The FENIX project: Integration of Renewables and ...

16
Prague, 8-11 June 2009 1 The FENIX project: Integration of Renewables and Distributed Generation in Networks through aggregation fenix ‘… a step towards the future of fenix ‘… a step towards the future of electricity networks

Transcript of The FENIX project: Integration of Renewables and ...

Page 1: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009 1

The FENIX project: Integration of Renewables and Distributed Generation in Networks through aggregation

fenix‘… a step towards the future of

electricity networks’

fenix‘… a step towards the future of

electricity networks’

Page 2: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

Enabling Distributed Energy Resources (DER) to make the EU electricity supply system cost efficient, secure and sustainable through aggregation into Large Scale Virtual Power Plant (LSVPP)

Objective

Page 3: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

José M. Corera – Spain Round Table RT4

• FENIX is an European collaborative project, partly funded by the European Commission within the 6th Framework Program for Research

• Launched in October 2005 and its duration is 4 years (ends September 2009)

• 20 partners are involved• The total budget is 14,7 MEuro14,7 MEuro

Project Coordinates

Page 4: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

4

The Netherlands

Romania

Slovenia

AustriaGermanySpain

France

United Kingdom

Partners

Page 5: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

VPP concept400 kV

VPP(G&L)

LG L

G

G

G

400kV

132kV

33kV 11kV

400 kV

P, QP, Q

=

Characteristics of aggregated active generation and load:

(1) Output (2) Reserve(3) Dynamic response (4) Cost characteristics

11 kV/0.4 kV

LV area 1 LV area 2TVPP area 1 TVPP area 2

Page 6: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

6

Specification and

development

Building the demonstrations

Cost benefit analysisRegulatory recommendations

Connection & use of

distribution system

Sale of electricity /

flexible demand services

Trade

TSO Ancillary Services

Local Network Services

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

ResourceCVPPCVPP

MarketMarket

TSOTSO TAOTAO

TVPPTVPP

Use of transmission

system

Electricity

Revenue

DAODAO

Connection & use of

distribution system

Sale of electricity /

flexible demand services

Trade

TSO Ancillary Services

Local Network Services

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

ResourceCVPPCVPP

MarketMarket

TSOTSO TAOTAO

TVPPTVPP

Use of transmission

system

Electricity

Revenue

DAODAO

Sale of electricity /

flexible demand services

Trade

TSO Ancillary Services

Local Network Services

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

Resource

Distributed Energy

ResourceCVPPCVPP

MarketMarket

TSOTSO TAOTAO

TVPPTVPP

Use of transmission

system

Electricity

Revenue

Electricity

Revenue

DAODAO

Progress We are here

Page 7: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

Key research challenges of Fenix1. Identify potential present (and future) contribution of DER to networks that can be

performed at advantageous cost.

2. Identify network needs and the way to satisfy them using DER

3. Revise regulations, incentive mechanisms and contractual relationships between the different participants (DER, aggregators, network operators and markets), to enhance DER contribution to the network with a fair economic return

4. Investigate aggregation (VPP) so the limited size of DER and their non-deterministic behaviour limitations can be overcome

5. Develop the ICT architecture to make it work:• At DER level: FENIX box• At VPP level: DEMS systems• At system operators: revision of EMS and DMS tools

6. Two physical demonstrations:• UK (hosted by EDF Energy)• Spain (hosted by Iberdrola)

Page 8: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

Región EsteRegión MadridRegión CentroRegión NorteRegión Oeste

Demonstration

Control Centre

Bilbao

Valencia

Alicante

Toledo

Madrid

Valladolid• Area around 3.000 km2

• 169.001 Low Voltage Customers – 70% Urban– 12% Suburban– 17% Rural

• 1.234 MVA = Total Capacity– 687 MVA Installed capacity (1775 T.C.)– 547 MVA Contracted capacity (799 T.C.)

