The Life Safety Specialist Surveyor Preparing for the Life Safety Specialist Documentation Review...
-
Upload
caroline-bailey -
Category
Documents
-
view
218 -
download
0
Transcript of The Life Safety Specialist Surveyor Preparing for the Life Safety Specialist Documentation Review...
The Life Safety Specialist Surveyor
Preparing for the Life Safety Specialist Documentation Review and Facility Tour
Healthcare Engineering Consultants
Will limit
The Life Safety Specialist (LSS)
It is likely that the LSS will arrive with the team on the first or second day, less likely later in the survey
For 2011, the LSS will usually be scheduled for an additional day based on the scheduled time of the previous survey
The LSS will spend several hours on dedicated documentation review, but much more time on the facility tour
Other responsibilities assigned to the LSS will depend on the survey team member preferences and responsibilities – they may conduct the “EC Interview” and Emergency Management tracers
The other survey team members will also observe life safety issues, but not as detailed as the LSS – it is not likely that the nurse and physician will request a ladder and flashlight!
If the LSS observes deficiencies outside of their defined responsibility (example: medical records privacy or medication security), they will report it to the other team members
Healthcare Engineering Consultants
The LSS Documentation Review
Healthcare Engineering Consultants
Life Safety Specialist (LSS) surveyor documentation responsibilities include at a minimum:
LS.01.01.01: SOC and Life Safety Code
LS.01.02.01: Interim life safety measures
EC.02.03.05: Fire system tests
EC.02.05.07: Emergency power systems
EC.02.05.09: Medical gas and vacuum systems
Note: In 2011, the Life Safety Specialist may be assigned additional responsibilities during the survey
The LSS Documentation Review
Healthcare Engineering Consultants
LS.01.01.01: SOC and Life Safety Code
The SOC completion will be verified through the Joint Commission Connect site (BBI’s and PFI’s)
Have the SOC notebook available for review
The PFI documents from the previous survey may be reviewed to verify completion of deficiencies (have them available, if requested)
The compartmentation drawings will be reviewed to assist in planning the facility tour
Life Safety Code compliance will be verified during the facility tour
The Statement of Conditions
Healthcare Engineering Consultants
How Should the Statement of Conditions (SOC) Document be
Completed?
The Statement of Conditions
Healthcare Engineering Consultants
What is the SOC?The Statement of Conditions (SOC) is a document that is required to be completed by every healthcare facility that applies for accreditation by the Joint Commission. It references the *2000 edition of the Life Safety Code and consists of the following sections:
Basic Building Information (BBI) Form – electronic on Connect site
Life Safety Assessment (LSA) Form – not electronic
Plan for Improvement (PFI) Form – electronic on Connect site
BBI’s, LSA’s and PFI’s are
*Note: Other LSC editions may be selected, but the entire edition must be followed
The Statement of Conditions
Healthcare Engineering Consultants
SOC Notebook (Best Practice)
A SOC notebook is strongly recommended to contain “hard copies” of the SOC documents
The notebook should include at least the following sections:
Section 1: The SOC policy and responsibility statement
Section 2: Current copies of the downloaded BBI forms
Section 3: Accurate, color-coded compartmentation prints
Section 4: The latest, completed LSA-type document
Section 5: Current and previous, downloaded PFI forms
Section 6: Any correspondence with the Joint Commission,
including equivalencies, letters and emails
The Statement of Conditions
Healthcare Engineering Consultants
Why Should I have an SOC Policy? (Best Practice)
The SOC policy describes how the Statement of Conditions program is organized for the facility
What Should the SOC Policy Include?
Who is responsible for completing and maintaining the SOC
How often the SOC documents are reviewed
Who reviews the SOC documents for timeliness
PFI guidelines (when does a work order become a PFI?)
Whether a BMP is implemented
Whether an above-the-ceiling program is in place
How the SOC documents are organized
Statement of Conditions Document
Healthcare Engineering Consultants
The current Statement of Conditions “hard copy” document is dated 5/2004 and can still be downloaded from JointCommission.org for the LSA form (do not use the BBI or PFI “hard copies” – they are obsolete)
Statement of Conditions Document
Healthcare Engineering Consultants
Notes About the e-BBI Form
List on the e-BBI cover page every occupancy that will be surveyed, even for business occupancies (make sure that the BBI and survey list match!)
