All construction of buildings and structures, including Underground Stations, Depots etc.;
• All Junctions, Traffic Crossings (vehicles, pedestrians, rail etc.);
• Agricultural Passes;
• Substrates under rails etc.; » Recommendations IRO required soil replacements;
» Recommendations IRO soil compaction/layers where required/relevant;
» Recommendations IRO revetment walls;
» Stabilization of slopes using anchors;
» Recommendations URO excavation methods;
» Recommended open excavation slopes;
» Stabilization of excavations using rock bolts;
» Drilling and casting of piles;
» Tunneling works of all types (TBM, C&C, Drill & Blast etc.);
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 10 -
Also, Hydrological report concerning relevant sections of the constructed lines will be carried out prior to the works, as warranted. These will address the issues for flows, drainage basins, rivers, other water bodies etc. The main issues that are to arise from the soil and hydrological reports are as follows:
• It is recommended that the contractors, the project managers and others adhere strictly to all the recommendations and conclusions of the soil and foundations report, the instructions of the constructor, the hydrologists, etc.;
• It is recommended that the contractors, the project managers and others take special care when carrying out works below or close to the site groundwater level, mainly during tunneling, underground construction, relocation of infrastructures, etc.;
• In addition, the report should be revised in accordance with any new finding, change of planning, etc., for their comments, recommendations and so on, in order to reduce the risks involved in the project;
• Additionally, the situation described in the above reports may be altered due to the project works, especially concerning disruptions in the precipitation flow, which may result in flooding of the project works as well as third party property;
• The sensitivity of clay types of soil layers to both swelling, if these absorbed water or humidity, as well as to the subsidence of these layers when water escape from these layers is brought to the attention of designers and the contractors/the Insured/ on should also acknowledge the fact that clay layers can't be properly compacted if these contain water or moisture;
• The project works involve changing of the existing slopes and erecting new ones and therefore, these will be susceptible to erosion until the vegetation protects these and/or until other protections (still mesh with sprayed concrete etc.) is in place. It is recommended that the contractors, the project manager and others take care IRO drainage of the slopes and particularly the prevention of the drainage of runoff on these, rain water that palls directly on the slops;
Prior to the construction works in any part/segment/area of the lines the investigation of the environment/the surrounding areas is to be carried out, which will address the following issues: A. The location of adjacent building and structured in the vicinity of the works, mainly the
tunneling, the underground stations and the construction of the lines in Tel Aviv, the surrounding cities and other densely and other populated areas including reference to the following:
1. The condition of the building/structure;
2. Year of construction;
3. Type of foundations;
4. Type of construction works (tunneling, construction of an underground station,
embankment construction, etc.);
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 11 -
5. Relocation, Demolition as well as required Strengthening of various buildings and structures; Along underground or lower than ground level sections of the lines, which will require excavation near buildings or building's strengthening, the surrounding buildings' condition will be documented.
B. The location of all infrastructures in the vicinity of the works, both underground as well as
at grade infrastructures, including but not limited to the following:
1. Cables of all types including: » Electric Power/Electricity, both high and low voltage; » Communications cables, including lines, wires, fiber optic etc.;
2. Pipes and piping systems of all types including:
» Water metal, plastic, concrete etc. pipes; » Sewage metal, plastic, concrete etc. pipes; » Oil & Petrol pipes; » Gas pipes;
D. PROJECT DESCRIPTION:
The Green and the Purple Lines' construction of major parts was authorized by the Government and thus construction works are intended to commence in various locations along their paths with preliminary works on the Green Line starting in year 2018.
By year 2024 all three (3) lines are intended to be operational:
• The Red Line already
under construction, and
which is not the subject
of this report, will start its
operations in year 2021;
• The Green and Purple
Lines, which are
describe in this report,
are intended to start
their operation in year
2024;
A. The Green line:
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 12 -
The Green Line is a light rail line to be operated in the Tel Aviv metropolitan area mass transit system. The line will connect the southern portions of the Gush Dan metropolitan area i.e. the city of Holon and the outskirts of Rishon Lezion, with the city of Tel Aviv.
The Green Line is to serve as the connecting line of the planned mass transit system, providing a solution for future development along the coast between the cities of Tel Aviv and Herzliya, and enabling accessibility to the employment centers in Ramat Hahayal, Tel Aviv University, Holon, and Rishon Lezion. The Green Line will be some forty (40) Km. long, mostly at ground level with a 4.5 Km. of underground section under the center of Tel Aviv, and a 0.3 Km C&C section near Tel-Aviv University, between the southern part of the inner ring (Rishon Lezion and Holon), and northern part of the inner ring, (Herzliya and northern Tel Aviv). The Green Line will cross four (4) municipalities, will have fifty eight (58) station on the street level and four (4) underground stations.
The southern section of the line has two (2) branches – the first (1st), the Western branch, begins in Rishon Lezion (Moshe Dayan station), and the second (2nd), the Eastern branch, also begins in Rishon Lezion at the meeting of Road 412 with the Blue Line station.
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 13 -
Both branches run through the city of Holon along two (2) routes, come together at Sokolov St. in the Holon city center, from where the line continues north through Holon Interchange, along Har Zion Blvd. in Tel Aviv, through the central bus station region and a crossing of the Purple Line at the intersection of Har Zion-Levinsky. From there the line goes underground, through the Karlibach station shared with the Red Line. It continues through Ibn Gvirol St., again meets the Purple Line at the Arlozorov-Ibn Gvirol intersection, and returns above ground before crossing the Yarkon river by way of a bridge crossing the Rokach Interchange and Sde Dov. The line splits at Einstein St. into two (2) branches: 1. The Eastern branch, towards Ramat Hahayal, through Einstein St., meeting the bus lane at the
Einstein-Namir intersection, continuing to Tel Aviv University, George Weiss St., crosses Ayalon Freeway, passes near Yarkon Park and the convention center, goes through Ramat Hahayal to Kiryat Atidim;
2. The Norther branch, continues parallel to the coastline up to the Herzliya's industrial zone and
the intersection of Abba Eban Blvd. and Naomi Shemer Blvd.; The line has several intersections with other transit lines:
» Meeting the Purple Line at the Levinsky Tel Aviv station and Arlozorov Tel Aviv station; » Meeting the Red Line at the Moshe Dayan station in Rishon Lezion, and Carlebach station; » Meeting the Yellow Line at the Holon Junction and at two (2) other points in the Ramat
Hahayal region of Tel Aviv; » Meeting the Blue Line on Road 412 in Rishon Lezion and at the Holon Junction; » Meetimg the Pink Line in Herzliya;
Additionally, there is a connection to Israel Train Lines at the Moshe Dayan station in Rishon Lezion, at the Holon Junction, and at the Tel Aviv University stop.
