Operation planning
(L5)
-
7/31/2019 TNB Operation 20Planning
2/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
2
A power system
-
7/31/2019 TNB Operation 20Planning
3/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
3
TNB power system
PG (Singapore)
EGAT (Thailand)
TNB (P. Malaysia)
-
7/31/2019 TNB Operation 20Planning
4/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
4
TNB power system
Transmission Voltage 500kV
275kV
132kV 66kV
Generation Total 18,323MW
(installed)
TNB 10,836MW (59%)
IPP 7,487MW (41%)
Demand 12,990MW (08/06)
12,724MW (11/06)
-
7/31/2019 TNB Operation 20Planning
5/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
5
TNB power system
=
-
7/31/2019 TNB Operation 20Planning
6/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
6
Who is who in the industry (in Pen. Malaysia)
-
7/31/2019 TNB Operation 20Planning
7/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
7
Interconnectivity of systems (in Pen. Malaysia)
-
7/31/2019 TNB Operation 20Planning
8/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
8
Grid codes & licence standards
-
7/31/2019 TNB Operation 20Planning
9/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
9
Building operation reliability & robustness TNB case
-
7/31/2019 TNB Operation 20Planning
10/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
10
1. TNB License (reflected in the Transm issionSystem Reliability & Pow er Quality
Standards)2. The Malaysian Grid Codes
3. TNBs contractual obligations
4. Operation based on the least cost
5. TNBs business objectives
Governing principles for operation TNB case
-
7/31/2019 TNB Operation 20Planning
11/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
11
Governing principles (continued)
1. TNB License;granted underthe ElectricitySupply Act
1990
The Licensee shall operate &m aintain its transm ission and the
connected generators, in
accordance w ith the license
standards (i.e. Condition no.13)
2. Transmission
SystemReliabilityStandards
(TSRS)
Generation security standards
Operation under no contingency
Operation under secured contingency
Operation under m ultiple
contingency
Operation under unsecured
contingency
-
7/31/2019 TNB Operation 20Planning
12/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
12
Governing principles (continued)
3. TransmissionSystem PowerQualityStandards
(TSPQS)
Voltage sag Voltage step change
Voltage fluctuations & flicker
Harm onics
Phase unbalance & traction load
Step change of pow er
-
7/31/2019 TNB Operation 20Planning
13/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
13
Governing principles (continued)
4. MalaysianGrid Codes
Planned outages (generator units &transmission)
Assignm ent of spinning reserve
Day ahead unit com m itm ent andgeneration schedules
W eekly operation plan
Annual operation plan Monitoring & testing
Planning data
Num bering of equipm ent in the gridsystem
-
7/31/2019 TNB Operation 20Planning
14/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
14
Governing principles (continued)
5. PowerPurchaseAgreements(PPAs)
13 PPAs betw een TNB & IPPs(currently in operation)
6. OtherAgreements
TNB-EGAT:
System Interconnection Agreement(2202)
Supplementary Agreement (2004)
7. TNB
requirements
TNB Process Standardisation &
Im provem en t Procedures (ISO) Risk Managem ent
Governance on disclosure of internal
information
-
7/31/2019 TNB Operation 20Planning
15/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
15
1. Matching generation (output) with the forecastdemand together with generation reserves
2. Taking into account, outages of generation andtransmission system
3. Complying the grid codes and the license
standards4. Meeting contractual obligations
5. Meeting least cost operation
6. Carrying out OP during operational timescale
Operation planning (OP) tasks
-
7/31/2019 TNB Operation 20Planning
16/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
16
Operation planning timescales
1. One day ahead (daily ; 24 hours; hour 0 0:00hour to hour 24:00 )
2. One week ahead (w eekly Friday to Thursday )
3. One month ahead (monthly)
4. One year ahead (yearly ; 1 Septem ber to 31
August)5. 2 years ahead (yearly)
6. 5 years ahead (yearly)
-
7/31/2019 TNB Operation 20Planning
17/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
17
Operation planning - activities
Daily Processes Monthly/ Weekly Processes Yearly Processes
1. Planning-System Operationcoordination (docket meeting)
2. Management of generator unitsavailability
3. Scheduling energy import/exportexchange
4. Scheduling generator unitplanned outages
5. Scheduling transmission plannedoutages
6. Scheduling of commissioning(transmission)
7. Scheduling of system tests (if any)8. Scheduling of unit commitment
and generation schedule
9. Assessment of system security
1. Scheduling of generator unitplanned outages
2. Scheduling of transmissionplanned outages
3. Scheduling of unit commitmentand generation schedule
4. Scheduling of gas nomination5. Transient security assessment
(WTSA)
6. Plan coordination (OPP-NLDCmeeting)
7. Fault level & system security
analysis8. Reports to regulators &
government.
