THEMIS MISSION PDR/CAREFI- 1 UCB, November 12-14, 2003 THEMIS ELECTRIC FIELD INSTRUMENT (EFI) Dr....
-
Upload
ella-blair -
Category
Documents
-
view
221 -
download
3
Transcript of THEMIS MISSION PDR/CAREFI- 1 UCB, November 12-14, 2003 THEMIS ELECTRIC FIELD INSTRUMENT (EFI) Dr....
THEMIS MISSION PDR/CAR EFI-1 UCB, November 12-14, 2003
THEMIS ELECTRIC FIELD INSTRUMENT (EFI)Dr. John Bonnell and the THEMIS EFI Team
University of California-BerkeleyUniversity of Colorado-Boulder
THEMIS MISSION PDR/CAR EFI-2 UCB, November 12-14, 2003
Outline
•Personnel and Organization•Summary of EFI Status at MPDR•Requirements, Specifications, and Design Compliance•Design Overview
•Top-Level Design•Designs of Individual Elements
•Design Drivers and Compliance•DC Error Budget•AC Error Budget
•Schedule•Design•Long-Lead Procurement•ETU
•EPR Results
THEMIS MISSION PDR/CAR EFI-3 UCB, November 12-14, 2003
Personnel and OrganizationOrganizational Chart (all UCB unless noted):
• Prof. F. Mozer (EFI Co-I).• Drs. J. Bonnell, G. Delory, A. Hull (Project Scientists)• P. Turin (Lead ME)• Dr. D. Pankow (Advising ME)• B. Donakowski (EFI Lead ME, SPB)• R. Duck (AXB ME)• D. Schickele (Preamp, SPB ME)• C. Smith (THEMIS Thermal Eng)• S. Harris (BEB Lead EE)• H. Richard (BEB EE)• R. Abiad (BEB FPGA Eng)• G. Dalton (EFI GSE Mechanical and General Mechanical)• J. Lewis, F. Harvey (GSE)• Technical Staff (H. Bersch, Y. Irwin, H. Yuan, et al.)• R. Ergun (DFB Co-I; CU-Boulder)• J. Westfall, A. Nammari, K. Stevens (DFB Eng; CU-Boulder)• C. Cully (DFB GSR; CU-Boulder)
THEMIS MISSION PDR/CAR EFI-4 UCB, November 12-14, 2003
EFI Status at MPDR• Design:
• The current EFI design meets Mission and Instrument requirements (exception: SPB mass estimate).
• The design will be ready for ETU fabrication on schedule.• The critical paths on the design (SPB boom length, AXB deploy and
stability,Preamp electro-mechanical and thermal, DFB FPGA definition and requirements) have been identified, and design elements are mature (exception: radial boom length (see EPR-Radial Booms)).
• Procurement:• All long-lead items have been identified:
– EEE parts ordered; rad testing of required parts arranged.– SPB and AXB mechanical items (custom wire cable, stacers, actuators,
motors) have been ordered, with exception of SPB motors (see Schedule and Procurement)).
• Vendors for mechanical and electrical machining and fabrication identified at mission-wide level.
• Personnel:• Team is essentially complete:
– All design engineering positions filled.– Two remaining MT positions to be hired Nov-Dec ’03; on-board by ETU
in Jan-Feb ’04.
THEMIS MISSION PDR/CAR EFI-5 UCB, November 12-14, 2003
REQUIREMENT EFI DESIGN
IN-1. The Instrument Payload shall be designed for at least a two-year lifetime.
Compliance. Lifetime has been considered in all aspects of EFI and DFB design (parts, performance degradation, etc.).
IN-2. The Instrument Payload shall be designed for a total dose environment of 33 krad/year
(66 krad for 2 year mission, 5mm of Al, RDM 2)
Compliance. Common Parts Buy for Instrument Payload. All parts screened for total dose. Radiation testing planned if TID is unknown.
IN-3. The Instrument Payload shall be Single Event Effect (SEE) tolerant and immune to destructive latch-up.
Compliance. Common Parts Buy for Instrument Payload. All parts screened for total dose. Radiation testing planned if LET is unknown. DFB design includes latchup mitigation circuits on ADCs, inclusion contingent upon results of LTC1604 radiation testing.
Mission Requirements
THEMIS MISSION PDR/CAR EFI-6 UCB, November 12-14, 2003
REQUIREMENT EFI DESIGN
IN-7. No component of the Instrument Payload shall exceed the allocated mass budget in THM-SYS-008 THEMIS System Mass Budget.xls
Compliance.
SPB: 1.88 kg Allocated; 1.92 kg CBE (CAD model).
AXB: 2.30 kg Allocated; 2.00 kg CBE (CAD model).
(Harness, BEB and DFB tracked with IDPU)
IN-9. No component of the Instrument Payload shall exceed the power allocated in THM-SYS-009 THEMIS System Power Budget.xls
Compliance.
Preamps: 0.09 W Allocated; 0.07 W CBE (BB).
BEB: 1.76 W Allocated; 1.67 W CBE (BB).
DFB: 1.00 W Allocated; 0.86 W CBE (modeling).
IN-13. The Instrument Payload shall survive the temperature ranges provided in the ICDs
Compliance. SPB/AXB ICDs signed off. Verification by Environmental Test planned.
IN-14. The Instrument Payload shall perform as designed within the temperature ranges provided in the ICDs
Compliance. SPB/AXB ICDs signed off. Verification by Environmental Test planned. Special thermal shock testing of preamp ETU planned.
Mission Requirements
THEMIS MISSION PDR/CAR EFI-7 UCB, November 12-14, 2003
REQUIREMENT EFI DESIGN
IN-16 The Instrument Payload shall comply with the Magnetics Cleanliness standard described in the THEMIS Magnetics Control Plan
Compliance. THM-SYS-002 Magnetics Control Plan. Budget for EFI Magnets (Boom Motors) is <0.75nT @ 2 meters.
IN-17 The Instrument Payload shall comply with the THEMIS Electrostatic Cleanliness Plan
Compliance. Design, fabrication, and testing in accordance with THM-SYS-003 Electrostatic Cleanliness Plan.
IN-18 The Instrument Payload shall comply with the THEMIS Contamination Control Plan
Compliance. Design and fabrication in accordance with THM-SYS-004 Contamination Control Plan.
IN-19. All Instruments shall comply with all electrical specifications
Compliance. Design in accordance with THM-IDPU-001 Backplane Specification (BEB, DFB).
IN-20. The Instrument Payload shall be compatible per IDPU-Instrument ICDs
Compliance. THM-SYS-103 DFB-to-IDPU ICD signed off. THM-SYS-104 BEB-to-IDPU ICD signed off. Verification Matrices to be completed.
IN-21. The Instrument Payload shall be compatible per the IDPU-Probe Bus ICD.
Compliance. Both THM-SYS-108 Probe-to-EFI Radial Booms ICD and THM-SYS-109 Probe-to-EFI Axial Booms ICD are signed off. Verification Matrices to be completed.
IN-23 The Instrument Payload shall verify performance requirements are met per the THEMIS Verification Plan and Environmental Test Spec.