• 1.907 Km of lines– 80% aerial– 20% underground

Alava Network

Page 9: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

320 MW peak demand

DER – 168 MVA Installed capacity

ANTOÑANA1,2 MW

BERGANZO1,2 MW

DSO – 30kV/13,2kV simplified network

ELGUEA

GAMARRAALI

ALSASUA

JUNDIZ

PUENTELARRA

Transformer 220/30 kV - TSO-DSO Boundary

G DER (Wind farms) MW

Capacitors MVAR

14,4 x 2 Mvar

14,4 x 2 Mvar 14,4 Mvar

5,4 x 4 Mvar

G

G

G

G

G

GUASCOR

HOSPITAL

GOJAIN MICHELIN

12 MW

2,0 MW

2,7 MW

TXAGORRITXU0,5 MW

47 MW

G

G

GENVIROIL

HOLZLAN

SEARSA

2,0 MW

1,0 MW

2,7 MW

G Small Hydro and renewable units MW

GELGUEA30 MW

GBADAIA

50 MW

GURKILLA

32 MW

13,2 kV

G

G

G

GG

G

DER (CHP) MWG

G

G

G

G

G

Transformation 30/13,2 kV

AggregatorFenix

GSALINERA7,5 MW

PV0,3MW G

TSO (REE) DSO(IBD)Market (OMEL)

Page 10: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009DER participants – Main challengeUnit Location MVA Connection Type

Cog. Fabrica Neumáticos Michelin Vitoria 47 Barras de 30 kV de Gamarra CHPCog. Guascor I+D P.T. Miñano 12 L 30 kV Gamarra-Villarreal 1-2 CHPCog. Hospital de Santiago Vitoria 2,06 L 30 kV Este-Oeste CHPCog. Hospital de Txagorritxu Vitoria 0,52 L 30 kV Gamarra-Peña 1 CHPCog. Kraslan P.I Jundiz 1 L 30 kV Jundiz-Ali 1-2 CHPCog. Leia BT Villarreal 0,42 L 30 kV Gamarra-Villarreal 1-2 CHPCog. Salinera Añana Añana 7,56 L 30 kV Jundiz-Puentelarra 1-2 CHPCog. Secados de Madera Goiain P.I. Goiain 2,72 L 30 kV Gamarra-Villarreal 1-2 CHPP.E. Badaia Sierra de Badaia 50 Barras de 30 kV de Jundiz WindP.E. ELGEA-URKILLA Sierra de Urkilla 32,3 Barras de 30 kV de Elgea WindCog. Searsa P.I Jundiz 2,76 L 30 kV Jundiz-Ali 1-2 CHPCog. Biometanización Vitoria 1,2 L 30 kV Jundiz-Ali 1 2 CHP-BIOMASSFotovoltaico Gamarra Menor Vitoria 0,3 L 30 kV Gamarra-Villarreal 1-2 PVFotovoltaico ULLIBARRI-ARRAZUAVitoria 0,3 L 30 kV Gamarra-Alsasua 1 PVFotovoltaico en Pobes Pobes 0,1 L 30 kV Jundiz-Puentelarra 2 PVZIGOR Vitoria 1,1 L 30 kV Gamarra-Villarreal 1-2 Back-upC.H. Araia San Pedro de A 0,96 STR ASPARRENA CTO 5 ARA HydroC.H. Santa Cruz de Campezo Santa Cruz de C 0,96 STR ANTOÑANA CTO 1 SANTA HydroCog. Fundación Estadio Vitoria 0,96 STR OLARIZU CTO 2 ARETXA CHPCog. Vertedero de Gardelegui Vitoria 0,65 STR OLARIZU CTO 1 BERGAN CHPC.H. Pedruzo Vitoria 0,7 STR OLARIZU CTO 1 BERGAN HydroC.H. Antoñana Antoñana 0,44 Barras STR ANTOÑANA HydroHuerta Solar en Legarda Legarda 0,7 STR NANCLARES CTO 3 TRES PVHuerta Solar en Treviño Treviño 0,19 STR OLARIZU CTO 1 BERGAN PVFOTOVOLTAICA en Berganzo Berganzo 0,1 STR OLARIZU CTO 1 BERGAN PVCH Contrasta Antoñana 0,2 STR ANTOÑANA CTO 1 SANTA HydroFOTOVOLTAICA VALLE DE ARANAAntoñana 0,3 STR ANTOÑANA CTO 1 SANTA PVFOTOVOLTAICA SANTA CRUZ DE Antoñana 0,1 STR ANTOÑANA CTO 1 SANTA PV

