The World Bank · Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00004483...
Transcript of The World Bank · Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00004483...
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: ICR00004483
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IDA-54450 / IDA-44060)
ON A
CREDIT
IN THE AMOUNT OF SDR 94.8 MILLION
(US$ 148.33 MILLION EQUIVALENT)
TO THE
DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA
FOR A
LK DAM SAFETY AND WATER RESOURCES PLANNING (DSWRPP) ( P093132 )
December 14, 2018
Water Global Practice
South Asia Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS
(Exchange Rate Effective May 15, 2018)
Currency Unit = Sri Lankan Rupee (Rs)
Rs 172.65 = US$1
US$ 1.43 = SDR 1
FISCAL YEAR
January 1 – December 31
Regional Vice President: Hartwig Schafer
Country Director: Idah Z. Pswarayi-Riddihough
Senior Global Practice Director: Jennifer J. Sara
Practice Manager: Takuya Kamata
Task Team Leader(s): Shyam KC
ICR Main Contributor: John Factora
ABBREVIATIONS AND ACRONYMS
AF Additional Finance
CAS Country Assistance Strategy
CEB Ceylon Electricity Board
CPF Country Partnership Framework
CPS Country Partnership Strategy
DSRP Dam Safety Review Panel
DSWRPP Dam Safety and Water Resources Planning
EA Environmental Analyses
EMP Environmental Management Plans
ERR Economic Rate of Return
FM Financial Management
GIS Geographic Information System
HMIS Hydrometeorological Information Systems
IAs Implementing Agencies
ICOLD International Committee of Large Dams
ICR Implementation Completion Report
ID Irrigation Department
IDA International Development Association
ISCs International Support Consultancies
ISR Implementation Status and Results Report
LSA Livelihood Support Assistance
MASL Mahaweli Authority of Sri Lanka
M&E Monitoring and Evaluation
MMDE Ministry of Mahaweli Development and Environment
MRRP Mahaweli Restructuring and Rehabilitation Project
NCDS National Center for Dam Safety
NPV Net Present Value
NWSDB National Water Supply and Drainage Board
NWUP National Water Use Plan
O&M Operation and Monitoring
OP Operational Policy
PDO Project Development Objective
PMU Project Management Unit
SDR Special Drawing Rights
TRC Technical Review Committee
WARM-P Water Resources Management Project
WBG World Bank Group
WRB Water Resource Board
Table of Contents
DATA SHEET .......................................................................................................................................1
I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ...................................................................6
A. CONTEXT AT APPRAISAL ......................................................................................................6
B. SIGNIFICANT CHANGES DURING IMPLEMENTATION .............................................................8
II. OUTCOME ..................................................................................................................................9
A. RELEVANCE OF PDOs ...........................................................................................................9
B. ACHIEVEMENT OF PDOs (EFFICACY) ................................................................................... 10
C. EFFICIENCY ........................................................................................................................ 17
D. JUSTIFICATION OF OVERALL OUTCOME RATING ................................................................. 17
E. OTHER OUTCOMES AND IMPACTS ..................................................................................... 17
III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ............................................. 18
A. KEY FACTORS DURING PREPARATION ................................................................................ 18
B. KEY FACTORS DURING IMPLEMENTATION .......................................................................... 19
IV. BANK PERFORMANCE, COMPLIANCE, AND RISK TO DEVELOPMENT OUTCOME .......................... 20
A. QUALITY OF MONITORING AND EVALUATION (M&E) ......................................................... 20
B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE.................................................. 21
C. BANK PERFORMANCE ........................................................................................................ 23
D. RISK TO DEVELOPMENT OUTCOME .................................................................................... 24
V. LESSONS AND RECOMMENDATIONS ......................................................................................... 24
ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ........................................................................ 26
ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ...................................... 38
ANNEX 3. PROJECT COST BY COMPONENT ........................................................................................ 41
ANNEX 4. EFFICIENCY ANALYSIS ....................................................................................................... 42
ANNEX 5. BORROWER COMMENTS .................................................................................................. 49
ANNEX 6. THEORY OF CHANGE ......................................................................................................... 53
ANNEX 7. TYPICAL OPERATIONAL DEFICIENCIES OF DAMS AND REMEDIAL MEASURES ...................... 54
ANNEX 8. DETAILS OF DAM SAFETY REHABILITATION ........................................................................ 55
ANNEX 9. STATUS OF CURRENT FEASIBILITY STUDIES OF PROPOSED INVESTMENT PROJECTS ............. 64
ANNEX 10. TRAINING DAYS COMPLETED .......................................................................................... 66
ANNEX 11. DELAYS IN CONTRACT COMPLETION ................................................................................ 67
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 1 of 67
DATA SHEET
BASIC INFORMATION
Product Information
Project ID Project Name
P093132 LK Dam Safety and Water Resources Planning (DSWRPP)
Country Financing Instrument
Sri Lanka Investment Project Financing
Original EA Category Revised EA Category
Partial Assessment (B) Partial Assessment (B)
Related Projects
Relationship Project Approval Product Line
Additional Financing P148595-LK: AF Dam Safety WRP - Addl Fin.
05-May-2014 IBRD/IDA
Organizations
Borrower Implementing Agency
Ministry of Finance and Planning MASL/Ministry of Mahaweli Development and
Environment (MoMDE)
Project Development Objective (PDO) Original PDO
(i) Establish long-term sustainable arrangements for operation and maintenance of large dams; and (ii) improve water resources planning.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 2 of 67
FINANCING
Original Amount (US$) Revised Amount (US$) Actual Disbursed (US$)
World Bank Financing IDA-44060
65,327,700 65,327,700 63,440,780
IDA-54450
83,000,000 83,000,000 73,002,344
Total 148,327,700 148,327,700 136,443,124
Non-World Bank Financing
Borrower 6,330,000 6,330,000 6,330,000
Total 6,330,000 6,330,000 6,330,000
Total Project Cost 154,657,700 154,657,700 142,773,123
KEY DATES
Approval Effectiveness MTR Review Original Closing Actual Closing
27-Mar-2008 26-Jun-2008 09-Sep-2011 30-Jun-2013 15-May-2018
RESTRUCTURING AND/OR ADDITIONAL FINANCING
Date(s) Amount Disbursed (US$M) Key Revisions
09-Sep-2012 28.41 Change in Loan Closing Date(s)
05-May-2014 55.05 Additional Financing Change in Results Framework Change in Components and Cost Change in Loan Closing Date(s)
19-Dec-2014 66.03 Reallocation between Disbursement Categories
KEY RATINGS
Outcome Bank Performance M&E Quality
Satisfactory Satisfactory Substantial
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 3 of 67
RATINGS OF PROJECT PERFORMANCE IN ISRs
No. Date ISR Archived DO Rating IP Rating Actual
Disbursements (US$M)
01 13-Oct-2008 Satisfactory Satisfactory .95
02 05-May-2009 Satisfactory Satisfactory .95
03 26-Nov-2009 Satisfactory Satisfactory 9.11
04 22-May-2010 Satisfactory Moderately Satisfactory 9.20
05 05-Dec-2010 Satisfactory Moderately Satisfactory 9.20
06 13-Jun-2011 Moderately Satisfactory Moderately Satisfactory 23.01
07 17-Dec-2011 Satisfactory Satisfactory 23.01
08 07-Jun-2012 Satisfactory Satisfactory 23.01
09 10-Dec-2012 Satisfactory Satisfactory 35.92
10 31-May-2013 Satisfactory Satisfactory 42.31
11 12-Dec-2013 Satisfactory Satisfactory 49.97
12 06-Mar-2014 Satisfactory Satisfactory 49.97
13 28-Sep-2014 Satisfactory Satisfactory 61.58
14 12-Mar-2015 Satisfactory Satisfactory 72.86
15 14-Aug-2015 Satisfactory Satisfactory 77.42
16 04-Mar-2016 Satisfactory Satisfactory 89.02
17 07-Sep-2016 Satisfactory Satisfactory 97.86
18 20-Jan-2017 Satisfactory Satisfactory 113.92
19 20-Jun-2017 Satisfactory Satisfactory 113.92
20 15-Dec-2017 Satisfactory Satisfactory 129.31
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 4 of 67
SECTORS AND THEMES
Sectors
Major Sector/Sector (%)
Public Administration 27
Central Government (Central Agencies) 27
Social Protection 1
Social Protection 1
Water, Sanitation and Waste Management 72
Other Water Supply, Sanitation and Waste Management
72
Themes
Major Theme/ Theme (Level 2)/ Theme (Level 3) (%) Finance 10
Finance for Development 10
Disaster Risk Finance 10
Urban and Rural Development 50
Rural Development 20
Rural Infrastructure and service delivery 20
Disaster Risk Management 30
Disaster Response and Recovery 10
Disaster Risk Reduction 10
Disaster Preparedness 10
Environment and Natural Resource Management 40
Water Resource Management 40
Water Institutions, Policies and Reform 40
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 5 of 67
ADM STAFF
Role At Approval At ICR
Regional Vice President: Praful C. Patel Hartwig Schafer
Country Director: Naoko Ishii Idah Z. Pswarayi-Riddihough
Senior Global Practice Director: Constance A. Bernard Jennifer J. Sara
Practice Manager: Adolfo Brizzi Takuya Kamata
Task Team Leader(s): Anthony Nihal Fernando Warnakulasuriya Alagappage
Shyam KC
ICR Contributing Author: John Factora
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 6 of 67
I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES
A. CONTEXT AT APPRAISAL
A1. Country and Sector Context
1. The project reflects the importance of water resources development to Sri Lanka’s economic growth and poverty
reduction. Development of dams, barrages, reservoirs, trans-basin canals and irrigation systems have been priorities
of all governments since independence, and investments in water resources were featured in the 2006-2016 national
development framework. These hydraulic assets serve the critical irrigation, hydropower, domestic and industrial
water supply needs, provide flood control in the river basins, and sustain human settlements in rural areas and the dry
zone, which cover nearly two-thirds of the country and are home to about 80 percent of the population. In the decades
preceding the project, there was growing concern over the public safety of large dams, part of an extensive network
of dams comprised of 80 large-sized, 270 medium-sized, and over 14,000 small dams located within 103 river basins.
The majority of large dams were past the 50-year effective life span of new construction and rehabilitation, and the
few repairs over the preceding four decades were done on a piecemeal basis as governments focused scarce resources
on downstream irrigation development. With no regular, comprehensive rehabilitation and modernization efforts,
large dams faced various structural deficiencies and shortcomings in operations and maintenance (O&M) facilities;
many of the large dams assessed in the late 1990s were determined to be high-hazard with some deemed unsafe.1
2. Concern centered on the risk of dam breach and the possibility of added pressure on downstream dams, which
may also succumb, threatening large populations. The Kantale dam failure in January 1986 led to loss of life,
displacement, and substantial damage to agriculture, commercial and public infrastructure and private assets. The
cost to the government of rebuilding the breached section of the dam was about three times the cost of the
government’s relief, rehabilitation, and housing expenditures for those displaced. Government and private reports
and consultations that followed recommended, inter alia, prompt action to ensure proper maintenance of dams and
reservoirs and long-term arrangements for dam safety. Moreover, the establishment of early warning systems through
reliable hydrological and meteorological data was critical to protecting the public from floods and dam failure. The
tsunami disaster in December 2004 intensified calls for improved disaster preparedness and management.
A2. Rationale for Bank Support
3. The project was fully in line with the government’s strategic sector priorities, as laid out in the national
development strategy for 2006-16 (called Mahinda Chinthanaya). The strategy included a framework to examine the
development potential of select river basins through a master plan and strategy for integrated water resources
management. The strategy also built on post-tsunami efforts to enhance disaster risk mitigation, including the creation
of new institutions, legislation, assessments, and action plans to address various risks.
1 See Project Appraisal Document (Report No. 39708-LK). High-hazard is a term used by a majority of dam safety programs. While the
definition varies slightly by program, it generally means if failure of a high-hazard dam occurs, there is potential for loss of life and
property damage. Unsafe dams are those that have deficiencies which leave them more susceptible to failure.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 7 of 67
4. The Bank’s Country Assistance Strategy (CAS) Progress Report for Sri Lanka of 2005 recognized that lending would
focus on infrastructure development. The Dam Safety and Water Resources Planning Project (DSWRPP) was to
strengthen public sector management by building capacity, establishing long-term sustainable arrangements for dam
O&M, contributing to protect the public against the risk of dam failure, and effectively managing the country’s water
resources. The project was to address the critical technical needs of the water sector, many of which were of a “public
goods” nature with high strategic priority. The project aligned with the Bank’s water resources strategy that recognized:
(i) the role water resources management plays in sustainable growth and poverty reduction; and (ii) the need to assist
countries in developing and maintaining appropriate stocks of well-performing hydraulic infrastructure. Moreover, the
Bank had supported similar operations within the region and had the global experience to undertake the project. In
fact, the project was preceded by the Sri Lanka Mahaweli Restructuring and Rehabilitation Project (MRRP, P034212,
1998-2004), which undertook preliminary studies on dams and recommended a dam safety project. The MRRP also
recommended modernizing the hydrometeorological network and enhancing the capacity for related data for planning
and management of dam operations, public safety, hydraulic assets, and drought and flood hazards.
A3. Contribution to Higher Level Objectives
5. The project was to help protect the public from potential water and dam induced hazards and enhance the long-
term capacity for sustainable planning and management of water resources and related hydraulic infrastructure. These
are all critical to agriculture, industry, energy, transport, and to the health, safety, and productivity of communities,
which, in turn, contribute to economic growth and poverty reduction.
A4. Theory of Change
6. Please see Annex 6.
A5. Key Expected Outcomes and Outcome Indicators
7. The key performance indicators for measuring progress in achieving the project development objectives included:
(i) reduced number of dams with unacceptable risk index; (ii) number of dams with risk-based O&M plans
operationalized; (iii) improved water database utilized by implementing agencies for flood forecasting and dam
operations; and (iv) national water use plan (NWUP) and at least one river basin development plan adopted by Cabinet.
A6. Components
8. The project had four components and comprised two IDA credits, the original for SDR 41.1 million ($65.33 million
at approval) and an additional financing (AF) for SDR 53.7 million ($83 million at approval). Total IDA financing was
SDR 94.8 million ($148.33 million at approvals) while the government committed $6.33 million in counterpart funding.
Total disbursed was $136.4 million in IDA funds (or 92 percent disbursement), plus the $6.33 million from government.