Compliance. THM-SYS-005 Verification Plan and Environmental Test Specification preliminary draft. Verification matrix to be completed.
IN-24 The Instrument Payload shall survive and function prior, during and after exposure to the environments described in the THEMIS Verification Plan and Environmental Test Specification
Compliance. THM-SYS-005 Verification Plan and Environmental Test Specification preliminary draft. Verification matrix to be completed.
Mission Requirements
THEMIS MISSION PDR/CAR EFI-8 UCB, November 12-14, 2003
REQUIREMENT EFI DESIGN
IN.EFI-1. The EFI shall determine the 2D spin plane electric field at the times of onset at 8-10 Re.
Compliance. Via compliance with IN.EFI-5 and -13.
IN.EFI-2. The EFI shall determine the dawn/dusk electric field at 18-30 Re.
Compliance. Via compliance with IN.EFI-5 and -13.
IN.EFI-3. The EFI shall measure the 3D wave electric field in the frequency range 1-600Hz at the times of onset at 8-10 Re.
Compliance. Via compliance with IN.EFI-6, -8, -9, -10, and –11.
IN.EFI-4. The EFI shall measure the waves at frequencies up to the electron cyclotron frequency that may be responsible for electron acceleration in the radiation belt.
Compliance. Via compliance with IN.EFI-6, -8, -9, -10, and –11.
Science Requirements
THEMIS MISSION PDR/CAR EFI-9 UCB, November 12-14, 2003
REQUIREMENT EFI DESIGN
IN.EFI-5. The EFI shall measure the 2D spin plane DC E-field with a time resolution of 10 seconds.
Compliance. On-board spin-fit of spin plane E-field at 3-s (one-spin) resolution.
IN.EFI-6. The EFI shall measure the 3D AC E-field from 1 Hz to 4kHz.
Compliance. 3-axis E-field measurement sampled at 8 ksamp/s. See AC Error Budget. Verified through Calibration.
IN.EFI-7. The EFI shall measure the Spacecraft Potential with a time resolution better than the spin rate (3 seconds; from ESA to compute moments).
Compliance. On-board spin-avg’d sphere potentials at 3-s (spin-rate) resolution; EFI data rate allocation includes single spheres at ¼-rate of E-field data.
IN.EFI-8. The EFI DFT Spectra Range shall be 16Hz to 4kHz, with df/f~25%.
Compliance. Spectral products from DFB cover 8 Hz to 8 kHz at 5%, 10%, or 20% BW (16, 32, or 64 bins)
IN.EFI-9. The EFI shall measure DC-coupled signals of amplitude up to 300 mV/m with 16-bit resolution.
Compliance. Analog gain and ADC resolution of DFB set accordingly. Verified through Calibration.
IN.EFI-10. The EFI shall measure AC-coupled signals of amplitude up to 50 mV/m (TBR) with 16-bit resolution.
Compliance. Analog gain and ADC resolution of DFB set accordingly. Verified through Calibration.
Performance Requirements
THEMIS MISSION PDR/CAR EFI-10 UCB, November 12-14, 2003
REQUIREMENT EFI DESIGN
IN.EFI-11. The EFI noise level shall be below 10-4 (mV/m)/Hz1/2.
Compliance. Low-noise preamp chosen (OP-15); good analog design practices throughout preamp, BEB and DFB; CBE is 3x10-5 on AXB, 3x10-6 on SPB. Verified through ETU testing.
IN.EFI-12. The EFI HF RMS (Log power) measurement shall cover 100-500 kHz with a minimum time resolution of the spin rate (on-board triggers).
Compliance. CBE of EFI response has gain of 0.8 out to 1 MHz; DFB provides HF-RMS at 1/16 to 8 samp/s.
IN.EFI-13. The EFI shall achieve an accuracy better than 10% or 1 mV/m in the SC XY E-field components during times of onset.
Compliance. See DC Error Budget Discussion.
Performance Requirements
THEMIS MISSION PDR/CAR EFI-11 UCB, November 12-14, 2003
REQUIREMENT EFI DESIGN
DFB FUNCTIONAL REQUIREMENTS
IN.DPU-36. The IDPU DFB shall provide an FFT solution for determining the parallel and perpendicular components of E and B in both fast survey and burst modes and produce spectra for each quantity separately.
Compliance. DFB design includes FPGA-based projection (E dot B, E cross B) and FFT solutions. Verified through Test and Calibration of ETU.
IN.DPU-37. The IDPU DFB shall integrate FGM digital data and EFI data to produce E·B
Compliance. DFB design includes FPGA-based projection ( E dot B, E cross B) solutions. Verified through Test and Calibration of ETU.
EFI Board Requirements
THEMIS MISSION PDR/CAR EFI-12 UCB, November 12-14, 2003
REQUIREMENT EFI DESIGN
BEB FUNCTIONAL REQUIREMENTS
IN.DPU-38. The IDPU BEB shall provide sensor biasing circuitry, stub and guard voltage control, and boom deployment for the EFI.
Compliance. The BEB design provides 3 independent bias channels per sensor (BIAS,GUARD,USHER) and one shared bias channel for the SPB sensors (BRAID). Boom deployment is provided through the IDPU/PCB and DCB.
IN.DPU-39. The IDPU BEB shall distribute a floating ground power supply to the EFI sensors.
Compliance. The BEB design provides 6 independent floating grounds to the LVPS, and distributes the derived +/-10-V analog supplies to the six EFI sensors.
IN.DPU-40. The IDPU BEB shall generate six independent BIAS, GUARD and USHER voltages with an accuracy of 0.1% for distribution to the EFI sensors.
Compliance. The BEB design includes matched gain-setting components, along with >12-bit DAC, allowing accuracy of better than 0.1%; Verified through Test and Calibration of ETU.
EFI Board Requirements
THEMIS MISSION PDR/CAR EFI-13 UCB, November 12-14, 2003
REQUIREMENT EFI DESIGN
IN.BOOM-5a. Deployed EFI Axials shall be repeatable and stable to = 1 degree and L/L = 1%.
Compliance. Adequate stiffness and angular alignment of AXB stacers and deploy system included in design; verified by testing of ETU.
IN.BOOM-5b. Deployed EFI Radials shall be repeatable and stable to = 1 degree and L/L = 1%.
Compliance. Proper SPB cable design (stiffness, tempco) along with std. Cable winding procedures included in design; verified by testing of ETU.
IN.BOOM-6. EFI Axial Booms shall be designed to be deployed between 2 and 25 RPM about the Probe's positive Z axis.
Compliance. Adequate stiffness and angular alignment of AXB stacers included in design; verified by testing of ETU.
IN.BOOM-7. EFI Radial Booms shall be designed to be deployed between 2 and 25 RPM.
Compliance. Adequate strength margins on cable included in design; verified by proof-loading of cable and testing of ETU.
IN.BOOM-8. EFI Axial Booms deployed stiffness shall be greater than 0.75 Hz (1st mode).
Compliance. Part of AXB stacer spec; verified by Testing of ETU.
IN.BOOM-12. All deployed booms shall include TBD inhibits to prevent inadvertent release.
Compliance. Test/Enable plugs included in design. Red tag door (SPB) and tube (AXB) covers.
