Theory of constraints

10
MANAGERIAL ACCOUNTING “LUCENT TECHNOLOGY” THEORY OF CONSTRAINTSBy: Eka Darmadi Lim 3094802 May Eka Saputri 3094814 Steven Auryn Hendro 3105812 Class: Y University of Surabaya Faculty of Business and Economics International Class 2012

description

 

Transcript of Theory of constraints

Page 1: Theory of constraints

MANAGERIAL ACCOUNTING

“LUCENT TECHNOLOGY”

“THEORY OF CONSTRAINTS”

By:

Eka Darmadi Lim 3094802

May Eka Saputri 3094814

Steven Auryn Hendro 3105812

Class: Y

University of Surabaya

Faculty of Business and Economics

International Class

2012

Page 2: Theory of constraints

STATEMENT OF AUTHORSHIP

This article about “Lucent Technology - TOC” created by our team ideas and

opinion, and this paper pure from our understanding not copy or paste from the

resource that “available”, we use the appendix and references to describe everything.

The person who signs this authorship statement, everything in this paper just for

internal use only, we consider as a student we have limitation, and mistakes, so the

whole paper is our group opinion for internal use only, for our case study. And we

consider if there is plagiarism in this paper, we as the team member, we are ready for

the consequences, that as our agreement before, and we understand that we must

deliver on-time as scheduled.

The Authors,

Eka Darmadi Lim May Eka Saputri

(3094802) (3094814)

Steven Auryn Hendro

(3105812)

Page 3: Theory of constraints

Introduction:

Each firm faces limited resources and limited demand for each product. These

limitations called “Constraint”, theory of constraint admit that the performance

of the company is limited by constraints. If the company wants to improve

their performance, a company must identify the constraints, exploit the

constraints in the short term and long term, and then find ways to overcome

them.

Theory of constraints focus on 3 activities, they are Throughput, Inventory and

operating expenses. Management goals are increasing throughput; minimize

inventory and decreasing operating cost.

1. Throughput: rate at which an organization generates money through sales.

2. Inventory: all the money the organizations spend in turning materials into

throughput.

3. Operating expense: all the money the organization spends in turning

inventories into throughput.

By increasing throughput, minimize inventory, and decrease operating

expense will give any impact on increasing finance performance, profit, return

on investment, and cash flow.

In traditional viewpoint, pressing in increasing throughput and decreasing operating

expense are very important, and minimize inventory are not really important.

TOC recognize that lowering inventory decreases carrying costs and thus

decreasing operating costs expenses and improves net income. More deeper, TOC

recognize lowering inventory helps produce a competitive edge by having, better

products and lower price and responsiveness to customer’s needs.

1. Better products higher quality

Company able to improve their products / product innovation, by

lowering inventory there is innovation, company can market their

product before their competitor market the same products, without

waiting for last stock.

2. Lower prices

3. Responsiveness

Page 4: Theory of constraints

TOC Steps:

1. Identify the organization’s constraint(s)

The constraints:

External constraints – limiting factors imposed on firm from external sources

( such as market demand )

Internal constraints – limiting factors on firm from internal sources

(Such as: product capacity, machine-time availability, etc.)

Loose constraints – constraints whose availability resources are not fully

utilized.

Binding constraints – constraints whose availability resources are fully

utilized.

Constraints are used to optimal mix reveals which is will maximize throughput

and how much of each constrained resources is used and which of the

organizations are binding.

For example

Hello company produce 2 component of machine x and y, margin contribution for

each $ 300 for x and $ 600 for y. Operation work 5 days in a week.

In here we can said that Hello Company better produce and sell component y

because y has a biggest MC/Unit. But this solution is not hundred percent good.

One binding internal constraints:

X Y

Hour/unit 1 hour 3 hour

MC/Unit $ 300 $ 600

Constraints : work processes 120 hours / weak

We can produce 120/1 = 120 units 120/3 = 40 units

MC total $ 36,000 / weak $ 24,000 / weak

MC resources $ 300/1 = $ 300 ( TOP ) $ 600/3 = $ 200

Page 5: Theory of constraints

Shown: Better just produce and sell product x, because x produce higher

MC/weak ( $ 36,000 for x and $ 24,000 for y ) its because MC/unit rare from

resources or constraints of product x higher than constraints of product y,

although MC/unit product y 2x bigger than MC/unit product x MC/unit

product is doesn’t matter but MC/unit unavailability resources is important.

Internal binding constraint and external binding constraint:

If hello company can sell maximum 30 units component x and 100 units

component y, so optimal mix will be:

Component x because MC/highest resources maximize first 30 X 1

hour unit = 30 hours, and 90 hours for component y 90 hours: 3 hours = 30

units.

2. Exploit the binding constraint(S)

In many companies there is some binding constraint, the main binding

constraint is drummer, whereas level of productivity drummer constraint are

level of production in all factory.

TOC add 2 more feature:

Rope

Buffer

Rope = actions taken to tie the rate at which material is released into the plant

(at the first operation) to the production rate of the constrained resource.

The standard of the process that have constraint continued upriver to

synchronize the basic materials used in accordance with the optimal product

mix eliminate raw materials unneeded.

Buffer : are made to ensure resource constraint that have kept busy, so for

scheduling, operations must produce the component required by the resource

drummer two days earlier before drummer constraints.

Page 6: Theory of constraints

For example:

Hello Company has 3 processes

Drilling – Grinding – Polishing

Assumption: the only internal binding constraint is grinding which

spend 120 hours grinding/weak grinding process is drummer.

With optimal mix (calculation before) 30 x and 30 y maximum grinding

And, grinding and polishing loose constraints can produce more than of

product mix required.

