THE STATE OF TRANSITION TO BIM: THE CASE OF...
Transcript of THE STATE OF TRANSITION TO BIM: THE CASE OF...
ISTANBUL TECHNICAL UNIVERSITY INSTITUTE OF SCIENCE AND TECHNOLOGY
ARCHITECTURAL DESIGN COMPUTING PHD PROGRAMME
MBL 607E / BUILDING INFORMATION MODELS
INSTRUCTOR: Salih OFLUOĞLU
THE STATE OF TRANSITION TO BIM:
THE CASE OF ENKA
523092009 Esra Gürbüz
523092015 Serdar Aşut
2
INDEX
Abstract 3
1. INTRODUCTION 4
2. TRANSITION TO BIM 7
2.1. Causes of the Transition 7
2.2. Training and Orientation Process 8
2.3. Hardware Requirements 8
3. THE PRACTICE OF MUSCAT AIRPORT PROJECT 9
3.1. The Content and Scope of the Project 9
3.2. Project Team and Organization 11
3.2.1. Project Team 11
3.2.2. Project Organization and Work Loads 12
3.2.2.1. Preliminary Process and Draft Model 12
3.2.2.2. Labor divisions 13
3.3. Work Process 14
3.4. Interoperability 16
4. CONCLUSION 17
References 20
3
ABSTRACT
The aim of this study is to analyze the process of transition to BIM for architectural
offices in Turkey and to illustrate the fundamental requirements within BIM
applications. The shift from traditional CAD practices to BIM makes it mandatory
for the companies in AEC industry to review their standards, methods and principles
in various aspects. This research focuses on the case of ENKA, which is one of the
leading companies in this industry in Turkey. The ongoing project of Muscat
International Airport is the very first experience of ENKA in using BIM, which
makes this case very appropriate to research in order to understand this paradigm.
The case shows that BIM brings about new understandings for work models and
environments comparing with traditional CAD practices.
4
1. INTRODUCTION
Overview of BIM
The concept of BIM was first used by Charles M. Eastman in his book “Building
Product Models: Computer Environments Supporting Design and Construction” in
the late 1970s. He used the term “Building Product Model" basically same as BIM
term. BIM software has stimulating effects on architectural and engineering
representation and production techniques fields. Besides, the software changed
traditional architectural production techniques and decision mechanisms.
Building Information Modeling (BIM) is the process of generating and managing
building data during its life cycle. Typically it uses three-dimensional, real-time,
dynamic building modeling software to increase productivity in building design and
construction. The process produces BIM, which encompasses building geometry,
spatial relationships, geographic information, and quantities and properties of
building components.
Building information modeling covers geometry, spatial relationships, light analysis,
geographic information, quantities and properties of building components (for
example manufacturers' details). BIM can be used to demonstrate the entire building
life cycle, including the processes of construction and facility operation. Quantities
and shared properties of materials can be extracted easily. Scopes of work can be
isolated and defined. Systems, assemblies and sequences can be shown in a relative
scale with the entire facility or group of facilities.
BIM stands for new concepts and practices that are so greatly improved by
innovative information technologies and business structures that they will
dramatically reduce the multiple forms of waste and inefficiency in the building
industry. Whether used to refer to a product – Building Information Model (a
structured dataset describing a building), an activity – Building Information
Modeling (the act of creating a Building Information Model), or a system – Building
5
Information Management (business structures of work and communication that
increase quality and efficiency), BIM is a critical element in reducing industry waste,
adding value to industry products, decreasing environmental damage, and increasing
the functional performance of occupants.
“BIM software facilitates an improved way of working collaboratively (Fig.1.), using
a model created from coordinated and consistent design information. This process
enables earlier decision-making, better documentation, and the evaluation of
alternatives for sustainable design or improvements using analysis before
construction begins” (United States, National Building Information Modeling
Standards).
Fig.1. Collaboration in BIM solutions
(http://images.autodesk.com/adsk/files/autodesk_revit_architecture_2011_brochure.p
df)
Company Profile
The history of ENKA begins in 1957 with the partnership between Şarık Tara and
the late Sadi Gülçelik. ENKA has set its sights on demanding contracts since its
inception. The essence of ENKA today was defined by the range of its earliest
6
projects, which included the construction of industrial plants, docks, marine
slipways, shipyards, grain silos, bridges, roads and piers, all in the Istanbul area.
