The Stability of Stage-constructed Embankments on Soft Clays

download The Stability of Stage-constructed Embankments on Soft Clays

of 10

Transcript of The Stability of Stage-constructed Embankments on Soft Clays

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    1/23

    The stability of stage constructedembankments on soft clays

    F

    TAVENAS

    Depu r tmet~ t C ivi l Engineer ing , Ln\wl U t~ iw ui ry , uebec , P . Q. , Ca tlu tlo GI K 7P4

    A N D

    R .

    BLANCHET

    N D

    R . GARNEAU

    Terrurech L tke. ,

    Montreal

    P.Q . , Cunukr H4N IJI

    A N D

    S . LEROUEIL

    Deprrrttnent ( Civil Engit~e ering. u\ d U r~i~v,:c . i ty ,~ ~ e b e c ,.Q . , C (~r~c lclnI K 7 P 4

    Received June

    6 ,

    1977

    Accepted December 14,

    1977

    The stage construction of seven high embankments on soft clays on the north shore of the St.

    Lawrence Valley has provided an excellent opportunity to check the applicability of the concepts

    of limit and critical stat es to the analysis of the behaviourof clay foundations.

    The construction pore pressures have confirmed the development of

    a

    significant consolidation

    in the initial period of construction.

    The consequences of this consolidation on the behaviour of the clay, in particular in terms of

    available strength, and on the method of stability analysis have been found entirely consistent

    with the general model proposed by Leroueil, Tavenas, M ie ~~ ss en snd Peignaud.

    It is suggested that the so-called

    0

    analysis based on the vane shear strength corrected

    according to Bjerlum gives the minimum factor of safety and may be too conservative during

    stage construction. Effective stress analyses are shown to be more representative of the true

    stability conditions, and they have been successfully used to accelerate the construction of the

    embankments.

    La construction par etapes de sept grands remblais sur des argiles molles de la rive nord du

    f le~~veaint-Laurent a fourni une excellente occasion cle verifier I'applicabilite des concep ts

    d'i ta t limite et d'ktat critique I'analyse du comportement des fondations argileuses.

    Les pressions interstitielles observees durant la construction ont confirme I'existence d'une

    consolidation importante au debut de la construction. Les consCquences de cette consolidation

    sur le comportement de I'argile, en particulier en ce qui concerne la resistance au cisaillement

    disponible, et sur les methodes d'analyse de la stabilite ont ete trouvees entierement en accord

    avec le rnodele general propose par Leroueil, Tavenas, Mieussens et Peignaud.

    On suggere que la methode dite c

    0

    basee sur la resistance au cisaillement mesuree au

    scissomktre et corligee selon Bjerrum donne la valeur minimum du facteurde securite et peut re

    trop pessimiste pour une construction par etapes. I1 est montre que les analyses en contraintes

    effectives sont plus representatives des conditions rCelles de stabilite, et qu'elles ont ete u tilisie s

    avec succes pour accC1Crer la construc tion d es remblais.

    Can Geotech J .

    15,283-305 1978)

    Introduction

    T he evaluation of th e stability of e mba nkme nts

    on soft clay deposits has always been a problem of

    major interest to geotechnical

    engineers

    and re-

    searchers. In recent years, much attention has been

    paid to the evaluation of the stability of fills built

    in a single construction phase. The use of a total

    stress, or

    0

    method of analysis connectcd

    with undrained shear strength values obtained from

    in s i t ~ l ane tests has been widely accepted. How-

    ever, based on the analysis of a number of ac-

    cidental failures as well as on an impressive series

    oE test fills built u p to failu re, th e shortco ming s of

    this method have been put in cvidence particu-

    larly by Bjerrum 19 72 ). As a result of the

    continuing research effort on this problem, thc

    necessity of empirical co rrecti ons of the results of

    0

    analysis, as proposed by Bjerrum, was at

    first confirmed Pilo t 19 72 ; Dasca l et al. 1 9 7 2 ) ;

    however, thc theoretical justification of such cor-

    rections was questioned, and othcr approaches to

    tbe

    0

    analysis were then proposed L a

    Rochelle

    et

    al 19 74 ). Mo re recently, Schmertmann

    1975) has even questioned the use of total

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    2/23

    284 C A N

    G E O T E C H .

    J . VOL.

    15

    1978

    stress approaches to the analysis of stability prob-

    lems in clays and he suggested that more con-

    sideration be given to methods based on effective

    stresses in spite of the practical difficulties noted

    by Ladd (1975). Surprisingly, little attention has

    been given to effective stress analyses in the

    evaluation of accidental or test failures, so that the

    relevance of this method has yet to be firmly

    established. In spite of these p roblems, th e evalua-

    tion of the stability of embankments built in a

    single phase can presently be carried out with a fair

    degree of reliability and economic designs are

    possible.

    The situation is quite different when stage con-

    struction is necessary for high embankments on

    soft clays. The method already discussed is ap-

    plicable to determine the geometry and stability

    conditions of the embankment at the end of the

    first construction phase. However, for the design

    of the further stages, two major difficulties arise in

    the determination of the increased strength pro-

    duced in the clay foundation during its consolida-

    tion.

    In preliminary design, the rate of increase of the

    vertical effective stress P,. has to be evaluated

    from the consolidation theory. Unfortunately, this

    is done only with great uncertainties, owing to the

    difficulties in measuring properly the coefficient of

    consolidation C, of the clay and in defining the

    true boundary conditions. Thus, in situ pore pres-

    sure measurements appear as a necessary control

    of the design assumptions during construction.

    Th e gain in undrained strength C,, produced by

    the consolidation under an increased effective ver-

    tical stress P, may be evaluated by two equally

    accepted methods. Having recognized that the

    relationship between C,, and the consolidation pres-

    sure is unique for a given material, one can deter-

    mine the value of th e ratio C,,/P , for the site und er

    consideration. This ratio, obtained at various

    depths from

    in situ

    vane tests and from oedometer

    test results, generally varies between 0.2 and 0.35.

    Its local value may be used in conjunction with P,.

    to obtain the new strength of the clay at any stage

    of construction and consolidation. Another ap-

    proach is by means of the so-called measured

    in consolidated undrained triaxial tests. Knowing

    the initial cohesion Cllo nd the corresponding con-

    solidation pressure P C, the cohesion C,, produced

    by a consolidatio n to P, is obta ined from

    C,, C,,,,

    (P,.

    P C ) a n

    c,,

    ,T h e new undrained strength profile , obtained in

    this way at the end of e ach consolidation phase, is

    used in a

    4

    0 analysis to determine the geomet

    and stability condition for the next stage of con

    struction of the embankment.

    In general, this practice has been satisfacto

    inasmuch as instability problems have seldom o

    curred. However,

    in situ

    measurements have show

    that undrained strength increases were not sy

    tematic, and the possibility of a temporary d

    crease of C,, during consolidation has even bee

    suggested by Lefebvre

    et 01

    (1974) on the bas

    of laborato ry tests. In th e framework of th e pre

    ent methods of stability analysis such a decrea

    in the undrained shear strength of the clay shou

    result in a corresponding decrease in the safe

    of the embankment so that delayed failure cou

    be possible. Yet, no clear case of 'long term' failu

    has been reported in the literature. This appare

    discrepancy might be associated with a lack o

    understanding of the true behaviour of the cla

    and points out the necessity of

    a

    careful analys

    of the phenomena that develop during constructio

    in a clay foundation.

    Schem atic Behaviou r of a Clay Foundation

    Th e concepts of limit and critical states propose

    by Roscoc et al. (1958) a nd the YL IGH T (Yie

    Locus Influenced by G eological History and Tim e

    model developed from these concepts by Taven

    and Leroueil (1977) have proved helpful in th

    analysis of the behaviour of clay foundations.

    Natural clays occur in a more or less overcon

    solidated state

    itz situ.

    At a given depth, the m

    chanical behav iour of the clay might be complete

    characterized by its preconsolidation pressure P

    its void ratio e its compression index C and i

    recomp ression index C,, a nd by its effective fri

    tion angle 4' in the normally consolidated stat

    In addition to being representative of the minimu

    effective strength available in the clay, 4' has al

    governed the stress conditions during the depos

    tion and consolidation of the deposit since, as

    well known, K O 0.9 (1 s in 4 ' ) . The void ra t

    e

    and the preconsolidation pressure P,

    a re t

    results of the combined effects of stress histor

    aging, thixotropic hardening and possibly ceme

    tation, the indices C, and C,, being also a resu

    of the same phenomena. Roscoe

    et

    al. ( 1 9 5 8

    have shown that the stress boundary between t

    overconsolidated and normally consolidated stat

    in a clay at a given void ratio, represented by P,

    oedom eter test conditions, is a unique surface in th

    stress space, called the limit state surface. The

    also showed that the strength of this clay is uniqu

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    3/23

    T A V E N A S ET A L . 285

    FIG. 1. Limit s ta te sur faces in in tac t and no rmal l y con -

    sol idated natural c lays .

    for given values of e and + , thus defining the so-

    called critical state.

