the new RICH beam pipe
description
Transcript of the new RICH beam pipe
![Page 1: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/1.jpg)
1Fulvio TESSAROTTO
the new RICH beam pipe
- pipe production, gluing and tests
- measurement and removal of the old pipe
- fixation system
- installation of the new pipe - characteristics of the new pipe
COMPASS TB meeting, CERN, 12/04/2012
Fulvio Tessarotto
![Page 2: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/2.jpg)
2Fulvio TESSAROTTO COMPASS TB meeting, CERN, 02/02/2012
Slide from the last TB:Issue status
Removal of presently used pipe Extremely difficult behind the mirrors
Material for the thin pipe 5 layer aluminized Mylar, 0.6 ‰ X
Geometry 2 pipes 100 mm diam., 1570 mm long
Gas He, few l/h, 15 mbar overpressure
End caps alum. Mylar glued on Al microflanges
Fixation system Thin stainless steel wire ropes Extremely difficult behind the mirror wall: still to be defined
![Page 3: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/3.jpg)
3Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
tubes, microflanges, gluing tests
weight = 15 g
![Page 4: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/4.jpg)
4Fulvio TESSAROTTO
Simulations for the new pipe
max = 0.1 Mpa,yield strength = 85 MPaCOMPASS TB meeting, CERN, 12/04/2012
![Page 5: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/5.jpg)
5Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
half-pipe He leak testsMeasured leak, including connections: 0.5 ml/h
![Page 6: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/6.jpg)
6Fulvio TESSAROTTO
“Safety is the first of our priorities”
- RICH is a “confined space”: access is allowed to authorized persons only- Authorization requires a confined space formation course and a medical certification- New procedure: CERN asks for medical certification to be provided by the Institutes.
- Inside the RICH we needed a scaffolding: the old scaffolding is not complying to the rules.- The new scaffolding can only be mounted by authorized people.- The authorisation requires ….
1) a general CERN confined space course was organized and people sent to attend it 2) a medical check and certification protocol was defined, agreed upon and applied in Trieste 3) the activity inside the RICH was defined in detail and an access protocol was produced 4) the supervisor was changed 5) special exception to allow access for radioprotection experts, scaffolding responsible, etc. 6) a scaffolding was borrowed / built and certified by the responsible in Clean Area 7) authorization to mount the scaffolding by ourselves was obtained 8) authorization to use the scaffolding (after check) with a use protocol was provided 9) … 10) …All involved persons have been extremely collaborative!
Firenze, 22/03/2012
![Page 7: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/7.jpg)
7Fulvio TESSAROTTO
RICH opening, old pipe removal1) Radiation level: < 0.2 μSv/h2) Surveying of the old pipe3) Large scaffolding installation4) Small scaffolding installation5) Removal of the old pipe4) Mirrors surveying
COMPASS TB meeting, CERN, 12/04/2012
![Page 8: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/8.jpg)
8Fulvio TESSAROTTO
After the removal of the old pipe - We confirmed it is not possible to access the area downstream of the mirrors
- We decided to change the fixation system and the gas pipes to reduce the material
1) We prepared two beam pipes of 1.6 m and tested them: measured leak rate: 0.5 ml/h 2) We decided to produce a unique pipe by gluing two halves on 1.6 m 3) The vertical middle gluing needed a special microflange and a system for vertical operation 4) We continued to put pressure on Lamina, despite the denials, to try producing a 3.2 m tube 5) One 3.5 m long tube arrived in Trieste just in time. 6) The microflanges and the system for gluing were ready: the long pipe was glued and 7) Tested together with the “Tygon” pipes and plastic strips for gas connection: 0.6 ml/h 8) Both long pipes (single piece and two-halves shipped to CERN) 9) We checked that two suspensions are enough (pipe rigidity better than expected) Two fixation points are enough
COMPASS TB meeting, CERN, 12/04/2012
![Page 9: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/9.jpg)
9Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
gluing end-caps on the single pipe
