Tilos for linear project

30
Visualize Project Success! Using TILOS for the linear planning and controlling of projects.

description

Two-dimensional planning based on time and location Combines CAD and project management features Excellent presentation capabilities Superb progress tracking Data exchange with other major project planning software 

Transcript of Tilos for linear project

Page 1: Tilos for linear project

Visualize Project Success!Using TILOS for the linear planning and controlling

of projects.

Page 2: Tilos for linear project

Characteristics of a linear project

� Repetition of each activity along the length of the project

� The goal is to optimize the productivity rates thus minimizing the

total time of crews on the ROW thereby reducing project duration

and overall cost

� Continuous movement of activities and crews along right-of-way

� Typical projects include: rail, tunnel, highway, pipeline, bridge and

high voltage transmission line projects

Page 3: Tilos for linear project

The graphical representation of linear projects

Road project Rail project

Building projectPipeline project

Page 4: Tilos for linear project

� TILOS connects the geography and constructability issues of a project with the schedule (what is built, when and where)

� Traditional CPM schedules and network diagrams fail to provide a visual connection between the project plan and the project itself

� Present your project on a single page using TILOS!

TILOS vs. traditional CPM and Gantt charts

40-page Primavera schedule

represented on one page using linear

planning

Page 5: Tilos for linear project

TILOS in Linear Construction Projects

Page 6: Tilos for linear project

Top soil

Stabilisation

Grading

Bridge

Cut

Fill

- How it works

Page 7: Tilos for linear project

- The Gantt Chart features

� Natural working with interactive Gantt chart - Milestone symbols can be defined free and put to 1 task line

- Multiple tasks on one line

- Task steps to monitor micro tasks or extra work to happen before, during and after the task execution time

� Multiple Windows support- Move or copy tasks across the windows by mouse

- Create links across the windows

Page 8: Tilos for linear project

- Railway Project

o Pictures from site

o Scale with side map

o Main construction windows

o Detailed work

� High quality layouts keep attraction

� Be one step ahead of your completion

Page 9: Tilos for linear project

- Railway Project

� Realistic scheduling using site data that influences construction progress

� Full integration of logistic and train rides

o Generated sitemap and grid

from sector table

o Track renewal with hindrance

and setup times

o Full calculated ballast trains

incl. train setup

o Train runs for drive in and out

Page 10: Tilos for linear project

o Rock classification

table with drilling

speed for tasks

o Connector tunnels

o Tunnel lining

(1 task based on

work profile)

o Water draw down

zone

- Metro tunnel building

Page 11: Tilos for linear project

o Bend and Coordinates based

on station table

o Pile works generated based

on station table incl.

relationships

o Deck works generated by

station table

o Elevated station

� Quick plan creation based on station tables with quantity values

� Ideal overview on the construction program

- Metro project: Elevated line

Page 12: Tilos for linear project

- Metro Rail Project in South Africa

� First basic construction program in TILOS with later detailing in Primavera

� Update of TILOS schedule done every 1 month using link to Primavera

o 8 zones with different station

numbering (non linear axis)

o Left part build as underground

o Cut and fill sections

o Evaluation phase

Page 13: Tilos for linear project

- Industry sample: Pipeline

� Pipeline project planned in 2 spreads to cover weather conditions

� Rainfall is shown in colors in the background of the schedule

o Elevation profile

o Strong rain fall

o Pump stations

o Linear works

Page 14: Tilos for linear project

- Highway Project

Page 15: Tilos for linear project

- Highway Project

o Exits and crossings

o Cut & Fill

o Bridges

o Tunnels

Page 16: Tilos for linear project

o Preparation

o Bridges

o Cut & Fill

o Black tops

o Monitoring

o Handover

- Highway Project

Page 17: Tilos for linear project

� Progress always contains distance information, not just % completed

� Enter progress directly into TILOS for an immediate evaluation

� Record progressImport progress (Clipboard or XML) Analyse progressApply progress

TILOS progress reporting

Page 18: Tilos for linear project

� Description of the track including GPS co-ordinates

Project description in XLS

� Description of the project complexities

Page 19: Tilos for linear project

Planning result in Google Maps

� Track renewal activity sliced into 3 hour working and reporting steps

� 06:00 – 09:00

� 03:00 – 06:00

� 00:00 – 03:00

Page 20: Tilos for linear project

@ 3am

Progress in Google

@ 6am @ 9am

� XML Export with time sliced data shows progress status along the ROW

� Comparison: planned (thick line) � actual (thin line)

Page 21: Tilos for linear project

Integration models

XML

- Tasks- Links- Profiles

- Resources- Costs- Progress

Page 22: Tilos for linear project

- XML: Data Exchange concept

TILOS XML

Microsoft Project

ASTA Power Project

Other programsExcel

ASCClipboard / File

o Library data- Resources and accounts- Categories (Codes)- Distance and time profile data

o Tasks

o Task data- Resource and cost data- Actual resource data- Links- Progress

o XLS Exchange- Same items as for ASC- Each object in a separate data sheet

o XLS Report- Export of task list with resources assignments - Summary of resource consumption at the end- Time sliced values (Days / Week / Month / Years)- Empty lines for collect actual data