    Tavenas and Leroueil (1977) have shown that

    these concepts could be applied to natural clays

    provided that the phenomena occurring during

    deposition and consolidation of these clays were

    properly accounted for. In particular they showed

    that the

    KO

    stress condition that prevails during

    deposition a nd th e com bined effects of aging, thixo-

    tropic hardening and cementation result in a limit

    s tate surface with a shape s imilar to Yo (Fig. la) .

    The critical state for such clays with a strain soft-

    ening behaviour is within the limit state at a point

    such as Co, on the 'large strain' effective strength

    envelope of the clay.

    Th e initial s tudy by Tavenas and L eroueil (1977)

    had indicated th at the limit state surface Y o was

    time dependent. In addition, a recent investigation

    by Brucy (19 77 ) showed that the shape of Y o is

    partly due to structural effects in the clay: when

    consolidating the intact clay just beyond P these

    effects are destroyed in the now normally con-

    solidated clay; the new limit state surface assumes

    a shape such as Y,, (Fig. l b ) , i .e. coinciding in i ts

    upper portion with the effective strength envelope

    at large strains; on the other hand, the critical state

    Co

    remains practically unchanged owing to the

    minimal variation in void ratio during this process.

    Leroueil

    et

    al. (1978) have used these concepts

    to interpret the variations of p ore pressures ob-

    served during embankment constructions in clay

    foundations. Based on the analysis of 30 case his-

    tories, they established that a significant consolida-

    tion develops during the early stages of construc-

    tion of an em bankm ent, owing to the initial rigidity

    and the associated high C in the overconsolidated

    clay. As a result of this consolidation the effective

    stress path under the center line of the embank-

    ment is such as OP (F ig . I b ) . At P, the clay be-

    comes normally consolidated; its rigidity and thus

    its coefficient of consolidation C, are considerably

    reduced so that further loading occurs in undrained

    condition. The limit state theory implies that, dur-

    ing undrained loading, pore pressures are gen-

    erated at such a rate that the effective stress con-

    dition remains on the limit state surface of the

    clay. In the present case this surface is the new Y,,

    corresponding to the normally consolidated state

    of the clay and the effective stresses will thus fol-

    low Y,, between

    P

    and o where complete failure

    of the fou ndation will occur. Leroueil

    et

    al. (1978 )

    have shown that the variations of the observed

    pore pressure with the applied embankment loads

    were entirely consistent with these principles for

    all considered case histories. As a result they have

    suggested some consequences of these effective

    stress variations during construction on the meth-

    ods of stability analysis and on the strength to use

    in these methods to arrive at a proper design of

    cmbankments .

    Th e design and construction of the Berthier-

    ville-Yamachiche section of the A.4 0 Highway on

    the north shore of the St. Lawrence River (F ig.

    2

    provided a n interesting case for the application and

    verification of these principles and suggestions.

    Seven overpass structures with 8.5-9 m high access

    embankments had to be built in stages on soft clay

    deposits similar to those encountered under the

    Berthierville embankments described by Samson

    and Garneau (1973). Four of the seven overpass

    structures, identified as B,

    C,

    D

    and

    E

    on Fig.

    2

    are considered here and it is the purpose of this

    paper to discuss the behaviour of the foundation

    clays during the stage construction in terms of the

    generation of pore pressures, the variations in un-

    drained shear strength and the stability conditions.

    As a result, the validity of the concepts developed

    by Tavenas and Leroueil (1977) and Leroueil

    e al. (1978) will be demonstrated, enabling the

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    4/23

    286 C A N . G E O T E C H . J .

    VOL..

    IS, 1978

    FIG . Location of investigated sites

    formulation of a general procedure for the eval-

    uation of the stability of stage constructed embank-

    mcnts.

    escription of the Sites

    Between Bcrthierville and Yamachiche (Fig. 2 ) ,

    the new section of the A.40 Highway runs through

    lowlands along the north shore of t he St. Lawren ce

    River and Lake St. Peter. This region is char-

    acterized from a geological point of view by very

    thick deposits of soft clays formcd in the Cham-

    plain Sea, during the period extending between

    12 00 0 years and 8500 years before present. Fol-

    lowing this period, the region was first covered

    by the post-glacial lake Lampsilis (Prest 1970),

    and later progressively assumed its present deltaic

    configuration. During these stages stratified de-

    posits of clay silt and sand were formcd in soft or

    brackish water.

    The geotechnical investigation at the sites of

    the various structures between Berthierville an

    Yamachiche has confirmed the existence of th

    two types of deposits under the ground surfac

    which is nearly horizontal at elevation 6 m . A

    all sites, the deep marine Champlain clay extend

    over a thickness of 53-73 m above the bedrock o

    a thin layer of bottom till, which are encountere

    at elevations varying from -60 to -80 m. Th

    upper limit of the marine clay is remarkably ho

    izontal at elevation

    -6

    m. This deposit is ver

    uniform in its properties: the natural water con

    tent varies arou nd an average of 6 0 , the liqu

    limit is of the ord er of 75 and the plasticity inde

    is abo ut 50 over the full extent of the depos

    at all sites. The undrained shear strength measure

    by field vanc tests increases linearly with dep

    with average values of 40 kP a at elevation -10

    and 80 kPa at elevation -30 m ; the sensitivity a

    mea sured by field van c is of th e ord er of 10-15

    Consolidation tests have shown that this clay

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    5/23

    sl ight ly overconsol idated, the measured values of

    P,. Po varying between 0 and 70 kP a wi th an

    average of 30 kPa. The C J P , , rat io is thus of the

    order of 0.29.

    Above this homogeneous marine clay formation,

    the lacustrine and fluvioglacial deposi ts are some-

    what variable from si te to s i te. In the western part

    of the region, at Rang St-Georges and Rang du

    Fleuve (F ig . 3 ) , the upper par t of the depos i t con-

    sists of a thin layer of weathered silt , clay and sand

    down to elevat ion +5.5 m, a very soft s i l ty clay

    layer extending to an elevat ion varying from 2 to

    0.5 m, and a stratified deposit of silty clay and

    clayey silt with local seams or discontinuous layers

    of silty sand. The soft silty clay between elevation

    +5.5 m and 0.5 m has a water content of the

    ordcr of 80%, a l iquid l imit of 70% and a plast ic-

    i ty index of 5 0 % ; i ts undrained shear s t rength is

    about cons tan t and equal to 12 kPa throughout the

    layer. The strat i f ied deposi t encountcred between

    elevat ion +2 and

    -6

    m at Rang S t -Georges and

    between elevat ion 0.5 m an d -6 m a t R a n g d u

    Fleuve is well identified in terms of its natural

    water content, liquid limit and plasticity index, but

    i ts undrained shear s t rength exhibi ts a cont inuous

    profi le with the s t rengths of the over- and under-

    lying clay formations. These surficial deposi ts ap-

    pear pract ical ly normally consol idated with an

    overconsol idat ion P,. Po of the order of 10 kPa.

    In the cen t ra l part o f the reg ion , a t Ran g de l a

    Concession (Fig. 4a) a 2 m thick layer of loose to

    medium dense s i l ty sand is encountered at ground

    surface. Und er this layer, at elevat ion 4 m, the

    stratified silty clay and clayey silt deposit contains

    very l i t t le sand and becomes more clayey between

    elevat ions 0 and -6 m; i t presents a water content

    and a l iquid l imit of the order of 50%, a plasticity

    index averag ing 25% and an undrained shear

    strength with a minimum value of 2 0 kP a a t eleva-

    t ion 0, increasing with depth under this level . Fi-

    nal ly, at the eastern end of the region, at Rang du

    Bri lC (Fig. 4b), the s t rat igraphy is s imilar to that

    encountcred in the west but the s i lty clay layer be-

    tween elevat ion +5 a nd 0.5 m is less plast ic, and

    i t has a smaller water content of 60 % and a higher

    undrained sh ear s t rength of the order of 2 0 kP a a t

    elevat ion +3 m. Thes e deposi ts have probably been

    submit ted to a preconsol idat ion somewhat greater

    than in the western area, P,.

    P

    being of the or dcr

    of 20-30 kPa. The C , , / P , ratio in these surficial

    deposi ts will b e discussed later.

    T A V E N A S T

    A L .