3. Subordinate everything else to the decision made in step 2

The drummer constraint essentially sets the capacity for the entire plant. Which

make the company will change their way to think. This make the use of efficiency

measures at the department level may no longer be appropriate. Consider that

confer company once again. Encouraging maximum productive efficiency for the

grinding department would produce excess work-in process inventories. For

example assume that the capacity of the grinding department is 80 units per week.

Assuming the 2 day buffer is in place, the grinding department would add 20 units

per week to the buffer in front of the drilling department. Then there will be a

large work-in process inventories. Polishing will produce at the rate of drilling

since the polishing follows drilling in the sequential production process.

4. Elevate the binding constraints.

Once actions have been taken to make the best possible use of the existing

constraint, the next step is to embark on a program of continuous improvement by

reducing the limitations that the binding constraints gave on the organizations

performance. Assume that the polishing has 160 hours available. Part X uses 1

hours and part Y uses 3 hours and we want to produce 30 part x and 30 part Y.

The total hours we spend is 120 hours ((30x1)+(30x3)). If we want to add more

production to the product Y by 20 (from 30 to 50) is possible. Since the increase

of production of part Y by 20 will increase the throughput by 12000 (20 x $600)

Page 7: Theory of constraints

per week. If the cost of adding the half shift is $50 per hour. Then the incremental

cost is $3000 per week. Then the decision to add the half shift is a good choice.

5. Repeat the process

Eventually the drilling constraint will be elevated to a point where the constraint is

no longer binding. Suppose for example that the company adds a full shift for the

drilling operation. Increasing the resource availability to 240 hours. both the

drilling and polishing constraints are capable of producing more of part X. but the

grinding cannot since the maximum production of product mix is only 80 per

week. Thus the new drumming constraint is grinding. Once the new drummer

constraints identified. Then the TOC process is repeated. The main objective is to

continually improve the performance by managing constraints

Summary TOC

“Theory of Constraints” (TOC) is good theory for factory, because TOC will

help factory to manage and solve their problems. After manage and solve the

problems, are easy for factory to get more and more profit.

Actually the main problems in factory, are managing the inventories. And

TOC are really help in managing inventories. TOC has buffer and rope to

solve the inventories, rope are to tie the rate at which materials is released into

the plant to the production rate of the constrained resources. Buffer, are made

to ensure resource constraint that have kept busy, so for scheduling, operations

must produce the component required by the resource drummer earlier before

drummer constraints.

In our opinion, the main idea from TOC is Rope and Buffer, but all the

process is related each other. And it will make TOC, as a union idea to

managing inventories and be the first or main company in this or that product.

Page 8: Theory of constraints

Case Study:

Lucent Technologies implement TOC

Background:

The Lucent Technology is a corporate owned by bell lab innovation, as we

know as AT&T (1970 – 2006) in United States America, but “The Lucent

Technology have different objective, “The Lucent Technology” build the

semiconductor, fiber optic, fiber cable. Means that the “Communication

Equipment”

The Lucent Technologies was built in 1970, and start producing wire, already

produce up to 107 Billion conductors that manufactured that year. The purpose

to build this company for takes a profit competing communication provider,

start from $8 / Share up to $84 / Share in 1999, and now in 2006 Lucent

bought by Alcatel and ready to start the most improvement ever, In 2011 for

implementing TOC inside.

After Lucent implement TOC inside the operational system, there are lots of

improvement that we get, for developing new product we need just half of

time needed, 100% of project can be done on time, we can 3x more for

product development capacity, 30% Revenue turnover, Multimillion dollar

profit improvement.

The Problem

1. How Lucent become more productive?

2. How Lucent can improve their performance?

3. How Lucent can win the competitor?

4. How Lucent can increase their profit?

Analysis:

By implementing TOC inside operation we can see lots of improvement that

we get, I will explain in a brief, using TOC system we can analyze which part

is our bottleneck, and the most inefficient one, before they implement TOC,

they kept producing in “continuous number” of a product, for example

Page 9: Theory of constraints

Machine A Can Produce 100, Machine B can Produce 500. In the “old” time,

their flow is like that, so machine B can’t reach the maximum capacity, but

after implement TOC after Machine A produce 500, then they continue to

machine B, so machine B can maximize their capacity. When the machine A

produces 500, we improve machine B to double size, so we can increase the

overall throughput.

The Solution

Step by Step

A. Identify organization constrain

- Lack overload of some machine in production capacity

- Lack of innovation

Internal and External Factor

Internal: Lack of technology that we have

External: We can’t fulfill the request of the market, may be our competitor

can made product similar, and better. Or our production capacity is not

enough to fulfill our customer request

B. Exploit the binding constrain

Some machine need to be operated with more than 1 people, the

reason, because while this people take some rest, the production kept

going by the substitute people. And the process that breaks down

should be repaired as a priority.

Solution:

A. Help the critically machine

B. Don’t allow the critically constrained resources run out of

work.

C. Realize just enough WIP into the system

D. Remove all excess WIP from system, because WIP cost money,

clutter, and slows the flow.

C. Subordinate everything else to the decision meet in step 2

Remove all excessive WIP, then if the buffer still full, do not release

any work into the system. (Make done it first)

Page 10: Theory of constraints

D. Elevate the binding constrain

After we implement step 1-3, now to elevate the constraint, get another

resource / workstation!

E. Repeat the process

Then we repeat the process to “test” if the system that already revised,

work or not. And do not let inertia become the constraint, because the

constraint becomes moved.

The Results:

1. New Product can be developed twice fast.

2. Project can be completed on time

3. More production capacity

4. Increase in revenue and profit

References:

Book of Managerial Accounting by: Maryanne M Mowen

http://en.wikipedia.org/wiki/Lucent

http://scmviews.blogspot.com/2011/04/toc-implementation-at-lucent2011.html

http://tocca.com.au/toc