The Olympics, Risk and Governance * Will Jennings, ESRC Research Fellow, University of Manchester,
Acknowledgements: thanks to the UK Economic and Social Research Council for support
through the ESRC Research Fellowship (ESRC Reference RES-063-27-0205), ‘Going for Gold:
The Olympics, Risk and Risk Management’.
Abstract
This paper explores the increasing influence of risk in governance of the Olympic
Games. It identifies three critical aspects of the relationship between risk and the Olympics:
first as a prism of organisational experience of the risk society, second in the contradiction
between the disproportionate risks associated with mega-events such as the Olympics and
wider controlling, blame-avoiding and risk-averse rationalities prevalent in contemporary
politics, government and organisational life, and third in the increased influence of risk as a
mobilizing concept in planning and organisation of the Games and in the governance of the
Olympic movement. This relates wider debates about risk and modernity (e.g. Beck 1992;
Giddens 1999), mega-projects and mega-events (e.g. Roche 1994; Flyvbjerg et al. 2003) and
the rise of risk management in the public and private spheres (e.g. Hood et al. 2001; Power
2004; 2007) to the Olympic experience of risk and changes over time in organising strategies
used to manage and mitigate risks. It considers in particular the implications for the London
2012 Olympic and Paralympic Games as a venue for interaction of risk, society, politics and
organisation.
“Great Games minimise risk.” (London 2012 Candidate File, p.11)
The Olympics is both a mirror to and an engine of broader social, political and economic
forces. It is neither a unique and insulated venue for organisational practice, cut off from the
external world, nor is it powerless in the face of broader changes in society, economics and
government. The task of governing the Games and the Olympic movement now occurs in an
age in which states and societies are increasingly organized in response to risks, and where
uncertainties, threats, hazards and vulnerabilities are said to be a product of modernization
itself (Beck 1992). This is a world in which concern with the creation of economic wealth has
been overtaken by the production of risk along with a reciprocal quest for safety and
security (Giddens 1991). The managerial expansion of the capacities of states and societies
for measurement, analysis and management of risk is manifested in growth of the regulatory
state (e.g. Majone 1994; Moran 2003) as well as the proliferation of audit and risk
management practices in both the public and private sectors (Hood et al. 1999; Power 1997;
2004; 2007). As a global media mega-event the Olympics is susceptible to heightened
anticipation of risks and threats and activation of special legal or institutional frameworks for
governing and securing the Games (e.g. Richards et al. 2010). It is, therefore, a context in
which broader dynamics of risk and risk management are of special relevance (e.g. Jennings
2008; 2010; Jennings and Lodge 2010; 2011).
The influence of risk and of risk management in Olympic organisation is a defining
feature of the modern Games. This paper argues that the relationship between Olympic
organisation and risk should be understood with regard to three essential dynamics. These
affect the production of risk in Olympic organisation and events, specific decision-making
biases and processes that are observed in planning for this mega-event and the increasing
commitment of organizers to the practice of risk assessment and risk management. First, the
social and technological production of risk in Olympic organisation has – since revival of the
Olympic Games in 1896 – reflected broader social processes of modernisation identified by
Giddens (1991; 1999), Beck (1992) and others (e.g. Scott 1998). At the same time the global
profile and salience of the Games has led this particular mega-event – through defining and
memorable events such as the 1972 Munich Massacre – to wider cognisance of hazards and
threats encountered in modernity, as well as contributing to the production of risk through
its geo-political salience and global brand and through the Olympic movement’s globalizing,
modernizing and commercial tendencies.
Second, the disproportionate level of risk that is associated with organisation of the
Olympic Games – as a mega-event, constituted in operation of a large scale event operation
that typically involves a complex web of multiple mega-projects concerning infrastructure
and facilities – are in contradiction to the aspirations of modern societies, governments and
businesses to measure, control, regulate and minimize risk (Moran 2001, p. 425). Third, and
last, contemporary trends in organisation of the Olympic Games reflect broader shifts in
governance observed in both the public and private sectors (across corporate governance
and public administration), with increasing attention to risk and its management.
This paper reflects briefly on these dynamics in light of the case of the London 2012
Olympic and Paralympic Games as the most recent Olympic venue for interaction between
risk, society, and organisation. It relates wider debates about risk and society (e.g. Douglas
and Wildavsky 1982; Beck 1992; Douglas 1994; Giddens 1999), mega-projects and mega-
events (e.g. Roche 1994; Flyvbjerg et al. 2003) and the rise of risk management in the public
and private sectors (e.g. Hood et al. 1999; Ericson et al. 2003; O’Malley 2004; Power 2004;
2007) to the Olympic experience of risk and changes over time in the organising strategies
used to manage and mitigate risks.
The paper is organised as follows. It first introduces the literatures on risk, society and
culture and explains how governance of the modern Olympics has reflected, as well as
contributed to, production of social, economic and organisational risk. It next explores the
contradiction between the optimism bias (in systematic under-estimation of risk) observed
in planning mega-events such as the Olympics and the wider risk averse and blame-avoiding
tendencies of policy-makers and bureaucrats. Last, it reflects upon the changing nature of
organisational responses to risk in the public and private spheres and presents evidence of
the increased influence of risk as a mobilizing concept in organisation of the Games and in
governance of the Olympic movement.
1. Risk and the Olympics
It is argued in some quarters that the world has entered a new era of extreme events
and risks (e.g. Beck 1992; OECD 2003; Lagadec and Michel-Kerjan 2005; Lagadec 2007).
Proponents of the risk society thesis cite examples such as the AIDS epidemic, the Chernobyl
disaster and the September 11th, 2001 terror attacks as evidence that social, economic and
political cleavages increasingly cut across new boundaries, tearing up existing power
relations and institutional structures. Ulrich Beck (1992, p. 21) argues that risk is modern
society’s response to “hazards and insecurities induced and introduced by modernization
itself.” While natural threats and hazards remain (e.g. famine, flood, drought, earthquakes),
increasingly risks are the consequence of scientific, technological and economic progress
itself – manufactured or amplified through modern forms of social, political and economic
organisation. According to proponents of this dystopian age of uncertainty, risk has diverged
from traditional class and power structures and now trespasses across the boundaries of the
nation state – contributing to the rise of governance to replace government. The globalised
interdependence and scale of modern social and economic life – with its complex interaction
of organisations, science, technologies and individuals – is argued to be a cause of many of
its own instabilities and vulnerabilities. The social production of risk is most clear in system-
level failures that result from unanticipated interaction of errors, failures or oversights (e.g.