    287

    Design and onstruction of the Fills

    The lowlands on which Highway A.40 i s bu i l t

    are frequently flooded in the spring a nd i t was nec-

    essary to establish the finished grade of the high-

    way 2 m above the original ground surface. As a

    resul t , al l overpass s t ructures had to be raised and

    access emb ankm ents with heights of 8.5-9 m were

    necessary. Considering the low undrained shear

    strength of the foundat ion clays, such high em-

    bankments could not be bu i lt in one sequence and

    the s tage cons t ruct ion method had to be used .

    Design Method

    Based on the usual assumption of undrained be-

    haviour of the clay foundat ion during each short

    period of fill placement, the stability of embank-

    ments during construct ion is commonly evaluated

    by means of a 0 method of analysis . Fo r the

    initial construction, the maximum height of fill

    compatible with an acceptable factor of safety,

    taken equal to 1.3 here, was determined by such

    a

    0 method using the undrained shear s t rength

    of the clay measured b y

    it2 situ

    vane tests. Th e com-

    puted factors of safety were corrected as proposed

    by Bjerrum (1972) to account for the d i f ferences

    in the shear s t rength, measured by vane test and

    actual ly avai lable under embankments .

    For the analysis of the stability during subse-

    quen t construct ion stages, the use of the 0

    method was cont inued. The new increased un-

    drained shear s t rength produced by the part ial

    consol idat ion of t he clay foundat ion was est imated

    on the basis of local values of the C , , / P , rat io. In

    the present case, a n av erage value of C,, /P , . 0 . 2 7

    was considered representative of the different clay

    deposi ts a nd was used for al l designs.

    In ord er to evaluate the undrained shear s t rength

    avai lable during each construct ion stage, the ver-

    tical effective stress

    P,

    had to be know n. Al though

    an initial estimate of the variations in P, , C,, and

    the resul t ing permissible construct ion schedule was

    mad e on the basis of a one-dimensional consol ida-

    t ion analysis , i t was considered necessary to check

    the actual progress of the consol idat ion by means

    of direct pore pressure observat ions. A minimum

    of 3 or

    4

    pore pressure cells were installed in all

    foundat ions as shown in F igs. 3a and 4 b . Fur ther-

    more , for the embankm ents located in the wes tern

    area of the region, multiple construction stages

    could be an t ic ipated and i t appeared des i rab le to

    check the actual magnitude of the increase in un-

    dra ined shear s t rength under these e mbankme nts in

    an effort to opt imize the construct ion; in situ v an e

    tests were thus carried out under the fi l ls during

    construct ion.

    Geometry and Constr~~ct iotzf t he E m bank m e nt s

    T he requirements of the Ministry of Trans port

    of Quebec cal led for the beginning of c onstruct ion

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    6/23

    CAN GEOTECH J. V O L . 15, 1978

    Gloetzl piezometer

    LP plast ic l imit

    ( lo)

    LLL

    L

    l iqu id l imit ( Io)

    2 0 4 0 6 0 8 0 0 2 0 4 0 6 0 8 0

    na tur ol water c ontent ( Io)

    W.LL.LP,(~/O) C,.kPa

    -RANG ST-GEORGES

    b-R AN G DU FLEUVE

    FIG Geon ~et ry oundat ion condi t ions and ins trunlenta t ion ang St -Georges and Rang du Fleuve .

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    7/23

    T A V E N A S

    ET A 1

    - ror ia i no l around sur face

    Lwater table

    W P Z - 1 5 3

    v

    W P Z - 1 5 2

    silt and cloy,soft,sensitive

    @

    marine si l ty c lay,sof t to f ir rqsensit ive

    1 I I \ l

    Legend

    Hydraulic piezometer

    Gloetzl piezometer

    Geonor piezometer

    P L L W L P =plastic limit (O/O)

    2 0

    40

    60

    8 0

    0

    2 0

    40

    6

    8

    LL

    =l iqu id l im i t

    O/O)

    W notural woter content ( )

    0 RANG DE L A CONCESSION.

    15

    10

     

    orioinol

    5

    0

    - 5

    E-

     

    10

    ..

    I5

    -20

    25

    Gloetzl piezometer

    30

    L P plas t ic l imit (O/O)

    35

    W,LL,LP,(O/O) Cu,

    kPa

    b-RANG

    DU BRULE

    iJopsoil

    @ silty clay and sond

    @

    si l ty c loy ,sof t ,sensit ive

    @ stratif ied silty cloy and clayey

    silt ,soft,sensitive

    @

    morine si l ty c la y,sof t to f irm sc

    FIG . Geometry foundation conditions and instrumentation ang de la Concession and Rang du Briil6.

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    8/23

    C A N .

    G E O T E C H . J. VOL. 15 1978

    2

    4

    7

    9

    1

    h lght

    of i l l

    m

    FIG

    Variation of the factor of safety with the height of fil l p laced in the first construction stage.

    of the most critical fills at Rang St-Georges and

    Rang du Fleuve in 19 72 , in view of a comp letion

    around 1977. Othcr embankments were to b e built

    later, starting between 1 97 3 and 19 75 .

    The stability analysis had first indicated the

    necessity of providing all embankments with lateral

    and frontal berms. Th e height and width of such

    berms had initially been selected at 2.4 and 15 m,

    respectively, for all embankments. However, the

    height was later increased to 3.0 at Rang du BrQlC

    and Rang de la Concession to take advantage of

    Ihc higher strcngth of the foundation at these loca-

    tions.

    The stability analysis of the initial construction

    sequence was carried out for various heights of fill,

    with the actual berm geometry and with a unique

    slope inclination of 2 : l . The modified Bishop

    method was used for all computations. The

    strength parameters were taken equal to 35 for

    the friction angle of the compacted fill material, to

    30 for thc loose silty sand forming the upper

    foundation layer at Rang de la Concession and to

    the vane shear strength profile obtained by n

    s t ~

    tests at each site prior to construction, and were

    corrected according to Bjerrum 19 72 ).

    Th e variations of the comp uted facto rs of safety

    with the height of fill are shown on F ig. 5. T he low

    initial shear strength at Rang St-Georges and Rang

    du Fleuve resu lts in low factors of safcty, which

    become rapidly less than the permissible minimum

    value of 1 .3. O n the other hand the higher strengt

    at Ran g du BrQlC and the uppcr silty sand layer a

    Rang de la Concession have an obvious beneficia

    effect, the co mp uted fact ors of safety being nearl

    sufficient to consider a construction in one stag

    As can be secn on Fig. 5 the maximum heights a

    the end of the first construction stage, compatib

    with a factor of safety of 1.3 after correction ac

    cording to Bjerrum (1972) , a re 4 .7 m a t Ran

    St-Georgcs, 3.8 m at Rang du Fleuve, 7.1 m a

    Rang de la Concession and 8.2 m at Rang d

    Brfild. However, the actual construction schedul

    was affected by non-technical considerations s

    that the heights of fill actually placed during th

    initial and subsequent construction stages hav

    varied, as shown on Fig.

    6. As of Novembcr 197

    the em bankm ent at R ang d u BrQlC was practicall

    completed and within 0.5 m of its final height

    Rang de la Concession; on the other hand, owin

    to the accumulated settlements about 2 m of fi

    remained to be placed to bring the embankmen

    to their final grade at Rang St-Georges and Ran

    du Fleuvc.

    onstruction Pore Pressures

    The systematic control of pore pressures durin

    construction was considered an essential part o

    the design of the embankments. The foundation

    of all fills were thus instrum ented b y mcan s of 3 o

    4 Gloetzl-type pneumatic pore pressure cells fo

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    9/23

    T A V E N A S T A L

    time, days

    m oy 72 nov 72 m 73 n 73 m 74 n 74 m 75 n 75 m ay 76 nov 76

    time, years

    FIG.

    .

    Schedu le o f const ruct ion o f the four embankments .

    lowing patterns such as those presented in Figs. 3a

    and 4b. However, in order to develop a clear

    understand ing of the pore pressure distribution, the

    foundations at Rang du Fleuve and Rang de la

    Concession were equipped with complementary

    instru men tation consisting respectively of 1 2 and

    14 Gloetzl (pneu matic) and Geon or (vibrating

    wire) pore pressure cells, as shown on Figs. 3 b and

    4a. Systematic pore pressure observations before,

    during and after each construction phase have

    allowed the analysis of the setup of construction

    pore pressures.

    Pore Pressures under the Center Lines of the Fills

    Figure 7 shows the variations as a function of

    th e em bankm en t lo ad A ~ Hf the excess pore pres-

    sure A U at various depths under the center line of

    the fills at Rang du Fleuve and Rang de la Con-

    cession.