The e-BBI questionnaires are only required for ambulatory, hotel/ dormitory and healthcare occupancies
Fill in the comments section regarding SOC preparer, location of building drawings, mixed occupancies, equivalencies, special building features or local AHJ requirements to the BBI
If multiple occupancies are entered, the greatest percentage defaults to the BBI form, so multiple BBI entries are required
Be sure to download the electronic version of the BBI form before it is saved so that a “back-up” is available, and place a copy in the SOC Notebook
Statement of Conditions Document
Healthcare Engineering Consultants
Compartmentation Requirements
Mixed Occupancies: (LSC: 19.1.2.1)
Sections of health care facilities shall be permitted to be classified as other occupancies, provided that they meet the following conditions:
1) They are not intended to serve health care occupants for purposes of housing, treatment, or customary access by patients incapable of self-preservation
2) They are separated from the health care occupancy by a fire rating of at least 2 hours
3) Separation between ambulatory and business occupancies only requires a 1 hour rating (LSC: 21.1.2.1)
Statement of Conditions Document
Healthcare Engineering Consultants
e-BBI Form – Buildings
Be sure to complete for all healthcare and ambulatory facilities
Optional for business occupancies, but strongly suggested for the cover page
Statement of Conditions Document
Healthcare Engineering Consultants
e-BBI Form - Healthcare
Refer to instructions related to “stories” in the Life Safety Code
Note instructions related to building construction type (occupancy)
Building age is important due to significant code changes
Statement of Conditions Document
Healthcare Engineering Consultants
e-BBI Form – page 2
1991 date significant due to sprinkler requirement
Emergency power fuel type important due to “wet stacking”
Statement of Conditions Document
Healthcare Engineering Consultants
e-BBI Form – page 3
“Previous inspections” data provides valuable information to the survey team!
Be sure to list local or regional requirements (example: limited generator testing due to high pollution days) in the “Comments” section at the bottom of the form as well as other requested information
Statement of Conditions Document
Healthcare Engineering Consultants
LSA Form (is not electronic):
Is a voluntary assessment tool, although some assessment is required at least annually
Is not required for “Business Occupancies”
The Joint Commission surveyor normally expects some type of form, document or evaluation to be completed
Dated 5/2004, so a cover sheet that is signed annually is recommended
Can still be downloaded from the Joint Commission home page website (search “Statement of Conditions”)
Can use PPR form or similar for the LSA document
Comments in LSA must match PFI deficiencies
Statement of Conditions Document
Healthcare Engineering Consultants
Life Safety Building Compartmentation Drawings
Blue – smoke barrier
Green – 1 hour fire wall (hazardous area)
Red – 2 hour fire wall
Note: Color-coded drawing is “best practice”
Statement of Conditions Document
Healthcare Engineering Consultants
Notes About the PFI Forms
The forms should not be used for “operational deficiencies”, such as exit lights burned out, doors out of minor adjustment or small penetrations that can be easily filled – these should be completed using the routine work order system
The normal “trigger time” from a work order to PFI is 45 days
Document the “PFI’s” on a continuing basis – be sure that the PFI log is up-to-date and ready to be reviewed by the surveyor
Don’t forget to enter the projected start and completion dates and the actual completion date
Failure to meet the completion dates without a delay approval results in Conditional Accreditation 6 months after the projected completion date has passed!
If applicable, keep any previously signed PFI copies available
Statement of Conditions Document
Healthcare Engineering Consultants
The first page for the electronic PFI forms is used to list the deficiencies
Notice that a “No Deficiencies” option is available
(and should be completed, if applicable)
Statement of Conditions Document
Healthcare Engineering Consultants
The second page for the electronic PFI forms is used to indicate the deficiency resolutions
Don’t forget to complete all of the requested information, including the proposed action, source of funds and the projected start and completion dates
The projected completion dates can be altered until they are “frozen” before or during the actual survey!
Comments for each PFI should include a note regarding the implementation of ILSM’s!
Statement of Conditions Document
Healthcare Engineering Consultants
The listing document simply provides a summary of all of the deficiencies that have been recorded on the PFI form for tracking purposes – keep a copy of this in the SOC notebook for reference purposes
The Life Safety Specialist Documentation Review
Healthcare Engineering Consultants
Should I Implement and Document a Building Maintenance
Program (BMP)?
