THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

download THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

of 21

Transcript of THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    1/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    1

    CARNEGIE MELLON UNIVERSITY 

    DOCTOR OF PROFESSIONAL PRACTICE 

    OFFICE VISITS ASSIGNMENT 

    PROJECT CASE STUDY: 

    THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL

    AIRPORT, TERMINAL RENOVATION PROJECT 

    BACKGROUND TO THE YVR-ETF-4 PROJECT1 

    Vancouver International Airport (code name YVR) is Canada’s second-busiest airport and one

    of the primary gateways for passenger traffic between Asia and the western coast of North

    America. The Airport Authority operates and manages YVR pursuant to a long-term lease with

    the Government of Canada.

    The Expedited Transfer Facility (ETF) is a corridor facility designed to enhance the movement of

    people and baggage for arriving passengers transferring to outbound flights at YVR.The

    Vancouver International Airport Authority (VIAA) wanted to design and construct this corridor

    facility to reduce times taken to transfer between flights.

    The ETF project was divided into five different sub-contracts with different scopes. ETF-1, ETF-

    2 and ETF-3 were all awarded to Kasian Architecture Interior Design and Planning Ltd (Kasian).

    For ETF-4, the largest of the sub-contracts, procurement rules at YVR made it necessary to

    tender. Kasian was asked to provide Schematic Design services and provide an indicative

    design for a Project Description Requirement (PDR) competition.

    Kasian was eligible for the competition and went on to win it. Kasian was also later awarded the

    smaller ETF-5 contract. This case study will focus on the ETF-4 contract. The overall scope of

    this contract can be seen in Figure 1. 

    BACKGROUND TO BIM AT KASIAN2 

    Kasian has been using Building Information Modelling (BIM) technologies for ten years. In this

    time it has completed more than 100 projects on the Autodesk Revit platform. Many of these

    projects have been social BIM projects with all engineering consultants also working in Revit to

    create a federated multi-disciplinary BIM model.

    .

    1 From ETF-4 RFP 

    2 From Kasian BIM Marketing Collateral

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    2/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    2

    Figure1. ETF-4 3D model view and project scope 

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    3/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    3

    Some of the proven benefits that BIM has brought include:

    ●  Better design visualization and communication with clients, consultants, contractors and

    internally within the project team. This leads to better understood and executed design

    decisions.

    ●  Better coordinated production document sets leveraging the parametric capabilities of

    BIM software to keep documents automatically and accurately coordinated.

    ●  Ability to automatically extract data from the design model to support analysis,

    scheduling and other design related computation.

    ●  Better resolved design documents during construction leading to fewer RFIs and change

    orders as well as fewer claims and disputes.

    ●  Ability to coordinate sub-trades better through clash detection and construction logistics

    planning in Autodesk Navisworks.

    ●  Leveraging BIM models for design assist to solve challenging design configurations and

    installations.

    ●  Leveraging BIM models for design to fabrication processes thereby eliminating

    traditional shop drawing reviews and dramatically reducing procurement schedules.●  Faster turnaround on resolving and coordinating design conflicts through collaborative

    3D live review sessions.

    ●  Higher quality details through standardized components and intelligent integration with

    specifications language.

    Kasian continues to invest in, and innovate, using BIM tools and technologies. It has a

    dedicated team of talented professionals supporting the BIM effort in each of its offices. It has

    developed working relations with leading consulting engineers, general contractors and

    construction managers that allow it to gain optimum results from collaborative BIM efforts. 

    PROJECT DESCRIPTION

    Architectural Team

    One of the critical components for success with BIM technology on a project of this description

    and complexity is a team of capable BIM users willing to explore, learn and possibly make

    mistakes. Kasian was fortunate to have just such a team through the duration of the project.

    There was also sufficient continuity to ensure knowledge and expertise gained through the

    process remained available to the conclusion of the project.