    T h e variations of Au ar e in agreement with the

    general model of pore pressure generation pro-

    posed by Leroueil et al. (1978), the principle of

    which is presented in Fig. 8. At the beginning of

    construction, the clay behaves as an overconsol-

    idated material with

    a

    high C, and a significant

    consolidation develops to produce values of the

    pore pressur e coefficients r,, o r of the order of

    0.4-0.6. A s a result the effective vertical stress P,

    increases and eventually becomes equ al to P, when

    AU,

    ACT^,,,.^, P,

    Po1

    At this point the clay

    becomes normally consolidated and any further

    construction at constant effective vertical stress has

    a resulting value of r or equal to 1 O. A s indi-

    cated on Fig. 8, the horizontal distance between th e

    actual hu

    f

    ( ay H ) curve and the Au AyH line,

    which is equal to the effective vertical strcss,

    s ho ul d, f o r l o ad s i n ex cess of A w ~ , ( , ~ ~ ,epresent the

    overconsolidation pressure in the clay at the level

    of thc pore pressure measurement. Analysing Fig.

    7 on e finds a preconso lidation difference P, P,,

    of the order of 10-15 kPa at 9 m depth at Rang

    du Fleuve and of the order of 25-35 kPa at 9 m

    depth at Rang de la Concession; these values are

    in very close agreement with the results of o edom -

    eter tests.

    Th e model of pore pressure generation proposed

    by Leroueil et al. (1978) implies that the rate of

    pore pressure buildu p during the co nstruction stages

    subsequent to a first consolidation period must

    be such that r, , or is equal to 1.0 . Such a pore

    pressure behaviour may be observed on Fig. 7b for

    embankment loads up to 10 0 kPa ; it was also

    observed fo r embankment loads up to 12 0 kPa

    at Rang St-Georges and for all construction stages

    at Ran g d u BrQlC and Ra ng dc la Concession thus

    confirming the validity of the model of Leroucil

    t

    al. However, during the final loading stages at

    Rang St-Georges and Rang du Fleuve (Fig. 7b),

    the pore pressure increase was less and corre-

    spon ded to r,, of the ord er of 0.5-0.7. Thes e re-

    duced values of r, , may be associated with the

    narrowing of the fill crest, and mainly with the

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    10/23

    CAN G E O T E C H . J . VOL. 15 1978

    piezometer depth

    A PZ-8 9 . 2 m

    A

    PZ 102

    9 . 2 m

    Z - 9

    3 . 2 m

    a RANG DE

    LA

    CONCESSION

    RANG DU FLEUVE

    FIG.

    .

    Variation of the observed pore pressure with the applied embankment load.

    change

    in total vertical

    stress

    Am

    FIG.

    Principle of the pore pressure generation model

    proposed by ~eioueil

    l

    d

    1978) .

    development of non-uniform stress distribution

    in theffill when it is deformed by the settlements

    of the foundation. This effect of the settlement of

    the foundation on the stress distribution at the

    base of the embankrncnt has been evidenced by

    Parry 19 72 ). Indeed the f il ls where the reduced r

    were observed had been in place for 3-4 years

    and had settled 1.4-1.6 m when the phenome no

    developed. Because of this arching the total stres

    increase induced by construction would be reduce

    under the center of the embankment but addition

    stresses would be thrown onto the toes of th

    fill. The pore pressures observed at different loca

    tions Fig. 9) under the Ran g St-Georges cmbank

    ment would tend to confirm the validity of th

    assumption: although the r distribution is norm

    for the load increments up to 6.5 m of fill, fo

    the last construction stage, rcduced r develo

    under the center line whereas increased r occu

    under the slope and the berm of the embankrncn

    This observation, which has an important influenc

    on t he analy sis of stability in effective stresse

    \vould need to be confirmed by more detaile

    investigation of the pore pressure behaviour und

    other embankments .

    Distributior7s of Po re Pressur es ar7d r Fa cto rs

    Under the embankments at Rang du Fleuv

    and Rang de la Concession, the instrumentatio

    for pore pressure measurements was sufficient

    allow for the determination of the complete por

    pressure regime. Figure 1 0a shows the lines of e qu

    pore pressure isobars) under Rang de la Conce

    sion on July 6, 197 6.

    A

    similar result was o btaine

    at all stages of construction undcr the two wel

    instrumented fills; by analogy and considering th

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    11/23

    T A V E N A S E T

    A L.

    lo r

    I

    I

    FIG. . Distribution of the

    r.

    coefficient a t various stages of construction of the Rang St-Georges fill.

    10   and fill 2

    v

    yt 18.4kN m3

    roriginol ground

    s u r f a c a

    v Gloetzl ptezometer

    - 2 0

    P

    r Geonar p~ezomeler

    3 sobar in metre of eoter

    -1.0- iso-

    r

    AY

    .FIG.

    0.

    Distribution of the pore pressures and

    r.

    coefficient under the Rang de la Concession f i l l

    local stratigraphy and the limited number of p ore

    pressure observations isobar networks were also

    established a t various stag es of constru ction of all

    fills. On the basis of such networks the stability of

    the embankments could be evaluated by means of

    effective stress analysis at any time.

    In order to predict the stability of an embank-

    ment befo re increasing its height it is necessary

    to predict the pore pressure after construction.

    Although the method proposed by Leroueil

    t al.

    1978)

    applies below the center line of the em-

    bankm ent the only reliable metho d applicable to

    the entire foundation consists in determining the

    distribution of the

    r

    au/a. H factors during

    each construction phase and using this result for

    predicting thc pore pressure setup during the next

    construction stage. Figure lob presents the iso-i

    observed under the Ran g d e la Concession fill . Th e

    high r values under the berm far away from the

    zone of load applica tion should be note d. A similar

    pattern was observed under all emb ankm ents in-

    dicating total stress variations different from those

    predicted by the thcory of elasticity or

    a

    significant

    effect of lateral spreading of the pore pressure by

    consolidation-like phenom ena. I n view of the strong

    influence of such pore pressure patterns on the

    effectivc stress stability analysis this phenomenon

    deserves further consideration in future.

    It is beyond the scope of this paper to analyse

    the dissipation of pore pressures between con-

    struction periods. It should only be noted that pore

    pressure dissipation did occur at all times and loca-

    tions leading to increa ses in cffective stresses as

    shown on Fig. 7b.

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    12/23

    294 C A N . G E O T E C H

    bserved Variations of the Vane Shear Strength

    In order to check the validity of the design

    ,~ssum ptions oncerning the gain in undrained shear

    strength resulting from the consolidation under the

    embankm ent loading, it situ vane shear tests were

    performed by means of a Nilcon vane under the

    centcr line and the berms of the different embank-

    ments. In addition, a reference vane profile was

    determined in an unloadcd area near each s ite.

    The periods at which these tests were carried out

    at the four sites discussed in this paper are in-

    dicated on Fig. 6.

    At Rang St-Georges, vane tests were performed

    in Jun e 1 973 , 40 0 days after the beginning of the

    construction, whcn the fill was 6.0 m high, and

    again in September 1975, 1130 days after the be-

    ginning of construction, when the fill was 7.4 m

    high. The average initial vane shear strength pro-

    file and the shear strengths measured in June 1973

    and September 1975 are shown on F ig . 11 . The

    increase in strcngth is evidcnt in the up per 12 m

    of the foundation. The shape of the C, , profiles

    suggests that the stratified silt and sand layer

    between elevation 0.5 m and 2 m had a draining

    effect in the foundation. The effects of increased

    times and embankment loads on the shear s trcngth

    are obvious, confirming that thc development of

    consolidation in the clay does result in an increased

    shear strcngth. The magnitude of the increase in C, ,

    could be compared to the change in vertical effec-

    tive stress at elcvation 4.2 an d -3.0 m, whe re

    pore pressures were measured. Before construction

    C, , /P , were computed from the results of con-

    solidation tests; after construction the vertical effec-

    tive stress was obtained from the computed vertical

    total stresses and the obscrved pore pressures. The

    resulting

    C, , /P ,

    and

    C,,/P,

    are shown in Table 1.

    At Rang du Fleuve, vane tests performed under

    the 5.8 m high f il l and the 2.4 m high berm 830

    days after the beginning of construction also evi-

    denced the gain in undrained shear strength caused

    by consolidation under the embankment loads, as

    shown in Fig. 12: the vane shear strength profiles

    assume an isochrone-like shape, influenced by the

    draining effect of a stratified sandy layer between

    elevations +0.5 and -1.5 m ; the s trength increases

    are mo re significant und er the high load of the m ain

    embankment than under the lower berm; no

    strength increase is observed below elcvation -7.0

    m where little settlement has developed. The varia-

    tions in the C,,/P, ratio could be estimated at

    elevation 3.5 m unde r the center line of the fill

    and at elevation 3.7 m under thc berm, where

    pore pressure observations were available. The

    J.