The Green Line will be divided into five (5) sections as follows:
Name Description Length [Km..] Nature of Sub-Section 1. G1 Southeastern Sub-Section 7.9 A Street Level Sub-Section;
2. G2 Southwestern Sub-Section 6.7 A Street Level Sub-Section;
3.
G3 Central Sub-Section 8.3 4.1 Km.. - An Underground Sub-Section; 4.2 Km.. - A Street Level Sub-Section;
4. G4 Northeastern Sub-Section 9.5 A Street Level Sub-Section;
5. G5 Northwestern Sub-Section 7.5 A Street Level Sub-Section;
_________ Total Green Line Length: 39.9 [Km..] Comment: At Grade/
Partially Submerged/On a Dridge
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 14 -
The Green Line's division into Sub-Sections
1. G1 - Southeastern Sub-Section:
• Length – 7.9 [Km..];
• No. of Stations: 13; Structures in Sub-Section: 1) Underground Vehicle
Passage in Mifratz Shlomo Junction;
2) Underground Vehicle Passage in Kugel Junction;
3) Hasayarim Bridge in the Holon East Interchange;
Additional element in section - Depot;
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 15 -
2. G2 - Southwestern Sub-Section:
• Length – 6.7 [Km..];
• No. of Underground Stations: 11;
3. G3 - Central Sub-Section:
• Length – 8.3 [Km..]:
4.1 Km.. –
An Underground Sub-Section;
4.2 Km.. - A Street Level Sub-Section;
• No. of Street Level Stations: 7: 1 on bridge, 6 on streel level;
• No. of Underground Stations: 4;
• The Levinsky Sunken Station (Levinsky Portal);
Structures in Sub-Section: 1) The Levinsky Southern Portal; 2) The Levinsky street passage & station; 3) The Nordau Portal; 4) The Yarkon passage bridge; 5) The Rokah passage bridge including a station on the bridge;
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 16 -
4. G4 - Northeastern Sub-Section:
• Length – 9.5 [Km..]:
• No. of Street Level Stations: 13: 2 on bridges, 11 on streel level;
• No. of Underground Stations: 1;
Structures in Sub-Section: 1) The Sunken train passage in the Namir/Einstein junction including underground station; 2) The Underground passage in Shalom Rosenfeld St.; 3) The Ayalon Bridge; 4) The Rokah Bridge; 5) The Underground passage below the train in Shitrit Bechor; 6) The Shitrit Bechor passenger bridge; 7) The Pinkas Rosen Bridge including a station on the bridge; 5. G5 - Northwestern Sub-Section:
• Length – 7.5 [Km..];
• No. of Street Level Stations: 14;
Additional element in section - Depot;
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 17 -
Green Line Work Parcels: Each of the Sub-Sections of the line is further segmented as follows: G1 Sub-Section's Segments:
Segment: Name: Type: Description: Length [Km..]:
Complexity: Orthophoto
G1-1 A.G. Rishon East
Above Ground Level
From Macabim Station fast Holon Depot;
1.53 Low
G1-2 Depot Holon
Depot Holon Depot; Low
G1-3 Sayarim Br.
Bridge Completion of Sayarim Bridge;
0.22 Medium
G1-4
A.G. Jerusalem
Above Ground Level
Completion of Mercava Bridge, Jerusalem Blvd. Underground Passage & Expropriations;
2.03 Medium
G1-5
A.G. Sokolov
Above Ground Level
Traffic Arrangements & Expropriations in Sokolov;
2.18 Medium
G1-6 A.G. Kugel Above Ground
Level
Level Separation of Kugel Junction;
1.86 Medium
Holon
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 18 -
G2 Sub-Section's Segments:
Segment: Name: Type: Description: Length [Km..]:
Complexity: Orthophoto
G2-1
A.G. Rishon West
Above Ground Level
Housing Relocation in Moshe Dayan Blvd. & Avrahab Bar St.;
2.96 Medium
G2-2
A.G. Holon
Above Ground Level
Building Expropriations in Phichman St. from Erlich St. till connection to Sokolov St.;
3.64 Medium
Holon
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 19 -
G3 Sub-Section's Segments:
Segment: Name: Type: Description: Length [Km..]:
Complexity: Orthophoto
G3-1 A.G. South
Above Ground Level
Above Ground Level Segment following Holon Junction up to Levinsky Portal, Trees Relocation & Buildings Clearing;
2.28 Medium
G3-2 Levinsky Levinsky Portal, Station, Entrance Shaft &
evacuation of commerce booths; 0.525 High
G3-3 U.G. South
Southern Tunnels
Levinsky-Karlibach Tunnels; 0.725 High
G3-4 Karlibach St.
Karlibach Station*
Green Line Level – Karlibach Station; 0.275 High
G3-5 U.G. North Northern
Tunnels
Strenghning of "Alyho House" Karlibach-Nordau TMB Tunnels;
2.825 High
G3-6 Nordau Nordau
Shaft
Underground Portal; 0.15 High
G3-7 A.G. Ibn Gabirol
Above Ground Level
Development of Above Ground Level; 2.65 Medium
G3-8 Rokach Brig.
Bridge Construction of Yarkon-Rokach Bridge, Rokach Station & Relocation of Water Culvert;
1.05 Medium
G3-9 A.G.North Above
Ground Level
Shy Agnon Station; 0.65 Low
* The Karlibach Station is the only station that is a joint station to the Green and Purple Lines however, each line will pass at a different level and it is expected that the Red Line's works in the station will be complete before the works on the Green Line start.