Perrow 1984; Vaughan 1997). Further, the idea of risk is interlinked with the anticipation of
catastrophe and disaster itself (Beck 2006), further reinforcing the preoccupation of modern
societies with risk.1 Indeed, whether or not one subscribes to such claims of the newness
and the pervasiveness of the risks encountered in late modernity, in this age of uncertainty
societies, economies and governments are all increasingly organized in response to risk. For
Giddens (1999, p. 3), “… the idea of risk is bound up with the aspiration to control and
particularly with the idea of controlling the future”.
The Olympics are an interesting, and important, site for exploring such questions of risk
and modernity. On the one hand, modernization of the Olympics has itself manufactured
risk through the growing scale, reputation, commercialization and globalization of the event
and through the ever more complex task both of governing the Olympic movement and
organizing the Games – echoing these macro trends. On the other, the Olympics have more
uniquely contributed to wider consciousness of some hazards and threats encountered in
modernity through actual incidents as well as through its influence over the imagination of
governments, media and the public on this mega-event in particular – further accentuating
preoccupation of the risks encountered in modernity. These two aspects of the relationship
between the Olympics and risk are now addressed in turn.
First, processes of modernisation have been critical to social and economic production
of Olympic risk. The growth in the size of the Olympic Games has been dramatic from the
humble origins of the inaugural Games of 1896 – which consisted of 241 athletes competing
in just 43 events across nine sports. In its current form, the Games itself has been described
by Dave Higgins, Chief Executive of London’s Olympic Delivery Authority as “...the world’s
largest peacetime event,”2 with the logistical operation equated to the simultaneous staging
of thirty-three world championships in one city. The London 2012 Olympic and Paralympic
1 Risk is also implicit to social and organisational processes of disaster and crisis sensemaking (e.g. Weick 1988;
1993; Gephart 1993). 2 David Higgins, Transcript of Oral Evidence, 5 March 2007, p.28, HC377, Committee of Public Accounts. (2007).
Preparations for the London 2012 Olympic and Paralympic Games – Risk assessment and management. London: The Stationery Office Limited.
Games, will provide a sporting mega-event on a vast scale – consisting of 26 sports hosted at
31 competition venues over 17 days of competition, bringing together 204 participating
states, around 10,500 athletes, 6,000 officials and coaches and 20,000 media, with around
500,000 visitors to the main Olympic site each day. It is to be policed by an estimated 15,000
police officers3 and 6,500 private security contractors.4 The increasing ambition of the design
and engineering of Olympic cities and urban agendas (Gold and Gold 2007) has meant that
the task of constructing facilities and infrastructure for the Games have required increasing
levels of investment as well as intensive project management and coordination. As the total
number of competition venues, accommodation and training facilities, media centres and
other urban developments has escalated, so too the planning process and operation of the
Games have each become more complex and interdependent – increasing the risk of failures
impeding project management or disrupting Games-time operations.
Because many of the organizational hazards faced by the Olympics are interconnected, it
is vulnerable to systemic exposure to incidents. The interaction of minor errors or failures at
a particular point in the infrastructure network, for example, with other facilities or services
such competition venues or transport routes, can result in severe disruptions. For example,
unpredictable variations in power demand during mega-events such as the Olympics can
increase the risk of blackouts. Ahead of the Sydney 2000 Olympic Games, Kingsford Smith
Airport suffered a power failure that created a backlog of flights – highlighting a potential
risk to the Games. Such a minor disruption to spectator or competitor travel nevertheless
has the potential to impede the entire schedule of Olympic events, as well as transport and
security plans, forcing organizers to abandon years of planning.5
3 Mayor of London (2004). London Assembly Questions on London bid for 2012 Olympic Games and Paralympic
Games – 13.10.04. Answers to non-oral questions, prepared by London 2012, GLA, LDA, TfL 18.10.04, Q. 357/2004. 4 London 2012 bid (2004). Candidate File, Volume 3, p. 39.
5 The concentration of the majority of events, athlete’s accommodation and press facilities on the main site, for
most Olympic Games in recent times, means that there is potential for a single incident to have systemic effects across both the site, infrastructure network and the programme of events.
At the same time, the financial stakes involved in staging the Olympics have increased
considerably over time. The cost to the host city of staging the Games has increased steadily
over time (see Preuss 2000; 2006). While smaller in comparison to the estimated $50 billion
cost of the Beijing 2008 Olympics, the public contribution to the London 2012 Olympics was
budgeted at £9.3 billion while the operating budget of the London Organising Committee for
the Olympic Games (LOCOG) amounts to around £2 billion. With host cities and the Olympic
movement each subject to growing operational costs, the magnitude of economic risk has
increased both for the IOC (which raises revenue through the sale of broadcast rights and
sponsorship partnerships) and for host cities (which depend upon revenues from ticket
sales, domestic sponsorship, and a share of IOC revenues). This now means the Olympics is
exposed to fluctuations in both national and global economies. Lend Lease, developer of the
Olympic Village for London 2012, experienced difficulties in raising private equity and debt
funding for the project because of the economic downturn that followed the global financial
crisis, requiring a government-led rescue package. Around the same period LOCOG was also
forced to cancel a sponsorship contract with Canadian telecoms provider Nortel, which had
filed for bankruptcy protection.
Olympic production of risk is not just organisational or economic in nature, however.
Growth of the Olympics as a global event has also resulted in higher volumes of passenger
flows across borders. The international travel of athletes, support staff, officials, media and
spectators is a potential source of public health risks due both to local factors, such as the
concern over the effects of pollution on visitors ahead of the Beijing 2008 Olympics, and the
increased likelihood cross-border transmission of infectious diseases. This has escalated the
attention of host cities to public health preparedness (Meehan et al. 1998; Jorm et al. 2003;
Davis et al. 2008). At the same time, technologies shape both the technical infrastructure
and the public face of Olympic organisation – for example, computers were first introduced
to record results at the Tokyo 1964 Olympics, while the first Games website created for the
Atlanta 1996 Olympics. However, modernisation of the technologies used to organise and
operate the Games has itself generated new risks that are transnational in their origin and
potential impact. Ahead of the Sydney 2000 Olympics, action plans were devised in response
to concerns over exposure of Olympic preparations to the Y2K problem (SOCOG 2001, p.