    V O L . 15,

    1978

    C . undr m e d s hwr S t r ena lh . k Pa

    sand before and after selllement

    rntttal vane shear strength

    overage of

    4 profiles

    .

    vane shear strenqlh under 6. 0

    metres of f111 4CC days afte r

    beqinnmg of construction

    vane shear strength under 7 4

    metres of ftl1 1130 days after

    FIG 1

    Varia t ions

    of

    the vane shear s trength under th

    center line of the embankment at Rang St-Georges.

    values of C, , /P , before construction and C, , /P

    at the time of the vane shear tcsts are given

    Table

    1.

    As shown in Table 1, in all cases the consolid

    tion under the embankment load has produced

    reduction in the C,,/P, ratio. In order to check

    such reduction was systematic, the

    C,,/P,

    rati

    were computed at all possible locations under t

    seven fills. In each case, the in itialvane shear streng

    and thc P,, measured in oedometer tests were use

    to compute C,,/P,. before construction; the s imu

    taneous observations of

    C, ,

    and the pore pressur

    during construction were used to obtain C,,/P

    corresponding to thp, prevailing embankment loa

    The results are presented in Fig. 13. The initi

    C,,/P, .decreases from a maximum of 0.4 at 1.5

    depth to an average of 0.26 at 6.0

    m

    in the upp

    plastic and probably slightly weathered clay; in t

    intermediate low plastic silty clay ( I P 2 5 %

    down to a depth of 13 m,

    C, , /P, .

    varies betwe

    0.23 and 0.29; in thc lower plastic marine cl

    C,,/P,. increases slightly with depth to an avera

    of the order of 0.29 at 24 m depth. After co

    struction, the com puted C,,/P,. are generally low

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    13/23

    T A V E N A S ET

    A L . 29

    5

    u undroined shear strenqth kPo

    2

    4

    6

    8 100

    FIG.12. Variat ions of the vane shear s t reng th under the

    cen ter l ine and the berm of the embankment a t Rang clu

    Fleuve.

    TABLE.

    Variations of the C,,/P,. ratio

    C, , /PVf

    Location

    C,,/Pc

    2 3

    R m g Saint-Georges

    I +4 .2 m 0.35 0.26 0.26

    El . -3 .0m

    0.26 0.23 0.22

    R m g i FIt~ioe

    1 . +3 .5

    m

    0.34

    0.25

    Berm El. +3.7111

    0.33

    0.24

    NOTES: 1. Obscrved 400 days after

    s tart

    of construction. 2 Ob-

    served

    113 days

    after s tart

    of construction. 3.

    Observed 830

    d y

    af t e r start

    of

    construction.

    than the initial

    C,,/P,.

    and they vary very little with

    depth, between 0.21 and 0.26 around an average

    of 0.24.

    From thcse observations, it may be concluded

    that the consolidation of the clay to vertical effec-

    tive stresses in excess of the preconsolidation pres-

    sure produces both an increase in the vane shear

    strength and a decrease in the C,,/P,. ratio. From

    Fig. 13, it appears that the reduction of C J P ,

    is strong in plastic clays with a high initial

    C , , /P , , but is limited in the low plastic clays; the

    final C J P , stems to vary little with the plasticity

    of the clay. Furthermore, from the observations

    at Rang St-Georges, the reduction of

    C , , / P ,

    ap-

    pears to occur rapidly during the initial stages of

    construction and probably as soon as P, exceeds

    P , ,

    the ratio C,,/P, remaining constant during

    i'urther consolidation.

    An exact interpretation of the strength measured

    by it

    s tu

    vane tests is difficult because the effec-

    tivc stress conditions at failure are not known.

    However, published evidence, for example by

    Bjerrum (1972), and the common observation of

    a strain softening bchaviour during the test sug-

    gest that the vane strength is representative of the

    intact clay structure. The corresponding effective

    stress condition should thus be located on the

    initial limit state surface, at a point that remains

    to be defined. Th e shape of the limit state surface

    being imposed by the geological history, thc C,,/P,.

    ratio representative of this shape is also imposed

    by the history of the clay deposit as noted by

    Bjer rum (1972) .

    It has been demonstrated by

    F.

    Brucy (1977)

    that the limit state surface is strongly deform ed when

    the clay becomes normally consolidated; as shown

    in Fig. lb, this deformation results in a reduction

    of the strength and thus of the C , , /P , ratio. The

    pore pressure observations have confirmed that

    the clay in the foundations of the emb ankme nts

    become normally consolidated during the early

    stages of construction. The observed variations

    in

    C,,/P, (Fig. 13) could thus be explained by the

    above-described phenomenon

    i

    the limit state sur-

    face of the intact clay presents a shape similar to

    that of Fig. la.

    The limit state surface of the intact clay has

    been determined on undisturbed samplcs, obtained

    at

    4.5

    m depth at Rang du Fleuve by means of a

    20 cm diameter overcoring thin wall sampler

    developcd at Lava1 University. The method used

    is the same as that describcd by Tavenas and

    Lcroueil 19 77 ) it consists of ( 1 ) a series of con-

    solidated, undrained triaxial tests with pore pres-

    sure measurements (CIU) to obtain the 'strength

    portion' of the limit state surf ace as we l as the

    peak strength envelope of the nornlally consol-

    idated clay and the 'large strain' strength envelope,

    (2 ) a series of v , / ~ T : , = C t triaxial consolidation

    tests, as well as (3) oedometer tests to obtain

    the 'volumetric portion' of the limit state surface

    below the Mohr-Coulomb envelope. Figure 1 4

    presents the results of these tests. They are typical

    of natural clays in eastern Canada, the shape of

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    14/23

    296

    C A N . G E O T E C H .

    J.

    VOL. IS,

    1978

    FIG 13. Variation of the CJP,. at io under the embankments .

    040

    \ ?

      before constructton

    0

    36

    f t e r

    c o n s t r u c t m i

    p;

    0 32

    >

    P

    028

    ,p

    0

    24

    c

    0

    20

    P a V e

    z 4 5 X - a P a V e

    ~ 2 5

    IPaVe

    =

    50

    0

    I6

    FIG 14

    Effective stress path and limit state surf ace fro m triaxial tests at Rang

    d u

    Fleuve.

    I

     

    the limit statc surface being identical to that shown

    in Fig. la. Since this surface is well above the

    Mohr-Coulom b envelope at large strains, the ef-

    fects of consolidation shown o n Fig. l b will also

    apply to the limit state surface of this clay. Con-

    sequently the observed variations in C,,and C,,/P,

    can be related to the modification of the shape

    of the limit state surface of the clay when it bc-

    comes normally consolidated.

    It might be interesting to note h ere that a similar

    bellaviour has been observed under embankments

    built on

    a

    variety

    of clays. Analysing the test

    embankments on

    a

    normally consolidated plastic

    clay at Sk:k Edeby in Sweden, Holtz and B roms

    1972) report a systematic reduction in the ratio

    of

    C, , /P , :

    the initial values of C,,/P,, the Sk5

    0

    2

    4 6

    8 10

    1A- r

    ep t h , m2 14 16

    18

      20 22 24

    Edeby clay is rcportedly no r~n ally consolidate

    varied from 0.22 to 0.28 around an average

    0.2 6; after 14 years of consolidation u nder t

    embankment loads, the observed vane she

    strength

    C

    and effective vertical stresses

    P,

    sulted in C,,/P, varying from 0.21 to 0.25 arou

    an average of 0.22. However, as was the case

    the A.40 embankments, this reduction in

    C,,/

    was associated with an increase in

    C .

    Under t

    Saint-Alban test section B Tav enas

    t

    a l . 197

    a

    slight increase in C was also observed 2.5 yea

    after construction in the upper

    3

    m of the found

    tion, but the C /P initially equal to 0.26 w

    reduced to

    C,, /P,

    of 0.21. On the other hand,

    a

    site near Ottawa, Can ada, Eden and Pooroosha

    1968n,b) haw noted no var ia t ion in the va

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    15/23

    T A V E N A S

    T

    A L . 297

    shear strength 3.5 ycars af ter the construction of

    an em bank men t: a t that si te the or[ginal values of

    CJP,

    in a clay of medium to low plasticity were

    probably of the order of 0.28 (based on the scat-

    tered

    P,.

    measurements values of

    C,,/P,

    f r om 0 .23

    to 0 .33 ma y be c om pute d) ; ba se d on t he da t a

    presented in the paper , thc

    C,,/P,

    af ter 3.5 ycars

    vary betwcen 0.16 and 0.20. A similar reduction

    in

    C,,/P,

    without significant vane strength increase

    has been obta ined under a 12 year o ld embank ment

    on the Eas te rn Township Highway southeas t of

    Montreal: in the clay with a plasticity index of

    4096, the ini t ia l

    C,,/P,.

    of 0.32 were reduced to

    C,,/P,

    of 0.24 but the vanc shear strcngth was

    essentially unchanged.

