TLMS-CEPSI2010

download TLMS-CEPSI2010

of 6

Transcript of TLMS-CEPSI2010

  • 8/7/2019 TLMS-CEPSI2010

    1/6

    Improvement of DT Load Estimation by Using

    Typical Load ProfilesAndrew Charles D. Yang

    1, Ronoel M. Dellota

    2

    Networks, Manila Electric Company

    Pasig City, [email protected]

    [email protected]

    Abstract This paper proposes a new methodology for singledistribution transformer (DT) load estimation using typicalcustomer load curves. The process described in this paper is an

    improvement over regression-based formulas to properlyestimate DT loads. The results of the methodology are compared

    and verified to the output of LP-capable meters installed at DTs.

    Keywords distribution, transformer, meter, DT, TLMS, loadprofile

    I. INTRODUCTION

    Transformer load monitoring is an important aspect ofelectric distribution utility operation. An accurate and reliableload monitoring system enables system planners and operatorsto determine transformers that are overloaded, normally

    loaded, under-loaded and idle.

    If properly identified, overloaded transformers can be

    readily scheduled for replacement. Hence, DT failures due to

    overloading can be prevented. Under-loaded transformers can

    be removed and replaced with the proper rating, therebymaximizing asset utilization. Idle transformers can be

    removed and used as new stocks, thereby, saving purchasecosts for new transformers.

    There are different methods of Transformer Loadmonitoring. The most accurate method to monitor the load of

    transformers is to install indicating demand (ID) meters thatregister the kW or KVA demand. Because of the number

    distribution transformers (DT) installed in the field, this is notpractical due to the significant investment required. However,

    installation of ID meters can be justified in areas with high

    incidence of DT failures due to overload.

    Other methodologies of transformer load monitoring deal

    with load estimation techniques. One particular method is byusing an empirical formula based on regression to estimate the

    DT KVA loading given only the kWh consumption ofconnected customers. This formula categorizes transformers

    into three groups: residential, mixed residential andcommercial. From this categorization, constants are obtained

    for use with the formula. Currently, our experience with a

    regression based DT load estimation methodology has shown

    that the results are only 64% accurate. This necessitatesfurther load testing on-site to verify overloaded transformers,

    which costs time and additional operational expense. Hence,

    there is a need to explore other load estimation methodologiesthat give more accurate results.

    In this study, the feasibility of using the typical customerload profiles for transformer load estimation will be explored.

    KVA loading will be computed using the aggregate loading of

    the connected customers.

    II. RELATED WORKS

    A load profile is a model of load characteristics representedby parameters such as customer types, day/season and

    temperature. The load profile is used in power generation tomonitor and plan their generation schedule. For the

    transmission system, load profiles are utilized for forecasting

    demand and system planning. Furthermore, the distributionutilities make use of load profiles to enhance the operationefficiency and reliability of their facilities. Load profiles can

    also be used for load balancing and customer billing in a

    deregulated environment [1].

    The importance and scope of the applications of load

    profiling lead to numerous researches related to the subject.Most of these studies are targeted to seek out the most

    accurate way to model the Typical Load Profile (TLP)

    classification. We can categorize the classification techniques

    into two. The first method is derived from the shape of theload curves while the second method is derived from a pre-

    determined set of consumers. Most of the papers that fallunder the first category introduced a fuzzy clusteringtechnique to group similar load curves ([1], [2]). In [1],

    Measured Load Profile (MLP) is classified according to

    hierarchical clustering method and fuzzy logic. In [2], a twostage FCM (Fuzzy C-Means) is introduced by grouping

    through load pattern and value. The second category wherein[3] and [4] belong retrieves data by sampling theory and

    applies statistical analysis to develop the typical load profiles.

