The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT...

14
The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®.

Transcript of The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT...

Page 1: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

The TKM PRE-ENGINEERED RAPID

DEPLOYMENT BTS SITEA Patented Design of TKM Maestro Ltd ®.

Page 2: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

The ChallengeRapid Site Build:To create a Rapid Build Site that can be

t t d i h lf th ti St d d Sitconstructed in half the time as a Standard Site.

A Smaller Site:A Smaller Site:To create a Site Design that occupies less than half the Space of a standard BTS Site.

A Recoverable Site:To create a Site that can be recovered and reusedTo create a Site that can be recovered and reused elsewhere after a Period of Service.

The Competitive Edge:To create a Site that offers the Telecom Provider an undisputed Competitive edge in both Economyundisputed Competitive edge in both Economy and Rollout execution.

Page 3: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

The Solution

• A Steel All Bolted Pre Engineered Structure.

• Pre Cast Concrete Foundations + SteelFoundation Option.

• Fabrication in controlled FactoryEnvironmentEnvironment.

• Rapid Bolt Only BTS Site Erection.p y

• Modular, Re-usable Site

Page 4: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

Lower Site Acquisition Costs (50% smaller Site Area): Smaller Site Area leads directly to q ( ) yless Site Acquisition and Rental Costs.

Rapid 2 week Site Build possible : Site is Designed for a Rapid 17 day Site Build period.

Shorter Towers required (3 meters less): Shorter Towers required for this Site Design due to the 3meter Pre Engineered Site Height.

Excellent Remote Site Solution : The entire Site is transported and simply erected on Site, eliminating all wet Concrete works.

Recoverable Site : The Site can be recovered relocated and reusedRecoverable Site : The Site can be recovered, relocated and reused .

Fewer Cable Trays and Feeder Cables : Shorter Feeder Cable lengths result due to Compact nature of the Site.

Potentially lower Power Costs: Expect savings in Power Consumption due to enhanced cooling.

Less Ducting and Manholes : Only 1 Manhole, less Ducting required as the Cable trays are laid on the Site floor.

3

Co-location is possible : New pre-engineered site can be placed next to the original Site.

Added Security: Enclosed nature of Site reduces Pilferage

Page 5: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

The Design Concept

A Steel All Bolted Pre Engineered Structure:g

• Tower Elevated: The BTSTower is supported elevated on aTower is supported, elevated on aSteel Pre Engineered Structurefabricated from Galvanized HighStrength Steel.

• Transported to Site by Truck.Transported to Site by Truck.

• All Equipment Housed: AllTransmission Equipment is housedTransmission Equipment is housedin the Room created bellow theTower by the Pre EngineeredStructure.

Page 6: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

Sturdy Rigid Support

Fabrication at Factory

Th i S i P

Frame

The entire Structure is PreEngineered and Fabricated inChennai-India at Ganges TowersCorp India’s preeminent TowerCorp, India’s preeminent TowerFabrication Firm.

•All the High Strength Steel•All the High Strength Steel

• All the Pre Cast ReinforcedConcrete Foundation Panels.

• The entire Site (Steel Work andPre Cast Foundations) aretransported in one convoy to Site.

Page 7: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

Pre Cast Concrete Foundations(Option A)

Th P E i d Sit i• The Pre-Engineered Site issupported and Bolted onto a PreCast Class RC Foundationproviding Overturning Stabilityproviding Overturning Stability.

• The BTS Shelter, Generatorand Tank sit on this Foundationand Tank sit on this Foundation.Equipment provides additionalOverturning Stability.

• Steel Formwork adapted,Concrete poured in Controlled

conditions

•Bearing Pressure exerted onthe Ground at 36 m/s wind

d i 120 KN/ 2speed is 120 KN/m2.

Page 8: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

Truss Frame Steel Foundation (Option B)

Pre Engineered Site issupported and Bolted ontoa Truss frame steelfoundation filled with PreCast concrete blocks.

The truss foundation isplaced into a freshlyexcavated and blindedfloor. The base is nowready for immediateready for immediateerection of the mainframe.