1. Two Year SystemOperation Plan(Transmission)
2. Five Year SystemOperation Plan(Production)
3. Generation Mixreport
4. Generation Security Standard Report
5. OperationCoordination (Joint
OperationCommittees)
6. Grid SystemPerformanceReport
As & when required1. Updating planning data (on the grid system and on the fuel price variation)
2. Managing fuel supply variation (including gas curtailment).
3. Validating availability of stand-by fuel
4. Submission of data/reports to Regulators, Government and TNB authorities
5. Power Quality Monitoring & Measurement
-
7/31/2019 TNB Operation 20Planning
18/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
18
Operation planning an overview(as documented in TNB ISO m anual)
-
7/31/2019 TNB Operation 20Planning
19/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
19
Operation Planning (OP) planning cycles
Monthly/weekly OP
Daily OP
Real-timeOperation
OPP (System Planning) department
NLDC department
Annual OP
-
7/31/2019 TNB Operation 20Planning
20/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
20
Operation Planning (OP) yearly cycles
Monthly/weekly OP
Daily OP
Real-timeOperation
OPP (System Planning) department
NLDC department
Annual OP
1. Two Year System Operation Plan (Transmission)
2. Five Year System Operation Plan (Production)
3. Generation Mix report4. Generation Security Standard Report
5. Operation Coordination (Joint OperationCommittees)
6. Grid System Performance Report
Annual OP
-
7/31/2019 TNB Operation 20Planning
21/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
21
Operation Planning (OP) monthly/weekly cycles
Monthly/weekly OP
Daily OP
Real-timeOperation
OPP (System Planning) department
NLDC department
Annual OP
1. Scheduling of generator unit planned outages2. Scheduling of transmission planned outages
3. Scheduling of unit commitment andgeneration schedule
4. Scheduling of gas nomination5. Transient security assessment (WTSA)
6. Plan coordination (OPP-NLDC meeting)
7. Fault level & system security analysis
8. Reports to the government, regulators & TNB.
Annual OP
-
7/31/2019 TNB Operation 20Planning
22/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
22
Operation Planning (OP) daily cycles
Monthly/weekly OP
Daily OP
Real-timeOperation
OPP (System Planning) department
NLDC department
Annual OP
1. Planning-System Operation coordination(docket meeting)
2. Management of generator units availability3. Scheduling energy import/export exchange4. Scheduling generator unit planned outages5. Scheduling transmission planned outages
6. Scheduling of commissioning (transmission)7. Scheduling of system tests (if any)8. Scheduling of unit commitment and generation
schedule
9. Assessment of system security
Annual OP
-
7/31/2019 TNB Operation 20Planning
23/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
23
Five Year System Operation Plan (FYOP)
FYOP addresses operation plan up to 5 years ahead,focusing on adequacy of generation capacity andproduction cost.
FYOP report highlights:
Demand forecast & growth Generation capacity and operating margins Generation mix
Operation cost Possible mitigative measures: -
Adjusting outage (maintenance) schedule Addressing stand-by fuel & stock
Uses software tools: PMonth (production schedule & cost optimisation)
Ref: W ork Instruction Level 3 no. TNBT-SPOD-750 -01-OPP-W I-09
-
7/31/2019 TNB Operation 20Planning
24/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
24
Generation Mix report (Genmix)
Genmix report addresses forecast generation for the(one) year ahead, mainly as input for preparingfinancial budget for:
Operation of TNBs Power Stations and Energy payment to IPPs
Genmix report highlights (for one year ahead): Forecast of generation production.
Forecast of generation mix by fuel type.
Uses software tools: PMonth (production schedule & cost optimisation)
Ref: W ork Instruction Level 3 no. TNBT-SPOD-750 -01-OPP-W I-11
i i d d ( )
-
7/31/2019 TNB Operation 20Planning
25/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
25
Generation Security Standard report (GSS)
Generation Security Standard (GSS) report addressesthe system generation capability to meet theforecast load and energy demand for up to 5 years
ahead.GSS report highlights: Demand forecast Generation capacity and operating margins
Uses software tools: PMonth (production schedule & cost optimisation)
Ref: W ork Instruction Level 3 no. TNBT-SPOD-750 -01-OPP-W I-10
i h d li
-
7/31/2019 TNB Operation 20Planning
26/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
26
Generator units outage scheduling
The objective is to satisfy request (by IPP/TNB powerplants) for planned outages for generator units (forscheduled, maintenance, repair, etc) yet to ensure:
The grid system is secured and reliable Generation reserve margin is adequate Cost of production is maintained at optimum level Availability of gas supply is within limits (declared by Petronas)
Hydro lake level (Kenyir and Temengor) are within targetsScheduling process:
Rolling five year outage plan (maintained in a database)
Revised annually, quarterly (for TNB plants) Finalised and confirmed weekly
Ref: W ork Instruction Level 3 no. TNBT-SPOD-750 -01-OPP-W I-06
-
7/31/2019 TNB Operation 20Planning
27/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
27
Weekly generation and unit commitment schedules
The objectives are: To plan for generator unit start/stop schedule To estimate quantum of gas supply requirement To plan for hydro lake level (based on the current level)
The plan is at the optimum cost (for the given demandforecast & planned outage schedule).