Tel-Aviv
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 20 -
G4 Sub-Section's Segments:
Segment: Name: Type: Description: Length [Km..]: Complexity:
G4-1 A.G. Levi Eshkol Above Ground
Level Segment;
Above Ground Level Segment following Shay Agnon Station until Einstein St.;
1.11 Low
G4-2 Namir Namir Station; Underground Station (Namir-Einstein Junction); 0.5 Medium
G4-3 A.G. University Above Ground
Level Segment;
Above Ground Level Segment in Einstein & Haim Levanon Streets;
1.31 Medium
G4-4 Mercaz Hayeridim Underground Passage for light train in Portal, Tunnel, Cut & Cover exit from Tunnel to Bridge & Bridge over Rokach;
1.23 High
G4-5 A.G. Hapark Above Ground
Level Segment;
Above Ground Segment which includes the Park & the Stadium Stations;
1.66 Low
G4-6 Railway Cross Above Ground
Level Segment;
Underground Passage for light train in Israel Rail Crossing in Shitrit St.;
0.06 Medium
G4-7 Pedestrian Brig. Pedestrian
Bridge;
Dismantling & Construction of Pedestrian Bridge in Shitrit St.;
- Low
G4-8 Pinkhas Rosen Station on Bridge; Station on Bridge & Dismantling of 2 Buildings; 1.52 Medium
G4-9 A.G. East Above Ground
Level Segment;
Above Ground Segment (HaBarzel, HaNechoshet, Dvora HaNeviah & Neve Sharet Stations);
2.21 High
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 21 -
Orthophoto
Tel-Aviv
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 22 -
G5 Sub-Section's Segments:
Segment: Name: Type: Description: Length [Km..]:
Complexity: Orthophoto
G5-1 A.G. Dov Above Ground
Level
Dov & Einstein Stations in Dov Airport;
1.65 Low
G5-2 A.G. Einstein
Above Ground Level
Connection to G4 Sub-Section;
1 Low
G5-3 A.G. Tlv Above Ground
Level
Above Ground Level in Tel-Aviv Area;
3.4 Low
G5-4 A.G. Herzeliya
Above Ground Level
Above Ground Level in Herzeliya Area;
2.3 Low
G5-5 Depot Herzeliya
Depot Herzeliya Depot; 0.2 Low
The Green line is expected to serve approximately 65 million passengers annually by year 2030.
Tel-Aviv
Herzeliya
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 23 -
B. The Purple Line:
The Purple Line will be some 29 Km. in length, will include forty five (45) stations, two (2) which will be combined with stations of the Red Line and two (2) other with the Green Line. The line will pass through eight (8) municipalities, seven (7) cities and one (1) regional council.
As per a Government decision the Purple Line was separated into the Western and Eastern sections, with the western section being split into the western & central sub-sections.
Tel-Aviv
Qiryat-Ono
Bnay-Brak
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 24 -
The Western Section:
The length of the Western Section is approximately 18 Km. and it includes twenty-nine (29) stations. The Western Section is divided into two (2) main segments PLW1 and PLW2. The section passes through the Tel Aviv, Ramat Gan, Givata'aim & Gival Shmuel municipalities.
The Eastern Section:
The length of the Eastern Section, which includes two (2) segments, will be some 10 Km., it will include sixteen (16) stations, a Depot, a Park & Ride carpark with some 4,000 parking spaces. The Eastern section passes through the Ramat Gan, Gival Shmuel, Petah Tikva, Or-Yehuda & Yahud municipalities as well as through the Modi'in's regional councils.
Western Section (PLW1+PLW2)
Eastern Section (PLE)
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 25 -
Purple Line Sections: The Purple Line will be divided into three (3) sections as follows:
Name Description Length [Km..] Nature of Sub-Section
1. PLW1 Western Tel Aviv 10.2 At Grade
2. PLW2 Western Ramat Gan/Shiba 8.4 At Grade
3. PLE Eastern Section 10.4 At Grade
_________ Total Purple Line Length: 29 [Km..]
PLW1 Sub-Section's Segments – Western Tel Aviv:
Complexity: Length [Km..]:
Description: Type: Name: Segment WBS
Medium 0.5 TLV Municipality LRT
At Grade + Depot
Savidor to Namir Road + Temp Depot
Arlozorov WBS1
Medium 0.525 TLV Municipality LRT
At Grade Namir Road to Wizman
Arlozorov WBS2
Medium 0.72 TLV Municipality LRT
At Grade Wizman to Ibn Gvirol
Arlozorov WBS3
Medium 0.84 TLV Municipality LRT
At Grade Ibn Gvirol to Ben Yehuda
Arlozorov WBS4
Medium 1.2 TLV Municipality LRT
At Grade Arlozorov to Bugrashov
Ben Yehuda WBS5
Medium 0.45 TLV Municipality LRT
At Grade Bugrashov to Alenby
Ben Yehuda WBS6
Medium 0.4 TLV Municipality LRT
At Grade Alenby to King George
Ben Yehuda WBS6a
Medium 0.2 TLV Municipality LRT
At Grade Mugrabi Terminus Ben Yehuda/Alenby
WBS7
Medium 1.13 TLV Municipality LRT
At Grade King George to YL Peretz
Alenby WBS8
Medium 1.1 TLV Municipality LRT
At Grade YL Peretz to Lavendeh
Levinsky WBS9
Medium 0.05 TLV Municipality LRT
At Grade Demolition of Ha'hagana 23 building
Ha'hagana WBS10
Medium 0.4 TLV Municipality LRT
At Grade Ha'hagana Bridge Ha'hagana WBS11
Medium 1.3 TLV Municipality LRT
At Grade Ha'hagana Bridge (Lavendeh to Kehilat New York)
Ha'hagana WBS12
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 26 -
Complexity: Length [Km..]:
Description: Type: Name: Segment WBS
Medium 0 TLV Municipality LRT
At Grade Ha'hagana - Kfar Shalem
Kfar Shalem WBS13
Medium 0.75 TLV Municipality LRT
At Grade Development of Kfar Shalem
Kfar Shalem WBS14
Medium 0.07 TLV Municipality LRT
At Grade Demolition of Ha'hagana area (4 buildings)
Ha'hagana WBS15
Medium 0.6 TLV Municipality LRT
At Grade level
Hatayasim Road to Oded
Hatayasim Roa WBS16
PLW1 Sub-Section's Segments – Western (Ramat Gan, 471 Road):
Complexity: Length [Km..]:
Description: Type: Name: Segment WBS
Medium 1 Ramat Gan LRT At Grade Oded to Rabin Aluf Sade WBS1
Medium 0.4 Ramat Gan LRT At Grade Rabin Underpass Aluf Sade WBS2
Medium 0.8 Ramat Gan LRT At Grade
Paz Gas station (North) to Ben Zvi Gadren (Aluf Sadeh)
Aluf Sade WBS3
Medium 1.5 Ramat Gan LRT At Grade
Aluf Sadeh interchange + Shiba Road + Refael Eitan Junction
Aluf Sade WBS4
Medium 1.7 Ramat Gan LRT At Grade Refael Eitan Underpass (Shiba Road to 471 Road)
Shiba Road to 471 Road