Bearing Pressure exertedBearing Pressure exertedby this Design on theGround at 36 m/s windspeed is 120 KN/m2.pMost Soils will have aCapacity above this.

Page 9: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

17 - DAY ERECTION PROCESS

150*

min

.

GLGL

DAY 1 t 2

ANCHOR BOLT

STAGE ONE EXCAVATION OF VEGETABLE SOIL MIN* 150mmSCALE1:25

150NB_CL_`B'PIPE 150NB_CL_`B'PIPE

150NB_CL_`B'PIPE

356x171x45 UB 356x171x45 UB920

6000

DAY 1 to 2

DAY 9 to 11ANCHOR BOLTANCHOR BOLT

ANCHOR BOLT

STAGE TWO PLACING OF PRECAST SLABSSCALE1:25

150

450

583 2918 2917 583

GLGL

STAGE FIVE ELECTION OF TOWER ON I BEAMSSCALE1:25

150

450

583 2918 2917 583

GLGL

DAY 3 to 4

6000

150NB_CL_`B'PIPE 150NB_CL_`B'PIPE

150NB_CL_`B'PIPE

450

583 2918 2918 583

3000

DAY 5 to 8

STAGE THREE FIXING OF STEEL COLUMNSSCALE1:25

150

4

GLGL

AC

APS CONTROL

PANELKPLC

356x171x45 UB 356x171x45 UB920

DAY 11 to 17• No Wet Site Concrete Works

5

AC

STAGE SIX INSTALATION OF EQUIPMENTSSCALE1:25

GLGL

•Site Preparation involves only Site Clearing and excavation

Page 10: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

Site LayoutyAll the Equipment, Shelter, Genset, Fuel Tank located in the Room.

Site Dimensions = 5 m x 5 m (35m Tower), 7m x 7m (40m Tower).

Feeder Cables from Tower enter Room through the Roof.

A C t lAccess ControlSteel Railing will run along the 4 Sided Roof to prevent acess

Alarms, Sensors and LightingCovered Nature of site eliminates Motion activated LightsMotion activated Lights

Earthing and Safety Equipment8 Legs tapped and connected to

5

g ppEarth Ring

Page 11: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

IMAGE OF Completed siteCompleted site Pre Engineered

Site

Cladding : The Pre Engineered Site is clad with St l B P l d f SHSSteel Box Panels made of SHS Frames and Steel Sheeting.Chain Link Fencing an Optiong p

Gates: The entrance gates are rigid Steel Box Panelsrigid Steel Box Panels.

Page 12: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

Actual Safaricom RDSActual Safaricom RDS Site for Mombasa, 5 X 5m

Page 13: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

From Inspiration

ToDesignDesign

ToReality

6

Page 14: The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT BTS SITE A Patented Design of TKM Maestro Ltd ®. The Challenge Rapid Site Build:

TECHNICAL SPECIFICATION SUMMARY.

Design Paramteres Limits and Load Conditions NOTES

Maximum Tower Height Supported

36 meter Tower45 meter Tower can be supported with minor modificationsmodifications

Maximum Loading on Tower 8 m2 12 m2 can be supported with

minor modifications

Maximum Basic Wind S d T

36 m/s Suitable for all of Region 1 d R i 2Speed on Tower and Region 2.

Pre Enginered Structure Dead Load

Tower Dead Load

Design Dead Loads i i l f i lDesign Dead Loads • Climbing ladder, Lugs and Cable Brackets• Feeder Cables• Antenna and Microwave Dish Weights

Critical Case of simultanouse loading adopted in Analysis Model.

Design Live Loads 6 Workers + Accidental Load

The Structural Analysis run on STAAD Pro Structural

1.0GK + 1.4WK + 1.6QK1.2GK + 1.2WK + 1.2QK

Structural Analysis Critical Load Combination Cases

on STAAD Pro Structural Analysis Software.Failure Ratios derived from worst possible Load combination.

1.2GK + 1.2HR + 1.2QK1.4GK + 1.6QK1.0GK + 1.0WK + 1.0QK1.0GK + 1.4HR + 1.6QK (G d d i d d Q li

6

(GK = Dead Load, WK = Wind Load, QK = live Load, HR = Incidental Load)