TLMS-CEPSI2010
-
Upload
andrew-yang -
Category
Documents
-
view
215 -
download
0
Transcript of TLMS-CEPSI2010
-
8/7/2019 TLMS-CEPSI2010
1/6
Improvement of DT Load Estimation by Using
Typical Load ProfilesAndrew Charles D. Yang
1, Ronoel M. Dellota
2
Networks, Manila Electric Company
Pasig City, [email protected]
Abstract This paper proposes a new methodology for singledistribution transformer (DT) load estimation using typicalcustomer load curves. The process described in this paper is an
improvement over regression-based formulas to properlyestimate DT loads. The results of the methodology are compared
and verified to the output of LP-capable meters installed at DTs.
Keywords distribution, transformer, meter, DT, TLMS, loadprofile
I. INTRODUCTION
Transformer load monitoring is an important aspect ofelectric distribution utility operation. An accurate and reliableload monitoring system enables system planners and operatorsto determine transformers that are overloaded, normally
loaded, under-loaded and idle.
If properly identified, overloaded transformers can be
readily scheduled for replacement. Hence, DT failures due to
overloading can be prevented. Under-loaded transformers can
be removed and replaced with the proper rating, therebymaximizing asset utilization. Idle transformers can be
removed and used as new stocks, thereby, saving purchasecosts for new transformers.
There are different methods of Transformer Loadmonitoring. The most accurate method to monitor the load of
transformers is to install indicating demand (ID) meters thatregister the kW or KVA demand. Because of the number
distribution transformers (DT) installed in the field, this is notpractical due to the significant investment required. However,
installation of ID meters can be justified in areas with high
incidence of DT failures due to overload.
Other methodologies of transformer load monitoring deal
with load estimation techniques. One particular method is byusing an empirical formula based on regression to estimate the
DT KVA loading given only the kWh consumption ofconnected customers. This formula categorizes transformers
into three groups: residential, mixed residential andcommercial. From this categorization, constants are obtained
for use with the formula. Currently, our experience with a
regression based DT load estimation methodology has shown
that the results are only 64% accurate. This necessitatesfurther load testing on-site to verify overloaded transformers,
which costs time and additional operational expense. Hence,
there is a need to explore other load estimation methodologiesthat give more accurate results.
In this study, the feasibility of using the typical customerload profiles for transformer load estimation will be explored.
KVA loading will be computed using the aggregate loading of
the connected customers.
II. RELATED WORKS
A load profile is a model of load characteristics representedby parameters such as customer types, day/season and
temperature. The load profile is used in power generation tomonitor and plan their generation schedule. For the
transmission system, load profiles are utilized for forecasting
demand and system planning. Furthermore, the distributionutilities make use of load profiles to enhance the operationefficiency and reliability of their facilities. Load profiles can
also be used for load balancing and customer billing in a
deregulated environment [1].
The importance and scope of the applications of load
profiling lead to numerous researches related to the subject.Most of these studies are targeted to seek out the most
accurate way to model the Typical Load Profile (TLP)
classification. We can categorize the classification techniques
into two. The first method is derived from the shape of theload curves while the second method is derived from a pre-
determined set of consumers. Most of the papers that fallunder the first category introduced a fuzzy clusteringtechnique to group similar load curves ([1], [2]). In [1],
Measured Load Profile (MLP) is classified according to
hierarchical clustering method and fuzzy logic. In [2], a twostage FCM (Fuzzy C-Means) is introduced by grouping
through load pattern and value. The second category wherein[3] and [4] belong retrieves data by sampling theory and
applies statistical analysis to develop the typical load profiles.