272). Fears ahead of the Beijing 2008 and London 2012 Olympics focused on the potential
threat of cyber attacks on the technological infrastructure of Olympic organizers and public
websites.6 Such technological risks are systemic to Olympic organisation and consistent with
the global interdependence of Olympic governance.
In terms of the Olympic production of risk, then, some risks at least are interlinked with
processes of modernisation – consistent with the claims of Beck (1992) and Giddens (1991) –
in organisational, economic and technological forms. As a global event the Olympic Games is
subject to the interconnectedness of risks associated with, for example, finance, security and
public health, while the Olympic movement itself has become a complex system of sports
governance that is transnational in both jurisdiction and influence. Risk and modernity are,
therefore, integral to the Olympic Games of today.
Second, at the same time as reflecting these broader processes of modernization, the
Olympics have provided a unique venue for the experience and the anticipation of risk. The
high level of global attention and real-time media reporting, during the opening and closing
ceremonies in particular, means that the Games have become a major target for symbolic
attacks or protests. Around 4.7 billion viewers watched the television coverage of the Beijing
2008 Olympic Games.7 The Olympics has long been an arena for geo-political agendas and
tensions, and a platform for occurrence of other high impact incidents – whether national or
international in origin. The IOC has long been aware of diplomatic and geo-political risks,
relocating its headquarters in Lausanne, Switzerland, during the First World War due to its
neutral status and enduring Cold War boycotts of the Moscow 1980 and Los Angeles 1984
6 E.g. Maija Palmer. (2009) 'Blunkett warns of cyber attack on Olympics', Financial Times, April 28, 2009.
7 AGB Nielsen Media Research (www.nielsen.com).
Olympics. The protests over China’s human rights record during the international torch relay
for the Beijing 2008 Olympics are more a recent example of such political tensions. Although
the global profile and reputation of the Olympics create opportunities for threats it has also
contributed to wider preoccupation with risk in modernity.
The trend of international terrorism that had emerged during the 1960s reached a new
and unprecedented watershed as the dramatic events of the Munich massacre at the 1972
Olympics unfolded live on televisions across the world. During the second week of Olympic
competitions, eleven Israeli athletes and coaches taken hostage by a group of Palestinian
terrorists, Black September, and later murdered during a botched rescue operation by the
German authorities. As the stage for this defining event in modern terrorism, the Olympics
performed a critical role in shaping global consciousness of the risk and symbolic power of
terrorism for such events. The Olympics are now a recognized and established target for
security threats and for the coordination of military and policing responses (see Richards et
al. 2010) and the biannual staging of the Summer and the Winter Games provides a regular
venue for attention to the threat of terrorism. The power of imagination of risk in planning
for both the Atlanta 1996 Olympics and Sydney 2000 Olympics was prescient of the later Al-
Qaeda attack on the World Trade Centre towers on September 11, 2001. National Security
Advisor Richard Clarke and the White House counter-terrorism team had prepared a plan for
a hijacked plane being flown into the Olympic stadium (Clarke 2004, pp. 107-109). Similarly,
the organizers for Sydney 2000 prepared strategies for the scenario that was most feared by
IOC President, Juan Antonio Samaranch: of a commercial plane being flown into the opening
ceremony.8 Indeed, Olympic concerns about aircraft being flown into the main stadium date
at least to planning for the Munich 1972 Olympics (see Wolff 2002).
In terms of reputational risk, the Olympic brand itself creates high cost for failures that
makes it distinct from other events or projects. Quite benign incidents or accidents can, as a
8 ‘Winning smiles turn to terror tears’, The Melbourne Age, July 8, 2005.
http://www.theage.com.au/news/world/winning-smiles-turn-to-terror-tears/2005/07/07/1120704502059.html
consequence, be amplified under the glare of the media spotlight. For example, journalists
labelled the Atlanta 1996 Olympics the “glitch Games”9 after it suffered a catalogue of minor
operational and logistical problems. In preparations for the London 2012 bid, a feasibility
study warned that “… the Atlanta experience showed the media can play an important role
in defining the perception of the success or otherwise of the Games” (Luckes 1997, p. 66) –
stressing the importance of the provision of high quality facilities for broadcast and media
centres. The Olympics therefore remains something of a special case when considering
questions of reputational risk and the perception of organisational or operational success.
2. The Paradox of Risk and Mega-Events
Why host the Games at all? The bias towards systematic under-estimation of risk in a
mega-event such as the Olympics – consisting of large scale event operations dependent
upon the coordination of multiple mega-projects concerning infrastructure and facilities – is
at odds with the risk averse, controlling, rationalist tendencies of the modern state (e.g.
Scott 1998; Moran 2003).10 Further, incidence of cost overruns or project mismanagement
risks the wrath of public opinion or support from local coalitions critical to mega-projects
(Altshuler and Luberoff 2003, pp. 219-247; Jennings n.d.). This paradox has been attributed
to the influence of ‘icon politics’ (Moran 2001) or a ‘monument complex’ (Flyvbjerg 2002, p.
288) among decision-makers.