Page 11: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

• Providing global services (TSO level)1- Selling active power in the day ahead market2- Tertiary reserve, balancing market 3- Selling reactive power capacity (PO7.4)

• Providing local services (DSO level)4- Help maintaining voltages in lines (use case 4 )5- Under equipment outages, use active power

generation to avoid reconfiguring the distribution network (simulated )

• Providing global services (TSO level)1- Selling active power in the day ahead market2- Tertiary reserve, balancing market 3- Selling reactive power capacity (PO7.4)

• Providing local services (DSO level)4- Help maintaining voltages in lines (use case 4 )5- Under equipment outages, use active power

generation to avoid reconfiguring the distribution network (simulated )

What is demonstrated?

Page 12: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

1. Aggregating DER of different technologies2. In Spain Generation schedules are validated only by TSO,

considering the Transmission Network3. Currently no SO is using DER capacities to give system

support, eg. tertiary reserve4. VVC optimizing Distribution networks that consider DER

outputs as a control variables is non exiting (requires State Estimation in Distribution).

5. Back-up generators are not allowed to export energy into the network

1. Aggregating DER of different technologies2. In Spain Generation schedules are validated only by TSO,

considering the Transmission Network3. Currently no SO is using DER capacities to give system

support, eg. tertiary reserve4. VVC optimizing Distribution networks that consider DER

outputs as a control variables is non exiting (requires State Estimation in Distribution).

5. Back-up generators are not allowed to export energy into the network

What is new?

Page 13: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

José M. Corera – Spain Round Table RT4

FENIX future(Higher DER penetration)

CentralGeneration

Distributionand Transmission Networks

DER

Feni

x co

ntro

l

CentralGeneration

TransmissionNetworks

Distribution Networks

DERC

entra

l con

trol

Pasi

ve c

ontro

l

If Current Status Quo

FB - Communications

CVPP - DEMSTVPP - DSO/TSO developments and operational costs

Benefit for society

Losses reduction

Energy –price reduction

Tertiary reserve price reduction

QoS improvement

Peak reduction and consequently, network investment reduction

Environmental benefits

Page 14: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

José M. Corera – Spain Round Table RT4

Regulatory recommendationsDistribution

network revenue regulation

Distribution network revenue

regulation

- Allow DNOs to benefit from active networks investments if defer capital expenditure- Unbundling of network businesses should not block cooperation among DER and network operators

- Allow DNOs to benefit from active networks investments if defer capital expenditure- Unbundling of network businesses should not block cooperation among DER and network operators

Metering and communicationMetering and

communication

- Permit meters to establish real-time communications with other control devices- Request Interoperability among Europe

- Permit meters to establish real-time communications with other control devices- Request Interoperability among Europe

Ancillary servicesAncillary services -No unjustified barriers to distributed generators’ participation in ancillary services markets-No unjustified barriers to distributed generators’ participation in ancillary services markets

Subsidies for renewable energy

generation and CHP

Subsidies for renewable energy

generation and CHP

- Support mechanisms for DER must allow to benefit from participating in ancillary service provision (ex. through Virtual Power Plants)

- Support mechanisms for DER must allow to benefit from participating in ancillary service provision (ex. through Virtual Power Plants)

Page 15: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

José M. Corera – Spain Round Table RT4

Impact• Potential impact is large, and grows with

penetration (…as DG becomes comparable in size to centralised generation, and hence implements more flexibility)

• However DG was not designed technically to give support to the system. And still many barriers still exist (too many “new” things), and differ among countries

• At the end of the project an impact for the 2020 EU scenario will be released

Page 16: The FENIX project: Integration of Renewables and ...

Prague, 8-11 June 2009

José M. Corera – Spain Round Table RT4

We see FENIX as a forerunner to the future Smartgrids. But a lot has to be done yet.

Thank you!