    Thus i t may be concluded that the consolidation

    of a clay foundation under an cmbankment wil l

    result in most cases in a modif icat ion of th e shap e

    of the limit state surface of the clay and in a cor-

    responding decrease of the

    C,,/P,

    rat io f rom init ial

    values of

    C,,/P,.

    of the ord er of 0.25-0.40 an d

    variable with the plasticity, the geological history

    and other featurcs of the intact clay structure, to

    values of the

    C,,/P,

    rat io varying much less with

    the clay propert ics and general ly of the order of

    0.1 8-0.25. This decrease occurs in the ear ly phases

    of the consolidation process, probably as soon as

    I- ,

    exceeds

    P,.

    Together with these reductions in

    C,,/P1,

    he vane shear strengths havc becn o bserved

    to be larger or in some cascs equal to the ini t ia l

    strengths measured in the intact clay; however, it is

    possible that a reduction in

    C,,

    develops momen-

    tar i ly when the

    C,,/P1

    atio is reduced in the ear ly

    phases of consolidation.

    Evaluation of the E mbankm ent Stability

    During onstruction

    As already noted, the ini t ia l dcsign was based

    on total strcss analyses, taking into accou nt the

    increases of th e undrained shear strength produced

    by the consolidation of the foundation clay. How-

    ever , by the end of 197 5 it appeared necessary to

    accelerate the construction process, and i t was

    decided to check the stabil i ty of the cmbankment

    by m eans of effective strcss analysis. T o this end

    thc effective strength parameters of the clays were

    determined in the laboratory and a complementary

    instrumentat ion was instal led at Rang du Fleuve

    (Fig . 3b) a nd Rang de la Concession (F ig . 4a) .

    As a result , a t any given stage of construction the

    stabil i ty of the embankrncnts could be determined

    by means of

    a

    total stress method based on the

    vane shear s t r ength measured under the embank-

    ment and of an effect ive stress method using the

    actual pore pressures.

    Total Stress nalyses

    Th c tota l stress analyses of stability hav e been

    carr icd out by means of a computer program using

    the modif ied Bishop meth od, an d accepting ver tical

    undrained shear strcngth profiles of different shape

    and magni tude depending on the i r loca t ion under

    the embankments. In al l cases the strength of the

    fill, represente d by a friction angle of 3 5 , w as

    assumed to be ful ly mobil ized.

    Th e var iat ions of th e factors of safcty with the

    height of fill during th e first constru ction s tage have

    a l ready been discussed. They were based on the

    vane sh ear strength of th e intact clay and corrected

    to account for Bjerrum's vane strength correction.

    Durin g construction the new factors of safety were

    est imated on the basis of thc new shear strength

    measurements made under the f i l ls;

    as discussed

    later thc vane strength correction proposed by

    Bjer rum (1972) was cons idered not appl icable

    in these cases.

    At Rang St -Georges , vane s t rength measure-

    ments were made in Jun c 19 73 when the f il l he ight

    was 6.1 m and in September 1975 when the f i l l

    height was 7.4 m. The factor of safety could thus

    be estimated for the diffcrent heights of fill using

    the strength prevail ing before and af ter the con-

    struction. Th e different factors of safety arc sh own

    as a function of the cmb ankm ent height in Fig. 15.

    The increase in the factor of safety caused by

    the gain in vane shear strength is very important

    be twcen the in i t ia l condit ion and Ju ne 197 3 but

    i t is much less be tween Jun e 197 3 and September

    1975 . This may b c explained not b y a var iable

    magnitude of the gains in the vane shear strength,

    but rather by the location of these gains in the

    foundation. Ind eed, a t the beginning of construc-

    t ion, addi t iona l loads a re imposed on the ent i r e

    arca of the embankment and i ts berms. After con-

    solidation und er these loads, increases in

    P,

    a nd

    C,,

    thus deve lop throughout the cnt i r e founda t ion; the

    available shear strength is increased along near ly

    the ful l extent of the potential fai lure surface. On

    ' the contrary, in subsequent construction stages only

    the main embankment i s bui l t up, so tha t the in-

    creases in vertical effective stress and thus in un-

    drained shear strength arc l imited to thc central

    area of the foundation, i .e . to a small port ion of th e

    potential fai lure surface (see Fig. 1 6 ) . Conse-

    quently, to take ful l advantage of the stage con-

    struction process i t would be desirable to also

    increase the height of the berms af ter thc f irst

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    16/23

    298 C A N . G E O T E C H .

    J.

    VOL.

    15.

    978

    o

    + O

    a na l y r r , u xn~1~al;correcleaaccording 10 Bjerrum(19721

    +

    = onalyr8r.

    Cu

    umol unrorrecfed

    I

    +

    =

    ono l y l l ,

    u A C u

    meorurea

    @

    in

    une

    973

    September 1975

    FIG 15 Compu ted factors of safety ang St-Georges

    fill.

    period of consolidation so as to produce increased

    strengths along the maximum possible length of

    potential failure surface. As can be seen, the over-

    all increase of the factor of safety prod uced by the

    gain in van e shear strength over a period of 3

    years is of th e ord er of 0 .6 at a fill height of 7.5 m ,

    i.e. very significant.

    As of December 197 6, the factors of safety cor-

    responding to the prevailing geometries and vane

    shear strengths are of th e order of 1.25 at Rang

    St-Georges and Rang du Flewe, 1 4 at Rang de la

    Concession and 1.55 at Rang du BrGlC. The small

    factors at Rang du Fleuve and Rang St-Georges,

    less tha n the originally selected minimu m of 1.3 ,

    are considered acceptable in view of the observed

    settlement and pore pressure behaviour as well as

    of the results of the effective stress analysis.

    Efe ct iv e S tress Analyses

    Peak strengths corresponding to a Mohr-Cou-

    lomb envelope defined by c = and

    +

    = 28

    have been given by CIU tests on the normally

    consolidated clay (Fig. 1 4 ). At large strains the

    strengths measured in C IU tests on b oth normally

    consolidated and overconsolidated samples cor-

    respond to the same residual strength envelope,

    which may be defined here by c = 4 kPa a nd

    I

    + = O A N A L Y S I S

    I N I T I A L

    Cu

    FIG 16 Potent ial fai lure surfaces from +

    =

    a n d

    + analyses ang St-Georges fill.

    + = 28 . To obtain a conservative estimate of th

    factors of safety, the stability analyses were ma

    using

    c

    = and +

    =

    28 .

    Stability analyses in effective stresses require th

    knowledge of th e pore pressures in the foun dation

    As already noted, two types of instrumentation f

    pore pressure observations were available. Fro

    the observation in the well instrumented found

    tion at Rang d u Fleuve and Ran g d e la Concessio

    typical pore pressure distribution patterns we

    defined (Fig. l o ) , which were then used to extr

    polate the limited number of observations und

    the other embankments. In this way complete po

    pressure distributions could be defined under a

    embankments at all stages of construction, base

    on the corresponding observations.

    The results of the stability analysis in effecti

    stresses at various stages of con struction of th

    four embankments are shown on Figs. 15 and 1

    At R ang St-Georges (F ig. 1 5) the factors of safe

    corresponding to the June 1973, September 19

    and November 197 6 situations vary between 1

    and 2.1 and are much higher than those obtaine

    from the total stress analysis. The con dition is qui

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    17/23

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    18/23

    C A N . GE OT E C H. J .

    V O L.

    15 978

    l l

    FIG.17b

    Computed factors of safety ang de la Concession.

    those obtained from the 0 analysis in spite of

    the rapid construction sequence, the better drainage

    conditions at Rang de la Concession resulting in

    higher differences.

    iscussion

    The concepts of limit and critical state, which

    have just been applied successfully to tlic analysis

    of the variations of the pore pressures and the vane

    shear strength under the A .40 embankments, might

    servc as a basis for the development of a rational

    approach to the design of stage-constructed ern-

    bankm ents. T o this end it is first necessary to

    establish a clcar picture of thc variations in effective

    stresses and strength in the clay foundations.

    Effective Stresses and Strength Variations under

    a Stage constr~tctedEm bankm en t

    Consider the case of an embankment built in

    threc stages on a slightly overconsolidated clay.

    Figure

    18

    shows the corresponding total and effec-

    tive stress paths as well as the relevant strength

    characteristics of the clay.

