TO CONTRACT DOCUMENTS ENTITLED

43
Page 1 of 6 ADDENDUM #4 DATE: 04.24.2017 TO CONTRACT DOCUMENTS ENTITLED: PROJECT MANUAL FOR: CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation CP161981 MUHC Emergency Power System Modifications – Phase 2 CP161741 General Site – Steam Utility Manhole 343 Repairs at Hospital Ambulance Bay CP170371 Missouri Psychiatric Center – Refurbish Steam Line ADVERTISEMENT DATE: 03.23.2017 PREPARED FOR: The Curators of the University of Missouri CONSULTANTS: CP150492 bcDESIGNGROUP 200 NE Missouri Rd, Suite 200 Lee’s Summit, MO 64086 913.232.2123 x802 CP161981 Burns & McDonnell 9400 Ward Parkway Kansas City, MO 64114 816.349.6701 CP151741 Crockett Engineering 1000 W. Nifong Blvd, Bldg #1 Columbia, MO 65203 573.447.0292 CP170371 Bric Partnership, LLC 343 Kirkwood Road, Suite 204 Kirkwood, MO 63122 314.725.5889 Drawings and Specifications for the above noted project and the work covered thereby are herein modified as follows, and except as set forth herein, otherwise remain unchanged and in full force and effect:

Transcript of TO CONTRACT DOCUMENTS ENTITLED

Page 1 of 6
ADDENDUM #4 DATE: 04.24.2017 TO CONTRACT DOCUMENTS ENTITLED: PROJECT MANUAL FOR: CP150492 University of Missouri Teaching Hospital – West Wing –
Expansion/Renovation
CP161981 MUHC Emergency Power System Modifications – Phase 2
CP161741 General Site – Steam Utility Manhole 343 Repairs at Hospital Ambulance Bay CP170371 Missouri Psychiatric Center – Refurbish Steam Line
ADVERTISEMENT DATE: 03.23.2017 PREPARED FOR: The Curators of the University of Missouri CONSULTANTS: CP150492
bcDESIGNGROUP 200 NE Missouri Rd, Suite 200 Lee’s Summit, MO 64086 913.232.2123 x802 CP161981 Burns & McDonnell 9400 Ward Parkway Kansas City, MO 64114 816.349.6701 CP151741 Crockett Engineering 1000 W. Nifong Blvd, Bldg #1 Columbia, MO 65203 573.447.0292
CP170371 Bric Partnership, LLC 343 Kirkwood Road, Suite 204 Kirkwood, MO 63122 314.725.5889
Drawings and Specifications for the above noted project and the work covered thereby are herein modified as follows, and except as set forth herein, otherwise remain unchanged and in full force and effect:
Page 3 of 6
SPECIFICATION CHANGES | CP150492| Volume 3:
1. Specification Section 23 0700 Mechanical Insulation: a. ADDED Heating Hot Water and Steam Vents to the Pipe Insulation Schedule in
Section 4.1 of this specification section. b. REVISED Chilled Water Pipe Insulation Schedule in Section 4.1 of this specification
section. DRAWING CHANGES | CP150492| Volume 2:
1. MD101: a. REVISED existing outside air ductwork demolition near column lines “9” and “B”. b. Refer to reissued sheet dated 04/24/2017 for revisions.
2. MD102:
a. REVISED existing air handling unit AHU S2-13 outside air ductwork demolition near column lines “X0” and “X”.
b. REVISED keyed note 9. c. Refer to reissued sheet dated 04/24/2017 for revisions.
3. M101:
a. ADDED rated dampers to duct systems. b. REVISED keyed notes 1 and 16. c. ADDED keyed note 30. d. Refer to reissued sheet dated 04/24/2017 for revisions.
4. M101A:
a. ADDED room pressure monitor model number to keyed note 4. b. ADDED keyed note 19. c. ADDED notes at new pipe riser location. d. Refer to reissued sheet dated 04/24/2017 for revisions.
5. M103:
a. ADDED rated dampers to duct systems. b. ADDED keyed note 20. c. Refer to reissued sheet dated 04/24/2017 for revisions.
6. M103A:
a. REVISED location of air terminal unit VAV 23-319. b. ADDED room pressure monitor model number to keyed note 6. c. ADDED keyed note 13. d. Refer to reissued sheet dated 04/24/2017 for revisions.
7. M300:
a. DELETED chilled water pump isolation valves on Chilled Water Flow Diagram. b. ADDED building chilled water isolation valve to Chilled Water Flow Diagram. c. Refer to reissued sheet dated 04/24/2017 for revisions.
8. M400:
a. REVISED keyed note 2, 7, and 14. b. ADDED keyed notes 22 and 23. c. ADDED AHU-23 and FCU-3 condensate drain piping.
Page 4 of 6
d. ADDED rated dampers to duct systems. e. REVISED return duct size on return fan inlet. f. Refer to reissued sheet dated 04/24/2017 for revisions.
9. M401:
a. REVISED keyed note 3. b. ADDED keyed notes 10 and 11. c. REVISED existing piping demolition. d. REVISED new piping riser arrangement. e. Refer to reissued sheet dated 04/24/2017 for revisions.
10. M600:
a. REVISED Control Valve Schedule. b. Refer to reissued sheet dated 04/24/2017 for revisions.
11. M601:
a. REVISED Air Flow Measuring Station Schedule. b. REVISED Combination Fire/Smoke Damper & Smoke Damper Schedule. c. Refer to reissued sheet dated 04/24/2017 for revisions.
12. M700:
a. REVISED text in the Combination Fire/Smoke and Smoke Damper Sequence. b. Refer to reissued sheet dated 04/24/2017 for revisions.
13. EP101:
a. ADD electrical connections for activation of fire/smoke dampers. b. Refer to reissued sheet dated 04/24/2017 for revisions.
14. EP102:
a. ADD electrical connection for activation of smoke dampers. b. Refer to reissued sheet dated 04/24/2017 for revisions.
15. EP103:
a. ADD electrical connection for activation of fire/smoke dampers. b. Refer to reissued sheet dated 04/24/2017 for revisions.
16. ES101:
a. ADD duct detectors and addressable relay for fire/smoke dampers. b. Refer to reissued sheet dated 04/24/2017 for revisions.
17. ES102:
a. ADD duct detectors and addressable relay for fire/smoke dampers. b. Refer to reissued sheet dated 04/24/2017 for revisions.
18. ES103:
a. ADD duct detectors and addressable relay for fire/smoke dampers. b. Refer to reissued sheet dated 04/24/2017 for revisions.
Page 5 of 6
GENERAL CLARIFICATIONS:
1. Bidders Questions & Answers: a. Q for project CP150492: Control isolation valves for chilled water pumps CHWP-10
& 11 are shown on the control valve schedule on M600 and chilled water piping flow diagram on M300 but are not shown on the controls flow diagram or DDC points list on M703. Please clarify if these valves are to be included as individual control points controlled via the BAS or are to be hardwire interlocked with their respective pump. A: Chilled water pump isolation valves are not required. Refer to reissued drawings in Addendum #4.
b. Q for project CP150492: Room pressure monitors shown on piping plans M101A & M103A via keyed notes do not have a product specification. They also do not have an installation detail in the M500 series plans, a schedule in the M600 plans, or a control detail or reference in the M700 plans. Please provide a desired model number for the room pressure monitor to be used. Also, please clarify if these monitors are to be interfaced with the BAS via BACnet MSTP network wiring or via hardwire control points to nearest DDC controller. A: A room pressure monitor manufacturer and model number will be added to the drawings, refer to reissued drawings in Addendum #4 and will be noted to be provided with a MS/TP card. Interface of the room pressure monitors (RPM) to the EMCS is shown on the FC Bus Schematic Diagram on Sheet M702. Room pressure monitors are to be installed per manufacturers installation instructions per keyed note 4 on Sheet M101A and keyed note 6 on Sheet M103A.
a. Q for project CP150492: Sequence for Combination Fire/Smoke Dampers on M700 indicates “Fire/smoke dampers shall not be controlled by the EMCS but shall be connected to EMCS. All fire/smoke dampers shall only controlled by the building fire alarm system. Dampers shall also close via their controlled closure device at temperatures above 165 deg F. The EMCS shall monitor damper position, via damper end switch. When a damper is closed an alarm signal shall be sent to EMCS.” Fire/smoke damper positions have not been monitored by the BAS on previous projects at this facility nor are they called out on the owner provided control diagrams and points list on the M700 plans. Please clarify the fire/smoke dampers are NOT to be monitored via end switches monitored by the BAS.
Page 6 of 6
A: Per University HVAC Supervisor, the new combination fire/smoke and smoke dampers added in this project are to be monitored by the EMCS.
ATTACHMENTS:
1. CP150492 Specification Section 23 0700 Mechanical Insulation 2. CP150492 Mechanical Drawing Sheets: MD101, MD102, M101, M101A, M103, M103A,
M300, M400, M401, M600, M601, and M700 3. CP150492 Electrical Drawing Sheets: EP101, EP102, EP103, ES101, ES102, and ES103
ISSUED BY: Kurt M. Broeckelmann bcDESIGNGROUP
END OF ADDENDUM 4
23 0700 - 1 Mechanical Insulation
SECTION 23 0700 - MECHANICAL INSULATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
B. Section 20 0800 “Seismic Protection,” Section 23 0100 “Basic Mechanical Requirements,”
and Section 23 0500 “Basic Mechanical Materials and Methods” all apply to the work of
this Section as if fully repeated herein.
1.2 SUMMARY
A. This Section includes mechanical insulation for ductwork, equipment, piping, appliance
breechings and other installations, including the following:
1. Insulation Materials: Flexible elastomeric, mineral fiber.
2. Insulating cements, adhesives, mastics, and sealants.
3. Factory-applied jackets.
C. SSL: Self-sealing lap.
D. Thermal Resistivity: “R-values” represent the reciprocal of thermal conductivity (k-value).
Thermal conductivity is the rate of heat flow through a homogenous material exactly 1-
inch thick. Thermal resistivities are expressed by the temperature difference in degrees F
between two exposed faces required to cause one BTU to flow through one square foot
of material, in one hour, at a given mean temperature.
E. VOC: Volatile Organic Compound as defined by LEED v3 Credit EQ 4.1.
F. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred
spaces, pipe and duct shafts, unheated spaces immediately below roof, spaces above
ceilings, unexcavated spaces, crawl spaces, and tunnels.
G. Exposed Installations: Exposed to view. Examples include finished occupied spaces
without ceilings, mechanical equipment rooms, courtyards and rooftop locations.
H. Concealed Installations: Concealed from view and protected from physical contact by
building occupants. Examples include above ceilings or within duct shafts.
I. Conditioned Space: Spaces that are served by both a mechanical heating and
mechanical cooling system are conditioned spaces. Heating-only spaces are not
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 2 Mechanical Insulation
conditioned spaces. The space above a ceiling is considered conditioned space if the
space directly below that ceiling is conditioned space. A vertical shaft is considered
conditioned space if the spaces on all sides surrounding the shaft are conditioned
spaces.
1.4 SUBMITTALS
A. Product Data: For each type of product indicated, identify thermal conductivity,
thickness, and jackets (both factory and field applied, if any).
B. MSDS (Material Safety Data Sheet) for each adhesive, mastic, sealant, and cement
furnished.
apprenticeship program or another craft training program certified by the Department
of Labor, Bureau of Apprenticeship and Training.
B. Fire-Test-Response Characteristics: Insulation and related materials shall have flame-
spread index of 25 or less, and smoke-developed index of 50 or less, as determined by
testing identical products per ASTM E84, by a testing and inspecting agency acceptable
to authorities having jurisdiction. Factory label insulation and jacket materials and
adhesive, mastic, and cement material containers, with appropriate markings of
applicable testing and inspecting agency.
1. Exception: Flame-spread index of 25 or less, and smoke-developed index of 150 or
less; is acceptable for insulation not installed in an air-handling duct, plenum,
space above ceilings if used as a return air plenum, or air-handling equipment
rooms if used as a return/exhaust/relief air plenum, or any other air-handling
situation.
A. Packaging: Insulation material containers shall be marked by manufacturer with
appropriate ASTM standard designation, type and grade, and maximum use
temperature.
1.7 COORDINATION
A. Coordinate size and location of supports, hangers, and insulation shields specified in
Division 23 Section “Hangers and Supports.”