    The distribution transformer is the most crucial component

    of the distribution system, customer wise. It bridges the gapbetween the distribution utility and the consumer by stepping

    down the distribution-level voltage to utilization voltage levels

    that are required by the customer. Thus, the loading level of

    the transformer should always be monitored in order tomaintain its good working condition and to ensure the

  • 8/7/2019 TLMS-CEPSI2010

    2/6

    continuous supply of power to customers. To monitoraccurately, the health and reliability of all distribution

    transformers, an ID (Indicating Demand) meters can be used

    to record the peak load. However, given the number of

    distribution transformers in the field, to put up ID (IndicatingDemand) meters for each is not practical. Non-invasive digitalload loggers, on the other hand, can also be employed to

    estimate the loading on the transformer with 800 kWhCons.>800 kWh

    401-800 kWh401-800 kWh

    301-400 kWh301-400 kWh

    201-300 kWh201-300 kWh101-200 kWh101-200 kWh

    71-100 kWh71-100 kWh

    51-70 kWh51-70 kWh

    1-50 kWh

    GeneralServices(Commercial)

    1-50 kWh

    Residential

    kWh RangeRate ClasskWh RangeRate Class

    Cons.>800 kWhCons.>800 kWh

    401-800 kWh401-800 kWh

    301-400 kWh301-400 kWh

    201-300 kWh201-300 kWh101-200 kWh101-200 kWh

    71-100 kWh71-100 kWh

    51-70 kWh51-70 kWh

    1-50 kWh

    GeneralServices(Commercial)

    1-50 kWh

    Residential

    kWh RangeRate ClasskWh RangeRate Class

  • 8/7/2019 TLMS-CEPSI2010

    3/6

    TABLEIIRATECLASSSTRATIFICATION(DEMAND)-INDUSTRIAL

    10,000kW2,000 kW

    201kW-2,000kW

    41kW-200kW

    5kW-40kW

    LargeCommercial

    kW Demand RangeRate Class

    For each segment, customers are selected based on a

    sample size computation of 90% confidence with a 10%margin of error. These customers have been installed with

    load profile (LP) capable meters and their monthly kWhdemand recorded.

    We let cnCand nNwhere N is the number of elements in

    C. Also, we let h be any number between {1H} where H isequal to 24. The recorded load profile for each customer isnormalized using (1).

    )max( 'h

    hc

    hkW

    kWPU n =

    (1)

    The normalized load profiles of each customer segment are

    averaged hourly to obtain a typical load profile to represent

    that particular rate class as shown in (2).

    N

    PU

    PU

    N

    n

    c

    h

    h

    n=

    =1

    (2)

    The hourly average of all customers in a particular

    customer group is normalized once again using (3) to obtain

    the typical load profiles for use with the TLP DT estimationmethodology.

    )max( 'h

    h

    hPU

    PU

    LP =(3)

    A sample typical load profile (normalized) for residentialcustomers with monthly kWh consumption of 301 to 400 kWh

    is shown in Fig. 3.

    Residential, Cons. = 301 - 401 kWh

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    1:00

    3:00

    5:00

    7:00

    9:00

    11:00

    13:00

    15:00

    17:00

    19:00

    21:00

    23:00

    Time

    PerUnit,P.U.

    Fig. 3. Typical Load Profile (Residential, Consumption = 301-

    400 kWh)

    B. Application of Customer kWh Consumption to the TypicalLoad Profile

    The process flow of the TLP methodology is shown in Fig.

    4.