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    4/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    4

    PROJECT PHASE TEAM SIZE BIM USERS BIM PROFICIENCY3 

    Schematic Design 3 2

    84%

    Design Development 4 3

    Construction Documents 8 6

    Contract Administration 2 1

    Kasian KnowledgesmartAverage for Revit

    60%

    Figure2. ETF-4 architectural team size and proficiency

    Project Team Matrix

    It was not only the architectural team that was willing to undertake the task in Revit, many of the

    consultants also showed willingness to participate in BIM through the duration of the project.

    This is important because many times team members will half-heartedly take part in a social

    BIM exercise only to pull out part of the way, or else to make it difficult for the coordinating

    consultant by constantly having BIM related issues. Some of the subcontractors such as steel

    fabrication and baggage handling also developed models that were incorporated into the BIM

    process.

    Project Schedule

    The project was scheduled to run from December 2012 to February 2016. The Construction

    Documents phase was to conclude in November 2013. The project is largely on schedule.

    As we will see the use of BIM was important for different aspects related to the schedule. Forexample, during Schematic Design, Kasian were simply developing the project requirements for

    VIAA to put into procurement tender. At this stage VIAA had no intentions of requiring BIM for

    the project. However, after seeing its value through Schematic Design, and after interaction with

    Kasian who further persuaded them, BIM clauses were added as an addendum to the RFP for

    Project Delivery Requirements.

    Later in the process – because parts of the project were being fast tracked – it became

    necessary to coordinate different streams of design development while issuing for construction.

    The BIM model was a critical part of managing this multiple tender process.  

    3Based on average scores from Knowledgesmart, a Revit assessment tool in use at Kasian

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    5/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    5

    Figure 3.ETF4 - project team matrix with software platforms

     

     

    &

    /

     

     

     

    ( )

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    6/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    6

    Figure 4.ETF4 - project schedule network diagram

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    7/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    7

    SCHEMATIC DESIGN

    During the Schematic Design phase it was mainly the architect (Kasian) and the owner (VIAA)

    who were active. The structural engineers, whose tender packages were due earlier due to fast

    tracking, also did some initial work like preliminary framing but were not involved in the BIM

    process. The mechanical and electrical engineers mainly did narratives.

    During Schematic Design the main activity in the architectural Revit model was programming.

    The Revit model was uses for creating room and area objects to generate space planning

    studies and to validate space plans against the programme requirements. The advantage of

    using Revit is that all room and area objects have embedded area data that is parametrically

    linked to the model, and which is then easily extracted into schedules for analysis. Revit also

    produced color diagrams linked to the room and area schedules that are very useful for visual

    analysis.

    Figure 5.ETF4 - color coded floor plans in the Revit model

    The other area where the use of Revit was crucial was in the exploration of design options.

    Revit has the ability to generate different design options as partitions of the main database. This

    means each design option is a full project in own right that can be presented, scheduled and

    analysed. However the main model remains intact and, importantly, does not need to be copied

    or recreated for each design option:one main model – multiple parametric design options.

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    8/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    8

    Figure 6. ETF4 - design options in Revit 

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    9/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    9

    The consistency provided by a single model database like Revit was also appreciated on a

    project of this complexity. Keeping the 400+ sheet document set coordinated, current and

    properly referenced, especially in a multiple tender packages situation, would have been a full

    time job without the help of a self-coordinating tool like Revit.

    Revit was also instrumental for providing high quality and evocative visual presentations. The

    architects leveraged the model to create myriad 3D studies and renderings in order to

    communicate the design and to help the client sell it to their own stakeholders. Ambitious

    interactive animations were also created as project marketing aids. For example, a time

    sequence animation of passenger movement through the terminal was generated based on 3D

    imagery from the Revit model.

    On the client side, they were not originally very knowledgeable about BIM. However as the

    Schematic Design phase progressed they realized they were receiving far more output then

    they were used to seeing, getting stronger visualizations and interacting more intimately with the

    design decision making process. This, together with the enthusiasm of the architect, persuaded

    them to mandate BIM as an addendum to their Project Description Requirements RFP.

    At the end of the Schematic Design stage VIAA, on the recommendation of Kasian, retained a

    BIM Consultant to not only help them develop a BIM addendum for their ETF-4 RFP but also to

    define BIM standard requirements for future projects.