B. Coordinate clearance requirements with piping Installer for piping insulation application,
duct Installer for duct insulation application, and equipment Installer for equipment
insulation application. Before preparing piping and ductwork Shop Drawings, establish
and maintain clearance requirements for installation of insulation and field-applied
jackets and finishes and for space required for maintenance.
1.8 SCHEDULING
A. Schedule insulation application after pressure testing systems and, where required, after
installing and testing heat tracing. Insulation application may begin on segments that
have satisfactory test results.
23 0700 - 3 Mechanical Insulation
B. Complete installation and concealment of plastic materials as rapidly as possible in each
area of construction.
PART 2 - PRODUCTS
A. Manufacturers: Subject to compliance with requirements, provide products by one of
the following manufacturers:
b. Armacell LLC; AP/Armaflex.
d. RBX Corporation; Insul-Sheet 1800 and Insul-Tube 180.
2. Mineral Fiber Insulation:
a. Insulco, Division of MFS, Inc.
b. P. K. Insulation Mfg. Co., Inc.
c. Rock Wool Manufacturing Company.
4. Sealants, Adhesives and Mastics: Same as insulation manufacturer, or
a. H.B. Fuller Construction Products Inc. (Childers and/or Foster brands)
b. ITW TACC, Division of Illinois Tool Works.
c. Marathon Industries, Inc.
d. Mon-Eco Industries, Inc.
a. P.I.C. Plastics, Inc.
b. PABCO Metals Corporation.
c. Pittsburgh Corning Corporation.
d. Polyguard Products, Inc.
e. Proto PVC Corporation.
f. RPR Products, Inc.
b. Compac Corp.
23 0700 - 4 Mechanical Insulation
d. Polyguard Products, Inc.
a. ACS Industries, Inc.
b. C & F Wire.
8. Insulation Pins and Hangers: Same as insulation manufacturer, or
a. AGM Industries, Inc.
2.2 INSULATION MATERIALS
A. Refer to Schedule in Part 3 for requirements about where insulating materials shall be
applied.
B. Products shall not contain asbestos, lead, mercury, or mercury compounds.
C. Foam insulation materials shall not use CFC or HCFC blowing agents in the manufacturing
process.
D. Adhesives shall be compatible with insulation materials, jackets, and substrates and for
bonding insulation to itself and to surfaces to be insulated, unless otherwise indicated.
E. Product manufacturers and/or their product numbers notwithstanding, each adhesive,
mastic, sealant, and cement shall have a VOC content not greater than the maximum
allowable under LEED v3 Credit EQ 4.1 regardless of whether or not this project is seeking
LEED certification.
F. Flexible Elastomeric: Closed-cell, sponge- or expanded-rubber materials. Comply with
ASTM C534, Type I for tubular materials and Type II for sheet materials.
1. Thermal Conductivity: 0.28 average maximum at 75ºF mean temperature using test
method ASTM C177 or C518.
2. Water Vapor Permeability: Maximum 0.1 perm-inch using test method ASTM E96
Procedure A.
3. Water Absorption: Maximum 0.2% by volume using test method ASTM C209.
4. Product shall pass mold growth, fungi resistance, and bacterial resistance tests per
UL 181, ASTM G21, G22, and C1338.
5. Adhesive: Comply with MIL-A-24179A, Type II, Class I; VOC content of 50 g/L or less
when calculated according to 40 CFR 59, Subpart D (EPA Method 24).
G. Mineral-Fiber Blanket Insulation: Mineral or glass fibers bonded with a thermosetting resin.
Comply with ASTM C553, Type II and ASTM C1290, Type III with factory-applied jacket.
1. Thermal Conductivity: 0.26 average maximum at 75F mean temperature.
2. Density: 1.5 lb/cf (24-kg/cu. m) minimum.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 5 Mechanical Insulation
3. Jacket: Aluminum-foil, fiberglass-reinforced scrim with kraft-paper backing;
complying with ASTM C1136, Type II.
H. Mineral-Fiber Board Insulation: Mineral or glass fibers bonded with a thermosetting resin.
Comply with ASTM C612, Type IA or Type IB.
1. Thermal Conductivity: 0.26 average maximum at 75F mean temperature.
2. Density: 2.0 lb/cf (32-kg/cu. m) minimum.
3. Jacket (Ducts): Aluminum-foil, fiberglass-reinforced scrim with kraft-paper backing;
complying with ASTM C1136, Type II.
4. Jacket (Equipment): White, kraft-paper, fiberglass-reinforced scrim with aluminum-
foil backing; complying with ASTM C1136, Type I.
I. Mineral-Fiber, Preformed Pipe Insulation: Type I, 850ºF (454ºC); mineral or glass fibers
bonded with a thermosetting resin. Comply with ASTM C547, Type I, Grade A, with
factory-applied jacket.
1. Thermal Conductivity: 0.26 average maximum at 75F mean temperature.
2. Jacket: White, kraft-paper, fiberglass-reinforced scrim with aluminum-foil backing;
complying with ASTM C1136, Type I; with self-sealing, pressure-sensitive, acrylic-
based adhesive covered by a removable protective strip.
3. Adhesive: Water-based and complying with ASTM C916 Type II; equal to Foster 85-
60 and/or Childers CP-127.
J. Mineral-Fiber, Pipe and Tank Insulation: Mineral or glass fibers bonded with a
thermosetting resin. Semi-rigid board material complying with ASTM C1393, Type II or
Type IIIA Category 2, or with properties similar to ASTM C612, Type IB.
1. Thermal Conductivity: 0.29 average maximum at 100F mean temperature.
2. Density: 2.5 lb/cf (40-kg/cu. m) minimum.
3. Jacket: White, kraft-paper, fiberglass-reinforced scrim with aluminum-foil backing;
complying with ASTM C1136, Type I
4. Adhesive: Water-based and complying with ASTM C916 Type II.
2.3 INSULATING CEMENTS
A. Mineral-Fiber Insulating Cement: Comply with ASTM C195.
B. Expanded or Exfoliated Vermiculite Insulating Cement: Comply with ASTM C196.
C. Mineral-Fiber, Hydraulic-Setting Insulating and Finishing Cement: Comply with ASTM
C449/C 449M.
2.4 MASTICS
A. Materials shall be compatible with insulation materials, jackets, and substrates.
B. Vapor-Barrier Mastic: Water based; suitable for indoor and outdoor use on below-
ambient services. Equal to Foster 30-33 or Childers CP-33 or Vimasco 749.
1. Water-Vapor Permeance: ASTM E96, Procedure B, 0.07 perms or less at 41 mil dry
film thickness.
2. Service Temperature Range: -20 to +180ºF (-29 to +82ºC).
3. Solids Content: ASTM D1644, 59 percent by volume and 71 percent by weight.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 6 Mechanical Insulation
4. Color: White.
C. Breather Mastic: Water based; suitable for indoor and outdoor use on above-ambient
services. Equal to Foster 46-50 or Childers CP-10/11 or Vimasco WC-5.
1. Water-Vapor Permeance: ASTM F1249, 3 perms (2 metric perms) at 0.0625-inch (1.6-
mm) dry film thickness.
2. Service Temperature Range: -20 to +200ºF (-29 to +93ºC).
3. Solids Content: 63 percent by volume and 73 percent by weight.
4. Color: White.
A. Joint Sealants: Permanently flexible, elastomeric sealant. Materials shall be compatible
with insulation materials, jackets, and substrates.
1. Service Temperature Range: -100 to +200ºF (-73 to +94ºC).
2. Color: White, tan, or gray.
3. VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D
(EPA Method 24).
B. FSK and Metal Jacket Flashing Sealants: Fire- and water-resistant, flexible, elastomeric
sealant. Materials shall be compatible with insulation materials, jackets, and substrates.
1. Service Temperature Range: -40 to +250ºF (-40 to +121°C).
2. Color: Aluminum.
3. VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D
(EPA Method 24).
C. ASJ Flashing Sealants, and Vinyl and PVC Jacket Flashing Sealants: Fire- and water-
resistant, flexible, elastomeric sealant. Materials shall be compatible with insulation
materials, jackets, and substrates.
1. Service Temperature Range: -40 to +250ºF (-40 to +121°C).
2. Color: White.
3. VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D
(EPA Method 24).
2.6 FIELD-APPLIED JACKETS
A. Field-applied jackets shall comply with ASTM C921, Type I, unless otherwise indicated.
B. PVC Jacket: High-impact-resistant, UV-resistant PVC complying with ASTM D1784,
Class 16354-C; thickness 30 mils (0.8 mm); roll stock ready for shop or field cutting and
forming.
1. Adhesive: Compatible with PVC, as recommended by jacket material
manufacturer.
3. Factory-fabricated fitting covers to match jacket if available; otherwise, field
fabricate.
4. Shapes: 45- and 90-degree, short- and long-radius elbows, tees, valves, flanges,
unions, reducers, end caps, soil-pipe hubs, traps, mechanical joints, and P-trap and
supply covers for lavatories.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 7 Mechanical Insulation
C. Metal Jackets: Sheet and roll stock ready for shop or field sizing. Factory pre-cut and
rolled to size is also acceptable.
1. Aluminum Jacket: Comply with ASTM B209, Alloy 3003, 3005, 3105 or 5005,
Temper H-14. Finishes and thickness as follows:
a. Indoor Ducts and Plenums: Smooth, 0.016-inch (0.41 mm) thick.
b. Indoor Equipment: Stucco Embossed, 0.016-inch (0.41 mm) thick.
c. Outdoor Ducts, Equipment, and Piping: Stucco embossed, with Z-shaped
locking seam, 0.024-inch (0.61 mm) thick.
2. Moisture Barrier for Indoor Applications: 1-mil- (0.025-mm-) thick, heat-bonded
polyethylene and kraft paper.
polyethylene and kraft paper.
4. Factory-Fabricated Fitting Covers: Same material, finish, and thickness as jacket;
provide as required for preformed 2-piece or gore, 45- and 90-degree, short- and
long-radius elbows, tee covers, flange and union covers, end caps, beveled
collars, and valve covers.
5. Field-fabricate fitting covers only if factory-fabricated fitting covers are not
available.
A. ASJ Tape: White vapor-retarder tape matching factory-applied jacket with acrylic
adhesive, complying with ASTM C1136 and UL listed.
1. Width: 3-inches (75 mm).
2. Thickness: 11.5 mils (0.29 mm).
3. Adhesion: 90 ounces force/inch (1.0 N/mm) in width.
4. Elongation: 2 percent.
5. Tensile Strength: 40 lbf/inch (7.2 N/mm) in width.
6. ASJ Tape Disks and Squares: Precut disks or squares of ASJ tape.
B. FSK Tape: Foil-face, vapor-retarder tape matching factory-applied jacket with acrylic
adhesive; complying with ASTM C1136 and UL listed.
1. Width: 3-inches (75 mm).
2. Thickness: 6.5 mils (0.16 mm).
3. Adhesion: 90 ounces force/inch (1.0 N/mm) in width.
4. Elongation: 2 percent.
5. Tensile Strength: 40 lbf/inch (7.2 N/mm) in width.
6. FSK Tape Disks and Squares: Precut disks or squares of FSK tape.
C. PVC Tape: White vapor-retarder tape matching field-applied PVC jacket with acrylic
adhesive. Suitable for indoor and outdoor applications.
1. Width: 2-inches (50 mm).
2. Thickness: 6 mils (0.15 mm).
3. Adhesion: 64 ounces force/inch (0.7 N/mm) in width.
4. Elongation: 500 percent.
5. Tensile Strength: 18 lbf/inch (3.3 N/mm) in width.
D. Aluminum-Foil Tape: Vapor-retarder tape with acrylic adhesive and UL listed.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 8 Mechanical Insulation
1. Width: 2-inches (50 mm).
2. Thickness: 3.7 mils (0.093 mm).
3. Adhesion: 100 ounces force/inch (1.1 N/mm) in width.
4. Elongation: 5 percent.
2.8 SECUREMENTS
A. Bands:
1. Stainless Steel: ASTM A167 or ASTM A240, Type 304; 0.015-inch (0.38 mm) thick, ½-
inch (13 mm) wide with wing or closed seal.