The distribution transformer is the most crucial component
of the distribution system, customer wise. It bridges the gapbetween the distribution utility and the consumer by stepping
down the distribution-level voltage to utilization voltage levels
that are required by the customer. Thus, the loading level of
the transformer should always be monitored in order tomaintain its good working condition and to ensure the
-
8/7/2019 TLMS-CEPSI2010
2/6
continuous supply of power to customers. To monitoraccurately, the health and reliability of all distribution
transformers, an ID (Indicating Demand) meters can be used
to record the peak load. However, given the number of
distribution transformers in the field, to put up ID (IndicatingDemand) meters for each is not practical. Non-invasive digitalload loggers, on the other hand, can also be employed to
estimate the loading on the transformer with 800 kWhCons.>800 kWh
401-800 kWh401-800 kWh
301-400 kWh301-400 kWh
201-300 kWh201-300 kWh101-200 kWh101-200 kWh
71-100 kWh71-100 kWh
51-70 kWh51-70 kWh
1-50 kWh
GeneralServices(Commercial)
1-50 kWh
Residential
kWh RangeRate ClasskWh RangeRate Class
Cons.>800 kWhCons.>800 kWh
401-800 kWh401-800 kWh
301-400 kWh301-400 kWh
201-300 kWh201-300 kWh101-200 kWh101-200 kWh
71-100 kWh71-100 kWh
51-70 kWh51-70 kWh
1-50 kWh
GeneralServices(Commercial)
1-50 kWh
Residential
kWh RangeRate ClasskWh RangeRate Class
-
8/7/2019 TLMS-CEPSI2010
3/6
TABLEIIRATECLASSSTRATIFICATION(DEMAND)-INDUSTRIAL
10,000kW2,000 kW
201kW-2,000kW
41kW-200kW
5kW-40kW
LargeCommercial
kW Demand RangeRate Class
For each segment, customers are selected based on a
sample size computation of 90% confidence with a 10%margin of error. These customers have been installed with
load profile (LP) capable meters and their monthly kWhdemand recorded.
We let cnCand nNwhere N is the number of elements in
C. Also, we let h be any number between {1H} where H isequal to 24. The recorded load profile for each customer isnormalized using (1).
)max( 'h
hc
hkW
kWPU n =
(1)
The normalized load profiles of each customer segment are
averaged hourly to obtain a typical load profile to represent
that particular rate class as shown in (2).
N
PU
PU
N
n
c
h
h
n=
=1
(2)
The hourly average of all customers in a particular
customer group is normalized once again using (3) to obtain
the typical load profiles for use with the TLP DT estimationmethodology.
)max( 'h
h
hPU
PU
LP =(3)
A sample typical load profile (normalized) for residentialcustomers with monthly kWh consumption of 301 to 400 kWh
is shown in Fig. 3.
Residential, Cons. = 301 - 401 kWh
0
0.2
0.4
0.6
0.8
1
1.2
1:00
3:00
5:00
7:00
9:00
11:00
13:00
15:00
17:00
19:00
21:00
23:00
Time
PerUnit,P.U.
Fig. 3. Typical Load Profile (Residential, Consumption = 301-
400 kWh)
B. Application of Customer kWh Consumption to the TypicalLoad Profile
The process flow of the TLP methodology is shown in Fig.
4.
Monthly Customer
kWh Consumption
Aggregate DT Load
Profile
Divide by the number of billing
days to obtrain the approximate
Daily kWh Consumption
Apply the Daily k Wh Consumption
to the Typical Load Profile to get
Customer Hourly kW Load Profiles
Hourly kW
Streetlight Load
Profile
Aggregate all Customer Hourly kW
Load Profiles connected to the
transformer, the Streetlight Load
and System Loss
Take the Peak kW Demand from
the Aggregate DT Load Profile and
multiply it with the transformers
power factor
DT Peak KVA = DT
Load Estimate
Monthly Customer
kWh Consumption
Aggregate DT Load
Profile
Divide by the number of billing
days to obtrain the approximate
Daily kWh Consumption
Apply the Daily k Wh Consumption
to the Typical Load Profile to get
Customer Hourly kW Load Profiles
Hourly kW
Streetlight Load
Profile
Aggregate all Customer Hourly kW
Load Profiles connected to the
transformer, the Streetlight Load
and System Loss
Take the Peak kW Demand from
the Aggregate DT Load Profile and
multiply it with the transformers
power factor
DT Peak KVA = DT
Load Estimate
Fig. 4. Typical Load Profile (Residential, Consumption = 301-400 kWh)
The monthly kWh consumption of each customer
connected to a distribution transformer is taken from thecustomer load database. The monthly consumption is divided
by the number of billing days between meter readings to getthe daily kWh consumption, as shown in (4).
-
8/7/2019 TLMS-CEPSI2010
4/6
daysbilling
kWhkWh
monthly
daily= (4)
The approximate load profile, that is, the hourly kW loadper customer for a 24-hour period, is obtained using (5).
=
=H
h
h
hdailyhour
LP
LPxkWhkW
1
(5)
The load profile to be used in the above formula
corresponds to the rate class of the customer, as obtained from(3). Note that the load profile represents a typical day only.
In addition to customer loads, the effect of streetlight loadsand system loss on the total transformer loading must also be
taken into account.