EFI Boom Requirements
THEMIS MISSION PDR/CAR EFI-14 UCB, November 12-14, 2003
EFI Block Diagram
A High-Input Impedance Low-Noise Voltmeter in Space
sensor
preamp
sheath
Floating groundgeneration
Bias channels
BIAS
USHERGUARD
BRAID VBraid
Vref
VBraidCtrl
THEMIS MISSION PDR/CAR EFI-15 UCB, November 12-14, 2003
Top-Level Design (1)
Diagram of THEMIS EFI Elements
THEMIS MISSION PDR/CAR EFI-16 UCB, November 12-14, 2003
Top-Level Design (2)
Description of THEMIS EFI Elements• Three-axis E-field measurement, drawing on 30 years of
mechanical and electrical design heritage at UCBSSL.• Closest living relatives are Cluster, Polar and FAST, with parts
heritage from CRRES (mechanical systems, BEB designs, preamp designs).
THEMIS MISSION PDR/CAR EFI-17 UCB, November 12-14, 2003
Radial Booms
Description of THEMIS EFI Elements• Radial booms:
• 20.8 to 27.8 m long.
• 8-cm dia., DAG-213 or Ti-N-coated spherical sensor.
• 3-m fine wire to preamp enclosure.
• USHER and GUARD bias surfaces integral to preamp enclosure.
• BRAID bias surface of 3 to 6-m length prior to preamp (common between all 4 radial booms).
• Sensor is grounded through 10 Mohm (TBR) resistance when stowed, providing ESD protection and allowing for internal DC and AC functional tests.
• External test/safe plug (motor,door actuator,turns click, ACTEST) to allow for deploy testing/enabling and external signal injection.
THEMIS MISSION PDR/CAR EFI-18 UCB, November 12-14, 2003
Axial Booms
Description of THEMIS EFI Elements• Axial booms:
• 4-m stacer with ~1-m DAG-213-coated whip stacer sensor.
• Preamp mounted in-line, between stacer and sensor.
• USHER and GUARD bias surfaces integral to preamp enclosure.
• No BRAID bias surface.
• Sensor is grounded through TBD Mohm resistance when stowed, providing ESD protection and allowing for internal DC and AC functional tests.
• External test/safe plug (deploy actuator, ACTEST) to allow for deploy testing/safing and external signal injection.
THEMIS MISSION PDR/CAR EFI-19 UCB, November 12-14, 2003
Performance Specification
Performance Specification• EFI radial sensor baseline will be 41.6 m, tip-to-tip.
• EFI axial sensor baseline will be ~10 m, tip-to-tip.
• 16-bit resolution.
• Spacecraft potential: +/- 60 V, 1.8 mV resolution, better than 46 uV/m resolution (allows ground reconstruction of E from spacecraft potential to better than 0.1 mV/m resolution).
• DC-coupled E-field: +/- 300 mV/m, 9 uV/m resolution.
• AC-coupled E-field: +/- 50 mV/m, 1.5 uV/m resolution.
• AKR log(Power) channel: <= 70 uV/m amplitude, 100-500 kHz bandwidth.
THEMIS MISSION PDR/CAR EFI-20 UCB, November 12-14, 2003
DFB Functional Block Diagram
AXIALBOOMS
RADIALBOOMS
EF1
EF2
EF3
EF4
EF5
EF6
SEARCHCOIL
SCM1
SCM2
SCM3
V6
V5
V4
V3
V2
V1
E12
E34
E56
E12AC
E34AC
E56AC
SC1
SC2
SC3
MUX16:1
ADC
ADC
FPGADSP Logic
DATA
COMMAND
1 PPS
±10V
±5V
+5V
+2.5V
Ba
ck
pla
ne
I/F
SCM ±10V
8MHzClk
SCM Control
Digital Fields PWBStandard 6U Card
Micro-D
6 X SMA
E12logRMS
SCM ±10V
SCM Control
FGM4KHz
10Hz - 4KHz
100KHz - 500KHz
THEMIS MISSION PDR/CAR EFI-21 UCB, November 12-14, 2003
DFB Data Flow Block Diagram
Spin-fit Filters:- E12, E34, E56,V1, V2, V3, V4- 50 Hz Filter- 128 S/s output
Efit (ID64)
FB #1 (6 bands)
Vfit (ID64)
VAFS (ID67)VBFS (ID68)
EFS (ID69)SCMFS (ID70)
VAPB (ID71)VBPB (ID72)
EPB (ID73)SCMPB (ID74)
VAWB (ID75)VBWB (ID76)EWB (ID77)
SCMWB (ID78)
SelectionLogic
16 analog dataquantities:V1, V2, V3,V4, V5, V6,E12, E34, E56,E12AC, E34AC,E56AC,E12logRMS,SC1, SC2, SC3
A/D #1128kS/s
A/D #2128kS/s
A/D routing256kS/s
Filter banks:- Any two inputs- 11 frequencies- output from 1/16to 16 S/s
AKR (LogRMS)signal
8-bit psuedo-logcompressor
ExB unit
Fast Survey Filters- All V, E, SCM- 0.8 - 100 Hz Filter- 2 -256 S/s
Particle Burst Filters- All V, E, SCM- 0.8 - 100 Hz Filter- 2 -256 S/s
Wave Burst Filters
FFT Unit
8-bit psuedo-logcompressor
Spec2 (ID81)Spec1 (ID81)
Spec4 (ID81)Spec3 (ID81)
Spec2 (ID80)
Spec1 (ID80)
Spec4 (ID80)Spec3 (ID80)
HFAve (ID65)
HFPeak (ID65)
Fbank1 (ID66)
Fbank2 (ID66)
FbankT2 (ID65)
FbankT1 (ID65)
FB #2 (6 bands)
FB #1 (All 11 bands)
FB #2 (All 11 bands)
Below Line is OnDuring FastSurvey Only
Above Line isAlways On
THEMIS MISSION PDR/CAR EFI-22 UCB, November 12-14, 2003
EFI Data Rates
Data Rates• Slow Survey
• Spin-fit radial and axial E-fields; SC potential (via ptcls).
• Filter Banks.
• Fast Survey• 3 E-field at 32 samp/spin; 2-3 sphere potentials at 8 samp/spin.
• Filter Banks and FFT spectra.
• Particle Burst• 3 E-field at 128 samp/s; 2-3 sphere potentials at 32 samp/s.
• Filter Banks and FFT spectra.
• Wave Burst• 3 E-field at 1024 or 4096 samp/s; 2-3 sphere potentials at 256 or
1024 samp/s.
• Filter Banks and FFT spectra.
• Diagnostic Mode (TBR)• E-field and sphere potentials at >= 32 samp/s.
• Bias control levels at >= 1 samp/s.