2. Aluminum: ASTM B209, Alloy 3003, 3005, 3105, or 5005; Temper H-14, 0.020-inch (0.51
mm) thick, ½-inch (13 mm) wide with wing or closed seal.
3. Springs: Twin spring set constructed of stainless steel with ends flat and slotted to
accept metal bands. Spring size determined by manufacturer for application.
B. Insulation Pins and Hangers:
1. Capacitor-Discharge-Weld Pins: Copper- or zinc-coated steel pin, fully annealed
for capacitor-discharge welding, 0.106-inch- (2.6-mm-) diameter shank, length to
suit depth of insulation indicated.
2. Cupped-Head, Capacitor-Discharge-Weld Pins: Copper- or zinc-coated steel pin,
fully annealed for capacitor-discharge welding, 0.106-inch- (2.6-mm-) diameter
shank, length to suit depth of insulation indicated with integral 1½-inch (38-mm)
galvanized carbon-steel washer.
3. Metal, Adhesively Attached, Perforated-Base Insulation Hangers: Baseplate
welded to projecting spindle that is capable of holding insulation, of thickness
indicated, securely in position indicated when self-locking washer is in place.
Baseplate shall be perforated, galvanized carbon-steel sheet, 0.030-inch (0.76 mm)
thick by 2-inches (50 mm) square. Spindle shall be copper, aluminum, or stainless
steel, fully annealed, 0.106-inch (2.6-mm) diameter shank, length to suit depth of
insulation indicated. Adhesive shall be as recommended by hanger manufacturer;
with demonstrated capability to bond insulation hanger securely to substrates
indicated without damaging insulation, hangers, and substrates.
4. Self-Sticking-Base Insulation Hangers: Adhesive-backed base with a peel-off
protective cover; and baseplate welded to projecting spindle that is capable of
holding insulation, of thickness indicated, securely in position indicated when self-
locking washer is in place. Baseplate shall be galvanized carbon-steel sheet, 0.030-
inch (0.76 mm) thick by 2-inches (50 mm) square. Spindle shall be copper,
aluminum, or stainless steel, fully annealed, 0.106-inch- (2.6-mm-) diameter shank,
length to suit depth of insulation indicated.
5. Insulation-Retaining Washers: Self-locking washers formed from 0.016-inch (0.41-
mm) thick, aluminum or stainless-steel sheet, with beveled edge sized as required
to hold insulation securely in place but not less than 1½-inches (38 mm) in diameter.
Protect ends with capped self-locking washers incorporating a spring steel insert to
ensure permanent retention of cap in exposed locations.
C. Staples: Outward-clinching insulation staples, nominal ¾-inch- (19-mm-) wide, stainless
steel or Monel.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 9 Mechanical Insulation
2.9 CORNER ANGLES
A. PVC Corner Angles: 30 mils (0.8 mm) thick, minimum 1 by 1-inch (25 by 25 mm), PVC
according to ASTM D1784, Class 16354-C. White or color-coded to match adjacent
surface.
B. Aluminum Corner Angles: 0.040-inch (1.0 mm) thick, minimum 1 by 1-inch (25 by 25 mm),
aluminum according to ASTM B209, Alloy 3003, 3005, 3105 or 5005; Temper H-14.
PART 3 - EXECUTION
A. Examine substrates and conditions for compliance with requirements for installation and
other conditions affecting performance of insulation application. Verify that systems and
equipment to be insulated have been tested and are free of defects. Verify that surfaces
to be insulated are clean and dry. Proceed with installation only after unsatisfactory
conditions have been corrected.
3.2 PREPARATION
A. Surface Preparation: Clean and dry surfaces to receive insulation. Remove materials that
will adversely affect insulation application.
B. Mix insulating cements with clean potable water; if insulating cements are to be in
contact with stainless-steel surfaces, use demineralized water.
3.3 COMMON INSTALLATION REQUIREMENTS
A. Install insulation materials, accessories, and finishes with smooth, straight, and even
surfaces; free of voids throughout the length of equipment, ducts and fittings, and piping
including fittings, valves, and specialties.
B. Install insulation materials, forms, vapor barriers or retarders, jackets, and thicknesses
required for each item of equipment, duct system, and pipe system as specified in
insulation system schedules.
C. Install accessories compatible with insulation materials and suitable for the service. Install
accessories that do not corrode, soften, or otherwise attack insulation or jacket in either
wet or dry state.
D. Install insulation with longitudinal seams at top and bottom of horizontal runs. Install
multiple layers of insulation with longitudinal and end seams staggered.
E. Do not weld brackets, clips, or other attachment devices to piping, fittings, and
specialties.
F. Keep insulation materials dry during application and finishing.
G. Install insulation with tight longitudinal seams and end joints. Bond seams and joints with
adhesive recommended by insulation material manufacturer. Install insulation with least
number of joints practical.
23 0700 - 10 Mechanical Insulation
H. Where vapor barrier is indicated, seal joints, seams, and penetrations in insulation at
hangers, supports, anchors, and other projections with vapor-barrier mastic.
1. Install insulation continuously through hangers and around anchor attachments.
2. For insulation application where vapor barriers are indicated, extend insulation on
anchor legs from point of attachment to supported item to point of attachment to
structure. Taper and seal ends at attachment to structure with vapor-barrier mastic.
3. Install insert materials and install insulation to tightly join the insert. Seal insulation to
insulation inserts with adhesive or sealing compound recommended by insulation
material manufacturer.
4. Cover inserts with jacket material matching adjacent pipe insulation. Install shields
over jacket, arranged to protect jacket from tear or puncture by hanger, support,
and shield.
I. Apply adhesives, mastics, and sealants at manufacturer's recommended coverage rate
and wet and dry film thicknesses.
J. Install insulation with factory-applied jackets as follows:
1. Draw jacket tight and smooth.
2. Cover circumferential joints with 3-inch- (75-mm-) wide strips, of same material as
insulation jacket. Secure strips with adhesive and outward clinching staples along
both edges of strip, spaced 4-inches (100 mm) o.c.
3. Overlap jacket longitudinal seams at least 1½-inches (38 mm). Install insulation with
longitudinal seams at bottom of pipe. Clean and dry surface to receive self-sealing
lap. Staple laps with outward clinching staples along edge at 2-inches (50 mm) o.c.
4. For below ambient services, apply vapor-barrier mastic over staples.
5. Cover joints and seams with tape as recommended by insulation material
manufacturer to maintain vapor seal.
6. Where vapor barriers are indicated, apply vapor-barrier mastic on seams and joints
and at ends adjacent to duct and pipe flanges and fittings.
K. Cut insulation in a manner to avoid compressing insulation more than 75 percent of its
nominal thickness.
L. Finish installation with systems at operating conditions. Repair joint separations and
cracking due to thermal movement.
M. Repair damaged insulation facings by applying same facing material over damaged
areas. Extend patches at least 4-inches (100 mm) beyond damaged areas. Adhere,
staple, and seal patches similar to butt joints.
N. At the following locations, omit jacket and provide a separate cutaway removable
segment of insulation clearly labeled “Access.” For below-ambient services, provide a
design that allows access but maintains vapor barrier.
1. Vibration-control devices.
3. Nameplates and data plates.
4. Manholes.
5. Handholes.
6. Cleanouts.
3.4 PENETRATIONS
23 0700 - 11 Mechanical Insulation
A. Insulation Installation at Roof Penetrations: Install insulation continuously through roof
penetrations.
2. For applications requiring only indoor insulation, terminate insulation above roof
surface and seal with joint sealant. For applications requiring indoor and outdoor
insulation, install insulation for outdoor applications tightly joined to indoor insulation
ends. Seal joint with joint sealant.
3. Extend jacket of outdoor insulation outside roof flashing at least 2-inches (50 mm)
below top of roof flashing.
4. Seal jacket to roof flashing with flashing sealant.
B. Insulation Installation at Interior Wall and Partition Penetrations (That Are Not Fire Rated):
Install insulation continuously through walls and partitions.
C. Insulation Installation at Fire-Rated Wall and Partition Penetrations:
1. Install pipe insulation continuously through pipe penetrations of fire-rated walls and
partitions.
2. Install duct insulation continuously through duct penetrations of fire-rated walls and
partitions, for cases where no fire or smoke damper is required.
3. Terminate duct insulation at fire or smoke damper sleeves for cases where fire or
smoke dampers are used, but overlap duct insulation at least 2-inches (50 mm)
onto sleeve.
4. Firestopping and fire-resistive joint sealers are specified in Division 07 Section
“Penetration Firestopping.”
D. Insulation Installation at Floor Penetrations:
1. Duct: Install insulation continuously through floor penetrations that are not fire
rated. For penetrations through fire-rated assemblies, terminate insulation at fire
damper sleeves and externally insulate damper sleeve beyond floor to match
adjacent duct insulation. Overlap damper sleeve and duct insulation at least 2-
inches (50 mm).
2. Pipe: For below-ambient piping services, install insulation continuously through floor
penetrations. For above-ambient piping services, either do the same as for below-
ambient piping, or it is acceptable to install uninsulated piping through the slab
and butt the pipe insulation tight to the slab on both the top side and the
underneath side.
3. Seal penetrations through fire-rated assemblies according to Division 07 Section
“Penetration Firestopping.”
A. See Part 4 Insulation Schedules for specific requirements.
B. The following ductwork items need not be insulated, unless noted otherwise:
1. Factory-insulated flexible ducts.
2. Factory-insulated plenums, casings, fan housings, and air terminal units.
3. Flexible connectors.
4. Vibration-control devices.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 12 Mechanical Insulation
C. Secure all insulation on ducts and plenums with insulation pins. Install either capacitor-
discharge-weld pins and speed washers or cupped-head, capacitor-discharge-weld
pins on sides and bottom of horizontal ducts and sides of vertical ducts as follows:
1. On duct sides with dimensions 18-inches (450 mm) and smaller, pins may be
omitted.
2. On duct sides with dimensions 18-inches (450 mm) and larger, place pins along
longitudinal centerline of duct. Space 3-inches (75 mm) maximum from insulation
end joints, and 16-inches (400 mm) o.c.
3. On duct sides with dimensions larger than 36-inches (900 mm), place pins 16-inches
(400 mm) o.c. each way, and 3-inches (75 mm) maximum from insulation joints.
Install additional pins to hold insulation tightly against surface at cross bracing.
4. Pins may be omitted from top surface of horizontal, rectangular ducts and
plenums.
5. Do not over-compress insulation during installation.
6. If using blanket insulation, impale insulation over pins and attach speed washers.
7. Cut excess portion of pins extending beyond speed washers or bend parallel with
insulation surface. Cover exposed pins and washers with tape matching insulation
facing.
D. For ducts and plenums with surface temperatures below ambient, install a continuous
unbroken vapor barrier. Create a facing lap for longitudinal seams and end joints with
insulation by removing 2-inches (50 mm) from 1 edge and 1 end of insulation segment.
Secure laps to adjacent insulation section with ½-inch (13-mm) outward-clinching
staples, 1-inch (25 mm) o.c. Complete the vapor barrier by applying FSK tape specified
in Part 2, or vapor-barrier mastic and sealant, at all joints, seams, and protrusions.
1. Repair punctures, tears, and penetrations with tape or mastic to maintain vapor-
barrier seal.
2. Install vapor stops for ductwork and plenums operating below 50ºF (10 C) at 18-
foot (5.5-m) intervals. Vapor stops shall consist of vapor-barrier mastic applied in a
Z-shaped pattern over insulation face, along butt end of insulation, and over the
surface. Cover insulation face and surface to be insulated a width equal to 2 times
the insulation thickness but not less than 3-inches (75 mm).
E. If using blanket insulation, overlap unfaced blankets a minimum of 2-inches (50 mm) on
longitudinal seams and end joints. At end joints, secure with steel bands spaced a
maximum of 18-inches (450 mm) o.c.
F. Unless factory-insulated, install duct insulation continuously and unbroken over duct-
mounted accessories such as fans, coils, terminal units, etc.
G. Install insulation on rectangular duct elbows and transitions with a full insulation section
for each surface. If using board insulation, groove and score insulation to fit as closely as
possible to outside and inside radius of elbows.
H. Install insulation on round and flat-oval duct elbows with individually mitered gores cut to
fit the elbow.
I. Insulate duct stiffeners, hangers, and flanges that protrude beyond insulation surface with
6-inch- (150-mm-) wide strips of same material used to insulate duct. Secure on
alternating sides of stiffener, hanger, and flange with pins spaced 6-inches (150 mm) o.c.