In general, mega-events and mega-projects are problematic for contemporary policy-
makers, planners and project managers. There is widespread evidence of systematic bias of
such projects towards the under-estimation of risk, typically manifested in cost over-runs,
delays and project failures (see Flyvbjerg et al. 2002; 2003; Altshuler and Luberoff 2003;
Flyvbjerg and Lowi 2004; Priemus et al. 2008). It has been argued, as a consequence, that
9 Kevin Sack. (25 July 1996). 'Atlanta: Day 6; Atlanta Bristles at All the Criticism', The New York Times. Section B,
p.19. 10
Mega-events can be defined, in general, as “short-term events with long-term consequences for the cities that stage them … associated with the creation of infrastructure and event facilities often carrying long-term debts and always requiring long-term use programming” (Roche 1994: p. 1).
mega-projects and mega-events do not exist in a “Newtonian world of cause and effect”
(Flyvbjerg et al. 2003, p. 6). This tendency to over-optimism in grand projects is a recurring
feature of bureaucratic planning (e.g. Hall 1981; Bovens and t’ Hart 1996; Scott 1998; Hood
1998, p. 149). As perhaps the definitive mega-event of modern times, the Olympic Games
provide an illuminating case for demonstrating how the problem of optimism bias is in direct
contradiction to aspirations towards the control and management of risk – both in adoption
and governance of Olympic bids and planning. Indeed, the Olympic Games are susceptible to
a number of decision-making biases and organisational effects that can accentuate hazards
or threats and condition the responses of organizers (see Jennings 2010; Jennings and Lodge
2011). These contribute to the difficulties encountered in calculating and managing Olympic
risk.
The Olympics is associated with organisational and operational processes that induce
optimism bias concerning both risks and benefits. Optimism bias refers to the systematic
over-estimation of positive outcomes and, therefore, under-estimation of risk. The right to
stage the Games is awarded through a competitive candidature process – with applicant
cities first evaluated by the IOC and then selected through a secret ballot of its membership.
Because of this, bids are often concerned with winning the votes of IOC delegates first and
asking questions later. Indeed, the formal bid documents submitted to the IOC have been
described by Dick Pound, former Vice-President of the IOC, as the “most beautiful fiction”
(see Luckes 1997, p. 1). The under-attention of bids to inadequacies (Luckes 1997, p. 14) is
therefore a source of risk. There is often limited funding available to bid teams for technical
evaluation or for detailed costing of proposals, not least because of the risk that investment
in the IOC candidature process will deliver no financial returns at all. This tends to encourage
reliance upon standardized templates and generic bids, rather than planning on the basis of
first principles. In preparation of the London bid, reference to previous bid documents (see
Luckes 1998) and the formulation of a ‘specimen bid’ (Arup 2002) are characteristic of such
concern with perception of the bid rather than substantive planning. As a consequence of
optimism bias in formal bid documents, the process often leads to divergence between the
initial proposals of bid teams and the subsequent phases of infrastructure construction and
event operations.
While mistaken assumptions about costs and private investment are common to mega-
projects (Flyvbjerg et al. 2003), organisation of the Olympic Games is likewise susceptible to
problems with private financing, both in terms of investment and revenues (Jennings 2010).
The final cost of the Games often is in excess of initial expectations. Indeed, Olympic budgets
have long been in the business of under-estimating expenditure (e.g. Official Olympic Report
London 1908, p. 388). The most renowned case was the $1 billion debt left for the Montreal
city government after the Montreal 1976 Olympics, but the under-estimation of financial risk
is the norm in Olympic budgeting. In more recent times, public funding of the Sydney 2000
Olympics was six times greater than the initial bid (New South Wales Audit Office 1999), the
total cost of the Athens 2004 Olympics increased from £3.2 billion to £6.3 billion (Houses of
Commons Library 2005, p. 37) and the forecast public expense of the London 2012 Olympics
has, to date, escalated from £2.4 billion to £9.35 billion (Jowell 2007, Col. 450-452).11 These
under-estimations of financial risk occurred despite the technical evaluation of costs and use
of expenditure controls (see Auditor-General of British Columbia 2003; National Audit Office
2007).
Another unknown in the candidature phase is the voting behaviour of IOC delegates and
the tallying of votes through the IOC’s run-off system. While the Olympic movement is most
concerned with avoiding the selection of host cities that could threaten their reputation and
revenues, the voting behaviour of the IOC membership itself is sometimes unpredictable,
organised around geopolitical blocs and inattentive to project risks, on occasion disregarding
the preferred choices of the IOC leadership (Pound 2004, pp. 200-201). The surprise win of
11
The original budget prepared for the London ‘specimen bid’ (see Arup 2002, p. 4) put the cost even lower at £1.8 billion.
the Sydney bid in 1993 ahead of Beijing, favoured by the then IOC President Juan Antonio
Samaranch, is one such example of this. The selection of host cities for the Winter Olympics
is more prone to “offbeat” results and voting patterns (Pound 2004, p. 201), with many IOC
delegates less interested in the Winter Games and fewer cities seeking to host it than their
summer counterpart.
There are, furthermore, a great number of uncertainties when developing provisional
bid proposals for staging an event such as the Olympics that is to occur a considerable time
in the future. The extended duration of the bid, planning, organisation and decommissioning
of the Games, often lasting for between fifteen and twenty years, creates a high degree of
uncertainty for organizers in making forecast assumptions about critical project details such
as infrastructure costs, expected revenues and security threats. Errors in bid forecasting can
occur either through incremental divergence from initial conditions (such as slow inflation in
costs) or through sudden shocks that require complete adjustment of planning assumptions
(such as terrorist incidents or economic crises). Since the original proposals for a London bid
(Luckes 1997; 1998; BOA 2000), a number of fundamental transformations have occurred in
the risk environment of the Games – with the escalation of some risks and others in relative
decline. The threat of terrorism to the London 2012 Olympics changed with the events both
of September 11, 2001 and July 7, 2005 highlighting the threat from Al-Qaeda and extremist
Islamic groups, while the threat of Irish republicanism on the British mainland (Luckes 1997,
p. 15) has declined since the 1998 Good Friday Agreement due to success of the Northern
Ireland peace process. Most prominently, while plans for the Games were developed during
a period of economic growth the events of the global financial crisis, and resulting economic
downturn, have impacted upon both public finances and investment from the private sector,
as well as having potential implications for revenue from ticket sales and sponsorship.
Alongside the disproportionate risks that are associated with bids for the Games and the
extended timeline of planning, the Olympics are subject to high costs of organisational and
operational failure that further contribute to risk aversion on the part of decision-makers.