    During the first construction phase, the tota1

    stress path is such as OA. As shown by Leroueil

    i

    a / . 1978 ,

    and as confirmed here, a significant

    consolidation develops at the beginning of con-

    struction, so that the effective stresses increase

    rapidly along O P and the clay becomes normally

    consolidated at PI. During a further increase in

    total stresses up to point A, pore pressures are

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    19/23

    T A V E N A S

    T

    AL

    + =

    o n o l y r ~ r ,

    ,

    lnlllol cnrecte d occordmg to Bp rrum 197 2 1

    o n o l y r ~ r , u nlllol uncorrrcted

    onolyris , C, bC u meorurea in Nowember 1976

    C

    + Onolyur , 3 )numbor d doyr otter lorl loodfng

    FIG.

    17c Computed factors

    of

    safety ang du BrGlC.

    generated so a s to maintain t he effective stress path

    on the limit state surface along P A ; this norm ally

    occurs at constant effective vertical stress g,. PCt

    with a pore pressure coeficicnt

    r 1 O

    This type

    of bchaviour was observed under all embankments

    of the Berthierville-Yam achiche section of High-

    way

    A.40.

    As shown by F. Brucy 19 77 ), the initial limit

    state surface is deformed when the clay becomes

    normally consolidated at P , and the new limit state

    surface is such as P1F,, Ro (see also Fig. l b ) . Th e

    strength of the intact clay, as obtained from UU or

    CIU tests in the laboratory or from vane tests

    in

    situ

    is thus reduced to values corresponding to the

    large strain Mohr-Coulomb effective strength en-

    velope. In this process, C,,will rcmain less than th

    initial strength as long as the effect of consolidation

    on th e effectivc stresses is small, an d C,,/P,. wil

    be permanently reduced to a value representative

    of the new shape of the limit state surface of th

    normally consolidated clay.

    If the first phase of construction werc contin ued

    beyond the height corresponding to the stress con

    ditions at points A a nd A , failure would be initi

    atcd at Fo on the Mohr-Coulomb envelope of th

    normally consolidated clay. Further load applica

    tion associated with the strain-softening behaviou

    of the clay would result in an effective stress path

    FolR o following the new limit state surface of the

    normally consolidated clay down to point

    Rot

    cor

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    20/23

    302 C A N . G E O T E C H .

    J .

    VOL.

    15

    1978

    FIG.18. Tota l and e f fec t ive s t ress pa ths under an embankment bu i l t up in s tages .

    responding to the residual strength and probably

    the critical state of the clay;

    C :

    would be the

    strength mobilized at complete failure. The magni-

    tude of this strength at failure has been analysed

    by Mesri (1 97 5) . Associating the correlations pro-

    posed by Bjerrum (1972) between the plasticity

    index and the ratios C,,/P,,' and P,./P,,' as well as

    the empirical vane strength correction fa ctor, Mesri

    has shown tha t the strength pC,, C,,, :,,, available

    at failure under an embankment was nearly in-

    dependent of the plasticity index and of such effects

    as aging and could be related to P,. by pC,,/P,. equa l

    to 0.18-0.23. These values are rema rkably similar

    to the ratio C,,/P,' of 0.18-0.25 measured by vane

    tests under embankments. It might thus be hypo-

    thesized that the strength correction factor

    p

    pro-

    posed by Bjerrum (1972) accounts essentially for

    the modification of the limit state surface when the

    clay becomes normally consolidated.

    The actual construction sequence corresponds

    to the interruption of construction at A, A' for a

    period of consolidation, which results in an effec-

    tive stress variation A'B'. During the next loading

    stage BC, th e effective stresses will stay on th e new

    limit state surfacc produced by consolidation under

    the effective stress condition at B' and they will

    follow B'C'. T he second consolidation period w ill

    produce a stress path C'D' and a corresponding

    new limit state surface D'Fs'Rsl as well as a new

    critical s tate at Rsl. If the embankment were then

    to be built up to failure from the s ituation D, D' ,

    the stress paths followed up to the initiation of

    failure would be such as DF, in total stresses and

    D'F,' in effective stresses, with a corr espo ndin g

    pore pressure factor r 1.0. Failure would

    be initiated at F2'; the development of strain

    softening under imposed total vertical stresses

    would necessarily result in an increase of the mean

    total s tresses along F 2R 2 and in

    a

    very marked

    increase in pore pressures, with I. much in cxcess

    of 1.0, to prod uce an effective stress path such as

    F2'R2'. T he principles of limit and critical state

    imply that the limit state surfaces A'Fo'Ro'and

    DIF,'R,' are homothetic and entirely defined by

    the respective values of the vertical effective stress

    and the effective strength param eters of the clay in

    the normally consolidated and residual states. As a

    consequence the C,,/P,.' ratio will remain constant

    and equal to the reduced ratio representative of the

    unstructured, normally consolidated clay during all

    stages subsequent to the first consolidation period.

    Simultaneously the vane shear strength will in-

    crease continuously from its momentarily reduced

    value, obtained when the clay becomes normally

    consolidated. Therefore, depending on the magni-

    tude of the consolidation allowed before vane tests

    are carried out under an embankment, it will be

    possible to measure vane strengths smaller, equal

    to o r greater than th e initial values of C ,,. Both the

    abo ve dcscribed variatio ns of C,, an d C,,/P,' are

    consistent with the field observations. It should be

    noted though that the strength really available at

    failure, and thus significant in design, will con-

    tinuously increase with ongoing consolidation from

    its initial value C,,(,:,,,.

    Evnluatiorz of

    the

    M eth od s of Stability naly sis

    The results of the stability analysis in total and

    in effective stresses may be evaluated by consider-

    ing the stress paths followed up to failure in the

    foundation clay (Fig. 18).

    At any given point in the foundations, failure

    is initiated when the effective stress condition satis-

    fies the Mohr-Coulomb criterion of the normally

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    21/23

    T A V E N A S ET A L

    consolidated clay. Subsequent strain sof tening de-

    velops unti l the residual shear strength

    C O:

    is

    reached, the strength reduction from F to R being

    associated with a strong increase in the pore pres-

    sures. Two factors of safety may thu s be def ined at

    any stage of con struction pr ior to complete fai lure:

    1. The effective stress analysis using the large

    strains effect ive strength parameters, or the con-

    servative c 0 , + values for the sake of safety,

    and the actual pore pressures prevail ing in the

    foundation wil l produce a tru e image of the stabil-

    ity condition.

    2. Th e minimum strength available in the foun-

    dation being

    C :

    stabil i ty analysis based on

    this resistance will yield the minimum possible

    value of the factor of safety. This residual strength,

    probably corresponding to the cr i t ical state of the

    clay, is the extremity of an effective stress path.

    However , i t appears to b e a unique function of the

    effective stress acting on the clay prior to the be-

    ginning of the construction up to failure, i.e. of P,.

    in a single stage construction or of

    P,

    in multiple

    stage construction. This effect ive strength thus has

    all the usual at tr ibutes of an undrained shear

    s t rength and m ay be used as such in a + 0 anal-

    ysis. This residual strength may be est imated from

    vane test results in the intact clay corrected ac-

    cording to Bje r rum 19 72 ) f rom uncor rec ted vane

    test results in the normally conso lidated clay unde r

    the embankment dur ing const ruc t ion, f rom the

    correlat ion to P,. o r P, proposed by Mesr i 19 75 )

    o r f r o m CIU tests on the overconsolidated clay

    carr ied out to large strains.

    The strength available in the foundation being

    higher than the residual strength at any t ime but

    at complete fai lure, the factor of safety computed

    from th e effective stress analysis will be necessarily

    higher than tha t obta ined f rom the

    +

    0 type

    analysis using the residual shear strength; this is

    consistent with the results reported above. HOW

    ever, at complete failure the two analyses will yield

    the same value of F S 1.0 if the local pore pres-

    sures are correctly measured. Figure 19 shows in

    principle the variations of the two factors of safety:

    before local failure is reached at any point in the

    foundation, t he two factors of safcty decrease at a

    similar rate with the increasing height of fill, the

    difference between the two factors being a function

    of the differences between the reference strengths

    at points F and R ; using the m ore representat ive

    cffective stress analysis will lead to a significant

    increase of the permissible height of fill as shown

    on Fig . 19. When some points of the founda t ion

    reach local fai lure at F, increased pore pressures

    FIG. 19. ariations o f the factors o f safety with the

    height of fill.

    are generated and the available strength decreases

    along F R ; as a result , the factor of safety will dc-

    crease rapidly towards 1.0 at com plete fai lure when

    the entire foundation is in the residual state . I t

    would be obviously dangerous to build u p embank-

    ments to such height that the factor of safety would

    be in the F R zone Fig . 19 ) s ince the ac tua l mar -

    gin of safety in term s of height of fill would be very

    limited. T he l imited exp erience presently available

    indicates that the discontinuity in the variation of

    the factor of safety occurs at a value less than 1.3

    An addit ional control is provided by the observa-

    t ion of the pore pressure parameter I. o r B either

    of which assumes values muc h in excess of 1.0

    when local failure and strain sof tening develop.

    onclusions

    Th e observations of construction pore pressures,

    vane shear strength var iat ions and stabil i ty con-

    dit ions in the clay foundations of four embank-

    ments buil t in stages, a long with the use of the

    YLIGHT

    model of clay behaviour proposed by

    Tavenas and Leroue i l

    (1977),

    have led to some

    important conclusions.