9. The main responsible agency was the Ministry of Mahaweli Development and Environment (MMDE) and the
Implementing Agencies (IAs) were Mahaweli Authority of Sri Lanka (MASL), Irrigation Department (ID), Ceylon
Electricity Board (CEB), National Water Supply and Drainage Board (NWSDB), and Water Resource Board (WRB). The
Project Management Unit (PMU), established under MMDE, coordinated overall activities.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 8 of 67
Component 1: Dam Safety and Operational Efficiency (projected $125 million, actual $115.9 million)
10. The component was to address various structural deficiencies and shortcomings in O&M facilities, thus enhancing
public safety of selected high-risk large dams and improving their operational efficiency. It was also to promote
sustainable institutional arrangements for dam safety management and O&M. The component comprised: (i) essential
remedial works for 63 high- and medium-risk large dams; (ii) provision of basic safety and operational facilities for 80
large dams (including the 63 dams); and (iii) collection of basic engineering and operational information essential for
sustainable operation and management of the 80 large dams; (iv) risk assessment on the remaining portfolio of large
dams and training in dam safety and O&M; (v) development of O&M manuals; (vi) preparation of codes of practice and
operating procedures and manuals; (vii) establishment of an inter-organizational arrangement for regular dam safety
inspection and dam safety regulation; (viii) establishment of two water quality laboratories within the MASL.
Component 2: Hydro-Meteorological Information System (projected $11.4 million, actual $14.4 million)
11. The component would enhance staff capacity and physical and analytical infrastructure for monitoring
hydrometric data, detecting and forecasting water hazards and assessing water resources for multi-sectoral planning,
development and management. This component comprised the: (i) establishment of 167 new and upgraded
hydrometric stations to strengthen the hydrometric network; (ii) establishment of data banks and improved analytical
capability; (iii) establishment of procedures and provision of tools and training for real-time analysis of flood situations
in some major reservoirs; and (iv) establishment of a core groundwater monitoring system.
Component 3: Multi-sector Water Resources Planning (projected $10.5 million, actual $7.5 million)
12. The expected outcome of this component included the: (i) development of a NWUP to achieve the country’s long-
term development goals and objectives based on an analysis of updated estimates of present and future water demand
and supply in the 103 river basins in the country; (ii) updating of the Mahaweli Water Resources Development Plan for
the Mahaweli Ganga and adjoining connected river basins, based on an optimization study of water supply and demand
in all sectors; and (iii) preparation of a multi-sector, integrated and comprehensive Mundeni Aru Basin Development
Plan, and feasibility studies of priority investments; (iv) improvement of two training centers.
Component 4: Project Management and Monitoring (projected $7.8 million, actual $4.9 million)
13. The component was to help ensure smooth implementation of project activities as well as monitoring project
processes and outputs.
B. SIGNIFICANT CHANGES DURING IMPLEMENTATION
B1. Project Restructurings, Additional Financing, and Other Changes
14. There were several key changes during implementation. The first was an approval in September 2012 of a two-
year extension of the project closing date from June 30, 2013 to June 30, 2015. The extension was needed to make up
for delays in recruiting three teams of international consultants (one for each main component) and to begin
implementation. The second change was the May 2014 approval of an AF for $83 million in IDA credits which financed:
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 9 of 67
(i) cost overruns totaling $25 million to complete the rehabilitation of 14 dams from the original project;2 and (ii) scale-
up of successful project activities, including 31 additional dams and 20 hydrometeorological information systems
(HMIS) stations.3 The AF also extended the project closing date to May 15, 2018 and changed results indicator values.
Another project restructuring in December 2014 allowed for a reallocation of credit proceeds between disbursement
categories and components to formalize the increase in the number of upgraded or new hydro-meteorological stations
from 50 to 122. Following the December 2014 restructuring, the government requested the installation of an additional
80 hydrometeorological stations. The project ultimately installed an additional 45, bringing the total to 167 stations.4
B2. Revised PDOs and Outcome Targets
15. There was no change to the PDO or to the Theory of Change throughout project implementation. However, the
AF introduced one new intermediate indicator to capture the preparation of feasibility studies for future investments.
In addition, the target values of some of the indicators were revised to reflect increased end of project values.
II. OUTCOME
A. RELEVANCE OF PDOs
Rating: High
16. The Sri Lanka Country Assistance Strategy (CAS) Progress Report of 2005 (Report No. 34054-LK) recognized that
IDA financing would focus largely on infrastructure. The indicative lending program of the CAS included the DSWRPP
for FY07. The project was to establish long-term sustainable arrangements for dam O&M to reduce the risk of dam
failures, strengthen capacity of key agencies to manage water resources and major water assets, which the government
saw as essential in promoting economic growth and poverty reduction in its national development strategy for 2006-
16. There was strong rationale for the project; it would address critical technical needs of the water sector, many of
which were of a “public goods” nature with strategic priority.
17. The AF was prepared in keeping with the Country Partnership Strategy (CPS) for FY13-16 (Report No. 66286-LK),
which was focused on (i) facilitating sustained private and public investment and (ii) improving living standards and
social inclusion. The CPS recognized that, with the end of almost three decades of internal conflict, the country had
started shifting from a focus on reconstruction to laying the foundation for growth and middle-income status. The CPS
proposed refocusing the Bank’s engagement on creating the enabling environment for increased foreign and domestic
2 There were several reasons for the cost overrun: (i) during project preparation, not all dams were inspected in detail and the actual
costs were higher than what was estimated; (ii) the scope of work at most dams was larger than estimated and required works had
increased over time, which is common for rehabilitation projects; and (iii) the construction costs had increased more than the 11
percent allocation for price contingencies.
3 The additional financing project paper noted that about 30 additional dams would be rehabilitated. In early 2016, the exact number
of additional dams to be rehabilitated turned out to be 31, when the ID dropped one and added two dams due to risk levels. The final
number of additional dams was noted in the Aide Memoire for the May 26-June 3, 2016 mission
4 See Aide Memoire for the October 1-6, 2015 mission. The government requested an additional 80 hydrometeorological stations but
available financing could cover no more than 50.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 10 of 67
investment and enhancing the efficiency of the state, while increasing resilience to natural disasters and climate
change. The rehabilitation and modernization of infrastructure, including dams and other hydraulic assets, and
improved water resources management, responded directly to the CPS goals. Furthermore, the AF was prepared as
part of the broader effort to consolidate peace and equitable growth through investments in conflict affected parts of
the country. Hence, some of the 31 dams selected under the AF were in the northern and eastern parts of the country.
18. The project remains relevant under the Country Partnership Framework (CPF) for FY17-20 which emphasizes
infrastructure strengthening under Objectives 1.3 (scaling up infrastructure), 2.3 (improving living standards in lagging
areas), and 3.2 (strengthening climate resilience and disaster risk management). The project’s objectives also remain
relevant to the government’s priorities, which seek to balance growth with environmental conservation and climate
resiliency, and to manage the country’s natural resources for sustained growth and livelihoods. These are crystalized
in recent strategies and action plans, such as the Public Investment Plan 2016-2020, the National Plan of Action for the
Social Development of the Plantation Community 2016-2020, and the Nationally Determined Contributions (NDC) to
address climate change. The Bank is preparing the new Water Resources Management Project (WARM-P) that builds
on the DSWRPP by rehabilitating hydraulic assets and improving water resources management, including the
restoration of watersheds, to contribute to climate resilience, sustainable growth, and poverty reduction.
B. ACHIEVEMENT OF PDOs (EFFICACY)
Rating: Substantial
19. The PDO consisted of two parts: (1) Establish long-term sustainable arrangements for operation and maintenance
of large dams; and (2) improve water resources planning. The outcome indicators used to monitor and assess
achievement of the PDO included: (a) reduced number of large dams with unacceptable risk index; (b) need-based
O&M plans operationalized in select dams; (c) improved water database utilized by implementing agencies for flood
forecasting, dam operations and water allocations; and (d) national water use master plan and at least one river basin
development plan adopted by the cabinet. Overall the PDO was substantially achieved.
B1. Assessment of PDO 1: Establish long-term sustainable arrangements for O&M of large dams
Rating: Substantial
(i) Dam Safety and Operational Efficiency
20. The first part of the PDO was to be achieved, in part, through remedial works of 63 high-risk large dams, the
provision of basic facilities to all 80 large dams, and the collection of essential basic engineering information for all 80
dams.5 The scope of remedial works varied by dam, but typical safety issues common in earthen dams include: (i)
seepage boils and leakages in the downstream of dams; (ii) deformity and some localized erosion of upstream and
downstream slopes; (iii) slope sloughing / slips, erosion of abutments, settlement and cracks along dam crests; (iv)
cracks in concrete spillway and outlet gate sections, etc. In the case of gravity dams, common issues were: (i)
malfunctioning of dam monitoring instruments and (ii) need for repair and replacement of spillway and outlet gates
5 The assessment and selection of the original 32 dams are described in Annexes 1 and 4 of the project appraisal document (PAD),
Report No. 39708-LK, February 26, 2008.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 11 of 67
and gate hoisting mechanism. Moreover, almost all the large dams lacked basic safety facilities, such as: (i) monitoring
and deformation measuring instruments including micro-seismographs and pore water pressure gauges; (ii) functioning
communication and observation systems (wireless or telephone at site, upstream and downstream flush lighting
system with standby generators); (iii) all weather access roads; and (iv) equipment for minor O&M and emergency
situations. Many reservoirs had undergone excessive sedimentation and reservoir rim deformation and did not have
updated engineering and operational information (such as reservoir elevation-capacity curves). The project undertook
remedial works to address these deficiencies in the 63 large dams, as described in Annex 8.
21. Remedial works reduced risks in all 63 dams. For each dam, risk assessments were carried out before works began
and after completion. The methodologies employed included both quantitative and semi-quantitative assessments for
the original 32 dams and a semi-quantitative assessment for the 31 dams under the AF.6 Based on the semi-quantitative
assessments, risks were reduced by 65 percent on average for all 63 dams. There was a higher risk reduction
percentage for the 32 dams under the original project (81 percent) compared to the 31 dams under the AF (48 percent),
reflecting the higher risk profile among the former set of dams. It should be noted that for Outcome indicator 1, “Large
dams with unacceptable risk index”, the word “unacceptable” was never clearly defined and no threshold score was
proposed. Neither the quantitative or semi-quantitative assessments had risk indices that easily corresponded to risk
“categories” (acceptable / unacceptable, extreme risk, high-risk, moderate risk, etc.).
22. There were other project activities that contributed to long-term sustainable arrangements for dam O&M. The
establishment of modern HMIS allows for automated, accurate, and real-time collection of rainfall, water volume and
flow data that is transmitted through a network to data centers at the MASL and ID for flood forecasting, dam
operations, and water allocations. This represents a tremendous improvement over the manual readings, which were
prone to errors and delays in data collection, transmission, and analysis. Data is also better integrated with greater
application and usage by the IAs. Authorities are now able to more accurately forecast floods and droughts and make
decisions accordingly, for example, on available water for irrigation purposes in a specific scheme or whether to call
for an evacuation of downstream residents due to an impending flood. This change is captured in the third PDO
outcome indicator: “Improved water database utilized by IAs for flood forecasting, dam operations and water
allocations”. The expectation was for hydrometeorological stations to be installed at every dam site and that enough
data would be collected over time (roughly two years) to enable IAs to use the databases to help manage dam
operations. While HMIS were installed in all 63 dams, the target value was kept to the 32 dams under the original
project. All 32 dams now have sufficient data collected over several years to allow for effective utilization by their IAs.
23. A Flood Control Center was also established that connects six major dams on the Mahaweli river basin through a
common control center where real time data on upper catchment conditions, reservoir inflows, gate operations, etc.,
is collected and analyzed, and decisions are taken to optimize reservoir operations. In times of heavy rain, the control
center could, for example, release flood waters in advance and in a controlled manner to avoid sudden downstream
6 The quantitative assessment is based on a methodology developed by the United States Bureau of Reclamation. The semi-
quantitative assessments were undertaken by Jason Gibb and Associates. A quantitative risk analysis yields a numerical estimate of
the risk of adverse consequence, considering the probability of load, probability of dam failure, and magnitude of adverse consequence
given dam failure. Annex 7 includes risk ratings for all dams.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 12 of 67
inundations. The Center is fully staffed and operational and is the first integrated dam management system in Sri
Lanka. Further discussion of HMIS is provided in the next section.
24. Emergency action plans were prepared for 13 dams for which dam engineers were trained to update on a regular
basis. A central electronic database now stores core engineering data related to dam design and operation (as-built
blueprints, records of flood history, geotechnical information, surveys and physical measurements, estimates and
investment information, and other data), which is a significant improvement over the dispersed storage of hard and
soft files by individual dam owners. Lastly, training and capacity building were a key aspect of establishing long-term
sustainable arrangements. All told, there were 487 training hours devoted to dam safety, operations, maintenance;
more than half took place overseas. Also see Section E for a discussion on institutional strengthening.
25. The project experienced a few shortcomings in establishing sustainable arrangements for O&M of large dams.
The first dealt with the O&M plans that were to be prepared for each of the 63 rehabilitated dams. This was the second
outcome indicator of the project. For the initial phase of the project, an international consultancy prepared the O&M
plans for the 32 dams (in addition to conducting the risk assessment studies, verifying detailed designs, preparing cost
estimates and specifications for tenders, inspecting works during and after completion). These responsibilities were
devolved to the individual IAs7 for the 31 dams rehabilitated under the AF, due to a Cabinet-imposed limit on
international consultancy contracts. While the IAs proved themselves capable of undertaking these responsibilities,
the post-renovation O&M plans were not treated with appropriate urgency and were delayed. As of this writing, all 31
plans have been reviewed by the independent Dam Safety Review Panel (DSRP) and are being used by the relevant IAs.
(ii) Institutional Arrangements
26. There were also delays in establishing a national-level dam safety institution (or Dam Safety Inspectorate, as
referred to at appraisal), an intermediate results indicator of the project. Now referred to as the National Center for
Dam Safety (NCDS), the institution was first attempted under the MRRP without success and was subsequently included
in the design of the DSWRPP to, inter alia, help establish codes of practice and essential guidelines and procedures for
dam O&M and dam safety, including inter-organizational arrangements for regular dam inspections, asset
management, and assistance for the establishment of dam safety regulation. Formal approval is expected by end-2018
and its set-up has been slow and incremental. It comprises a high-level National Dam Safety Steering Committee and
a Dam Safety Secretariat. Suitable offices have been identified near the city of Kandy. And while staffing requirements
have purportedly been approved by the Management Services Department, transfer of staff to the Secretariat and
recruitment are pending. In the meantime, the PMU has arranged a work program of dam inspection by a team of
senior engineers from the IAs to revisit the rehabilitated dams for inspection. This is a temporary measure that is no
substitute for the envisioned NCDS. Despite delays, progress over the past eight months indicates the NCDS will be
fully operational soon. The WARM-P provides a platform to continue advising and supporting its operationalization.
7 Of the 63 dams rehabilitated, 31 were owned by the Irrigation Department, 21 by the Mahaweli Authority, 5 by the Ceylon Electricity
Board, 3 by the Northern Provincial Council, 2 by the Kandy Municipal Council, and 1 by the National Water Supply
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 13 of 67
While bureaucratic inertia and intransigence provide an explanation for the limited progress, the underlying issue
seems to be the recurring challenge of establishing a comprehensive framework for managing water resources.