    The one challenge with Revit reported by the architectural project manager is the inability for

    more senior staff to interact directly with the Revit model. Experienced staff members tend not

    to be as computer savvy as younger staff, and many do not use Revit. This means that they

    must rely on junior staff to drive the production tool as it were. In the case of the YVR ETF-4

    project this worked out fine for the architect, but this is not always the case. Some project

    managers get saddled with junior staff members who are not highly competent or motivated,and this can put their projects at a disadvantage. They never know what is going wrong until it is

    too late.

    DESIGN DEVELOPMENT 

    During the Design Development stage the Schematic Design developed by Kasian was

    approved by the VIAA board and a tender prepared for the Design Development to Contract

    Administration phases of the project. Kasian succeeded in winning the competition.

    Through Design Development, Revit was heavily used by all consultants for modeling and

    coordination. Autodesk Navisworks was also introduced as a visual coordination tool.Navisworks has the advantage that it easily aggregates 3D models from many different sources

    including non-Autodesk software. Also it optimizes large models for navigation which makes

    them light weight and easy to move through.

    Weekly coordination meetings with all stakeholders were used to keep the effort coordinated

    and on track. Consultants participated as did some sub-contractors with critical scope like the

    baggage handling contractor. These weekly meetings took advantage of Navisworks models to

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    10/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    10

    visualize and resolve issues in 3d. Navisworks also allowed for coordination with the baggage

    handling contractor who was working in Autodesk AutoCAD Architecture – a completely

    different platform than Revit.

    Figure 7. 3d working visualizations shown to the client

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    11/21

    Confidential for academic purposes only

    Code Review

    The code review consultant wor

    outputs both these formats, the

    (Adobe format) for the code con

    drawings into Revit, which again

    Separately, the code consultant

    studies were done in specialized

    models.

    Multiple Tenders

    With a project of this scale and s

    inevitable that parts of the contr

    disruptions of airport operations.

     

    Thus, for example, some structu

    scopes like interior design were

    coordination in order to detail, is

    were still in the design stages.

    Revit proved useful for this. The

    for issue were always coordinat

    Automated numbering and renu

    referencing. Revit design option

    aspects of the model for issuing.

    Figure 8.

    Prepared by Victor

    ed primarily in AutoCAD and PDF formats. Sin

    rchitectural team output in DWG (AutoCAD for

    ultant. Any coordination was done by importin

    the software has the capability to do.

    prepared 3D smoke studies and time egress st

    software and there was no integration with the

    cope in a major international transit hub like V

    ct would be fast tracked to mitigate against clo

    ral and civil engineering scopes were due early

    still in their design development. This meant a l

    sue for permit and tender parts of the documen

    Revit coordination system meant that docume

    d and referenced without hours of manual che

    bering of views, sheets and title blocks also h

    were also invaluable for continuing to design

    View of composite BIM model in Navisworks

    khoya in October 2014

    11

    ce Revit easily

    mat) and PDF

    CAD format

    udies. But these

    project BIM

    ncouver, it was

    sures and

    while other

    ot of

    t set while others

    t sets needed

    king.

    lped with cross

    hile freezing

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    12/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    12

    Engineering Consultants

    The project had two structural engineers, mechanical, electrical, civil and aviation as its major

    engineering consultants.

    The two structural engineers were a legacy of the history of the building. The domestic building

    at the airport was an older building and had been engineered by Reed Jones Christoffersen

    (RJC), while the international building was more recent. ETF-4 involved both buildings in its

    scope and Bush-Bohlman had been recently involved in renovation work at the airport. So both

    RJC and Bush-Bohlman were selected.

    This meant that each engineer produced their own document set. The engineers coordinated

    details and specifications as required but remained separate in their modeling and each

    maintained their own Revit model.

    The preferred BIM workflow for structural engineering at Kasian is for the architect to model

    their own structural members (columns and walls, structural slabs and roofs) early in the design

    process when they need to quickly make multitudes of changes. Later in the process, they void

    out or turn off their structural elements and rely on the structural engineer’s model. Structural

    framing is however left strictly to the engineer.