3.6 EQUIPMENT, TANK, AND VESSEL INSULATION INSTALLATION
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 13 Mechanical Insulation
A. See Part 4 Insulation Schedules for specific requirements.
B. Where required, secure blanket or board insulation to equipment, tanks and vessels with
adhesive and anchor pins and speed washers.
1. Apply adhesives according to manufacturer's recommended coverage rates per
unit area, for 50 percent coverage of tank and vessel surfaces.
2. Groove and score insulation materials to fit as closely as possible to equipment,
including contours. Bevel insulation edges for cylindrical surfaces for tight joints.
Stagger end joints.
4. Install adhesively attached or self-sticking insulation hangers and speed washers
on sides of tanks and vessels. Do not weld anchor pins to ASME-labeled pressure
vessels. Select insulation hangers and adhesive that are compatible with service
temperature and with substrate. On tanks and vessels, maximum anchor-pin
spacing is 3-inches (75 mm) from insulation end joints, and 16-inches (400 mm) o.c.
in both directions. Do not over-compress insulation during installation. Cut and miter
insulation segments to fit curved sides and domed heads of tanks and vessels.
Impale insulation over anchor pins and attach speed washers. Cut excess portion
of pins extending beyond speed washers or bend parallel with insulation surface.
Cover exposed pins and washers with tape matching insulation facing.
5. Secure each layer of insulation with stainless-steel or aluminum bands. Select band
material compatible with insulation materials.
6. Where insulation hangers on equipment and vessels are not permitted or practical
and where insulation support rings are not provided, install a girdle network for
securing insulation. Stretch pre-stressed aircraft cable around the diameter of
vessel and make taut with clamps, turnbuckles, or breather springs. Place one
circumferential girdle around equipment approximately 6-inches (150 mm) from
each end. Install wire or cable between two circumferential girdles 12-inches (300
mm) o.c. Install a wire ring around each end and around outer periphery of center
openings, and stretch pre-stressed aircraft cable radially from the wire ring to
nearest circumferential girdle. Install additional circumferential girdles along the
body of equipment or tank at a minimum spacing of 48-inches (1200 mm) o.c. Use
this network for securing insulation with tie wire or bands.
7. Stagger joints between insulation layers at least 3-inches (75 mm).
8. Install insulation in removable segments on equipment access doors, manholes,
handholes, and other elements that require frequent removal for service and
inspection.
9. Bevel and seal insulation ends around manholes, handholes, ASME stamps, and
nameplates.
10. For equipment with surface temperatures below ambient, apply mastic to open
ends, joints, seams, breaks, and punctures in insulation.
C. Flexible Elastomeric Thermal Insulation Installation for Tanks and Vessels: Install insulation
over entire surface of tanks and vessels.
1. Apply 100 percent coverage of adhesive to surface with manufacturer's
recommended adhesive.
D. Insulation Installation on Pumps:
1. Fabricate metal boxes lined with insulation. Fit boxes around pumps and coincide
box joints with splits in pump casings. Fabricate joints with outward bolted flanges.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 14 Mechanical Insulation
Bolt flanges on 6-inch (150-mm) centers, starting at corners. Install 3/8-inch- (10-mm-
) diameter fasteners with wing nuts. Alternatively, secure the box sections together
using a latching mechanism.
2. Fabricate boxes from aluminum or stainless steel, at least 0.040-inch (1.0 mm) thick.
3. For below ambient services, install a vapor barrier at seams, joints, and
penetrations. Seal between flanges with replaceable gasket material to form a
vapor barrier.
A. See Part 4 Insulation Schedules for specific requirements.
B. Requirements in this Article generally apply to all insulation materials except where more
specific requirements are specified in various pipe insulation material installation articles.
C. Insulation Installation on Straight Pipes and Tubes:
1. Secure each layer of insulation to pipe with tape or bands and tighten without
deforming insulation materials. If furnished in half sections, orient longitudinal joints
at 3 and 9 o'clock positions on the pipe.
2. All insulation shall be tightly butted and free of voids and gaps at all joints.
3. Where vapor barriers are indicated, seal longitudinal seams, end joints, and
protrusions with vapor-barrier mastic and joint sealant.
4. For insulation with factory-applied jackets on above ambient services, secure laps
with outward clinched staples at 6-inches (150 mm) o.c.
5. For insulation with factory-applied jackets on below ambient services, do not staple
longitudinal tabs but secure tabs with additional adhesive as recommended by
insulation material manufacturer and seal with vapor-barrier mastic and flashing
sealant. Vapor barrier must be continuous.
D. Insulation Installation on Pipe Flanges or Mechanical Couplings:
1. Install preformed pipe insulation to outer diameter of pipe flange or mechanical
coupling (such as grooved pipe couplings, if applicable).
2. Make width of insulation section same as overall width of flange/coupling and
bolts, plus twice the thickness of pipe insulation, not to exceed 1½-inch (38-mm)
thickness.
3. Fill voids between inner circumference of flange/coupling insulation and outer
circumference of adjacent straight pipe segments with cut sections of block
insulation of same thickness as pipe insulation.
4. Install jacket material with manufacturer's recommended adhesive, overlap seams
at least 1-inch (25 mm), and seal joints with flashing sealant.
E. Insulation Installation on Pipe Fittings and Elbows:
1. Install preformed sections of same material as straight segments of pipe insulation
when available. Secure according to manufacturer's written instructions.
2. When preformed insulation elbows and fittings are not available, install mitered
sections of pipe insulation, to a thickness equal to adjoining pipe insulation. Secure
insulation materials with wire or bands.
3. Cut sectional pipe insulation to fit. Each piece shall be butted tightly against
adjoining piece and bonded with adhesive. Fill joints, seams, voids, and irregular
surfaces with insulating cement finished to a smooth, hard, and uniform contour
that is uniform with adjoining pipe insulation.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 15 Mechanical Insulation
F. Insulation Installation on Valves, Strainers, Unions, and Specials:
1. Insulate valves using preformed fitting insulation or sectional pipe insulation of same
material, density, and thickness as used for adjacent pipe. Overlap adjoining pipe
insulation by not less than two times the thickness of pipe insulation, or one pipe
diameter, whichever is thicker. For valves, insulate up to and including the bonnets,
valve stuffing-box studs, bolts, and nuts. Fill joints, seams, and irregular surfaces with
insulating cement.
2. Arrange insulation to permit access to packing and to allow valve operation
without disturbing insulation.
otherwise indicated.
4. Insulate strainers using preformed fitting insulation or sectional pipe insulation of
same material, density, and thickness as used for adjacent pipe. Overlap adjoining
pipe insulation by not less than two times the thickness of pipe insulation, or one
pipe diameter, whichever is thicker. Fill joints, seams, and irregular surfaces with
insulating cement. Insulate strainers so strainer basket flange or plug can be easily
removed and replaced without damaging the insulation and jacket. Provide a
removable reusable insulation cover. For below-ambient services, provide a design
that maintains vapor barrier.
5. Insulate unions using a section of oversized preformed pipe insulation. Overlap
adjoining pipe insulation by not less than two times the thickness of pipe insulation,
or one pipe diameter, whichever is thicker.
6. Cover segmented insulated surfaces with a layer of finishing cement and coat with
a mastic. Install vapor-barrier mastic for below ambient services and a breather
mastic for above ambient services. Reinforce the mastic with fabric-reinforcing
mesh. Trowel the mastic to a smooth and well-shaped contour.
7. For services not specified to receive a field-applied jacket except for flexible
elastomeric, install fitted PVC cover over elbows, tees, strainers, valves, flanges,
and unions. Terminate ends with PVC end caps. Tape PVC covers to adjoining
insulation facing using PVC tape.
8. Stencil or label the outside insulation jacket of each union with the word “UNION.”
Match size and color of pipe labels.
G. Insulate instrument connections for thermometers, pressure gages, pressure temperature
taps, test connections, flow meters, sensors, switches, and transmitters on insulated pipes,
vessels, and equipment. Shape insulation at these connections by tapering it to and
around the connection with insulating cement and finish with finishing cement, mastic,
and flashing sealant.
following:
1. Make removable flange and union insulation from sectional pipe insulation of same
thickness as that on adjoining pipe. Install same insulation jacket as adjoining pipe
insulation.
2. When flange and union covers are made from sectional pipe insulation, extend
insulation from flanges or union long at least two times the insulation thickness over
adjacent pipe insulation on each side of flange or union. Secure flange cover in
place with stainless-steel or aluminum bands. Select band material compatible
with insulation and jacket.
3. Construct removable valve insulation covers in same manner as for flanges except
divide the two-part section on the vertical center line of valve body.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 16 Mechanical Insulation
4. When covers are made from block insulation, make two halves, each consisting of
mitered blocks wired to stainless-steel fabric. Secure this wire frame, with its
attached insulation, to flanges with tie wire. Extend insulation at least 2-inches (50
mm) over adjacent pipe insulation on each side of valve. Fill space between
flange or union cover and pipe insulation with insulating cement. Finish cover
assembly with insulating cement applied in two coats. After first coat is dry, apply
and trowel second coat to a smooth finish.
5. Unless a PVC jacket is indicated in field-applied jacket schedules, finish exposed
surfaces with a metal jacket.
I. Special Requirements for Flexible Elastomeric Insulation Installation: Seal all transverse
seams, longitudinal seams, end joints, and section joints with manufacturer's
recommended adhesive to eliminate openings in insulation that allow passage of air to
surface being insulated.
A. See Part 4 Insulation Schedules for specific requirements.
B. Where PVC jackets are indicated, install with 1-inch (25-mm) overlap at longitudinal
seams and end joints; for horizontal applications, install with longitudinal seams along top
and bottom of tanks and vessels. Seal with manufacturer's recommended adhesive.
Apply two continuous beads of adhesive to seams and joints, one bead under lap and
the finish bead along seam and joint edge.
C. Where metal jackets are indicated, install with 2-inch (50-mm) overlap at longitudinal
seams and end joints. Overlap longitudinal seams arranged to shed water. Seal end joints
with weatherproof sealant recommended by insulation manufacturer. Secure jacket
with stainless-steel bands 12-inches (300 mm) o.c. and at end joints.
3.9 FINISHES
A. Flexible Elastomeric Thermal Insulation: After adhesive has fully cured, apply two coats of
insulation manufacturer's recommended protective coating.
PART 4 - SCHEDULES
4.1 INSULATION SCHEDULES
A. Furnish and install duct, equipment, and piping insulation as specified above and in
accordance with the schedules below. All insulation thicknesses and pipe sizes in the
following tables are given in nominal inches. Where more than one type of allowable
material or more than one type of field jacket is listed, the choice is contractor’s option.
CP150492 University of Missouri Teaching Hospital – West Wing – Expansion/Renovation
23 0700 - 17 Mechanical Insulation
DUCT INSULATION Duct Duct Minimu
m
Allowabl
e
Insulatio
(including outdoor air Round,
that has been heated Outdoo
rs R-6 FGBK,FE 2.00 AL,SS
or cooled) ICC,ICN R-3.5 FGBK 1.50 ---
Rectangul
Outdoo
Outdoor Air Service ICC,ICN R-3.5 FGBK 1.50 ---
(prior to being heated Round,
Oval IEC,IEN R-3.5 FGBK 1.50 AL (3)
or cooled) Outdoo
Outdoo
rs --- --- --- ---
KEYED NOTES:
(1) Insulate only if the exhaust is routed to an energy-recovery device.
(2) Insulate only between final isolation damper and penetration of
building exterior.
(3) The specified field jacket is required only if less than 84-inches AFF.
LEGEND:
Silicate
space FRW
IEN Indoor, Exposed, in Non-conditioned
space SS Stainless Steel
FE Flexible Elastomeric
23 0700 - 18 Mechanical Insulation
EQUIPMENT INSULATION Allowabl
s
Thicknes
s
Jacke
Heat Exchangers Outdoors Any FE 2.00 AL,SS
Heating Indoors Any MF 2.00 ---
Outdoors Any MF 2.00 AL,SS
Expansion Tanks Heating Indoors Any MF 1.00 ---
Water Outdoors Any MF 1.00 AL,SS
Other
Services
HVAC Pumps, Chilled Indoors Any FE 1.00 ---
Air/Dirt Separators, Water Outdoors Any FE 2.00 AL,SS
Other
Services
Steam System Equipment
Condensa
KEYED NOTES:
(1) Insulate only if used as part of a water-side economizer.