WBS5
Medium 1.5 Ramat Gan LRT At Grade 471 Bridge to Bar Ilan station
Keren Ayesod WBS6
Medium 1.5 Givat Shmuel LRT At Grade Bar Ilan station to Jabotinsky
Max & Anna Wob WBS7
PLE Sub-Section's Segments – Eastern (461 Road):
Complexity: Length [Km..]:
Description: Type: Name: Segment WBS
Medium 1.6 Ramat Gan LRT At Grade Sheba Road to 461 Road (Yigal Allon junction)
Sheba Road WBS1
Medium 1.9 Or-Yehuda LRT At Grade Yigal Allon junction to Avia Junction
461 Road WBS2
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 27 -
Complexity: Length [Km..]:
Description: Type: Name: Segment WBS
Medium 5.1 Or-Yehuda / Yehud LRT
At Grade Avia Junction to Hatayasim Road
461 Road WBS3
Medium 0 Or-Yehuda / Yahud LRT
At Grade Preliminary works for Depot - Tayasim + Access
461 Road WBS4
Medium 1.8 Givat Shmuel LRT At Grade Bar Ilan to Rabin Road
Givat Shmuel WBS5
Road 461
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 28 -
The Depot at the Eastern end of Road 461
C. Division of the works to Infra 1 & Infra 2: The project works on both lines may also be divided into two (2) groups, as per two (2) types of works: Concerning the Green Line: Infra 1 – includes the relocation of infrastructures, bridges and works on submerged sections,
treatment of roads and sidewalks;
Infra 2 – includes all above grade buildings, track building, various systems, Depot sites and maybe completion of underground stations;
Concerning the Purple Line: Infra 1 – includes road construction (road building and paving), traffic arrangements, construction
works (including bridges, below grade passages, support walls), wet infrastructures, dismantling works, landscape development, final traffic arrangements etc.;
Infra 2 – includes all above grade buildings, track building, various systems, Depot sites and maybe completion of underground stations;
• The Insured intend to carry out two (2) separate CAR Policies for the Infra 1 section only,
one (1) for the Green Line and the second for the Purple Line of the project:
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 29 -
• The tunneling works in the Green Line are to be Insured by the Design Build contractor
who will construct these;
D. Construction Methods: The paths of the lines are to be either over ground or underground, as detained above. The construction over ground of railway lines involves significant earth works, including clearing, laying aggregates and substrates, construction of embankments etc., not unlike the paving of a new road. The above includes the required support walls, water drainage systems, including culverts, channels, pipes and ducts, earth replacement, laying of layer with required compaction etc. the construction also includes bridge construction, construction of depos and other required buildings/structures. Owing to the fact that parts of the lines will be underground lined in populated areas, the construction is to involve excavation, and later all other required works, to be carried out underground. There are several methods for carrying out these type of project, as detailed further on.
Tunnel Boring Machine (TBM):
A tunnel boring machine (TBM), consists of a shield (a large metal cylinder) and trailing support mechanisms. At the front end of the shield a rotating cutting wheel is located. Behind the cutting wheel there is a chamber where, depending on the type of the TBM, the excavated soil is either mixed with slurry (so-called slurry TBM) or left as-is (earth pressure balance or EPB shield).
The Cutting wheel of the TBM
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 30 -
Behind the chamber there is a set of hydraulic jacks supported by the finished part of the tunnel which are used to push the TBM forward.
Once a certain distance has been excavated (roughly 1.5-2 meters), a new tunnel ring is built using the erector. Behind the shield, inside the finished part of the tunnel, several support mechanisms which are part of the TBM can be found: Dirt removal, slurry pipelines if applicable, control rooms, rails for transport of the precast segments, etc.
The Mechanisms behind the Cutting Wheel of the TBM
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 31 -
The tunnel lining is the wall of the tunnel. It usually consists of precast concrete segments which form rings and are installed by a system called the Erector. The erector is a rotating system which picks up precast concrete segments and places them in the desired position.
These segments are brought on site and are constructed immediately behind the excavating section of the TBM, forming the final support of the tunnel, thus minimizing the possibility of collapses during construction of a new tunnel.
Erection of the Concrete Lining Sections by the TBM
Erection of the Concrete Lining Sections by the TBM
Tunnel boring machines (TBM) excavate tunnels with a circular cross section through a variety of
geologies. They can be used to bore through hard rock or sand and almost anything in between.
Tunnel diameters can range from one (1) meter (done with micro-TBM's) to fifteen (15) meters.
Tunnel boring machines are used as an alternative to drilling and blasting (D&B) methods. A TBM
has the advantages of not disturbing surrounding soil and producing a smooth tunnel wall. This
significantly reduces the cost of lining the tunnel, and makes them suitable to use in built-up areas.
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 32 -
The key disadvantage is cost. TBM's are expensive to construct, difficult to transport and require
significant infrastructure.
Modern TBM's typically have an integrated shield. The choice of a single or double shielded TBM depends on the type of geology and the excavation speed required.
Double shielded TBM's are normally used in unstable geology, or where a high rate of advancement is required. Single shielded TBM's, which are less expensive, are more suitable to hard rock geology.