    Figure 9. Structural model

    Mechanical engineers produced a mechanical model and electrical engineers developed an

    electrical model. However both were reluctant to populate their models with information forwhich they thought they would then be liable such as setting out dimensions which the

    contractors need. This is a bottleneck in the BIM process.

    Also the engineers do not model everything. The mechanical engineer is typically only required

    to model items up to 2 inches in diameter while the electrical engineer does not model wiring or

    conduit unless it is critical for coordination.

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    13/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    13

    The preferred mechanical workflow at Kasian is for the mechanical engineer to place her own

    spaces in her Revit model. These can be based on the architectural room objects in the

    architect’s model. The architect places and locates plumbing fixtures and the mechanical

    engineer has the choice of whether to copy them into her model or to connect to the ones in the

    architect’s model.

    Figure 10. Mechanical model

    The preferred electrical workflow at Kasian is for the architect or interior designer to provide an

    indicative layout of light fixtures in the reflected ceiling plan. The electrical engineer or lighting

    consultant can then replace these generic fixtures with specific designed fixtures.

    Figure 11. Electrical model

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    14/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    14

    The civil engineer worked in 3D DWG format using Autodesk Civil 3D software. She provided

    3D CAD backgrounds that the architect leveraged to create 3D toposurfaces in Revit. This was

    critical to coordination of pavements, fueling stops, curbs, bridges and exterior envelope as

    even minor height changes make a difference.

    Figure 12. Consultant models and composite view

    Coordination with the aviation consultant was important for designing the bridges and

    connections to the aircraft and coordinating with fuel rigs. Minimum distances and constraints,as specified in the NFPA 4154 standard, had to be maintained. All of this while tying into the

    existing building and its fixed levels.

    The aviation consultant worked in 2D format using Vectorworks. This presented a twofold

    challenge: first coordination of these complex conditions was weakened by working in 2D.

    4 NFPA 415: National Fire Protection Association Standard on Airport Terminal Buildings, Fueling Ramp

    Drainage, and Loading Walkways

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    15/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    15

    Secondly, the Vectorworks platform presented challenges translating to and from Revit.

    Although both platforms read and write DWG format files, the export/import process always has

    related portability errors because of the different approaches of the two vendors, and their tacit

    unwillingness to provide seamless processes across their products.

    Baggage Handling Subcontractor

    The baggage handling subcontractor, Vanderlande industries, had a major scope of which the

    ETF-4 project was just a part. In all they had been tasked to install 9 km of baggage lines in the

    airport. They were under a separate contract with the VIAA and as such were present in the

    process much earlier than the normal tender sub trades.

    Their software platform was a heavily customized version of AutoCAD Architecture with which

    they produced a detailed 3D model of their installation. The model was sufficiently detailed for

    fabrication. This would have presented a problem if coordination was being done strictly in Revit

    as the combined architectural and baggage handling models would have been heavy and

    difficult to navigate. Fortunately, Navisworks was in use and this made the navigation of the

    aggregated models much easier.

    The baggage contractor clearly saw the value of 3D coordination and in fact organized several

    of the weekly coordination sessions including teleconferencing in the designers at their home

    office in the Netherlands.

    One challenge with trying to coordinate design models with subcontractors is the question of

    tolerances. The latter are used to working to real world tolerances while designers provide much

    wider leeway in their models and documents. Thus, for example, the baggage subcontractor

    would want to model baggage lines to within millimeters of a column which the architect would

    dispute because the model does not show everything. Fire proofing spray on the column may

    alone account for 50 additional millimeters. 

    CONSTRUCTION DOCUMENTS 

    Tendering and Cost Estimating

    Bid documents were issued in PDF format. This is usual practice because the PDFs are the

    sealed instrument of service of the architect. Professionals do not want the little understood

    potential for liability associated with issuing a BIM model for tender purposes.

    Cost estimates are also prepared off PDF packages to legally secure the contract sum. This is

    an area where technology has far outstripped the conservative tendencies of practice. Toolsexist to do material take-offs from BIM models but these werenot used on the ETF-4 project.