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    22/23

    304

    C A N .

    CEOTECH. J . VOL. I S 1978

    1 Owing to an initial consolidation the clay be-

    comes normally consol idated during the early

    stages of con struct ion of an emban kment .

    2. T h e passage from t he ini tial overconsol idated

    state to the normally consol idated s tate produces

    impo rtant ~nod ificatio ns of th e characteristics of

    the clay. In part icular: ( i ) T he s t ructure of the

    clay resulting from the combined effect of aging,

    thixotropic hardening and eventual cementat ion is

    obl i terated. ( i i ) Th e shape of th e l imit s tate surface

    of the clay, representative of its structure, is modi-

    fied, the s t rength of the clay being reduced. ( i i i )

    The ini t ial rat io of vane shear s t rength to precon-

    solidation pressure, C , , / P , , ssociated with the shap e

    of the limit state surfac e of th e intact clay is redu ced

    to a new Cl , /P , ratio, which seems to vary litt le

    with th e type of clay. Th e vane s t rength correc t ion

    factor

    p

    proposed by Bjer rum (1972) p robably

    represents the magnitude of the deformation of th e

    limit state surface of the clay when it becomes

    normally consolidated.

    3.

    With the development of consol idat ion the

    l imit s tate surface of the clay keeps i ts new shape

    and is homothet ical ly displaced with the increase

    in effective stresses. As a result, the vane strength

    will increase, the ratio Cll/P,. remaining constant

    and e qual to i ts new low value. I t is suggested th at

    Bjerrum s correct ion factor should not be appl ied

    to the s t rength obtained from vane tests carried

    out und er an embankm ent dur ing conso lidat ion .

    4. The s t rength avai lable at fai lure under an

    em b an k m en t m ay b e o b ta i ned f ro m C IU t es ts o n

    the overconsol idated clay carried to large s t rains ,

    from vane tests in the intact clay corrected accord-

    ing to Bjer rum (1 97 2) , f rom vane t est s in the nor-

    mally conso l idated c lay unde r the embankm ent o r

    from the correlat ion with P,. proposed by Mesri

    (1 97 5) . When used in a 0 ty pe a nalysis, i t will

    lead to the minimum possible factor of safety of

    the embankment at any s tage of construct ion.

    5.

    T he only way of obtaining an est imate of th e

    true s tabil i ty condit ion at an y s tage of con struct ion

    is by means of an cffectivc stress an2lysis using the

    actual pore pressures observed in the foundat ion

    and the large s t rain effect ive s t rength parameters

    c ,

    +'.

    However, for increased safety, the param-

    eters

    c

    0 , +', obtained from the peak s t rength

    measured in C IU tes ts o n normal ly conso l idated

    samples may be used . Thi s approach wi l l l ead to

    increased permissible heights of fill during stage

    cons t ruct ion . However , care should be t aken no t

    to ini t iate local fai lure and s t rain softening in the

    foundat ion clay; this may be achieved by keeping

    the fa ctor of safety in effective stresses in excess of

    1.3 or preferab ly 1.4 and by observ ing that th

    pore pressure parameter r or does no t exceed 1 .0

    The use of this approach on the Berthiervi l le-

    Yamachiche sect ion of Highway A.40 has resul te

    in a significant accelcration of the constructio

    schedule of seven important embankments .

    cknowledgements

    Th e present s tudy has been m ade possible by th

    kind cooperat ion of the Minist ry of Transport o

    the Province of Quebec, and of Ham cl Rue

    Consul t ing Engineers for the project .

    Th e au thors a re indebted to the ir co l leagues L

    Samson and B. Trak for the i r comments , and t

    the edi tors and reviewers of th e Cana dian Geotech

    nical Journal for their valuablc suggestions.

    Parts of the work have been supported by th

    research fund of Terratech LimitCe and by Gran

    number A .7724 of the Nat ional Research Counc

    of Canada.

    BJERRUM,. 1972. Embankments on soft ground. Proceeding

    ASCE Conference on Performance of Earth and Earth Su

    ported Structures, Purdue University, Vol. 11, pp. 1-54.

    BRUCY, . 1977. Effets du passage I etat normalement con

    solid6 sur I etat limite d une argile naturelle. M.Sc. thesi

    Department of Civil Engineering, Laval University, Quebe

    P.O.

    ASCAL,0 TOURNIER,.-P., TAVENAS, . and L

    ROCHELLE,. 1972. Failure of a test embankment on sensitiv

    clay. Proceedings, ASCE Conference on Performance o

    Earth and Earth Supported Structures, Purdue University

    Vol. I, Part 1, pp. 129-158.

    EDEN,W. J. , and POOROOSHASB,. B. 1968~1. ettlement o

    servations at Kars Bridge. Canadian Geotechnical Journal,

    pp. 28-45.

    968b. Settlement observations at Kars Bridge: Reply

    Canadian Geotechnical Journa l,

    5

    p. 248.

    HOLTZ,R. D., and BROMS, . B. 1972. Long-term loading tes

    at Ski-Edeby, Sweden. Proceedings, ASCE Conference o

    Performance of Earth and Earth Supported Structures, Pu

    due University, Vol. I, Part I , pp. 435-464.

    LADD, . C. 1975. Measurement of in situ shear strength. Pro

    ceedings, ASCE Conference on in situ measurement of so

    properties, Raleigh, NC, Vol. 11, pp. 153-160.

    LA ROCHELLE,., TRAK, ., TAVENAS,., and ROY,M. 197

    Failure of

    a

    test embankment on a sensi tive Champlain Cla

    deposi t. Canadian Geotechnical Journal , 11, pp. 142- 164.

    LEFEBVRE,., LEFEBVRE,. M., and ROSENBERG,. 197

    Behaviourof a cemented plastic clay as an embankment fou

    dation. Canadian Geotechnical Journal, 11, pp. 46-58.

    LEROUEIL,., TAVENAS,., MIEUSSENS,., i~nd EIGNA

    M. 1978. Construction pore pressures in clay foundation

    under embankments. Part 11: generalized behaviour. Can

    dian Geotechnical Journal , 15, pp. 66-82.

    MESRI,G. 1975. Discussion of new design procedure for stabi

    ity of soft clays. ASCE Journal of the Geotechnical Enginee

    ing Division, 101(GT4), pp. 409-412.

    PAR RY, . H . G. 1972. Stability analysis for low embankmen

    on soft clays. Proceedings, Roscoe Memorial Symposium

    Edited by G. T Foulis. pp. 643-668.

    PILOT,G. 1972. Study offive embankmentsfailureson soft soil

  • 8/20/2019 The Stability of Stage-constructed Embankments on Soft Clays

    23/23

    T A V E N A S

    ET

    A L . 30

    Proceedings, ASCE C onference on Performance of Earth and

    Earth Suppo rted Structures, Purdue Un iversity , Vol. I, Part

    I , pp . 81-100.

    PREST, V. K . 1970. Quaternary geology.

    In

    Geology and

    economic minerals of Cana da.

    dited by

    R. J. W. Douglas.

    Econom ic Geology Rep ort No. 11, Geological Survey of

    Canada.

    ROSCOE, . H. , S C H O F IE L D ,. N. ,a nd WRO TH, . P. 1958. On

    the yieldingof soils. Geo techn ique, 8 1), pp. 22-53.

    S A M S O N ,. , an d G A R N E A U ,. 1973. Settlement performance

    of two embankments on deep compressible soils. Canadian

    Geotechnical Journal, 10 pp. 21 1-226.

    S C H M E R T M A N N ,H. 1975. Measurement of

    in situ

    shea

    strength. Proceedings, ASCE Conference on In Sitlr Mea

    surem ent o fso il Pro perties , Raleigh, NC, Vol. 11, pp. 57-138.

    T A V E N A S ,. C H A P E A U ,. , L A R O C H E L L E ,. , and ROY,M

    1974. Immediate settlements of three test embankm ents o

    Champlain Clay. Canadian Geotechnical Journal,

    11

    pp

    109-141.

    T A V E N A S ,. a n d L E R O U E I L ,. 1977. Effects of stresses and

    time on yieldingof clays. Proceedings, 9th International Con

    ference on Soil Mechanics and Foundation Engineering, To

    kyo, Vol. I, pp. 319-326.