The Story of a Week in Production on DR Site - Francois Vancoppenolle
-
Upload
nrb -
Category
Technology
-
view
61 -
download
0
Transcript of The Story of a Week in Production on DR Site - Francois Vancoppenolle
1
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
The story of a week in
production on DR site
N.R.B. Mainframe Day 2015
27 May 2015
2
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Overview
• Introduction : P&V Group
• Mainframe architecture
• DRP Scenarios
• Testing the DRP Scenarios
• Test DRP Scenario on Production partitions
• Test Scenario DRP P&V 2012
• One week in DRP : Lessons learned
• What’s next ?
3
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Introduction : P&V Group
Market Position in 2013 (in Belgium) :
• NON-Life : 6th (702.796 k€)
• Life : 7th (748.642 k€ )
4
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Overview
• Introduction : P&V Group
• Mainframe architecture
• DRP Scenarios
• Testing the DRP Scenarios
• Test DRP Scenario on Production partitions
• Test Scenario DRP P&V 2012
• One week in DRP : Lessons learned
• What’s next ?
5
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Mainframe Architecture (1/4)
Bruxelles
Antwerpen
Herstal
Villers-le-Bouillet
6
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Mainframe Architecture (2/4)
Bruxelles
AntwerpenHerstal
Villers-le-Bouillet
119 Km
82 Km
32
Km
46
Km Network
configuration
7
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
EC12 EC12
DS8700 DS8700
VTS7700 VTS7700
PPRC
Ptp
Switch Switch
HerstalVillers-le
-Bouillet
8
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Mainframe Architecture (4/4)
P&V LPARS on NRB infrastructure :
ZOS : ZVM :
LPAR PROD 1
LPAR PROD 2
LPAR QLTY 1
LPAR QLTY 2
LPAR TEST 1
LPAR TEST 2
LPAR SYSTEM
LPAR PRODUCTION :
- 13 Linux Production
- 15 Linux Quality
- 15 Linux Test
- 2 Linux System
LPAR SYSTEM
- 2 Linux System
9
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Overview
• Introduction : P&V Group
• Mainframe architecture
• DRP Scenarios
• Testing the DRP Scenarios
• Test DRP Scenario on Production partitions
• Test Scenario DRP P&V 2012
• One week in DRP : Lessons learned
• What’s next ?
10
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
DRP Scenarios (1/6)
4 Scenarios are taken in consideration
• Villers-le-Bouillet Down
• Disks and/or VTS7700 Down at Herstal
• Z13 Herstal Down
• Herstal Down
11
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
EC12 EC12
DS8700 DS8700
VTS7700 VTS7700
Switch Switch
HerstalVillers-le
-Bouillet
12
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
EC12 EC12
DS8700 DS8700
VTS7700 VTS7700
Switch Switch
HerstalVillers-le
-Bouillet
13
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
EC12 EC12
DS8700 DS8700
VTS7700 VTS7700
PPRC
Ptp
Switch Switch
HerstalVillers-le
-Bouillet
14
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
EC12 EC12
DS8700 DS8700
VTS7700 VTS7700
Switch Switch
HerstalVillers-le
-Bouillet
15
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
EC12
DS8700
Herstal Villers-le
-Bouillet
EC12
DS8700
DRP Scenarios (6/6)
4 situations
to test(VTS is not an issue)
16
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Overview
• Introduction : P&V Group
• Mainframe architecture
• DRP Scenarios
• Testing the DRP Scenarios
• Test DRP Scenario on Production partitions
• Test Scenario DRP P&V 2012
• One week in DRP : Lessons learned
• What’s next ?
17
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Testing the DRP Scenarios (1/3)
Every 6 months, the 4 scenarios are tested on :
• The 2 ZOS QLTY Partitions + ZOS System Partition
- Check that system engineers can logon in TSO;
- Check the sysplex between the 2 partitions;
- Check the connexions are correct (VTS/DS8000/OSA/…)
• The ZVM System Partition
- Check that system engineers can logon in CMS;
- Check that system engineers can logon in Linux;
- Check the connexions are correct (DS8000/OSA/…)
18
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Testing the DRP Scenarios (2/3)
IF SYSTEM ENGINEERS CAN PERFORM
-> A LOGON IN 1 ZOS/TSO,
-> A LOGON IN 1 ZVM/CMS,
-> A LOGON IN 1 LINUX
THEY ARE ABLE TO SOLVE ALL
PROBLEMS ON OTHER PARTITIONS.
19
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Testing the DRP Scenarios (3/3)
WHAT DOES THIS TEST PROVE :
Minimum cabling is available
System Engineers should be able to
restart all partitions and to solve all
problems.