THEMIS MISSION PDR/CAR EFI-23 UCB, November 12-14, 2003
Individual Design Elements
• Radial Boom Unit (Spin-Plane Boom, or SPB)
• Boom Motor Driver Board (BMD)
• Axial Boom Unit (AXB)
• AXB and SPB Thermal Modeling
• Preamp (Mechanical and Electrical)
• Boom Electronics Board (BEB)
• Digital Fields Board (DFB; see Top-Level Design)
• GSE (Mechanical and Electrical)
THEMIS MISSION PDR/CAR EFI-24 UCB, November 12-14, 2003
SPB Design Overview
4 x Attach Legs with G10 Spacers for Thermal Isolation
Brushless Gearmotor
With Bevel Gears
Meter Wheel
Base
(Magnesium)
Sphere and Preamp
Release Doors
(Spring Preloaded)
Main Wire Spool
Exit Tube
THEMIS MISSION PDR/CAR EFI-25 UCB, November 12-14, 2003
Customization of Design for THEMIS Use
Wire Length• Increased to 18 m; capability of 25 m.
Packaging for mounting to THEMIS Probe
Structure Attachment• Magnesium replaced 6061 Al for weight savings
Sphere Coating• Titanium Nitride may replace DAG 213
DC Gearmotor• Same Motor Manufacturer (Globe Motors)• Similar Performance (300 ounce-inches Torque)• Brushless Unit Selected over Brushed
• Brushless better design in vacuum
• Better Thermal Characteristics
• Less Stray Magnetic Field
• Higher Performance in smaller package
• New Electronics Drive Package Required (BMD)• Designed in-house
• Prototype up-and-running 5 weeks without problems
THEMIS MISSION PDR/CAR EFI-26 UCB, November 12-14, 2003
Theory of OperationIntegration and Launch
• Stowed and Unpowered• Wire Wound about Spool, constrained by pinch wheels• Release Doors Closed• Sphere/Pre-Amp Constrained by Release Doors
Deployment• Release Doors Opened via SMA Pin-Puller• Spin of S/C puts outward force on Sphere and Preamp• Motor Acts as brake to prevent motion; coaxial wire in tension• Motor powers rotation of Meter Wheel • Sphere and Preamp is payed out • Release Doors Close Back Around Wire• As Centrifugal Force exceeds 2G at Sphere, Sphere Key Reel Spring
force is overcome and Sphere moves away from Preamp• Monitoring
• Limit Switch on Shaft counting Rotations• Tension Sensor to sense High Tensile Force
Science Ops• Deployed Booms Configuration Unchanged
THEMIS MISSION PDR/CAR EFI-27 UCB, November 12-14, 2003
Theory of Operation
Meter Wheel
Preamp
Motor
Main Wire Spool
Pinch Rollers
Release Doors
Sphere
Motor Drive Electronics
THEMIS MISSION PDR/CAR EFI-28 UCB, November 12-14, 2003
Materials and Construction
Standard UCB Construction• Most Components Machined Aluminum
• 6061 T6 and 7075 T73
• Alodined and Anodized
• Machined Plastics• PEEK
• Machined Magnesium Alloy AZ31B• Chosen for Weight Relief in Structure
• Not MSFC-SPEC-522 High Resistance to SCC– Table II ‘Moderate Resistance’– Requires MUA for use
Thermal Treatments• Surfaces covered with VDA tape or blankets• No Heaters Required
Common manufacturing techniques used • No Unusually Tight Tolerances • No Difficult Fabrications
THEMIS MISSION PDR/CAR EFI-29 UCB, November 12-14, 2003
BMD Requirements:• Brushless DC Motor driver
• Sense rotor position with Hall Effect devices
• Drive stator coils based on commutation logic
• Supply voltage: 28 ± 6 Volts
• Load current: ~300 mA
• Higher radiation environment than IDPU (100-kRad)
• Short term exposure (6 months)
SPB Boom Motor Driver (BMD)
THEMIS MISSION PDR/CAR EFI-30 UCB, November 12-14, 2003
Motor Driver Board
Brushless Gearmotor
BMD Block Diagram
THEMIS MISSION PDR/CAR EFI-31 UCB, November 12-14, 2003
Axial Boom (AXB) Overview
AXB are integral part of THEMIS probe• Primary probe structure provided by Swales Aerospace• AXB located along center axis of probe• AXB deployment through top and bottom decks of
probe.
Test & Safe Plug
Lower Deck Mount
Composite Tube
Antennae Mount (TBD by Swales)
AXB relative to THEMIS Probe Internal View
AXB Assembly
THEMIS Probe
Upper Deck Mount
Upper AXB
Lower AXB
AXB Housing
THEMIS MISSION PDR/CAR EFI-32 UCB, November 12-14, 2003
Axial Boom General Assembly
Whip Canister (Whip Sensor Inside)
Double Deploy Assist Device
(“DDAD”)
Tube Mounting Brackets
Preamp
Cable Bobbin
Stacer Canister (Stacer inside)
INDIVIDUAL BOOM IN STOWED CONFIGURATION
Frangibolt Actuator (inside)
Whip Doors
DDAD Doors
STACER
Design Modifications• Stacer Length• Double Deploy Assist Device• SMA Frangibolt Actuation• Whip Sensor
Roller Nozzles
Whip Posts
THEMIS MISSION PDR/CAR EFI-33 UCB, November 12-14, 2003
AXB Theory of OperationIntegration & Loading
• Whip Sensor is loaded into whip canister• Whip canister is locked to the preamp by the whip clamp• Stacer is loaded into stacer canister, DDAD doors hold the DDAD, and
whip doors hold the whip canister• Removable stacer pin is inserted through stacer tip piece, which locks the
stacer, DDAD, and Whip canister to the boom assembly• Cable is spooled around the cable bobbin• Stacer actuation bolt is threaded into Stacer tip piece and Frangibolt
actuator is slid over bolt and screwed tight with nut.• Stacer pin and whip clamp are removed• Boom is loaded into housing
Deployment• SMA Frangibolt is actuated and actuation bolt is broken.• Stacer tip piece is released• DDAD extends and initiates stacer deployment• DDAD separation opens whip doors, initiating whip sensor deployment
Science Ops• Deployed boom configuration unchanged
THEMIS MISSION PDR/CAR EFI-34 UCB, November 12-14, 2003
Whip Sensor
Deployed Properties• Whip sensor deployed length: 40 inches • Stacer deployed length: 150 inches
Stacer
Frangibolt ActuatorCable Bobbin with Cable
DDAD
DDAD Doors
Stowed Boom Deployed DDAD
4”
4”
Stacer Canister
Stacer Tip Piece
Whip Canister
Whip Doors
Roller Nozzle
Deployed Boom
Deployed Whip Sensor
150”
40”
Theory of Operation
THEMIS MISSION PDR/CAR EFI-35 UCB, November 12-14, 2003
AXB Assembly & Materials
Standard Flight Materials• AL 6061 T6, SST 440, Eligiloy, PEEK, M55J Graphite
Composite.
Standard Flight Coatings• DAG-213, DAG-154, Type 3 Hard Anodize.
Long Lead Items (see Schedule and Procurement)• Stacers, Multi-conductor wire, FrangiBolts.
THEMIS MISSION PDR/CAR EFI-36 UCB, November 12-14, 2003
SPB and AXB Thermal (1)Heat Transfer
• 80 mW dissipated at preamp irrelevant to bus temperatures.
• Essentially inert hunks of metal after deployment
• Long eclipse temperatures:
• Top deck, -93 C.
• Bottom deck, -36 C.