![Page 10: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/10.jpg)
10Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
Careful packaging
![Page 11: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/11.jpg)
11Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
And transport
![Page 12: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/12.jpg)
12Fulvio TESSAROTTO
Preparation for the new pipe10) Putting in place the top fixation systems was challenging but successful11) Dummy flanges positioned using a laser system12) Pipe introduced in the RICH and put in place13) Surveying to check the position found several millimeter offsets14) Position partially corrected and fixation system tensioned at 2 kg
COMPASS TB meeting, CERN, 12/04/2012
![Page 13: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/13.jpg)
13Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
Pre-alignment of pipe holders
![Page 14: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/14.jpg)
14Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
the new pipe inside the RICH
![Page 15: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/15.jpg)
15Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
The polycarbonate suspension ring
![Page 16: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/16.jpg)
16Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
![Page 17: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/17.jpg)
17Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
New fixation system and gas pipes
![Page 18: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/18.jpg)
18Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
Pipe specificationsInner diameter: 100.0 mm (+0.0-0.1)Thickness: 140 μm Length: 3140 mmMaterial: Mylar (PET) + 1 μm Al
Single pipe, front and rear window:same material: 140 μm Mylar + 1 μm AlMicroflanges: “F” shape Al, 0.5 mm thick
Upstream microflange acts as holder,Downstream holder at 80 cm from edge,Policarbonate 8mm x 8mm + 2 nylon screws
Fixation via stainless steel microwire ropes:4 ropes (90 degrees) per holder,1 x 7 wires 90 μm diam. (limit = 9 kg)+ 10 μm nylon coating, tensioning: 2 kg,thermal expansion +- 2 mm, equiv. 1 kg
Adjustement and tensioning microsystems placed out of the acceptance
![Page 19: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/19.jpg)
19Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
Upstream fixation and gas connections
Total amount of materialin the acceptance:
Fe (8 m microwire ropes): 5 gAl ( 2 m pipe + microfl.): 60 gMylar: 180 gPolycarbonate (fixation): 20 gEpoxy: 6 gCu: 0.5 gTygon: 5 gNylon: 4 g
Old gas pipes: 6x4 mm stainless steel tubes, new pipes: 6x5 mmAl pipes (10 times less X0)
![Page 20: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/20.jpg)
20Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
Measurement and adjustment
![Page 21: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/21.jpg)
21Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
position regulation and surveying
![Page 22: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/22.jpg)
22Fulvio TESSAROTTO COMPASS TB meeting, CERN, 12/04/2012
Material budgetactual pipe material budget: (0.15 mm / 17.6 mm) 8.523 ‰ X0
goal for the material budget of the new pipe: 10% actual = 0.852 ‰ X0
5 layers of 27 μm thick Mylar : (0.135 mm / 287 mm) 0.470 ‰ X0
5 layers of 200 nm thick Al coating: (1.0 μm / 89 mm) 0.011 ‰ X0
4 layers of 6 μm thick Mylar glue: (24 μm / 280 mm) 0.086 ‰ X0
-----------------------------------------------------------------------------------------------------------total material budget for orthogonal crossing: 0.567 ‰ X0
total material budget for parallel crossing (r < 42 mm): 2.26 ‰ X0
parallel crossing (42 mm < r < 49 mm): 1.9 % X0
6 mrad particle crossing the pipe (old value = 1.4 X0) 9 % X0
The contribution from end caps, fixation rings, gas connections has been minimized
![Page 23: the new RICH beam pipe](https://reader031.fdocuments.net/reader031/viewer/2022020219/56816230550346895dd26004/html5/thumbnails/23.jpg)
23Fulvio TESSAROTTO COMPASS TB meeting, CERN, 02/02/2012
time schedule
RICH opening February 21Scaffolding mounted February 24Old pipe measurement March 6Removal of the old pipe March 7Mirror measurement March 16Installation of the new pipe April 5He leak test April 17Scaffolding dismounting April 18RICH closing April 19 or April 25