E. New Austrian Tunneling Method (NATM): The NATM is an approach of philosophy integrating the principles of the behaviour of rock masses under load and monitoring the performance of underground construction during construction. The fact is that the NATM is not a set of specific excavation and support techniques. There are seven (7) features on which NATM is based:
1. Mobilization of the strength of rock mass - The method relies on the inherent strength of the surrounding rock mass being conserved as the main component of tunnel support. Primary support is directed to enable rock support itself;
2. Shotcrete protection - Loosening and excessive rock deformation must be minimised. This is
achieved by applying thin layer of shotcrete1 immediately after face advance;
1 Shotcrete is mortar or (usually) concrete conveyed through a hose.
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 33 -
3. Measurements - Every deformation of excavation must be measured. NATM requires
installation of sophisticated measurement instrumentation. It is embedded in lining, ground, and boreholes;
4. Flexible support - The primary lining is thin and reflects recent strata conditions. Used is rather active than passive support and strengthening is not by thicker concrete lining but by a flexible combination of rock bolts, wire mesh and steel ribs;
5. Closing of invert - Quickly closing of invert and create load-bearing ring is important. It is crucial in soft grounded tunnels where no section of tunnel should be left open even temporarily;
6. Contractual arrangements - Since the NATM is based on monitoring measurements, changes in support and construction method are possible. This is possible only if the contractual system enables these changes;
7. Rock mass classification determines support measures - There are main rock classes for tunnels and corresponding support. These serve as the guidelines for tunnel reinforcement;
Based on the computation of the optimal cross section, just a thin shotcrete protection is necessary. It is applied immediately behind the Tunnel boring machine, to create a natural load-bearing ring and therefore to minimize the rock's deformation. Additionally, geotechnical instruments are installed to measure the later deformation of excavation. Therefore a monitoring of the stress distribution within the rock is possible.
E. PROJECT VALUE – SUMS OF INSURANCE
The total project value, as stated by the Insured, before VAT, is some $ 8,663,632,000, which may be divided into the construction costs of each line as follows:
Description: Estimated Value - $
1. Estimated Construction Costs IRO the Green Line: 5,718,569,000
2. Estimated Construction Costs IRO the Purple Line: 2,945,063,000
_______________
Total Estimated Project Value: $ 8,663,632,000
Concerning the Green Line: Infra 1 – the Insured's estimate is some:………………………………………..$ 620,000,000;
Description: Budget - $
1. Buildings Architecture: 3,414,000
2. Road Works & Development: 64,265,000
3. Traffic Arrangements: 16,762,000
4. Relocation & Construction of Infrastructure: 3,838,000
5. Buildings Construction: 71,570,000
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 34 -
Description: Budget - $
6. Gardening & Irrigation: 30,183,000 ___________
Total Infra 1, Green Line: $ 620,032,000
Infra 2 – the Insured's estimate is some:………………………………………..$ 5,098,569,000; Concerning the Purple Line: Infra 1 – the Insured's estimate is some:………………………………………..$ 418,880,000;
The above may be divided as follows:
Description: Budget - $
1. Road Works: 82,053,000
2. Traffic Arrangements: 3,971,000
3. Construction Works: 117,111,000
4. Dry & Wet Infrastructures and Dismantling Works: 96,582,000
5. Landscaping: 82,282,000
6. Temporary Traffic Arrangements: 28,017,000
7. Acoustic Protections: 5,718,000
8. Drillings: 1,716,000
9. Monitoring: 1,430,000
_____________
Total Infra 1, Purple Line: $ 418,880,000 Infra 2 – the Insured's estimate is some:………………………………..ILS 2,526,183,000;
Remarks concerning the Project Value and the Sums of Insurance:
• The Insured intend to carry out two (2) separate CAR Policies for the Infra 1 section only, one
(1) for the Green Line and the second for the Purple Line of the project, with Project Values as
follows:
1. Total Infra 1, Green Line: $ 620,032,000
2. Total Infra 1, Purple Line: $ 418,880,000
• The tunneling works in the Green Line are to be Insured by the Design Build contractor
who will construct these;
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 35 -
F. CONSTRUCTION PERIOD: The Green Line's construction period of some forty-five (40) months, starting from the date of the Notice to Proceed (NTP) order. The above Green Line Work Parcels Time Table may be divided, as pert the type of segment constructed, as follows:
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 36 -
a) Green Line Above Ground Level Segments:
Segment: Description: Length [Km.]:
Construction Time Frame
1. G1-1 From Macabim Station fast Holon Depot; 1.53 09/12/2019 – 12/08/2021 2. G1-5 Traffic Arrangements & Expropriations in Sokolov; 2.18 31/03/2020 – 30/06/2022 3. G2-1 Housing Relocation in Moshe Dayan Blvd. & Avrahab Bar St.; 2.96 31/03/2020 – 30/03/2023 4. G2-2 Building Expropriations in Phichman St. from Erlich St. till connection to Sokolov St.; 3.64 31/03/2020 – 30/06/2022 5. G3-1 Above Ground Level Segment following Holon Junction up to Levinsky Portal, Trees
Relocation & Buildings Clearing; 2.28 31/03/2020 – 30/06/2022
6. G3-9 Shy Agnon Station; 0.65 09/12/2019 – 09/12/2020 7. G4-1 Above Ground Level Segment following Shay Agnon Station until Einstein St.; 1.11 09/12/2019 – 09/12/2021 8. G4-3 Above Ground Level Segment in Einstein & Haim Levanon Streets; 1.31 09/12/2019 – 08/04/2021 9. G4-5 Above Ground Segment which includes the Park & the Stadium Stations; 1.66 09/12/2019 – 08/04/2021 10. G4-9 Above Ground Segment (HaBarzel, HaNechoshet, Dvora HaNeviah & Neve Sharet Stations); 2.21 09/12/2019 – 07/03/2022 11. G5-1 Dov & Einstein Stations in Dov Airport; 1.65 31/03/2020 – 01/12/2021 12. G5-2 Connection to G4 Sub-Section; 1 09/12/2019 – 08/12/2020 13. G5-3 Above Ground Level in Tel-Aviv Area; 3.4 09/12/2019 – 07/03/2022 14. G5-4 Above Ground Level in Herzeliya Area; 2.3 31/03/2020 – 01/08/2022
