The performance of spatial planning within a complex area development
description
Transcript of The performance of spatial planning within a complex area development
The performance of spatial planning within a complex area development
Learning to anticipate the spatial strategy formation in the face of conflicting interests at ‘SPOORZONE DELFT’
Alan Kazzaz Dept. Of Urbanism12 – 4 – 2011P5 presentation
Presentation structure
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 02
The legitimacy and performance of the Dutch spatial planning practice
Empirical testing
Theoretical focus
Conclusions and recommendations on planning practice
Case introduction
Case introductionSpoorzone Delft
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 03
(Adapted from De Jong Luchtfotografie, 2010)
Case introductionA dualistic project
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 04
(Author’s illustration)
Spoorzone DelftProject area
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 05
(Author’s illustration)
Spoorzone DelftTowards implementation
2008: implementation phase
“everything has been agreed upon,From now its only a matter of fine-tuning while executing”
(Bijleveld, 2010)
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 06
(Bestemmingsplan Spoorzone Delft, 2006)
However, today:
Dissatisfied stakeholders
Disagreement on expected results
Unfeasible plan
Delays and a new planning challenge
Spoorzone DelftPlanning challenge
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 07
Spoorzone DelftCrisis the cause of conflicts ?
A lack of adaptive capacity to respond to meaningful developments
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 08
Theoretical focus
2.Goal of planning
Role of planning
Context of planning
Suitable planning in the context of area development
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 09
Goal of planningTowards legitimate public action
“Knowledge & action”(Friedmann, 1987)
“Planning is a techno-ethical challenge…” (Forester, 1989)
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 10
(Author’s illustration)
‘material outcome’Planned effects and externalities
Social world:dynamic biased
viewpoints
‘Mobilized bias’Through practicesof power exertion
Context of planningDutch traditional planning culture
“The Dutch planning profession pays very limited attention to the societal and political context in which planning is to take place”
(Kreukels, 1997)
“Comprehensive integrated approach”(Hajer and Zonneveld, 2000)
Technocratic planning traditionA positivistic planning approach
Planning
Steering
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 11
(Author’s illustration)
Context of planningTop down planning exercise
public
peopleprivate
State controlled planningLegitimized by the representative
Capacity of a sovereign state
Inefficient operability
Undesirable developments
Unrealistic ambitions
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 12
(Author’s illustration)
Context of planningOntological dynamics
Statesovereignty
Cross-sectoralinterdependency
(semi) Public
Private market
Collective Individual
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 13
(Adapted from Jonge, 2007)
Role of planning Integrating planning to deciding
Interactive collaborative steering: Governance
Planning
Planning practice could focus attention, influence bias and mobilize directive action
Faludi, 1979; Forester, 1989; Fischer, 1993; Healey, 1997; Oxley, 2004
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 14
(Author’s illustration)
“The performance of planning”(Faludi, 2000)
Planning paradigmArea development
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 15
National
Provincial
Municipal
Private sector Civil society
Pose conditions
Co-produceplans
“The government should formulate objectives; not solutions”Wolting, 2006
(Author’s illustration)
3.Nature of the project
Inconsistencies in planning operability
Planning mechanism Initiation Mobilization Public collaboration Cross-sectoral collaboration
Empirical testingSpoorzone Delft
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 16
Nature of the projectThe railway viaduct in Delft
Local nuisance
Urban spatial fragmentation
Obstructive curve in railline
the viaduct was conceived as necessary evil
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 17
Railway viaduct was constructed in 1965
(Author’s illustration; photo source: Engel, 2007)
InitiationRail-21
1987: A proposed railline duplication by the NS
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 18
(Author’s illustration)
MobilizationA wider perspective
1993: Urban development perspective
list of requirements:1600 homes50.000 m2 office space
“The greater the ambition, the higher the amount of required actors will have to be”klijn, 2004
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 19
(Adapted from www.palmbout.nl)
Public CollaborationA dualistic comprehensive focus
Ministry of V&W
‘BereikbaarheidsoffensiefRandstad’
Ministry of VROM
‘Nota Ruimte 5’
DelftDelft
DelftBallast Nedam
DelftRegion Haaglanden
DelftProvince Z-H
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 20
(Author’s illustration)
Public collaborationMasterplan
Functions
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 21
(Author’s illustration, adapted from Delft, 2003)
Public collaborationMasterplan
Functions
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 22
(Author’s illustration, adapted from Delft, 2003)
Public collaborationMasterplan
Building heights
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 23
(Author’s illustration, adapted from Delft, 2003)
Public collaborationMasterplan
Non-negotiable alignment
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 24
(Author’s illustration, adapted from Delft, 2003)
Public collaborationMasterplan
Implementation plan
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 25
(Author’s illustration, adapted from Delft, 2003)
Public collaborationMasterplan
Public actor Contribution (x million)
Ministry of V&W € 272
Ministry of VROM € 75
Municipality of Delft € 45
Province South Holland € 30
Region ‘Haaglanden’ € 11
Betterments from area developments € 80
Total € 513
‘Spoorzone Delft’ was to be
executed conform the
regulation as set within
the masterplan
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 26
(Delft, 1999)
Cross-sectoral collaborationInstitutional arrangement
Urban development Railway tunnel
Ministry V&W
ProRail
Municipality
OBS
Ballast nedamNS Poort
OCSDCivil Society
Crommelijn
Conditioning Conditioning
Contracting
Negotiating
Approving
Integrating
- ? -
Does this governance landscape allow for a legitimate and effective course of decision-making ?