Oracle Primavera

Page 23: Tilos for linear project

- XML: Export from TILOS

o Select Action - File / Import- File / Export

o Select format- ASC- XML- Excel

o Data source- Select Clipboard or File

o Select profile- Data exchange rules

o Select project- Select sub projects- Set a filter

o Start exchange

Page 24: Tilos for linear project

- XML Exchange with Primavera

o Log in - Standard Primavera Log in

o Select action- Import or Export- Create user fields

o Data source- Select profile to use

(Contains exchange rules)- Select data file

(Contains exchange data)

o Projects and filters- Select project- Select a filter for export

o Start Import

Page 25: Tilos for linear project

- Primavera Master Project

o Task ID from TILOS (alternatively GUID)

o WBS code

o Location data (UDF fields)

o TILOS Template as code assignment

Page 26: Tilos for linear project

� A tool that connects schedule and site

information in a single chart. Site

constraints are integrated into the plan

from the beginning

� Is used in any project phase: FEED,

Tendering and Estimating, Execution

and Claim analysis.

� A tool that can be used by any

participant in the construction process:

Owners, Engineers and Construction

company.

TILOS – professional linear project management solution

� TIME DISTANCE is superior to GANTT CHARTS for

linear projects.

� Rapid creation of repetitive tasks in different locations

saves time and effort for detailed planning. Easy clash

detection and avoiding errors saves money during

construction phase.

� Powerful progress measurement tool to monitor

construction exactly as it was done in the field ( move-

arounds, work stoppages and out of sequence

progress).

� Flexible integration methods allow usage of TILOS

along with other software and also if the project has

already started.

Page 27: Tilos for linear project

"TILOS transformed our engineers' attitude

towards project scheduling from something

extra they never had time for to a tool they

"owned" and wouldn't go to a meeting without.”

James Lyon - HDR Inc. in USA

What one of our clients is saying

Page 28: Tilos for linear project

Cityringen project in Kopenhagen, Length: 15.2 km Finish: in 2018

TILOS was used in early design phase to schedule

TBM and the work in stations. We got the following

remark on TILOS from :

“TILOS is being used as the strategic planning tool for

the Copenhagen Cityringen Project. Early in the

project it was used to assess the impact of different

TBM sequences and number of TBM’s on both the

overall programme and the interfaces with the

individual station construction. As the project has

developed the tool has been invaluable in quickly

assessing the affects of changes, possible delays and

determining suitable mitigation measures, for both

the TBM drives and the station constructions. Not

only has TILOS been great as an analysis tool, but the

easy to understand graphical output provides a simple

tool for explaining the planning to all members of the

project team.”

This from :

Steen Nielsen

Head of Planning

Metroselskabet I/S

Metrovej 5

DK - 2300 Copenhagen S More info about project and contracts: http://intl.m.dk/Cityringen-en.aspx

Page 29: Tilos for linear project

Pipeline project Alberta Clipper, Canada

Enbridge Pipelines Inc. operates, in Canada and the U.S., the

world’s longest crude oil and liquids pipeline system. These

pipeline systems have operated for over 55 years and now

comprise approximately 13,500 kilometres (8,500 miles) of

pipeline, delivering more than 2 million barrels per day of crude oil

and liquids. Alberta Clipper is a crude oil pipeline that will provide

service between Hardisty, Alberta, and Superior, Wis. This 1,000-

mile / 1,607-km pipeline will have an initial capacity of 450,000

barrels per day (bpd), with ultimate capacity of up to 800,000 bpd

available.

Enbridge Pipelines Inc. used TILOS as their best in class linear

scheduling tool for managing the Alberta Clipper Mainline

Construction for this immense project in Canada. The software

was used in the field, and in the main offices to bring together

stakeholders to greatly enhance planning, and reporting making

the project a huge success.

More info about pipeline projects: http://linearproject.com/pipeline-construction.html

Page 30: Tilos for linear project

TILOS (TIme LOcation System)

� Railway companies: Saudi Archirodon, DB, SNCF, Network Rail, Herzog, Nurol Construction,

Dogus, Larsen & Toubro Ltd., Qatar Railway Company, MMC Gamuda

� Railway equipment: Alstom, Bombardier, Siemens, IJM Corporation-

� Building companies: Bilfinger Berger, Hochtief, Strabag, Skanska, Bouygues, Vinci, Hill

International, Kiewit, Flatiron, Enka, Parsons-UAE

� Engineering: Bechtel, Fluor, HDR Inc, Drees & Sommer, Lahmeyer, DB Consult,

SNC Lavalin, Gulf Interstate, Worley Parsons, Engineers India Ltd. Indian

Institute of Technology, Leighton Contractors Asia Limited, AECOM

� Pipeline: TransCanada, Enbridge, Willbros, Henkels & McCoy, Techint, Repsol, Rel.Gas

Transport. Infra.LTD, NABUCCO Consortium, Stroytransgaz, Punj Lloyd Oil & Gas

� Power: ATCO Electric, Balfour Beatty

� Road: Mota-Engil, Hess. Straßenbauamt, Hermann Kirchner, DMRC

� Metro / light rail: Kopenhagen, Dallas, Toronto Transit, Houston Rapid Transit, Astaldi,

Gulermak

Who is using TILOS ?