b) Ground Level with lower than Ground Level Segment:
Segment: Description: Length [Km.]:
Construction Time Frame
15. G1-4 Completion of Mercava Bridge, Jerusalem Blvd. Underground Passage & Expropriations; 2.03 31/03/2020 – 01/08/2022 16. G1-6 Level Separation of Kugel Junction; 1.86 31/03/2020 – 31/03/2022 17. G4-2 Underground Station (Namir-Einstein Junction); 0.5 31/03/2020 – 30/10/2021
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 37 -
c) Special Segments:
Segment: Description: Length [Km.]:
Construction Time Frame
1. G1-2 Holon Depot; - 10/06/2021 – 31/12/2023 2. G1-3 Completion of Sayarim Bridge; 0.22 31/07/2019 – 07/03/2022 3. G3-2 Portal, Station, Entrance Shaft & evacuation of commerce booths; 0.525
02/10/2019 – 02/01/2024
4. G3-3 Levinsky-Karlibach Tunnels; 0.725 5. G3-5 Strenghning of "Alyho House" Karlibach-Nordau TMB Tunnels; 2.825 6. G3-6 Underground Portal; 0.15 7. G3-4 Green Line Level – Karlibach Station; 0.275 8. G3-7 Development of Above Ground Level; 2.65 31/07/2019 – 07/03/2022 9. G3-8 Construction of Yarkon-Rokach Bridge, Rokach Station & Relocation of Water Culvert; 1.05 31/03/2019 – 12/08/2020 10. G4-4 Underground Passage for light train in Portal, Tunnel, Cut & Cover exit from Tunnel to Bridge
& Bridge over Rokach; 1.23 09/11/2023
11. G4-6 Underground Passage for light train in Israel Rail Crossing in Shitrit St.; 0.06 09/12/2019 – 20/08/2020 12. G4-7 Dismantling & Construction of Pedestrian Bridge in Shitrit St.; - 24/06/2019 – 24/06/2020 13. G4-8 Station on Bridge & Dismantling of 2 Buildings; 1.52 31/03/2020 – 26/09/2022 14. G5-5 Herzeliya Depot; 0.2 10/06/2021 – 31/08/2023
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 38 -
d) Under Ground Stations – Design Build Option:
Station Name: Construction Time Frame
1. Karlibach 19/03/2020 – 24/05/2023 2. Dizingoff 18/11/2020 – 17/12/2024 3. Rabin 18/11/2020 – 17/12/2024 4. Arlozorov 18/11/2020 – 17/12/2024
e) Tunneling options:
a 4 Km. long section: Levinsky Portal, Levinsky Station's Infrastructure, Levinsky – Karlibach, Karlibach – Nordau Tunneling; Segment: Recommended Tunneling Method/Remarks Construction Time Frame
1. G3-2
G3-3 G3-5
Design Build - 2 TBM Machines from Levinsky to Nordau; 03/10/2019 – 04/03/2024
2. G3-2
G3-3 G3-5
Design Build - 2 TBM Machines from Nordau to Karlibach followed by same 2 TBM machines from Levinsky to Karlibach;
06/10/2019 – 22/07/2024
3.
G3-2 G3-3 G3-5
Design Build – 3 TBM Machines 2 TBM Machines from Nordau to Karlibach 1 TBM Machine from Levinsky to Karlibach;
06/10/2019 – 15/05/2024
4.
G3-2 G3-3 G3-5
Design Build – 3 TBM Machines 2 TBM Machines from Levinsky to Karlibach 1 TBM Machine from Karlibach following the disassembling of first TBM Machime;
02/10/2019 – 02/01/2024
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 39 -
f) Purple Line Construction Period – Western Section PLW1:
Construction Time Frame Length [Km..]:
Description: Name: Segment WBS
01/01/2021 – 31/03/2022 0.5 TLV Municipality
LRT Savidor to Namir Road +
Temp Depot Arlozorov WBS1
01/12/2018 – 31/07/2019 0.525 TLV Municipality
LRT Namir Road to Wizman Arlozorov WBS2
01/01/2019 – 31/08/2019 0.72 TLV Municipality
LRT Wizman to Ibn Gvirol Arlozorov WBS3
01/03/2019 – 31/10/2019 0.84 TLV Municipality
LRT Ibn Gvirol to Ben Yehuda Arlozorov WBS4
01/05/2019 – 31/01/2020 1.2 TLV Municipality
LRT Arlozorov to Bugrashov Ben Yehuda WBS5
01/07/2019 – 31/03/2020 0.45 TLV Municipality
LRT Bugrashov to Alenby Ben Yehuda WBS6
01/07/2019 – 31/03/2020 0.4 TLV Municipality
LRT Alenby to King George Ben Yehuda WBS6a
01/09/2019 – 28/02/2020 0.2 TLV Municipality
LRT Mugrabi Terminus Ben Yehuda/
Alenby WBS7
01/11/2019 – 31/07/2020 1.13 TLV Municipality
LRT King George to YL Peretz Alenby WBS8
01/01/2020 – 30/09/2020 1.1 TLV Municipality
LRT YL Peretz to Lavendeh Levinsky WBS9
01/06/2019 – 31/08/2019 0.05 TLV Municipality
LRT Demolition of Ha'hagana
23 building Ha'hagana WBS10
01/02/2020 – 31/06/2023 0.4 TLV Municipality
LRT Ha'hagana Bridge Ha'hagana WBS11
01/06/2020 – 28/03/2021 1.3 TLV Municipality
LRT Ha'hagana Bridge
(Lavendeh to Kehilat New York)
Ha'hagana WBS12
01/12/2021 – 31/06/2022 0 TLV Municipality
LRT Ha'hagana - Kfar Shalem Kfar Shalem WBS13
01/12/2021 – 31/12/2022 0.75 TLV Municipality
LRT Development of Kfar
Shalem Kfar Shalem WBS14
01/06/2019 – 31/08/2019 0.07 TLV Municipality
LRT Demolition of Ha'hagana
area (4 buildings) Ha'hagana WBS15
01/06/2020 – 31/01/2021 0.6 TLV Municipality
LRT Hatayasim Road to Oded Hatayasim
Roa WBS16
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 40 -
g) Purple Line Construction Period – Western Section PLW2:
Construction Time Frame Length [Km..]:
Description: Name: Segment WBS
01/04/2021 – 31/12/2021 1 Ramat Gan LRT Oded to Rabin Aluf Sade WBS1
01/06/2020 – 31/12/2022 0.4 Ramat Gan LRT Rabin Underpass Aluf Sade WBS2
01/06/2020 – 31/12/2020 0.8 Ramat Gan LRT
Paz Gas station (North) to Ben Zvi Gadren (Aluf Sadeh)
Aluf Sade WBS3
01/06/2020 – 31/07/2022 1.5 Ramat Gan LRT
Aluf Sadeh interchange + Shiba Road + Refael Eitan Junction
Aluf Sade WBS4
01/04/2020 – 30/05/2022 1.7 Ramat Gan LRT
Refael Eitan Underpass (Shiba Road to 471 Road)
Shiba Road to 471 Road
WBS5
01/05/2021 – 28/02/2022 1.5 Ramat Gan LRT 471 Bridge to Bar Ilan station
Keren Ayesod WBS6
01/05/2021 – 28/02/2022 1.5 Givat Shmuel LRT Bar Ilan station to Jabotinsky
Max & Anna Wob WBS7
h) Purple Line Construction Period – Western Section PLE:
Construction Time Frame Length [Km..]:
Description: Name: Segment WBS
01/10/2020 - 31/10/2022 1.6 Ramat Gan LRT
Sheba Road to 461 Road (Yigal Allon junction)
Sheba Road WBS1
01/10/2020 - 31/10/2022 1.9 Or-Yehuda LRT Yigal Allon junction to Avia Junction
461 Road WBS2
01/10/2020 - 31/04/2023 5.1 Or-Yehuda / Yehud LRT
Avia Junction to Hatayasim Road
461 Road WBS3
01/03/2020 - 31/05/2022 0 Or-Yehuda / Yahud LRT
Pelimanary works for Depot - Tayasim + Access
461 Road WBS4
01/01/2020 - 30/11/2020 1.8 Givat Shmuel LRT Bar Ilan to Rabin Road
Givat Shmuel WBS5
The start of construction of the Purple Line is planned for November 2018 and its completion for December 2024. The above time schedule may be divided as follows:
Infra1 - Construction Works: November 2019 – January 2023
Infra 2 - Construction Works: January 2021 – March 2024