Scheduling process: Review availability of unit & capacity of generator units Review availability of gas supply (in mmscfd volume) Develop generation schedule based on the demand forecast
Uses software tools:
PCOM (production schedule & cost optimisation)
Ref: W ork Instruction Level 3 no. TNBT-SPOD-750 -01-OPP-W I-07
h d d h d l
-
7/31/2019 TNB Operation 20Planning
28/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
28
Day ahead generation and unit commitment schedules
The objectives are: To confirm power exchange between TNB & EGAT To develop the plan for committing generator units and their output
on a half-hourly basis for 24 hours operation during the next day[See *] from hour 00:00 to hour 24:00.
To work-out that the plan meets the forecast demand with adequatespinning reserve throughout the day
The plan is at the optimum cost.
Scheduling process: Review availability of unit & capacity of generator units Review availability of gas supply (in mmscfd volume) Develop generation schedule based on the demand forecast
Uses software tools: PCOM (production schedule & cost optimisation)
* W eekend/ holidays are given special exception
Ref: W ork Inst ruction Level 3 no. TNBT-SPOD-750 -0 1-OPP-W I-0 3
T Y S O i Pl (TYSOP)
-
7/31/2019 TNB Operation 20Planning
29/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
29
Two Year System Operation Plan (TYSOP)
TYSOP addresses operation plan two years ahead, focusing on
adequacy of transmission and stability of the grid system.TYSOP report highlights:
Operational issues in specific Regions (Northern, Eastern,Central and Southern)
Operational issues of interconnection with Singapore and withThailand
Impacts of new generation plant coming on-line
Possible mitigative measures, taking into account: - Committed transmission & generation development plan Possible transmission options Defence plan
Uses software tools: PSS/E (power flow, OPF, fault level, and transient stability) DSA Power Tools (transfer limit, voltage and transient security).
Ref: W ork Instruction Level 3 no. TNBT-SPOD-750 -01-OPP-W I-12
T i i
-
7/31/2019 TNB Operation 20Planning
30/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
30
Transmission outage management
The objective is to satisfy request for planned outages for
transmission apparatus (for scheduled maintenance, repair,construction, etc) yet to ensure:
The grid system is secured and reliable Cost of production is maintained at optimum level The above are confirmed through studies
Scheduling process: Maintain details of planned outages (in a database)
Coordinate with planned outages of generator units Revised monthly, confirmed one week up to 10 days ahead Revised and re-confirmed 1 day ahead Highlight controls (if necessary to maintain system security)
Uses software tools: WOMS (Web-based Outage Management System) PSS/E (for conducting studies of individual outage cases)
Ref: W ork Inst ruction Level 3 no. TNBT-SPOD-750 -0 1-OPP-W I-0 5
C di i f i i i * f i i
-
7/31/2019 TNB Operation 20Planning
31/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
31
Coordination of commissioning* of transmission
The objective is to satisfy request for commissioning of
transmission apparatus (for new equipment) yet to ensure: The new apparatus meet the general requirement for safe and
correct operation, in terms of connectivity & labeling Impact to the transmission network is minimum (even if the
commissioning is unsuccessful)Coordination process:
Prepare equipment drawings (3 months ahead) Assign numbering of equipment (in the drawing) Prepare commissioning memorandum & submit to NLDC for
implementation (7 days ahead minimum) Prepare switching program (in the commissioning memo)
* Com m issioning refers to energising transm ission equipm ent for the 1st time
Ref: W ork Instruction Level 3 no. TNBT-SPOD-750 -0 1-OPP-W I-16
E l f thl t i i t l
-
7/31/2019 TNB Operation 20Planning
32/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
32
Example of a monthly transmission outage plan
E l f ti l d i t
-
7/31/2019 TNB Operation 20Planning
33/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
33
Example of a contingency plan during outage
E l f ti l d i t
-
7/31/2019 TNB Operation 20Planning
34/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
34
Example of a contingency plan during outage
E l f ti l d i t
-
7/31/2019 TNB Operation 20Planning
35/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
35
Example of a contingency plan during outage
E l f ti l d i t
-
7/31/2019 TNB Operation 20Planning
36/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
36
Example of a contingency plan during outage
E ample of a commissioning memo (1)
-
7/31/2019 TNB Operation 20Planning
37/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
37
Example of a commissioning memo (1)
Example of a commissioning memo (2)
-
7/31/2019 TNB Operation 20Planning
38/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
38
Example of a commissioning memo (2)
Example of a commissioning memo (3)
-
7/31/2019 TNB Operation 20Planning
39/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
39
Example of a commissioning memo (3)
Example of a commissioning memo (4)
-
7/31/2019 TNB Operation 20Planning
40/41
Asean Residential School in ElectricalEngineering (ARSEPEO6), 9 January 2007,Universiti Tenaga Nasional
40
Example of a commissioning memo (4)
Example of a commissioning memo (5)
-
7/31/2019 TNB Operation 20Planning
41/41
Asean Residential School in ElectricalEngineering (ARSEPEO6) 9 Jan ar 2007
41
Example of a commissioning memo (5)