27. One of the envisioned tasks of the NCDS was to help with budget planning and allocation for O&M and dam safety.
Although not an explicit output of the project, sufficient budget for O&M is key to sustainability of the project’s
investments, including the remedial works for dam safety. The Bank was unable to obtain evidence of budgetary
allocation for need-based O&M expenditure. And while it could be argued that the relatively recent completion of
remedial works precludes the need for immediate budget allocation, discussions with officials from the ID indicate that,
at least by one estimation, only 25 percent of the requested budget for O&M is approved in any given year. Visits to
dam sites and talks with field operators also indicate insufficient resources for even relatively routine maintenance,
such as repairing bund roads, clearing / preventing overgrowth of vegetation along the banks of reservoirs, etc. This
issue is expected to be addressed as the NCDS takes shape and with support from the WARM-P.
28. Despite these shortcomings, the project substantially achieved the first objective of establishing long-term
sustainable arrangements for O&M of large dams. The rehabilitation and modernization of 63 large dams improved
the stability of the dams per international dam safety standards and extended the effective design life period by
another 50 years, effectively reducing the dams’ risk index and concerns over public safety. All 63 dams have O&M
plans that have been operationalized and all 80 of the country’s large dams have proper O&M equipment. Despite
delays in establishing the NCDS, considerable capacity building, institutional strengthening, and operational-level
institution building (new flood control centers, HMIS databanks, training centers, etc.) were successfully carried out to
establish long-term sustainable arrangements for dam O&M. Other issues beyond the scope of the project, such as
adequate budgetary allocation for need-based O&M and establishment of an overarching national water sector
framework for integrated management of water resources, will continue to be addressed through on-going dialogue
with the government, particularly under the WARM-P. All told, an estimated 500,000 people who live near the dams
and whose lives would be directly affected by a dam breach have benefited by the achievement of the first objective.
Beyond this group of people, the government considers “direct beneficiaries” to be the 1.3 million people whose
livelihoods directly depend on the dams, reservoirs, and in many cases, the associated irrigation schemes. These
include farmers, fishermen, aqua-culturalists, etc. Indeed, field visits and beneficiary feedback indicate positive effects
of dam modernization on livelihoods, such as improved irrigation and agricultural intensification.
B2. Assessment of PDO 2: Improve water resources planning
Rating: High
29. The second part of the PDO was to be achieved through, inter alia, improved physical and analytical infrastructure
for monitoring hydrometeorological data, detecting and forecasting water hazards, and assessing water resources,
including groundwater. In addition, water resources planning would be enhanced through the completion of a national
water use plan and two water resources development plans for future priority investments in select river basins.
(i) Hydrometeorological Information System Improvement
30. The project succeeded in establishing and upgrading hydrometeorological stations. In proper planning and usage
of water-related infrastructure, especially in the operations of reservoirs, hydrological data analysis and applications
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 14 of 67
play a vital role. These data are extremely useful in forecasting floods, operating dams, allocating bulk water, and
managing irrigated agriculture. All told, the project financed the installation of 167 hydrometric stations (a scale up
from the target of 142 revised at the time of the AF), including the upgrading of 35 existing stations, replenishing the
basic equipment and tools used for stream monitoring and installing more robust and modern automated data-
collection tools. The latter included: data loggers to control automated sensors and locally store data; various water-
level, precipitation, and other sensors to provide data to the loggers; solar-powered and other power supply
subsystems; technologies to telemeter data from stations to a databank; capacity to download data directly from the
data logger; and other tools and equipment, including lightning protection. As mentioned in the previous section, the
upgraded system represents a significant improvement over the manual readings, which were prone to errors and
delays in data collection, transmission, and analysis. One Aide Memoire reported differences by approximately 200mm
in hourly rainfall in the Kelani River Basin as reported by manual observation versus modern HMIS.8
31. There was tangible evidence of improved local capacity. Officers for relevant IAs were trained on data collection,
database management, flood forecasting, catchment water yield computations, and rainfall-runoff models. In total,
there were 260 training hours conducted on topics related to HMIS, including 30 hours conducted overseas. By the AF
phase of the project, the IAs took a lead role on several key activities. These included site surveys, development of a
plan for each station, preparation of the design package, and some of the civil works and instrument installation. Two
data centers were established at the Hydrology Divisions in the ID and Water Management Secretariat in MASL and all
necessary equipment was installed. As discussed in the previous section, these two data centers are now receiving and
utilizing data from the 32 dams rehabilitated under the original project.
32. Hydrometeorological stations were also installed for the 31 dams under the AF and since some time is required
to collect data, the use of the data banks to monitor and manage these dams are limited. The management of the
HMIS themselves was dependent on the capacity of IA staff to collect and analyze data and to monitor and manage the
hydrometric databases. In this regard, the project succeeded in providing modern data collection and analysis
infrastructure, and the framework for improving analytical capacity, including advanced applications of hydrologic and
meteorological data, and integration of historical and real-time data with remote sensing data and existing spatial
dataset of topography, land use, soils, and population, to develop rainfall-runoff models to compute reservoir inflow
and outflow, all necessary for decision making for flood hazard management and dam operation. As of the project
closing date, HMIS data was accessible to IA staff only but the HMIS website will soon allow access to the general public.
33. As was seen in some dams, there are concerns over the sustainability of the HMIS due to inadequate funding for
O&M. Although the Bank could not verify budget allocation for such purposes, a discussion with field officers at HMIS
sites indicated insufficient resources to undertake anything beyond menial repairs. Moreover, some HMIS belonging
to the ID have not been correctly handed over to regional ID offices and, as a result, are not being properly maintained.
The HMIS should be transferred, with care-takers appointed, and guidance provided for upkeep of stations.
(ii) Groundwater Monitoring
8 Aide Memoire, June 3, 2016.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 15 of 67
34. Another important means of improving water resources management was groundwater monitoring. This entails
monitoring, assessing, and safeguarding groundwater resources, which had been over-exploited in some parts of the
country. Many aquifers in Sri Lanka are shallow and highly vulnerable to pollution. Over extraction for irrigated
agriculture in many coastal areas induces saltwater intrusion and puts many aquifers at risk. Other natural and human-
induced contaminants include fluoride, iron, nitrates, industrial contaminants; fecal coli from bacteria; and a range of
agricultural chemicals. Exacerbating these issues is the lack of systematic and coordinated monitoring of groundwater
level and quality as well as little public awareness regarding groundwater resources.
35. The project identified and monitored eight pilot areas in different provinces with groundwater issues. These issues
included bacteriological and extensive fertilizer usage, extensive agriculture, over-extraction of groundwater, kidney
diseases,9 industrial pollution, salinity, water quality assessments. For each pilot, the project established a
groundwater monitoring network and information system to inventory groundwater use and catalogue issues and
complaints; monitored groundwater quality and quantity, and disseminated results to researchers, policymakers, and
universities; developed hydrological maps; established a groundwater database, coupled with geographic information
system (GIS) and other applications; built the analytical capacity of the WRB staff for groundwater monitoring and
analysis; and undertook a public awareness campaign on groundwater. On capacity building, 81 training hours were
conducted on a range of topics on groundwater monitoring and analysis. The project also provided funds to upgrade
and equip the existing water quality laboratory in Anuradhapura operated by the WRB, by which they could analyze
chemical, bacterial, and metallic content in water samples. Public outreach included "Jala Sayana" (Water Clinics)
programs set up by request, which provide knowledge of local water levels, water quality, and purification methods.
36. Design methodology was established for a groundwater monitoring program to carry out a systematic long-term
monitoring network in the country. Field activities included in-situ testing, detailed laboratory analysis, groundwater
level monitoring, drilling of wells, installation of automated data loggers, well levelling, and pumping tests made the
program successful. Subsequently, hydrological maps were developed, awareness program for community and officials
in the area were conducted, and preparation of base maps and geographic surveys in pilot areas were carried out for
effective implementation of the sub-component. One-hundred wells were drilled in the pilot areas and water samples
tested to assess the standard water quality, heavy metals, bacteriological analysis, and pesticide analysis. The
establishment and functionality of regional-level groundwater monitoring committees was undertaken by the WRB
and government has committed to continued work by WRB such that longer term and sustainable monitoring work
could be done to better understand trends and draw clearer conclusions on ground water quality.
(iii) Multi-sector Water Resources Planning
37. Current demographic and economic trends indicate greatly increased demand for agriculture, safe and reliable
water supply for domestic, commercial and industrial use, and increased and more reliable electricity. These trends,
9 Public interest in groundwater has grown in recent years given the alarming rise in “chronic kidney disease of unknown etiology”
(CKDu) of which some districts report a 15-22 percent prevalence rate. While no definitive cause for CKDu has been identified,
geographical mapping indicates a relationship between CKDu and agricultural irrigation water sources. More information is available at
https://www.ncbi.nlm.nih.gov/pmc/articles/PMC5102238/
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 16 of 67
along with heightened sensitivity to environmental conservation, have resulted in increased competition for water
among different uses and sectors, and disputes over where water resources are available for development. The project
helped to address these issues by (1) developing a NWUP; (2) updating the Mahaweli Water Resources Development
Plan for the Mahaweli Basin; and (3) preparing a multi-sector development plan for the Mundeni Aru Basin.
38. The NWUP entailed broad stakeholder consultations conducted at both the district and national levels. It was
based on an assessment of the availability of water in 103 river basins; studied 30-year potential water demands and
development policies in the country; took into account social and environmental assessments to develop baseline
scenarios; studied potential impacts; identified alternative strategies for planning and implementation; and proposed
potential water resource investments to consider for the short, medium, and long-term horizons. The updated
Mahaweli Water Resource Development Plan (originally completed in 1968) consists of three development options
that would use water from the Mahaweli Basin for the development of North-Central and Central Provinces. The
Mundeni Aru basin plan includes regulating water resources for domestic water, additional supply for irrigation, and
environmental flow requirements. Staff were trained in water resources planning and management and supported the
preparation of all three plans which were then reviewed by the Technical Review Committee (TRC), representing the
main IAs.10 Final plans were presented in a national workshop and approved by the Cabinet for implementation.
39. Based on the three plans, 26 water investment projects with an approximate cost of $240 million were proposed.
Eight feasibility studies have been completed and are in various stages of review by the TRC. Subsequently, the Bank
together with IAs prepared the Report "Strategic Options for Water Conservation, Management, and Development in
Sri Lanka" which details the government policy, priorities, development plans, institutional arrangements, challenges,
and strategies in irrigation and water resources development in the country. The report provides a framework for
discussing future water sector priorities between the government and development partners.
40. The project fully achieved the second PDO of improved water resources planning. Hydrometeorological data
collection and analysis have significantly improved, owing to the establishment and upgrading of 167 hydrometric
stations, establishment of data centers that are in full operation in the two main water resources ministries, and the
provision of tools and training for real-time analysis of flood situations in the influent streams of key reservoirs.
Groundwater monitoring and analysis have also improved through the eight pilot programs, paving the way for scale-
up and possible development of regulations to safeguard groundwater resources. Lastly, the development of the
National Water Use Plan, the updated Mahaweli Water Resources development plan, and Mundeni Aru Basin
Development Plan have provided government with a strategic framework to assess options for future development of
water resources. As previously discussed, issues beyond the scope of the project, including establishment of an
overarching national policy, legal and institutional framework for water resources management, will continue to be
addressed through policy dialogue, particularly through the WARM-P and Bank advisory services and analytics (ASA).
B3. Justification for Overall Efficacy
10 The intermediate indicator measuring the number of core staff trained for multi-sectoral water resources planning targeted 15 staff
across the key water agencies but it was later determined that only 10 were required to help develop the three plans.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 17 of 67
41. Overall efficacy is rated “Substantial”, based on substantial achievement of the first PDO (Establish long-term
sustainable arrangements for the O&M of large dams) and full achievement of the second PDO (Improve water
resources planning), as reflected in progress on outcome and intermediate indicators.
C. EFFICIENCY
Rating: Substantial
42. Following the methodologies adopted for the project appraisal in 2008, the ICR-stage ex-post economic analysis
was conducted to re-assess the economic viability of the project investment. Given the fact that economic analyses
were conducted at both the original project appraisal (Phase 1) and appraisal for the additional finance (Phase 2) in
2014, the ICR-stage economic analysis was conducted with four different scopes: (i) 32 dams for Phase 1; (ii) five
portfolio dams for Phase 2; (iii) 30 dams for Phase 2; and (iv) the entire 63 dams of Phase 1 and 2. The primary benefits
of the project are: (i) reduced risk of dam failure and (ii) reduced risk of floods caused by deficient dam operation. More
detailed information including assumptions used for the analysis can be found in Annex 4.
43. The results of the ICR-stage economic analysis for the entire project (Phase 1+2) indicate a positive net present
value (NPV) of US$ 23.9 million and an Economic Rate of Return (ERR) of 26.6 percent. The ERR for Phase 1 dams and
Phase 2 dams were 30.6 percent and 16.8 percent, respectively. Phase 1 shows higher ERR than that at appraisal-stage
(18.8 percent). This is presumably attributable to the project cost that did not exceed the estimated expenditure
despite the high inflation rate during the project period (5.1 percent per year on average). However, it is hard to identify
the source of difference since the cash flow chart used in the project appraisal is no longer available.
44. It should be noted that some of the benefits materialized by the project (e.g., reduced risk of deaths from floods,
increase of agricultural productivity and contribution to the reconstruction of post-conflict area) were not included in
the current analysis due mainly to the difficulty in valuation, which made the analysis more conservative. The efficiency
of the Project is rated as “Substantial”, given the reasonably high economic viability. Some implementation delay and
cost overruns were observed in Phase 1, but after the project extension in 2012 and the AF to scale up project activities
in 2014, there were no further delays or cost overruns. The higher ERR in comparison to the ex-ante assessment
suggests the rating as “High” instead of “Substantial”. However, the limited availability of data from the ex-ante
analysis made the results of ex-ante and ex-post analyses less comparable, therefore there is too limited unambiguous
evidence to justify a rating of “High”.
D. JUSTIFICATION OF OVERALL OUTCOME RATING
45. Based on the above assessment, with Relevance rated “High”, Efficacy rated “Substantial”, and Efficiency rated
“Substantial”, the overall outcome rating of the project is “Satisfactory”.
E. OTHER OUTCOMES AND IMPACTS
E1. Institutional Strengthening
46. As discussed in the above sections, the project had a strong institutional strengthening element with the aim of
building the capacity of the IAs in several specialized skills. Those included modem state-of-the-art dam engineering
principles; risk assessment and dam portfolio management; engineering design and construction quality control; social
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 18 of 67
and environmental management of dams and water resources management; dam safety codes of practices; dam
operation and risk-based maintenance; safety monitoring and inspection; dam emergency preparedness planning;
hydrological and meteorological data management; flood forecasting; and multi-sectoral water resources planning. To
build capacity, a number of trainings were conducted both in-country and overseas (Annex 10). Moreover,
implementation responsibility of all three main components were anchored within relevant government departments,
which built strong ownership and created a favorable environment for sustaining project activities and investments.