Streetlight loads connected to the transformer, if any, are
assumed to be 70W high pressure sodium (HPS) luminariesfor residential transformers and 250W HPS luminaries for
commercial transformers. Streetlight loads are assumed tooperate between the hours of 1800H to 600H and the total
streetlight load is distributed within this period. Thus the
streetlight consumption is added to the hourly kW load of theDT for the said range. The hourly streetlight load is denotedas STLhour.
The technical loss of the transformer should consider theconsumption of the connected customers and the incident
streetlight load. For the study, a technical loss of 2% is
assumed. Hence, the calculation of the hourly losses isexpressed as in (6):
LossDTxSTLkWLosses hourhourhour )(+=
(6)
The hourly streetlight load and DT losses obtained in (6) areto be used in the TLP load estimation:
C. Aggregation of Demand Profiles and DT Load EstimationThe total hourly kW loading is obtained as the aggregate of
the hourly kW load, the streetlight load, if any and the hourly
kW loss, also known as the Aggregate DT load profile. Thisis also expressed as in (7).
hourhourhourhourLossesSTLkWkWTotal ++= (7)
One may begin to obtain a DT load estimate from theaggregate DT load profile. To do so, the Peak kVA load of
the transformer is computed by converting the max. totalkWhour load to its kVA load equivalent, using (8).
pf
kWTotalPeakkVAPeak
hour= (8)
For (8), a power factor (pf) of 0.85 lag is assumed in the
calculation. As DT load estimates are commonly expressed asa percentage of total transformer capacity, the Peak DT kVAload (%) is taken from (9).
100% XkVADTRated
kVAPeakkVADTPeak = (9)
The Peak kVA value from (8) is analogous to the peak kVA
demand of the transformer, whereas the percentage obtained
in (9) is equivalent to the percent ratio of the peak DT kVA
demand to the rated DT capacity. Hence, this is the resultant
DT load estimate.
IV.RESULTS AND EVALUATION
In developing the typical load profiles, load profile datafrom 1,730 customers installed with LP-capable meters are
collected and analyzed. The gathered data was recorded for a
period of one (1) year from November 2004 to October 2005,and from these, typical load profiles for each rate class have
been developed. Fig. 5, Fig. 6, Fig. 7 and Fig. 8 show thetypical load profiles for the residential, general services
(commercial), large commercial and industrial rate classes
respectively.
Typical Load Profile of Residential Custome rs
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1:00
3:00
5:00
7:00
9:00
11:00
13:00
15:00
17:00
19:00
21:00
23:00
Time
PerUnitP.U.
0-50 kWh
51-70 kWh
71-100 kWh
101-200 kWh
201-300 kWh
301-400 kWh
401-800 kWh
Cons. >800
kWh
Fig. 5. Typical Load Profiles for Residential Customers
Typical Load Profile for General Services (Commercial)
Customers
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1:00
3:00
5:00
7:00
9:00
11:00
13:00
15:00
17:00
19:00
21:00
23:00
Time
PerUnitP.U.
0-50 kWh
51- 70 kWh
71-100 kWh
101-200 kWh
201-300 kWh
301-400 kWh
401-800 kWh
Cons. >800kWh
Fig. 6. Typical Load Profiles for General Services Customers
-
8/7/2019 TLMS-CEPSI2010
5/6
Typical Load Profile of Large Commercial Customers
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1:00
4:00
7:00
10:00
13:00
16:00
19:00
22:00
Time
PerUnitP.U.
5-40 kW
41-200 kW
201-2,000 kW
2,000 kW< Demand
Fig. 7. Typical Load Profiles for Large Commercial Customers
Typical Load Profile of Industrial Customer s
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1:00
4:00
7:00
10:00
13:00
16:00
19:00
22:00
Time
PerUnitP.U. 5-40 kW
41-200 kW
201-2,000 kW
2,001-10,000 kW
10,000 kW< Demand
Fig. 8. Typical Load Profiles for Industrial Customers
To validate the accuracy of the developed load profiles
against the actual measured transformer loading, the TLPLoad Estimation methodology is applied to a representative
transformer and the resultant aggregate transformer load
profile is superimposed against a plot of the actual meteredtransformer loading, shown in Fig. 9. From observation, the
TLP demand profile closely approximates the shape of theactual metered DT loading, although the most crucial point for
the load estimate, which is the peak demand occurring at23:00 shows a deviation of around 13.2% from the actual
transformer peak demand, as is with the test case.