• Preamp, -170 C.
• AXB and SPB are heat leaks for bottom deck, and are isolated with 1/8-th inch G10 spacers.
• All surfaces covered with low e VDA tape or blankets.
• External snout of SPB dominates its heat leak; black-body open end of AXB tube dominates its heat leak.
Monitoring and Control• Probe bus monitors near one SPB; no monitoring on AXB.
• No thermistors in preamp.
• No operational heaters required.
• No survival heaters needed after deploy.
• Unlikely to need deploy heaters.
THEMIS MISSION PDR/CAR EFI-37 UCB, November 12-14, 2003
SPB and AXB Thermal (2)
AXB/SPB Limits (°C)
Predictions
(°C)
Margin
(°C)
Cold Hot Cold Hot
Deployment 0 30 8/-17 35/36 8/-17 -5/-6
Pre-Amp 52 -130
•Steady state prediction based on deck temperature from Swales•Cold prediction from cold orbit, not long eclipse.•Hot prediction from hottest orbit and attitude.
•Will not deploy in extreme hot or cold cases.•Better predictions await more complete instrument thermal models.
THEMIS MISSION PDR/CAR EFI-38 UCB, November 12-14, 2003
• Evolution of CLUSTER-II sphere/”puck” design
• Simple design, flight-proven components
3m thin wire, d ~10 mil
sphere, d ~8 cm
Preamp Housing, d ~2.3 cm
3m
Preamp Housing, d ~2.3 cm
1 m
Preamp and Sensor Geometry
THEMIS MISSION PDR/CAR EFI-39 UCB, November 12-14, 2003
Preamp Requirements
DC - 500 kHz
DC: Coupling impedances up to 10,000 M.
AC: Minimize capacitive voltage division (low input capacitance)• Radial Ccoupling ~13 pF, Axial Ccoupling ~6.5 pF
Wide temperature range (+100-370º K)
Survive high radiation exposure (~750 kRad/year behind 1 mm of Al)
THEMIS MISSION PDR/CAR EFI-40 UCB, November 12-14, 2003
Preamplifier Mechanical Design
Goal: Minimize preamp-sphere interference
(shadowing, photoelectrons, potential geometry…)
Cable Holder
Peek Stub
Socket HolderCan Shield Can Isolator
(optional) PC BoardWave Spring
0-80 Flat HeadScrew
Ferrule
Fuzz Button
Top
Pin (Keystone)BottomSocket (Hypertronic)
Guard
Front Shield
TO-99Screw Fitting
THEMIS MISSION PDR/CAR EFI-41 UCB, November 12-14, 2003
Sphere Preamplifier SensorElectronics Design
±40 V
THEMIS MISSION PDR/CAR EFI-42 UCB, November 12-14, 2003
Preamplifier IC
Op-Amp: OP-15AJ
MIL-STD 883, CRRES Heritage
Rin ~1012 ohms, Cin ~3 pF
Low Power Dissipation (<80 mW)
Internally compensated, unity-gain stable
Capability to drive capacitive loads (>4000 pF)
40 kRADs with little performance degradation (satisfied behind ~7 mm Al over two years)
THEMIS MISSION PDR/CAR EFI-43 UCB, November 12-14, 2003
Functional Requirements• Spin Plane Booms, for each provide:
• Floating Ground Driver• “Bias”, “Stub”, “Usher” programmable potentials• “Braid” programmable, switchable potential• AC test signal source
• Axial Booms, for each provide:• Floating Ground Driver• “Bias”, “Stub”, “Usher” programmable potentials• AC test signal source
BEB Requirements
THEMIS MISSION PDR/CAR EFI-44 UCB, November 12-14, 2003
Preamp Signal CharacteristicsDC voltage level: ± 60Vdc w.r.t. AGNDAC voltage level: 12 VppAC frequency band: DC – 500kHz
Floating Ground Driver SpecificationsInput: Preamp signal (VSPHERE)Input filter: 300 Hz (3dB)Output voltage level: ± 60Vdc w.r.t. AGNDOutput: References floating ground supply (± 10Vdc)
Bias, Usher, Guard SpecificationReference Input: Preamp signal (VSPHERE)Reference Input filter: 300 Hz (3dB)
Vref ± 40Vdc w.r.t. AGND, where FS DAC == Vref + 40Vdc
DAC resolution: 1 nA (12-bit DAC == 0.65 nA resolution on Bias)DAC accuracy: Opposing booms matched to 0.1%DAC step response: < 10 ms (For information only)
EE PartsSelection / Derating / Radiation / Gen'l. Specs
IAW Themis Product Assurance Implementation Plan (PAIP)
Output voltage level:
BEB Requirements (con’t)
THEMIS MISSION PDR/CAR EFI-45 UCB, November 12-14, 2003
Bias Driver
Vin
+100VA
+10VA
-10VA
-100VA
AGND
Vsphere_Ref
Vout
+100VA
Vrefence ±40VDC
0 - 5V
Floating GND Driver
PreAmpIn
+100VA
+10VFloating
-10VFloating
-100VA
FloatingGND
AGND
VSphere
Vrefence ±40VDC
-10VBus
Power Filter
+10Floating
Floa
tingG
ND
-10Vin
-10Floating
+100Vin
-100V
+100V
-100Vin
+10Vin
AGND
+10FltVin
-10FltVin
+10V
-10V
-100VBus
±60VDC
Vrefence ±40VDCfreq
+100VBus
0 - 5V
0 - 5V
+10FltVout
Guard
+10FltVin
BiasControl
-10VFltVout
Bias
freq
freq
+10VA+10VBus
freq
-10FltVin
freq
-100VA
Guard Driver
Vin
+100VA
+10VA
-10VA
-100VA
AGND
Vsphere_Ref
Vout
Usher Driver
Vin
+100VA
+10VA
-10VA
-100VA
AGND
Vsphere_Ref
VoutUsherControl
FloatGNDfreqPreAmp In
freq
Usher
freq
-10VA
±60VDC12Vpp AC (to 500kHz)
GuardControl
AGND
BEB Analog Electronics
THEMIS MISSION PDR/CAR EFI-46 UCB, November 12-14, 2003
EFI_
P10V
A
EFI_P100VA
BR AID 1
FV1_P10VA
J 501
D D 26F
1234567891011121314151617181920212223242526
EFI_C LK
SH IELD 3
BEB_H SKP
10M
FV6_GN DFV6_M10VA
J 512
AGN D
U SH ER 5
Analog Mux
+10V
IN
AGN D
-10V
IN
D GN D
+5VD
BIAS
1CU
SHER