    General Contractor and Construction Manager

    The General Contractor (GC) and Construction Manager (CM) were most active when

    permitting and tendering got underway through the Construction Documents phase. There were

    a total of five tender packages: Civil, Structural (2), Envelope and Building. The CM was present

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    16/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    16

    Figure 13. Baggage handling model

    through the entire design process but the GC was selected only after the first tender was

    issued.

    The GC did not initially intend to use the BIM models but once they understood their potential

    value for their construction conditions modeling, they virtually demanded that the consultants

    provide 3D models. They also used Navisworks for coordination and some virtual construction

    logistics. However, they were not prepared for full on clash detection and coordination using the

    powerful clash detection features within Navisworks.

    The exchange between the Owner, the Consultants, the GC and the CM over the BIM models

    was interesting. The GC felt that the Consultants should hand them over since they facilitatedthe GC’s process. When the consultants hesitated the GC turned to the owner who demanded

    that the consultants turn over the models.

    The consultants, on their part, were hesitant for two main reasons. First, they were not sure

    about liability for inaccuracies and errors within the models. Models are typically not quality

    assured as this could potentially be a lengthy process, and in any case they are not the primary

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    17/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    17

    deliverable of the architect or her engineers. To this the GC said they would be willing to sign

    any number of waivers and indemnifications that the consultants required.

    The second objection of the consultants stemmed from the question what is the value of a BIM

    model. There is definitely a premium in terms of investing in the tools and skills to produce BIM

    models. There is also clearly a benefit to the GC and its trades.

    But the owner argued that it had retained the consultants to deliver a building and that any and

    all tools of their trade that made this possible was implicit in the commission. The owner felt that

    it did not need to provide any additional consideration to the consultants for the use of their

    models. It should be said that this matter was not entirely resolved, but the consultants did

    share their models in the interests of maintaining amicable relations.

    Another big challenge during the CD phase was the large number of issues (over 50). This

    requires a sophisticated approach to the management of revisions. Even though Revit helps a

    lot in managing sheet numbering information and cross referencing it does not have the

    workflow tools for complex tender situations with demanding revision tracking and logging. 

    CONTRACT ADMINISTRATION

    The Consultant team agreed to update their models through the Contract Administration (CA)

    phase. This is not always the case in the industry. Many times CA is undertaken by senior

    staffers who are not Revit users. They typically prefer to use AutoCAD.

    Even when CA is done using Revit, many users do not update the model. Instead they issue

    sketches and instructions as 2D line work based on the Revit model. The YVR team however

    decided to maintain their models up to date as they made changes through the CA phase.

    The benefit of doing this on this project was that the complexity of the project required it. There

    were constant changes, updates and interim conditions arising from multiple tenders and

    constructing in an operational facility environment. If the model was not up to date many of the

    change orders would have been difficult to effect.

    Another advantage of keeping the model up to date is that it is then record drawing ready at the

    end of the process. No additional work needs to be done to issue record drawings. This also

    means that the model is fit for further uses like facilities management or operations and

    maintenance should this be required.

    Steel Fabricator

    The steel fabricator had a massive scope with steel accounting for 20% of the overall contract

    price. Steel was tendered in multiple packages with each tender set up to follow the sequence

    of construction.

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    18/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    18

    Figure 14. Steel subcontractor's model showing fabrication details

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    19/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    19

    The steel fabricator chose to model the steel details from scratch in Tekla, a steel detailing BIM

    application. A big difference between the structural engineers steel model and the steel

    detailer’s model is that the engineer does not typically model connectors, gusset plates, end

    plates, stiffeners and other miscellaneous steel. These items can, however, be critical for

    coordination, especially with interweaving mechanical systems.

    In addition, engineers may not bother to slope structural members in their model, instead

    providing this information as notes or with 2D symbols. Also, since they do not have final

    member sizes for chords and struts in open web steel joists their structural framing tends to be

    approximate especially when dealing with tight tolerances.