    Monthly Customer

    kWh Consumption

    Aggregate DT Load

    Profile

    Divide by the number of billing

    days to obtrain the approximate

    Daily kWh Consumption

    Apply the Daily k Wh Consumption

    to the Typical Load Profile to get

    Customer Hourly kW Load Profiles

    Hourly kW

    Streetlight Load

    Profile

    Aggregate all Customer Hourly kW

    Load Profiles connected to the

    transformer, the Streetlight Load

    and System Loss

    Take the Peak kW Demand from

    the Aggregate DT Load Profile and

    multiply it with the transformers

    power factor

    DT Peak KVA = DT

    Load Estimate

    Monthly Customer

    kWh Consumption

    Aggregate DT Load

    Profile

    Divide by the number of billing

    days to obtrain the approximate

    Daily kWh Consumption

    Apply the Daily k Wh Consumption

    to the Typical Load Profile to get

    Customer Hourly kW Load Profiles

    Hourly kW

    Streetlight Load

    Profile

    Aggregate all Customer Hourly kW

    Load Profiles connected to the

    transformer, the Streetlight Load

    and System Loss

    Take the Peak kW Demand from

    the Aggregate DT Load Profile and

    multiply it with the transformers

    power factor

    DT Peak KVA = DT

    Load Estimate

    Fig. 4. Typical Load Profile (Residential, Consumption = 301-400 kWh)

    The monthly kWh consumption of each customer

    connected to a distribution transformer is taken from thecustomer load database. The monthly consumption is divided

    by the number of billing days between meter readings to getthe daily kWh consumption, as shown in (4).

  • 8/7/2019 TLMS-CEPSI2010

    4/6

    daysbilling

    kWhkWh

    monthly

    daily= (4)

    The approximate load profile, that is, the hourly kW loadper customer for a 24-hour period, is obtained using (5).

    =

    =H

    h

    h

    hdailyhour

    LP

    LPxkWhkW

    1

    (5)

    The load profile to be used in the above formula

    corresponds to the rate class of the customer, as obtained from(3). Note that the load profile represents a typical day only.

    In addition to customer loads, the effect of streetlight loadsand system loss on the total transformer loading must also be

    taken into account.

    Streetlight loads connected to the transformer, if any, are

    assumed to be 70W high pressure sodium (HPS) luminariesfor residential transformers and 250W HPS luminaries for

    commercial transformers. Streetlight loads are assumed tooperate between the hours of 1800H to 600H and the total

    streetlight load is distributed within this period. Thus the

    streetlight consumption is added to the hourly kW load of theDT for the said range. The hourly streetlight load is denotedas STLhour.

    The technical loss of the transformer should consider theconsumption of the connected customers and the incident

    streetlight load. For the study, a technical loss of 2% is

    assumed. Hence, the calculation of the hourly losses isexpressed as in (6):

    LossDTxSTLkWLosses hourhourhour )(+=

    (6)

    The hourly streetlight load and DT losses obtained in (6) areto be used in the TLP load estimation:

    C. Aggregation of Demand Profiles and DT Load EstimationThe total hourly kW loading is obtained as the aggregate of

    the hourly kW load, the streetlight load, if any and the hourly

    kW loss, also known as the Aggregate DT load profile. Thisis also expressed as in (7).

    hourhourhourhourLossesSTLkWkWTotal ++= (7)

    One may begin to obtain a DT load estimate from theaggregate DT load profile. To do so, the Peak kVA load of

    the transformer is computed by converting the max. totalkWhour load to its kVA load equivalent, using (8).

    pf

    kWTotalPeakkVAPeak

    hour= (8)

    For (8), a power factor (pf) of 0.85 lag is assumed in the

    calculation. As DT load estimates are commonly expressed asa percentage of total transformer capacity, the Peak DT kVAload (%) is taken from (9).

    100% XkVADTRated

    kVAPeakkVADTPeak = (9)

    The Peak kVA value from (8) is analogous to the peak kVA

    demand of the transformer, whereas the percentage obtained

    in (9) is equivalent to the percent ratio of the peak DT kVA

    demand to the rated DT capacity. Hence, this is the resultant

    DT load estimate.

    IV.RESULTS AND EVALUATION

    In developing the typical load profiles, load profile datafrom 1,730 customers installed with LP-capable meters are

    collected and analyzed. The gathered data was recorded for a

    period of one (1) year from November 2004 to October 2005,and from these, typical load profiles for each rate class have

    been developed. Fig. 5, Fig. 6, Fig. 7 and Fig. 8 show thetypical load profiles for the residential, general services

    (commercial), large commercial and industrial rate classes

    respectively.