1CG
UAR
D1C
BIAS
2CU
SHER
2CG
UAR
D2C
BIAS
3CU
SHER
3CG
UAR
D3C
BIAS
4CU
SHER
4CG
UAR
D4C
VOU
T
Se lec t3Selec t2Selec t1Selec t0
USH
ER6C
USH
ER5C
BIAS
6C
GU
ARD
5C
GU
ARD
6C
BIAS
5C
Se lec t4
Tem
pA
Tem
pB
AC TEST6
P500
123456789
1011121314151617181920212223242526272829303132333435363738394041424344454647484950
1234567891011121314151617181920212223242526272829303132333435363738394041424344454647484950
U SH ER 2 FV4_GN D
SH IELD 2
GU AR D 5
EFI_P10VA
BackPlane
BIAS1U SH ER 1
FVF3_P10VA
EFI_P10VA
BR AID 4
U SH ER 4BR AID 2
t
TH ER MISTOR
GU AR D 3
Front Panel
EFI_M10VA
EFI_M10VA
GU AR D 2
BR AID 1
EFI_P100VA
FV1_M10VA
FV4_P10VA
AC TEST3
BIAS5
J 515
U SH ER 6
BR AID 5
FVF1_M10VA
BIAS2
AC TEST2
GU AR D 1
EFI_P10VA
EFI_
M10
VA
FV5_M10VA
FVF5_M10VA
FVF1_P10VA
VSPH ER E3
J 516
VSPH ER E4
10M
VSPH ER E6
BR AID 3
FV6_P10VA
SH IELD 4
VSPH ER E5
FV2_GN DFV2_M10VA
FV1_GN D
EFI_M100VA
EFI_M100VA
BR AID 6
FV5_P10VA
AC TEST1
FV1_M10VA
FVF6_M10VA
J 513
EFI_P100VA
FV2_P10VA
Same TreatmentChannels 3/4Channels 5/6
Braid Driver
BREF
1_R
ESET
BREF
1_SE
TBR
EF0_
RES
ETBR
EF0_
SET
V3_IN
V1_IN
BSEL
_RES
ETBS
EL_S
ET
BR AID 1
BR AID 2
BR IAD 3
BR AID 4
+100VBus
+10VBus
-10VBus
-100VBus
AGN
D
Brai
dCon
trolU SH ER 3
VSPH ER E1
GU AR D 4
FVF2_M10VA
EFI_C MD
FV5_GN D
J 514
FV3_GN D
SH IELD 6
EFI_D GN D
FV3_P10VA
FV4_M10VA
BIAS4
FVF5_P10VA
EFI_
VP5D
VSPH ER E3
Control Block
C LK
C MD
BIAS1C
U SH ER 1C
GU AR D 1C
BIAS2C
U SH ER 2C
GU AR D 2C
BIAS3CU SH ER 3CGU AR D 3C
BIAS4CU SH ER 4CGU AR D 4C
BIAS5CU SH ER 5CGU AR D 5C
BIAS6CU SH ER 6CGU AR D 6C
+5V
D GN D
AC TEST1AC TEST2AC TEST3AC TEST4AC TEST5AC TEST6
MSE
L0M
SEL1
MSE
L2M
SEL3
BR AID C
+2.5V
MSE
L4
BR EF0_SET
BR EF1_SET
BSEL_SET
BR EF0_R ESET
BR EF1_R ESET
BSEL_R ESET
FVF4_M10VA
BR AID 4
FV1_P10VA
AC TEST5
Channel 1
PreAmp In
+100
VBus
+10FltVin
-10FltVin
-100
VBus
+10V
Bus
-10V
Bus
AGN
D
GuardC ontro l
Bias C ontro l
U s herC ontro l
FloatGN D
Bias
U s her
Guard
+10FltVout
-10VFltVout
FV3_M10VA
AC TEST4
J 502
D D 26F
1234567891011121314151617181920212223242526
FVF2_P10VA
EFI_M100VA
EFI_VP2.5D
AGN D
FV2_P10VA
FVF4_P10VA
BIAS3
GU AR D 6
BR AID 2
FVF6_P10VA
VSPH ER E1
SH IELD 1
VSPH ER E2
J 503
D D 26F
1234567891011121314151617181920212223242526
FVF3_M10VA
SH IELD 5
BR AID 3
EFI_D GN D
EFI_M10VA
FV1_GN D
BIAS6
J 511
Channel 2
PreAmp In
+100
VBus
+10FltVin
-10FltVin
-100
VBus
+10V
Bus
-10V
Bus
AGN
D
GuardC ontro l
Bias C ontro l
U s herC ontro l
FloatGN D
Bias
U s her
Guard
+10FltVout
-10VFltVout
EFI_P100VA
EFI_P10VA
FV2_GN D
EFI_VP5D
FV2_M10VA
BEB Block Diagram
THEMIS MISSION PDR/CAR EFI-47 UCB, November 12-14, 2003
+10VA
+10VA
10K
BSEL_RESET
+100VA
+100VBus
10K
10K
10K
10M
V3_IN
-10VA
+10VA
AGND
+10VA
BREF0_SET
+100VA
421D
-100VA
Q1
2N2222A
Q1
2N2222A
+10VBus
-100VBus
+10VA10M
BRAID1
421D
BSEL_SET
BRAID4
BREF0_RESET
BRIAD3
BREF1_SET
10K
10M
V1_IN
10M
BREF1_RESET
Q2
2N2222A
421D
Braid Driver
Vin
+100VA
+10VA
-10VA
-100VA AGND
Vsphere_Ref
Vout
10K
Power Filter
-10Vin
+100Vin
-100V
+100V
-100Vin
+10Vin
AGND
+10V
-10V-10VBus
BraidControl
-10VA
Q2
2N2222A
Q1
2N2222A
10M
-100VA
Q2
2N2222A
BRAID2
1M
BEB Braid Bias
THEMIS MISSION PDR/CAR EFI-48 UCB, November 12-14, 2003
Mechanical GSE Requirements
Functional Requirements• Provide for simulation of actuators and motors during
functional tests, FSW testing, etc.
• Connect through test/enable plugs on SPBs and AXB pair.
THEMIS MISSION PDR/CAR EFI-49 UCB, November 12-14, 2003
Electrical GSE
Block Diagram of EFI/BEB GSE
THEMIS MISSION PDR/CAR EFI-50 UCB, November 12-14, 2003
Electrical GSE Requirements (1)
Power/Thermal/Mechanical• Provide regulated voltages.
• Facilitate current measurements.
• 6U VME support (w/out Wedgelocks) for BEB.
• Portable and rugged for transport.
• Open rack for access while under test.
• Connectors acceptable for Flight interconnection
Electrical Interface• Backplane interface per IDPU backplane specification.
• 1 MUX’d analog housekeeping output (ANA HSK).
• GSE interface circuitry must be flight-grade.
THEMIS MISSION PDR/CAR EFI-51 UCB, November 12-14, 2003
Electrical GSE Requirements (2)
Command and Telemetry Handling• GSE sends 24-bit CDI commands per ICD specification.
• Command format is compatible with IDPU and MOC GSE (TBD).
• Before DFB and DCB, data is from GSE’s IEEE-1394 ADC.
• Afterwards data is extracted from telemetry.
Test Support Equipment• GSE controls GPIB function generator and +/- 100-V
supplies.
• “Faraday cage”-type test fixture (pairs for SPB and AXB).
Compatibility with Next Level of Integration• Uses ITOS, Matlab (or equiv), C.
• PC standards.
• Easy accessibility to data for offline processing (FTP, HTTP, etc.).
THEMIS MISSION PDR/CAR EFI-52 UCB, November 12-14, 2003
Electrical GSE Requirements (3)
Data Manipulation and Display• Plot any of 16 channels over user-specified timespan.