The rigid schedule of ceremonial and sporting events – with the immovable deadline of the
Olympic opening ceremony – heightens the concern of organizers both about project non-
completion and operational or security disruptions. In Olympic planning, postponement is
not an option (although London’s host city contract with the IOC includes a provision for a
postponement of up to three months under certain conditions, in practice the reputational
damage to the UK, London and the Olympics would be quite catastrophic). Concerns over
the readiness of Olympic facilities ahead of the Athens 2004 Olympics highlighted the high
levels of risk associated with project completion. In some cases, Olympic planning is subject
to risk aversion that is more general in origin. For the Salt Lake City 2002 Winter Olympics,
the US Federal Government intervened in security planning after the events of September
11, 2001 – with the Office of Homeland Security designating the Games a National Special
Security Event (the designation of National Special Security Event had, in fact, been created
after the Atlanta 1996 Olympics, Clarke 2004, p. 111). This reflected the heightened state of
concern over terrorism within the Bush Administration and the influence of Vice President
Cheney’s ‘one per cent doctrine’ (Suskind 2006) – which considered a one per cent chance of
an attack to be equivalent to a certainty with respect to formulation of security responses.
Indeed, there is evidence that staging of the Olympic Games is associated with processes of
securitization (e.g. Karyotis 2007, p. 286; Yu et al. 2009).
3. Risk Management and Governing the Games
Studies across a range of disciplines – including history, law, accounting, political science
and sociology – have highlighted the rise of formal controls, regulation and risk management
as a mode of governing modern states, societies, economies and organizations (e.g. Breyer
1993; Majone 1994; 1997; Power 1997; 2004; 2007; Scott 1998; Hood et al 1999; 2001;
Moran 2003; Sunstein 2003; Lodge 2008; Hutter 2010). The concept of risk itself has become
ubiquitous (Bernstein 1996; Leiss and Chociolko 1994).12 Furthermore, risk is increasingly an
organizing concept (e.g. Hood et al. 1992; 2001; Hood and Jones 1996; Ericson et al. 2003;
O’Malley 2004; Power 2007), in fields as diverse as counter-terrorism, nuclear energy, public
health, financial markets and food safety. The replication of organisational responses to risk
across domains has been further reinforced through development of the professional fields
of risk analysis (Hacking 2003) and risk management (Power 2003).
Since the 1980s, risk has been influential both in governance of the Olympic movement
and in organisation and operation of the Games – across functions ranging from finance to
security to critical infrastructures to public health (Jennings 2008; 2010; Jennings and Lodge
2009). This is observed in increased oversight of Olympic bids and host preparations as well
as in the spread of formal oversight, audit and risk management practices in organising the
Games. In terms of oversight, the IOC Candidature Procedure and Questionnaire (IOC 2004a)
requires bids to host the Games to present their plans in a standardised template, evaluated
through assessments of the IOC Evaluation Commission. The IOC candidature process for the
2012 Games was an explicit exercise in risk assessment, with the IOC Evaluation Commission
describing its mission as “… a technical and fact-finding one: to verify the information stated
in the candidature file, to determine whether proposed plans are feasible and to make a
qualitative assessment of risk” (IOC 2004: p. 5). After the candidature phase, monitoring of
host city preparations is conducted on a regular basis by the IOC Coordination Commission –
with its inspection visits providing opportunities to identify risks in project management and
operations. For London organizers, these inspections have generated positive reports of
progress with preparations for the 2012 Games (e.g. Gibson 2009). Oversight processes are
therefore an essential instrument for the IOC to exert some control over organisational and
operational risk.
12
Our modern understanding of risk was established first through the birth of probabilistic thinking during the eighteenth and nineteenth century as mathematicians sought to understand the nature of chance (see Hacking 1975) – often through the lens of gambling – and second in developments in the logic of scientific enquiry around that same period that promoted measurement and quantification (Porter 1995).
In comparison to such public exhibitions of oversight, the spread of risk management
practices throughout Olympic governance has been unobtrusive but is perhaps even more
significant. Risk management was first introduced as a formal mode of organising for the
Calgary 1988 Winter Olympics (Chang and Singh 1990), while the Atlanta 1996 Olympics is
considered ‘the first Games built with a risk management infrastructure,’ 13 having grown out
of the pioneering of risk management by the US Olympic Committee during the 1980s. The
implementation of the industry standard ‘Enterprise Risk Management’ at the Vancouver
2010 Winter Olympics was another first with the comprehensive management of risk by an
Organizing Committee (VANOC).14
Risk-based thinking has been even more extensive and integrated in preparations for the
London 2012 Olympics (Jennings 2009). Formal controls through audit and risk management
have been implemented across the whole of the Olympic programme – covering its policy,
infrastructure, security, finance, operations and legacy functions (see National Audit Office
2007). For example, the audit and the management of programme risks is conducted by the
Olympic Board and Government Olympic Executive, using general information from reports
on threats and hazards to the UK (such as the Cabinet Office’s National Risk Register) as well
as Olympic-specific information compiled from risk registers and risk logs of bodies such as
the Olympic Delivery Authority (ODA) and the Olympic Security Directorate (OSD) within the
Metropolitan Police. At the same time, audit and management of project and operational
risk is also conducted at the level of the individual organisation – through implementation of
bespoke strategies for management of risk, such as the ODA’s ‘three lines of defence’ policy
of line management, programme assurance and risk and audit functions (ODA 2008, p. 67)
and the evaluation of risk and value-for-money in the OSD’s assurance of security projects
for internal funding.15 Likewise, LOCOG conducts ongoing risk assurance that it identifies and
13
Interview with David Mair, Risk Manager for the US Olympic Committee and for the Atlanta 1996 Olympics. 14
Interview with David Mair and Ron Holton, Vice President for Risk Management and Assurance, VANOC. 15
Interview with OSD official.
manages its own business risks (LOCOG 2009, p. 37). In frontline operations, such as public
health and counter-terrorism, risk management instead often occurs through surveillance
and early warning systems – rather than though management of the risks that are internal to
organisation itself.
