The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

16
The PDP and Decision-Making Ohio Department of Transportation O f N E P A The PDP FHWA

Transcript of The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

Page 1: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

The PDP and Decision-Making

Ohi

o D

epar

tmen

t of T

rans

port

ation

Of

NEP

AThe PDP

FHWA

Page 2: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.
Page 3: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

PDP Phased Approach

Project Development Process

• Streamlined to meet the objectives of ODOT’s core program

• Allows for more flexibility between phases• Pulls Stage 1 and Stage 2 Engineering into PE and

Environmental• Redefines how alternatives are developed• Proactive merger of Design and NEPA

Page 4: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

PDP Paths

Project Development Process

Page 5: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

PDP Milestones

Project Development Process

Typical Deliverables

Page 6: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

Project Development Process

Page 7: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

Flexibility is Key!

Page 8: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

ODOT’s PDP is designed to allow the PM to develop the design and decision detail to the level necessary for a good decision.•Project Initiation•Feasibility Study•Alternative Evaluation Report•PE Design-Stage 1-2•NEPA Document

Page 9: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

PDP- Solid Decision Faster/Cheaper• New scoping process (Project Initiation Package)

ensures that only necessary work gets scoped and that the projects are properly planned out.

• During the Preliminary Engineering (PE) Phase of the PDP, the “Feasibility Study” focuses on the narrowing of Alternatives and hopefully, get’s to a preferred.

• The Alternative Evaluation Report addresses environmental and design issues, then recommends a Preferred Alternative.

• Once a Preferred Alternative is chosen, Stage 1/Stage 2 can begin and additional environmental studies/permits can occur concurrently.

Page 10: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

What was our Goal in producing these decision products?

1.Concise! (Feasibility study can be 1 page to 100 pages.)2.Readable. (If it wasn’t an impact, say it and move on. If we did a study, summarize and attach- not repeat. Use graphics, tables and charts!)3.We wanted it to contain everything! (Thank you DVD’s!)

Page 11: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

Decision-making within the PDP is Unique.

Page 12: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

ODOT’s PDP and Decision-making• Each Project can have different detail

needed to make the decision…– Environmental– Preliminary Engineering

• Each PDP report (feasibility Study, AER, etc.) can have different level of detail to make the decision…

• Still have core issues that need to be addressed to meet legal requirements…

Page 13: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

• Tell the Story

• Keep it Brief

• Keep it Legal

PDP Documentation- How much is too much?

Page 14: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

PDP- Solid Decision Faster/Cheaper• PDP redefined how alternatives are developed

and to what level of detail – early review of alts.

• Proactive merger of design and NEPA. Focused on balance of when NEPA/design studies are needed. (Stage I/II redesigned)

• Common sense decision-making.• New emphasis on Critical Path Management and

scheduling of milestones.• Requirement for new department-wide project

manager training.

Page 15: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

PDP Decisions

• Be Flexible• Risk

Management

• Make good decisions…

Page 16: The PDP and Decision-Making Ohio Department of Transportation Of NEPA The PDP FHWA.

Questions and Discussion