(2) Includes heat recovery, dual-service, and closed-loop condenser
water.
feedwater.
(4) Includes deaerators, CRT/P, flash tanks, flash separators, blow-off tanks.
LEGEND:
MF Mineral Fiber SS Stainless Steel
CRT/P Condensate Receiver Tank & Pump
Package
23 0700 - 19 Mechanical Insulation
PIPE INSULATION Temperature Size Allowabl
e Thick- Field Keyed
Service drains,
blowdowns, steam
vents, coil
condensate, all 8 & up Indoors MFW 0.50 PVC (3)
equipment drains above 105 All All MF 1.00 AL,SS (2)
¾ to
Chilled Water Piping 40 and up Outdoors FE 2.00 AL,SS
(supply and return) 1½ to
6 Indoors FE 1.50 ---
Outdoors FE 2.00 AL,SS
Steam Condensate
1½ &
201-250 HW, ¾ to
≤15#Steam, 4 & up All MF 3.00 AL,SS (2)
& all SCR
15.1#Steam
120#Steam 1½ &
KEYED NOTES:
(1) Insulate condenser water piping only if used as part of a water-side
economizer, or if freeze-protected (e.g., heat-traced) outdoors.
(2) The specified field jacket is required only if outdoors.
(3) The specified field jacket is required on fittings only.
LEGEND:
FE Flexible Elastomeric PI Polyisocyanurat
e
SCR Steam Condensate Return HW Hot Water
MFW Mineral Fiber with Wicking Design SS Stainless Steel
PVC Polyvinyl Chloride # psig
STAIR
ELEVATOR
MECHMECH
EMERGENCY
ELEVATOR
ELEV.
ELEV.
ELEV.
ELEV.
ELEV.
ELEV.
LOBBY
CLOSET
OFFICE
ROOM
30"/16" SA
18"x10" RA
10"x8" RA
12"x10" SA(X)
8"ø SA(X)
7
9
1
1
1
7
72
72
1
(X )
24"x12" SA UP (AHU S2-3) WITH FIRE DAMPER AT 2ND FLOOR SLAB. REFER TO SHEET MD102.
20"x12" SA DOWN (AHU S2-3). REFER TO SHEET MD100 FOR CONTINUATION.
VVR-7
CVR-6
CVR-10
FSD
FSD
FSD
VVR-8
VVR-12
VVR-5 VVR-10
UP (VFE-2)
80"x36" EA UP & DOWN (VFE-1)
48"x18" OA DOWN (VFS-1)
1
7
71
1
8"Ø
REFER TO SHEET M000 FOR GENERAL NOTES.
CAP ALL EXISTING TEMPERATURE CONTROL PNEUMATIC TUBING AT MAINS WITH BRASS COMPRESSION FITTING WHERE EXISTING PNEUMATIC CONTROLS HAVE BEEN REMOVED.
REFER TO ARCHITECTURAL PHASING PLANS PRIOR TO THE START OF ANY DEMOLITION WORK TO VERIFY WHAT SYSTEMS ARE AFFECTED IN EACH PHASE. COORDINATE ALL REQUIRED SHUT DOWNS WITH OWNER'S REPRESENTATIVE.
GENERAL NOTES:
Pr o
je c
t Ti
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
- DEMOLITION
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
KEYED NOTES
9 REMOVE EXISTING RECESSED CABINET UNIT HEATER AND PORTION OF EXISTING BRANCH PIPING FROM CONNECTION POINT OF UNIT TO ABOVE CEILING AS SHOWN AND PROVIDE TEMPORARY CAPS. REFER TO SHEET M101A FOR NEW WORK.
10 REMOVE EXISTING ISOLATION ROOM LOW WALL EXHAUST GRILLE, EXHAUST DUCT, AND ASSOCIATED VENTURI VALVE TO POINT SHOWN.
11 REMOVE EXISTING RATED DAMPER IN EXISTING DUCT. REFER TO SHEET M101 FOR NEW WORK.
12 REMOVE PORTION OF EXISTING DUCTWORK FOR INSTALLATION OF NEW RATED DAMPER. REFER TO SHEET M101 FOR NEW WORK.
13 PRIOR TO THE START OF ANY DEMOLITION WORK, PROVIDE DUCT TRAVERSE AT POINT INDICATED. RECORD AIRFLOW AND COMPILE IN A WRITTEN REPORT. SUBMIT REPORT TO OWNER, ARCHITECT, AND ENGINEER FOR THEIR RECORDS. DATA SHALL BE USED TO REBALANCE EXISTING EXHAUST SYSTEM DURING REMODEL PORTION OF PROJECT. REFER TO SHEET M102 FOR NEW WORK.
14 REMOVE EXISTING PNEUMATIC CONTROLLER ON EXISTING AIR TERMINAL UNIT AND REPLACE WITH NEW DDC CONTROLLER. REFER TO SHEET M101 FOR NEW WORK.
15 THIS PORTION OF EXISTING DUCTWORK THAT IS SHADED FALLS IN PHASE 3 BUT IS REQUIRED TO BE REMOVED IN PHASE 1C. REFER TO SHEET M101 FOR NEW WORK.
KEYED NOTES
4 REMOVE EXISTING SUSPENDED FAN COIL UNIT ABOVE CEILING AND ALL ASSOCIATED DUCTWORK AND AIR DEVICES. REFER TO SHEET MD101A FOR DEMOLITION WORK ASSOCIATED WITH EXISTING PIPING AND CONTROLS.
5 REMOVE EXISTING FLOOR MOUNTED CABINET UNIT HEATER. PATCH AND FINISH PER ARCHITECT. REFER TO SHEET MD101A FOR DEMOLITION WORK ASSOCIATED WITH EXISTING PIPING AND CONTROLS.
6 REMOVE EXISTING 36"x15" OUTSIDE AIR DUCT LOCATED IN AREAWAY. REFER TO SHEET MD100 FOR CONTINUATION OF DUCT DEMOLITION.
7 CAP EXISTING DUCT AIRTIGHT WITH SHEETMETAL. INSULATE CAP IN SUPPLY DUCTS WITH 1 1/2" THICK FOIL FACED DUCT WRAP.
8 REMOVE AIR DEVICE AND PORTION OF BRANCH DUCT AS SHOWN. REFER TO SHEET M101 FOR NEW WORK.
KEYED NOTES
1 REMOVE EXISTING DUCTWORK AND AIR DEVICES TO POINT SHOWN.
2 REMOVE EXISTING PNEUMATIC AIR TERMINAL UNIT. REFER TO SHEET MD101A FOR DEMOLITION WORK ASSOCIATED WITH EXISTING PIPING AND CONTROLS.
#
OFFICE OFFICE
EXISTING 6" CWS AND CWR RISERS
EXISTING 18"x14" EXHAUST DUCT DOWN TO FIRST FLOOR (EF-18)
2
E18-1
2
E24-1
2
E24-2
2
E18-2
3
8.1 XD
E.1
EXISTING 2" OIL TANK VENT EXPOSED ON WALL, TERMINATE APPROXIMATELY 8'-0" ABOVE SECOND FLOOR.
6
7
FC
8 "
REFER TO SHEET M000 FOR GENERAL NOTES.
PROVIDE SOLDERED CAP ON ALL EXISTING TEMPERATURE CONTROL PNEUMATIC TUBING AT MAINS WHERE EXISTING PNEUMATIC CONTROLS HAVE BEEN REMOVED.
REFER TO ARCHITECTURAL PHASING PLANS PRIOR TO THE START OF ANY DEMOLITION WORK TO VERIFY WHAT SYSTEMS ARE AFFECTED IN EACH PHASE. COORDINATE ALL REQUIRED SHUT DOWNS WITH OWNER'S REPRESENTATIVE.
GENERAL NOTES:
Pr o
je c
t Ti
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
# KEYED NOTES
1 REMOVE EXISTING 34" x 14" EXHAUST RISER (EF-24) AND ASSOCIATED EXHAUST DUCT TO POINT SHOWN. REFER TO SHEET M102 FOR NEW WORK. PATCH FLOOR PER ARCHITECT.
2 PRIOR TO THE START OF ANY DEMOLITION WORK, PROVIDE DUCT TRAVERSE AND STATIC PRESSURE READING AT POINT INDICATED. RECORD AIRFLOW AND STATIC PRESSURE DATA AND COMPILE IN A WRITTEN REPORT WITH NUMBER INDICATED ON THE PLANS. SUBMIT REPORT TO OWNER, ARCHITECT, AND ENGINEER FOR THEIR RECORDS. DATA SHALL BE USED TO REBALANCE EXISTING SYSTEM DURING REMODEL PORTION OF PROJECT. REFER TO SHEET M102 FOR NEW WORK.
3 REMOVE EXISTING 6" CWS AND CWR AND 1" PNEUMATIC CONTROL RISERS FROM APPROXIMATELY 8'-6" A.F.F. THRU THIRD FLOOR PENETRATION. REMOVE EXISTING FIBERGLASS INSULATION ON CHILLED WATER PIPING TO REMAIN AND RE-INSULATE WITH ELASTOMERIC. PATCH FLOOR PER ARCHITECT. RISERS TO BE RELOCATED FOR NEW STAIR ACCESS ON THIRD FLOOR. REFER TO SHEET M102 FOR NEW WORK.
4 REMOVE EXISTING EXHAUST LOUVER AND PLENUM ABOVE WINDOW. REFER TO SHEET M102 FOR NEW WORK.
5 REMOVE EXISTING 48" W x 12" H OUTSIDE AIR LOUVER. PATCH WALL PER ARCHITECT.
6 REMOVE EXISTING EXPOSED FUEL OIL TANK VENT PIPING AND VENT TERMINATION CAP. REFER TO SHEET M400 FOR NEW WORK.
7 EXISTING OUTSIDE AIR INTAKE LOUVER TO REMAIN.
8 PRIOR TO THE START OF ANY DEMOLITION WORK, PROVIDE DUCT TRAVERSE AT POINT INDICATED. RECORD AIRFLOW AND COMPILE IN A WRITTEN REPORT. SUBMIT REPORT TO OWNER, ARCHITECT, AND ENGINEER FOR THEIR RECORDS. DATA SHALL BE USED TO REBALANCE EXISTING EXHAUST SYSTEM DURING REMODEL PORTION OF PROJECT. REFER TO SHEET M102 FOR NEW WORK.
9 REMOVE EXISTING OUTSIDE AIR LOUVERS. PATCH WALL PER ARCHITECT. REMOVE PORTION OF EXISTING AHU S2-13 OUTSIDE AIR DUCT AS SHOWN. REFER TO SHEET M400 FOR NEW WORK ASSOCIATED WITH EXISTING AHU S2-13 OUTSIDE AIR DUCT.
10 REMOVE PORTION OF EXISTING DUCTWORK FOR INSTALLATION OF NEW RATED DAMPER. REFER TO SHEET M102 FOR NEW WORK.
11 REMOVE EXISTING DUCT TO POINT SHOWN AND CAP TO FACILITATE INSTALLATION OF NEW CHILLED WATER PIPING. REFER TO SHEET M102 FOR NEW WORK.
12 REMOVE EXISTING EXHAUST FAN ABOVE CEILING. REFER TO SHEET M102 FOR NEW WORK.
3
3
36"x32" RA 36"x18" RA
36"x16" RA 20"x12" RA
12"x10" RA
(X )
5
11
12
EXISTING 24"x12" SA DUCT UP (AHU S2-3). REFER TO SHEET M102 FOR CONT.
EXISTING 20"x12" SA DUCT DOWN (AHU S2-3). REFER TO SHEET M100 FOR CONT.
VAV
23-102
EAB
23-109
S-2
100
R-1
100
E-1
50
E-2
80
11
11
11
12"x10" RA
REFER TO SHEET M000 FOR GENERAL NOTES.
REFER TO AIR TERMINAL UNIT SCHEDULE ON SHEET M600 FOR AIR INLET SIZES TO AIR TERMINAL UNITS.