With risk now becoming paradigmatic in Olympic governance, London 2012’s ‘whole-of-
Games’ approach incorporates programme, project and operational risks as well as creating
a shared language, a ‘boundary object’ (Power 2004, p. 34), that enables communication or
coordination between organisations with discrete functions and professionals from different
communities of practice (such as interaction between agencies concerned with programme-
level risk, operational risk and business risks). However, the risk management instruments
imported from the private sector since the 1980s have become ever more complex and, on
some occasions, have themselves contributed to the production of risk. For example, risk-
transfer agreements negotiated by the Vancouver Organizing Committee (VANOC) for the
Vancouver2010 Winter Olympics transferred the financial burden to venue developers, but
required ongoing project and contract monitoring since the risk transfer created the risk of
non-completion (see Auditor-General of British Columbia 2006, p. 26). In other instances,
such tools have failed to prevent the under-estimation of risk and reinforced optimism bias
in the planning stages due to faith in expert judgments and methodologies. The probabilistic
cost assessment conducted on the budget of the London bid (see PricewaterhouseCoopers
2003) calculated an 80% chance of the cost of the Games falling between £3.4 billion and
£4.2 billion, well below the present estimate of £9.3 billion. This quantification of budgeting
uncertainties did not, therefore, bring a solution to control of financial risk for the London
2012 Olympics, but instead is an example of the sometimes misplaced trust in numbers and
methodologies of risk management that can lead, paradoxically, to the under-estimation of
risk (e.g. Scott 1998; Moran 2001).
4. Conclusion
The task of governing the Olympics now occurs in an age in which states and societies
are increasingly organized in response to risks, and where uncertainties, threats, hazards
and vulnerabilities are said to be a product of modernization itself (e.g. Beck 1992; Giddens
1999). Across a range of theories and disciplines, it is observed that one of the unanticipated
consequences of attempts at control – enabled through scientific, technological, economic
and social progress – is the creation of risk itself (e.g. Beck 1992; Scott 1998; Giddens 1999;
Moran 2003; Power 2004). This age of progress also brings its own unique set of threats and
hazards.
Questions of risk are central to understanding the organisation of the Olympic Games
and governance of the Olympic movement – with regard to the production of risk itself, its
hyper-problematic nature in the context of mega-events, and the growing influence and the
pervasiveness of practice of risk management in Olympic organisation. In this, the analyses
presented in this paper have shown how trends in governance of the Olympics often reflect
broader processes of economic, social and governmental modernisation – in particular in its
own production of organisational-operational hazards or threats and in increasing attention
to risk and its management. As such, the growing scale, reputation, commercialization and
globalization of the Olympic Games have manufactured risks both for its organisation and
operation. As the Games have grown in size and global profile, and the stakes involved have
become ever higher, the potential impact of hazards or threats has multiplied. Much like the
concern of Beck (1992) with scientific and technological production of ecological peril, the
case of the Olympics demonstrates how progress can itself be an unplanned cause of its own
hazards and threats. For the London 2012 Olympic and Paralympic Games, this highlights the
risks that are interlinked with hosting of such a large and complex enterprise.
Risk is known to be hyper-problematic in the context of mega-events and mega-projects
(e.g. Flyvbjerg et al. 2003; Altshuler and Luberoff 2003; Priemus et al. 2008). As the world’s
largest peacetime event, with its operations dependent upon coordination of a network of
mega-projects concerning infrastructure and facilities, the Olympics are susceptible to
decision-making biases and organisational effects that can accentuate the likelihood of
hazards or threats encountered in organisation of the Games. In particular, problems of
optimism bias (Flyvbjerg and Lowi 2004) distort budgeting during the candidature phase as
well as in later project management, while the extended timeline of Olympic planning tends
to create opportunities for slippage and shocks that disrupt preparations. These tendencies
to over-optimism and the under-estimation of risk shape some of the subsequent problems
encountered in calculating and managing Olympic risk.
Last, recent trends in organisation of the Olympics reflect wider shifts in contemporary
governance observed in both the public and private spheres – in particular increased formal
practice of audit, regulation and risk management (e.g. Breyer 1993; Majone 1994; Power
1997; 2004; 2007; Hood et al 1999; Ericson et al. 2003; Moran 2003; O’Malley 2004; Lodge
2008; Hutter 2010). As such, the heightened attention to risk and its formal management in
Olympic organisation is consistent with broader changes in government and business. With
the organisation-wide Enterprise Risk Management first introduced at the Vancouver 2010
Winter Olympics, the London 2012 Olympics represent a new phase in the nexus between
risk and the Games. Risk-based thinking has been ubiquitous in preparations for 2012 so far.
Risk management for London 2012 is holistic, with audit and risk management governing the
whole-of-programme – ranging from policy, infrastructure, security, finance, operations and
legacy functions – both at a strategic level and at the level of individual organisations.
Despite comprehensive introduction of risk management to Olympic governance, these
systems and technologies cannot provide any guarantee that the Games will pass without
serious incident – just as security plans prepared for international terrorism for the Atlanta
1996 Olympics failed to prevent an attack by a lone domestic bomber (Clarke 2004, p. 109).
Such possibilities remain uncertain as the probability of numerous threats and hazards are
difficult to quantify and are matters for qualitative forecasting rather than constituting a
hard quantitative science of risk management. For the London 2012 Olympics, then, even
the integrated and comprehensive implementation of measures designed to minimize,
inhibit and manage risk cannot guarantee the Games will be free of adverse incident in 2012.
More widely, the inexorable growth of the modern Games and Olympic movement
offers a fine example of adaption and evolution of a system of governance in response to
risk – having survived political, financial, security, operational and reputational crises over
the course of its history (see Payne 2006: pp. 5-12). Such problems have taken the form of
political boycotts, cost overruns, terrorist incidents, logistical failures, corruption scandals,
refereeing controversies, doping, and ambush marketing. This also demonstrates how the
production of risk is a potential side-effect of success and the organisational growth of such
a mega-event. While the jurisdictions and responsibilities of the main Olympic organising
authorities – the IOC, host government and organizing committee (OCOG) – have changed
little since the inaugural Games were held in Athens in 1896, a fundamental transformation
has occurred in how the Games are governed with institutionalisation of risk as a mobilizing
concept – both in more nebulous forms of regulation and in the formal management of risk.
These changes in the risks confronting each Games and the preoccupation of Olympic
organizers with their formal management have had deep-rooted effects on how the Games
is organised in modernity.
Bibliography
Altshuler, Alan A., and David Luberoff. (2003). Mega-projects: The changing politics of urban
public investment. Washington, DC: Brookings Institution.