Comparison of TLP vs. Actual Metered DT Loading
4
6
8
10
12
14
16
1:00
3:00
5:00
7:00
9:00
11:00
13:00
15:00
17:00
19:00
21:00
23:00
Time
kWDemand
Metered
Demand
TLP
Demand
Fig. 9. Comparison of TLP Methodology with Actual Metered Load
In comparing the accuracy of the TLP methodology against
the regression formula, the monthly transformer demandestimates of both techniques were compared to the actualmetered demand of four transformers installed with LP-
capable meters over a period of 6 months. The summary of
the findings are shown in Table IV.
TABLEIVVRESULTSCOMPARISON(TLP VS REGRESSION)
18.76% - 24.02%2.88% - 8.44%Commercial4
15.37% - 26.00%77.18% - 130.27%Commercial3
6.34% - 19.81%0.08% - 17.94%Residential2
0.18% - 14.31%16.83% - 29.2%Residential1
TLP
Methodology
Regression
Formula
TypeTrafo
% Deviation from Actual Metered DT
Demand (Over the Study Period)
18.76% - 24.02%2.88% - 8.44%Commercial4
15.37% - 26.00%77.18% - 130.27%Commercial3
6.34% - 19.81%0.08% - 17.94%Residential2
0.18% - 14.31%16.83% - 29.2%Residential1
TLP
Methodology
Regression
Formula
TypeTrafo
% Deviation from Actual Metered DT
Demand (Over the Study Period)
Based on our side-by-side comparison of the demand
estimates of both techniques against the actual metered
transformer peak demand, on the average, the results of the
TLP methodology are more precise than the regression
formula. Although there are instances where the regressionformula is more accurate than the TLP methodology and vice-
versa, the TLP methodology provides more consistent resultsthat range within 20% of the actual DT loading value for
residential DTs and 26% of the actual DT loading for
commercial DTs. The regression formula on the other hand,provides results that range from 30% of the actual DT loading
for residential DTs, and 130% of the actual DT loading forcommercial DTs.
V. CONCLUSIONS
The load profile methodology for DT load estimationshows a lot of potential based on the results of our data
analysis.
Overall, the LP methodology is more precise than the
regression formula for DT load estimation, as the results are
much closer on the average to the actual metered demand thanthe regression formula. But still, there is a lot of room forimprovement of the methodologys accuracy, which shall be
the subject of future studies.
For instance, the load profiles of commercial and industrial
customers could be stratified into different categories based on
the type of establishment and load behavior.
Furthermore, introducing load profiles for weekday and
weekend loads and load profiles that differentiate loadbehavior between wet and dry seasons may make the LPmethodology more accurate.
However, it should be noted that proper facility-customer
connectivity in the customer load database is a primerequirement for either technique to be accurate as well, as
customer kWh consumption, which is one of the requisite datafor both estimation techniques, comes from the load database.
ACKNOWLEDGMENT
The authors would like to thank the following: Jona D.Villanueva and Mercedo P. Delgado for being the initial
proponents of this project; the Meralco Metering Services
Asset Management group for lending their technical expertise
-
8/7/2019 TLMS-CEPSI2010
6/6
and use of their facilities; Manuel M. Galvan, Tomas A.Javellana, Carl G. Aquino and Ireneo Acua for their
endorsement and support for the project; Ricardo V.
Buencamino and the staff of OH-Networks for their unending
support; and Ma.Victoria B. Que, for her support andguidance in the completion of this study.
REFERENCES
[1] D. Gerbec, S. Gasperic and F. Gubina, Determination and Allocationof Typical Load Profiles to the Eligible Consumers, in Proc. IEEE
Power Tech Conference,2003, vol.1.
[2] K. L. Lo, Z. Zakaria and M. H. Sohod, Determination of ConsumersLoad Profiles Based on Two-stage Fuzzy C-means, in Proc. 5th
WSEAS International Conference on Power Systems and
Electromagnetic Compatibility , 2005, pp.212-217.[3] C. S. Chen, J. C. Hwang, and C. W. Huang, Application of Load
Survey Systems to Proper Tariff Design, IEEE Trans. Power Systems,
vol. 4, pp. 1746-1751, Nov. 1997.
[4] C. S. Chen, J. C. Hwang, Y. M. Tzeng, C. W. Huang, and M. Y. Cho
Determination of Load Survey System at Taipower, IEEE Trans.
Power Delivery, vol. 11, pp. 1430-1436, July 1996.
[5] I. H. Yu, J. K. Lee, J. M. Ko and S. I. Kim, A Method for
Classification of Electricity Demands using Load Profile Data, inProc. Fourth Annual ACIS International Conference on Computer and
Information Science, 2005, pp.164-168.