The tasks performed by international consultants during the original project were delegated to and satisfactorily carried
out by the IAs during the AF phase. The improved implementation performance during the second half of the project
implementation period testifies to the success of improved capacity and knowledge transfer.
47. Knowledge transfer through experience sharing, exposure visits, and on-the-job training proved extremely useful
for field staff at the dam site who may not have been able to participate in national or regional training events. For
example, the idea of building simple O&M structures to store tools and as a resting place for field workers spread from
one scheme to another. Another example was the idea to cover the newly installed gate-lifting motors and supporting
accessories with a simple roof structure to guard against exposure to the elements. During field visits, it was noted
that such minor matters significantly contribute to the effectiveness and sustainability of the investments.
E2. Peace Consolidation
48. There were a few other key changes in the country context and operating environment that impacted the project
scope and implementation. The first revolved around the formal end of the 26-year civil war in May 2009 between the
Sri Lankan government and the Liberation Tigers of Tamil Eelam. The conflict had particularly affected the northern
and eastern parts of the country, which had largely been inaccessible to the government and its development partners.
Hence under the original project, none of the 32 dams selected for rehabilitation were located in these areas. The
peace accords called for a new era of peace, reconciliation and development, and the latter included reconstruction of
both social and economic infrastructure. The DSWRPP was conceived as a good vehicle for spurring economic growth
through dam rehabilitation that inter alia, had associated benefits for irrigation schemes and therefore to farmer
livelihoods. Thus, for the AF, 10 of the 31 dams were selected from conflict-affected parts of the country.
III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME
A. KEY FACTORS DURING PREPARATION
49. The project benefited from good project preparation which was guided by the objective of reducing disaster risk
and improving water resources management. The objectives were clear, realistic, and achievable, and buttressed by a
straight forward project design with clearly structured components and clear operational logic. The project was well
designed and entailed a comprehensive technical review that followed internationally acceptable methodologies.
However, detailed inspection of all dams could not be fully undertaken during preparation, resulting in an
underestimation of projects costs by 27.8 percent, which necessitated AF to cover cost overruns. The identification of
risks and mitigation measures were well-founded and adequate. Procurement risks were addressed through the
recruitment of a strong procurement unit within the PMU (the procurement specialist eventually became the PMU
director) and the preparation of a comprehensive procurement manual and training in line with Bank guidelines. The
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 19 of 67
risk of communities not agreeing to civil works that could affect their livelihoods was mitigated by a well-designed and
executed outreach campaign to ensure informed decision making as well as transparency in transactions.
50. There were some shortcomings in project design and preparation that affected implementation. First, the
monitoring and evaluation (M&E) framework had some measurability issues (see Section IV). Secondly, there were
limitations to what could be achieved under a conventional investment project design, e.g., the operationalization of a
national dam safety entity, which could have been better supported by other approaches, including output / results-
based financing, development policy financing, and technical assistance. Lastly, the long delays in hiring the three
international support consultancies (ISCs), which were critical to implementation, could have been mitigated by
ensuring the recruitment process was further along prior to project approval.
B. KEY FACTORS DURING IMPLEMENTATION
B1. Factors Subject to Government / PMU Control
(i) Implementation Delays
51. As noted above, there were significant delays during the first three years of the project in hiring the ISCs
responsible for providing technical inputs to plan, design, and initiate the three components. The delays meant very
little implementation could be done and were caused by a number of factors: (a) the complex nature of procurement
and evaluation process; (b) the large number of proposals and the length of time needed to review; and (c) approval
processes from various agencies, including the World Bank. According to Aide Memoires, the ISCs for Components 1
and 3 were on board by February 2010, while the ISC for Component 2 was recruited in August 2012, representing
delays of 20 and 50 months, respectively, from the effectiveness date.
52. Contract management was challenging throughout implementation but particularly during the original project
period. The ISCs took more time than expected to develop detailed designs of more complex dams. Delays continued
during the construction phase. As shown in Annex 11, under the original project, 19 contracts were to be completed
within 12 months, but they were instead completed in 28 months. Similarly, seven contracts were to be completed
within 18 months but were instead completed in 33 months. While there were fewer and shorter delays during the AF
period, any delay defers achievement of results; risks escalation of the price of materials, transport and labor; risks
cash flow issues; and delays succeeding activities. Furthermore, contractors often cited adverse weather conditions as
the justifications for contract extensions to avoid penalties. Another problem observed was the use of the mobilization
advances (MA) for other purposes (settle previous loans, buy new vehicles, etc.). The project officers have the authority
to advise the contractors on use of MA or to pay the MA in instalments. Many of these delays could have been averted
by enhanced monitoring and contract management.
(ii) Implementation Roles and Responsibilities
53. A Cabinet decision in September 2007 affected the implementation of the AF in several ways. First, the AF was
mandated to be completed within four years (whereas it was originally planned for five). Secondly, IAs were to limit
international consultancies and to give preference to local consultants or implementing agencies. Third, the project
was to be implemented in greater coordination with line ministries. The Ministry of Irrigation and Water Management
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 20 of 67
subsequently advised that financial management (FM) and procurement administration would come under the purview
of the ID, thus requiring these functions to be devolved to the ID to the extent possible with oversight provided by the
PMU. Both ID and MASL followed the above decisions and acted accordingly, effectively taking over key responsibilities
undertaken by the ISCs during the original project. By and large, these Cabinet and ministerial decisions did not
adversely affect implementation of the AF. The capacity of the IAs had improved due to institutional strengthening
activities and the close collaboration between IA and ISC staff. In addition, the independent six-member Dam Safety
Review Panel continued to provide regular technical support (though not as often during the last two years).
54. The above decisions enhanced the role of IAs which had the effect of promoting ownership, sustainability, and
institutional strengthening. However, they also effectively diminished the role of the PMU. While still responsible for
overall project management (see Annex 1 for achievements against intermediate indicators related to project
management), the PMU took on more of a coordinating role. It continued to take the lead in designing and executing
training, M&E, and environmental and social safeguards. But its capacity to be a central, independent, and authorized
entity to ensure inter-ministerial collaboration and agreement on more substantive matters, were constrained.
B2. Factors Subject to World Bank Control
55. The Bank provided adequate supervision of the project. During the 10-year implementation period, there were
three task team leaders (TTLs) and the transition between them seems to have been smooth. The Aide Memoires
indicate that teams proactively identified opportunities to scale up project activities for development impact, engaged
in appropriate follow-up and resolution of bottlenecks, and appropriately adapted to changing conditions. The M&E
design and utilization had some minor weaknesses. Moreover, the delays and lack of progress during the first few
years of implementation were well documented but inadequately reflected in the project ISR ratings.
IV. BANK PERFORMANCE, COMPLIANCE, AND RISK TO DEVELOPMENT OUTCOME
A. QUALITY OF MONITORING AND EVALUATION (M&E)
Rating: Substantial
A1. M&E Design
56. The M&E framework contained features that one would expect from a Bank-financed project in terms of clear
roles and responsibilities, sources of data, and frequency of data collection and reporting. The reports would cover the
key inputs, outputs, and processes of project management, as well as the expected outcomes necessary to show
achievement of the PDO. While the outcome indicators encompassed all aspects of the PDO, they were some
weaknesses. Most notably, the first indicator, “Large dams with unacceptable risk index”, would have benefited from
a clear definition of “unacceptable risk index.” As discussed earlier, the risk index used a point system with the more
points assigned, the higher the risk. The index, however, did not indicate a certain threshold for “unacceptable” nor
does the project attempt to provide one. Remedial works were assumed to lower risks below unacceptable levels.
A2. M&E Implementation
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 21 of 67
57. Generally speaking, M&E data was collected, analyzed, and reported in a methodologically sound manner.
However, there seems to have been some confusion on the part of the PMU on the third outcome indicator, “Improved
water database utilized by IAs for flood forecasting, dam operations, and water allocations.” The achievement
constituted: establishment of new or upgraded hydrometric stations at dam sites; establishment of a databank at the
IA and MASL; improved analytical capacity by IA and MASL staff; and establishment of procedures and provision of
tools and training for real-time analysis. The PMU nonetheless reported on the number of dams with installed HMIS.
A3. M&E Utilization
58. The PMU prepared monthly, quarterly, and annual reports as planned. However, the reports mostly focused on
contract details, inputs, activities, and outputs with very limited reflection and evaluation. The Bank Aide Memoires
on the other hand, did utilize the M&E framework to inform implementation and decision making. The project would
have benefited from a mid-term review, which was planned but never undertaken. The AF project paper also indicated
that an interim ICR would be undertaken after the closing of the original credit, but this too was not done. However,
by the close of the original credit, project implementation had been progressing well and a stocktaking of progress,
lessons learned, and course corrections for the remainder of the project period were not seen as priorities.
A4. Justification of Overall Rating of Quality of M&E
59. Based on assessment of design, implementation, and utilization, the overall rating of quality of M&E is
“Substantial”. Despite the shortcomings described above, the M&E framework was more than sufficient to assess the
achievement of the project’s objectives. It should also be noted that the PMU continues to use the M&E framework
as part of the preparation of the proposed WARM-P which would continue the dam modernization program and efforts
to improve water resources management.
B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE
B1. Environmental Safeguards
60. The project was a Category B as it did not entail construction of new dams, alteration of primary design profiles
of selected dams, or capacity augmentation of reservoirs. Environmental impacts were not significant or irreversible
and overall, the project would result in positive environmental benefits, due to reduced risk from rehabilitated dam.
Nonetheless, dam rehabilitation works resulted in removal of large quantities of topsoil, boulders and in the generation
of concrete debris and other construction wastes. As such, two environmental safeguard policies were triggered: OP
4.01 on Environmental Assessment and OP 4.37 on Safety of Dams. The measures required to address the provisions
of the policies included environmental analyses (EA), environmental management plans (EMP), the hiring of experts to
design, supervise civil works and adhere to certain dam safety measures in the design, tendering, construction, O&M
of the dam and associated works. The government appointed a DSRP to review and advise the IAs on matters related
to dam safety and other critical aspects of the dam, its appurtenant structures, catchment areas, the area surrounding
the reservoir and downstream areas. All other requirements were met. The project remained fully in compliance with
safeguards policies; even with the departure of the PMU’s environmental officer during the last year, there were no
lapses in safeguards implementation and monitoring. Bank ISRs consistently rated safeguards as “Satisfactory”.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 22 of 67
B2. Social Safeguards
61. The project triggered OP 4.11 on Cultural Property and OP 4.12 on Involuntary Resettlement. In both cases, the
project remained in compliance with requirements and the project was consistently rated “Satisfactory”. The former
required Department of Archaeology assistance in the implementation of an archeological impact assessment and an
implementation action plan when dam structures deemed archeologically significant were found. The policy calls for
that structure to be preserved, as was the case of an ancient sluice structure identified at the Urusitawewa site.
62. The policy on involuntary resettlement was triggered but the project did not entail any land acquisition or physical
displacement of people. However, in the case of seven dams, water flows to the reservoir and to connected irrigation
schemes were interrupted in order to conduct detailed technical investigations and rehabilitation works. These
interruptions had adverse impacts on the livelihoods of farmers and others downstream dependent on dam reservoirs.
A Livelihood Support Assistance (LSA) Plan was developed to deal with the hardships faced by affected people. The
plan consisted of several types of activities for about 15,500 affected households. These included a wage assistance
plan which provided wage employment for affected farmers, fishermen, and landless laborers; an alternative crop plan
to assist farmers in growing drought resilient crops; a program to replenish inland fish stocks; a gender action plan; and
a domestic water supply provisioning program. A grievance redress mechanism was established and monthly reports
issued. An oversight committee was established to resolve the complaints with direct participation by stakeholders.
B3. Procurement
63. Procurement was identified as a substantial risk to the project with likely delays in procurement processing.
Indeed, the project experienced significant delays as described in Section III. However, over time, capacity and
proficiency in Bank procurement guidelines improved, as did overall contract management. A strong procurement unit
was established in the PMU which produced a project specific, comprehensive procurement administration manual in
line with Bank guidelines. The risk rating was eventually lowered to “Moderate” and then “Low”. The Bank team
provided close monitoring and there were periodically updated procurement plans and procurement activity
monitoring plans. In addition, considerable training (317 hours) was provided to PMU and IA staff on procurement and
contract management and, indeed, over time, performance on both improved (see Annex 10). The senior procurement
staff in the PMU eventually became the PMU Director for the project.
64. Generally speaking, there were no issues in regard to procurement compliance and the quality, reliability, and
transparency of procurement administration has been satisfactory. The procurement process complied with Bank
procurement rules and procedures. The IAs and PMU demonstrated sufficient capacity in carrying out procurement
activities in a satisfactory manner, including procurement preparation, planning, bidding process, and contract
management. Bank ISRs consistently rated procurement as “Satisfactory”.
B4. Financial Management
65. Financial management (FM) was identified as a moderate risk to the project and was consistently rated
“Satisfactory” in Bank ISRs, reflecting adequate arrangements and capacity for planning and budgeting, funds flow,
disbursement arrangements, internal controls, physical verification of assets, accounting, reporting, and auditing.
There were no concerns regarding staffing or incidents of non-compliance. The fund transfer mechanism was
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 23 of 67
effectively implemented through the Special Dollar Account and there were no cash flow issues. Financial reporting
was carried out in a timely manner and while the PMU was asked on several occasions to ensure consistency between
project records and Client Connection, the quality of reporting was acceptable. Audit reports were timely and were of
good quality. FM arrangements also proved adequate in the execution of the LSAs, as described above.
C. BANK PERFORMANCE
Rating: Satisfactory
C1. Quality at Entry
66. The project reflected the strategic priorities of both the Bank and the government and the development objective
was highly relevant. Costs were underestimated by 27.8 percent but largely because of the difficulties in arriving at a
precise cost without detailed technical inspection of all dams. The project was nonetheless well designed and entailed
a comprehensive technical review that followed well-established, internationally acceptable methodologies. As noted
above, the LSA helped to mitigate the adverse impacts of the dam rehabilitation works on farmers and others
downstream dependent on dam reservoirs and was based on a well-designed and executed outreach campaign to
ensure informed decision making as well as transparency in transactions. Procurement risks were addressed through
a strong procurement unit within the PMU and the preparation of a comprehensive procurement manual in line with
Bank guidelines. The implementation delays at the outset of the project were largely due to internal government
procedures associated with the recruitment of three teams of international consultants. Implementation
arrangements were appropriate and adequately addressed the risks of poor collaboration among different ministries
and dam custodians. All other risks were similarly well founded and properly addressed. As discussed above, there
were a few shortcomings in terms of the M&E framework and limitations to using a conventional investment project
design to support and incentivize the type of institutional reform (establishment of the NCDS) and behaviors
(preparation and updating of O&M manuals) that the project envisioned.