ARUP/Insignia Richard Ellis. (2002). London Olympics 2012: Executive Summary, 21 May
2002.
Auditor General of British Columbia. (2003). Review of Estimates Related to Vancouver’s Bid
to Stage the 2010 Olympic Winter Games and Paralympic Winter Games. Victoria:
Queen’s Printer for British Columbia.
Beck, Ulrich. (1992). Risk Society: Towards a New Modernity. London: Sage.
Bernstein, Peter L. (1996). Against The Gods: The Remarkable Story of Risk. New York: John
Wiley & Sons.
Bovens, Mark, and Paul ‘t Hart. (1996). Understanding Policy Fiascos. New Brunswick:
Transaction.
Breyer, Stephen G. (1993). Breaking the vicious circle: toward effective risk regulation.
Cambridge, MA: Harvard University Press.
British Olympic Association. (2000). ‘London Olympic Bid: Confidential draft report to
government, 15 December 2000’. Wandsworth: British Olympic Association Library.
Cabinet Office. (2010) National Risk Register of Civil Emergencies (2010 edition). London: The
Stationery Office Limited.
Chang, Philip C., and Kiren K. Singh. (1990). ‘Risk management for mega-events: The 1988
Olympic Winter Games,’ Tourism Management 11(1): 45-52.
Clarke, Richard A. (2004). Against All Enemies: Inside America's War on Terror. New York:
Free Press.
Davis, Xiaohong M., Susan MacDonald, Sarah Borwein, David O. Freedman, Phyllis E.
Kozarsky, Frank von Sonnenburg, Jay S. Keystone, Poh Lian Lim and Nina Marano. (2008).
‘Health risks in travelers to China: the GeoSentinel experience and implications for the
2008 Beijing Olympics.’ American Journal of Tropical Medicine and Hygiene 79 (1): 4-8.
Ericson, Richard V., Aaron Doyle and Dean Barry. (2003). Insurance as Governance. Toronto:
University of Toronto Press.
Flyvbjerg, Bent, Nils Bruzelius and Werner Rothengatter. (2003). Megaprojects and Risk: An
Anatomy of Ambition. Cambridge: Cambridge University Press.
Flyvbjerg, Bent, Mette K. Skamris Holm and Søren L. Buhl. (2002). ‘Underestimating Costs in
Public Works Projects: Error or Lie?’, Journal of the American Planning Association, 68, 3,
279-95.
Gibson, Owen. (2009). ‘Olympics 2012 work wins London high praise from IOC inspectors’,
The Guardian, 24 April 2009.
Giddens, Anthony. (1991). Modernity and Self-Identity: Self and Society in the Late Modern
Age. Cambridge: Polity Press.
Giddens, Anthony. (1999a). ‘Risk and Responsibility’, Modern Law Review 62 (1): 1-10.
Giddens, Anthony. (1999b). The Third Way and its Critics. Cambridge: Polity.
Gold, John R., and Margaret M. Gold. (Eds.). (2007). Olympic Cities: city agendas, planning,
and the world’s games, 1896–2012. London: Routledge.
Hacking, Ian. (1975). The Emergence of Probability: A Philosophical Study of Early Ideas
about Probability, Induction and Statistical Inference. Cambridge: Cambridge University
Press.
Hacking, Ian. (1990) The Taming of Chance. Cambridge: Cambridge University Press.
Hacking, Ian. (2003). ‘Risk and Dirt’. In Richard V. Ericson and Aaron Doyle (eds.), Risk and
Morality. Toronto: University of Toronto Press. pp. 22-47.
Hall, Peter. (1980). Great Planning Disasters. London: Weidenfeld & Nicolson.
Hood, Christopher, David K.C. Jones, Nick F. Pidgeon and Barry A. Turner. (1992). 'Risk
Management'. In Royal Society, Risk: Analysis, Perception, Management. London: Royal
Society. pp. 135-92.
Hood, Christopher and David K.C. Jones (Eds.). (1996). Accident and Design: contemporary
debates in risk management. London: UCL Press.
Hood, Christopher, Robert Baldwin and Henry Rothstein. (2001). The Government of Risk.
Oxford: Oxford University Press.
Houses of Commons Library Research Paper 05/55. (2005). The London Olympics Bill. 14 July
2005.
Hutter, Bridget M. (Ed.) (2010). Anticipating Risks and Organising Risk Regulation.
Cambridge: Cambridge University Press
Jennings, Will. (2008). ‘London 2012: Olympic Risk, Risk Management, and Olymponomics’,
John Liner Review 22 (2): 39-45.
Jennings, Will. (2009). ‘London 2012 – A Risk-Based Olympics?’, Risk & Regulation, Vol. 18
(Winter): pp. 14-16.
Jennings, Will, and Martin Lodge. (2009). ‘Coping with the Risks and Vulnerabilities of a
Mega-event’, National Safety & Security and Crisis Management (Special issue of the
magazine of the Ministry of the Interior and Kingdom Relations, Netherlands, October
2009), pp. 34-36.
Jennings, Will. (2010). ‘Governing the Games in an Age of Uncertainty: the Olympics and
organisational responses to risk’, in Anthony Richards, Peter Fussey and Andrew Silke
(eds.) Terrorism and the Olympics: Major Event Security and Lessons for the Future.
London: Routledge.
Jennings, Will, and Martin Lodge. (2010). ‘Critical Infrastructures, Resilience and
Organisation of Mega-Projects: the Olympic Games’, in Bridget Hutter (ed.) Anticipating
Risks and Organising Risk Regulation. Cambridge: Cambridge University Press.
Jennings, Will, and Martin Lodge. (2011). ‘Governing Mega-Events: Tools of Security Risk
Management for the London 2012 Olympic Games and FIFA 2006 World Cup in
Germany’, forthcoming in Government & Opposition 46(2).
Jowell, Tessa, Minister for the Olympics. (2007). House of Commons, Parliamentary Debates,
15 March 2007, Col. 450-452.
Jorm, Louisa R., Sarah V. Thackway, Tim R. Churches and M.W. Hills. (2003). ‘Watching the
Games: public health surveillance for the Sydney 2000 Olympic Games’, Journal of
Epidemiology & Community Health 57: 102-108.