Healthcare Engineering Consultants
Is voluntary; no scoring benefit in 2011
No longer requires a measure of effectiveness
Measurement system can use random samples
Results should be used to determine revisions to inspection or test frequencies
Information should be provided to the hospital safety committee if changes are made to the program
Is basically a PM program for the buildings
Is still considered a Best Practice
The Building Maintenance Program (BMP)
Fire System Tests
Healthcare Engineering Consultants
Points to Remember
Clearly define supervisory devices (fire pump, low air pressure on dry or pre-action systems and water tank level indicators expected)
Tamper and flow device test intervals increase to quarterly on 7/1/11
Inventory all doors on magnetic releasing devices and document test results
Document tests results for each individual heat and smoke detector, pull box and audible and visual device
Fire System Component Test Schedule
Standard Element of Performance Scoring Category
Test Interval
NFPA Reference
EC. 02.03.05
Fire Component Tests
1 Supervisory switches
C Q NFPA 72
2 Tamper switches, flow devices
C S/A NFPA 72
3 Duct detectors, door releasing devices
C A NFPA 72
3 Smoke and heat detectors, pull boxes
C
A NFPA 72
4 Audible and visual alarms
C A NFPA 72
5 Off-premises transmission equipment
A Q NFPA 72
6 Fire pump churn test
C W NFPA 25
7 Water tank level alarms
C S/A NFPA 25
8 Water tank level alarms (cold weather only)
C M NFPA 25
9 Main drain tests on system risers
C A NFPA 25
10 Fire department connections
A Q NFPA 25
11 Fire pumps (flow test)
A A NFPA 25
12
Standpipe test C 5 yr NFPA 25
13 Kitchen extinguishing systems
A S/A NFPA 96
14 Carbon dioxide/ gaseous extinguishing systems
A A NFPA 2001
15 Portable fire extinguishers (visual check)
C M
NFPA 10
16
Portable fire extinguishers (preventive maintenance)
C A NFPA 10
17 Occupant hoses
C 3 yr–hydro 5 yr–new
NFPA 25, 1962
18 Smoke/ fire dampers
C 6 years NFPA 80, 105
19 HVAC smoke detectors w/ shutdown
A A NFPA 90A
20 Horizontal/ vertical fire doors
C A NFPA 80
Fire System Tests
Healthcare Engineering Consultants
Points to Remember
Document receipt time of fire alarm signal to local fire department or receiving station
Document static and residual pressure readings for main drain tests and time back to static pressure (best practice)
Visually inspect fire department connections quarterly
The 5-year standpipe test was added to the requirements in 2009
Indicate the day and month of portable fire extinguisher checks
Fire System Component Test Schedule
Standard Element of Performance Scoring Category
Test Interval
NFPA Reference
EC. 02.03.05
Fire Component Tests
1 Supervisory switches
C Q NFPA 72
2 Tamper switches, flow devices
C S/A NFPA 72
3 Duct detectors, door releasing devices
C A NFPA 72
3 Smoke and heat detectors, pull boxes
C
A NFPA 72
4 Audible and visual alarms
C A NFPA 72
5 Off-premises transmission equipment
A Q NFPA 72
6 Fire pump churn test
C W NFPA 25
7 Water tank level alarms
C S/A NFPA 25
8 Water tank level alarms (cold weather only)
C M NFPA 25
9 Main drain tests on system risers
C A NFPA 25
10 Fire department connections
A Q NFPA 25
11 Fire pumps (flow test)
A A NFPA 25
12
Standpipe test C 5 yr NFPA 25
13 Kitchen extinguishing systems
A S/A NFPA 96
14 Carbon dioxide/ gaseous extinguishing systems
A A NFPA 2001
15 Portable fire extinguishers (visual check)
C M
NFPA 10
16
Portable fire extinguishers (preventive maintenance)
C A NFPA 10
17 Occupant hoses
C 3 yr–hydro 5 yr–new
NFPA 25, 1962
18 Smoke/ fire dampers
C 6 years NFPA 80, 105
19 HVAC smoke detectors w/ shutdown
A A NFPA 90A
20 Horizontal/ vertical fire doors
C A NFPA 80
Fire System Tests
Healthcare Engineering Consultants
If the occupant hoses have been removed, keep a copy of the approval letter from the AHJ
Place inaccessible smoke and fire dampers on the PFI for a 6-year, renewable period (for tracking purposes only)
Document that duct detectors trip the air-handling units