C2. Quality of Supervision
67. The task team undertook 20 formal implementation support missions, not including technical and other visits.
Aide Memoires raised key implementation issues, generally proposed remedies, and were of good quality. Certain
issues, such as establishing the NCDS and delays in preparing O&M manuals, were highlighted multiple times. There
were some minor shortcomings in M&E that were not addressed during supervision. These issues, however, should
not take away from the task team’s focus on development impact, strong implementation, and problem solving,
particularly in the second half of the project implementation period. As noted previously, implementation began
against the backdrop of an on-going conflict and fledgling implementation capacity relative to what was required for a
comprehensive dam safety program with large civil works contracts. Accelerated implementation during the second
half of the AF period allowed the project to finish strong. About 65 percent of total disbursements took place over the
last three years, reflecting, in part, success in addressing bottlenecks and building local implementation capacity.
C3. Justification of Overall Rating of Bank Performance
68. Based on the quality of Bank performance at entry and at supervision, the overall rating for Bank performance is
rated “Satisfactory”.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 24 of 67
D. RISK TO DEVELOPMENT OUTCOME
69. The risk to the project’s development outcomes is relatively moderate and is based on assessment of three aspects
of sustainability: (i) technical sustainability; (ii) institutional sustainability; and (iii) financial sustainability. In terms of
technical sustainability, and as discussed throughout the report, the project helped strengthen capacity and skills
among IAs to maintain asset inventories, dam O&M, water resources planning and management, and the use and
management of hydrometeorological stations and systems. With the remedial works, the expected life of the dams
were extended by another 50 years. New monitoring instruments installed as part of the remedial measures and
modernized HMIS allow for timely and effective detection of problems and risks in dam operation. However, technical
sustainability requires skills transfers to be passed on through formal and informal learning. The NCDS, once
operational, could help strengthen the culture of O&M and public safety to the next generation of engineers.
70. In terms of institutional sustainability, the project imparted a strong institutional strengthening element with the
aim of building the capacity of the IAs in several specialized skills. Those include modem state-of-art dam engineering
principles; risk assessment and dam portfolio management; engineering design and construction quality control; social
and environmental management of dams and basin water resources management; dam safety codes of practices; dam
operation and risk-based maintenance; safety monitoring and inspection; dam emergency preparedness planning;
hydrological & meteorological data management; flood forecasting; groundwater monitoring and analysis; and multi-
sectoral water resources planning, among others. The implementation arrangement that anchored the
implementation responsibility of all three components with the concerned government departments have built a
strong sense of ownership of the project and its outcomes, creating a favorable environment for sustainability. The IAs
themselves should serve as the institutional, skill and information base for post-project water resources management,
to be supported eventually by the NCDS. As discussed earlier, the Bank looks to consolidate and build upon the
project’s institutional achievements, including the WARM-P and ASA that have helped underpin the team’s policy
dialogue with government and development partners.
71. From the financial sustainability perspective, there is a higher awareness of the importance of O&M in ensuring
not only operational efficiency but public safety. Dialogue between the government and the Bank and other
development partners continue to look at options to optimize social, economic and environmental benefits of large
dams as a means for income generation from providing ancillary public services (like mini-hydro systems, recreational
parks, fisheries, eco-tourism, etc.) to supplement O&M funding.
V. LESSONS AND RECOMMENDATIONS
72. The project has delivered many positive results in terms of ensuring sustainable arrangements for O&M of large
dams and improved water resources planning. The following are some good lessons for future Bank assistance.
73. Instrument choice and project design. While the government demonstrated strong ownership and commitment
throughout, the project fell short in establishing the NCDS, despite repeated assurances. The lack of progress on this
important output reflects, in part, the challenges of supporting policy and institutional reforms through a conventional
investment project design. As the Bank intends to continue to support Sri Lanka’s water sector, there are various
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 25 of 67
instruments and approaches to support future reform efforts, starting with high level policy dialogue underpinned by
ASA and complemented by technical assistance, as well as more results-based approaches to program financing.
74. Comprehensive water sector framework. Beyond instrument choice, broader reforms are needed to put in place
a national policy, legal, and institutional framework for the integrated management of water resources. The slow
progress with regard to the NCDS is symptomatic of the broader challenge of instituting a national, inter-ministerial
framework, which can only be achieved through strong government ownership and a bottom-up approach to policy
and institutional reforms. The major water sector agencies need to be willing to address water resources development
and management needs, taking into account competing demands for water and associated social, economic, and
environmental dimensions. To this end, the project’s water resources development plans and the cross-agency
collaboration undertaken to identifying priority investments were a small but important step toward a more integrated
water resources framework which the WARM-P looks to address more fully in the coming years.
75. Implementation arrangements. Many of the core responsibilities of implementation were transferred to the IAs
during the AF period and the role of the PMU gradually became confined to coordination and monitoring. Though
empowering line ministries is critical to promoting ownership, institutional development, and sustainability, a strong
entity at the central level is important for addressing broader cross-ministerial and technical issues. The weakened
role of the PMU in the last few years in particular contributed to the lack of progress on the national dam safety entity.
76. Building and sustaining capacity. The ability of the IAs to take the lead in implementing the project during the AF
phase reflects the strong capacity developed during the initial phase of the project. While the ISCs took the lead on
key aspects of implementation, there was very close collaboration with IA staff, resulting in knowledge transfer. Formal
training was also emphasized throughout the project. This allowed sufficient capacity to be built to take over
responsibilities of the ISCs once the AF was requested. This level of capacity will need to be sustained as senior
engineers and dam operation staff retire or move on. Once fully operational, the NCDS is expected to help continue
capacity strengthening and instill a culture of dam safety and O&M among younger engineers and dam operators.
77. Climate change adaptation. As discussed, the project’s objectives continue to be highly relevant to both the Bank
and government, particularly in light of climate change and predicted climate variability. Sri Lanka is considered highly
vulnerable to climate change, which is projected to, inter alia, result in more frequent and severe flooding. While dam
safety is critical to government’s efforts at adaptation, so too are efforts to improve watershed management to reduce
vulnerability and enhance adaptive capacity. Building on the project’s achievement, the WARM-P will continue the
dam safety program, complemented by activities to restore and rehabilitate watersheds to promote sustainable land
and water management practices, thereby reducing degradation, erosion, and improving flood control.
78. Project management. Given the 10-year duration of the project, there are a number of useful lessons learned
from the Bank’s and government’s management of the project. The ICR highlights a few salient issues, including the
need to ensure good contract management and the monitoring of contractor practices to reduce delays; the focus
on capacity building through formal and informal knowledge and skills transfer; the importance of maintaining a
strong implementing unit to not only competently execute core tasks but also to lead on broader strategic issues; and
the need to ensure results indicators are well defined and measurable. .
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 26 of 67
ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS
A. RESULTS INDICATORS A.1 PDO Indicators
Objective/Outcome: PDO1: Establish long-term sustainable arrangements for O&M of large Dams
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
(Reduced) Number of Large Dams with Unacceptable Risk Index
Number 63.00 0.00 0.00 0.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): Additional financing project paper in 2014 proposed an increase in total dams to be rehabilitated to about 62. This was changed to 63 shortly afterward. The indicator was also modified and the word "reduced" was deleted. 100% target achieved.
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Dams with need-based operation and maintenance (O&M) plans operationalized.
Number 0.00 32.00 63.00 63.00
01-Jul-2008 30-Jun-2013 15-May-2018 28-Sep-2018
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 27 of 67
Comments (achievements against targets): 55% target achieved at project closing date. 100% target achieved by end-September 2018.
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Direct project beneficiaries Number 0.00 0.00 1030000.00 1348000.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Female beneficiaries Percentage 0.00 0.00 535000.00 754000.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 131% of the target achieved. Objective/Outcome: PDO 2: Improve Water Resources Planning
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Improved water database utilized by IAs for flood forecasting, dam operations, and water allocations.
Number 0.00 32.00 32.00 32.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% target achieved.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 28 of 67
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
National Water Use Master Plan and at Least One River Basin Development Plan adopted by the Cabinet of Ministers
Text No National Water Use Plan and river basin plan exist.
Mundeni Aru Basin plan completed
National Water Use Master Plan and at 2 River Basin Development Plans adopted by the Cabinet of Ministers.
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% achieved for two basin development plans and National Water Use plan adopted by cabinet.
A.2 Intermediate Results Indicators
Component: Component 1: Dam Safety and Operational Efficiency Improvements
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Large dams rehabilitated with necessary remedial measures.
Number 0.00 32.00 63.00 63.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% target achieved.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 29 of 67
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Dams provided with basic safety facilities
Number 0.00 80.00 80.00 80.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% target achieved.
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Dam Safety Inspectorate with essential guidelines and procedures established and operational
Text Dam Safety Inspectorate does not exist.
Dam Safety Inspectorate Fully operational
Mixed Progres
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): The National Center for Dam Safety (NCDS) was formally established but is not yet fully operational.
Component: Component 2: Hydro-metrological information system
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Hydrometric stations and agro-meteorological stations established/upgraded and
Amount(USD) 0.00 50.00 142.00 167.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 30 of 67
functional
Comments (achievements against targets): 118% of the target achieved.
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Hydrology and meteorology databases developed and accessible by different users
Text Databases do not exist.
Database fully operational and accessible by different users
Databases developed, accessible, and in use by IAs.
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% target achieved.
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Basic groundwater monitoring system with sufficient number of observation points established
Number 0.00 0.00 8.00 8.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% target achieved. Eight pilot groundwater monitoring systems established.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 31 of 67
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Staff trained for O&M of HMIS
Number 0.00 50.00 142.00 167.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 118% of the target achieved.
Component: Component 3: Multi-Sector Resources Planning
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
A national water use master plan developed
Text Plan does not exist. Plan finalized and adopted.
Plan fully developed.
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% target achieved.
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Mahaweli basin development plan updated
Text Plan exists but outdated.
Updated Plan completed and adapted.
Plan fully updated.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 32 of 67
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% target achieved.
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Water resources development plan for Mundeni Aru river basin developed
Text Plan does not exist. Basin Plan finalized. Plan fully developed.
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% target achieved.
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Core team, in number of staff, trained for multi-sectoral water resources planning.
Number 0.00 12.00 15.00 10.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 67% target achieved. Government realized that only 10 core staff were needed for multi-sectoral water resources planning.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 33 of 67
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Feasibility studies prepared for key interventions identified in the various Plans
Number 0.00 0.00 6.00 8.00
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 133% target achieved.
Component: Component 4: Project Management, Monitoring and Evaluation
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Timely completion/update of annual work programs, progress reports, FMRs, procurement plans
Text No N/A Yes
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
Comments (achievements against targets): 100% target achieved.
Indicator Name Unit of Measure Baseline Original Target Formally Revised
Target
Actual Achieved at Completion
Cumulative physical and disbursement performance targets do not fall below 80%
Text No N/A Yes
01-Jul-2008 30-Jun-2013 15-May-2018 15-May-2018
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 34 of 67
of trhe cumulative targets after Year 1
Comments (achievements against targets): 100% target achieved after Year 3.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 35 of 67
B. KEY OUTPUTS BY COMPONENT
Objective/Outcome 1: Establish long-term sustainable arrangements for O&M of large Dams
Outcome Indicators
1. Number of large dams with unacceptable risk index
2. Dams with need-based O&M plans operationalized
3. Direct project beneficiaries
Intermediate Results Indicators
1. Large dams rehabilitated with necessary remedial measures
2. Dams provided with basic safety facilities
3. Dam Safety Inspectorate with essential guidelines and procedures established
and operational
Key Outputs by Component
(linked to the achievement of the Objective/Outcome 1)
Component 1. Dam Safety and Operational Efficiency
1. Large dams rehabilitated / modernized
2. O&M plans for rehabilitated / modernized dams operationalized
3. All large dams provided with basic safety facilities
4. Emergency action plans prepared for 13 critical dams
5. Central electronic database stores key data on dam
6. Dam Safety Inspectorate (National Center for Dam Safety) established
7. Flood control center established for Mahaweli River Basin
8. Staff trained on dam safety and O&M
9. Training center rehabilitated
Objective/Outcome 2: Improve water resources planning
Outcome Indicators 1. Improved water database utilized by IAs for flood forecasting, dam operations,
and water allocations
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 36 of 67
2. National water use master plan and at least one river basin development plan
adopted by the Cabinet of Ministers
Intermediate Results Indicators
1. Hydrometric stations and agro-meteorological stations established/upgraded
and functional
2. Hydrology and meteorology databases developed and accessible by different
users
3. Basic groundwater monitoring system with sufficient number of observation
points established
4. Staff trained for O&M of HMIS
5. National water use master plan developed
6. Mahaweli Basin development plan updated
7. Water resources development plan for Mundeni Aru river basin developed
8. Core team, in number of staff, trained for multi-sectoral water resources
planning
9. Feasibility studies prepared for key interventions identified in the various Plans
Key Outputs by Component
(linked to the achievement of the Objective/Outcome 2)
Component 2. Hydro-Meteorological Information System
1. Hydrometric stations and agro-meteorological stations established/upgraded
2. Data centers housing hydrology and meteorology databases established
3. Groundwater monitoring pilot conducted
4. Staff trained on HMIS O&M and data analyses, groundwater monitoring
Component 3. Multi-sector Water Resources Planning
1. National water use master plan developed
2. Mahaweli Basin development plan updated
3. Mundeni Aru River Basin development plan developed
4. Staff trained on multi-sectoral water resources planning
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 37 of 67
5. Feasibility studies prepared for key interventions identified in the various plans
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 38 of 67
ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION
A. TASK TEAM MEMBERS
Name Role
Preparation
Nihal Fernando Task Team Leader,
Xiaokai Li Co-Task Team Leader, Water Resources
Ohn Myint Dam Engineering and Costing (Consultant)
Seeniathamby Manaoharan Implementation Arrangements and Coordination
Suryanarayan Satish Social Development Specialist
Walter A Garvey Water Resources River Basin Planning (Consultant)
Nagaraja Harshadeep Rao Hydrological Models and DSS Tools
Sumith Pilapitiya Environmental Safeguards
Supervision/ICR
Shyam KC Task Team Leader(s)
Asif Ali, G. W. Anjali U. Perera Vitharanage, Sunethra
Chandrika Samarakoon
Procurement Specialist(s)
Bernadeen Enoka Wijegunawardene Financial Management Specialist
Zakia B. Chummun Team Member
Joop Stoutjesdijk Team Member
Cecilia Belita Team Member
Anju Gaur Team Member
John Factora Team Member
Samanmalee Kumari Sirimanne Team Member
Seenithamby Manoharan Team Member
Rolande Simone Pryce Team Member
Susrutha Pradeep Goonesekera Social Safeguards Specialist
Prabha Kumari Perera Team Member
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 39 of 67
Jun Matsumoto Team Member
Suranga Sooriya Kumara Kahandawa Team Member
Mokshana Nerandika Wijeyeratne Environmental Safeguards Specialist
B. STAFF TIME AND COST
Stage of Project Cycle Staff Time and Cost
No. of staff weeks US$ (including travel and consultant costs)
Preparation
FY05 10.660 48,160.56
FY06 13.851 43,563.41
FY07 46.445 324,996.93
FY08 15.985 80,877.88
Total 86.94 497,598.78
Supervision/ICR
FY08 4.750 20,884.72
FY09 21.490 80,724.27
FY10 13.025 60,204.14
FY11 19.655 78,320.34
FY12 19.363 113,071.13
FY13 13.975 73,765.33
FY14 19.039 152,223.65
FY15 15.632 66,793.81
FY16 21.275 121,687.83
FY17 23.927 187,270.47
FY18 23.817 189,867.85
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 40 of 67
FY19 5.582 39,037.63
Total 201.53 1,183,851.17
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 41 of 67
ANNEX 3. PROJECT COST BY COMPONENT
Components Amount at Approval
(US$M)
Actual at Project
Closing (US$M)
Percentage of
Approval (%)
1. Dam Safety and
Operational Efficiency
Improvement
125.0 115.9 92.7
2. Hydrometerological
Information Systems
Improvement
11.4 14.4 126.4
3. Multi-Sectoral Water
Resources Planning 10.5 7.5 71.7
4. Project Management,
Monitoring and Evaluation 7.8 4.9 63.3
Total 154.7 142.8 92.3
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 42 of 67
ANNEX 4. EFFICIENCY ANALYSIS
Background
1. Although Sri Lanka’s economy is shifting towards industry and services, agriculture still plays a key role (7.5
percent of GDP and 27.1 percent of employed population) especially in rural economy. However, aging reservoirs
are threatening the life of local residents and infrastructures, as has been witnessed in the accident in 1986
where the Kantale tank in Trincomalee District breached, killing over 100 people, destroying 1,600 houses and
800 ha of paddy and affecting over 8,000 families.