• Calculate 2N-point FFT on user-specified channels.
• Compute and display power spectra and transfer functions of user-specified channels.
• Display control values for GPIB and GSE interface equipment.
• Support hardcopy output.
• Raw and derived data, as well as configuration information stored in tabular ASCII format file.
• Data manipulation and display scriptable to allow for automation of test and cal procedures.
THEMIS MISSION PDR/CAR EFI-53 UCB, November 12-14, 2003
DC Error Budget (1)
The estimated electric field along the direction between the two probes is E=(v1-v2)/2L.
Errors arise from and are mitigated by:• Errors in baseline (L).• Errors in v1 and v2; eg. (v1-v2) or each individually.
THEMIS MISSION PDR/CAR EFI-54 UCB, November 12-14, 2003
DC Error Budget (2)
Errors in baseline (L).• Fly as long of booms as possible, given resources (41.6-m
baseline, ~55-m possible w/in mass resources).• Control boom length to 1%.• Trim deploy length to 4-cm accuracy to allow for electrical center
offsets (AXB in particular).• Increase fine wire length to reduce boom shorting effect
(observed up to 20% on Cluster; predicted 5% on THEMIS (better Lf/L)).
• Fly dual-length system to allow for differentiation between geophysical and SC fields.
THEMIS MISSION PDR/CAR EFI-55 UCB, November 12-14, 2003
DC Error Budget (3)Errors in v1 and v2; eg. (v1-v2) or each individually.
• Use TI-N or DAG-213 coating on sensors for uniform photoemission. Keep all sensors clean pre-launch.
• Use high-impedance preamp (1012 ohm) to reduce DC attenuation.
• Current-bias sensor to reduce sheath impedance and susceptibility to photoemission asymmetries (20-100 Mohm typ.; 0.2-0.5 mV/m SPB systematic).
• Mount sensor on fine wire and reduce emission area of preamp to reduce magnitude and effect of asymmetric photoemission (3-10 times smaller than Cluster; < 0.5 mV/m SPB systematic).
• Use USHER and GUARD surfaces to control photocurrents to sensor (>= 20-V bias range, well above bulk of photoelectron energies).
• Use fine wire and BRAID bias surface to reduce ES wake effects (scale with D/L or 1/L; roughly equivalent to Cluster). Fly dual-length SPB system to detect ES wake effects.
• Enforce 1.0-V electrostatic cleanliness specification on THEMIS to reduce SC potential asymmetry effects to < 0.1 mV/m on SPB; 0.1-V goal reduces AXB effects to this level as well.
THEMIS MISSION PDR/CAR EFI-56 UCB, November 12-14, 2003
AC Error Budget
EFI Spectral Coverage and System Noise Estimates
AKR band
CDI
BBF
Preamp and Rbias
Current Noise
Preamp VoltageNoise
axial
radial
Maximum Spectra(DC-Coupled)
1-LSB Spectra(DC-Coupled)
flat
1/f
1/f3
Spinfrequency
4-kHzAnti-aliasing roll-off
10-HzAc-coupled roll-in
THEMIS MISSION PDR/CAR EFI-57 UCB, November 12-14, 2003
Schedule (1)
Design (Definition and BB)• Preamp Mechanical (Aug-Oct ’03; complete).
• Preamp Electrical (Aug-Oct ’03; complete).
• BEB (Jul-Oct ’03; complete).
• BMD (Sep ’03; complete).
• SPB (Aug ’03 – Nov ‘03; freezing design Nov 21).
• AXB (Jun ’03 – Dec ’03; freezing design Nov 14).
• DFB (Aug ’03- Dec ’03; 50%).
THEMIS MISSION PDR/CAR EFI-58 UCB, November 12-14, 2003
Schedule (2)
Long-Lead Parts• AXB stacers (ordered Sep ’03; delivery by 26 Dec ’03 (12-wk lead
time))• SPB wire cable (final RFQ issued 7 Nov; final order expected by
17 Nov; delivery by 15 Jan ’04)• FrangiBolt actuators (final RFQ issued 7 Nov; final order expected
by 17 Nov; early delivery of 3 units late Dec; remainder in late Jan ’04).
• SPB motors:• Original vendor on brushless motors (Avnet/Globe) returned with 21-
week, rather than 12-week lead time. This would push EFI F1 delivery back 3 months, leaving no schedule slack for delivery to II&T.
• Exploring two options:– New brushless vendor (MicroMo) with space-qualified pedigree. 12-wk
lead time (pushes F1 delivery back 1 month to 16 Jul ’04. Example ordered for validation Nov 17-21; order to follow if passes validation.
– Brush motors from Avnet/Globe. Original SPB design. 8-wk lead time (no schedule impact). Additional magnetic impact.
THEMIS MISSION PDR/CAR EFI-59 UCB, November 12-14, 2003
Schedule (3)
EM/ETU• SPB
• Mach, Dec ’03; Assy, Dec ’03 – Jan ’04; Test, Feb ’04.
• AXB• Mach, Dec ’03 – Jan ’04; Assy, Feb ’04; Test, Feb ’04.
• Preamp (Mechanical and Electrical)• Layout/Fab/Assy, Oct-Nov ’03; Test, Dec ’03.
• BEB• Layout/Fab, Nov-Dec ’03; Build, Dec ’03; Test, Dec ’03.
• BMD• Layout/Fab, Nov-Dec ’03; Build, Dec ’03; Test, Dec ’03.
• DFB• Layout/Fab, Jan-Mar ’04; Build, Mar ‘04; Test, Apr ‘04.
THEMIS MISSION PDR/CAR EFI-60 UCB, November 12-14, 2003
Summary of EPR Findings
•Radial Boom design (1,2,3,9; Draft findings, 3 Nov 2003):•Dynamic stability issues (spin/trans MOI ratio) (Bus EPR)•Dual-length/longer-length designs
•Axial Boom design (6,10):•Deploy force margin•Length vs. noise margin, whip vs. sphere sensors.
•Attitude information and jitter requirements (14).•Miscellaneous mechanical findings (15,18,5):
•Deploy sequence modeling.•Boom deployment temperature.•SPB miter gear life testing.
•Hot parts and thermal stresses•Gain and Filter Specifications of EFI and SCM on DFB (4,8,12).•BEB FPGA specification and programming (20).•Preamp electro-mechanical design (11).•Electrostatic Cleanliness Specification (RFA UCB-8)(7,17).•EMI/EMC Specification (RFA UCB-9)(13).•Detailed I&T plan development (RFA UCB-10)(19).
THEMIS MISSION PDR/CAR EFI-61 UCB, November 12-14, 2003
EPR Findings—Radial Booms
•Dynamic stability issues:•Bus and Instrument team analysis of dynamic stability not in accord; question is proper spin/transverse MOI ratio for non-rigid boom systems on THEMIS.•Swales analysis indicates shorter AXB (60%) or longer SPB required to achieve stable configuration (Bus EPR finding).