GENERAL NOTES:
NEW AIR HANDLING UNIT SYSTEM (AHU-23/RF-23) SHALL NOT BE USED TO CONDITION FIRST FLOOR DURING ANY PHASE. UNIT SHALL BE ACTIVATED ONLY AFTER PHASE 1 IS COMPLETED AND SHALL ONLY CIRCULATE AIR IN SPACES AS SPACES ARE COMPLETED.
Pr o
je c
t Ti
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
- NEW WORK
U n
iv e
rs ity
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
KEYED NOTES
19 INSTALL NEW DDC CONTROLLER ON EXISTING AIR TERMINAL UNIT. BALANCE TO MAXIMUM AND MINIMUM CFM NOTED ON PLAN.
20 EXISTING 18"x18" EXHAUST DUCT (EF-1) UP TO SECOND FLOOR. SEE SHEET M102 FOR CONTINUATION.
21 EXISTING 18"Ø SA DUCT (AHU-2) UP TO SECOND FLOOR. SEE M102 FOR CONTINUATION.
22 EXISTING 16"x10" OA DUCT UP TO SECOND FLOOR. SEE M102 FOR CONTINUATION.
23 LOCATION OF DUCT STATIC PRESSURE SENSOR FOR CONTROL OF AHU-23 SUPPLY FANS VARIABLE FREQUENCY DRIVES. REFER TO SEQUENCE OF OPERATION ON SHEET M700. ADDITIONAL DUCT STATIC PRESSURE SENSOR LOCATED ON THIRD FLOOR. REFER TO SHEET M103 FOR LOCATION.
24 INSTALL NEW MANUAL BALANCING DAMPER IN EXISTING DUCT. VERIFY EXISTING DUCT SIZE IN FIELD PRIOR TO ORDERING.
25 INSTALL MANUAL BALANCING DAMPER IN PHASE 1B AND INSTALL TEMPORARY CAP. REMAINING BRANCH DUCTWORK AND AIR DEVICES TO BE INSTALLED IN PHSE 1C
26 EXHAUST AIR TERMINAL UNIT TO BE INSTALLED IN PHASE 1C. TEMPORARILY CONNECT NEW 10"Ø EXHAUST DUCT TO EXISTING EXHAUST MAIN IN PHASE 1A. FINAL BALANCE OF AIR DEVICES ASSOCIATED WITH EXHAUST AIR TERMINAL SHALL BE DONE IN PHASE 1C.
27 THIS SHADED PORTION OF NEW DUCTWORK FALLS IN AREA DESIGNATED FOR PHASE 3 BUT NEEDS TO BE INSTALLED IN PHASE 1C. PROVIDE 8" TAP AND RECONNECT EXISTING VAV THAT WILL REMAIN UNTIL PHASE 3. REFER TO SHEET MD101.
28 12"Ø EXHAUST DUCT (EF-51) UP TO SECOND FLOOR WITH COMBINATION FIRE/ SMOKE DAMPER IN SECOND FLOOR SLAB. REFER TO SHEET M400 FOR CONTINUATION.
29 COORDINATE LOCATION OF DUCTWORK AND AIR DEVICES INSIDE X-RAY ROOM WITH X-RAY EQUIPMENT SUPPORTS.
30 SEAL ALL NEW AND EXISTING DUCT PENETRATIONS OF WALLS AND AROUND AIR DEVICES INSTALLED IN CEILING AND SIDEWALL IN ISOLATION AND ANTE ROOMS AIRTIGHT TO FACILITATE MAINTAINING PRESSURE RELATIONSHIP TO ADJACENT SPACES.
KEYED NOTES
8 34"x20" RETURN DUCT (RF-23) UP TO SECOND FLOOR WITH COMBINATION FIRE/SMOKE DAMPER IN SECOND FLOOR SLAB. REFER TO SHEET M400 FOR CONTINUATION.
9 40"x24" SUPPLY DUCT (AHU-23) UP TO SECOND FLOOR WITH COMBINATION FIRE/SMOKE DAMPER IN SECOND FLOOR SLAB. REFER TO SHEET M400 FOR CONTINUATION. ROTATE IN VERTICAL BELOW SECOND FLOOR SLAB AS SHOWN.
10 REBALANCE EXISTING AIR DEVICE TO CFM NOTED ON PLAN.
11 CONNECT NEW AIR DEVICE BRANCH DUCT TO EXISTING AND EXTEND TO NEW AIR DEVICE. PROVIDE TRANSITION AS REQUIRED FOR NEW AIR DEVICE NECK SIZE. PROVIDE NEW MANUAL BALANCING DAMPER IN BRANCH DUCT.
12 CONNECT NEW DDC AIR TERMINAL UNIT TO EXISTING SUPPLY DUCT. PROVIDE TRANSITION AS REQUIRED.
13 EXISTING 43"x30" AND 24"x18" SUPPLY AIR DUCTS (AHU-1) UP TO SECOND FLOOR. REFER TO SHEET M102 FOR CONTINUATION.
14 INSTALL NEW RATED DAMPER IN EXISTING DUCT. VERIFY EXISTING DUCT SIZE IN FIELD PRIOR TO ORDERING.
15 REBALANCE EXISTING AIR TERMINAL UNIT TO MAXIMUM AND MINIMUM AIR QUANTITIES NOTED ON PLAN.
16 20"x14" SUPPLY DUCT (AHU-23) UP TO SECOND FLOOR WITH COMBINATION FIRE / SMOKE DAMPER IN SECOND FLOOR SLAB. REFER TO SHEET M400 FOR CONTINUATION.
17 18"x16" SUPPLY DUCT (AHU-23) AND 16"x14" RETURN DUCT (RF-23) DOWN THRU EXISTING FIRST FLOOR SLAB TO GROUND FLOOR. REFER TO SHEET M100 FOR CONTINUATION. LOCATE NEW OPENINGS BETWEEN EXISTING CONCRETE TEES. VERIFY LOCATION OF TEES IN FIELD.
18 DUCT CROSSING PERPENDICULARLY AT EXISTING COLUMN LINE "X", TO ROUTE UNDER EXISTING CONCRETE BEAM. HOLD TOP OF DUCT TIGHT TO BEAM.
KEYED NOTES
1 9" ISOLATION EXHAUST DUCT UP TO SECOND FLOOR (EF-53A & EF-53B) WITH COMBINATION FIRE / SMOKE DAMPER IN SECOND FLOOR SLAB. REFER TO SHEET M400 FOR CONTINUATION.
2 18"Ø EXHAUST DUCT UP THRU ROOF TO EXHAUST FANS EF-52A AND EF-52B. REFER TO SHEET M120 FOR CONTINUATION.
3 CONNECT NEW 16"x10" EXHAUST DUCT TO EXISTING 16"x10" EXHAUST DUCT AS SHOWN.
4 INSTALL NEW PORTION OF EXISTING DUCTWORK WHERE RATED DAMPER WAS REMOVED. VERIFY EXISTING DUCT SIZE IN FIELD. INSULATE DUCT WITH FOIL FACED INSULATION TO MATCH EXISTING. PROVIDE PROPER VAPOR BARRIER WHERE NEW INSULATION BUTTS TO EXISTING INSULATION.
5 EXISTING 14" EXHAUST RISER UP TO EXISTING EXHAUST FANS EF-1 AND EF-2 ON EXISTING FIRST FLOOR LOW ROOF. REFER TO SHEET M120 FOR CONTINUATION.
6 CONNECT NEW 12" EXHAUST DUCT TO EXISTING EXHAUST MAIN.
#
# #
3/4"
VAV
23-109
VAV
23-101
VAV
23-116
VAV
1-111
VAV
1-100
VAV
23-113
7
CUH-1
VAV
W R EXISTING 2 1/2" LPR, 4" LPS,
2 1/2" HWR, 2 1/2" HWS, 5" CWS, 5" CWR UP TO SECOND FLOOR
VAV
1-101
VAV
23-105
19
19
19
19
19
STACK PIPING THRU EXISTING WALL ABOVE NEW DOOR OPENING. PROVIDE LINTEL AS REQUIRED.
PIPING SHOWN SIDE BY SIDE FOR CLARITY. INSTALLATION WILL REQUIRE PIPING TO BE STACKED IN TWO LAYERS.
AREA OF WORK | CP150492
REFER TO SHEET M000 FOR GENERAL NOTES.
HEATING HOT WATER RUN OUT SIZES TO AIR TERMINAL UNIT REHEAT COILS SHALL BE 3/4" UNLESS NOTED OTHERWISE.
INSTALL NEW WALL MOUNTED TEMPERATURE, HUMIDITY, AND CO2 SENSORS 48" A.F.F. TO TOP OF DEVICES .
GENERAL NOTES:
Pr o
je c
t Ti
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
NEW WORK
U n
iv e
rs ity
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
1 FIRST FLOOR PLAN - PIPING - NEW WORK
KEYED NOTES
10 REBALANCE EXISTING UNIT TO GPM NOTED ON PLAN.
11 INSTALL NEW DDC 2-WAY CONTROL VALVE IN EXISTING BRANCH PIPING SERVING EXISTING AIR TERMINAL UNIT. BALANCE FOR GPM NOTED ON PLAN.
12 INSTALL NEW WALL MOUNTED DDC THERMOSTAT IN SAME LOCATION EXISTING PNEUMATIC THERMOSTAT WAS REMOVED. PATCH WALL PER ARCHITECT.
13 THE CONTRACTOR SHALL FABRICATE A STAINLESS STEEL DRIP PAN WITH ROLLED EDGES (NO EXPOSED CUT EDGES) FOR INSTALLATION UNDER FAN COIL UNIT. SUSPEND FROM STRUCTURE ABOVE. PAN SHALL BE 3" TALL AND EXTEND A MINIMUM OF 4 INCHES BEYOND OUTLINE OF UNIT. INSTALL AN EARLY WARNING WATER LEAK DETECTION SYSTEM IN DRIP PAN. PROVIDE SENSOR CABLE IN PAN AND ROUTE CONTROL SIGNAL BACK TO NEAREST EMCS PANEL AND ALARM AT EMCS. INSTALL CONDENSATE PUMP IN DRIP PAN. REFER TO FAN COIL UNIT SCHEDULE ON SHEET M600 FOR CONDENSATE PUMP SPEC.
14 CALIBRATED BALANCING VALVE. BALANCE FOR 1 GPM.
15 LOCATION OF HEATING HOT WATER SYSTEM DIFFERENTIAL PRESSURE SENSOR FOR CONTROL OF HEATING HOT WATER PUMPS HWP-10 AND HWP-11 VARIABLE FREQUENCY DRIVE. REFER TO DETAIL 4 ON SHEET M500 AND 4 ON SHEET M703.
16 3/4" HWS AND HWR DOWN IN WALL TO GROUND FLOOR. REFER TO SHEET M100 FOR CONTINUATION.
17 INSTALL CEILING MOUNTED SPACE PRESSURE SENSOR. REFER TO DETAIL 3 ON SHEET M703.
18 6" STEAM VENT UP THRU ROOF. REFER TO SHEET M120 FOR CONTINUATION.
19 SEAL ALL NEW AND EXISTING PIPE PENETRATIONS OF WALLS IN ISOLATION AND ANTE ROOMS AIRTIGHT TO FACILITATE MAINTAINING PRESSURE RELATIONSHIP TO ADJACENT SPACES.
KEYED NOTES
1 6" STEAM VENT, 4" HWS, 4" HWR, LPS, 1" LPR, 4" CWS, AND 4" CWR PIPING DOWN TO GROUND FLOOR. REFER TO SHEET M100 FOR CONTINUATION. VERIFY LOCATIONS THRU EXISTING FLOOR SLAB WITH EXISTING STRUCTURE.
2 4" HWS, 4" HWR, LPS, 4" CWS, AND 4" CWR PIPING UP TO SECOND FLOOR. REFER TO SHEET M400 FOR CONTINUATION.
3 PROTECT EXISTING BRANCH PIPING AND PIPE ACCESSORIES SERVING EXISTING CABINET UNIT HEATER DURING INSTALLATION OF NEW WALL.
4 INSTALL WALL MOUNTED NEGATIVE PRESSURE MONITOR DIGITAL INTERFACE MODULE ON CORRIDOR WALL PER MANUFACTURERS INSTALLATION INSTRUCTIONS. PROVIDE LABEL FOR ROOM SERVED. COORDINATE LETTERING STYLE WITH OWNERS REPRESENTATIVE. ROOM PRESSURE CONTROLLER SHALL BE TRIA-TEK MODEL FMS-1655 OR APPROVED EQUAL. PRESSURE MONITOR SHALL BE BACNET MS / TP COMPATIBLE WITH ACCURACY ± 0.5% FULL SCALE.