• Starting the project works all along the project and completing construction and opening for public use of the entire Green Line:………………………………………………. 40 Months
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 41 -
To the above we recommend adding a 12 months leeway, safety/buffer period;
• Starting the project works all along the project and completing construction and opening for public use of the entire Purple Line:………………………………………………. 72 Months
__________ Total Construction Period: 72 Months
To the above we recommend adding a 18 months leeway, safety/buffer period;
Remarks concerning the project period:
• The Insured intend to carry out two (2) separate CAR Policies for the Infra 1 section only, one
(1) for the Green Line and the second for the Purple Line of the project with Construction Periods,
including a 12 month leeway, safety/buffer period as hereunder:
1. Total Infra 1, Green Line: 72 Months
2. Total Infra 1, Purple Line: 66 Months
• The project works will begin on several locations along the entire length of both line simultaneously with additional considerations dictating which section of each line will be worked on in each instant, and what type of construction work is to be carried out and when;
• Both time frames are overlapping as there are measured from the date of the NTP. Completion of sections of the work however and handing these over to the principal may be moved to an earlier period, if any of these is complete ahead of the plans, owing to operational considerations during the construction period;
G. RISKS, HAZARDS & PROTECTION MEASURES:
As is typical of long duration construction projects of the type we are discussing, particularly with large site areas which would remain open and is use of the public, as well as construction of over the ground, and underground buildings/stations/bridges and the line itself, there are risks, hazards and exposures to Insurers, unless certain important protection measures, safety and security procedures are implemented and strictly adhered to.
We list below some of the immediately apparent risks and/or hazards together with general issues to which the contractors and the consultants will adhere to.
1. The project site is located largely in a flat area, large sections of which being carried underground and/or in tunnels. Construction works will include mainly earthworks, e.g. clearing, digging, tunneling, quarrying and underground construction, the laying of various fill, subsoil/aggregates and concrete and other materials excavation works, excavation during infrastructure relocation, etc.. When taking into consideration the fact that the construction is to be carried out for some seventy two (72) months, during several winter seasons, as well as the soil conditions onsite and the fact that a major part of the works will be carried out below ground level, there is a potential risk of flooding and inundation and/or related damages, as a result of heavy rains & precipitation, gusts etc.
• In view of the above preparations will be made for preventing such damage by arranging for surface water to be diverted from the work/project area and its surroundings, third party property etc. to suitable and adequate drains, as well as implementation of required protections e.g. ducts, channels, pumps and the like if required, per instructions &
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 42 -
recommendations of the soil engineer and/or the hydrologist and/or other relevant consultants etc.
• Items susceptible to gales/tempest/gusts etc. will be secured properly so as to avoid damages to the items as well as to project works and/or neighboring property etc.
• During laying of substrates, aggregates etc. the contractors working onsite ascertain that these are not accessible to water which may cause these damage;
• Proper and adequate drainage in maintained while working underground and while working close to any third party property especially when interrupting the drainage of these;
2. Sufficient & adequate firefighting equipment e.g. fire extinguishers, water hoses etc. will be spread throughout project areas and kept operational at all times, periodically inspected etc.
3. During the construction include works such as sealing works and Hot Works, including welding, disk cutting, open flame gluing etc., i.e. "Hot Works", the Insured will strictly supervise all of these carried out throughout the project site, and allow these to be carried out as per the strict “Hot Works” codes etc. which include the following:
• Clearing the surrounding area, where Hot Works are about to be carried out, of all Inflammable and/or Combustible materials and/or covering these with protective fire resistive material/sheet etc.
• Positioning a Fire Scout on site where Hot Works are about to be carried out, with suitable and sufficient firefighting equipment.
• Remaining in the area, where Hot Works were carried out, for at least 30 minutes after the works have been completed.
4. Project works will be carried out adjacent to third party property, buildings, roads, aboveground & underground infrastructures etc.
Maximum care will be exercised during any of the project’s works, which is carried out near as well as on any third party property, so as to minimize the risk of third party property damage etc.
• Special consideration will be placed on coordination of all the construction operations with the various related entities e.g. the City & Regional Councils and other Municipal councils, involved third part companies, Police Department, etc.
• Underground as well as aboveground infrastructures etc. e.g. electricity, communication and the like within project areas will be identified prior to commencement of project works. Excavation etc. will be carried out only following obtainment of an excavation permit, detailed plans etc. and will be fully coordinated with relevant entities. This is especially critical concerning the relocation of infrastructures and temporary traffic arrangement work as well as work on/around public roads.
The condition of buildings along underground or lower than ground level sections of the lines, which will require excavation near buildings or building's strengthening will be documented.