    For these reasons, the architect as coordinating consultant, and the baggage handling

    contractor were pleased to use the fabricators model for further coordination. Since the model

    was created in a non-Autodesk platform, the fabricator exported it using the open format

    Industry Foundation Classes (IFC) which was then imported into Revit and Navisworks.

    The ability to visually coordinate steel with the fabricators model has been a big benefit to the

    over-taxed CA architect who did not have the budget to review shop drawings in great detail.

    Frequent interaction with the steel model has enabled him to catch several issues like

    connecting plates sticking out of the floor which would have been elusive to catch by reviewing

    2D drawings.

    The Trades

    Other subcontractors included Mechanical, Electrical, Envelope and Conveyancing. They all

    used PDFs and CAD format drawings and did not participate in the 3D model. This has meant

    that they were not as well coordinated and it has showed up on site with the Mechanical

    subcontractor repeatedly infringing on the Electrical zone clearance.

    CONCLUSIONS

    The use of BIM technology on the YVR-ETF4 project was enjoyable, effective and beneficial for

    the architect. It presented Kasian with a vivid picture of what project delivery will look like in the

    near future. It set the bar in terms of applying digital technology to their transportation projects.

    There were some important lessons learned along the way. First, you need good people to do

    good things. Investing in human resources and skill development in BIM continues to be a

    priority at Kasian.

    Second, you need willing and ambitious leadership. Many of the experiments undertaken on

    YVR-ETF4 would not have happened without the willingness and support of the Project

    Manager and Principal in Charge, both of whom were not even Revit users.

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    20/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    20

    Figure 15. Leveraging the models during construction 

    Finally, you need willing partners to make the process work. If consultants and contractors arerecalcitrant then much less will be achieved. In this case the role of the owner is also important.If the owner is uninformed or apathetic about BIM then this will make it difficult to motivate theconservative elements on the project towards progressive solutions.

    There were also opportunities missed on YVR-ETF4. Even though the technology was available

    to them they did not fully leverage laser scanning technology and use point clouds to coordinate

    complex existing conditions. This was however done to good effect on YVR-ETF5.

    The client was ultimately not able to plan the integration of the BIM models into their facility

    management and operations and maintenance systems. This remains a goal to strive for onfuture work.

    Other value added capabilities were also skipped due to lack of progressive industry partners.

    Thus integrating BIM models with specifications or with quantity take off tools did not happen

    because spec writers and cost estimators have not fully embraced these capabilities.

  • 8/19/2019 THE UTILIZATION OF BIM SOFTWARE ON VANCOUVER INTERNATIONAL AIRPORT, TERMINAL RENOVATION PROJECT

    21/21

    Confidential for academic purposes only Prepared by Victor Okhoya in October 2014

    Finally, neither the consultants nor the contractors used Navisworks for formal clash detection

    exercises even though they used it extensively for visual coordination. This was probably a

    significant omission on a project of this scope and complexity and Kasian has since developed

    the capabilities to run consultant coordination clash checks on Navisworks models as part of

    their delivery process.

    We end by mentioning some practice related challenges that the progressive use of BIM on

    projects like YVR-ETF4 exposes. First, the lack of quantifiable metrics with which to describe

    the successes of an aggressive BIM project like this one is striking. While most participants in

    the process will hail it as successful and beneficial, no one can easily say how much time or

    money it saved the project. This makes it harder to convince skeptics to invest more in

    technology driven processes. Indeed, apart from self-fulfillment, the main positive outcome

    Kasian can point to is an intangible – a deeper respect and relationship with the client.

    There are also contractual impediments to the use of BIM that need to be resolved as the

    technology becomes more widespread and mainstream. Consultants worry about turning over

    models because drawings are still perceived as the instruments of service. The quality

    assurance of BIM models is not an easy process, but without rigorous reviews BIM models carry

    increased risk since they also carry much more information than drawings. It does not help that

    the insurance and legal professions have not come out definitively on the status of BIM as a

    delivery method preferring to take a wait and see attitude instead.

    Figure 16. Point cloud technology on YVR-ETF5