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 27
(Author’s illustration)
Cross-sectoral collaboration dualistic friction
Urban development Railway tunnel
Ministry V&W
ProRail
Municipality
OBS
Ballast nedamNS Poort
OCSDCivil Society
Crommelijn
Conditioning Conditioning
Contracting
Negotiating
Approving
Integrating
- ? -
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 28
(Author’s illustration)
80 million value capturing
Cross-sectoral collaborationIntrinsic steering
OBS
OCSD
Municipality
Masterplan
Land-use plan
Civil society
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 29
(Author’s illustration)
Cross-sectoral collaborationCentralized steering
OBS
OCSD
Municipality
Masterplan
Land-use plan
Civil society
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 30
(Author’s illustration)
Cross-sectoral collaborationLand-use plan
Variable ParameterHomes Market housing 214.000 M 2 g.f.a. 1315 homes
Social housing 15.000 M 2 g.f.a. 210 homes
Offices City council 29.000 m 2 g.f.a.
Private 25.000 M 2 g.f.a.Parking (semi)
Underground2834 places
Surface 600
Building Volume
Height 3 to 5 floors/block (accents up to 9 floors)
Gross Floor Area 283.000 m2
Facades Front façade preconditionedBack façade variable
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 31
Cross-sectoral collaborationBeeldkwaliteitsplan
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 32
(Delft, 2009)
Cross-sectoral collaborationConflicts
Urban development Railway tunnel
Ministry V&W
ProRail
Municipality
OBS
Ballast nedamNS Poort
OCSDCivil Society
Crommelijn
Conditioning Conditioning
Contracting
Negotiating
Approving
Integrating
- ? -
too narrow solution spaces for further optimization and anticipation;
Conflict
Symbolical reassuring participatory activities;
Result:An unfeasible plan
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 33
“The planning operability has a lack of adaptive capacity to respond to meaningful developments which marks contemporary urban life”
(Slagmolen, 2010)
Cross-sectoral collaborationRegaining steering competence
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 34
Ministry V&W
ProRail
Municipality
OBS
Ballast nedamNS Poort
OCSDCivil Society
Crommelijn
(Author’s illustration)
Cross-sectoral collaborationA positivistic planning discourse
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 35
A B
‘a predictable future’
(Adapted from Govaart, 2011)
Cross-sectoral collaborationA post-positivistic planning discourse
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 36
A B
‘the acknowledgement of uncertainty’A responsive alternative
(Adapted from Govaart, 2011)
Cross-sectoral collaborationTowards a wider institutional embedding
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 37
Municipality
OBS
Ballast nedamNS Poort
OCSDCivil Society
(Author’s illustration)
4.Conclusions and recommendations
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 38
Conclusions
Recommendations
Planning context Planning tools Planner’s conduct
ConclusionTowards an integrated outcome
(Author’s illustration)
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 39
ConclusionDiscursive conflict on decision-making
National
Provincial
Municipal
Private sector Civil society
National
Provincial
Civil societyPrivate sector
Municipal
Area development idealIntrinsic steering
Reality of practiceControl and hierarchy
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 42
(Author’s illustration)
ConclusionThe performance of planning
Planning phase Power division Plan PerformanceMobilization Centralized municipality NS: rail-21
Palmboom’ s visionBusquet’s vision
Well
Public collaboration Inter-level public sector, Municipality and V&W most centralized
Busquet’s masterplan Moderate
Cross-sectoral collaboration Cross-sectoral dispersed, land-use plan Weak
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 40
The public and private sector operate under very distinctive principles. A mixed type will not be stable
(Simon, 1990)
ConclusionDiscursive conflict on planning
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 41
(Author’s illustration)
Recommendation 1Shaping the planning context
Urban development Railway tunnel
Ministry V&W
ProRail
Municipality
OBS
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 43
Integrality has its limits
(Author’s illustration)
Recommendation 1Shaping the planning context
Municipal
PrivateCivil Society
Consumer orientation
Legitimacy Efficiency
time
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 44
(Author’s illustration)
Recommendation 2Planning tools for urban management
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 45
Planning tools:
‘Seduction-by design’ planning approaches fail to perform in complex decision-making arrangements;
There is a need for learning-oriented planning tools which are to make variables and parameters within urban space explicit in order to facilitate relational clarity on the current situation and to provide a referential frame for negotiation if the current situation is desired to be changed.
Recommendation 3The argumentative turn in planning
1. Introduction 3. Testing2. Theory 4. Conclusions and recommendations 46
Planner’s conduct:
The argumentative turn in planning (Forester, 1989, Fischer, 1993)
Planning in the context of complexity requires contextual-sensitive communicative skills to confront the diversity of (sectoral-bound) value patterns towards a shared commitment and a collective focus for action.
“Planning with all your senses” (Stein, 2005)
Thank you
(Author’s illustration)