During the period of 1970’s and 80’s ENKA’s activities shifted from local projects in
the Istanbul region to larger and more diverse projects across Turkey and beyond. In
the early 1980s, ENKA continued to sign contracts for increasingly larger scale
projects broadening the scope of its operations in Turkey as well as in Libya, Saudi
Arabia, Iraq and Jordan. In addition, projects completed in Russia and Germany have
confirmed ENKA’s ability to compete with international companies on their own
territory.
By 1990, ENKA had begun to rank among the top general contracting companies in
the world, offering a comprehensive range of services from design and procurement
to construction, erection, operation, maintenance and management. From the 1990s
onward, ENKA’s operations continued to expand in different parts of the world.
Fig.2. Headquarter building of ENKA in İstanbul
7
Fig.3. A highway and an industrial plant project of ENKA
The contact person
To collect information about BIM and ENKA personal interviews and electronic
correspondences have been done with Özlem Yurttakal, who is working as a senior
architect in ENKA, since 2006. Besides, web site of the firm is used as a major data
source.
Muscat International Airport Project’s modeling process which is ENKA’s first
experience about BIM, have been handled in the scope of this study.
2. TRANSITION TO BIM
2.1 Causes of the Transition
The encounter of the company with Revit as a BIM solution was through the offer of
the software vendor. When ENKA bought AutoCAD three years ago, Revit was
given for free by the vendor and that is how ENKA first met BIM. However, the
company did not start busing BIM immediately after this offer. The contract of the
Muscat International Airport Project was demanding the company to use BIM. Using
BIM solutions for the Muscat Airport Project was the requirement that was put
forward by the employer of the project, who is the Sultanate of Oman. In this way,
ENKA had to start using BIM as a work constraint.
8
After the BIM training which was first given to a limited number of senior architects
in the company, the necessity of reviewing the existing work standards and shifting
to a new understanding became obvious. While working on the airport project,
ENKA ran a learning and transition process synchronously.
2.2 Training and Orientation Process
The software vendor provided various training and consultancy opportunities for
ENKA. However, the training first, was for a limited number of staff. These trained
staff then started to assist the other staff of the company. During this training and
orientation process, all the staff who are in the BIM process individually, self trained
themselves through the online forums and software guides in order to reach a more
advanced level in BIM. However, the first serious applications and hands on
practices started by the Muscat Airport Project. Training and orientation process of
the office is explained more detailed in part 3.2.1.
The case showed that using BIM as the work constraint became an advantage for
ENKA. The ease in obtaining material lists precisely and fast and easy and
simultaneous update of data and output are the first advantages that they are
expecting to have. Özlem Yurttakal pointed out that, ENKA decided to use BIM not
only for this project, but also for their further projects.
2.3. Hardware Requirements
Using BIM software makes it necessary to advance the qualities of the computers in
the work environment. This is mainly because a BIM model of a project is a very
large and extensive package that contains various types of information. The alpha-
numeric and geometric information of each single building component and all data,
parameters and outputs related to design, construction, or management make BIM
files substantially large. For this reason, BIM software demands a high and advanced
9
level of computer system specification. Especially large scale projects, such as the
Muscat International Airport Project of ENKA, make it necessary to use computers
with high-end CPU charts, memories, and more importantly video cards.
Additionally, the interfaces of BIM software are usually relatively more complex,
contain various palettes and menus, and therefore require screens with high
resolution and preferably large dimensions. One can say that, each new version of
any BIM software does not reduce these system requirements but demand more
advanced work stations progressively. This situation points out the fact that BIM
users have to be able to allocate a continuous specific budget to set up the necessary
work environment and follow up the innovations.
When ENKA decided to use BIM, they had to update their computer systems
because of the situation described above. Company’s old computers, which were
appropriate for traditional CAD software, had to be updated according to the new
system requirements. And the velocity of the innovations in BIM software shows that
this process of update needs to be continuous. The importance of hardware for BIM
users also indicates that BIM users need to have a sufficient knowledge about
computer hardware. The users need to be able to follow the innovations in hardware
technologies in order to sustain their competitive power within BIM.
3. THE PRACTICE OF MUSCAT AIRPORT PROJECT
3.1 The Content and Scope of The Project
The Ministry of Transport and Communication of Oman plans to expand the
passenger terminal in Muscat International Airport, located in Seeb, Muscat, Oman.