    Typical Load Profile of Residential Custome rs

    0.00

    0.20

    0.40

    0.60

    0.80

    1.00

    1.20

    1:00

    3:00

    5:00

    7:00

    9:00

    11:00

    13:00

    15:00

    17:00

    19:00

    21:00

    23:00

    Time

    PerUnitP.U.

    0-50 kWh

    51-70 kWh

    71-100 kWh

    101-200 kWh

    201-300 kWh

    301-400 kWh

    401-800 kWh

    Cons. >800

    kWh

    Fig. 5. Typical Load Profiles for Residential Customers

    Typical Load Profile for General Services (Commercial)

    Customers

    0.00

    0.20

    0.40

    0.60

    0.80

    1.00

    1.20

    1:00

    3:00

    5:00

    7:00

    9:00

    11:00

    13:00

    15:00

    17:00

    19:00

    21:00

    23:00

    Time

    PerUnitP.U.

    0-50 kWh

    51- 70 kWh

    71-100 kWh

    101-200 kWh

    201-300 kWh

    301-400 kWh

    401-800 kWh

    Cons. >800kWh

    Fig. 6. Typical Load Profiles for General Services Customers

  • 8/7/2019 TLMS-CEPSI2010

    5/6

    Typical Load Profile of Large Commercial Customers

    0.00

    0.20

    0.40

    0.60

    0.80

    1.00

    1.20

    1:00

    4:00

    7:00

    10:00

    13:00

    16:00

    19:00

    22:00

    Time

    PerUnitP.U.

    5-40 kW

    41-200 kW

    201-2,000 kW

    2,000 kW< Demand

    Fig. 7. Typical Load Profiles for Large Commercial Customers

    Typical Load Profile of Industrial Customer s

    0.00

    0.20

    0.40

    0.60

    0.80

    1.00

    1.20

    1:00

    4:00

    7:00

    10:00

    13:00

    16:00

    19:00

    22:00

    Time

    PerUnitP.U. 5-40 kW

    41-200 kW

    201-2,000 kW

    2,001-10,000 kW

    10,000 kW< Demand

    Fig. 8. Typical Load Profiles for Industrial Customers

    To validate the accuracy of the developed load profiles

    against the actual measured transformer loading, the TLPLoad Estimation methodology is applied to a representative

    transformer and the resultant aggregate transformer load

    profile is superimposed against a plot of the actual meteredtransformer loading, shown in Fig. 9. From observation, the

    TLP demand profile closely approximates the shape of theactual metered DT loading, although the most crucial point for

    the load estimate, which is the peak demand occurring at23:00 shows a deviation of around 13.2% from the actual

    transformer peak demand, as is with the test case.

    Comparison of TLP vs. Actual Metered DT Loading

    4

    6

    8

    10

    12

    14

    16

    1:00

    3:00

    5:00

    7:00

    9:00

    11:00

    13:00

    15:00

    17:00

    19:00

    21:00

    23:00

    Time

    kWDemand

    Metered

    Demand

    TLP

    Demand

    Fig. 9. Comparison of TLP Methodology with Actual Metered Load

    In comparing the accuracy of the TLP methodology against

    the regression formula, the monthly transformer demandestimates of both techniques were compared to the actualmetered demand of four transformers installed with LP-

    capable meters over a period of 6 months. The summary of

    the findings are shown in Table IV.

