T&i live tests
-
Upload
hyperchanaka -
Category
Education
-
view
258 -
download
1
description
Transcript of T&i live tests
Inspection and Testing
Module 5
Testing Methodology
Live Tests
20kA2000A
200A
20Ω200Ω
2000Ω
TEST
Earth Loop Testing
Loop Tester
20kA2000A
200A
20Ω200Ω
2000Ω
TEST
Earth Loop Testing
Loop Tester
1.15Ω
Direct measurement of Zs
ON
Direct measurement of Zs
ON
0.35Ω
Direct measurement of Zs
ON
0.55Ω
Direct measurement of Zs
ON
0.65Ω
Direct measurement of Zs
ON
0.85Ω
Record the highest value i.e 0.85Ώ
0.25Ω
Measurement of Ze
Earthing conductor must be disconnected for this test and the installation turned off
ON
OFF
0.25Ω
Measurement of Ze (three phase)
Fuses must be removed to disconnect the installation for this test
ON
OFF
0.26Ω
Measurement of Ze (three phase)
Fuses must be removed to disconnect the installation for this test
ON
OFF
0.25Ω
Measurement of Ze (three phase)
Fuses must be removed to disconnect the installation for this test
20kA2000A
200A
20Ω200Ω
2000Ω
TEST
Fault Current Testing
Loop Tester
0.865
20kA2000A
200A
20Ω200Ω
2000Ω
TEST
Loop Tester
865
Fault Current Testing
1.25kA
Measurement of Prospective Short Circuit Current
Note: The Earth lead is connected to the neutral terminal
1.25kA
Measurement of Prospective Earth Fault Current
ON
OFF
2.25kA
Note: The Earth lead is connected to the neutral terminal
Measurement of Prospective Short Circuit Current 3ph
ON
OFF
2.28kA
Note: The Earth lead is connected to the neutral terminal
Measurement of Prospective Short Circuit Current 3ph
ON
OFF
2.25kA
Note: The Earth lead is connected to the neutral terminal
Measurement of Prospective Short Circuit Current 3ph
Determination of 3phase fault current
Highest single phase value measured = 2.28kA
2.28 X 3 = 3.95kA
An approximation can be done as 2 x the reading i.e.2 x 2.28 = 4.56kA
Note:- The minimum breaking capacity for
protective devices is 4kA
RCD Testing
TEST
00 1800
10
2030 100
200
300X 1/2
X 1X 5
mA
RCD Testing
TEST
00 1800
10
2030 100
200
300X 1/2
X 1X 5
mA
ON
OFF
0 18030
1/21
5
OR 1
No Trip Test ½ current (15mA)
32A
30mA
Load must be disconnected
ON
OFF
030
1/21
5
32A
30mA
Full Current Test (30mA)
Must trip within:-
200ms BS4293
300ms BSEN61008-1
26ms180
ON
OFF
030
1/21
5
32A
30mA
Full Current Test (30mA)
Change half cycle
18ms
Record highest value i.e 26ms
180
ON
OFF
030
1/21
5
32A
30mA
Fast Trip Test (150mA)
Must trip within 40ms
15ms180
ON
OFF
030
1/21
5
32A
30mA
Fast Trip Test (150mA)
9ms
Change half cycle
Record highest value i.e 15ms
180
C1 P1 P2 C2
125Ω
TEST
d
Earth Electrode Test
Electrode under test
TEST SPIKES
Minimum 10 x d15m-25m 15m-25m
3m 3m
C1 P1 P2 C2
127Ώ
TEST
d
Earth Electrode Test
Electrode under test
TEST SPIKES
Minimum 10 x d15m-25m 15m-25m
3m 3m
C1 P1 P2 C2
122Ω
TEST
d
Earth Electrode Test
Electrode under test
TEST SPIKES
Minimum 10 x d15m-25m 15m-25m
3m 3m
Percentage Deviation
Average Value 122 + 125 + 127
3= 124.7
Maximum deviation
124.7 – 122 = 2.7 *
125 – 124.7 = 0.3
127 – 124.7 = 2.3
Percentage deviation2.7
124.7 x 100 = 2.1%
2% is very good, any value above 5% should be re-tested increasing the distance between the Electrode and the current spike.