The purpose of the project is to increase the airport's capacity from 5 million
passengers per year to 12 million passengers per year. The project calls for
construction of a 332,000 m² terminal. The main building will be 460 meters long
and 200 meters wide. It will include a four-star hotel with 90 rooms. Project’s
estimated value is 1.8 billion USD. Expansion of Muscat International Airport - New
10
Terminal Building project’s main contractors are ENKA, Bechtel and Bahwan
Contracting Company. The terminal is expected to be completed in 2014.
Fig.4. New Muscat International Airport
ENKA began the project 1.5 years ago; however because of the economical crisis
and bureaucratic processes the work started in full extent recently. During these 1.5
years, they started to work on the rough model. This period was an effective training
and preparation period for the staff. During this time, with the help of the online
forums, guides and vendor’s assistance, the firm started to generate its own methods
and strategies in using BIM. And at the end of this period, they had a rough model to
be detailed, and a trained staff that consists of 10 people. Normally, waiting for such
a long time for a construction company would have been an important drawback;
however, this time had been a good transition for BIM for the company.
The architectural project (conceptual design) of the airport was sent in a DWG
format by JV of COWI & Partners and Larsen Architects and Consulting Engineer.
ENKA was asked to produce a three dimensional BIM model that incorporates the
static and mechanical projects.
11
3.2 Project Team and Organization
3.2.1 Project Team
When ENKA bought BIM software there was not any staff who was experienced in
BIM. The software vendor offered a training program which was at an introduction
level, for a limited number of staff. Afterwards, 4 people from this group, who will
be in charge of the project, got an extra period of training.
At the moment, there are 80 people working for the Muscat International Airport
project. For this project approximately 60 architects were hired. The most important
criteria for the company to hire these architects were their experiences and skills in
BIM. However finding experienced BIM users was not an easy task. Therefore, they
even had to hire some architects with no BIM knowledge at all. The hired architects
were mostly young architects and new graduates. Knowledge and experience levels
of the staff now are quite diverse. Every individual is personally working to improve
themselves to catch up with the project requirements. Seminars and trainings are
organized for the new staff. Also some architects follow independent trainings on
their own support. It takes at least 15 days for a new staff to adapt the office’s
requirements and BIM principles. Then they start working with an experienced
architect of the company and learning by assisting him/her.
Fig.5. A view from architecture department of ENKA
12
3.2.2 Project Organization and Work Loads
One of the most important aspects of BIM is that, the process is based on a practice
where different actors take part in a project work together on one single model, and
all the information flow is realized through this model. This makes it easier, more
practical and precise for different actors from different disciplines collaborate with
each other. In order to make the collaboration run easier, more practical and precise
as desired, the methods of collaboration and the organization of the collaborators are
vital. A well modeled team organization leads to an efficient workflow and a clearer
and reliable communication with engineers, contractors, fabricators and owners.
3.2.2.1 Preliminary process and draft model
From the early phases of Muscat International Airport project till today, project team
organization changes due to the workload of the phase. In the early phases of the
project (first 1.5 years) there were 3 main teams in charge and each team consists of
approximately 10 people. One group was to generate the model libraries, the second
to generate the model, and the third one for generating the drawings. Even though
there might have been different types of labor division, this model of organization
was sufficient for this very first phase for ENKA. In this organizational model, the
first group was working to create a unique model library for this particular airport
project. This library was following the standards of ENKA, the standards that have
been used and inured since years during the previous experiences of the company.
However, the new library had to be appropriate for the particular airport project,
while being suitable and efficient to be used in BIM process. Therefore a team which
works on the transition of the existing standards into the BIM process of the new
project was necessary. The second group who was working on the model generation
was using this new model library. And the third group was using this model to
generate the drawings out of, since conventional drawings still constitute an
important and valid medium.
13
3.2.2.2 Labor divisions
After ENKA officially started the airport project, the number of employees was
increased and therefore the project team organization was changed. As mentioned
before, at the moment, there are 80 people working on the model. Such a large
amount of team members who work on the same model makes the definition of the
obligations and responsibilities of each single member very crucial.
The first things to consider when starting a shared project are the team sizes
according to the project size and roles of the team members. The control mechanism
and hierarchy on the work sharing, which are crucial matters within the division of
labor, is formed per se according to the architects’ personal experiences in BIM and
architectural materials. For each project matter, there is a team of approximately 10
people in which 2 or 3 of them are responsible for the coordination. And the entire
team is coordinated by a team leader and the project manager. Everyone has to
follow certain well defined roles and methods in terms of the labor division. In order
to define this division for the airport project, the model was first divided into sub-
parts. Different groups of building components such as walls, ceilings or structural
elements were defined as the sub-parts of the model. Then each group got the
responsibility of one single component group of the building and started working on
their own pre-defined tasks. For instance, there was a group of architects which was
responsible for the walls while there was another one which works on the ceilings.