2. This project was implemented to reduce the probabilities of dam failure and ‘artificial flood’ caused by lack
of hydro-met information in the upstream and dam mismanagement through: i) remedial works of dam facilities;
and ii) establishment and upgrading of hydro-meteorological stations. The primary beneficiary of the project is
both urban and rural population of over 0.5 million in the downstream area of target dams, who could be placed
at physical risk in the case of dam failure.
Methodology
3. To keep consistency with the past appraisals of the project, the project benefit was defined as the difference
of expected value of flood and dam failure damage with project and without project scenario. The expected
damage value for each scenario was calculated as product of dam failure (or flood) probability and damage
caused by dam failure (or flood).
4. Economic analysis for this project has been conducted twice to date, i.e. original appraisal in 2008 and
appraisal for additional finance (AF) in 2014. As is summarized in Table A4.1, each appraisal covers different
dams and different methodologies. In order to analyze the project viability from different angles but in a
consistent manner, the ICR-stage economic analysis was conducted with four different scopes, i.e. i) 32 dams for
Phase 1, ii) 5 portfolio dams for Phase 2, iii) 31 dams for Phase 2, and iv) entire 63 dams of Phase 1 and 2. For
benefits, both dam failure and flood was considered as source of reduced damage.
Table A4.1: Scope of past economic analyses
Original
appraisal (2008)
Additional Finance appraisal (2014)
Dams
covered
Phase 1 Entire 32 dams Entire 32 dams
Phase 2 N/A 5 sample dams
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 43 of 67
Benefits covered Reduced
damage by dam
failure and flood
Fixed benefit11 Reduced
damage of dam
failure
5. The key assumptions used in the ICR-phase economic analysis are as follows:
i ) The period covered by the analysis is in accordance with the estimated project life of 25 years,
which spans over 2008 to 2032.
ii ) The exchange rate of Sri Lanka Rupee (Rs) to US Dollar (USD) in 2008 to 2018 is based on the
rate by the Central Bank of Sri Lanka.
iii ) The cost of annual O&M is assumed to be 0.3 percent of the total capital investment for
respective dams.
iv ) The economic discount rate is 12 percent.
v ) All the capital investment amount during the project (nominal or current prices) are converted
to the real (or constant) prices as of 2008 using the inflation rate by the Central Bank of Sri
Lanka. (The average inflation rate in 2008 to 2018 is 5.1 percent per year.)
vi ) Standard Conversion Factor (SCF) is not applied to convert domestic financial prices to
economic prices for couple of reasons12.
vii ) The unit prices used for project benefit (avoided flood damage) estimation is based on Jacobs
Gibb study (2004)13. All the unit prices are converted to the prices in 2008 using the inflation
rate by the Central Bank of Sri Lanka. Current beneficiary population is estimated using the rate
of national population growth by the Department of the Census and Statistics of Sri Lanka. (cf.
Table A4.2 and A4.3)
viii ) Probability of failure of each dam increases by 4 percent per year irrespective of dam
rehabilitation works. (e.g. If the failure probability of a dam is 0.1 percent in a certain year, it
increases to 0.104 percent in the next year.)
11 Rs 1.25 million per year was allotted as the fixed benefit from the project after the completion.
12 i) the cost breakdown of domestic/import materials and labor for respective 63 dams was not available; ii) according to the
Central Bank of Sri Lanka, the SCF in 2014 is 0.97, which translates to quite small impact by the use of SCF; and iii) past
appraisals of the project did not use SCF either.
13 Jacobs Gibb (2004) Activity 18: Protfolio Safety / Conservation Review, Risk & Economic Assessment, Dam Safety & Reservoir
Conservation Program, Mahaweli Authority of Sri Lanka.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 44 of 67
Table A4.2: Unit prices for damage estimation
No. Items (unit) Original value in
Jacob Gibbs (2004)
Adjusted value
in 2008 prices
1 Damage to houses14 (Rs. per unit) 200,000 309,931
2 Damage to public buildings 50% of housing damage
3 Damage to major roads (Rs. per km) 1,750,000 2,711,895
4 Damage to local roads (Rs. per km) 1,000,000 1,549,654
5 Damage to railways (Rs. per km) 10,000,000 15,496,541
6 Damage to agriculture (Rs. per ha) 100,000 154,965
7 Loss of economic production (Rs. per
capita)
325,000 503,638
8 Loss of hydropower generation
(Rs. per kWh)
10 15
9 Intangible cost 20% of tangible cost15
10 Dam replacement cost (Rs.) 50,000,000,000*(h/100) ^3
h: dam height (m)
77,482,706,400*(h/100) ^3
h: dam height (m)
6. Table A4.3 presents the key figures describing overall extent of target dams and beneficiaries.
Table A4.3: Key figures related to target dams and beneficiaries
Items Value
Population at risk 547,208
Houses (20% of population) 103,580
Paddy area (ha) 248,672
Hydropower capacity (MW) 924
Major road length (km) 117
Local road length (km) 524
Railway length (km) 51
Costs
7. The actual and estimated cost build-up of the project is shown in Table A4.4. The project had encountered
some delay at the initial stage but gained acceleration in the second half of the entire project period. For cost
calculations, government contributions to the project have been included in addition to the loan from the World
14 It is assumed one house is resided by 5 persons. Therefore, the number of houses is one-fifth of population.
15 Tangible cost is defined as the sum of item 1 to 8 in Table A4.2.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 45 of 67
Bank. The O&M cost of 0.29 million per year (0.3 percent of total capital expenditure for dam remedial works)
was also allocated for each year after the close of project period.
Table A4.4: Estimated and actual disbursement schedule
Unit: million Rs.
Year Planned Actual
2008 2.4 0.0
2009 10.1 0.4
2010 20.3 8.3
2011 20.5 5.5
2012 10.3 8.3
2013 1.8 19.3
2014 10.0 13.2
2015 15.0 17.3
2016 28.0 16.2
2017 25.0 24.9
2018 5.0 25.1
Total 148.3 138.5
Benefits
8. The primary benefits gained through the project includes: i) reduced risk of dam failure, and ii) reduced risk
of floods caused by inappropriate dam operation due to lack of hydro-meteorological information in the
upstream catchment area. These benefits are calculated as the product of reduced probability of disaster
occurrence (dam failure or flood) and expected damage and loss caused by respective disasters. Through the
review of past documents, it was noted that the additional finance appraisal in 2014 counted only reduced risk
of dam failure as project benefit, while the original appraisal counted both dam failure and flood. It was also
found that the additional finance appraisal overvalued the probability of dam failure cited from Jacobs Gibb
study (2004) by 10 times. If correct values of failure probability are applied, both ERR and NPV will turn to
negative values (-4.49 percent and -713 million USD, respectively). Given these discrepancy in the benefit
calculation methodology in the past appraisal, this report follows the benefit counting of original appraisal which
considers both dam failure and flood as source of benefit.
9. Ideally, estimated flood damage is to be calculated through numerical flood simulation models for each
flood cases with different return-period. These models require extensive input data such as historical
rainfall/river flow monitoring record, grid-wise topography, longitudinal/cross-sectional river profile and so on.
Due to the constraints of time and financial resources, under current analysis, expected values of flood damage
was estimated by simple linear regression model developed through the flood simulation results conducted at
the original appraisal in 2008. Population at risk, which showed highest correlation with flood damage value,
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 46 of 67
was selected as explanatory variable to estimate the damage amount caused by floods with different return-
period.
10. Following past appraisals, the unit cost for respective damage and loss factors were cited from Jacobs Gibb
(2004), which are summarized in Table A4.2. For Phase 1 dams, the benefit of three dams, i.e. Victoria,
Randenigala and Kotmale, that accounts for 28 percent of total cost for the phase are calculated respectively
and those of other 29 dams are calculated in aggregated manner. For Phase 2 dams, benefit of all 31 dams are
calculated in aggregated manner, since the probability of failure are not available for some of the target dams.
It should also be noted that some of the benefit factors are not included in the current analysis due to the
difficulty of quantification. These include: i) reduction of human life mortality and injuries caused by dam failure
or floods; and ii) improvement of agricultural productivity downstream of the dam, which was reported by
farmers but direct assessment was not feasible due to data constraints.
Results of the economic analysis
11. The results of economic analysis are summarized in Table A4.5. In all cases, the updated ERR showed higher
value than past appraisals. This increase is attributed mainly to the decrease in the capital investment value in
real (constant) prices as of 2008. While the nominal (current) total capital investment amount was almost
equivalent to those envisaged in the appraisal, it is reduced by more than 20 percent when converted to real
prices of 2008 by applying the inflation rates of respective years, which are as high as 5 percent on average16. In
other words, we can say that the project was implemented quite efficiently despite the high inflation rate during
the project period. On the other hand, the NPVs did not show as much increase as ERRs. Since the cash flow data
for the economic analysis of past appraisals are no longer available, it is hard to identify the cause behind this
inconsistency, but these results imply less nominal benefit values in the CRR than past appraisals.
12. Phase 1: While same tendency (higher ERR) as the overall results are observed with Phase 1, it should be
also noted that the benefit from the three portfolio dams, i.e. Victoria, Randenigala and Kotmale, accounted for
more than 50 percent of the total benefit generated through the phase. The annual project benefit was between
Rs. 1.24 to 1.31 billion.
13. Phase 2: The results of ICR- and additional finance -stage economic analyses are not comparable, since the
methodology adopted for benefit counting differs significantly. However, what is to be noted is, when compared
with the results of Phase 1, the entire 31 dams of Phase 2 show lower ERR (16.8 percent), while the ERR of 5
portfolio dams is as high as 30.6 percent. This implies that the dams selected for Phase 2 are less efficient in
terms of economic return. However, the ERR is still higher than 12 percent, which means the investment itself
16 In principle, project economic analysis is conducted in real (constant) prices, which are nominal (current) prices adjusted with
the inflation rate. This is based on the assumption that inflation affects the prices of both inputs and outputs equally. By using
real prices, the analysis can avoid the impact of unpredictable inflation (or deflation) in the future. (cf. ADB (2017) Guidelines
for the Economic Analysis of Projects)
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 47 of 67
can yet be economically viable. The fact that is not reflected in the analysis is that many of the dams of Phase 2
are located in the northeastern part of the country which was devastated by the civil war, therefore, the project
has also achieved indirect positive impacts on the reconstruction of post-conflict area.
14. Entire project: The ERR and NPV of entire 63 dams were 26.6 percent and Rs. 2.6 billion respectively. The
viability of entire project is thus confirmed as envisaged at the original and additional finance appraisal.
Table A4.5 Summary result of economic analysis
ERR NPV
(Rs. million)
Phase 1
(32 dams)
Original appraisal 18.8% 2,371
AF appraisal 15.0% 670
ICR 28.9% 2,368
Phase 2
(Portfolio of
5 dams)
AF appraisal17 17.9%
(-4.5%)
320
(-712)
ICR 30.6% 249
Phase 2
(31 dams)
AF appraisal N/A N/A
ICR 16.8% 224
Phase 1 + 2
(63 dams)
ICR 26.6% 2,592
Sensitivity analysis
15. Sensitivity analysis of economic viability of the project was conducted for Phase 1, Phase 2 and the entire
project (Phase 1 + 2) respectively. Although the ERR of Phase 2 in the scenario of benefit decrease showed the
values slightly below 12 percent threshold, the ERR of entire project still shows robust economic viability with
any scenarios. Increase in the O&M cost, which is very likely in growing economies like Sri Lanka, has negligible
impact on the economic viability, while the decrease of benefit has relatively large impact.
17 Values in parenthesis are those when correct probability of dam failure is applied for economic analysis. As described at, AF
appraisal overvalued the probability of dam failure by ten times, while excluding the benefit of flood damage mitigation.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 48 of 67
Table A4.6 Summary results of the sensitivity analysis
ERR NPV (Rs. Million)
Ph.1 Ph.2 Ph.1+2 Ph.1 Ph.2 Ph.1+2
Base case 28.9% 16.8% 26.6% 2,368 224 2,592
O&M cost at 150% of the
base case
28.9% 16.7% 26.5% 2,355 216 2,571
Benefit at 80% of the base
case
22.2% 11.7% 20.0% 1,431 -13 1,418
O&M cost at 150% &
benefit at 80% of the base
case
22.2% 11.5% 19.9% 1,418 -21 1,397
Conclusions and recommendations
16. Recalculation of ERR and NPV at ICR stage confirmed the economic viability of Phase 1, Phase 2 and the
entire project, thus justifying the investment over the last decade. It is to be noted that some of the benefits
materialized from the project, such as reduction of death casualties from floods, increase of agricultural
productivity and contribution to the reconstruction of post-conflict area were not included in the current analysis
due mainly to the difficulty in quantification.