WHAT DOESN’T THIS TEST PROVE
All partitions will start without problem
Everything will work as it should in DRP
20
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Overview
• Introduction : P&V Group
• Mainframe architecture
• DRP Scenarios
• Testing the DRP Scenarios
• Test DRP Scenario on Production partitions
• Test Scenario DRP P&V 2012
• One week in DRP : Lessons learned
• What’s next ?
21
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Test DRP Scenario on Production Partitions (1/2)
To be sure that the production partition will have no
(?) problem in DRP, you have to test this situation…
and test EVERYTHING.
But this is impossible…
One example: will you during the test execute the
batch programs that runs once a year ?
Test as much as possible
test the most important things !!!!
22
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
What to test ?
• All starting taskes and Specific programs
(Scheduler, Tape manager, Output managers, …)
• Databases;
• Transactional programs (CICS, IDMS, …);
• The Batch process.
• Connectivity available and sufficient.
• Power of the CPU sufficient.
• “all other things that you don’t think about…”
Test DRP Scenario on Production Partitions (2/2)
23
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Overview
• Introduction : P&V Group
• Mainframe architecture
• DRP Scenarios
• Testing the DRP Scenarios
• Test DRP Scenario on Production partitions
• Test Scenario DRP P&V 2012
• One week in DRP : Lessons learned
• What’s next ?
24
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Test Scenario DRP P&V 2012 (1/2)
In October 2012, upon proposal of the mainframe
system engineers, P&V has decided to run one week
in DRP mode.
Purpose :
• Testing the batch process seriously.
• Check that connectivity is sufficient.
• (Check that the power of the CPU is sufficient).
• “Test all other things that you don’t thinks about…”
25
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
EC12
DS8700 DS8700
VTS7700 VTS7700
Switch Switch
HerstalVillers-le
-Bouillet
PPRC
Ptp
26
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Overview
• Introduction : P&V Group
• Mainframe architecture
• DRP Scenarios
• Testing the DRP Scenarios
• Test DRP Scenario on Production partitions
• Test Scenario DRP P&V 2012
• One week in DRP : Lessons learned
• What’s next ?
27
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
One week in DRP : Lessons Learned (1/5)
WHAT WENT WELL ?
• “Yes, we can” : We are on the cloud but …
everything was performed by ourself without the
intervention of NRB (except CBU activation).
• It should be possible to switch in DRP mode in 1
hour but 3 additional hours needed for collecting
the licence keys for the other CPU.
Trends since 2012 : DRP key available on the web.
• “No problem to startup : ZOS, ZVM and Linux.
28
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
One week in DRP : Lessons Learned (2/5)
WHAT FAILED ?
• Cabling was not sufficient for the I/O after the W.E.
Cables added by NRB on Monday => Problem solved.
Switch installed by NRB 3 months later
• Cables where added by NRB, but we (P&V) fail to
activate all of them (detected on Thursday)
Avoid defining new cables during DRP. With the switch
installed by NRB, this should not be necessary anymore.
29
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
One week in DRP : Lessons Learned (3/5)
WHAT FAILED ?
• HMC consoles not reachable on DRP site.
IPL performed from the consoles at Herstal;
Changes performed by NRB to make the HMC console
available.
30
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
One week in DRP : Lessons Learned (4/5)
WHAT FAILED ?
• Batch was OK except :
Bugs in some “system” programs based on the LPAR
name => Programs have been fixed.
Problem detected with the BACKUP that uses DISK on
one DS8700 and that are not defined on the other
DS8700 => Temporary solution (for the DRP test) : Disk
added on the other DS8700; Definitive solution : Disk
space added on the other DS8700 & Flash Copy S.E.
implemented.
31
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
One week in DRP : Lessons Learned (5/5)
WHAT WAS NOT PROVEN WITH THIS DRP TEST
• CPU, memory and cabling are sufficient if ALL
partitions (all NRB customers) work on the DRP
infrastructure.
To prove it, all customers should perform the same test
at the same time. Not easy to plan…
32
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
Overview
• Introduction : P&V Group
• Mainframe architecture
• DRP Scenarios
• Testing the DRP Scenarios
• Test DRP Scenario on Production partitions
• Test Scenario DRP P&V 2012
• One week in DRP : Lessons learned
• What’s next ?
33
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
What’s next ? (1/2)
• All problems detected during the test are solved
(we hope so), but another test need to be planned.
Next DRP test : October 2015
34
The Group P&V is comprised of the brands P&V, VIVIUM, Actel, PNP, Euresa-Life and Arces
What’s next ? (2/2)
• Scenario not yet tested :
Suppose that the disks/tapes are destroyed partially or
totally on the primary and on the secondary site (because
of an “error” of a Storage Administrator/System Engineer)
In 2016 (? - when NRB will replace the disk infrastructure),
we will restore a tape backup on it and try to restart the
partitions on the restored disks…