    TABLEIVVRESULTSCOMPARISON(TLP VS REGRESSION)

    18.76% - 24.02%2.88% - 8.44%Commercial4

    15.37% - 26.00%77.18% - 130.27%Commercial3

    6.34% - 19.81%0.08% - 17.94%Residential2

    0.18% - 14.31%16.83% - 29.2%Residential1

    TLP

    Methodology

    Regression

    Formula

    TypeTrafo

    % Deviation from Actual Metered DT

    Demand (Over the Study Period)

    18.76% - 24.02%2.88% - 8.44%Commercial4

    15.37% - 26.00%77.18% - 130.27%Commercial3

    6.34% - 19.81%0.08% - 17.94%Residential2

    0.18% - 14.31%16.83% - 29.2%Residential1

    TLP

    Methodology

    Regression

    Formula

    TypeTrafo

    % Deviation from Actual Metered DT

    Demand (Over the Study Period)

    Based on our side-by-side comparison of the demand

    estimates of both techniques against the actual metered

    transformer peak demand, on the average, the results of the

    TLP methodology are more precise than the regression

    formula. Although there are instances where the regressionformula is more accurate than the TLP methodology and vice-

    versa, the TLP methodology provides more consistent resultsthat range within 20% of the actual DT loading value for

    residential DTs and 26% of the actual DT loading for

    commercial DTs. The regression formula on the other hand,provides results that range from 30% of the actual DT loading

    for residential DTs, and 130% of the actual DT loading forcommercial DTs.

    V. CONCLUSIONS

    The load profile methodology for DT load estimationshows a lot of potential based on the results of our data

    analysis.

    Overall, the LP methodology is more precise than the

    regression formula for DT load estimation, as the results are

    much closer on the average to the actual metered demand thanthe regression formula. But still, there is a lot of room forimprovement of the methodologys accuracy, which shall be

    the subject of future studies.

    For instance, the load profiles of commercial and industrial

    customers could be stratified into different categories based on

    the type of establishment and load behavior.

    Furthermore, introducing load profiles for weekday and

    weekend loads and load profiles that differentiate loadbehavior between wet and dry seasons may make the LPmethodology more accurate.

    However, it should be noted that proper facility-customer

    connectivity in the customer load database is a primerequirement for either technique to be accurate as well, as

    customer kWh consumption, which is one of the requisite datafor both estimation techniques, comes from the load database.

    ACKNOWLEDGMENT

    The authors would like to thank the following: Jona D.Villanueva and Mercedo P. Delgado for being the initial

    proponents of this project; the Meralco Metering Services

    Asset Management group for lending their technical expertise

  • 8/7/2019 TLMS-CEPSI2010

    6/6

    and use of their facilities; Manuel M. Galvan, Tomas A.Javellana, Carl G. Aquino and Ireneo Acua for their

    endorsement and support for the project; Ricardo V.

    Buencamino and the staff of OH-Networks for their unending

    support; and Ma.Victoria B. Que, for her support andguidance in the completion of this study.

    REFERENCES

    [1] D. Gerbec, S. Gasperic and F. Gubina, Determination and Allocationof Typical Load Profiles to the Eligible Consumers, in Proc. IEEE

    Power Tech Conference,2003, vol.1.

    [2] K. L. Lo, Z. Zakaria and M. H. Sohod, Determination of ConsumersLoad Profiles Based on Two-stage Fuzzy C-means, in Proc. 5th

    WSEAS International Conference on Power Systems and

    Electromagnetic Compatibility , 2005, pp.212-217.[3] C. S. Chen, J. C. Hwang, and C. W. Huang, Application of Load

    Survey Systems to Proper Tariff Design, IEEE Trans. Power Systems,

    vol. 4, pp. 1746-1751, Nov. 1997.

    [4] C. S. Chen, J. C. Hwang, Y. M. Tzeng, C. W. Huang, and M. Y. Cho

    Determination of Load Survey System at Taipower, IEEE Trans.

    Power Delivery, vol. 11, pp. 1430-1436, July 1996.

    [5] I. H. Yu, J. K. Lee, J. M. Ko and S. I. Kim, A Method for

    Classification of Electricity Demands using Load Profile Data, inProc. Fourth Annual ACIS International Conference on Computer and

    Information Science, 2005, pp.164-168.