•Longer-length/Dual-length designs (science-driven):•56-m (2x(25+3)m system) tip-to-tip SPB possible with current mechanical design.•Direct improvement in DC error budget (30%).•Allows for dual-length (21/28 m) system that would allow the detection of ES wake effects (not mission critical, however).•Mass hit (56 g/SPB) for 7-m cable addition; fuel hit (~60%, 452 g increase) for final spin up.
•Resolution:•Must be resolved by Jan ’04 (EFI F1 Cable Assy); Cable Assy schedule margin allows push back to Apr ’04, if necessary.•Dynamic stability analysis is ongoing at Swales and UCB.
THEMIS MISSION PDR/CAR EFI-62 UCB, November 12-14, 2003
EPR Findings—Axial Booms
•Deploy force margin and AXB length repeatability:•AXB design may not have enough deploy force margin to ensure dL/L = 1% repeatability of deploy length.•Resolution: AXB ETU testing (Feb ’04).
•Length vs. Noise Margin; whip vs. sphere sensor response•Current AXB length (~9-m effective, 10-m tip-to-tip) allows only factor of 3 S/N margin at 4 kHz (CBE of system noise level).•SC perturbations will strongly affect DC E-field in AXB (several mV/m, dependent upon SC potential (plasma conditions).•AXB whip sensor may have different response para/perp to B than SPB sphere+wire sensor.•Resolution: AXB length can not be reduced significantly without compromising 3D AC measurement. AXB lengths will be trimmed based on simulation results to reduce DC offset due to SC potential (final length Feb ’04 (AXB F1 Mach)). Literature on antenna response to be investigated to determine significance of whip vs. sphere effect (no mitigation planned; different capacitance of SPB and AXB sensors already known, and part of electrical Calibration plan).
THEMIS MISSION PDR/CAR EFI-63 UCB, November 12-14, 2003
EPR Findings—Attitude
•Attitude knowledge and jitter requirements are modest, and achievable by Bus and Instrument designs.
•5.6 degree (10%) knowledge required; better than 1 degree (0.5%) achieved via post-processing of FGM and EFI data.•Better than 3-degree accuracy and jitter in spin phase required for accurate on-board spin fits of E-field data; current IDPU design provides much better than 0.1 degrees.
•Alignment requirements more stringent, driven by DC error budget of SPB.
•Opposing pairs of SPB booms must align within 1 degree to bring systematic error due to differential photoemission below 1 mV/m for nominal biasing scheme and sphere sheath impedances.
THEMIS MISSION PDR/CAR EFI-64 UCB, November 12-14, 2003
EPR Findings—Misc. Mech.
•UCB should initiate kinematic and dynamic modeling of the boom deploy sequences.
•Resolution: Kinematic model of boom deploy already exists (Th_booms3d.xls; D. Pankow) at UCB as tool for understanding timing, spin-up requirements, mechanical loads, boom/SC modes, coriolis displacements, etc.•Resolution: Algor product will be taken under advisement as part of on-going resolution of dynamic stability question (see Radial Booms; Jan ‘04).
•Boom deployment temperature range should be defined.•Resolution: Boom deployment temperature range will be defined as part of I&T test flow (Dec. ’03-Jan. ‘04).
•SPB miter gear life testing under worst-case load required.•Resolution: Such testing will be included in SPB I&T test plan (Dec ’03 – Jan ’04).
THEMIS MISSION PDR/CAR EFI-65 UCB, November 12-14, 2003
EPR Findings—Hot Parts
•High-dissipation (> 100 mW) parts should be identified, and junction temperature coefficients tabulated.
•Resolution: Data will be provided to thermal analysis as required.
THEMIS MISSION PDR/CAR EFI-66 UCB, November 12-14, 2003
EPR Findings—Gain/Filter
•DC/AC-coupled dynamic range and solitary waves•Large-amplitude (>=100 mV/m) solitary waves have been observed at frequencies from 1-1000 Hz on Polar and Cluster in the THEMIS observation region. Such waves will saturate the AC-coupled (10 Hz-6 kHz) E-field channels with a dynamic range of +/- 50 mV/m.•Resolution: Other channels can handle the large-amplitude events, although not simultaneously. DC-coupled (0-4 kHz) channels have a dynamic range of +/- 300 mV/m. Dc-coupled sphere/whip voltages have +/-60-V range (3 V/m on SPB, ~13 V/m on AXB). AC-coupled gain may be reduced to allow higher rate sampling of large-amplitude signals (TBR, Nov-Dec ’03, DFB ETU design).
•Filter specifications•SCM channels use Butterworth, EFI uses Bessel. Difference means non-trivial phase differences and time-domain responses over entire 0-4 kHz range, maximizing between 1-4 kHz, preventing direct comparison of time-domain signals.•Resolution: Trade between filter types underway; component value issue; active filter topology doesn’t change (TBR, Nov-Dec ’03, DFB ETU design).
THEMIS MISSION PDR/CAR EFI-67 UCB, November 12-14, 2003
EPR Findings—BEB FPGA
•BEB FPGA specification and programming•Resolution: BEB FPGA requirements are modest and now well-defined (CDI interface, DAC control, Analog housekeeping), and common to most IDPU boards, allowing FPGA programmer (R. Abiad, UCB) to work on design and programming within BEB ETU schedule (Build/Test, Dec ’03).
THEMIS MISSION PDR/CAR EFI-68 UCB, November 12-14, 2003
EPR Findings—Preamp
•Bootstrapping and guarding of preamp inputs•Bootstrapping and guarding of preamp electronics in the current electromechanical design should be reviewed. Potentials of all conductors need to be defined (can, shields, etc.).•Resolution: Current design does not include input guard, based on estimated input capacitance of preamp enclosure. Preamp ETU Assy and Test begins early Dec ’03 to characterize input capacity, and allow for changes and re-evaluation before FLT fabrication begins (Jan ’04).
THEMIS MISSION PDR/CAR EFI-69 UCB, November 12-14, 2003
EPR Findings—ESC
•Electrostatic Cleanliness Specification and Enforcement•Resolution: Rev. B of THM-SYS-003 Electrostatic Cleanliness Plan has been posted for review and will be signed off in Nov ’03. It includes a complete specification of electrostatic cleanliness requirements as well as verification procedures. The specification sets a 1-V potential uniformity requirement under an 8 nA/cm2 current density, with 0.1-V potential uniformity as a goal (see DC Error Budget for discussion).
THEMIS MISSION PDR/CAR EFI-70 UCB, November 12-14, 2003
EPR Findings—EMI/EMC
•Electromagnetic Interference/Cleanliness Specification•Resolution: A Draft of the THEMIS EMI/EMC Specification has been posted for review and will be signed off in TBD. This specification is modeled on that for the FAST mission, adapted to the instrument properties on THEMIS (SCM/EFI system noise levels and expected wave amplitudes). Testing and verification of compliance with EMI/EMC TBD, and requires some work, due to low frequencies of interest (0-4 kHz).
THEMIS MISSION PDR/CAR EFI-71 UCB, November 12-14, 2003
EPR Findings—I&T Plan
•I&T test flow needs to be defined to include development, ETU, qualification and acceptance testing.
•Resolution: An EFI I&T plan will be developed in Dec ’03 to support qualification and acceptance testing of the EFI ETU in Jan-Mar ’04.