Only applies to vertical and horizontal smoke and fire doors, not security doors or curtains
Fire System Component Test Schedule
Standard Element of Performance Scoring Category
Test Interval
NFPA Reference
EC. 02.03.05
Fire Component Tests
1 Supervisory switches
C Q NFPA 72
2 Tamper switches, flow devices
C S/A NFPA 72
3 Duct detectors, door releasing devices
C A NFPA 72
3 Smoke and heat detectors, pull boxes
C
A NFPA 72
4 Audible and visual alarms
C A NFPA 72
5 Off-premises transmission equipment
A Q NFPA 72
6 Fire pump churn test
C W NFPA 25
7 Water tank level alarms
C S/A NFPA 25
8 Water tank level alarms (cold weather only)
C M NFPA 25
9 Main drain tests on system risers
C A NFPA 25
10 Fire department connections
A Q NFPA 25
11 Fire pumps (flow test)
A A NFPA 25
12
Standpipe test C 5 yr NFPA 25
13 Kitchen extinguishing systems
A S/A NFPA 96
14 Carbon dioxide/ gaseous extinguishing systems
A A NFPA 2001
15 Portable fire extinguishers (visual check)
C M
NFPA 10
16
Portable fire extinguishers (preventive maintenance)
C A NFPA 10
17 Occupant hoses
C 3 yr–hydro 5 yr–new
NFPA 25, 1962
18 Smoke/ fire dampers
C 6 years NFPA 80, 105
19 HVAC smoke detectors w/ shutdown
A A NFPA 90A
20 Horizontal/ vertical fire doors
C A NFPA 80
Points to Remember
Don’t forget to implement and document “Interim Fire System Measures” (IFSM), when required
Fire System Test Monitoring
Healthcare Engineering Consultants
Regulatory Compliance Dashboard for Fire System Tests
Description JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Comments Supervisory Devices
1/15 X X X
Tamper Switches
1/15 X X X
Water Flow Devices
1/15 X X X
Duct Detectors
1/22
Door Releasing Devices
X
Smoke Detectors
X
Pull Boxes
1/18 X
Audible Alarms
X
Visual Alarms
X
Signal Time to FD
1/6 X X X
Fire Pump Churn Test
4, 11 25
W W W W W W W W W W W
Fire Pump Flow Test
X
Water Tank Level Alarms
N/A X X X X X X X
Main Drain Riser Test
X
Fire Dept. Connections
1/12 X X X
Standpipe Test
X 5 yr
Kitchen Systems
X X
Best Practice for Monitoring Compliance
Fire System Test Monitoring
Healthcare Engineering Consultants
Regulatory Compliance Dashboard for Fire System Tests (continued)
Description JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC Comments CO2/ Gaseous Systems
X
Portable Extinguishers
1/23 X X X X X X X X X X X
Portable Extinguishers
X
Occupant Hoses
X 3 yr
Smoke/ Fire Dampers
X 6 yr
HVAC Shutdown
1/25 X
Horiz/ Vertical Fire Doors
X
Key to dashboard symbols: X – Indicates that action is required during the month indicated; W – Indicates that weekly action is required A/R – Indicates that action is required when applicable Key to colored boxes: Red boxes indicate non-compliance (tests were not performed); Yellow boxes indicate partial compliance (tests have been delayed or not fully completed); Green boxes indicate full compliance (tests satisfactorily completed).
The LSS Documentation Review
Healthcare Engineering Consultants
EC.02.05.07: Emergency Generators Perform and document weekly generator visual checks (NFPA 110)
Perform and document monthly generator tests between 20 and 40 days and with at least 30% of the rated load for 30 minutes
Document that all automatic transfer switches are exercised monthly
Conduct annual load bank tests if the 30% load is not achieved and manifold temperatures are not sufficient (possible change from the 2 hour to a 1.5 hour test in 2011 – not yet approved)
Combining the annual and trienniel tests can be performed by starting the load at 30% of nameplate for the first 30 minutes of the test
Document the static or dynamic 4-hour trienniel test for all generators
Test fuel oil quality annually, unless fuel is consumed from the entire tank (NFPA 110)
Utilize “Interim Emergency Power Measures” (IEPM) when necessary
Note: Refer to NFPA 99 and 110 for more information
The LSS Documentation Review
Healthcare Engineering Consultants
EC.02.05.07: Emergency Battery Lights Required in all anesthetizing locations (NFPA 70: 517.63 ) Task Light!