Karyotis, Georgios. (2007) 'Securitization of Greek Terrorism and Arrest of the `Revolutionary
Organization November 17', Cooperation and Conflict 42(3): 271-293.
Lagadec, Patrick. (2004). ‘Understanding the French 2003 Heat Wave Experience: Beyond
the heat, a Multi-Layered Challenge.’ Journal of Contingencies and Crisis Management,
Vol. 12, pp. 160-169.
Lagadec, Patrick. (2007). ‘Over the Edge of the World.’ Crisis Response Journal 3 (4): 48-49.
Lagadec, Patrick, and Erwann O. Michel-Kerjan. (2005). ‘A New Era Calls for A New Model.’
International Herald Tribune, November 1, 2005.
Leiss, William, and Christina Chociolko. (1994). Risk and Responsibility. Montreal: McGill-
Queen's University Press.
LOCOG. (2009). The London Organising Committee of the Olympic Games and Paralympic
Games Ltd Annual Report 2008-09. London: LOCOG.
Lodge, Martin. (2008). ‘Regulation, the Regulatory State and European Politics’, West
European Politics, 31(1/2): 280-301.
Luckes, David. (1997). ‘London Olympic Bid Feasibility Study: A report for the NOC Meeting
of May 28th, 1997.
Luckes, David. (1998). ‘Appraisal of Successful Bids: The winning cities for 1996, 2000, 2004’
(November 16th, 1998).
Majone, Giandomenico. (1994). ‘The Rise of the Regulatory State in Europe,’ West European
Politics 17 (3): 77-101.
Majone, Giandomenico. (1997). ‘From the Positive to the Regulatory State. Causes and
Consequences of Changes in the Mode of Governance.’ Journal of Public Policy 17(2):
139-167.
Meehan, Patrick, Kathleen E. Toomey, James Drinnon, Samuel Cunningham, Nancy Anderson
and Edward Baker. (1998). ‘Public Health Response for the 1996 Olympic Games.’
Journal of the American Medical Association 279 (18): 1469-1473.
Moran, Michael. (2001). ‘Not Steering but Drowning: Policy Catastrophes and the Regulatory
State’, The Political Quarterly, 72, 414-27.
Moran, Michael. (2003). The British Regulatory State. Oxford: Oxford University Press.
National Audit Office. (2007). The budget for the London 2012 Olympic and Paralympic
Games. London: The Stationery Office.
New South Wales, Audit Office. (1999). The Sydney 2000 Olympic and Paralympic Games:
Review of Estimates. Sydney: New South Wales Audit Office.
O’Malley, Pat. (2004). Risk, Uncertainty and Government. London: Cavendish
Press/Glasshouse.
OECD (2003), Emerging Risks in the 21st Century, An Agenda for Action. Paris: OECD.
Olympic Delivery Authority. (2008). Olympic Delivery Authority Annual Report and Accounts
2007–2008. London: The Stationery Office.
Payne, Michael. (2006). Olympic Turnaround: how the Olympic Games stepped back from the
brink of extinction to become the world’s best known brand. Westport: Praeger.
Perrow, Charles. (1984). Normal Accidents: Living with High-Risk Technologies. New York:
Basic Books.
Pidgeon, Nick F., Kasperson, Roger K. and Slovic, Paul (Eds.). (2003). The Social Amplification
of Risk. Cambridge: Cambridge University Press.
Power, Michael. (1997). The Audit Society. Oxford: Oxford University Press.
Power, Michael (2003) Risk management and the responsible organization’. In Richard V.
Ericson and Aaron Doyle (Eds.) Risk and Morality. Toronto: University of Toronto Press,
pp. 145-164.
Power, Michael. (2004). The Risk Management of Everything. London: Demos.
Power, Michael. (2007). Organized Uncertainty: Organizing a World of Risk Management.
Oxford: Oxford University Press.
Preuss, Holger. (2000). Economics of the Olympic Games: Hosting the Games 1972-2000.
Sydney: Walla Walla Press.
Preuss, Holger. (2006). The Economics of Staging the Olympics: A Comparison of the Games
1972-2008. Cheltenham: Edward Elgar.
PricewaterhouseCoopers. (2003). Olympics Bid London 2012: Probability assessment for the
Department of Culture, Media and Sport, 13 January 2003.
http://www.culture.gov.uk/images/freedom_of_information/2012_ProbabilityAssessment.pdf
Priemus, Hugo, Bent Flyvbjerg and Bert van Wee (Eds.). (2008). Decision-Making On Mega-
Projects: Cost–benefit Analysis, Planning, and Innovation. Cheltenham: Edward Elgar.
Richards, Anthony, Peter Fussey and Andrew Silke (Eds.). (2010). Terrorism and the
Olympics: Major Event Security and Lessons for the Future. London: Routledge.
Roche, Maurice. (1994). ‘Mega-Events and Urban Policy.’ Annals of Tourism Research, 21, 1,
1-19.
Roche, Maurice. (2000). Mega-Events and Modernity: Olympics and Expos in the Growth of
Global Culture. London: Routledge.
Scott, James C. (1998). Seeing Like A State: How Certain Schemes to Improve the Human
Condition Have Failed. New Haven: Yale University Press.
SOCOG (Sydney Organising Committee for the Olympic Games). (2001). Official Report of the
XXVII Olympiad. Sydney: SOCOG.
Sunstein, Cass R. (2003). Risk and reason: safety, law, and the environment. Cambridge:
Cambridge University of Press.
Weick, Karl. (1988). ‘Enacted Sensemaking in Crisis Situations.’ Journal of Management
Studies 25: 305-317.
Weick, Karl. (1993). ‘The Collapse of Sensemaking in Organizations: The Mann Gulch
disaster.’ Administrative Science Quarterly 3: 628-652.
Wolff, Alexander (2002). ‘When The Terror Began’, Time Magazine, 25 August 2002.
http://www.time.com/time/europe/magazine/2002/0902/munich/
Yu, Ying, Francisco Klauser and Gerald Chan. (2009). ‘Governing Security at the 2008 Beijing
Olympics,’ The International Journal of the History of Sport 26(3): 390-405.