17. There are essentially two lessons learned in terms of economic analysis obtained through ICR preparations.
Firstly, the data used for appraisal-stage economic analysis should be handed over until the project closure or
even after that. Ideally, ICR-stage economic analysis should adopt consistent methodology as the appraisal-
stage, but this was not the case with the current analysis since the calculation spreadsheet was lost over the
decade-long project implementation period and little clues for recalculation was left on the appraisal document.
Therefore, this ICR had to conduct economic analysis almost from scratch, resulting in incomparability of key
parameters, i.e. ERR and NPV, between different project stages.
18. Secondly, key parameters for economic analysis should be included in the results framework of the project.
In the case of current project, some of the statistical parameters such as affected population and irrigation
command area, are subject to change over project period, and this may have significant impact to the project
benefit. However, such time-dependent change was not captured in the current analysis due to the lack of latest
data. The quality of economic analysis can be improved if at least key parameters are included in the M&E
framework.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 49 of 67
ANNEX 5. BORROWER COMMENTS
The External Resources Department (ERD) of the Government of Sri Lanka circulated the ICR report among the
different stakeholders and the comments below were received by the Ministry of Mahaweli Development and
Environment (MMDE). The Bank concurs with these comments which are reflected in the ICR. A second letter
from MMDE was received on November 30, 2018 reiterating the Ministry’s concurrence with the ICR findings.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 50 of 67
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 51 of 67
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 52 of 67
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 53 of 67
ANNEX 6. THEORY OF CHANGE
Activities Project Outputs
Project Development
Objectives / Outcomes
Longer Term
Outcomes
Co
mp
on
ent
1
• Remedial works for high-risk
dams
• Provision of basic safety
facilities for large dams
• Training for strengthening
dam-owning organizations
• Studies and supply of
specialized equipment
• Livelihood Assistance Plan
for affected communities
1. 63 large dams rehabilitated with
necessary remedial measures
2. 80 large dams provided with
basic safety facilities
3. Dam Safety Inspectorate with
essential guidelines and
procedures established and
operational
PDO 1. Establish long-term
sustainable arrangements for
O&M of large dams
1. Reduced number of large
dams with unacceptable risk
index
2. Need-based O&M plans
operationalized in select
dams
PDO 2. Improve water
resources management
3. Improved water database
utilized by implementing
agencies for flood
forecasting, dam operations
and water allocations
4. National water use master
plan and at least one river
basin development plan
adopted by the cabinet
Effective management
and development of
water resources and
hydraulic assets help
prevent or mitigate
natural disasters and
contribute to
productive sectors and
communities,
economic growth, and
poverty reduction.
Co
mp
on
ent
2
• Establishment and upgrading
of hydrometric stations
• Establishment of a databases
at ID & MASL
• Flood protection procedures,
tools and training for
analysis of flood inflows to
major reservoirs
• Establishment of a
groundwater monitoring
system
1. Hydrometric stations and agro-
meteorological stations
established / upgraded and
functional
2. Hydrology and meteorology
databases developed &
accessible by different users
3. Staff trained for O&M of HMIS
4. Basic groundwater monitoring
system with sufficient number
of observation points
established
Co
mp
on
ent
3
• Preparation of a National
Water Use Plan
• Updating the Mahaweli
Water Resources
Development Plan
• Preparation of a Water
Resources Development Plan
for Mundeni Aru River Basin
• Train core staff on integrated
water resources planning
• Prepare feasibility studies of
priority developments
1. A national water use master
plan developed
2. Mahaweli Basin Development
Plan updated
3. Water resources development
plan for Mundeni Aru river basin
developed
4. A core team trained for
integrated multi-sectoral water
resources planning
5. Feasibility studies prepared for
key interventions identified in
the various plans (AF)
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 54 of 67
ANNEX 7. TYPICAL OPERATIONAL DEFICIENCIES OF DAMS AND REMEDIAL MEASURES
No. Problems existed Remedial measures attended
1 Bund-related activities
1.1 Inadequate free-board, steep
upstream and downstream slopes,
weak sections of the bund
Raised the bund, renovated slopes as per designed specifications,
and strengthened the weak sections by providing berms - filling and
compacting of selected earth and planted strip turf to new earth
fill.
1.2 Slope sloughing, slips, settlements,
cracks along the dam crest,
settlement of abutments, and erosion
Constructed loading berms, removed and re-filled some sections
with necessary compaction;
Removed dead trees, anthills and filled with suitable material and
compacted.
1.3 Seepage boils and leakages in the
downstream of the dam
Provided toe-filters, drains, loading berms, fixed Piezometers to
assess the pore-water pressure & weirs to measure seepage flow;
Cleared the toe road for easy inspections
1.4 Collapsed rip-rap and eroded
upstream slopes due to wave actions
Removed the disturbed rip-rap, earth-filled and compacted the
upstream slope, placed Geotextile along the U/S slope and
replaced/ repaired the riprap up to a maximum 600 mm depth.
1.5
In concrete dams, malfunctioning of
equipment, weak conditions in pre-
tension cables and accessories
Replaced most of the equipment; checked the pre-tension cables
and replaced the weak cables.
2 Remedial measures in sluices/ outlets and spills
2.1 Damaged/mal-functioning of gates,
hoisting mechanisms, electro-
mechanical work in sluices & spills
Repaired and improved the concrete structures, sluice barrels,
replaced or repaired the damaged gates, and painted them.
Attended to all electro mechanical works.
2.2 Damaged spills, the inadequacy of
discharge in an emergency situation,
damaged stilling basin and other
Fabricated and installed new radial gates for selected spills, fixed
hoisting arrangements, improved stilling basins, and other civil and
electro-mechanical work.
3 Access
3.1 The public roads on the bunds were
highly damaged
Repaired and improved all bund roads (metalling and tarring);
Improved the access roads.
3.2 Damaged bathing places and other
related activities
Renovated or constructed new bathing places, constructed small
bridges and culverts.
3.3 Encroachments into reservations in
some schemes
Surveyed and fixed permanent concrete posts along the bund
channels or water holding area in some selected schemes.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 55 of 67
ANNEX 8. DETAILS OF DAM SAFETY REHABILITATION
Phase 1 Dams
No Name of the
dam / Agency
Tank Charac-teristics
Remedial measures in Bund Remedial measures
in Sluices Remedial measures
in Spills Other relevant activities
Total cost Rs M
Risk Index
Reduction
1 Nachchaduwa (ID) T- HE
L- 1646 m H- 11m C-55.7 mcm
Installation of Safety and Monitoring Facilities (SMF), improvements to dam including replacement of Rip Rap, construction of toe filter and toe drain
Improvements to RB high level sluice and RB low level sluice
Repairs the spill way wall, spill way gates, reinstall gantry crane, electrification for operations
Construction of access roads, Construction of bathing places, Improvements to foot bridge,
138.5 85%
2 Kaudulla (ID) T-HE
L- 9236 m H- 15m C-64 mcm
Installation SMF, improvements of tank bund and replacing Rip Rap, construction of toe drain
Improvements to LB and RB sluices
Improvements to spill way
Construction of bathing places
328.8 72%
3 Minneriya (ID) T-HE
L- 2332 m H- 21m C-136 mcm
Installation of SMF, improvements to the dam, Construction of toe drain
Improvements of sluices
Improvements of main spill way
Improvements of access road, construction of bathing steps,
168.3 73%
4 Ridiyagama (ID) T-HE
L- 5000 m H- 8.5 m C-27 mcm
Installation of SMF, improvements to dam, replacement of Rip Rap, construction of toe filter & toe drain
Repairs to LB sluice including electro-mechanical works
Improvements to spill ways 1 and 2
Construction of bathing steps and other
239.6 89%
5 Nalanda (ID) T-CG
L- 123 m H- 31m C-15 mcm
Installation of SMF, Improvements of concrete dam including d/sside work
Improvements to outlets control valves
Reinstallation of spill way,
309.7 91%
6 Nuwarawewa (ID) T- HE
L- 6500 m H- 11m C-44 mcm
Installation of SMF, improvements of dam, construction of toe drain, improvement of Rip rap,
Improvement to Right and Left bank sluices
Improvements to RB spill way including foot bridge over it.
Construction of access road, bathing place and inspection steps
428.95 77%
7 Kantale (ID) T- HE
L- 2300 m H- 18 m C-135 mcm
Installation of SMF, Improvements to the dam, Construction of toe drain and Rip rap improvement,
Electro mechanical work, repairs in sluices and electrification
Improvements to spill way, Electro mechanical work, radial gates to spill
Improvt. of access road, construction of bathing and inspection steps Connecting tank bund with Vendarasn
118.8 72%
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 56 of 67
8 Giritale (ID) T- HE
L- 550 m H- 23m C-24 mcm
Improvements to dam, construction of toe drain, Replacing and extension of Rip rap, work related to the saddle dam,
Repairs t LB and RB sluices and electro mech.l work in RB sluice
Construction of access road, bathing and inspection steps
131.19 81%
9 Vandarasan (ID)T- HE
L- 1143 m H- 16 m C-245mcm
Installation of monitoring and safety facilities, construction of toe drain and toe filter, Improvements of dam, Rip rap replacement.
Improvements to LB and RB sluices, electro-mechanical work in sluices
Improvement to spill way
Construction of bathing and inspection steps,
153.22 89%
10 Tabbowa (ID) T- HE
L- 1910 m H- 9 m C- 19mcm
Installation of SMF, Improvements to tank bund, Rip rap & Construction of toe drain,
Construction of LB sluice and outlet structure, improvement to center sluice, & RB sluice
Improvements to spill way gates
Construction of access roads, bathing & inspection steps, Improvements to foot bridge,
220.55 88%
11
Usgala Siyambal angamuwa (ID) T- HE
L- 1433 m H- 4 m C-27mcm
Installation of SMF, Bund raising, slope stabilization& seepage control, toe dam, replacement of Rip rap,
Improve LB & RB sluices & electro improvement work
Refurbishment of spill ways No.2 and 3
preliminaries, bathing steps etc. access roads
157.26 84%
12 Tissawewa (ID) T-HE
L- 3480 m H- 11 m C-4.3 mcm
Installation of SMF, improvements to bund, construction of toe drain, Replacement of Rip Rap,
Repairs to center and RB sluice, seepage control of LB sluice, mechanical work in LB and RB sluices
Repairs to concrete in LB spill way
Construction of access road, construction of bathing and inspection steps
150.68 75%
13 Huruluwewa (ID) T-HE
L- 2377 m H- 25 m C-67 mcm
Installation of SMF, Improvements to dam, construction of toe drain and toe filter, improvement to Rip rap
Repairs to LB, RB and Center sluices, electro mechanical work in sluices
Repairs of spillway, Improvements to natural spill way, electro mechanical work
Construction of access roads, Construction of bathing, inspection steps,
150.2 86%
14 Inginimitiya (ID) T-HE
L- 4115 m H- 24 m C-72 mcm
Installation of inspection and monitoring facilities, improvement to tank bund including to U/s slope, Construction of toe drain,
Repairs to sluices and electro mechanical work.
Repairs to cubicle room at spill way, electro mechanical work, Repairs to radial gates
Additional funds for tank bund road.
146.7 75%
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 57 of 67
15 Parakrama Samudra (ID) T-HE
L- 12300 m H- 15 m C-134 mcm
Installation of SMF, Improvement to tank bund, construction of loading berm and toe drain, improvement to Rip Rap,
Repairs to sluice tower, repair and electro mechanical work in sluices
Repairs of spill way, electro mechanical work, radial gates to main spill way, and electrification
Construction of access road, construction of bathing and inspection steps and bathing steps,
181 73%
16 Rajangana (ID) T- HE
L- 4043 m H- 18.3 m C-100.6 mcm
Installation of safety and monitoring facilities, Improvements to tank bund, rip rap establishment, Construction of toe drain,
Repairs to LB and RB sluices, Electrification and automation of radial gates (
Spill way repair, Replacement of 15 Nos radial gates (27.02 m), stage Ii, Radial gates
Construction of access roads, bathing steps,
270.8 69%
Average cost per scheme = Rs 206 million Total 3,294 80%
No Name of
the dam / Agency
Tank Charac -terictics
Remedial measures in Bund Remedial measures in
Sluices Remedial measures
in Spills Other
Total cost Rs M
Risk Index
Reduction
17 Chandrikawea (MASL) T- HE
L- 2500 m H- 19 m C-27 mcm
Installation of SAF, improvements of the dam, construction of toe drain and berms, Rip rap
Repairs to sluices, mesh fencing of sluice gates,
Improvements to spill way, construction of gabion wall
Construction of access roads, construction of bathing steps,
281.3 91%
18 Rantambe (MASL) T-CG
L- 420 m H- 41.5 m C-11.5 mcm
Installation of SAF, improvements to the dam, construction of toe drain and berms, Rip rap replacement
Bottom outlets and control gate repair,
Repairs to spill way gates, cranes, mechanical works
Providing lightening 133.31 90%
19 Polgolla (MASL) T- CG
L- 143 m H- 15 m C-4.1 mcm
Establishment of Reservoir control center (new building establishment and old building repaird)
296.47 77%
20 Kandalama (MASL T- HE)
L- 975 m H- 20 m C-33 mcm
Installation of SMF, D/s and U/S face remedial work, Renovation of existing toe drain, construction of loading berms, inverted filter
Rip rap around U/s of LB sluice, repairing of sluice barrel and tower
construction of D/s gabion wall for spill way(LHS)
construction of inception steps on D/S face,
39.25 79%
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 58 of 67
21 Victoria (MASL) T- CA
L- 520 m H- 122 m C-722 mcm
Installation of SMF, SCADA system Construction of dam distribution sub-station,
Repairs to low level outlet,
Improvements to spill way, repairs to gantry crane
installation of transformer, supply of O&M manuals, safety equipment and training
1,405.60 87%
22 Maduru Oya (MASL) T- RF
L- 1008 m H- 43 m C-722 mcm
Installation of SMF, Improvements to toe dam including restoration of slopes
Repair to sluice gate towers, power supply and distribution , installation of flow measuring inst.