These building components that are used by different groups in the model were the
ones that were generated by another group which was responsible for creating the
libraries.
The building components that need to be completed first are the walls. Because every
component in the building is related to each other and the tasks of teams should
follow each other. Once the walls are defined, the generation of structural elements
and other building components such as slabs can be done. In other words, after the
rough model that is made out of the walls is generated, all the team can start working
on their own work sets simultaneously.
14
While working separately on different sub-parts of the same model, the qualities of
the software which makes it possible to view the updates of other teams made it
possible to collaborate between the groups and work accordingly. This work sharing
across the project team provided simultaneous access for different groups to the same
shared model. Each group was working on their own work set while being able to
view the development of the other sets; however they were not able to do any change
on them. This quality of the software prevents the conflicts which can cause big
errors in the entire project.
3.3 Work Process
“Building information models may be shared during a project in many settings. In
full-service design and engineering organizations, information may be shared during
the design phase across several engineering disciplines (Fig.6). Such sharing would
require the identification of which group in the firm has access to add, edit, and
delete specific types of building systems and/or components. Procedures for version
control and check-in/check-out of individual parts of building models must be
established within these firms. Information assurance to identify who made what
changes and when is critical to future confidence in the information. Checks based
on the contents of the BIM for completeness, consistency, and collisions are enabled
when sufficient progress is made on the shared building model” (United States,
National Building Information Modeling Standards).
One important aspect of the work process is that it is also a learning process at the
same time. Since almost everyone is working on BIM, there are always interactions
among the staff within learning and improving. The company is constantly working
on building their own corporate standards and decisions for BIM use. Since the main
focus of the company is application projects, it is a very important matter to work
precisely. The qualities of the building components such as walls or doors are to be
decided precisely. The precision here refers to having all the information, both
geometrical and alpha-numeric, correctly. Because the drawings which will be used
15
at the construction site and the manufacturing details for prefabricated components
are generated directly from the model. Therefore preparation period for any project
becomes a vital issue.
Fig.6. Facility Lifecycle BIM Repository (United States, National Building Information
Modeling Standards).
The first issue to be completed in a work process is to gather the data, classification
of the data and accordingly building up the model libraries, and defining the model
types. What to be used as data and what to be defined as a type need to be well
defined. For instance, if an interior wall is defined as a type, then every team member
should use that type of the wall. That is why there is one specific team which is
responsible for generating the model libraries.
It requires a certain amount of time to start the BIM process of a project. It is because
it takes a while to gather the data in order to define the model base and get the main
project decisions. Hence, if this period is handled effectively, the following steps
become much faster. This means the work system needs to be precisely and well
defined at the beginning.
16
One of the very important aspects that are provided by BIM is the ease of revisions
on the project. As different representations of a building, such as the plans, sections
and elevations are separate medium when working with traditional CAD software,
any small revision that needs to be applied should be considered in all these different
mediums. However in a BIM model, all the information is stored in one single model
which also is used for generating the drawings. So any change that is applied on the
model updates the information in any types of mediums, and also different outputs
such as the lists and schedules. This feature of BIM does not only save time, but also
allows more precise and correct work process.
Still, 2 dimensional drawings, which are usually in dwg file format in CAD practices,
are valid. That is mainly because using the BIM model for construction on site is not
practical. Therefore 2 dimensional application drawings are generated through the
model to be used on site. These drawings can be generated in different scales such as
the site plans or 1/1 detail drawings. However, as Yurttakal mentions, ENKA does
not find it practical to try to generate each single construction detail from the same
model and they prefer to work on the details on 2 dimensional CAD software. This is
because a model that includes each single detail becomes too large and difficult to
handle. And such a model that is shared by a big number of team members has
potentials for any errors and break down. Because of these reasons, ENKA continues
using AutoCAD to generate these 2 dimensional detail drawings. Generating certain
drawings in two dimensional software is still a custom that makes the process faster.
And this working principle is also recommended by the software vendor as well.
This shows the fact the BIM solutions have to be interoperable with other CAD tools
such as 2 dimensional drafting or rendering software.
