The public views “THE CITY”

36

Transcript of The public views “THE CITY”

Page 1: The public views “THE CITY”
Page 2: The public views “THE CITY”

The public views everyone on a public works project as “THE CITY” performing these operations

Page 3: The public views “THE CITY”

INDOT CERTIFIED TECHNICIAN PROGRAM and other industry certifications demonstrate the individual’s basic understanding of the construction inspection process

• Bridge Construction & Deck Repair• Concrete Paving• Construction Earthworks• Construction Procedures Part 1• Construction Procedures Part 2• Hot Mix Asphalt Paving

Lead consultant must verify that their subs are qualified

APWA Certifications

Page 4: The public views “THE CITY”

Be Prepared for Each Day’s Activities

Have the proper equipment

Arrive at the project site PRIOR to the commencement of any major operation

Page 5: The public views “THE CITY”

Measurement tools• Plans• Scale• Tape Measure• Measuring Wheel• Level

Page 6: The public views “THE CITY”

Replaces Chapter 100 of the INDOT Standard Specifications

Page 7: The public views “THE CITY”

Do not process monthly payment until a valid schedule has been provided by the contractor

Page 8: The public views “THE CITY”

Changes to specifications,standards and construction requirements occur constantly and often times from project to project

Special Conditions –work restrictions, Holidays, Events

Basis of paymen

Page 9: The public views “THE CITY”

Understanding the plans and being able to apply the contract documents and specifications

Know your project site and verify plans match current field conditions

Have information concerning the current field conditions at the Pre-Con

Page 10: The public views “THE CITY”

Know what permits are required to perform the work

Responsibility• ROW - Contractor• Flora Permit – Contractor• Sanitary – Contractor• Structural - Contractor• SWPPP – Designer/Owner

Page 11: The public views “THE CITY”

Look ahead and determine what issuesmay lay ahead

Page 12: The public views “THE CITY”

Discuss testing requirements at Pre-Con

Verify that the contractor is performing and passing all materialtesting as required by the DPW Frequency Manual

RPR is responsible for scheduling Quality Assurance Testing with DPW’s testing consultant

Page 13: The public views “THE CITY”

• Verify that things are done correctly and that the required procedures are followed

Crosswalks• Line up directly across

street unless designed otherwise

• When using Transverse Markings, 24 Inch Crosswalk Line, “Piano Keys” Oriented parallel with

approaching vehicle wheel path

Page 14: The public views “THE CITY”

• Traffic Control Devices• Check construction signage often• Proper layout of construction joints• Proper location and placement of ramps • Orientation of detectable domes and grooved

surfaces• Stop Bars

Page 15: The public views “THE CITY”

Keep up on them dailyWrite a story/narrativeDescribe the Contractors means and

methodsNotate any visitors on jobsite Include drawings and pictures

Page 16: The public views “THE CITY”

Keep daily and progressive records up to date and accurate

Maintain accurate drawings,measurements and calculations

Page 17: The public views “THE CITY”

RPR should know well in advance of any projected overruns and underruns

RPR shall inform the DPW Project Manager prior to the situation becoming an issue

Page 18: The public views “THE CITY”

Pre & Post Construction Photos• Same locations

During Construction

Page 19: The public views “THE CITY”
Page 20: The public views “THE CITY”
Page 21: The public views “THE CITY”
Page 22: The public views “THE CITY”
Page 23: The public views “THE CITY”

RFIRFPField OrderWork Directive ChangeChange Order

Page 24: The public views “THE CITY”

• From Prime Contractor on their letterhead• Keep a RFI log• Each RFI must have a unique number• RPR is first person to answer• Request Interpretation from Design Engineer

Page 25: The public views “THE CITY”

Form in the contract documents

Page 26: The public views “THE CITY”

Form in the contract documents

Page 27: The public views “THE CITY”

-

• Form in the contract documents

• -Include Attachment A• -Include backup

documentation from Contractor

Page 28: The public views “THE CITY”

• -Form in the contract documents

• -Attachment A

• -Referenced Documents

• -Contract Summary Sheet

Page 29: The public views “THE CITY”

All lead and sub consultants should have quality control procedures in place

Proof read paperworkDouble check calculationsVerify dates

Page 30: The public views “THE CITY”
Page 31: The public views “THE CITY”
Page 32: The public views “THE CITY”
Page 33: The public views “THE CITY”
Page 34: The public views “THE CITY”

Update capitol outputs as part of the final construction record• Sidewalks in LFT• Paving in Lane Miles• Number of ADA Ramps• Number of Inlets

Page 35: The public views “THE CITY”

• Tells a story of the entire project• Protection and documentation in case of audit• Protects City from issues arising from

contractor workmanship and/or tort claims• Everything should be electronic • Hardcopies and folders should match

electronic records• Organized and easy to navigate

Page 36: The public views “THE CITY”

Questions?