5. The project areas in which the lines will be constructed will remain open, in use and accessible to the public.
The project documents' requirement concerning traffic arrangements will be followed;
• If open ditches, channels, unpaved roads and/or pedestrian pavements are left open
or accessible to passersby, these will be clearly marked with signs posted and
flashing lights at night;
• The location where construction of underground project sections, be that
underground stations and structures as well as the lines themselves, will be closed
and sectioned from public access;
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 43 -
If, however there are certain locations where tunnels & holes are excavated during relocation of infrastructures, or during construction of specific structures, e.g. the stations, the underground sections of the lines, culverts, support walls etc., or other specific works, these will be surrounded, if possible, throughout the duration of the project’s construction period, subject to the standards and codes that are prevalent in the construction/building industry, in order to prevent the entry of unauthorized persons, thus minimizing the risks of injury and/or damage to third parties as well as the risk of burglary/theft.
Additionally, the mobilization site/s and project staging areas will be in continuation, completely surrounded by a fence and guarded throughout the duration of the project’s construction period, subject to the standards and codes that are prevalent in the construction/building industry, in order to prevent the entry of unauthorized persons, thus minimizing the risks of injury and/or damage to third parties as well as the risk of burglary/theft.
6. If during the long construction period large quantities of various attractive/coveted property items will be stored on site, or manual tools and costly materials are stored on site, these will be placed in closed and locked rooms/containers etc. secured with a 12-16 mm padlock (or similar) and clamp and a guard will patrol by these on a regularly.
7. The project as well as all the systems will be complying with all the binding standards/building codes, as required by law, including SI 413/SI 2413 – protection of new/old buildings against earthquake risks.
8. The Insured are the principal of the project, and as such will hire several contractors, sub-contractors etc.
The Insured and/or the General Contractor etc. will hire only reputable, approved contractors of proven experience, who are registered in the Contractors Registrar as qualified contractors for the work they are hired to do.
9. All the safety instructions for the construction industry will be strictly adhered to, and especially the Work Safety Regulations (Construction works), 5748-1988.
A certified safety officer as well as safety trustees etc. be appointed for the duration of the project’s construction.
10. Construction works will require the use of mobile cranes, raising device etc.
All raising devices and tackles will undergo periodical inspections and certification closely inspected by a qualified & certified engineer authorized for this task by the Ministry of Labor – as per the law's requirements, and their arcs of travel should be limited as possible.
The above will be carried out so as to avoid any possibility of damaging neighboring property as well as in order to avoid the possibility of items falling from these onto public areas, causing injury.
11. Contractors, the project manager sand others will strictly adhere to all the recommendations and conclusions of the soil and foundations report, the instructions of the constructor, the hydrologists, etc. In addition, the soil & hydrological reports should be revised in accordance with any new finding, change of planning, etc., for their comments, recommendations and so on, in order to reduce the risks involved in the project.
12. Groundwater pumping – the Insured, General Contractor and all project contractors, particularly concerning underground construction of stations, the lines themselves any infrastructures' relocation or other works bellow the site's ground level should be aware of the groundwater levels and be prepared to deal with these, especially during winter/rainy season;
Natural Hazards:
Earthquake:
In consideration of the Syrian – African Rift, separating the Asian and African Tectonic plates, Israel is regarded as a relatively high earthquake risk zone.
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 44 -
The Syrian – African Rift goes along the whole eastern side of the country, from the Galilee right down to the Red Sea, along its length are located the Sea of Galilee, Jordan River and the Dead Sea.
The site is located in a "High (0.41-0.61)" Seismic Hazard zone, according to Swiss-Re CatNet® (See attached screenshot).
Swiss Re.'s Seismic Hazard Zone – Green, Purple & Red Project's Section Site Location – Not to Scale!
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 45 -
Flood:
Certain areas along the along the project site are located within the 100 – 200 year return period of river flood and outside of the risk area for flood, as per CatNet® – see attached screenshot.
Swiss Re.'s Seismic Hazard Zone – Green, Purple & Red Project's Section Site Location – Not to Scale!
Storm & Tempest:
In general, Israel is characterized with relatively mild winters, however no. of occurrences of excessive winds/rain were reported in past years– the 3-day precipitation amount with a 50 year return period is 150-300 mm, same results for a 100 year return period (as per CatNet®). Additionally, the area can be affected by strong seasonal gales, gusts etc.
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 46 -
H. SUMMARY:
The subject of the above report, is a project which involves the design and construction of two (2) new additional LRT Lines, the Green and the Purple Lines in the Tel Aviv Metropoline.
The total project value, as stated by the Insured, before VAT, is some $ 8,663,632,000, which may be divided into the construction costs of each line as follows:
Description: Estimated Value - $
1. Estimated Construction Costs IRO the Green Line: 5,718,569,000
2. Estimated Construction Costs IRO the Purple Line: 2,945,063,000
_______________
Total Estimated Project Value: $ 8,663,632,000
• The Insured intend to carry out two (2) separate CAR Policies for the Infra 1 section only, one
(1) for the Green Line and the second for the Purple Line of the project, with Project Values as
follows:
1. Total Infra 1, Green Line: $ 620,032,000
2. Total Infra 1, Purple Line: $ 418,880,000
• The tunneling works in the Green Line are to be Insured by the Design Build contractor who will construct these;
• Starting the project works all along the project and completing construction and opening for public use of the entire Green Line:………………………………………………. 40 Months To the above we recommend adding a 12 months leeway, safety/buffer period;
• Starting the project works all along the project and completing construction and opening for public use of the entire Purple Line:………………………………………………. 72 Months
__________ Total Construction Period: 72 Months
To the above we recommend adding a 18 months leeway, safety/buffer period;
• The Insured intend to carry out two (2) separate CAR Policies for the Infra 1 section only, one
(1) for the Green Line and the second for the Purple Line of the project with Construction Periods,
including a 12 month leeway, safety/buffer period as hereunder:
File No. 02/18010013
NTA – Metropolitan Mass Transit System (MTS), Green & Purple Lines
- 47 -
1. Total Infra 1, Green Line: 72 Months
2. Total Infra 1, Purple Line: 66 Months
We are at your service for any additional information.
Attached:
Debit Note of agreed fees and expenses;