3.4 Interoperability
One of the main issues that need to be handled in a project is the work coordination
between collaborating companies. The three dimensional coordination between the
architectural, structural and mechanical solutions is very vital. Therefore ENKA
17
works with companies who use interoperable software. It was also a constraint in the
contract between ENKA and employer to work with companies that use such
software that can operate with Revit. For example one of the collaborators is using
Tekla.
ENKA is also planning to use Navisworks for coordination between collaborators. In
this way the overlapped architectural, static and mechanical areas will be pinpointed
and they will report and forward to the concerned collaborator so that they make the
necessary revisions.
4. CONCLUSION
The architectural project of Muscat Airport was prepared by JV of COWI & Partners
and Larsen Architects and Consulting Engineers. ENKA was responsible for
generating the BIM model through the geometrical models which were already
generated and prepare the constructional application project. This very first
experence of ENKA in using BIM is seen as a good example in terms of the
transformation of the work environment from traditional CAD practices to BIM.
ENKA, which is one of the leading architectural and constructional offices in
Turkey, had a great experience and their own standards and principles in using CAD.
However, the shift to BIM made it necessary to review these standards and principles
and model new ways of work and models of work environment. This paper aims at
researching this case and pointing out the crucial matters within transition to BIM.
One of the most important aspects of this case is that it is not only a process of a
work on a new project, but also a learning process for ENKA. During this process the
company encountered the innovative requirements that BIM brought about and they
had to update their work environment in terms of various aspects such as the
qualities of the staff, labor division among team members, corporate standards,
collaborational models and hardware capacities.
18
The architectural design of the airport was not a consideration for ENKA. Instead,
the task was to prepare the constructional application project. Therefore the material
information and constructional details for both the on-site construction and
prefabricated components needed to be well defined. This required to start the model
by generating the model libabries. The model libraries consisted of the detailed
components to be used in the model. The generation of these libraries was the first
step in the work process and labor division. The building component types were
defined as sub-groups and each sub-group is assigned to a different project team. The
simultaneous work of different project teams on the shared model and the overall
coordination became possible with the qualities of the software used.
The case shows that traditional models of team organization can not be anymore
valid for BIM. As a very novel practice, BIM requires to generate a virtual prototype
of the building which will be accessible to all of the collaborators. In other words,
unlike the traditional methods, the collaborators do not have their own spesific
medium to work on, but rather they work on the same medium, while each
collaborator have their own spesific work-set. Therefore the definitions of the work-
sets, the limits, obligations and responsibilities of each collaborator needs to be well
defined during the preperation phases of the work.
Using BIM, in one sense, makes the companies in AEC industry dependent on the
software vendors. Because interoperability, which is a very crucial aspect of BIM,
can only be realized between the collaborators who use the approriate software that
can operate together. One can say that only AEC companies who can follow the
innovations in the software industry can sustain their competative power in the
market. And this brings about the necessity to follow the innovations in hardware
technologies as well, as the new versions of the software demand more advanced
levels of hardware spesification. This points out to a new sort of economical cost for
the companies’ budget. Therefore it seems that only the companies who are able to
spare such a budget can sustain their existence in the market. Or on the other hand,
the companies with smaller budgets need to find new types of collaborations that will
help them to compete with the leading companies.
19
BIM leads to a new type of expertize definition in the market. In the close future, the
market will be demanding specialized BIM experts in terms of both the offices and
individuals. This is, in a way, the transformation of the practice of preparing
constructional application projects. Therefore this new definition will affect the
companies who compete in this field, while the ones who focus on the conceptual
design projects will be affected relatively less. The forthcoming BIM companies will
need to hire architects and engineers with the spesific knowledge and skills. And this
situation may refer to the remodelling of the curricula in the universities who aim at
educating professionals to easily fit into the market cycle.
20
REFERENCES
National Institute of Building Sciences, 2007, United States, National Building
Information Modeling Standards, Version-1, Part-1: Overview, Principles, and
Methodologies.
Url-1 < http://www.enka.com >, [Date Visited: 18.01.2011].
Url-2 <http://www.bechtel.com >, [Date Visited: 18.01.2011].
Url-3 < http://usa.autodesk.com/>, [Date Visited: 18.01.2011].
Url-4 < http://www.zawya.com/projects/project.cfm/pid130707112031?cc>, [Date
Visited: 18.01.2011].