The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT...
Transcript of The TKM PRE- ENGINEERED RAPID DEPLOYMENT BTS SITE€¦ · The TKM PRE-ENGINEERED RAPID DEPLOYMENT...
The TKM PRE-ENGINEERED RAPID
DEPLOYMENT BTS SITEA Patented Design of TKM Maestro Ltd ®.
The ChallengeRapid Site Build:To create a Rapid Build Site that can be
t t d i h lf th ti St d d Sitconstructed in half the time as a Standard Site.
A Smaller Site:A Smaller Site:To create a Site Design that occupies less than half the Space of a standard BTS Site.
A Recoverable Site:To create a Site that can be recovered and reusedTo create a Site that can be recovered and reused elsewhere after a Period of Service.
The Competitive Edge:To create a Site that offers the Telecom Provider an undisputed Competitive edge in both Economyundisputed Competitive edge in both Economy and Rollout execution.
The Solution
• A Steel All Bolted Pre Engineered Structure.
• Pre Cast Concrete Foundations + SteelFoundation Option.
• Fabrication in controlled FactoryEnvironmentEnvironment.
• Rapid Bolt Only BTS Site Erection.p y
• Modular, Re-usable Site
Lower Site Acquisition Costs (50% smaller Site Area): Smaller Site Area leads directly to q ( ) yless Site Acquisition and Rental Costs.
Rapid 2 week Site Build possible : Site is Designed for a Rapid 17 day Site Build period.
Shorter Towers required (3 meters less): Shorter Towers required for this Site Design due to the 3meter Pre Engineered Site Height.
Excellent Remote Site Solution : The entire Site is transported and simply erected on Site, eliminating all wet Concrete works.
Recoverable Site : The Site can be recovered relocated and reusedRecoverable Site : The Site can be recovered, relocated and reused .
Fewer Cable Trays and Feeder Cables : Shorter Feeder Cable lengths result due to Compact nature of the Site.
Potentially lower Power Costs: Expect savings in Power Consumption due to enhanced cooling.
Less Ducting and Manholes : Only 1 Manhole, less Ducting required as the Cable trays are laid on the Site floor.
3
Co-location is possible : New pre-engineered site can be placed next to the original Site.
Added Security: Enclosed nature of Site reduces Pilferage
The Design Concept
A Steel All Bolted Pre Engineered Structure:g
• Tower Elevated: The BTSTower is supported elevated on aTower is supported, elevated on aSteel Pre Engineered Structurefabricated from Galvanized HighStrength Steel.
• Transported to Site by Truck.Transported to Site by Truck.
• All Equipment Housed: AllTransmission Equipment is housedTransmission Equipment is housedin the Room created bellow theTower by the Pre EngineeredStructure.
Sturdy Rigid Support
Fabrication at Factory
Th i S i P
Frame
The entire Structure is PreEngineered and Fabricated inChennai-India at Ganges TowersCorp India’s preeminent TowerCorp, India’s preeminent TowerFabrication Firm.
•All the High Strength Steel•All the High Strength Steel
• All the Pre Cast ReinforcedConcrete Foundation Panels.
• The entire Site (Steel Work andPre Cast Foundations) aretransported in one convoy to Site.
Pre Cast Concrete Foundations(Option A)
Th P E i d Sit i• The Pre-Engineered Site issupported and Bolted onto a PreCast Class RC Foundationproviding Overturning Stabilityproviding Overturning Stability.
• The BTS Shelter, Generatorand Tank sit on this Foundationand Tank sit on this Foundation.Equipment provides additionalOverturning Stability.
• Steel Formwork adapted,Concrete poured in Controlled
conditions
•Bearing Pressure exerted onthe Ground at 36 m/s wind
d i 120 KN/ 2speed is 120 KN/m2.
Truss Frame Steel Foundation (Option B)
Pre Engineered Site issupported and Bolted ontoa Truss frame steelfoundation filled with PreCast concrete blocks.
The truss foundation isplaced into a freshlyexcavated and blindedfloor. The base is nowready for immediateready for immediateerection of the mainframe.
