THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

42
THE CUNENE RIVER BRIDGE IN ANGOLA (2009). CHALLENGING CONDITIONS AND THEIR IMPACT ON THE DESIGN AND CONSTRUCTION OF AN 880m BRIDGE IN ONE OF ANGOLA’S MAIN ROAD CORRIDORS. Juan Jorge 3 rd of April 2012

Transcript of THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Page 1: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

THE CUNENE RIVER BRIDGE IN ANGOLA (2009).

CHALLENGING CONDITIONS AND THEIR IMPACT ON THE DESIGN AND CONSTRUCTION OF AN 880m BRIDGE IN ONE OF ANGOLA’S

MAIN ROAD CORRIDORS.

Juan Jorge3rd of April 2012

Page 2: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Locality Plan

Bridge

Cunene River

EN – 120 Road, linking Lubango to Namibia

Page 3: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

First Solutions

Page 4: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

War and Destruction

Page 5: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Emergency Solution on Main Channel and Bailey Bridge that was incorporated in a second stage

Satellite View of Cunene River Crossings

Previous Permanent Crossing

Page 6: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Bypass Fill and Bailey Bridges

Satellite View of Cunene River Crossings

Previous Permanent Crossing

View of Bailey Bridge over 3rd Channel View of Fill

Page 7: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Definitive Solution Desired

• National Reconstruction Program• INEA - MINUC• Robust permanent structure• Quick construction required• Minimize concrete use because of lack of existing

nearby quarries – Light superstructure in order to reduce dimensions of

piles • Have independence from changing riverbed

conditions during construction

Page 8: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Definitive Solution Adopted

8m1.8m

Page 9: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Camp Establishment

Page 10: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Camp Establishment

Drinking water?

Electricity?

Diesel, food, general supplies?

Construction supplies?

Communications?

Page 11: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Difficulties Surrounding Camp Establishment

Page 12: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

DateActivity 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12

Precast SlabsPiles

Substructure

LaunchingDeck

SurfacingJoints

2007 2008 2009

Girder Sections (Fab. y Trans.)

Construction Program

Reconstruction of Corrosion Protection

Page 13: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Precast Slabs

Type A Type B

Shear Connectors

Drainages

Page 14: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Precast Slabs Yard

Page 15: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Precast Slabs Yard

Page 16: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Precast Slabs Yard

Page 17: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Construction of Girder Sections in China

10 Types of sections

142 sections in total ≈ 2 500 tons of steel

Page 18: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Construction of Girder Sections in China

Page 19: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Transport of Girder Sections

Qinhuangdao, Hebei, China1st First Delivery February 2008

Xangongo, Cunene, Angola1st Delivery arrives April 2009

Page 20: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Transport of Girder SectionsRoad Transport in

Angola

Juan Jorge
Namibe - Lubango 225kmLubango- Xangongo 320km
Page 21: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Substructure

Page 22: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Substructure

Page 23: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Substructure

Page 24: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Substructure

• 12 piles had to be built in the main channel of the river.

• In these cases end tipping, in order to build a dry working platform, was executed and the piles constructed in a second stage

Page 25: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Substructure

Page 26: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Substructure

Page 27: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Superstructure – Welding and Launching of Girders

Page 28: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Superstructure – Welding and Launching of Girders

Page 29: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Deck Construction

3mm every 3 metres

Insitu concrete of sidewalk?

Leave service ducts for future services in sidewalk?

Page 30: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Surfacing and Expansion Joints

Page 31: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Guardrails and Lighting

Page 32: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Guardrails and Lighting

Page 33: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Recent Images

Page 34: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Soft Water AttackObserved Effects

Page 35: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Soft Water AttackObserved Effects

Page 36: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Soft Water AttackObserved Effects

Page 37: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Soft Water AttackObserved Effects

Page 38: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Soft Water AttackObserved Effects

Page 39: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Soft Water AttackObserved Effects

Page 40: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Soft Water AttackObserved Effects

Page 41: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)

Soft Water AttackSolutions

Page 42: THE CUNENE RIVER BRIDGE IN ANGOLA (2009)