5 INSTALL ROOM PRESSURE SENSOR FLOW TUBE AND COVER PLATES ABOVE DOOR PER MANUFACTURERS INSTALLATION INSTRUCTIONS. SEAL AROUND ALL WALL PENETRATIONS WITH GASKET AND CAULK.
6 CONNECT TO EXISTING 2" FUEL OIL TANK VENT PIPE BELOW GRADE AND ROUTE UP IN WALL AS SHOWN. OFFSET ABOVE CEILING AND ROUTE UP TO SECOND FLOOR. VERIFY EXISTING PIPE SIZE IN FIELD. REFER TO SHEET M400 FOR CONTINUATION.
7 1" LPR UP TO SECOND FLOOR. REFER TO SHEET M400 FOR CONTINUATION.
8 REMOVE TEMPORARY CAPS AND EXTEND EXISTING HEATING HOT WATER PIPING AS SHOWN.
#
12"x4" EA(X)
8"x6" EA
8 "x
8 "x
10
SD
11
SD
12
SD
13
20
20
NOTE: CEILINGS IN PATIENT AREAS CONSIST OF A SECURED METAL CEILING TILE AND GRID SYSTEM. THE GRID SYSTEM IS SUPPORTED FROM STRUTS PLACED AT EACH TEE-INTERSECTION. SYSTEMS ROUTING ABOVE-CEILINGS MUST BE COORDINATED TO AVOID INTERSECTING WITH METAL CEILING GRID SUPPORTS. COMPONENTS REQUIRED TO MOUNT WITHIN THE SECURED CEILING GRID (E.G. LUMINAIRES, DIFFUSERS, ETC.) MUST BE SECURED TO PROVIDE A TAMPER-PROOF AND ANTI-LIGATURE INSTALLATION, ENSURING DISPLACEMENT OF DEVICES CANNOT BE ACHIEVED FROM BELOW CEILING. COMPONENTS REQUIRING PENETRATION OF METAL CEILING TILES FOR FUNCTIONALITY (E.G. SPRINKLER HEADS) OR MOUNTING WITHIN BACKBOXES SUCH THAT THE DEVICE IS FLUSH WITH THE UNDERSIDE OF THE CEILING TILE (E.G. FIRE ALARM DEVICES, TELECOMMUNICATION DEVICES, ETC.) WILL REQUIRE FIELD-CUTTING OF METAL CEILING TILE. COORDINATE FIELD-CUTTING REQUIREMENTS WITH GENERAL CONTRACTOR. REFER TO ARCHITECTURAL REFLECTED CEILING PLAN FOR LOCATION OF NEW METAL CEILING TILE AND GRID SYSTEM. VERIFY ALL REQUIREMENTS WITH MANUFACTURER OF ACTUAL CEILING SYSTEM PROVIDED.
1
2
REFER TO SHEET M000 FOR GENERAL NOTES.
REFER TO AIR TERMINAL UNIT SCHEDULE ON SHEET M600 FOR AIR INLET SIZE TO AIR TERMINAL UNITS.
GENERAL NOTES:
NOTE: ACCESS TO VAV BOXES AND VOLUME DAMPERS TO BE MADE AVAILABLE THRU METAL CEILING BY METAL ACCESS PANELS PROVIDE BY THE ARCHITECT. REFER TO SHEET A203 RCP FOR ACCESS PANEL LOCATION. COORDINATE ACCESS PANELS WITH VAV BOXES AND VOLUME DAMPERS SO THAT MINIMAL REACH IS REQUIRED FOR ACCESSIBILITY.
NEW AIR HANDLING UNIT SYSTEM (AHU-23/RF-23) SHALL NOT BE USED TO CONDITION THE THIRD FLOOR DURING CONSTRUCTION.
Pr o
je c
t Ti
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
KEYED NOTES
1 16"x16" EXHAUST DUCT UP THRU ROOF TO EXHAUST FANS EF-53A AND EF-53B. REFER TO SHEET M120 FOR CONTINUATION.
2 9"Ø EXHAUST DUCT (EF-53A, EF-53B) DOWN TO SECOND FLOOR. REFER TO SHEET M400 FOR CONTINUATION.
3 34"x14" EXHAUST DUCT (EF-24) DOWN TO SECOND FLOOR. REFER TO SHEET M102 FOR CONTINUATION.
4 CONNECT NEW 34"x14 EXHAUST DUCT (EF-24) TO EXISTING EXHAUST RISER BELOW FOURTH FLOOR SLAB.
5 34"x12" EXHAUST DUCT (EF-18) DOWN TO SECOND FLOOR. REFER TO SHEET M102 FOR CONTINUATION.
6 CONNECT NEW 32"x12" EXHAUST DUCT (EF-18) TO EXISTING EXHAUST DUCT BELOW FOURTH FLOOR SLAB.
7 20"x18" EXHAUST DUCT UP. TRANSITION FROM 20"x18" TO 18"x18" THRU ROOF TO EF-51.
8 36"x36" RELIEF AIR DUCT UP THRU ROOF TO GRAVITY RELIEF HOOD AND 36"x36' DOWN TO SECOND FLOOR. REFER TO SHEET M120 AND M400 FOR CONTINUATION.
9 12"x6" EXHAUST DUCT DOWN IN WALL TO LOW WALL EXHAUST GRILLE. BOTTOM OF GRILLE 8" A.F.F.
10 INSTALL FAN COIL UNIT AS HIGH AS POSSIBLE WITH MASON TYPE PC30N SPRING ISOLATORS WITH 1" DEFLECTION.
11 REBALANCE EXISTING AIR DEVICE TO CFM NOTED ON PLAN.
12 REBALANCE EXISTING DDC AIR TERMINAL UNIT FOR 955 CFM MINIMUM AND MAXIMUM CFM.
13 40"x24" SUPPLY DUCT DOWN TO SECOND FLOOR. REFER TO SHEET M400 FOR CONTINUATION. ROTATE IN VERTICAL ABOVE THIRD FLOOR SLAB AS SHOWN.
14 34"x24" RETURN DUCT DOWN TO SECOND FLOOR. REFER TO SHEET M400 FOR CONTINUATION.
15 SLOPE SUPPLY DUCT DOWN UNDER EXISTING BEAM AT EXTERIOR WALL. HOLD TIGHT TO BEAM AND RISE UP ON OTHER SIDE.
16 EXISTING 30"x12" SA DUCT UP (AHU-S7-4).
17 16"x8" EXHAUST DUCT DOWN TO SECOND FLOOR . OFFSET ABOVE THIRD FLOOR CEILING AS SHOWN AND EXTEND UP THRU ROOF TO EXHAUST FAN EF-52. REFER TO SHEETS M102 AND M120 FOR CONTINUATION.
18 LOCATION OF DUCT STATIC PRESSURE SENSOR FOR CONTROL OF AHU-23 SUPPLY FAN VARIABLE FREQUENCY DRIVES. REFER TO SEQUENCE OF OPERATION ON SHEET M700. ADDITIONAL DUCT PRESSURE SENSOR LOCATED ON FIRST FLOOR. REFER TO SHEET M101 FOR LOCATION.
19 12"Ø EXHAUST DUCT (EF-51) DOWN TO SECOND FLOOR. REFER TO SHEET M400 FOR CONTINUATION.
#
5
EXISTING 1 1/2" HWS AND HWR RISERS UP TO FOURTH FLOOR (14.0 GPM)
1 1/2"
REFER TO SHEET M000 FOR GENERAL NOTES.
HEATING HOT WATER RUN OUT SIZES TO AIR TERMINAL UNIT REHEAT COILS SHALL BE 3/4" UNLESS NOTED OTHERWISE.
TOP OF ALL THERMOSTAT DEVICES & CARBON DIOXIDE SENSORS TO BE 48" A.F.F.
INSTALL NEW WALL MOUNTED TEMPERATURE AND HUMIDITY SENSORS 48" A.F.F. TO TOP OF DEVICE.
GENERAL NOTES:
Pr o
je c
t Ti
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
NEW WORK
U n
iv e
rs ity
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
KEYED NOTES
1 2" HWS AND 2" HWR DOWN TO SECOND FLOOR. REFER TO SHEET M102 FOR CONTINUATION.
2 1" PNEUMATIC CONTROL LINE, 6" CWS, AND 6" CWR DOWN TO SECOND FLOOR. REFER TO SHEET M102 FOR CONTINUATION.
3 CONNECT NEW 1" PNEUMATIC CONTROL LINE, 6" CWS, AND 6" CWR PIPING TO EXISTING RISERS BELOW FOURTH FLOOR SLAB. PROVIDE PROPER VAPOR BARRIER WHERE NEW INSULATION ABUTS EXISTING INSULATION ON CHILLED WATER PIPING.
4 REBALANCE EXISTING VAV FOR 4 GPM.
5 INSTALL NEW VALVES AND AS MUCH PIPING AS POSSIBLE PRIOR TO DISCONNECTING EXISTING FOURTH FLOOR RISERS FROM EXISTING HEATING HOT WATER SYSTEM IN EXISTING NORTH MECHANICAL ROOM TO MINIMIZE SHUT-DOWN TIME. REFER TO KEYED NOTE 4 ON SHEET MD103A. COORDINATE FOURTH FLOOR SHUT-DOWN WITH OWNER'S REPRESENTATIVE.
6 INSTALL WALL MOUNTED NEGATIVE PRESSURE MONITOR DIGITAL INTERFACE MODULE ON CORRIDOR WALL PER MANUFACTURERS INSTALLATION INSTRUCTIONS. PROVIDE LABEL FOR ROOM SERVED. COORDINATE LETTERING STYLE WTTH OWNERS REPRESENTATIVE. ROOM PRESSURE CONTROLLER SHALL BE TRIA-TEK MODEL FMS-1655 OR APPROVED EQUAL. PRESSURE MONITOR SHALL BE BACNET MS / TP COMPATIBLE WITH ACCURACY ± 0.5% FULL SCALE.
7 INSTALL ROOM PRESSURE SENSOR FLOW TUBE AND COVER PLATES ABOVE DOOR PER MANUFACTURERS INSTALLATION INSTRUCTIONS. SEAL AROUND ALL WALL PENETRATIONS WITH GASKET AND CAULK.
8 2" FUEL OIL TANK VENT DOWN TO SECOND FLOOR AND UP THRU ROOF. REFER TO SHEET M400 AND M120 FOR CONTINUATION.
9 LOCATION OF HEATING HOT WATER SYSTEM DIFFERENTIAL PRESSURE SENSOR FOR CONTROL OF HEATING HOT WATER PUMPS HWP-10 AND HWP-11 VARIABLE FREQUENCY DRIVE. REFER TO DETAIL 4 ON SHEET M500 AND 4 ON SHEET M703.
10 CONTRACTOR SHALL FABRICATE A STAINLESS STEEL DRIP PAN WITH ROLLED EDGES ( NO EXPOSED CUT EDGES) FOR INSTALLATION UNDER FAN COIL UNIT. SUSPEND FROM STRUCTURE ABOVE. PAN SHALL BE 3" TALL AND A MINIMUM OF 4 INCHES BEYOND OUTLINE OF UNIT. INSTALL AN EARLY WARNING WATER LEAK DETECTION SYSTEM IN DRIP PAN. PROVIDE SENSOR CABLE IN PAN AND ROUTE CONTROL SIGNAL BACK TO NEAREST EMCS PANEL AND ALARM AT EMCS. INSTALL CONDENSATE PUMP IN DRIP PAN. REFER TO FAN COIL UNIT SCHEDULE ON SHEET M600 FOR CONDENSATE PUMP SPEC.
11 CONNECT NEW CHILLED WATER BRANCH PIPING TO EXISTING BRANCH PIPING AT CORRIDOR WALL. PROVIDE PROPER VAPOR BARRIER WHEN NEW PIPE INSULATION BUTTS AGAINST EXISTING INSULATION.