“administration of nonflammable inhalation anesthetic agents
in the course of examination or treatment”
Note: Grandfathering usually permitted in existing OR’s
Required in “Level 1 or Level 2 EPS equipment locations” (NFPA 110: 7.3.1) Task Light!
Required in business occupancies for egress lighting where emergency power is not required or not available (NFPA 101: 7.9.1.1) Egress Light!
Monthly push-to-test required for all battery installations
Differentiate between “task lighting” and “egress” lighting
Annual battery replacement in lieu of 90-minute discharge test
Note: 10% of lights must be tested for 90 minutes annually, even if the batteries are changed.
The LSS Documentation Review
Healthcare Engineering Consultants
EC.02.05.07: Stored Emergency Power Supply Systems (SEPSS)
Standard applies to Level 1 systems (NFPA 111: 4.5.1)
Level 1: “failure of the equipment to perform could result in
loss of human life or serious injuries”
Testing requires:
1. Quarterly functional test (5 minutes or class specification)
2. Annual full-load test for 60% of SEPSS class duration
Note 1: NFPA 111 requires a monthly inspection, quarterly functional test and annual full load test for full class duration for Level 1 systems
Note 2: The Joint Commission references exit lighting, life support ventilation, fire detection and alarm systems, and public communications systems as Level 1 systems, but most are not SEPPS systems
The LSS Documentation Review
Healthcare Engineering Consultants
EC.02.05.09: Medical Gas and Vacuum Systems
Medical gas and vacuum system preventive maintenance
program is required (facility must define PM) and must include:
- Bulk medical gas and vacuum system components and source valve
- Master signal panels and area alarms
- Automatic pressure switches and shutoff valves
- Flexible connectors and outlets
Testing per NFPA 99 is required for new installation,
modification or repair (cross-connections, purity, pressure)
Main supply valves and area shut-off valves must be
accessible and clearly labeled
Utilize “Interim Medical Gas Measures” (IMGM) when necessary
Note: Significant changes to NFPA 99 are likely to occur when the next vote occurs at the NFPA Annual Meeting
The LSS Documentation Review
Healthcare Engineering Consultants
EC.02.05.09: Medical Gas and Vacuum Systems
Certification of installers and verifiers per ASSE 6000 series is
required
Medical air quality must meet NFPA 99 requirements below:
Parameter Limit Value
Pressure dew point 39 degrees F
Carbon monoxide 10 ppm
Carbon dioxide 500 ppm
Gaseous hydrocarbons 25 ppm (as methane)
Halogenated hydrocarbons 2 ppm
The LSS Documentation Review
Healthcare Engineering Consultants
Medical Gas and Vacuum System PM Recommendations
Component Description
Recommended Test Frequency
Gas cylinder manifold pressure
Daily
Gas cylinder manifold changeover signal
Daily
Liquid cylinder manifold pressure
Daily
Liquid cylinder manifold changeover signal
Daily
Liquid cylinder reserve/ in-use signal
Annually
Bulk liquid system contents gauge
Daily
Bulk system pressure gauges
“Regularly” (weekly)
Bulk system master signal
“Periodically” (monthly)
Main line vacuum system gauge
Daily
Medical air intake location
Quarterly
Medical air pressure gauge
Annually
Medical air high level water sensor
Annually
Medical air receiver drain
Daily
Medical compressed air alarms
Annually
Medical air compressors/ vacuum pumps
Per manufacturer specifications
Dew point sensor/ CO monitor
Annually
Warning system components
Annually
Audible/ visual alarms
Monthly
Shut-off valve leak test
“Periodically” (annually)
Outlet leakage and flow
“Periodically” (annually)
Medical air purity
As determined by facility
Note: The recommendations provided in the chart to the right are from NFPA 99, the 2005 edition, Appendix C, section 5.2. Tests that are required due to new system installations, renovations or repair are listed in chapter 5 of NFPA 99
The LSS Documentation Review
Healthcare Engineering Consultants
Interim Utility System Measures (IFSM, IEPM, IMGM) Interim Utility System Measures
Project Number: _________________ Date: ____________________ Affected System: Fire System: _____ Emergency Power _____ Medical Gas: _____ Description of Project: ______________________________________________________ __________________________________________________________________________ __________________________________________________________________________ __________________________________________________________________________ Interim Measures Required: _____ Affected staff notified Comments: ______________________________________ _____ Additional Equipment Required Specify: _________________________________ _____ Back-up Procedures in Place Specify: ___________________________________ _____ Emergency Procedures Reviewed Comments: ____________________________ _____ Other: ______________________________________________________________ _____ Other: ______________________________________________________________ _____ Other: ______________________________________________________________ Additional Comments: ______________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ _________________________________________________________________________ Date Project Completed: ___________________ Reviewed By: ____________________
Best Practice!