Lightening spill
Construction of access road, lightening RB, dam crest, preparation of O&M manuals and training
152.98 82%
23 Randenigala (MASL) T- RF
L- 495 m H- 94 m C-460 mcm
Installation of SMF Repairs to granty cranes
Repairs to spill way gates, top logs
Preparation of O&M manual and training,
123.6 74%
24 Kotmale (MASL) T-RF
L- 600 m H- 87 m C-175mcm
Installation of SMF, modification of control room, power supply to dam, Preparing O&M manuals and provision of training
Repairs and installation of electric facilities to outlet
Spill way repair, gantry crane repair, spill way gate control
143.04 74%
25 Kalawewa (MASL) T- HE
L- 6500 m H- 14.8 m C-123.3 mcm
Installation of SMF, Improvements to the dam,
Repairs to sluices, made of cement and masonry stones, repairs to sluices
Spill way repair, gantry crane repair, power supply to the crane, spill way gate control
Construction of bathing steps
160.9 69%
26 Bowatenna (MASL) T- CG
L- 327 m H- 30 m C-56 mcm
Installation of SMF, Improvements dam, data acquisition and monitoring system,
Improvements to bottom outlet, main outlet shelter, Irrigation tunnel shelter, import. to RB and LB outlets, elec work,
Improvements to spill, Rb and LB spill way repair, spill way radial gates, Repair to RB and LB outlets (Low level), ,
maintenance and safety equipment, electrification of control boards, lightening protection system, building electrical services
67.12 83%
27 Dambulu Ova (MASL) T- HE
L- 1680 m H- 12 m C-11.7 mcm
Dam crest remedial work, D/s inspection path, and surface drainage, U/s face remedial work, rearrange the rip, rap, Renovation of measuring well,
Repairing of RBsluice barrel,tower, Repairs to LB sluice,
Repairing spill way, mechanical work in spill way
Construction of inspection steps, Renovation of building Renovation of access roads,
105.61 67%
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 59 of 67
28 Laxapana (CEB) T -CG
L- 137 m H- 29.6 m C-597 mcm
Installation of SMF, Improvements to dam,
Improvements of outlet including electro mech. work
Improvements to spill way including electro mech work
Supply of electrical equipment
116.6 88%
29 Canyon (CEB) T- CG
L- 181 m H- 28 m C-925 mcm
Installation of safety and monitoring facilities, Improvements to the Dam,
Improvements to bottom outlet. Electrical work
Improvts to spill way, Electrical work in sluice including electro mech..work
Spill way lightening 172.7 88%
30 Norton (CEB) T- CG
L- 103 m H- 29 m C-395 mcm
Installation SMF, improvements to dam
Improvements to bottom outlet
Improvement to spill way including electro mech. work,
Mechanical work in inlet and main distribution board, control gate s,
192.3 88%
31 Castlereigh (CEB) T- CG
L- 2033 m H- 47 m C-55 mcm
Installation of SMF, Improvements to the dam, improvements to electrical control chamber,
Electro mechanical work in bottom outlet,
Electrical work in the sluice,
Electrical work in control chamber, bridge and galleries
104.98 89%
32 Kalatuwawa(NWSDB)
L- 1143 m H- 16 m C-245 mcm
Installation of SMF, Improvements to abutments and dam
Outlet work Improvements to spill way
electrical work 42.01 71%
Total Average per scheme = Rs. 221 million
Total 3,538 81%
Phase 2 Dams (Additional Financing)
No Name of
the dam /
Agency
Tank Charac
-terictics Remedial measures in Bund
Remedial measures in
Sluices Remedial measures
in Spills Other
Total cost
Rs M Risk Index
Reduction
1 Nawakiri
T- HE
L- 3310 m
H- 11 m
C-60 mcm
Provided monitoring facilities, Constructed a bridge
across RB spillway 86
22%
2 Padaviya
T- HE
L- 4400 m
H- 18 m
C-105 mcm
Improvement of tank bund; Rip rap
replaced; consisting of toe drain and
toe filter
Improved with new GI
pipes; Installed 3
emergency gates
Site office; Installed steel
gates in main canal;
bathing place 131
35%
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 60 of 67
3 Angamuwa Installation of SMF, Improvement of
tank bund; Rip rap replaced;
consisting of toe drain and toe filter;
Repair walls, const. of
gabion walls
Repair of spill way.
Construction of
curtain wall;
Construction of watcher
hut; Boat yard 167
82%
4 Mahawilac
hchiya T-HE
L- 3100 m
H- 12 m
C-40 mcm
Improvement of tank bund; Rip rap
replaced; loading berms; toe drain
and toe filter; Installation of SMF
Improved RB & LB
sluices; provided new
emergency gates Repaired the spill
Access road impt;
uprooting trees in canal
bunds 210
64%
5
Mahakana
darawa T-
HE
L- 3219 m
H- 17 m
C-44.7 mcm
Improvement of tank bund; Rip rap
replaced; toe drain and toe filter;
fixed monitoring facilities; gravelling
the road
Impt. RB & LB sluices;
improved access road
to the sluice Repaired radial gates
Bathing steps, inspect.
steps, security hut, guard
stones 102
33%
6 Kottukachc
hiya
Improve tank bund; Replacing
collapsed Rip rap, filling of tank bund,
consisting of toe drain and toe filter,
removing trees on the tank bund
Construction of Hume
pipe culvert &
construction of a new
sluice
Reduce rock surface
level of D/S and U/S
of the spill and
construed spill gate
Repairs to tank bund
road, Construction of
bathing steps 74.5
68%
7 Kachchima
du
Improvement in tank bund including
earth work and Rip rap
establishment, removal of trees in
tank bund, construction of toe filter
and toe drain
Removal of damaged
sluice and new spill
way gate
constructed
Construction of a service
road, a new dam office
and bathing steps 97
40%
8 Thoppur Rehabilitation of 2.6 m of tank bund
and construction of a net barrier for
weeds
Const. of a new sluice
at Supply channel &
sluice
Improvt to spill No:1
at Thoppur tank
bund & sluice
Const. of a road at spill,
improvt. to Potta
drainage 48.3
53%
9 Wan Ela
Providing toe drain and toe filer Rip
rap in a section of tank, construction
of piezometers, and level
monuments
Construction of service
roads, and bathing steps 69.17
22%
10 Bandagiriya Improvements in Badagiriya tank
bund Improvements to
sluice Construction of R/B,
L/B gated spills Construction of toe road 78.29 62 %
11 Janaranjan
a
Improvements to tank bund, breach
filling of a section of tank bund, Improvts of main
sluices Improvements to
spill No:1, Const. of roads, R walls
in channels. 108.5
36%
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 61 of 67
12 Sorabora
T-HE
L- m
H- m
C-20.7 mcm
Improvements to tank bund, and Rip
Rap protection,
Improvements to
spill way, 19.46 64%
13 Unnachchai
T-HE
L- 1776 m
H- 15 m
C-51 mcm
Rehabilitation of mechanical system
and electrification of radial gates (03) Electrification of sluice
gates Improvements to LB
spill 73.81 46%
14 Badulu Oya Improvement to tank bund, Improvement of sluice
tower
Improvement to access
road, box culverts 59.85 44%
15 Muthukand
iya T-HE
L- 1113 m
H- 22 m
C-30.3 mcm
Filling pot holes in tank bund and
improvements to Rip Rap.
Electricity supply for
the sluice, improvet to
the sluice.
Reconstruction of
spill basin
Lighting road and
boundary blocks,
retaining wall 20.04 33%
Total Cost per scheme - Rs 90 million
Total 1,345 47%
No Name of
the dam /
Agency
Tank Charac
-terictics Remedial measures in Bund
Remedial measures in
Sluices Remedial measures
in Spills Other
Total cost
Rs M RI
reduction
16
Ulhitiya-
rathkinda
T-
HE;Includin
g Minipe
trans basin
canal
L- 4670 m
H- 28 m
C-146 mcm
Installation of SMF, construction of
toe drain, Rip Rap, construction of
mid-drains from and cascade drains
Installation of SMF and ther civil
works, mechanical and electrical
works
Improvements of
sluices including
electro mechl work
Removed trees
blocked spill,
Civil and Electro
mechanical work
Rehabilitation of bund
road access roads const
of bathing steps,
261 +
482.54 =
743.54
54%
17 Henanigala
(MASL)
Installation of SMF, improvements of
D/S slopes of dam, toe filter and toe
drain, improvements of Rip Rap
Improvements to
sluice gates Clearing of spill way
Rehabilitation of access
roads, toe road, foot
step D/S slope, 125.5 36%
18 Bambaraw
ana (MASL)
Installation of SMF, improvements of
dam slopes, improvements to toe
drain and toe filter, Rip rap
Rehabilitation of
outlet sluice gates,
servicing sluice gates
Rehabilitation of crest
road, toe road, cons. of
bathing steps 59.27 35%
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 62 of 67
19
Muwagam
mana
(MASL)
Installation of SMF, improving bund
& D/S slopes, construction of toe
drain, installation of electric items
Installation of a sluice
gates (cast iron (in BC Repair of surface of
spill
Rehabilitation of bund
top road, construction of
bathing steps, 64.09 33%
No
Name of
the dam /
Agency
Tank Charac
-terictics Remedial measures in Bund
Remedial measures in
Sluices
Remedial measures
in Spills Other
Total cost
Rs M Risk Index
20
Pimburatht
hewa
(MASL) T-
HE
L- 1951 m
H- 18 m
C-49 mcm Improve bund, slope protection 261 64%
21 Pusselawin
na (MASL)
Installation of SMF, improvement of
U/s and D/s slopes of the bund, Rip
rap
Construction of
Bridge cum spill way
structure
Repairs of road, new
bathing places, toe road 42.4 33%
22
Udawalawa
(MASL) T-
HE
L- 4023 m
H- 39 m
C-269 mcm
Installation of SMF, electro
mechanical work and improvements
to bypass gates
Repairs to bypass
gates Electro mechanical
work in spill
Drain clearing and road
establishment, import.
of toe road 91.47 45%
23 Panakkiniy
a (MASL) Improving tank bund and rip rap
Renovating the spill,
wing wall at Spills of
LB and RB
construction of a gabion
wall bathing places 15.14 29%
24
Ambagaha
gama
(MASL)
Improvement to earth bund including
to Rip Rap, Construction of RB
and LB sluices Construction of spill
way
Construction of bridge
retaining wall and
bathing steps 34.72 44%
25 Urusitawe
wa (MASL)
Installation of SMF, Rehabilitation
and improvement of tank bund Repairs to sluice
structures, Improvement of spill
way 48.66 29%
26
Muthyanka
ddu (NCP)
T-HE
L- 1829 m
H- 20 m
C-50.5 mcm
Bund raising rip rap & bund top road
& flank bunds (119.47m) Fixed radial gates
New radial gates &
structures Construction of Unit
office, bathing steps, 599.5 56%
27
Periyapand
ivirachchan
(do) )
Improvement of tank bund including
Rip Rap establishment and i Improvements to LB
and RB sluices Improvements to
spills Construction of bathing
steps 72.44 29%
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 63 of 67
28
Thodaman
aru barrage
(NCP)
Electo-Mechl work, constructed cut
off wall, cushion, raising gate sill
level, flood protection bunds etc. 382 94%
29 Dunumadal
awa (KMC)
Improvements to concrete dam, de-
silting of tank, Improvements to
sluice gates
Improvements to spill
tail canal, and road 43.94 78%
30 Roseneath
(KMC)
Improvements to the tank bund,
structures and removing silt
Improvement to road
way 24.62 64%
31 Maussakela
(CEB) T-CG
L- 4188 m
H- 41 m
C-144 mcm
Installation of SMF, improvements to
dam and valve house, construction of
Gibbon walls at d/s
Electrification of gate
operations
Improvements to
spill way gates &
steel wire ropes
Improvements of dam
monitoring office 69.24 75%
Total Average Rs 161 million Total 2740 50%
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 64 of 67
ANNEX 9. Status of Current Feasibility Studies of Proposed Investment Projects
No. Project Present Status
1 Feasibility Study for upper Elahera canal
& North Central Province canal
Feasibility studies in upper Elahera canal was completed, and the
constructions are on-going; In NCP canal, the feasibility studies
completed by Lahmaya Internat. Co. and the constructions are on-
going under Mahweli Water Security Investment Program
2
Feasibility study on Environmental
Assessment of Trans basin diversion of
Mahaweli Ganga flows to North Central
Province.
Environment Assessment (EA) for the Phase 1 (Moragahakanda to
Hurulu wewa, Mannakkattiya, Eru wewa & up to Mahakanadarawa)
has been completed. EA for NCP will be done after completing the
Feasibility Study
3 Feasibility study on the River for Jaffna Construction works are on-going under the supervision of ID
4 Diversion of Gin and Nilwala Ganga
project to south eastern dry zone
Through this project, which covers 25 Divisional secretary areas in
Galle, Matara and Hambantota Districts, it is proposed to divert part
of the water (117 MCM per year) to the adjacent south-eastern dry-
zone areas to cultivate 4,000 ha in both Yala and Maha seasons. In
addition, it is expected to provided 160 MCM per year to the propose
Hambantota Industrial Zone and to generate 73 Gig watt Hours of
electricity per year. The feasibility study has been completed with the
total cost estimated at Rs. 76,000 million.
5
Feasibility study to investigate the
option of increasing the capacity of
Maduru oya reservoir
Feasibility Study is on-going and is part of a contract that includes
engineering procurement & construction contract.
6
Feasibility study for Mundeni aru basin
water resource development project
Environmental and Social Assessment
FS completed by a French company (Agence Francaise de
Development AFD). The scope of the projects to ‘ improve livelihoods
of local population in Batticaloa and Ampara districts with improved
water management in a sustainable way”. The specific objective is to
join the Rugam Tank and the Kithulwewa tank with a dam constructed
across the Mundeniaru to increase cultivated area and to reduce the
impact of inundation of the downstream area of the basin.
Proposed to provide irrigation facilities to 3,380 ha. 14 mcm of water
from 03 reservoirs for domestic and industrial usage, and 1.2 GWh
and 2.1 GWh hydro-electricity generations.
According to FS, the NPV is Rs. 8,782 million, IRR is 15.8%, and the
cost-benefit ratio is 1.7; project feasibility is satisfactory. The total
cost of the project will be Rs. 24,500 million.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 65 of 67
8
Feasibility study on broad-scale
improvement of irrigation efficiency in
Sri Lanka
Proposals have been prepared to improve irrigation, land, and crop
productivity in 40 large schemes (command area is more than 600 ha)
and 40 medium schemes (command area is between 80 ha to 600 ha).
This is an integrated programme with four line agencies – Irrigation
Department, Department of Agriculture, Irrigation Management
Division, and Agrarian Development Department.
The estimated project cost is Rs.18, 500 million.
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 66 of 67
ANNEX 10. TRAINING DAYS COMPLETED
Component In-
country Overseas Total
Dam safety 219 268 487
HMIS & Ground-water monitoring 229 111 340
Procurement 317 317
GIS and comp. applications 91 91
Other 149 149
Total 1,005 379 1,384
The World Bank LK Dam Safety and Water Resources Planning (DSWRPP) ( P093132 )
Page 67 of 67
ANNEX 11. DELAYS IN CONTRACT COMPLETION
Agreed contract timeframe (months)
Original Project Additional Financing
12 18 24 12 18 24
No. of contracts per agreed timeframe 19 7 5 24 7 1
Avg. actual timeframe completed 28 33 34 18 21 41
Increase in the period as a percentage 133% 83% 42% 50% 17% 71%