12 CALIBRATED BALANCING VALVE. BALANCE FOR 1 GPM.
#
HEAT EXCHANGERHEAT EXCHANGER
AIR / DIRT SEPARATOR
1"
4"
4"
4"
1 1/4"
CONNECT TO EXISTING MAKE-UP WATER PIPING IN PSYCH BUILDING MECHANICAL ROOM
HEATING HOT WATER PUMP ISOLATION VALVE HWP-10
HEATING HOT WATER PUMP ISOLATION VALVE HWP-11
REFER TO SHEET M101A
REFER TO SHEET M400
GENERAL NOTES:
CWR
CWS
M4"
CWR
CWS
B & G MODEL 1510, 6 G 1100 GPM @ 48' HD, 25 HP, 1200 RPM
CWS
EXISTING PLATE FRAME HEAT EXCHANGER
B & G MODEL VSX-VSH 10 6x8x10.5B, 1032 GPM @ 95' HD, 40 HP, 1800 RPM
BASEMENT PSYCH BUILDING
3"
4"
4"
6
M500
4"
5
M501
5
M501
Pr o
je c
t Ti
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
NTS 2
KEYED NOTES
1 HEATING HOTWATER SYSTEM DIFFERENTIAL PRESSURE SENSOR FOR CONTROL OF HEATING HOT WATER PUMPS HWP-10 AND HWP-11 VARIABLE FREQUENCY DRIVES. REFER TO M101A AND M103A FOR LOCATIONS.
2 CHILLED WATER SYSTEM DIFFERENTIAL PRESSURE SENSOR FOR CONTROL OF CHILLED WATER PUMPS CWP-10 AND CWP-11 VARIABLE FREQUENCY DRIVES.
4 ADDENDUM 4 04-24-2017
19'-0"w. x 5'-0"h. x 24"d. OUTSIDE AIR PLENUM
MD
2
MD
3
16
15
FSD
2
2"2"
15
20"x14"
T
UH-2
21
SD
7
" C
D
CO
CO
COORDINATE FAN COIL UNIT PIPE ROUTING WITH ELECTRICAL PANELS. REFER TO E-SERIES SHEETS.
C D
GENERAL NOTES:
Pr o
je c
t Ti
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
KEYED NOTES
1 36"x36" RELIEF DUCT UP TO THIRD FLOOR. REFER TO SHEET M103 FOR CONTINUATION.
2 9"Ø ISOLATION EXHAUST DUCT (EF-53A, EF-53B) UP TO THIRD FLOOR WITH COMBINATION FIRE / SMOKE DAMPER IN THIRD FLOOR SLAB. REFER TO SHEET M103 FOR CONTINUATION.
3 40"x24" SUPPLY AIR DUCT (AHU-23) UP TO THIRD FLOOR & 40"x24" DOWN TO FIRST FLOOR. REFER TO SHEET M101 AND M103 FOR CONTINUATION.
4 34"x24" RETURN AIR DUCT (RF-23) UP TO THIRD FLOOR & 34"x20" DOWN TO FIRST FLOOR. REFER TO SHEET M101 AND M103 FOR CONTINUATION. PROVIDE 45 DEGREE SHOE TAPS AT CONNECTION POINTS TO 40"x34" RETURN MAIN.
5 16"x8" EXHAUST AIR DUCT UP TO THIRD FLOOR. REFER TO SHEET M103 FOR CONTINUATION.
6 CONNECT TO EXISTING 16"x8" EXHAUST AIR DUCT ABOVE EXISTING LAB CEILING AND EXTEND AS SHOWN. VERIFY EXISTING DUCT SIZE IN FIELD. PROVIDE DUCT TRANSITION AS REQUIRED.
7 9"Ø ISOLATION ROOM EXHAUST DUCT (EF-53A, EF-53B) DOWN TO FIRST FLOOR. REFER TO SHEET M101 FOR CONTINUATION.
8 4" HWS, 4" HWR, 3" LPS, 4" CWS, 4" CWR DOWN TO FIRST FLOOR. REFER TO SHEET M101A FOR CONTINUATION.
9 2" FUEL OIL TANK VENT PIPING DOWN TO FIRST FLOOR. REFER TO SHEET M101A FOR CONTINUATION. OFFSET AS SHOWN AND EXTEND UP TO THIRD FLOOR. REFER TO SHEET M103A FOR CONTINUATION. ROUTE AS HIGH AS POSSIBLE.
10 2" HWS AND HWR UP TO THIRD FLOOR. REFER TO SHEET M103A FOR CONTINUATION.
11 PROVIDE SHUT-OFF VALVE AND BLIND FLANGE FOR FUTURE CONNECTION.
12 PROVIDE END OF MAIN DRIP TRAP AND EXTEND 1" LPR DOWN TO FIRST FLOOR. REFER TO SHEET M101A FOR CONTINUATION.
13 DUCT SIZE NOTED IS BASED ON SCHEDULED AIR HANDLING UNIT. PROVIDE DUCT SIZE BASED ON APPROVED AIR HANDLING UNIT SHOP DRAWING.
14 CONNECT NEW OUTSIDE AIR DUCT TO EXISTING INSIDE EXISTING BUILDING AND EXTEND AS SHOWN. PROVIDE TRANSITION AS REQUIRED. VERIFY EXISTING DUCT SIZE IN FIELD.
15 INSTALL AIRFLOW MEASURING STATION UTILIZING MANUFACTURERS UPSTREAM AND DOWNSTREAM INSTALLATION CRITERIA.
16 20"x14" SUPPLY DUCT (AHU-23) DOWN TO FIRST FLOOR. REFER TO SHEET M101 FOR CONTINUATION.
17 LOCATION OF CHILLED WATER SYSTEM DIFFERENTIAL PRESSURE SENSOR FOR CONTROL OF CHILLED WATER PUMP CWP-10 AND CWP-11 VARIABLE FREQUENCY DRIVES. REFER TO DETAIL 4 ON SHEET M500 AND 5 ON SHEET M703.
18 PROVIDE 24"x24" ACCESS PANEL TO CLEAN AND MONITOR AFS. SEAL AIR TIGHT.
19 PROVIDE 16"x24" ACCESS PANEL TO CLEAN AND MONITOR AFS. SEAL AIR TIGHT.
20 CONTRACTOR SHALL FABRICATE A STAINLESS STEEL DRIP PAN WITH ROLLED EDGES ( NO EXPOSED CUT EDGES) FOR INSTALLATION UNDER FAN COIL UNIT. SUSPEND FROM STRUCTURE ABOVE. PAN SHALL BE 3" TALL AND A MINIMUM OF 4 INCHES BEYOND OUTLINE OF UNIT. INSTALL AN EARLY WARNING WATER LEAK DETECTION SYSTEM IN DRIP PAN. PROVIDE SENSOR CABLE IN PAN AND ROUTE CONTROL SIGNAL BACK TO NEAREST EMCS PANEL AND ALARM AT EMCS. INSTALL CONDENSATE PUMP IN DRIP PAN. REFER TO FAN COIL UNIT SCHEDULE ON SHEET M600 FOR CONDENSATE PUMP SPEC.
21 12"Ø EXHAUST DUCT (EF-51) UP TO THIRD FLOOR AND DOWN TO FIRST FLOOR. REFER TO SHEET M103 AND M101 FOR CONTINUATION.
22 FLOOR DRAIN BY DIVISION 22. REFER TO P-SERIES DRAWINGS.
#
PIPING PROVIDED IN PROJECT
FUTURE CONNECTION.
GENERAL NOTES:
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
FRAMING. BOTTOM OF HEAT EXHANGERS APPROXIMATELY 5'-0"
A.F.F.
2 INSTALL NEW PUMPS ON 4" HIGH HOUSEKEEPING PAD.
3 6" STEAM VENT, 4" CWR, 4" CWS, 1" LPR, 3" LPS, 4" HWR, 4" HWS
UP TO FIRST FLOOR. REFER TO SHEET M101A FOR
CONTINUATION. COORDINATE RISER LOCATIONS WITH EXISTING
CONDUITS AND PIPING.
CAP ALL EXISTING ACTIVE PNEUMATIC TUBING AT MAINS WITH
BRASS COMPRESSION FITTINGS.
SHELVING TO BE REMOVED BY OWNER.
6 EXISTING CONDUIT TO REMAIN.
7 EXISTING ELECTRICAL PANELS, AUTOMATIC TRANSFER SWITCH,
ETC. TO REMAIN.
8 CONNECT NEW 1 1/2" PC TO EXISTING LPR MAIN AT EXISTING
CONDENSATE PUMP.
EXISTING BACKFLOW PREVENTOR AND EXTEND TO NEW
HEATING HOT WATER SYSTEM. REFER TO DETAIL 3 ON SHEET
M501.
POINT SHOWN AND CAP.
11 REMOVE PORTION OF EXISTING 3" HPR AS SHOWN. REFER TO
PLAN 1 ON THIS SHEET FOR NEW WORK.
#
2 ENLARGED MECHANICAL ROOM PC0016 - DEMOLITION
3
3
3
3
3
3
Lee's Summit, MO 64086
bcdg Project #: MU Project #:
BOB D. CAMPBELL & COMPANY
CROCKETT ENGINEERING
Missouri Certificate of Authority #000148
Missouri Certificate of Authority #000442
Missouri Certificate of Authority ####
MARK NUMBER MANUFACTURER MODEL TYPE
INLET DUCT
CFM PRIMARY MIN
(NOTE 1)
OUTLET DUCT SIZE WxH (IN) AUXILIARY HOT WATER HEATNG COIL MAX NC LEVEL @ MAX CFM
NOTESWIDTH HEIGHT HEATING MAXIMUM
AIRFLOW (CFM) CAPACITY
(MBH) EAT (°F) LAT (°F) EWT (°F) FLOW (GPM) MAX WPD
(FT HD) MAX APD (IN WC) DISCHARGE RADIATED
EAB 1-104 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 6" 1ST FLOOR 320 CFM 320 CFM 1.0 0.30 12" 8" 0 0 - - - 0.00 GPM - - 30 30 4
EAB 1-108 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 5" 1ST FLOOR 220 CFM 220 CFM 1.0 0.30 12" 8" 0 0 - - - 0.00 GPM - - 30 30 4
EAB 1-118 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 6" 1ST FLOOR 310 CFM 310 CFM 1.0 0.30 12" 8" 0 0 - - - 0.00 GPM - - 30 30 4
EAB 23-109 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 6" 1ST FLOOR 350 CFM 350 CFM 1.0 0.30 12" 8" 0 0 - - - 0.00 GPM - - 30 30 4
EAB 23-338 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 7" 3RD FLOOR 540 CFM 540 CFM 1.0 0.30 12" 10" 0 0 - - - 0.00 GPM - - 30 30 4
VAV 1-100 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 7" 1ST FLOOR 390 CFM 390 CFM 1.0 0.75 12" 10" 390 13.5 55 87 180 0.70 GPM 2.0 0.25 30 30 2,3,5
VAV 1-101 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 9" 1ST FLOOR 680 CFM 680 CFM 1.0 0.75 14" 12 1/2" 680 23.5 55 87 180 1.20 GPM 2.0 0.25 30 30 2,3
VAV 1-102 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 7" 1ST FLOOR 445 CFM 445 CFM 1.0 0.75 12" 10" 445 15.4 55 87 180 0.80 GPM 2.0 0.25 30 30 2,3,5
VAV 1-103 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 6" 1ST FLOOR 260 CFM 260 CFM 1.0 0.75 12" 8" 260 9 55 87 180 0.50 GPM 2.0 0.25 30 30 2,3,5
VAV 1-104 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 7" 1ST FLOOR 380 CFM 380 CFM 1.0 0.75 12" 10" 380 13.1 55 87 180 0.70 GPM 2.0 0.25 30 30 2,3,5
VAV 1-105 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 9" 1ST FLOOR 560 CFM 560 CFM 1.0 0.75 14" 12 1/2" 560 19.4 55 87 180 1.00 GPM 2.0 0.25 30 30 2,3
VAV 1-106 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 4" 1ST FLOOR 150 CFM 150 CFM 1.0 0.75 12" 8" 150 5.2 55 87 180 0.50 GPM 2.0 0.25 30 30 2,3
VAV 1-107 TITUS DESV SINGLE DUCT PRESSURE INDEPENDENT 4" 1ST FLOOR 120 CFM 120 CFM 1.0 0.75 12" 8" 120 4.1 55 87 180 0.50 GPM 2.0 0.25 30 30 2,3