Strongly recommended to document that interim measures have been implemented to compensate for utility systems that are taken out of service
The LSS Facility Tour
Typical Tour Sequence1. Start on the roof, penthouse, mechanical equipment rooms
2. Take the “most traveled stairwell” from the top to the bottom
3. Take the elevator back up to the top patient floor
4. Check smoke/ fire doors and compartmentation features
5. Inspect chutes, storage areas, utility chases, hazardous areas
6. Continue down to the lower and basement levels to specific areas, such as the kitchen, loading dock, fire pump, emergency generators, fire annunciator panel, compressed gas and infectious waste storage
7. Complete checklist, or until problems are found!
Healthcare Engineering Consultants
The LSS Facility Tour
Checklist for the Facility Building Tour
Smoke and fire doors
Check: Closure, label rating, gaps, undercuts, warpage, kick plate
Smoke and fire compartments
Check: Penetrations, proper sealant
Roof and penthouse
Check: Contractor supplies, smoking, exhaust fans labeled
Exit stairwells
Check: Door rating, closure, signage, exit discharge
Linen/ trash chutes and receiving rooms
Check: Door rating, closure, fusible link, chute blockage
Healthcare Engineering Consultants
The LSS Facility Tour
Checklist for the Hospital Building Tour (cont’d)
Hazardous areas
Check: Storage of flammables, room rating, door closer
Fire pump
Check: Controls turned “on”, valves open, tampers OK
Fire annunciator panel
Check: Bypass, trouble, ground fault or supervisory
Soiled linen rooms
Check: Proper storage, dirty separated from “clean”
Healthcare Engineering Consultants
The LSS Facility Tour
Checklist for the Hospital Building Tour (cont’d)
Medical waste storage
Check: Locked area, secure, sharps not accessible
Loading dock
Check: Smoking, improper storage, powered equipment
Kitchen area
Check: Cleanliness, storage, CO2 tanks, refrigerator temps, K-type portable extinguishers within 30’ of fat fryer
PFI verification
Check: Previous PFI’s have been resolved as listed
Healthcare Engineering Consultants
The LSS Facility Tour
Checklist for the Hospital Building Tour (cont’d)
ILSM verification
Check: Construction areas for ILSM implementation
Mechanical equipment rooms
Check: Storage, unlabeled containers, cigarettes, labeling
Emergency generators
Check: In “auto” mode, batteries/ charger, fuel leaks
Medical gas systems
Check: Manifolds, medical air and vacuum pumps
Healthcare Engineering Consultants
The LSS Facility Tour
Checklist for the Hospital Building Tour (cont’d)
Compressed gas storage rooms
Check: Full and Empty separation, chained or on racks
Egress corridors
Check: Equipment “not in use”, containers > 32 gallons
Eyewashes, showers and portable fire extinguishers
Check: Test dates on log or tag
Chapel
Check: Candles, open flames
Other?
Healthcare Engineering Consultants
Multiple “Operational” Deficiencies are Likely to
be Found During the Facility Tour
Healthcare Engineering Consultants
The LSS Facility Tour
Healthcare Engineering Consultants
Operating Features
A clear space >18 inches below sprinkler heads to the top of storage must be maintained
Exception: Perimeter wall shelving, unless below the sprinkler (refer to NFPA 13)
Portable space heating devices are only permitted in non-sleeping staff and employee areas, with heating elements that do not exceed 212 degrees F (LSC, 2009 edition, 19.7.8)
Combustible decorations are prohibited, unless flame retardant (19.7.5.4)
Soiled linen or trash collection receptacles shall not exceed 32 gallons in capacity (19.7.5.5)
Exception: Attended or in hazardous area
Operational Deficiencies
Healthcare Engineering Consultants
Operating Features
Holiday decoration policy and implementation
Candles used in the chapel
Furnishings, decorations or other objects may not obstruct access, egress or block the visibility of exits (7.1.10.2.1)
Exit doors must be free of mirrors, draperies or hangings that may conceal, obscure or confuse the direction of exit (7.5.2.2), and;
Hallway Clutter!
Operational Deficiencies