145Ω
Bonding
Earthing Conductor
To ElectrodeLoop Tester
T.T Systems RCD protected Electrode Test
ON
RCD
OFF
Section B School Nursery
1) a) Which type of verification is required for this installation
b) What documentation/information is required
c) State two statutory regulations that govern the inspection and test
d) What documentation will need to be completed
1)a) As a new installation it will require an Initial Verification
b) The results of the assessment regarding maximum demand, methods of earthing etc and charts or diagrams regarding the type of circuit, number of points
served, location of control, methods of protection and equipment vulnerable to damage by the test equipment
c) State two statutory regulations that govern the inspection and test
c) The Health and Safety at Work Act and the Electricity at Work Regulations
d) What documentation will need to be completed
d) The Electrical Installation Certificate and
i) schedule of test results
ii) schedule of inspection
2) List the test instruments required for this installation
Voltage proving unit
Low reading Ohm meter and insulation resistance meter (contained in a combined Insulation/Continuity tester)
Earth loop impedance and Prospective Short-circuit current meter
There are no RCDs in the installation, therefore no test equipment is required for these tests
3) List in the correct sequence the tests that are required
i) Continuity of protective conductors including bonding
ii) Ring final circuit continuity
iii) Insulation resistance
iv) Polarity
v) Earth loop impedance
vi) Prospective fault current
vii)Functional testing
4)a) Calculate the approximate value of R1 + R2 of the ring final circuit in rooms 1 and 2
b)Calculate the approximate Zs value for the above ring
c) What other test is automatically carried out when carrying out the ring final circuit continuity test
a) 2.5mm2 + 1.5mm2 = 7.41 + 12.1 = 19.51mΩ/m
R1 + R2 = 0.25(19.51/1000 x 30) = 0.15Ω
b) Zs = Ze + (R1 + R2)
Zs = 0.4 + 0.15 = 0.55Ω (measured at 200 C)
c) This test proves, continuity of the live conductors as a ring, continuity of the cpc and proves polarity
5) The following insulation resistance values have been recorded for 3 circuits supplied from the distribution board:-
2MΩ, 7MΩ and 50MΩ, all other circuits are > 200MΩ
Calculate the overall insulation resistance value and determine if this value is acceptable or unacceptable (give reasons)
1/RT = 1/R1 + 1/R2 + 1/R3 + 1/R4
1/RT = 1/2 + 1/7 + 1/50 + 1/200
1/RT = 0.5 + 0.143 + 0.02 + 0.005 = 0.668
RT = 1/0.668 = 1.5MΩ
This is greater than the minimum of 0.5MΩ (acceptable)
6)a) Calculate the Zs value of the air conditioning unit
b) What factors need to be applied when correcting measured Zs values
c) What other method can be used to verify the measured Zs value
d) Apply the method given in c) above and confirm of the measured Zs value is acceptable or unacceptable
e) If unacceptable give two methods of overcoming this unacceptable reading
a)Zs = Ze + (R1 +R2)
(4.0mm2 + 1.5mm2 = 4.61 + 12.1 = 16.71mΩ/m)
Zs = 0.4 + (16.71/1000 x 15) = 0.65Ω (measured at 200 C)
b) Factors which need to be applied are:-
i) Ambient temperature when the test is conducted
ii) Cable operating temperature (usually 700C)
c) The rule of thumb (0.75 x max Zs)
d) Max Zs = 1.5Ω (1.5 x 0.75 = 1.125Ω > 0.65Ω measured
The circuit is acceptable
e) The two methods recognised in BS7671 are:-
i) Provide the circuit with an RCD
ii) Provide local supplementary bonding complying with the max resistance value of 413-02-27/8
7) For one of the lighting circuits list all components of the earth fault loop impedance path
a
b c
e
d
f
a) Supply phase, b) supply phase conductor, c) circuit phase conductor, d) exposed-conductive-part of the light, e) c.p.c of the lighting circuit, f) return path (armour/sheath) of the supply cable