Bearing Pressure exertedBearing Pressure exertedby this Design on theGround at 36 m/s windspeed is 120 KN/m2.pMost Soils will have aCapacity above this.
17 - DAY ERECTION PROCESS
150*
min
.
GLGL
DAY 1 t 2
ANCHOR BOLT
STAGE ONE EXCAVATION OF VEGETABLE SOIL MIN* 150mmSCALE1:25
150NB_CL_`B'PIPE 150NB_CL_`B'PIPE
150NB_CL_`B'PIPE
356x171x45 UB 356x171x45 UB920
6000
DAY 1 to 2
DAY 9 to 11ANCHOR BOLTANCHOR BOLT
ANCHOR BOLT
STAGE TWO PLACING OF PRECAST SLABSSCALE1:25
150
450
583 2918 2917 583
GLGL
STAGE FIVE ELECTION OF TOWER ON I BEAMSSCALE1:25
150
450
583 2918 2917 583
GLGL
DAY 3 to 4
6000
150NB_CL_`B'PIPE 150NB_CL_`B'PIPE
150NB_CL_`B'PIPE
450
583 2918 2918 583
3000
DAY 5 to 8
STAGE THREE FIXING OF STEEL COLUMNSSCALE1:25
150
4
GLGL
AC
APS CONTROL
PANELKPLC
356x171x45 UB 356x171x45 UB920
DAY 11 to 17• No Wet Site Concrete Works
5
AC
STAGE SIX INSTALATION OF EQUIPMENTSSCALE1:25
GLGL
•Site Preparation involves only Site Clearing and excavation
Site LayoutyAll the Equipment, Shelter, Genset, Fuel Tank located in the Room.
Site Dimensions = 5 m x 5 m (35m Tower), 7m x 7m (40m Tower).
Feeder Cables from Tower enter Room through the Roof.
A C t lAccess ControlSteel Railing will run along the 4 Sided Roof to prevent acess
Alarms, Sensors and LightingCovered Nature of site eliminates Motion activated LightsMotion activated Lights
Earthing and Safety Equipment8 Legs tapped and connected to
5
g ppEarth Ring
IMAGE OF Completed siteCompleted site Pre Engineered
Site
Cladding : The Pre Engineered Site is clad with St l B P l d f SHSSteel Box Panels made of SHS Frames and Steel Sheeting.Chain Link Fencing an Optiong p
Gates: The entrance gates are rigid Steel Box Panelsrigid Steel Box Panels.
Actual Safaricom RDSActual Safaricom RDS Site for Mombasa, 5 X 5m
From Inspiration
ToDesignDesign
ToReality
6
TECHNICAL SPECIFICATION SUMMARY.
Design Paramteres Limits and Load Conditions NOTES
Maximum Tower Height Supported
36 meter Tower45 meter Tower can be supported with minor modificationsmodifications
Maximum Loading on Tower 8 m2 12 m2 can be supported with
minor modifications
Maximum Basic Wind S d T
36 m/s Suitable for all of Region 1 d R i 2Speed on Tower and Region 2.
Pre Enginered Structure Dead Load
Tower Dead Load
Design Dead Loads i i l f i lDesign Dead Loads • Climbing ladder, Lugs and Cable Brackets• Feeder Cables• Antenna and Microwave Dish Weights
Critical Case of simultanouse loading adopted in Analysis Model.
Design Live Loads 6 Workers + Accidental Load
The Structural Analysis run on STAAD Pro Structural
1.0GK + 1.4WK + 1.6QK1.2GK + 1.2WK + 1.2QK
Structural Analysis Critical Load Combination Cases
on STAAD Pro Structural Analysis Software.Failure Ratios derived from worst possible Load combination.
1.2GK + 1.2HR + 1.2QK1.4GK + 1.6QK1.0GK + 1.0WK + 1.0QK1.0GK + 1.4HR + 1.6QK (G d d i d d Q li
6
(GK = Dead Load, WK = Wind Load, QK = live Load, HR = Incidental Load)